Weekly Report for Week Ending March 28, 2002


 Exec. Comm. Agenda
Highlights
LSC
Administration
Hanford Observatory
Livingston Observatory
MIT
Caltech
Detector
40 Meter
TNI
LASTI
Data Analysis
LIGO II/Adv. R&D
Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  April 1, 2002 will be:

 (Meeting time: 10:30 am Pacific Time)

Open meeting 10:30 - 11:30

  1. Announcements
  2. LSC Issues (Weiss)
  3. Comments on Weekly Report
  4. WBS 1 LIGO I Construction (Lindquist)
  5. WBS 2 LIGO Lab Operations
  6. WBS 3 and 4  Advanced R&D and LIGO II (Sanders)
Executive Committee only 11:30 - noon   Topics:
 

Special Items:


Special Announcements:


Weekly Report Highlights
 


LSC Issues (Weiss)


no report


LIGO I Construction/LIGO Laboratory Administration (Lindquist)



 

LIGO Operations--Administration



LIGO Weekly Site Telecon (Lindquist)

A Site Teleconference was held on Thursday, March 28, 2002.  This meeting focused on "Lessons Learned about 24/7 Operations during the Recent E7 Engineering Run," and Financial Status as of the end of February.  The status of the site construction projects was also discussed.

Twenty-four/Seven Operations

We reviewed the successes and problems encountered during 24/7 operations during the recent engineering run (E7) at the end of December and beginning of January.  There were three issues: How many bodies are needed to support 24/7 operations, how those bodies to be divided between scientists and operators, and organizationally how are we supposed to provide these bodies.  It was noted that to some extent resources are disipated on airplanes, etc., during travel.

At Hanford, Fred estimates that one operator and several (2-3) scientists are needed per interferometer per shift for commissioning.  One operator and one scientist is still deemed adequate for operations.

Factoring in the planned ratio of time for operation of the interferometer relative to time spent on other duties, Fred estimates that 20 to 30 scientists (head count) would be required to support commissioning of both interferometers.  Currently there are six plus one open position at Hanford. Need to increase residence of existing staff plus component from other organizations.

A comparable estimate for scientists at Livingston is 10 to 15.  This is thought to be less of a problem given current staffing and the LSU resources.  The current model for operations is two people, a scientist and an operator per shift, and this should still work for operations.  It was noted that there is a shortage of Post Docs world wide.

The problem is different for commissioning and running.  People are working to establish commitments from other organizations for grad students, visiting scientists, LSC members, etc.

Currently the sites do not foresee a problem supporting operations during the first science run (S1) this summer.  For S1 the configuration will freeze weeks ahead of time, and round-the-clock operation will start maybe a week before the actual start. Before that some time will be dedicated to making the machine reliable.

An unknown: what is the likely burden for things like calibrations, repairs, other kinds of support?

Concerning shift lengths, Fred reports that 12 hour shifts did not seem to work well because the staff was much too fatigued at the end of the shift. Ten hour shifts seemed to work, but in actuality reduced performance was noted in the wee hours.  This seems to be a biological fact of life.  Eight hour shifts simplify rotation of personnel through the less desirable shifts.

In the middle of April we will need to have materials to start training additional operators.

Bottom line...need to staff the sites adequately...longer term solution will depend on a better understanding of operations.

Safety

What are the rules for activities that can be performed by one operator, what requires two people, etc.  Bill Tyler, Kaz, and Gary are to look at it. It was noted that the science runs represent the period of safest operation because all noisy activity is curtailed.  On the other hand commissioning provides lots of opportunities to do things wrong.  It is expected that something should be added to the safety procedures about shift rotation concerning acceptable lenghts of shifts, shift rotations, etc.

Kaz noted that having and super "gate keeper" monitoring shift operations is good, a role that Fred performed during E7 of checking the condition of the operators and intervening when necessary. Fred's observation that people are not as good in the wee hours is useful. Have to give people more rest.

