|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The LIGO Executive Committee Agenda for Monday March 25, 2002 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
Special Items:
no report
The list of current actions revised to reflect
the status of open actions assigned through March 7, 2001 and notes for
that meeting may be found at ACTION
LIST.
From: Ed Chargois <chargois_e@ligo.caltech.edu>
>From: Linda Turner
- turner@ligo.caltech.edu>
Web pages for the
DCC give simple how-to's for document numbering, easy access to the latest
on-line documents, and search capabilities for the DCC database. Take
a look. . .
ACCOMPLISHMENTS
ACTIVITY From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS
PAYABLE HISTORY DATA .
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
Financial reports can be found
at: http://docuserv.ligo.caltech.edu/~fireport From: irena@ligo.caltech.edu (Irena Petrac)
SUPPORT (Baldon, Torres, Lloyd,
Tischler)
>Irene Baldon
Processed the usual requisitions and change orders.
Continue to monitor contract and blanket order encumbrance
and notify task managers when supplements are needed.
Managed to get some copying and filing done.
Jim continues with data entry in the LIGO database. Updated site trips. Placed more Pcard orders. Followed
up on a delayed order for hydraulic parts. Chased invoices to reconcile,
did 34 this period. There were no changes or additions this week to the
LIGO Roster. Progress Period from 03.15 to 03.21
Accomplishments:
The Annual Report for the Construction Project
as of the end of November has been delivered to the NSF.
A quarterly report for the Construction effort
is now due. I have started to assemble material for it. The
goal is to prepare a short report comparable to the old Monthly Reports
without molesting the task managers to heavily.
The following change requests have been submitted:
Press for the latest Contingency
Needs Projection.
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
Here is the website with voice mail tips.
Nothing to report for QA and Safety this week.. -----------------
This week has been largely consumed by preparations, support, and participation
in the LSC meeting, but some installation and commissioning activity is
going on. The VPN and video server for the remote control room at Caltech
were installed here this week. There was also some effort to reduce the
overall electronic noise environment - new shielded cables were installed
on the ASC rack (and they will be installed in the LSC on Friday), and
new ASC control software is being installed and tested.
Bill Kells has continued to measure the scattered
light from the 2 km test masses. Measurements of an ETM at two angles
have found to be consistent with an omega^-2 angular dependence, and rough
calibration would indicate a scatter level of approximately 40 ppm, although
obviously with fairly large uncertainties.
Work continues on commissioning WFS 2-4.
SEI Hydraulic Pump Station (Ken Mailand)
LAYOUT DRAWING: I have started a plan and elevation acad 2D layout drawing
of the location of the components for assembly.
MANIFOLDS: Station servo noise filter manifold is finished. Test load
design is nearly finished. designing the resistor internal components,
[3 resistors], pressure sensors [4] are here.
LONG TUBE RUN: Support frame is finished. ref. Test taps at the 60 foot
mark [shortest run] and 180 foot mark [Longest] set up starting 3-21 Internal Stack Damping
MCFM10 has been polished and is at Caltech awaiting coating with the
next batch of pieces that will go to REO (mostly 40 Meter optics)
The slow loop PID code has been running for over a week now without
any hang ups. The performance seems to be okay, although it hasn't
really been tweaked. The fast actuator voltage is consistently under
100 mV, with occassional excursions over.
The frequency servo lock acquisition code was taken out for a test drive.
The sequencer appears to function correctly if the pre-modecleaner is locked
but has some problems in not stopping the automatic incrementing of the
slow actuator if the pre-modecleaner happens to drop out of lock.
Rich Abbott, Flavio Nocera
Mohana is engaged in testing of the new variable timing boards interrupt
capability.
Jay Heefner
The designs for the pentek differential drivers and receivers has been
on hold while Jay has been on travel. The designs will be restarted next
week.
no report
We recently finished a first draft of a new TNI schedule and passed
it
no report
Simulation and Modeling (Bhawal)
Software Systems (Blackburn)
FrameCPP: Two problems were identified and fixed in the frameCPP
FrameAPI: The inconsistent behavior of exposed C++ routines to
DataConditionAPI: The string class in the standard (template)
MetaDataAPI: Several reliability issues/inconsistencies in the
DataBase Tables: Two new database tables were added to LDAS in
ControlMonitorAPI: Finished changes requested by Greg Mendell
MpiAPI: the new behavior of the "-dynlib" user option to
managerAPI: Began writing new code to have managerAPI handle
Hardware Systems (Anderson)
* Tested new versions of the VIRGO Frame library.
General Computing (Wallace)
Livingston:
Hanford:
CIT:
(Mike)
(Veronica)
(Lisa)
(Larry)
From Peter King:
AdLIGO PSL
From Rich Abbott:
Parts are coming in to build 12 more voice coil drivers along with a
chassis that will be used to house 6 modules.
