|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The LIGO Executive Committee Agenda for Monday April 8, 2002 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
Special Items: Reprise of meetings at NSF
no report
LIGO Operations--Administration
A Site Teleconference was held on Thursday, April 4, 2002. The meeting focused on budgetary issues raised at previous meetings. It appears that two additional operators were included in Florence's most recent budget for Hanford (at 0.6 FTEs each). Fred is going to check his head count against the budgeted head count oif 24.2 for FY 2002. Actions to scrub the contingency liens list for construction have been assigned. It will also be necessary to review the open commitments for the old operations accounts as well as for the Advanced R&D accounts as part of the process of closing then down.
We also discussed the budgetary performance as of the end of March and the status of the site construction projects. Otto requested a go ahead for spending some of the underrun on building construction on paving in lieu of requiring contingency. There were no objections, but Hanford was requested to provide a sketch of the proposed parking.
The list of current actions revised to reflect
the status of open actions assigned through March 28, 2001 (no update this
week) may be found at ACTION
LIST.
From: Ed Chargois <chargois_e@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .
ACCOMPLISHMENTS
ACTIVITY
| 04/04/02 | Packages | Faxes |
| In | 42 | 40 |
| Out | 6 | 29 |
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS PAYABLE HISTORY DATA .
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
From: irena@ligo.caltech.edu (Irena Petrac)
CONSTRUCTION:
Work on the LLO Staging Building is proceeding, with a walk-through on the entire existing building punch list scheduled for April 10. Completion of the entire building is scheduled for April 26. This is dependent, however, on the results of an appeal to the fire marshal regarding handicapped access to the restroom by the auditorium.
The schedule on the LHO OSB East Building is slipping a bit due to late deliveries of materials. The contractor is scheduling some overtime to try to make up time.
OPERATIONS:
Significant discussions have been held regarding support by the sites for 24/7 operations. At this time, it is felt that there may be staff shortages, particularly scientists, for some of the shifts.
SUPPORT (Baldon, Torres, Lloyd, Tischler)
Progress Period from 03.29 to 04.04
Accomplishments:
I have started to assemble a quarterly report for the Construction effort. The goal remains to prepare a short report comparable to the old Monthly Reports without having to harrass the task managers excesssively.
The following change requests have
been submitted:
| CR-010012
Revision B |
WBS 1.4.4.1 | Closeout Construction Budgets for Initial Computer Equipment Complement at the Sites | P. Lindquist |
| CR-020002 | WBS 1.3 (OPS) | CDS Remote Control Room | D. Coyne |
| CR-020003 | WBS 1.3 (OPS) | Fine Actuators for the LIvingston Input Test Masses | D. Coyne |
We will also prepare a request to close out some of the items on the contingency liens list.
Press for the latest Contingency Needs Projection.
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
Nothing to report.
-----------------------------
Dave Barker's Report
-----------------------------
Remote Controls Stations:
Purchased Sun Workstations which will be installed at CIT and MIT remote
controls stations. Purchased and installed web video servers for both
LHO and LLO. Evaluating a VPN based solution to making the most
efficient use of the observatorys' T1 network bandwidth.
EPICS Upgrades:
Evaluating the latest official EPICS release (3.13.6). Porting this
code
to the MIPS CPU, installing LIGO customized drivers. Will soak test
this
release on mv162-333, mv162-242, baja4700 and baja4700E test systems
at
LHO. Writing code to integrate 3.13.6 code development procedures with
the LIGO standard.
Evaluating beta release of EPICS 3.14. This system is released for
Solaris and Linux IOCs, and could be used to allow DMT/LDAS direct
data
injection into the CDS controls system.
Control Room Upgrade:
Upgrading LHO control room to SunBlade1000 workstations. Expanding
fast
ethernet network. Expanding ATM infrastructure in MSR, with possible
OC12 upgrade to the frame builder.
--------------
Facilities
--------------
The contractor submitted a new schedule indicating how he will make
up for
lost time due to late material delivery.
Presently the contractor is installing the roofing and doing electrical
rough in.
Interferometer: The mode cleaner wavefront sensors are being re-measured in order to implement the servos. (Joe Kovalik)
Considered the influence of MMT1 - MMT3 orientation (angular misalignment of MMT from nominal orientation) to beam pointing of the output beam (beam toward beam splitter). Made a little program to calculate beam shift caused by misalignment of each MMT and/or pointing of MC output beam (i.e. input beam to MMT chain represented by misalignment of SM). The resultant beam shift can be calculated at each MMT in terms of translational shift (how much off center the beam hits on the MMT) and angular shift (shift in angle of reflection from nominal value). When SM, MMT1 or MMT2 is misaligned (one at a time keeping others aligned), misalignment of MMT1 has a factor of two greater effect than SM or MMT2 in translational shift on MMT3. The reason why the influence of SM is smaller than MMT1 in spite of the fact that SM is farther from MMT3 than MMT2 is believed to be because of the radii of curvatures of MMT1 and MMT2. (Sany)
Optics and Installation: Laser Safety Interlock system is functioning with few, if any bugs!! Still waiting upon the contractor to add a device to the perimeter loop whereby operators will be able to tell which exterior door is opened, from the control room. Completed fabrication of three brackets and associated fixtures to mount scatterometers at both ITMs. (Jonathan Kern)
CDS: Completed the installation (software mods & processor rebooting) for the epics security system. Installed 24 single mode fiber cable from the mass storage room to the communicaiton room in the new building (it needs to be terminated). Built the shielded replacement cables for the lsc rack. (Rus Wooley and Chethan)
Completed the power schematics for the end station microphones. Awaiting approval before final installation. Plan to complete the resonance web page by Friday. (Doug)
LDAS: This week has primarily been spent laying out the organization of the computer room in the new building. We have been investigating the power requirements, cabling requirements, etc. I have put together a drawing of a floor plan and the equipment that will be going in individual racks. (Shannon Roddy)
* Upgraded firmware and OS on all the LDAS SUN machines
* Still learning LAL ...
* Preparing DB2 presentation for Caltech visit ...
(Igor Yakushin)
|
Commissioning:
|
|
The 2 km continues
to lock with reasonable reliability.High
ground motion due to the construction limits locking on certain days, but
most evenings are fine.