Construction

BRUNT is making significant progress on the Storage and Staging Building at Livingston. On punch list 85 percent of interior items have been addressed while about 15 percent of exterior have been fixed, but it must be recognized that the contractor just got the list last Thursday. By next Friday the contractor will be ready for the final punch list for new part of building.

The building is expected to be finished by April 26 with one possible exception: the Fire marshall taking exception to the layout of one men's rest room relative to the needs of handicapped persons. The architect is preparinjg drawings for fixes. The ruling is being appealed, but it is not clear that an appeal is warranted. Fixes fall under the errors and ommissions claus and should be addressed by the architect.

At Hanford, the OSB East Building is behind schedule due to late material deliveries.  However, work-arounds are being considered to catch up.

Finances

Financial Reports have been distributed summarizing the status as of the end of February for Construction, Advanced R&D, old Operations, and new Operations. We expect to review this data in the Executive Committee meeting on Monday, April 1, 2002.

The list of current actions revised to reflect the status of open actions assigned through March 28, 2001 may be found at ACTION LIST.


PROPERTY MANAGEMENT (Chargois)

From: Ed Chargois <chargois_e@ligo.caltech.edu>


DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner - turner@ligo.caltech.edu>

Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .

ACCOMPLISHMENTS

> From: Cleveland Mak <mak_c@ligo.caltech.edu>

ACTIVITY

Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.


COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman)

From: Esther Cunningham <esther@ligo.caltech.edu>

Press here for ACCOUNTS PAYABLE HISTORY DATA .


From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

From: Florence Kaufman <fkaufman@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: irena@ligo.caltech.edu (Irena Petrac)

From: Ed Jasnow <jasnow@ligo.caltech.edu>

No report--at Livingston for meetings with Construction contractor.


SUPPORT (Baldon, Torres, Lloyd, Tischler)

 
>Irene Baldon >Dorothy Lloyd >Rita Torres >From: Ryan Tischler <rtischle@ligo.caltech.edu>

Advanced LIGO (Frey)

From: Thomas Frey <tfrey@ligo.caltech.edu>

Progress Period from 03.22 to 03.28

Accomplishments:

Schedule 03.29 to 04.04:

Reports (Lindquist)

I have started to assemble a quarterly report for the Construction effort.  The goal remains to prepare a short report comparable to the old Monthly Reports without bothering the task managers.



Change Control/Contingency (Lindquist)

The following change requests have been submitted:
 

CR-010012 
Revision B
WBS 1.4.4.1 Closeout Construction Budgets for Initial Computer Equipment Complement at the Sites P. Lindquist
CR-020002 WBS 1.3 (OPS) CDS Remote Control Room D. Coyne
CR-020003 WBS 1.3 (OPS) Fine Actuators for the LIvingston Input Test Masses D. Coyne

Press for the latest Contingency Needs Projection.


Human Resources (Akutagawa)

From: Cindy Akutagawa <cindy@ligo.caltech.edu>


Quality/Safety (Tyler)

>From: Bill Tyler <tyler@ligo.caltech.edu>

No report this week.
 


LIGO Hanford Observatory (LHO) Operations (Raab)


-------------------
FACILITIES
-------------------
The new building construction progressed well this week. Four different
trades were working at the same time. Trying to make up for some of the
lost time due to late material delivery.

The Staging building columns are being beefed up to accept a five ton crane.


