|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The LIGO Executive Committee Agenda for Monday February 25, 2002 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
Special Items:
no report
LIGO Operations--Administration
A Site Teleconference was held on Thursday, Frebruary 21, 2002. Discussion included the status of FY 2002 costs-to-date, of NSF funding and the Cooperative Agreement, the establishment and budgeting of FY 2002 accounts, the FY 2002 Financial Reporting format, as well as the status of the construction at the two sites.
From: Ed Chargois <chargois_e@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .
ACCOMPLISHMENTS
ACTIVITY
| 02/21/02 | Packages | Faxes |
| In | 33 | 31 |
| Out | 05 | 48 |
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS PAYABLE HISTORY DATA .

From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
From: irena@ligo.caltech.edu (Irena Petrac)
CONSTRUCTION:
SUPPORT (Baldon, Torres, Lloyd, Tischler)
(For weeks ending 2/13 & 2/20)
Progress Period from 02.15 to 02.21
Accomplishments:
We are doing a standard Annual Report for the Construction Project as of the end of November. The final draft has been distributed and some comments received. We will be sending to the NSF shortly.
The following change request has been submitted:
| CR-010012
Revision B |
WBS 1.4.4.1 | Closeout Construction Budgets for Initial Computer Equipment Complement at the Sites | P. Lindquist |
In addition, Gerry Stapfer is preparing a change request (CR-020001) for cost increases incurred on the HPD contract. We have tentatively scheduled a meeting of the LIGO Change Control Board for 11 am PST, Tuesday, February 26, 2002.
Press for the latest Contingency Needs Projection.
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
THIS IS SOMETHING TO NOTE, the website with voice mail tips:
http://www.atc.caltech.edu/Telecom/vmail.htm (Click on Intuity Voice Mail tips.)
The first phase (funded by PMA) of the modifications to room 215 Synchrotron
for the LDAS fire suppression system installation is well underway.
As of today (Thursday, 21 February), the elevator door and frame have been
removed and the opening rough framed in. The new electrical work
is also in progress and most of the old floor tile has been "lifted."
A plastic wall and doorway have been installed to isolate the construction
area. Next week the HVAC modification work and raised floor extension
work is scheduled to start.
no report
CDS: We got the prestabilized laser data acquisition channels straightened
out. There were many channels that had been misdirected or that had been
removed, and these have all been restored to their proper configuration.
Details are in the e-log. Completed the semi-annual electronic test equipment
inventory. Out of 109 pieces, we are chasing down 7. A list of those items
w/descriptions, serial #'s and G #'s has been distributed.
Did some troubleshooting of QPDY signals (both hardware and software).
All the channels work correctly - we were unable to repeat the quad
1 problem that was observed. Fixed the common mode over ride switch for
the LSC. A connector was twisted and shorted the input to the Xycom 220.
Testing is being done to try and relieve noise generated by the cooling
fans on the suspension controllers. We should have a solution in the next
few days. Completed the wiring of the new 1X6 (SOS digital suspension).
Both of the new suspension racks will be put into storage awaiting seismic
isolation or the Saints winning the Super Bowl. (Rus Wooley)
Worked on getting back the CDS disk-to-disk backups working. The backups were affected by the new security measure installed after the OS upgrade. Downloaded and configured new medm screens for QPDX and QPDY whitening board. Bought additional licenses and DSP Blockset for MATLAB and installed them on CDS. Working on writing programs for testing of the penteks and xycom 220 DO cards. Upgraded some more CDs systems to Solaris 8. (Chethan)
LDAS: Configured a test federated database 'sample1' on sunbox1 that
uses tables from metaserver's 'LDAS_TST', 'LLO_1', 'LLO_2' database, from
linuxbox1's 'sample' and from local 'sample' database. Tested that one
can really execute joins on tables from different databases, create views
that are union of similar tables from different local or remote databases.
Helped Erik Katsouvanidis to figure out how to extract data from metadatabase
using a script instead of guild (Erik was unhappy that guild has 10000
row
restriction, he wanted to get all the data for E7 from some tables).