The
transmission on the antisymmetric port EO shutter was increased by a factor
of 8 to allow more of the laser power to be used.This
resulted in a lowering of the noise at 1 kHz by a factor of 4. Further
increases in power were prevented by the large low frequency signals on
AS_Q.Reduction of the residual AS_Q
will require tailoring the DARM servo loop to give better suppression of
the error signal.This is required
anyway to meet the 10^-13 m rms requirement for the DARM degree of freedom.
The suspension controllers in the LVEAand for ETMYwere modified to improve the grounding of the last stage and to add power supply bypass capacitors with better high frequency performance.These changes reduced the nonlinear behavior that Peter Fritschel had observed a few weeks ago and which was thought to be a likely candidate for the source of the f^-3 noise in the 2 km.Unfortunately, these changes did not improve the overall interferometer noise.
Locking on
the 4 km has continued to improve, though it is still not entirely predictable.Several
locked stretches over 2 hours have been recorded.The
signal chain for WFS1 has been checked out, and we are waiting for a good
locked stretch to set the phases and (hopefully) get it going.
Starting to
work on the common mode servo.The
common mode board has been modified to match the 2k one, and it is installed
in the rack.Setting up a temporary
optical lever to diagonalize the analog fast drive on MC2.New
LSC code has been brought up from Caltech and will be loaded and tested
tomorrow.
Have started to test the dewhitening filters on the digital suspensions.The initial result is that the hardware filters seem to work as expected, but the digital compensation filters seem to be misplaced; This is under investigation.
Improvements
in 4km interferometer:
·Recalibration
and linearization of the cavity transmission monitors indicates that the
overall power buildup due to recycling and the arm cavity resonance is
1800.
·The
noise in the optical levers have been improved by reducing the spot sizes
and centering. The ability to make and tune digital filters in the optical
lever servo loops has resulted in improved operation by enabling improved
damping of parasitic mechanical modes and further reduction in the influence
of isolation stack resonances on mirror orientation. The optical lever
servo noise now lies a factor of about 30 below the current displacement
noise.
Three interferometer
operators are now able to align, acquire and run the fully recycled interferometer
at night.
Mode cleaner:
·The wavefront sensor system for the mode cleaner is being brought on line. A PZT actuator on a PSL beam steering mirror was found broken and has been replaced.
The design
review is scheduled for Friday April 12th at 9:00 am PT. Documentation
for the Review, and instructions for joining the teleconference, are available
here.
·dspace controllers for the fine actuation systems (the interim solution) have been ordered.
·Detailed drawings for the spring/actuator assembly are available for review. Quotes have been requested. Most small parts are on order for the prototype.
·Powder coating of the original coil spring prototype run is pending.
·Two double helix machined springs are being fabricated to test the stiffness.
·Work on electronics interfaces and equirements is proceeding for the initial dSpace controller version.
Jonathan Kern
will take responsibility for final review & procurement of the hydraulic
actuator. The design of the welded version of the hydraulic actuator assembly
is expected to be transferred from Stanford to the lab very soon. The Hyspan
bellows design is ready for transfer. There is an issue related to the
welding cuff on the ends of the bellows that needs to be resolved with
Hyspan.
Pump Station:
·CONSTRUCTION:
Most materials and Components have arrived for the assembly of the test
pump station. Assembly has started Accumulators (6) have been ordered and
will be here by tue. 4-9
·LAYOUT
DRAWING: Working on a plan and elevation acad 2D layout drawing of the
location of the components for assembly.
·MANIFOLDS:
Station servo noise filter manifold is finished. Test load design is finished.
Resistor (3) parts finished / assembled by Friday 4-5
·LONG
TUBE RUN: Support frame is finished, tube runs suspended and connections
partly assembled.
·FLUIDmineral
oil 55 gal. Shell Vitrea #46 due here Friday 4-5, in search of alternate
fluid
·'glycerin'
modified for our application, lubricity etc. and viscosity 100 Centipoise
Finished up
installation of new ASC code at LLO last week.Report
from Rana is that it is working well.There
was one bug report of the Optlev coeffs not downloading "on the fly" properly.Lori
found and fixed a bug in the EPICS part of the code that appears to have
cleared this problem. New code was downloaded to LLO last night. We will
now concentrate on getting this new code ready for the LHO2k (mostly EPICS
stuff) and testing that it works without the optical levers.
Alex has framebuilder
code which should now be able to incorporate trend data produced by the
DMT machines.Zweizig is now making
changes to the DMT software to make it compatible and then we will do further
testing.
I've been
working with Khan, the new software engineer for LLO, this week in going
over CDS systems. Tomorrow, we will go over to the 40m lab and build up
the CDS server there the same at the sites.This
should be good experience to help get familiar with the system.Khan
has also been working this week on a 16Hz decimation filter (needed for
new ASC and LSC code), which also gets him familiar with our vxWorks compilers
and downloading to VME processors.
Hongyu almost
has the new EPICS data collection unit (EDCU) ready to go.We
are presently testing both the EDCU and Framebuilder with 10000 EPICS channels.
We should be able to ship the unit to LHO in another week or so.
Alex has incorporated
upsampling filters in the end station software.This
is to upsample 2k control signals (ASC and DSC) for 16KHz output, such
that we don't hit the anti-imaging boards large steps, which causes ringing.This
was seen by Peter at LHO a few weeks ago during a test. We want to add
this to the LVEA coil driver DSC software for the LHO4k as well.
We received
three of the new VMIC pentium boards last week and Alex was able to build
the appropriate vxWorks kernel to get them to run. As a test, we ran the
LSC software on one unit.It looks
like it saves us an additional 5usec or so in processing time (about 10%).
I guess that allows for a few more test points, at least.One
nice feature is that it has three PMC sites, such that we would no longer
require the PMC expander module on the ASC/LSC systems.I
would like to have tried one of VMICs new dual pentium processor boards,
but they do not have VxMP (vxWorks for multi-processors) running on it
yet.
Starting to look at upgrading the LSC software to incorporate the same digital filter modules as the new ASC code. Presently, most of the LSC filters are still "hard coded" and the user definable ones are only second order sections. It would probably take Lori and I three weeks full time to upgrade it. Given other demands on my time, it may not be ready until mid/end May.Depends on priorities.