LIGO Livingston Observatory (LLO) Operations (Coles)



Detector Installation: The wavefront sensor on the anti-symmetric port is now operating. Some adjustments to the Guoy phase need to be made. The PZT for the M1mode cleaner steering mirror failed and will be replaced. (Joe Kovalik)

I've been learning the administrative software for the Laser Safety Interlock system, and now understand the routine operations necessary to manage day to day issues.  Fabricated and installed 5 new beam dumps for the upper periscope mirrors on ISCT 1, 3 and 4. Received and am assembling components for the ITM integrating scatterometers. Also working on a spatial system as well as a 2-omega detector. (Jonathan Kern)

CDS: Installed new slider to enable the removal of the DC offset from the MC2 control signal by adjusting the mode cleaner path length with MC1. Ordered 4 Pentek 6102's. Installed the tidal servo summing module and the seismic feed-forward safety. Ordered spare anti-aliasing filters. Completed the testing of the new shielded cables in 1X8(ASC). Initial noise plots show a decrease in 60Hz noise by a factor of 10.Replaced blown up photo diode on ITMX. (Rus Wooley)

LLO VIDEO SERVER for the virtual control room is online and is accessible through the CDS web page. Created a javascript - epics interface to bring up the camera buttons on the web page for users of the Video Web page to dynamically select cameras. The interface creates an medm screen type feel for selecting the cameras replicating the video medm screen on CDS machines. Currently the buttons are inactivated by the Epics Security installed. Will investigate on how to provide secure camera access before activating the buttons.Virtual Private network was installed both at LLO and LHO and tested. Found we cannot have same subnets on both sides of the VPN tunnel. VPN tunnel cannot have UDP broadcasts through it. This is a big show stopper as Channel Access Clients (remote machines) cannot get their UDP broadcasts on to the CDS LAN at the observatories. In the mean time, the VPN box broke and I am working with the tech support to get it fixed. More testing needs to be done. Dave and I are looking at other possibilities for secure tunnelling.

Control3 was rebooted and the nfs mount was corrupted. Fixed the corrupted disk and mounted it on control3.
Wrote a perl script for checking syntax on ASC Coefficient files. Working on Epics Channel Access security. Installed a supervisor processor. Loaded the security databases. Loaded a security database on the PEM processor for testing. Found some problems with permitting access from outside. Changed the processor and created medm screens to permit and deny access to gateway and gdssmt machines from operator stations. We will plan on migrating security database to all processors. (Chethan Parameswariah)

Worked on optimizing the code for the LIGO Online Data Client. Began to study the plot library code that will allow plotting capability by the Online Data Client. Will alter power supply schematic for the end station microphones so
that we can get them powered up by the end of next week. (Doug Lormand)
 


Detector/Technical Support (Whitcomb, Coyne)


 
Installation& Commissioning:
Hanford
Livingston
Other Science/EngineeringActivities:
Design/Analysis/Fab
Issues/Concerns
See also the Installation web page

1.1 LHO INSTALLATION & COMMISSIONING

2km Commissioning

Nergis  reporting:
Further scatterometer measurements were made to test the angular dependence of the scatttering. A slightly slower than theta^2 dependence was found, possibly indicating that there is non-zero, but small, contribution from the more isotropic "globular cluster" (to quote Bill K) of point scatterers. Theta here is the angle between specular reflection and observation.

The arm cavity visibility was measured using the RF modulation, rather than the DC reflected power (which has a strong dependence on alignment and beam aperturing effects). Perfect anti-resonance of the RF sidebands at f_m in the locked arm cavity coincide with resonance of the 2*f_m. Based on measuring the minimum in the 2*f_m reflected signal, an upper limit of 3% was put on the cavity visibility. DC reflected power measurements had shown cavity visibilities as high as 7% in the Y arm, so there is an inconsistency in the measured arm cavity losses.

After replacing a faulty fast photodiode used to detect the Spob signal, the 2k ifo returned to good locking. Since then we have been working on understanding the excess noise being generated in the suspension controller in the presence of rather low level signals. It was found that the excess noise is strongly dependent on the ASC biases applied to the coils. Some hopeful electronics modifications have not yet given fully understandable results, though we may have some inadvertent improvement.

4 km Commissioning

Nergis reporting:
The ifo still locks infrequently and then too not for very long. Some alignment shifts in the input beam pointing were remedied. Various improvements are being carried out, such as position-to-angle drive decoupling, revised alignment procedures, etc.