(Igor Yakushin)
IFO: Analyzed the motion of MC mirrors. Coherences between MC transmitted power, MC length control, MC1-MC3 OSEM sensors shows that near 1.6 Hz MC trans power has low coherence with MC length control but high coherence with MC1 and MC3 sensor. HAM stack has a peak near 1.6 Hz. This indicates that possibly MC1 and MC3 move at the same time without changing the MC length (because of the curvature of MC2). (Sany)
Optics and Installation: Looks like the Laser Safety Interlock is about ready to enable, began working with the installer to learn the software and issue user cards. Built a test rig for Gaby to characterize the WF sensors. Scanned the IFO beam at several positions on ISCT4 (the darkport) searching for clipping/apodizing. Preparing support material to float a BSC leg so that Joe Giaime can measure its transfer function. (Jonathan Kern)
IOT and ISCT tables have been photograghed and posted in the e-log. Harry, Jonathan, and I removed the shaker from BSC3 SW pier. (Gary Traylor)
Emlyn Hughes, the new chair of Caltecch's LIGO Oversight Committee,
visited LLO this week and had the opportunity to meet many LIGO staff and
local collaborators during his visit.
| Installation&
Commissioning:
Livingston |
Other Science/EngineeringActivities:
Issues/Concerns |
See also the Installation web page
When the 2km was returned to locking it did so with a vengeance, having a record setting 14 hour 45 minute locked stretch, with 5 W input to the modecleaner and with the common mode servo running. During the week we continued to work on the ASC system, testing WFS2, 3, and 4, and owrking with the WFS1 servo. The dewhitening filters on the ASC controls to ETMX and ETMY were engaged, but with no immediate improvement to the interferoometer noise.
Bill Kells made an important set of measurements, looking at the scattered light from the 2 km arm cavity mirrors when the inteferometer was in lock. He saw a clear signal that correlated well with the power stored in the arms. Both ETMs had similar scattering levels, but the measured scatter from ITMY was several times larger than for ITMX. If this result holds up to further scutiny it could indicate the reason for the poorer than expected recycling factor in the 2 km interferometer.
Bill Kells made a quick repeat of the scattering measurements for the ITMs on the 4 km; the data are preliminary but they appear to be similar to each other.
We have been trying to bring the antisymmetric wavefront sensor into operation and find large variations in the response of the different quadrants of the photodetector when illuminated by the interferometer light that is supposed to be free of wavefront shear or the admixture of higher spatial modes. The electronics is balanced and we are beginning to suspect the relay optics.
Work has begun on reducing the coupling of test mass angular motion to the longitudinal fringe signal. Initial efforts are directed toward finding the beamspot locations on the mirrors that are only second order sensitive to phase change with rotation.
Preparations are underway to measure the transfer function of the isolation stacks via the interferometer output. The dynamical impedence of the isolation system support pillars is also being measured. Both efforts are needed to support the design of the seismic retrofit at Livingston.
Impulses in the amplitude of the laser light after the premode cleaner in the pre stablized laser system were noticed during the E7 run and are a noticeable component of the non-Gaussian noise in the output of the interferometer. Work has begun on establishing the source of these pulses.
Pre-isolator
Pier testing at LASTI indicates that the first pier resonance is ~25
Hz and is a pier bending mode. The pier was disconnected from the cross-beam
and loaded with spacers for the coarse & fine actuators. This has been
repeated on 2 piers. This is markedly different from the original tests
done by Joshua; The initial tests were done shortly after the grout was
set at the pier base and this may have been responsible for more compliance
at the base. A repeat of this pier reaction compliance test will be performed
at LLO soon. Then the instrumentation will be used to do more complete
stack transfer function characterization than was done by Hytec on the
BSC prototype.
Made a decision to procure the Kaman DIT-5200 inductive position sensors instead of the MicroEpsilon sensors because their noise floor is lower. Also plan to use the 1Hz L4C geophones instead of the originally planned 2Hz geophones for better low frequency noise performance. (However, see comment below under hydraulic actuator.)
Hydraulic Actuator
Testing with a modified nozzle (.012" radius, .002 chamfer) in the
DYP2S valve body showed a turbulence onset at Reynolds number of Re = 6.5
to 8.5 with considerable dependence on supply pressure. Received the newly
machined nozzles with a much larger flat end (not just modifications of
the existing nozzle). Stanford has been unable to cause a transition to
turbulence in their valve test stand with these new nozzles. Since the
laminar - turbulent transition shows considerable hysteresis, they will
have to modify their test stand to get higher Reynolds numbers in order
to insure that we will not have problems in the LIGO application.