From: ctorrie <ctorrie@ligo.caltech.edu>
Janeen and I discussed in detail the status of the design for the LIGO
Mode cleaner suspension.
Both Norna and Rich are giving talks relating to the QUAD at MIT at
the LSC meeting and I provided pictures, results for the MATLAB model and
an animated assembly of the LIGO Mode Cleaner suspension, using E-drawings.
Janeen and I have been working closely with Russell in Glasgow on the
coil former design and its components. We should have a prototype of the
new head in the next week or so.
Attended a meeting to discuss amoung other things computer packages
eg. COSMOS etc.. I reported on the excellent demo I attended for COSMOS
and the problems I have been finding with ALGOR.
Started some work in the lab in advance of the SURF students arriving
and attended another workshop class.
From: Janeen Romie <jromie2001@yahoo.com>
40m Suspensions
AdLIGO Suspensions
From: Helena Armandula <ahelena@ligo.caltech.edu>
Received from Stanford the absorption losses on the mirrors coated by
MLD with different coating materials.
For additional information about this report, contact sanders@ligo.caltech.edu
LIGO Operations--Administration
LIGO Weekly Site Telecon (Lindquist)
PROPERTY
MANAGEMENT (Chargois)
DOCUMENT
CONTROL CENTER (Turner, Mak)
>
From: Cleveland Mak <mak_c@ligo.caltech.edu>
COST SCHEDULE
CONTROL SYSTEMS (Cunningham, Brambila, Kaufman)
SUBCONTRACTS MANAGEMENT (Petrac,
Jasnow)
Advanced LIGO (Frey)
From: Thomas Frey <tfrey@ligo.caltech.edu>
Cost Book Tool development continues. (Highest
Priority Task)
Reports (Lindquist)
Change Control/Contingency (Lindquist)
CR-010012
Revision BWBS 1.4.4.1
Closeout Construction Budgets for Initial Computer Equipment Complement
at the Sites
P. Lindquist
CR-020002
WBS 1.3 (OPS)
CDS Remote Control Room
D. Coyne
Human
Resources (Akutagawa)
Quality/Safety (Tyler)
>From: Bill Tyler <tyler@ligo.caltech.edu>
LIGO Hanford Observatory (LHO) Operations
(Raab)
FACILITIES
-----------------
The construction of the new building is falling a little behind
schedule.The siding delivery will be two weeks late. We requested a
new
schedule from the contractor to show how he is going to make up those
two
weeks. Several minor Field work directives were issued, so far the
total
contract price is a few $K less than the original contract, this small
lead
will disappear shortly, we discovered that the HVAC needs more modification
than initial thought. This is necessary for the system to be compatible
with the local weather.
Received the first budgetary cost for the A/V system, $95K. This is
substantially higher than the LLO system, we are investigating the
causes.
For dust and dirt control it makes a lot of sense to pave the road
and the
parking lot as early as possible.
the cost on that work will be approximately $30K.
LIGO Livingston Observatory (LLO) Operations
(Coles)
Detector/Technical Support (Whitcomb,
Coyne)
Installation&
Commissioning:
LivingstonOther Science/EngineeringActivities:
Issues/Concerns
See
also the Installation
web page
1.1 LHO INSTALLATION & COMMISSIONING
2km Commissioning
Stan reporting:
A likely candidate for the cause of the f^-3
noise below 1 kHz has been identified by Peter and Rana. It appears
that the ETMY controller has a nonlinearity that causes noise at a level
that is consistent with the differential noise level.
4 km Commissioning
Stan reporting:
Continued work to set light levels and electronic gains on the various
photodiode signals to achieve reliable locking.
1.2LLO INSTALLATION & COMMISSIONING
ASC
Rolf Bork
At LLO installing and testing new ASC software.
2.0 OtherEngineering and Scientific Activities
2.1 Design/Analysis/Fab
Seismic Retrofit Project
CONSTRUCTION: Most materials and Components have arrived for
the assembly of the test pump station. Assembly has started, accumulators
are still on hold from jeremy, a dimensional ref. part number is now known.
Electro-Magnetic External Pre-Isolator (MEPI)
Received actuator driver from the CDS group at MIT; awaiting shipment
of the BEI linear electro-magnetic motor before bench testing begins.
Optics Fabrication and Testing
GariLynn Billingsley
MCFM01, 04 and 06, MCCM4K04, and 05 and MCCM2K03 have been coated at
REO and are awaiting surface measurement.
PSL
Peter King
NPRO #393 was returned to Caltech as a 500 mW NPRO.
Flavio is close to finishing the simulations of the ISS circuitry.