The ISS DC
photodiode design is finished, and the pcb file should go to the board
house sometime in the next day or two.
Mohana Mageswaran
The new Variable
Timing board has been sent to the board house. I am ordering the parts
for the 30 boards, which will in production soon. I am also preparing a
test procedure for the Variable Timing module and will test the first production
units before handing the task over to the tech shop.
Sander Liu
LEMO Anti-alias
Filter Chassis
Wrote
a new Acceptance Test Procedure (T020053-00-C) for the chassis.
Four
chassis were built. They are currently under test.
Micro-Seismic
Signal Processor
Designed
a preliminary system interface block diagram. It is currently under review
by the end user.
Remote
Interface Box PCB design is near complete. Expect to finalize the design
by the end of the week.
Post
Processor PCB design is in progress.
After a discussion
with Irena, Lightwave have accepted to take back NPRO #393 and repair it
back to its originally shipped performance level, ie 777 mW.
Last week
the reference cavity temperature control sequencer was put through its
paces.Unfortunately the interferometer
was not locked in long enough stretches to really give it a good test drive.During
the times the interferometer was locked the temperature correction was
insufficient, which is better than the alternative.In
any case the gain is adjustable on the fly, so this parameter will be tweaked
as more experience is gained.
The output
of NPRO #259 was mode-matched into the reference cavity.The
NPRO laser was locked to the reference cavity using the power adjust actuator
as the frequency actuator.Rich and
I measured a few transfer functions, which after some manipulation should
yield the transfer function of the power adjust actuator.
Lee Cardenas
I have finished the laser alignment needed to bring the NPRO laser beam into the Reference cavity.
·Consistency of old FFT analysis work with respect to new results (dual recycling version) by the CSUDH group. We (Erika, and I with prompting from Peter F.) are exploring the consequences.
·The
impact of the mirror surface imperfections on the power stored inside the
Fabry-Perot cavities is a Lorentzian curve at least according to my model,
and because of the performance of the interferometer, the coupling of the
cavities makes a lot of difference, while for a single resonator the curve
of the power versus the standard deviation of the micro-roughness is far
smoother. The data have been cleansed but luckily I still have some paper
notes with a view to a comparison with the more recent results by Ken Ganezer.
Putting the parameters of Ligo II in my formulas gives a curve that surprisingly
predicts the one he got by doing simulations.
·More
precise meaning of matching into a generally distorted double cavity interferometer.
The goal is to be able to predict how much a large distortion (thermal
lensing) can degrade the carrier for ADvLigo design. Working on this now
after long hiatus.
·Ongoing analysis, and absorbing feedback on the studies of scattering loss (and loss, in general) for the LHO TMs. With Jordan, GariLynn, Stan, Peter F.
·We
have finished a paper on the Braginsky parametric effect, after finally
having the imprimateur of Vyatchanin and Braginsky.
·Our
ongoing SB balance studies are full steam with the hope of getting in draft
soon (one can say that is actually in progress).
We are preparing for the first contaminant studies. We have been now routinely reproducing the Daqun/Jordan results.
Contamination
cavity #2,It has been pumped down
(~9E-9 torr of pressure) and it is ready and waiting on the test samples.Meanwhile,
we are continuing to take ring down and beat frequency data everyday. This
cavity has a new PC Dycor RGA but I could not take an RGA scan. The rga
head filament is not responding. The RGA head will be replaced when we
open the cavity to introduce a test sample.
Contamination
cavity # 1,in preparation of ring
down measurement is undergoing. I will still need another rga head for
the cavity #1.
Note from Dennis Coyne: We plan to test mineral oil first to understand the implications of an inadvertent introduction of the seismic retrofit hydraulic fluid. Later glycerol (an alternate hydraulic fluid) will be tested. A “Kapton paint” (Cycom 3001 adhesive) used for the voice coil windings in the active internal damping system (part of the seismic retrofit) will also be tested soon.
This week (and last week) we made further modifications to the arm-cavity
servo filters in an attempt to reduce our lock acquisition time. By
replacing our
crude, passive notch with a series of four active notches, we were
able
to substantially increase both the bandwidth of the servo and the phase
margin at the unity-gain frequency. With the old, passive notch, typical
acquisition times were between 30 minutes and two hours. The active
notches reduce this acquisition time to just a few seconds, typically.
For eleven acquisitions in the South Cavity, times ranged from 3 seconds
to just over 3 minutes, and improvement of more than one order of
magnitude! Moreover, with good alignment there is little or no need
to
break and reacquire to obtain the TEM00 mode. Of the eleven locks
performed on the South cavity, ten were to the TEM00 mode. Similar
performance was obtained when the notch filters were installed in the
North cavity. Our next task is to get a duplicate set of notches, so
that both cavities can be locked simultaneously.
Also, we attempted to measure the Q's of the input masses by switching
the controllers and ringing up the lowest-frequency mode. We have used
this method before to measure the Q's of the output masses, and applying
it to the input masses becomes straightforward now that the acquisition
time is so short.
When acting on the input masses, we find that an additional mode appears
that we did not observe in the output masses. The new mode has a
frequency of 22.3kHz, as opposed to 27.4kHz for the lowest measured
frequency in the output masses, and it is easily excited by the servo
even with low gain. Introduction of a passive notch of sufficient depth
at this low frequency would cause our phase margin to become negative
at
the unity-gain frequency, so we must build yet another active notch
to
perform this measurement. Before we do so, we would like to calculate
the frequencies of all of the expected modes below about 40kHz, so
that
no more surprises come up. Ken Mailand has generously offered to help
us
with this using Finite Element Analysis modeling.
We also started looking at the difference between the North and
South Arm Cavities to try and find out why the South Arm Cavity (SAC)
was so much quieter than the North Arm Cavity (NAC). One rather striking
difference between the two cavities is the slope of the error signal,
which was nearly a factor of ten larger in SAC than in NAC. Suspecting
that the photodiodes might be to blame, we swapped them, placing SAC's
r.f. photodiode in NAC's reflected beam, and vice versa.
With the photodiodes swapped, we find that the asymmetry in the error
signals is reversed. Now NAC's error signal is larger than SAC's. The
ratio between the two is now closer to a factor of two (NAC/SAC) than
ten (formerly SAC/NAC), which is consistent with the relative amounts
of
power going into each cavity.