Most of the bellows internal volume is filled with an aluminum cylinder. Corwin (Stanford) foudn that he could use this space to mount the larger L4C geophone and could then fit the Kaman inductive sensor as well with no changes to the balance of the hydraulic actuator. However, Stanford now thinks that the lower than expected bellows resonance is due to the fluid compressibility and the resonance can be pushed higher if we reduce the size of the cylindrical plug, which now is also used to house the geophone. A test is under way to see if this theory is correct. If so, we have another round of optimization before we know how to incorpoaret the chosen geophone & inductive sensor.
SEI Hydraulic Pump Station (Ken Mailand)
CONSTRUCTION: Materials and Components are arriving for the assembly of the test pump station. Assembly has started.Electro-magnetic ActuatorWORK SPACE: CES work space is finished, power etc. is in.
LAYOUT DRAWING: I have started a layout drawing of the location of the components on the granite base, and configuration of the plumbing.
MANIFOLDS: Station noise filter1, and test load 1 &2 have not been started yet.
LONG TUBE RUN: Design of a method to assemble, support and isolate the 360 foot tubing run is in progress. Test taps at the 60 foot mark [shortest run] and 180 foot mark.
Additional parts and hardware have to be located and ordered. Final word on the accumulator, resistor configuration, and test load requirement from the Stanford group is hoped for soon, final layout and parts purchase require these components be defined.
Internal Active Damping
A HAM-like stack is being set up in Lauritsen Lab in air for prototype
testing using spare constrained layer damped springs and spring seats.
All materials for the stack have been received.
Drawings for the mounting arrangement of the system have been completed
and will be reviewed to insure that the dimensions are correct and that
a viable method of installation is known. Fabrication in Italy should start
soon. Fabrciation for the LVDT and voice coil parts has already begun.
A D-space system has been ordered for use in prototype testing on the
HAM-like stack.
Ordered boards (LVDT and coil drivers) for CDS stuffing.
Rich Abbott
The slides and the abstract of the seminar can be watched on the E2E web page.
Contamination Cavity # 1 is in progress. We'll follow the same procedure as cavity #2 but in this case we'll use the broadband EOM Pockel Cell instead of the resonator EOM . hopefully, We'll lock the cavity.
Other task has been performed as placing orders, looking into a new RF Photodiode needed for the Contamination Cavities. I have sent (3) Model SRS 560 Pre-amplifiers to have them repaired. The front end has been blown out and it is always overload as one turns it on.
The new version of the laser slow loop has been written and tested on the IOC processor in the PSL Lab. The code now implements a PID algorithm to control the SLOW actuator. Implementation of the state code will require a few additions to the EPICS records database. The code has been tested on the IOC in the PSL Lab for the past 3 days, without any detrimental effects.
Flavio Nocera
Flavio has contacted Rita and she is helping him get a handle on the
status of parts in the PSL.
no report
LASTI (MacInnis, Mason, Mittleman, Ottaway, Rollins, Shoemaker, Zucker)
=======================================================================
VACUUM ENVELOPE:
We're making more sense of our rate of rise data and air
signature after a tutorial
by John Worden. The good news is that, with the
right interpretation, our turbopump behaves sensibly. Some not so good
news is that our RGA's electron multiplier is shot, perhaps due
to extended storage at atmospheric pressure before installation.
We're able to do what we need to do right now in its Faraday mode and
will
pull the multiplier for refurbishment at the next maintenace cycle.
EXTERNAL PRE-ISOLATORS:
Pier reactance test-
We rigged two BSC piers with a shaker and accelerometers and gently
lifted
the BSC stack load off one corner at a time using our crane.
This
was done to measure their
resonant reactances (design input for the isolator
control laws). A previous measurement in October
had turned up unexpected low-frequency resonances that didn't match
models and
would have been difficult to design around. It also raised the possibility
that the lab foundation at MIT was excessively compliant.
The repeat test showed no such
complications; the pier responds as a simple cantilever with about
the calculated stiffness, implying a firm connection to a stiff floor.
A
static deflection test using a dynamometer and dial indicators added
confirmation. Ken made a finite element model which gets close to the
measured frequencies and compliance value by assuming an infinitely
stiff
floor attachment.