LSC/ASC/DSC
Rich Abbott
Received the tiny little replacement variable gain amplifier solutions
for the MC servo, stuffed one and began test. So far, we see that
they indeed seem to vary gain in a predictable manner but have not done
any noise comparison measurements.
With the exception of the cables from the 4116 DACs we have replaced
all cables in the LVEA ASC system with shielded ribbons.The replacement
is part of the rewiring necessary to incorporate the optical levers and
5 WFSs into the system. The system and the new software should be fully
operational by the end of this week.
Advanced LIGO DAC
Jay Heefner
The PO for the development of the low noise DAC modules will be issued
next week. The first prototypes should be available for test in 3-4 months.
EO Shutter Controller
Sander Liu
Received the high voltage power supplies ordered from Ultravolt. While
testing one of the new unit, it seems to take less voltage to adjust the
unit's high voltage output. If this proved out to be the case with the
rest of the them, setting of the daughter board's threshold voltage will
be reduced accordingly.
Antialiasing Filter Chassis
Sander Liu
We now have four completed circuit boards waiting for final assembly.
Expect to complete this task in the next few weeks.
Microseismic and Tidal Correction
Jay Heefner
The Tidal and Microseismic summing modules and the slew rate limiters
are at LLO and will be installed following the completion of the ASC system
upgrade.
DMT
John Zweizig
This week I wrote a Makefile to build all available Monitor documentation
and move int into a common directory. I also wrote a script that generates
a web page with links to online documentation, Author, DCC documentation
and a short description of each monitor in cvs.
40 Meter Interferometer (Weinstein)
Thermal Noise Interferometer (Libbrecht)
on to Thomas Frey. This new schedule anticipates installation of
sapphire in early August of this year and still includes approximately
three months of sapphire measurements before a report is presented
to
the downselect committee. The new short-term goal is to obtain more
complete measurements of noise in fused-silica test masses. With that
in
mind, we have begun installation and testing of a new set of notch
filters in the current setup.
LASTI (Zucker)
Data Analysis and Computing (Lazzarini)
No report received
LIGO Data Analysis System
frame C++ I/O library. There was a bug in the "get compression"
routines which caused the encoding of data to occasionally be
incorrectly accessed. There was also a but in the "get byte order"
routines which had a similar risk of incorrectly determining the
data encoding. In addition, all the exception specifications
were removed from the frameCPP library to correct a core dump
problem associated with supporting multiple frame versions.
the TCL layer for concatenating data sets read from frames has
now been fixed. New accessors were added to the frameAPI to
handle the new metadata found in the version 5 frame spec. The
associated exception specifications for the frameAPI were also
removed. A new translation routine was added to the frameAPI
to handle conversion of FrADC data objects into FrProc data
objects. This was needed to handle legacy code for resampling
which will be changed in the next release of LDAS. An issue
with properly identifying the start time of a resampled data
set as represented in and ILWD object were fixed. Another
collection of changes were made to the frameAPI to support
the productions of reduced data sets.
library bundled with GCC was discovered to be the source of
most of the multi-thread issues in the dataConditionAPI. The
source code for this class was modified to remove this instability
and was demonstrated to greatly improve the situation. In addition,
the boolean vector class was identified to be a source of similar
multi-thread instabilities. This code base has not yet been
modified in an attempt to correct this issue. Several other
issues associated with the ingestion of metadata from the
database into the database were also discovered this week. An
extensive suite of tests were performed and the matrix of test
results were used to identify and fix all these issues. The
use of intermediate() in the dataConditionAPI has been
replaced with output(). A problem in the TCL layer with an
algorithm option with only one action was identified and
fixed.
handling of metadata movers used in dataPipeline jobs were
traced to this API. New variables and changes to several macros
were required to remove this problem. No performance degradation
was seem when database tests on new code were performed.
support of the search codes. These will store summary information
for each search code. Documentation on these new tables has been
added to the LDAS webpages. The new table names are "search_summary"
and "search_summaryvars". The event candidate tables (e.g. sngl_inspiral)
were modified to include "channel" name column.
to support the operators while monitoring the performance of
the tapeControl script. Added support for viewing new job
directory tree structure needed to avoid having too many
files in one subdirectory.
automatically look in the /lal directory when no library
directory path is specified has now been documented.
all remote URL requests.
No report received
Data Analysis Activities (Lazzarini)
Scientific activites (Shawhan)
* Released new versions of some LIGOTOOLS packages.
* Prepared for LSC meeting.
MIT:
Nothing to report.
Busy with the LSC. Did get the VRVS working and used it during the
conference.
(Christine)
- Finished setting up the last of the 9 new PCs. One of the original
9
new PCs had a hardware problem and is being sent back for replacement.
Two more new PCs are on order.
- Continued helping users copy files from their old PC to their
new
one. Continued teaching users how to use Win2k OS.