We also measured the noise in each cavity after switching photodiodes.
Using SAC's photodiode in the North Cavity, we see a noise spectrum
similar to our best SAC spectrum taken with the original configuration.
SAC's noise floor, on the other hand, increased with NAC's photodiode.
These results are very preliminary, and we are now in the process of
verifying them and making sure they are reproducible.
no report
Simulation and Modeling (Bhawal)
E2E for LIGO I meeting
------------------------
The monthly 'E2E for LIGO I' meeting between simulation specialists
and Hardware experts
took place on April 2nd. Matt summarized the status of the new LIGO
simulation model
and especially the inclusion of ground motion with correlation information
in it.
Hiro summarized the brief plan of E2E activities. In the short term,
we will
evaluate noise levels using available simulation tools. For the long
term, we are
planning a schedule of developments targeting to make a fairly complete
package
by the S2 run. We welcome support and feedback for the planning and
development.
LIGO I simulation system
--------------------------
(Matt) Completed restructuring of seismic sub-system (coherent ground
motion,
approximate seismic spectra, 6x6 HAM and BSC transfer function matrices).
Modal model
--------------
(Biplab) The bug reported earlier is found to be some accumulating
round-off error
arising from inexact cancellation of Guoy phase and longitudinal phase
offset. An
way-around to this problem has been implemented.
Code development and maintenance
---------------------------------
(Hiro) created new primitives and fixed bugs for the new LIGO simulation
package.
He worked with Matt to create a DAC noise generator based on a bit-flip
mechanism
hinted by Rana at LLO.
Hiro and Ed kept working with SLU collaborators to install e2e on their machine.
(Biplab) After discussing with Matt and Hiro, Added a new setting(s)
"dphiGuoy" to
propagator and for each length in summation cavity modules. This allows
us to compare
different runs for studying spatial modal model features like mismatch.
Alfi
----
(Bruce)
- Out sick most of the week.
- Working on focus problems after upgrading to Java 1.4.
(Ed Maros)
Worked on integrating JAlfi into standard build
(Melody)
- Fixed some focus problems in alfi5 with the settings dialog using
the latest
release of Java (1.4.0). Working on fixing a popup menu problem
when using fvwm.
LIGO Data Analysis System
Software Systems (Blackburn)
Kent is on vacation this week. Lazzarini compiled the weekly.
testing continues in preparation for the code freeze next week and
LDAS release.
Issues being tracked involve documentation updates, recompilation of
core modules
to handle some class modifications needed to improve code thread safety.
The first working version of our "last" API -- the diskcaching module,
was committed to CVS.
Hardware Systems (Anderson)
Caltech
-------
(Dan Kozak)
* Continued HPSS migration from Redwoods/3590s to 9940s.
* More HPSS user directory reconfiguration and account maintenance.
* Provided support for Keith (MIT) and Greg (Hanford) with Qlogic HBA
firmware and T3 pSOS upgrades.
* Did Qlogic HBA and T3 pSOS upgrades on ldas-sw and the three ldas-dev
systems (gateway, dataserver, metaserver). Upgraded the
"extra" HBA we
have in the file cabinet drawer on the 6th floor.
* LIGO SAN testbed:
* Finally closed the loop with Lance at LSC/Sun about our
problems with SAM-QFS/ACSLS. So far it's still
not working,
but at least I'm getting responses to email in a
timely
fashion.
* Benchmarking T3/switch performance continues--trying to get
a
baseline to judge multiple inter-switch link performance
against. It does appear that lmdd and dvt
are doing something
quite different--I'm going to try to figure out
what that
difference is.
(Al Wilson)
* Make operational the new P4 dual 2.2gig machine. Named ldas-pctest1
it is on
the 131.215.115.xxx network with no NIS+ services.
* Cleared conflicts with RPM packages for redhat. Systems built within
the
last month should be rebuilt with the new list of RPM's.
* Made some minor changes in BigBrother: changed warning levels, and
fine
tuned some configurations.
(Stuart Anderson)
* Researching prices for the LDAS S1 & S2 beowulf clusters.
* Synchronized multiple LDAS filesystems between all of the CIT LDAS
systems to provide uniform test systems for validating the next
LDAS software release.
* Finished all Solaris, T3, and HBA patches to the 6th floor Millikan
LDAS machines.
MIT
---
(Keith Bayer)
* 'Stage 1' patches applied to ldas Solaris equipment.
* DC-DC power converter chips replaced in SF880 by Sun Reps.
* QFS filesystem installed on dataserver T3.
* Currently reloading T3 data from tape.
* Investigating TB disk space solution for MIT data needs.
Livingston
----------
(Igor Yakushin)
* Upgraded firmware and OS on all the LDAS SUN machines.
* Still learning LAL ...
* Preparing DB2 presentation for Caltech visit ...
(Shannon Roddy)
* This week has primarily been spent laying out the organization of
the
computer room in the new building. We have been investigating
the power
requirements, cabling requirements, etc. I have put together
a drawing
of a floor plan and the equipment that will be going in individual
racks.
Data Analysis Activities (Lazzarini)
Scientific activities (Shawhan)
* Learned how to run the "absGlitch" DMT monitor, and started looking
at glitches in LLO E7 data with the goal of setting thresholds, etc.,
for vetoing astrophysical event candidates using auxiliary
interferometer channels.
* Figured out how to build the GDS software tree, in preparation for
making the Event Analysis Tool available as a LIGOtools package.
* Tried out using the Event Analysis Tool.
General Computing (Wallace)
MIT:
(Keith)
-Looking into redundant file server solutions for mail file server
(firewire drives not an option due to incompatibility with SB100/
SB1000 machines - no driver support from sun)
-Rebuilt linux box ldas-pcdev1.mit.edu after suspicious activity
on machine (rebuild ldas-sundev1.mit.edu as well due to identical
configuration)
-Patched several Win2K machines
-Upgraded SSH to 3.1p1 on several machines
Livingston:
(Shannon)
-This week has primarily been spent laying out the organization of
the
computer room in the new building. We have been investigating
the power
requirements, cabling requirements, etc. I have put together
a drawing
of a floor plan and the equipment that will be going in individual
racks.