There are several theories regarding why the prior measurement failed,
but
it is suspicious that the pier grout had only been poured a week or
so prior
to the first test. It may have still been "green," softening
the effective
attachment.
Pre-isolator assembly-
The design modifications from the pre-isolator summit have been
completed and half the detail fabrication drawings have been updated.
A problem came up with the fabricator building the springs for us. The
10 springs which were built have sharp radiuses in a critical area
which
results in a high stress concentration. In addition the supplier is
having trouble with consistency. We have started looking for additional
suppliers and looking at a design of a "machined" spring.
CDS/DAQ/GDS:
No problems to report.
PSL:
Working on debugging our new FSS servo. Bandwidth has not yet
reached design values; Dave and Jamie are tracking down delays
in the system. Careful measurements of the photodiode, PMC
and EOM "intrinsic" bandwidths are ongoing.
Simulation and Modeling (Bhawal)
Weekly Physics meeting
-----------------------
Erika D'Ambrosio gave a talk on Optics and perturbation theory focussing
on the
characteristics of the eigenmodes of a composite system when the perturbations
conserve energy and when they do not (details in http://www.ligo.caltech.edu/~e2e).
Virginio reported a bug in MSE code.
Biplab explained some tests to understand relationship between mode
mismatch at mirrors
and the difference in gouy phase between a matched and a mismatched
beam inside a cavity.
LIGO I simulation system
--------------------------
(Matt) I've been testing the LOS sub-system. LSC sub-system testing
is next.
Mode mismatch
---------------
(Biplab) This is related to our study of transition of LIGO from cold
to hot state and
how much change in mirror position there should be for the changing
level of mismatch:
Included the difference in gouy phase between a matched and a mismatched
beam
as a phase-offset in propagators inside a 2-mirror cavity (as a setting
in box file;
This phase is not included in code) and tested its relation with the
phases acquired
due to mismatch by various modes on reflections at mirrors. Found that
these two kinds
of phases cancel each other even for large mismatch leaving the cavity
length resonant
for its TEM00.
[Studied the cases of both the W2K arm cavity and a simpler (flat ITM)
Virgo arm cavity.
The conclusion remains valid not only for the actual finesse
of LIGO-arm but also for
much higher finesse when many more reflections occur]
Code development and maintenance
---------------------------------
(Matt) I spent, and continue to spend, time testing the various simulation
tools
(modeler, adlib, and alfi) in an unforgiving user environment.
(Biplab) Detected an unnecessary conditional statement in mirror module
which was
not allowing mismatch calculation for flat-flat mirrors. Removed that.
Alfi
----
(Bruce)
- Implemented new bookkeeping event methodology in Alfi5.
- Cleaning up port positioning problems in edit windows.
(Melody)
- Addressed problem reports for the alpha version of alfi5.
LIGO Data Analysis System
Software Systems (Blackburn)
We have now fully implemented support for the linked list structure
of the
FrHistory and FrDetector structures of the frame that were implemented
in
the frameCPP I/O library last week into the frameAPI.
We are working to improve the memory usage of the frameAPI when resampling
of data is requested in this API (instead of the dataConditionAPI).
We
have already improved the memory usage of the dataConditionAPI by about
25% through similar changes to the TCL layer.
The new diskCacheAPI is in the shakedown phase now. It is marginally
functional, though daily problems show up as we test for backwards
compatibility with the functionality.
The requested support for FrDetector data objects has been added to
the frameAPI and the wrapperAPI. The next major area for code rework
to support it is in the dataConditionAPI. Because of the complex
relationship of detector geometry to channel data, this is requiring
a rework of the internal call chain code. This is the code that
houses the interpreted language in the dataCondtionAPI.
The new resampling library has been fully integrated into both the
frameAPI and the dataConditionAPI, replacing the previous code that
was found in the dataConditionAPI. Testing has begun and only slight
numerical errors between the Sun and Linux platforms exist due to
hardware differences in the handling of floating point computation
between the two hardware platforms.
The core file management code in the controlMonitor had a bug in it
which prevented it from properly notifying responsible individuals
when an LDAS API dropped core. This has been fixed and we are now
being notified if any LDAS component aborts.
Philip Charlton is attending the GEO meeting in Germany as a
representive from LDAS.