1.2LLO INSTALLATION & COMMISSIONING

Commissioning

Rai Weiss reporting:
OVERALL CHANGES: The software and hardware has been changed to allow the use of both optical lever damping as well as wavefront sensors. Furthermore, it is now possible to adjust filter coefficients in the ASC signal chain while running. The capability to easily include digital filters in the ASC will allow improvement in the noise arising from the angular/length coupling. The changes come with new computer control panels.

The cleanup of the EMI and RFI has begun with the installation of shielded ribbon cables in the ASC system. We are doing this iteratively by observing the noise after each major change and then going on to the next change. The LSC wiring will be shielded in the next iteration.

NOISE: The strain sensitivity since the E7 run has improved by almost a factor of 3 at frequencies above 700 Hz and has a good chance of being improved further as we learn how to operate the recycled interferometer at higher power and also allow more light to be incident on the photodetectors. The noise at 100 Hz has not changed despite a significant effort which includes: removal of noisy D/A converters, application of two stages of de-whitening, cleanup of the bad grounding and more adequate buffering of the signals to avoid ground loops, improved application of the common mode servo and improved filtering of the optical levers as well as centering of the beams in the levers to balance against amplitude noise in the lasers. There may have been a significant discovery at Hanford in the noise mixing of the coil driver due to non-linearity in the power stage. Measurements at Livingston indicate that the amplifiers have harmonic and intermodulation distortion at levels consistent with their specification and are, at least at our current level of sensitivity, not responsible for the noise at 100 Hz.

WAVEFRONT SENSORS: The antisymmetric wavefront sensor (WFS1) has been brought on-line and is now able to control the alignment against differential motions of the long arm cavity optic axes. The wavefront sensor still has significant inhomogeneities between quadrants and will therefore be alignment sensitive. The major improvement has been reduction of vignetting in the electro-optic shutters. The next steps are to bring more wavefront sensors into operation, however it would be advantageous to push harder on the optical redesign being planned for this subsystem.

PIER TRANSFER FUNCTION MEASUREMENT: An isolation system support pier on one of the ITM was unloaded by using the air bearing while under vacuum to make measurements of the beam compliance. The operation was followed on the optical lever and showed little if any change in the ITM alignment. This bodes well for attempts to install the feedback system to reduce the seismic motion at Livingston.

DATA VISUALIZATION: Two different versions of histogram programs are now beginning to operate. These will help in diagnosing glitches and give an important different cut at understanding the interferometer than power spectrum methods that have been the mainstay of the commissioning. During the next few weeks the programs will be improved to become a standard display for the operators.
 

GENERAL COMMENT ON OPERATIONS: The 4 km at Livingston has currently been blessed with reasonably short acquisition times and, when the seismic noise is small as at night, by robust operation. One could attribute this to skill and care in execution but it would be safer to attribute it to luck. This becomes evident when one wants to change experiment parameters such as increasing the power and it becomes difficult to acquire. We will ask the operators to begin systematically exploring the range of the parameter space around the mean for acquisition.

2.0 OtherEngineering and Scientific Activities

2.1 Design/Analysis/Fab

Seismic Retrofit Project

Dennis Coyne reporting
The team is working on the documentation for the Design Requirements and Conceptual Design Review. The review is scheduled for Friday April 12th at 9:00 am PT.
Hytec has been contracted to procure two more fine actuation systems, to be installed on the ITMs at LLO. Delivery is expected about 6/13.
External Pre-Isolation
A prototype machined spring with counter-winding helixes (double helixes at each end) is being machined in stainless steel for stiffness testing this week.

Changes to the interfaces between the hydraulic actuator and the spring/actuator assembly are being incorporated into the design (based on the welded version of the hydraulic actuator). Quotes are pending on the large weldment. All small parts are already in fabrication; A few may need to be re-machined to accommodate the changes for the new smaller, welded actuator version.