Hanford:
(Christine)
- Continued setting up new Win2k PCs.
- Continued trying to get AutoCAD CD from Caltech ITS.
- Added a few user accounts, miscellaneous user support and
miscellaneous support to CDS.
CIT:
(Mike)
-Loaded a new PC with all GC software plus additional engineering packages.
-Added additional hardware to a new Dell 4100 Dimension; then loaded
(Windows 2000 Server) and am configuring this for a Ghost Enterprise
Server.
-Swapped out the final PC that was in the queue for an upgrade in the
OTF; this
included adding additional hardware and loading special software.
-Maintenance performed on two printers 4500 & 5000; this is included
replacing a fuser, rollers, transfer kit, and replacing filters.
-Started reloading two laptops, one for Janeen and Calum that is going
to
include special engineering packages for travel; and the other one
is for
the loaner pool.
-Finished up tightening up security procedures that was recommended
by
(ITS Security Auditors)
-Went around and gathered our old switches for Larry to be ready for
shipping to other sites.
-Had a lot of user support this week that included printing, networking,
hardware and software problems.
(Lisa)
-Began working on the blade 1000 to replace luna
-Did monthly backups
-Worked on some cadence problems with the guys in EE.
-Swapped out the boot disk in algol for a larger one.
-Put an entry in the sys admin FAQ on how to use ufsdump/ufsrestore
to copy a
boot drive
-Got a new visitor, Michael Hall, set up.
(Veronica)
-LIGO website: the LSC transparencies keep coming in. I am posting
them as
they arrive.
-Per Peter Shawhan's suggestions, have rewritten the Research Bulletin
Boards webpage. The new page will be up and running in a few days.
-Posted updates to various parts of the LIGO website.
-LDAS: Met with Bruce Sears to talk about maintenance of the gnats
database.
-CaJAGWR: Taped Massimo Tinto's lecture to post on the web.
(Larry)
-Resolved a number of procurement issues. The matching grant equipment
from SUN
has started arriving and is being distributed.
-Working on a couple of server replacements.
-Worked out a couple of printing problems. The worst one was a persons
print job
went crazy and made a 400MB print file, which caused the prints services
to hang
for a couple of hours.
-Working a number of budget related issues.
-Checked on the WAN connection for Hanford. Should be receiving some
information
from NoaNet in the next few days.
-Still tweaking the network installation. Along those lines, Ed C.
has shipped
most of the FORE equipment to the Observatories.
-Reviewed a number of documentation issues. The group is working on
getting some
of the documentation up to date.
-Setup a couple of accounts and the general cleanup of old accounts.
Working on
a list of old accounts that are to be deleted.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Bhawal)
(This report has contributions of past two weeks)
The short term and long term plan of the simulation group are under
discussion.
This is to make e2e most efficiently used for LIGO. The short term
effort is to
evaluate the realistic limiting noise curve using the capability of
e2e available
now, and the long term effort is to identify the needed features for
various
science runs, to prioritize to-be-developed functionalities and to
set the schedule
to follow.
E2E school @ LLO
------------------
About 10-15 people attended the E2E school on 18th Mar at LLO. There
were talks by
Hiro, Biplab and Matt and a demonstration session. Thanks to Szabi
Marka for
initiating this and taking all organisational responsibilities. Details
available at
http://www.ligo.caltech.edu/~e2e
Weekly E2E Physics meeting
----------------------------
(On 28th Mar) Luca matone talked about "absolute calibrations" and
comparison with
other methods. Details in our homepage.
LIGO I simulation system
--------------------------
(Matt) Began testing SimLIGO. I am currently restructuring the
stack sub-system
and parameterizing the ground motion.
Mode mismatch
--------------
(Biplab)
- (Before LSC meet) After taking proper phase offsets into account
(in order to
make a proper comparison among intermediate states between
hot and cold IFO),
locked various states. Gave a talk on this topic in LSC
meeting (detector charac.)
- Trying to fix a bug. Did the above work devising a way that avoids
that bug.
- Started documenting the work done so far.
Code development and maintenance
---------------------------------
(Hiro) Improvements and bug fixes to support the new LIGO simulation
package.
(Ed Maros)
- Worked on getting release out and worked for LSC meeting.
- Installed latest version of JDK for Solaris
Alfi
----
(Bruce)
- Fixed problems with saving blank lines in comments and macros.
- Better version tracking implemented.
- Working on updating files' data regarding locations of elements in
edit windows.
- Fixed other misc PRs.
(Melody)
- Fixed several popup menu problems in alfi5. Also wrote a document
outlining some
tips and shortcuts for using alfi5.
- Implemented a routine which converts the node coordinates in the
files from center
to top left. Keeping the top-left coordinates of the nodes
fixed solved some
problems reported in alfi5.
- Testing the latest Java version (1.4.0) with the third-party graphics
package and
alfi5. The latest version addresses some problems with
the windowing focus subsystem.
LIGO Data Analysis System
Software Systems (Blackburn)
A problem with the use of the ilwdfcs library used to convert internal
data
into
a pre-frame formated ILWD was discovered in the eventmonitorAPI. Strangely,
the
misuse of the library did not result in corrupt data even though there
was a
chance of this happening. The usage has been corrected and the
eventMonitorAPI
is properly generating pre-frame data objects.
The FrDetector data objects have now been fully unit tested in the LDAS
APIs. A
new DSO is being developed to pass through this data so that a full
end to
end
test at the system level can be performed.
The dataConditionAPI is now running without multi-thread issues for
periods
of
time as long as we have tested (over night). This is a tremendous
improvement
in the reliability of the dataConditionAPI. The changes to the GNU
STL
string
class were responsible for this improvement. However, a costumized
GNU GCC
must
be used (and is being made available by LDAS) under LDCG.
The stack has now been completely removed from the dataConditionAPI.
This
now
completes all memory optimizations for this API. We should see roughly
5
times
less memory usage in the next release of LDAS as was seen in the version
used
in E7.