Peter Shawhan has enhanced the "getMeta" utility in LIGOtools to be
able to retrieve an arbitrary number of database table rows,
circumventing the 10000-row limit nominally imposed by LDAS by
retrieving the data in blocks and concatenating it.
With members of the LSC, we have been discussing the creation of two
new database tables to record summary information about search jobs
running within LDAS.
Lazzarini and Benoit Mours took advantage of Benoit's visit to the US
to complete the final draft for Revision E of the Frame Format specification.
The large number of changes included in this revision were discussed
priori to re-writing the specification in both the the LSC SW Configuration
Control Board and its Virgo counterpart. The changes support, e.g., the
ability to merge multiple detectors from different geographic sites into
a single frame, improved detector geometry to support bars, improved definition
of a data QA word for each detector within the frame.
Hardware Systems (Anderson)
Caltech
-------
(Dan Kozak)
* Did some HPSS migration from 3590s to 9940s and got started on Redwood
-> 9940 copies.
* Fixed various breakages in HPSS (lots of DCE problems this week, for
some reason).
* The Ultra 10 (with the LIGO supplied memory) crashed again.
Now
waiting on StorageTek to make good on coming up with a replacement
machine.
* Mostly worked on setting up the LIGO SAN testbed in Booth. Should
be
done later today.
(Al Wilson)
* Contacted Sun for a FRU on the Sun V880. They need to upgrade the
power
supplies. All 6 machines at Caltech will be done.
* Rebuilt m90 with redhat 7.1
* completing file list for tripwire. Will also create a subset for desktop
machines.
* After the machine swap(see Stuart's entry) did some tweaks to big
brother.
This will be ready for general release for LDAS site by next
weeks end. Get
your request in soon.
(Stuart Anderson)
* Upgraded the main LDAS software server from an E220R to an E450.
* Finished integrating the new SunFire V880 and T3 unit at MIT into
the ldas-mit system, where it is now running the frameAPI.
* Started integrating the new SunFire V880's in ldas-archive, ldas-lho,
and ldas-llo. Only the 3 V880 servers for ldas-cit remain to
be integrated.
MIT
---
(Keith Bayer)
* Contacted Sun regarding power supplies.
* Rebuild SF880.
* Mirrored root with DiskSuite.
* Put several Hanford E7 data tapes onto E450.
Livingston
----------
(Igor Yakushin)
* Configured a test federated database 'sample1' on sunbox1 that uses
tables from metaserver's 'LDAS_TST', 'LLO_1', 'LLO_2' database,
from
linuxbox1's 'sample' and from local 'sample' database. Tested
that one
can really execute joins on tables from different databases,
create
views that are union of similar tables from different local
or remote
databases.
* Helped Erik to figure out how to extract data from metadatabase using
a
script instead of guild (Erik was unhappy that guild has 10000
row
restriction, he wanted to get all the data for E7 from some
tables).
* Read first 8 chapters from 'Fundamentals of interferometric
gravitational wave detectors' by Peter Saulson.
Hanford
-------
(Greg Mendell)
* Directories and permissions were set up to allow the writing of an
E7
RDS data set.
* Sun was contacted about a problem reported by Sun's sale representative
with the power supplies in SunFire 880s. A Sun engineer
inspected the
LDAS SunFire 880 at LHO on Wed Feb 20, and found it does need
replacement parts. The parts are on back order. In the
meantime, I am
told that it is safe to use this server (nothing will be damaged,
no
safety issues are involved). The recalled part (a DC-DC power
converter)
may cause the server to reboot unexpectedly, however.
Data Analysis Activities (Lazzarini)
Mendell:
1) Scripts were started last Friday which drive knownpulsardemod dso
jobs in LDAS to produces SFTs at LHO and LLO. The production
of SFTs is
the first step for several of the analysis conducted by the Periodic
Upper Limits Group. At LHO, 247 of 249 jobs ran successfully
on the
LDAS system. However, at LLO, memory problems occurred which
caused the
frameAPI to fail. This problem is currently being debugged. Errors
were
also reported to occur in the clean_locks files used to generate the
quality channel. Once these error and bugs are corrected, the scripts
will be restarted.
2) Attended the PULG telecon on Thu Feb 14 and updated the group on
SFT
production. Made sample SFTs available with the AEI group, and discussed
issues associated with the meta data and format of the SFTs. One hurdle
to overcome is that, with the current format, it will take AEI 19 days
to ftp SFTs to their site. We also discussed independent ways
to check
the validity of the SFTs.