A spare HAM bellows will be shipped to MIT for stiffness testing (apparently only the BSC was stiffness tested in the development program). Acoustic transmission tests will also be conducted.

Hydraulic External Pre-Isolation (HEPI)
The design of a smaller, welded version of the hydraulic actuator is nearly been completed. We have decided to go forward with this version for the LASTI prototypes rather than the bolted version.

Tests on new nozzles for the outflow ports in the hydraulic servo valve are pending from the shop.

All components have been received for assembly of the pump station. Detailed layouts are in process. The transmission line and load are being soldered/assembled. The balance of the pump station will be assembled/soldered in the next couple of weeks. In the interest of keeping to schedule and getting some experience with the layout & assembly, there are a number of connections with threads wetted by the fluid (mineral oil or glycol). The plan is to retrofit these joints later in the prototype program if/as feasible.

Electro-Magnetic External Pre-Isolator (MEPI)
Received shipment of the BEI linear electro-magnetic motor for bench testing. The unit was not properly secured in shipment and suffered some damage to the magnets, but is still useful for testing.

Internal Stack Damping

The simulated HAM stack (in the ‘synchrotron’ hih bay lab) has been actuated upon with the D-space system; Still debugging the system.

Optical Modeling

Erika D'Ambrosio
Going on with the sidebands imbalance studies, the theoretical part is wrapped up although it will need a lot of writing for the article. I am now focused on quantitative considerations and I started studying the detection scheme using the sidebands in order to modify the formulas when the amplitude is different for the two sidebands.

Optics Testing

Lee Cardenas
Contamination Cavities:
Cavity # 1,  previously locked is unstable.  New locking is in progress and ring down test will be performed to determine the contamination of the mirrors.
Cavity # 2, it has been locked for almost two weeks and daily measurements of ring down and cavity beat frequency performed.
New turbo pump has been attached to this cavity today as well as an RGA spectrum gas analyzer.  The pressure of this cavity is 3E-6 torr.  It is now locked again.   We'll continue taking measurements.

PSL

Peter King
I wrote a new version of the frequency servo lock acquisition sequencer. During testing it correctly stopped when a TEM00 mode was visible in the reference cavity.  However a large number of events were triggered when the pre-modecleaner dropped out of lock.  Since then Rolf has put me onto the monitor deadband field of an EPICS record, which seems to be the cure.

A new version of the common mode tidal correction sequencer has been written.  In testing at LLO last night, the sequencer correctly picked up when the interferometer was locked and halted when the interferometer dropped out of lock, as well as when the engage/disable button was activated.

A granite slab, ordered to help in the fabrication of optically contacted pre-modecleaners, has arrived.

Lee Cardenas
New mode matching is in progress in order to bring laser beam into the reference cavity.

Rich Abbott, Flavio Nocera
Intensity servo design is complete for the inner loop including dynamic AC coupling (auto-zero).  Flavio is adding the hooks to allow analysis of our best effort on the outer loop as well.  Ben is completing his revised DCPD to be compatible with the auto zero function.

LSC/ASC/DSC

Rich Abbott, Mohana Mageswaran
Mohana finished her debugging of the variable timing module.  All functions are working in the design.  We will be in the process of making these boards available asap.

Jay Heefner
The schematics for the differential driver and receiver boards for the links between the penteks and the Euro card crates are complete and have been sent around for final comments. Board layout should begin next week.

Advanced LIGO DAC

Jay Heefner
The vendor has been given a verbal confirmation of the PO and the actual PO should be out next week.

EO Shutter Controller

Sander Liu
Shipped one chassis to LLO. Four more are in various stage of completion.

Antialiasing Filter Chassis

Sander Liu
We now have four completed circuit boards. They will be put into final assembly in the nex few days.