A bug in the resampling code was discovered for resampling values of
p/q
where
p was not 1. The problem was that the pass-band edge frequency in the
low-pass
filter was wrong. The procedure is meant to be equivalent to upsampling
by p
(inserting p-1 zeroes between each input sample), filtering out everything
above the target frequency p/q*Nyq_in, and decimating by q. The pass-band
frequency was set to fc = 1/(p*q) (units of upsampled Nyquist = p*Nyq_in)
when it should have been set to fc = 1/q (units of upsampled Nyquist
=
p*Nyq_in).
I'm in the process of retesting today. This has now been fixed.
Unfortunately, the improvement in reliability in the dataConditionAPI
has
been
countered by a new issue in the metaDataAPI. The metaDataAPI is failing
about
twice each hour in which it is heavily used as a result of dereferencing
a
null
pointer.
The managerAPI now has support for fully managing *all* URL request
within
LDAS.
This new code allows more of LDAS to run inside the private network.
Test is
currently underway for this new functionality.
Work began on implementing the new cache structure in the diskCacheAPI
this
week. There are several more days of development needed here so testing
will
likely not begin until middle of next week.
The issues with jobs not working properly at MIT was finally sorted
out and
fixed this week. The problem resulted from extraneous files being added
under
the frame mount point.
Greg Mendell reported statistic from using the LDAS system at Hanford
for
construction of the SFT (short Fourier transform) frame data sets.
Of the
roughly 2000 jobs submited 0.5% failed with an additional 1.3 reporting
success before the job was known to successfully complete.
A significant increase in our testing of LDAS was carried out this week
as we get closer to being ready for a code freeze. The additional testing
has identified numerous problems which have been easy to fix.
Hardware Systems (Anderson)
Caltech
-------
(Dan Kozak)
* Continued HPSS migration from Redwoods to 9940s. Had a 24 period
in
which migrations ran continuously without operator (me) intervention--a
first! Due to DCE credentials expiring, this is the theoretical
limit
given the way it's being done.
* More HPSS user directory reconfiguration and account maintenance.
* LIGO SAN testbed:
* Got a response from Lance at LSC/Sun
about our problems with
SAM-QFS/ACSLS, but none of his suggestions panned
out. No
reply to that info from him. I'm asking Linda
Feather if
there's something we can do to move this along at
a faster
speed.
* Trying to replicate directio QFS bug
(unable to do so given a
single host with the new QFS version, but I'll be
testing the
old version and multiple host configurations as
well).
(Al Wilson)
* Flashed the EEPROMs for the 450's and 880 on the 6th floor.
* Moved ultra 10's and setup.
* Linux machine couch ready for a student.
* Called sun for bad 100b pci card.
* Got alcor (ultra 10 ) running.
* Cleaned up file system at MIT.
* Cleaned up security holes in ldas systems.
* Added new warning levels for cpu loads in BB.
(Stuart Anderson)
* Upgraded the boot and diagnostic PROM code on the ldas-test and ldas-cit
SPARC servers (E450 and V880).
* Switched ldas-sw over to Gigabit Ethernet and verified 500-800Mbit/s
TCP/IP performance.
* Cleaned up legacy fiber connections from the recent general computing
switch from ATM to Ethernet at Caltech.
* Fixed a long-standing issue with lock file contention for the CGI
based
LDAS software mirroring interface.
* Installed the recent RedHat Beta release (Skipjack) on a laptop.
This is a candidate for the next LDAS Linux reference platform
when the final version is released.
* Configured and started a pre-release of LDAS on the new LDAS-CIT system.
Hanford
-------
(Greg Mendell)
* Ran the tapecontrol script to put the triple coincidence E7 data,
identified by Erik Katsavounidis, onto tape at LHO and LLO.
The tapes
are on there way to MIT.
The GPS start time and intervals for the coincidence data are
given in
Erik's email below:
Erik Katsavounidis wrote:
Hi guys,
Here's the list with the triple coincidence data. I've already augmented
them by 16 seconds at both ends. The list includes GPS times and duration
in seconds. The total data is about 4.5 hours.
Thanks a lot,
--Erik
693641096 968
693727231 985
693768256 1114
693793913 1214
693836529 1188
693879462 1101
693943822 1139
693961577 983
694067741 1118
694086913 1197
694147861 935
694250455 1201
694254892 1220
694420685 1098
694614036 1172
694843198 1115
* A complete list of the coincidence data frame files on tape is at
these
URLs for LHO and LLO respectively:
http://www.ldas.ligo-wa.caltech.edu/ldas_outgoing/tapecontrol/logs/clientlibrary.html
http://www.ldas.ligo-la.caltech.edu/ldas_outgoing/tapecontrol/logs/clientlibrary.html
* Upgraded firmware from OBP/POST 4.0.45/1.2.6 to 4.5.9/2.0.1 on Sun
Blade 100 admin host at LHO.
* Assisted Igor in reconfiguring the backup script on admin at LLO.
Report from Previous Week 2002.03.29
Data Analysis Activities (Lazzarini)
Scientific activities (Shawhan)
* Investigated the distortion observed in burst-like signals injected
into the LLO interferometer during the E7 run, and found that it was
consistent with what you would expect from the frequency-dependent
response of the interferometer.
* Created a "LIGO Science Links" web page to collect various LIGO/LSC
web resources into one central place.
For The Weekly Report: Mar. 28, 2002; Data Analysis Update:
1) The knownpulsardemod DSO ran under LDAS from Mar 13 2002 to Mar 28
2002, generating SFTs at LHO and LLO on E7 data. As of this report
99%
of the SFTs have been generated. The remainder will be completed
by the
end of today. The SFTs will then be backed up onto tape, as well as
made
available via anonymous ftp to those with proper permissions (see
below).
Statistics:
1393 jobs have run at LHO. 7 jobs failed with an error in LDAS, for
a
0.5% failure rate. However, 18 jobs claimed to finish without
error but
produced no SFT output, for another 1.3% failure rate.
702 jobs have run at LLO. 4 jobs failed with an error in LDAS,
for a
0.6% failure rate. However, 9 jobs claimed to finish without
error but
produced no SFT output, for another 1.3% failure rate.
Thus, SFT generation has run mostly very successfully within LDAS.
The
errors messages have been sent to LDAS and discussed at today's SLUG
telecon. The cases where errors were reported in LDAS were all due
to
timing issues with sockets. These issues are known, and are being
addressed. The case where no error is reported, but no result
is
output, is also a known issue where the LDAS managerAPI reports back
before a job has finished. Again, LDAS is taking steps to prevent
this
error in the future.