- Working on getting the CD for AutoCAD from Caltech ITS as part of
their site license. Also, working on getting VPN client
software for
Win2k from Caltech ITS.
- Renewed maintenance contracts on several software packages.
-Worked with Larry and Lisa swapping out forerunner switches with new
edge
switches; then swapping fibers over to GIGE backbone.
-Loaded two PC's with General Computing software for sub basement for
Dennis Coyne.
-Troubleshooting a webserver that is hosting the project science website.
-The replacement server has not shown up yet, once it does I well reload
it
for a new webserver and transfer projectscience.org over right away.
-Started working on loading a laptop to add to the loaner pool.
-Assisted Larry and Shannon setup videoconference.
- LIGO website: posted various updates on Elba GWADW, LSC March Meeting,
MOUs, student programs. Working with Ryan on the LIGO Policies and
Procedures pages: Worked with Rita on the how-to of the
DCC electronic
document submittals.
- CaJAGWR: videotaped the talk by Lazzarini; compressed and posted
the
video.
- Met with Bruce Sears to discuss what needs ti be done on the GNATS
database.
- Working on the webpages for the Advanced Suspension group.
-Assisted in the network switch-over for the LIGO CIT network.
-Assisted Gary on setting up SUN box for his PDA sync.
-Rebuilt a couple of SUN boxes. Worked on getting a 160GB disk system
installed
on a Blade 100 but appears will have to go to a 120GB disk drive.
-Worked a couple of backup issues.
-Worked on various documentation and updates for the wireless.
-Worked on patch installations and so far working well. Will be making
changes
on a few more SUN boxes so they too will have automated patch upgrade
capability.
-Worked on the switch-over from the FORE ATM backbone to the Foundry
GigE
backbone. For the most part things went well. There were a few minor
problems
but nothing that was a show stopper. There will be some tweaking and
changes for
the next few weeks now that we have freed up a number of fibers. Also,
the FORE
equipment is getting prepared to be shipped to the Observatories. Everything
should be ready for shipping in another week.
-Worked a number of procurements. The matching grant orders should
be in by the
first of next week.
-Worked with Shannon and others on getting the LSC meetings going on
the VRVS.
The quality has improved a great deal over the past few days. A number
of people
have been able to use the system. Tom Prince used it to give his presentation
to
the group, from Caltech. Also, helped with a few other logistical items
at the
LSC.
-Worked a couple of PC installs and fixes. Working on SUN server s/w
upgrades.
LIGO II/Advanced R&D (Sanders)
A question was asked by
Andreas Weidner if a Pentium target could
be used to run EPICS, since the price of a vxWorks development system
for a
Pentium target is considerably cheaper than for a Motorola or Baja4700E.
After getting clarification from Rolf, they will be getting a Motorola
licence.
Sent off the high current voice coil driver and associated BEI actuator
(eventually) to MIT. We are eagerly awaiting any feedback from them.
Suspensions
As a result we have been working on drawings and assemblies for the
wire jigs and the detailed layout of components of the suspension. Russell
Jones in Glasgow has been helping us with designs, drawings and supplying
parts, including some GEO magnets.
Janeen and I have an action of supplying several problems to the various
suppliers for analysis.
Todd will be sending the MC osems to LHO for cleaning
and baking tomorrow afternoon. Helena and I assembled
the mechanical parts under the flow hood in the So.
Annex and checked that all parts were there along with
other supplies. She and I will start work on Monday.
Betsy has confirmed that she'll be at Caltech on
Tuesday afternoon, April 2nd. The counterbored,
silver-plated screws for safety stops were cleaned and
baked last week; they were the last mechanical parts
to be baked.
Coordinating with Calum on what mechanical parts still
need to be designed for the controls prototype mode
cleaner suspension. Had a telecon with Harry Ward and
Norna Robertson on the controls prototype
sensor/actuators. It was agreed that Caltech will
supply the LEDs and photodiodes (LIGO I vintage) along
with the circuit boards upon which they mount. The
head/former has already been design to accomodate the
boards. I have the circuit board drawings ready and
will go out for quote today. I submited a PO on Monday
for the maraging steel sheet stock for the RM and ETM
controls prototypes. There is a 6-7 week lead time for
the material
Advanced LIGO Coating Development
Measurements are by the Photo Thermal Common-Path Interferometry technique.
They use a thin film coated fused silica ND filter as a primary standard
and a Ta2O5/SiO2 coated mirror which had been previously measured by JMM
as a secondary standard.
Below is the table that lists the baseline optical loss values, and
the chart which shows the correlation with annealing temperature. The lowest
loss values found (for Nb2O5/SiO2 annealed at 400°C) appear to be well
less than 1 ppm. However, these values are still considered "preliminary".
Additional studies are planned.