Microseismic and Tidal Correction

Sander Liu
Schematic capture for both remote interface box and post processor were done. PCB and associated hardwares design will be next.

DMT

John Zweizig
After the LSC meeting I continued to work at LLO. I installed the histogramming monitor that the Livingston commissioning group have been clamoring for. This entailed a little debugging because filtering code was just installed and reamained untested and the Histogram Interface between monitors and the DMT viewer had been broken at some point. Rai also suggested some enhancements that will be made ASAP.

I also worked with Ed Daw on installing the GDS software tree on alvar (the linux DMT node at LLO). Ed has just upgraded the operating system to RedHat 7.2 which made it possible to install and run the new GDS tree.

Szabi Marka
We took advantage of the "down time" following the LSC meeting and completed the slightly invasive maintenance and upgrade tasks on our list. We installed new and hopefully more secure version of Zlib and OpenSLL libraries on SAND, which were mirrored to Delaronde. We installed the new release (v3.1p1) of OpenSSH, which will be the primary ssh for Delaronde. The bootable image of the system disk was also transferred to the spare backup disk. I also improved the DMT monitor web output sofware (based on the LSC feedback) and now it can handle histograms.

40m Bake Ovens

Lee Cardenas
Bake oven # D, old one, has been fixed the leak and it is ready and in standby.
Bake oven # E, the new one, has already been pumped down with a  21"x27" stainless steel optical plate and (6) end plates,
which will be baked at 200 C.
Bake oven # B & C, small bake ovens are ready to be used.
The other new bake oven # F is in preparation.
 


40 Meter Interferometer (Weinstein)




Thermal Noise Interferometer (Libbrecht)


no report


LASTI (Zucker)


LASTI (MacInnis, Mason, Mittleman, Ottaway, Rollins, Shoemaker, Zucker)
=======================================================================
 

VACUUM ENVELOPE:
 

Myron removed the internal vibration sensors and cabling, replaced
the BSC door and pumped the vacuum system down since there was a 2
week hiatus in EPI vibration testing (LSC meeting and spring break).
Pumping and instrumentation system performed well as usual.
 

EXTERNAL SEISMIC PRE-ISOLATORS:
 

Initial transfer function results from in situ BSC stack
characterization were reviewed with Joe Giaime at LLO and appear good
in quality. Although the EM shakers did not provide enough drive to
obtain coherence over a wide frequency band when oriented in the
vertical direction, the Cambridge ground noise provided plenty of
energy by itself and the transfer functions look very clean.  Next week
when people are back we will re-orient the shakers horizontally, vent
and reinstall the sensors, and complete the suite of tests.
 

Stanford submitted substantial modifications to the hydraulic piston
design (e.g., size reduction, welded vs. bolted assembly) .  Ken
updated the corresponding structural drawings and is now traveling to
vendors to update their drawing packages.
 

We received a BEI electromagnetic actuator from Caltech with some
damage to the magnet.  DHS succeeded in cleaning most of the magnetic
particles from the gap with sticky tape and will proceed to test it
as-is; revised shipping procedures have been developed and shared with
the team.
 

DHS and Ken working on preparation of documents for the upcoming
design review (4/12).
 

PSL (Ottaway and Rollins)
 

No progress as folks were out of town.


Data Analysis and Computing (Lazzarini)


NO REPORT


LIGO II/Advanced R&D (Sanders)


From Peter King:
AdLIGO PSL

The spare laser cable set from LLO was shipped to Stanford, on loan.
Should an emergency arise at LLO, Stanford is obligated to return the
cables overnight.

From Rich Abbott
Sent out the chassis and ordered all the parts for the +/- 10 amp voice coil drivers.  PCBs are in house and being stuffed.  Chassis will take 3 weeks.

Took in the verbal requirements for the inductive position sensor interface electronics, the hydraulic pump servo, and the L4C interface electronics.  These designs will begin immediately.
 