The SFTs are generated on the "gravity-wave" channel, using the
clean_locks files for quality information from this URL
http://tenaya.physics.lsa.umich.edu/~dwchin/LIGO/E7/LockSegments/.
SFTs
are FFTs of every 2048 seconds of the data, with data of poor quality
replaced with the mean value of the good data. The percent of the data
"padded" in this way is stored in the history structure of the SFT.
The
FFT data is stored as COMPLEX8 data. (SFTs are output in frame format.)
SFTs are not produced when there is missing raw data during a 2048
second segment. The complete SFT specification is in the DCC as
LIGO_T020043-00-W.
For those with permission to connect to LDAS via anonymous ftp, SFTs
are
available at these URLs:
For the SFTs of H1:LSC-AS_Q:
$ ftp ldas.ligo-wa.caltech.edu
ftp> cd /output/sfts/sft_E7_H1_CleanLocks_031302
For the SFTs of H2:LSC-AS_Q:
$ ftp ldas.ligo-wa.caltech.edu
ftp> cd /output/sfts/sft_E7_H2_CleanLocks_031302
For the SFTs of L1:LSC-AS_Q:
$ ftp ldas.ligo-la.caltech.edu
ftp> cd /output/sfts/sft_E7_L1_CleanLocks_031302
2) Attended the March 2002 LSC meeting at LLO 3/20-3/23. Reported
on
the progress with SFTs and discussed progress on the LALDemod function
with Steve Berukoff.
General Computing (Wallace)
MIT:
Nothing to report.
Livingston:
(Tom)
-Recovering from the LSC and getting things together to send back.
-New location for network usage can be found at :
http://kahuna.net.lsu.edu/mrtg/ligo.html
(Larry)
-There will be more discussion on improving the VRVS system usage in
the
conference rooms. Many things were learned from the LSC conference
setup.
Shannon and Tom did a great job on getting the video conferencing up
and going.
Hanford:
(Christine)
- Continued setting up more new PCs.
- Continued trying to get the AutoCAD CD from Caltech ITS.
- Modified the access list for the site GC network due to a hacker
getting into one of the GC/CDS gateways.
- Attended a meeting about getting LHO on Noanet through the local
Energy Northwest site. Minutes of the meeting have been sent to the
attendees.
CIT:
(Mike)
-Loaded two laptops with full GC software one for Stan Whitcomb and
the
other for loaner pool.
-Swapped out a PC for the OTF (Subbasement), this included special
hardware that
took some time to get to work with upgraded computer.
-Loaded NT4.0 server on a new PC for a webserver to host (project science
website), this is up and running.
-Building a backup server to replace old Ghost server that is max out
on disk space.
-Worked with Ed on tagging new computer equipment.
-Reloaded and setup PC's for visitors.
(Lisa)
-Rebuilt electra (new hard disk)
-Rebuilt spica (hacked)
-Rebuilt asterope (upgrade to solaris 8)
-Looked at how to redo the mailman archives to accommodate mime attachments.
It
can be done but it will take some work.
-A lot of small housekeeping tasks: add new tapes to tape robot, put
nis+ on
some ldas machines, chase down some mac addresses, clean up the dns
tables, test
the modem pool.
(Veronica)
- LIGO website: posted LSC March transparencies. The remaining files
are
still coming, will be posted as they arrive. Attended 2 meetings regarding
LIGO Policies and Procedures manual. Created draft webpages for it;
links
will be activated as the task force decides on the content.
Together with Mike, looked into the DCC database to see why it was
malfunctioning. It seemed that compression of the file may have been
the
cause. We restored the file from the backup in its uncompressed form,
and
it is now running. Met with Linda to talk about possible improvements
to
the DCC database structure.
-Posted updates to various parts of the LIGO website (Undergraduate
projects, Int. BBoard, LSC).
- CaJAGWR website: did usual upkeep.
- LDAS webpages: edited various images.
(Larry)
-Ordered a couple more PC's and SUN hardware for various people. Assisted
others
in getting on the matching grant program with SUN.
-Cleaning up some documentation. Discovered I need to get the General
Computing
Policy out to the Engineering Committee, that should happen next week
after some
cleanup.
-Just as a point of information on the wireless access. For the LIGO
wireless
access you need to have a configuration to connect to the network name
"AIRLIGO". Those without Orinoco cards may have trouble doing this.
This will
help you get on the LIGO network in place of some other wireless network.
-Worked a couple of logistical issues for the visitors that are arriving.
-Worked a number of web, network and server issues. All just annoyances
nothing
major.
-Worked with Ed C. on some property issues. As a side note we are sending
a
number of FORE switches to the Observatories to be used as spares and
augment
their resources.
-Resolved a few printer issues. Mostly, PC's that lost their connections.
-Worked a couple of hack related issues. We did have a couple of machines
hacked
into. They have been rebuilt. Also, worked with ITS on some other attempts
that
were made, they have blocked the offenders at the edge routers.
for the 40m Lab:
40 m (from Betsy Weaver)
MC1 has guide rods glued.
MC2 has guide rods and all magnets glued.
MC3 has guide rods glued.
Rolf Bork
- We are setting up the 40m lab Digital Suspension Control (DSC) VME
crate here at Wilson house. We will test the code here, along with
connections to our DAQ and GDS, as much as possible and then move it into
place at the 40m lab. Since the 40m lab will not have the same 5588
reflected memory as the sites, Alex will need to modify the DAQ controller
and AWG software to run with 40m systems.
Sander Liu
40M EO Shutter Controllers
Received three high voltage
pulsers from DEI. Ben delivered them to 40M
Three controllers are currently
under test.
and for advanced LIGO:
Janeen Romie:
AdLIGO Suspensions
Submitted a PO for the sensor/actuator ceramic circuit boards for the
controls prototype suspensions.
AdLIGO PSL
Peter King
Shally Saraf reports that he managed to get approximately 10-13 W (I
don't
recall which) out of the 10-W laser/amplifier chain. The input
power from
the laser was approximately 4 W. During the recent LSC Meeting,
I gave
instructions to Shally on how to increase the diode current and thereby
increase the output power of the laser.