Scientific activities (Shawhan)
Worked on characterizing the effect of non-gaussian noise on different
methods of selecting inspiral event candidates using data from multiple
detectors (basicially, coincidence vs. coherent analysis).
Checked RDS (reduced data set) frame files, produced by I. Leonor, for
consistency with the raw frame files.
Brainstormed about a "job sequencer" to coordinate the execution of
LDAS jobs at the observatory sites, which has been identified as being
needed for future on-line running.
Restored access to old engineering-run data in the HPSS archive using
the 'getFrames' utility. (Data from the most recent engineering
runs
is still not retrievable from HPSS using 'getFrames', but it IS
retrievable from the observatory sites using 'getFrames'.)
General Computing (Wallace)
MIT:
(Keith)
-A couple more MU6 upgrades performed on Sun machines
-Setup conference room computer with VRVS video
-Investigated X resolution settings on Solaris for use with a small
LCD
monitor for LASTI
Livingston:
(Shannon)
-The Firewall is installed and going through configuration changes.
-Working on some of the logistics for the LSC conference.
-Working out some IP issues which will include some DNS changes for
next week.
-LSU is trying to debug some T1 problems between LSU and the Observatory.
Hanford:
(Christine)
- Spent most of this week re-building/recovering a guest PC that had
all
the Windows 98 system files and all the driver files wiped out.
Don't
know for sure how it happened. It appears to have been caused
by
"helpful" users trying to fix some other problem.
- Contacted Criselda about a problem with the pcard software we have
on
site not installing properly due to missing files.
- Created a couple of new user accounts.
- Tracked several orders that are overdue.
- Provided user support for user's printer problems, remote login
problems, put a user's laptop on the wireless network, because of the
guest computer crash setup the old photoreader again, and dealt with
the
pcard installation problems.
CIT:
(Mike)
-Rebuilt Fred Mann's computer.
-Replaced Fabio's monitor.
-Ran a security audit on a few PC users. I am still waiting on the
results.
-Mohana,
-Mohana's Computer was having problems reading CD's; I checked the
settings and made
some adjustments but no luck. I ended up replacing this with a new
CDROM. Also, had
to clean out the cpu fan, it was over heating and causing some problems.
-Did some more work on the original Amaldi server but didn't have the
time to finish
it up. Elba website is still running on a temp server.
-Flavio Nocera's PC was corrupted I had to reload OS and all General
Computing
software.
-We received two new PC's that I checked out to make sure they were
what we
ordered.
-I upgraded multiple Solid Works installations to Solid Works Plus.
-Started to create updated ghost backups of all NTSRV's, and then will
start to tighten up security permissions on shares and stopping processes
that do not need to be running; this is to prevent vulnerability to
our
servers from unknown users such as hackers.
(Bruce Sears)
* (BS) Gnats maintenance:
(1.0 day)
- Ilog upgrade. Added UTC time stamps and
a few minor features.
(Lisa)
- Worked out a plan on how best to improve our ssh setup. I expect
to have that
in place in the next couple of days.
- Peter king's workstation electra had a bad hard disk. I replaced
electra with
mira. I spent 2 days trying to recover the files off the bad
hard disk. I
recovered about 50%. Peter had a full backup of all his data files,
so that 50% loss
is merely inconvenient.
- The backup system had a glitch over the long weekend. That's
now back on
track.
(Veronica)
- LIGO website: updated MOUs/reports, Employment, LSC March registration
form, LIGO 2; made changes to roster, Student Programs. Posted updates
on
Elba 2002 GWADW website. Worked with Rita and Irena on tracking down
an
older version of an LSC Progress Report. The LSC database needs to
be
changed to better handle multiple versions of the same documents.
- CaJAGWR: Compressed and posted the video of Sterl Phinney's talk
last
week. Posted updates to the seminars and directory roster pages.
(Larry)
-Made the changes on the General Computing Usage Policy. It has been
approved by
Albert and will be going by Gary for final approval and then on through
the
signature cycle. Along the same line Ed C. has been asked to put labels
on the
computing equipment informing users that they should not have any expectation
of
privacy when using LIGO computing resources.