From: Peter Fritschel <pf@ligo.mit.edu>

Presented our trade-study of the low-frequency cutoff for the advanced
LIGO interferometer at the LSC meeting. The write-up has been submitted to
the DCC under T020034-01.pdf. The basic recommendation is that the test
mass suspension's highest vertical mode be 12 Hz or lower. This is higher
than the heretofore target of below 10 Hz. The recommended change is
driven by a combination of: the lack of any clear impact on source
detection; the possibility of recovering the spectral region around the
vertical mode by line removal from the data stream; technical and
performance risks in the suspension design associated with a low vertical
mode; the real possibility that the spectral region below ~15 Hz will be
obscured anyway by gravitational gradient noise.
 

From: Mark Barton <mbarton@ligo.caltech.edu>

    This week I reworked the provisions for blades in my quad model to
allow the user to specify the elasticity of a blade explicitly as a list
of parameters rather than implicitly as a hand-crafted potential term.
This had previously been done for the wires and makes it easy for the
user to specify a system and easier for me to implement the dissipation
dilution. In the process I allowed for a slightly more general blade
model with optional crosscouplings. The new blade code produces exactly
the same results as the old and is only marginally slower, despite the
added generality. I then implemented the corrected calculation of damping
and thermal noise incorporating dissipation dilution. This has not been
fully validated but is at the point of running without obvious errors.
 

From: Janeen Hazel Romie <romie_j@ligo.caltech.edu>

40m Suspensions
The osems for the 3 small suspensions were sent to LHO and received friday. Stan signed off on the RGA this afternoon. Helena and I have queued parts for assembly. We'll clean and air bake fixtures tomorrow. Before Betsy's arrival Tuesday afternoon we will also assemble magnet/standoff assemblies. Bob will ask Steve Vass to have the cleaning person clean the So. Annex before Monday.
AdLIGO Suspensions
Waiting for a quote for the LED and photodiode circuit boards. Continuing parts designs and assembly drawing of MC suspension. Norna Robertson will be here on Monday, April 1st to work with us for a month.

 
 From: Helena Armandula <ahelena@ligo.caltech.edu>

Advanced LIGO Coatings

I circulated a "near future" coating plan to evaluate mechanical loss in coatings with the information gathered at the LSC meeting and at the telecon we had with J.M. Mackowski during his visit at Caltech.

As it stands now the next coating runs will be as follows:

SMA/VIRGO
Coat 2 thin, 2 thick substrates with 30 layers of Ta2O5/SiO2 (1/8 - 3/8 wave thickness)
The substrates have been shipped to be able to get them coated before the next run of VIRGO mirrors.

MLD
Coat 2 thin, 2 thick substrates with Nb2O5/SiO2 to obtain maximum reflectivity at 1064nm.
The parts are in Oregon. One thick substrate has also been shipped as control to get just annealed with the 4 coated ones.
MLD will make interferometric measurements after coating and after annealing to assess changes.

I'll get quotes for the next MLD runs:
1)      A Nb2O5 / Al2O3 coating run for maximum reflectivity @ 1064nm on 2 thick and 2 thin substrates
and
2)      An Al2O3/SiO2 coating run for maximum reflectivity @ 1064nm on 2 thick and 2 thin substrates
 

On these runs I will include 1"dia. substrates to evaluate coating absorption.
 

From: ctorrie <ctorrie@ligo.caltech.edu>

Suspensions

We now have a complete set of drawings for the wire fixtures and jigs for the LIGO Mode cleaner suspension. This includes several assembly drawings.

Janeen and I have been working on various sub-assemblies for this suspension using SOLIDWORKS.

Janeen and I have been working on preparing the lab area, including making some posters, for the visiting Students on Friday. I am now onto my project in my weekly machine shop class.

For Thomas I have been working on a drawing information sheet for the LIGO Mode Cleaner suspension


For additional information about this report, contact sanders@ligo.caltech.edu