From: Mark Barton <mbarton@ligo.caltech.edu>
I had a bit of a setback with the modelling when Mathematica crashed
while saving the quad model definition file and corrupted it. Fortunately
I had a backup only two days old; unfortunately I had been editing
like
crazy for that two days. I put back all the changes, did a bit more
debugging and released it as v2.1: <http://www.ligo.caltech.edu/~mbarton/
SUSmodels/asus4/index.html>. This is a major milestone: the model is
now
feature-complete and the only refining left to do is to put in some
better values for the blade parameters, which will probably happen
in the
summer when the prototype gets moved here from MIT. In the meantime
we
should be able to get some interesting thermal noise results out of
it.
From: GariLynn Billingsley <Billingsley_G@ligo.caltech.edu>
Sapphire homogeneity
Homogeneity compensation at Goodrich is complete. Goodrich will
be sending the 250mm sapphire piece to Caltech where the homogeneity will
be verified. Goodrich has supplied before and after images of the
homogeneity of this piece.
LIGO-C020137-02 contains four of these images, all are measurements
made with circularly polarized light. The first two images represent
the current state of the optic. One can clearly distinguish the orientation
of the optic by the birefringence fringes running at 45 degrees, these
are perpendicular to the wedge of the optic. Recall that the inhomogeneity
of sapphire measures differently depending on the polarization with which
it is probed.
1. Current compensated homogeneity, RMS 13 nm. They have
chosen orientation "A" as the preferred orientation. There
is a circular pattern, I don't know if this is incomplete subtraction of
side one or just a residual on side two.
2. Current map of (what is believed to be) the other polarization.
This is seen by aligning a different reflection. They apparently
get three returns, one from the first surface, and two from the rear surface.
3. Orientation A before the last correction
4. As received from LIGO, which reflection was used is unknown.
It is certainly plausible that the two returns represent each polarization. Unfortunately these images are not clear because of the birefringence fringes running at 45°.
Gingin
The homogeneity data of one of the 150 mm sapphire pieces has been
examined for beam sizes on the order r=10mm.
http://www.ligo.caltech.edu/~gari/Supporting/2cmSaphAhomog.JPG
shows an image of the homogeneity (over r=10mm) of one of the 150 mm
diameter pieces that we have been considering using for Gingin.
The image of the whole piece can be seen at http://www.ligo.caltech.edu/~gari/LIGOII/homogeneity.htm
by choosing Saphah9a (the third data set.)
For the analysis above, I chose an area in the blue streak just down
from center (there are masked pixels in the center of the data set due
to an internal reflection in the interferometer)
If I choose a r=10mm area just to the right of center it is even better, ~2.7nm rms.
Crystal Systems
CSI reports a successful growth of a 15" boule. They say it looks
good. This is the third attempt at the new size.
From: ctorrie <ctorrie@ligo.caltech.edu>
Advanced LIGO Suspensions
I was on vacation on Thursday, Friday and Monday.
Norna is visiting again from Stanford for the month of April . We have been looking again at the MATLAB model for the mode cleaner suspension and we have made some small changes to the parameter set to improve the coupling between some of the modes.
I have been working on various drawings and assemblies for the mode
cleaner suspension.
From: "k.strain" <k.strain@physics.gla.ac.uk>
Subject: Minutes of the 40m Tech Adv Committee
minutes of the 40m TAC committee meeting at
the LLO LSC last month.
Dennis Ugolini gave a concise presentation outlining the progress on
the
40m over the last 6 months or so. He detailed a few minor changes relating
to the detection optical bench at the antisymmetric output of the
intferferometer. Some minor difficulties with dust in the clean area
are
under investigation.
Our attention is drawn to the last page of the presentation where a
number
of tasks that are not viewed as being the responsibility of the 40m
group,
but which could be tackled by them if necessary/best are listed.
A small number of points were raised in discussions after the talk
Q. Was communication between the LSC groups working on RSE sufficient
A. This should be improved. Especially in the frequency of less formal
exchanges.
Q. Are the technical issues relating to the VHF photodiodes being
addressed? - especially for wavefront sensing
A. This is currently viewed as an LSC task. Is unclear if a solution
will
be available in time to meet the 40m program, without additional work.
The
work at Stanford, on high speed photodetectors is not on the critical
path
for the 40m program.
Committee recommendations:-
We should avoid undue formality getting in the way of smooth and
continuous communication between groups working on RSE. The
relatively formal reports (6 monthly/LSC meetings) should continue,
but these should be supplemented by informal exchanges and requests
for
input whenever the need/opportunity arises.
Report of the LASTI Technical Advisory Committee LIGO-T020048-00-R
Based on its 5 th meeting, 21 March 2002, at the LSC Meeting at LLO
Members in attendance: Rolf Bork, Dennis Coyne, Riccardo DeSalvo, Brian
Lantz, Fred
Raab, Peter Saulson (chair), and Alan Weinstein.
Mike Zucker gave the presentation on behalf of the LASTI team.
LASTI has completed its infrastructure. It now has a functioning PSL,
a 1 meter test
cavity, and LIGO I stacks in both a HAM and a BSC chamber. All of the
installation was
done in a way that preserved vacuum cleanliness. The LASTI team, as
well as the large
set of visitors from the rest of the Lab and from the LSC, deserves
congratulations for
this achievement.
Since our last meeting, LASTI was asked to carry out the testing of
the new External
Pre-Isolator system being designed in response to the strong seismic
noise at LLO.
LASTI was the only facility available within LIGO where such tests
could be carried out,
so one could say that it has already proven its value, in a way not
quite intended by its
designers. Tests have started, and are slated to be intensive through
3Q02.
This work of course has an effect on the rest of the LASTI schedule,
although it is hard
to argue that anything is more important right now. In fact, much of
the impact on the
LASTI schedule comes from the fact that the EPI work has caused the
SEI team to
lengthen its own schedule for delivering prototypes to LASTI. The LASTI
team has done
a nice job of inserting other interesting tests into its own schedule,
including an earlier set
of suspension tests made on the “controls” version instead of the “noise”
version.
In summary, the TAC’s simple message is “Keep up the good work.”
For additional information about this report, contact sanders@ligo.caltech.edu