-Worked out more procurement issues. Dell is having a hard time delivering
things on
schedule. Worked out a couple more issues with Foundry and it looks
like things
should be finalized with them in the next week or so.
The SUN orders are placed and working on some deals with them to get
extra discounts
on future purchases.
-Minor changes on the web page for the LSC and roster.
-Worked a couple of network issues. Most dealing with the new installation
of fiber
and related equipment. Things should be finished by the first of next
week.
-Talked with NoaNet and they still have a few things to work out before
meeting with
us.
-Worked with Lisa and others on the announcement of LIGO CIT no longer
supporting
Cadence for the Campus. Tony Ruyter is working on the Campus support.
The LIGO
licensing should be good until the end of June.
-Worked on some of the logistics for the LSC conference that is to
be held at the
Livingston Observatory.
-Did a little more work on the mail server.
From Janeen Romie:
AdLIGO Suspensions
Worked with Thomas on suspension costs.
From Peter King:
AdLIGO PSL
Paul Russell has finished fabricating the wiring harness. It has
been buzzed out and checked.
From: ctorrie <ctorrie@ligo.caltech.edu>
Prototype quadruple pendulum, MIT
(Norna Robertson, Mark Barton and Rich Mittleman)
Early results indicate that the all of the modes are damping very well
in the longitudinal direction but at least one of the modes in pitch is
not damping.
I believe this is due to the fact that the "d's", the break off position
of the wires wrt the centre of mass, are not the 1mm we would like them
to be. Using the MATLAB model I have been able to show that with increased
values of d the pitch mode is not damped as well as it should be.
There are several reasons for this:
1) The upper masses had to be adjusted as in scaling the design from
the one used in GEO I did not made stiff enough and with the help of Ken
Mason we had to add extra mass in the form of stiffening bars.
2) Extra mass has been added to one of the upper masses
3) As a result of point 1 and also partly due to the blade design,
the tips of the blades are not in the position we require.*
(*At the time of installation I did not believe that the size of "d"
would be a big factor in affecting the pitch frequency. This feeling was
from my experience in hanging GEO suspensions.
However, with 2 wires to one blade the spring constant,k in pitch is
to first order the k of the wire, therefore the terms in the equations
of motion associated with "d" become more significant than they were with
1 wire to 1 blade.)
As of yesterday afternoon I have data from Rich at MIT that suggests
that this in fact the case. I am now working on adjusting the position
of the "d's" wrt the centre of mass. I hope the adjustment should not be
too difficult due to the modularity of the masses. The plan is to remove
mass from the final stage and therefore reduce the size of the d's on the
upper stages by changing the position of the tips of the blades. Mike Plissi
and others at GEO are also helping with input at this stage.
Suspensions
Janeen and I have started to re-organise our area in the high bay. This
will include the installation of 2 optical tables, a hydraulic crane
and other fixtures.
Janeen checked the set of drawings I created for a planned single
pendulum experiment. Both of us have been using the drawing section in
SOLIDWOKS to learn how to add the various parts that are required for a
LIGO engineering drawing.
Janeen and I have begun to investigate the benefits of using ANSUS or
COSMOS for FEA with SOLIDWORKS. We should be receiving a free trial for
COSMOS in the next few days and Janeen has arranged a demo for us on ANSUS
with SOLIDWORKS.
From: Helena Armandula <ahelena@ligo.caltech.edu>
Advanced LIGO Coatings:
Four "Q" measured substrates, received from Glasgow, Stanford and MIT
were sent to MLD to be coated with Ta2O5 / Al2O3.
Received from MLD 9 coated substrates, 1"dia., coated with ZrO2 / SiO2.
These parts were sent to Stanford for absorption measurements.
Advanced LIGO SUS
Identified a new glass polisher, Valley Design, in Santa Cruz, CA
Valley Design can polish the large heavy glass masses. They are working
on a quote.
From Dave Reitze
Minutes of the Core Optics Subgroup, 2/14/02
9 am PST US/Europe meeting
UF: David R.
CIT: GariLynn, Helena, Gary, Ricardo
MIT: Gregg, David S., Peter F.
Glasgow: Jim, Sheila, Peter S.
Stanford: Roger, Sheila, Vlad, Norna,
1) Coating Status (Helena)
- Some questions have arisen about the processing (high temperature
baking) of some of the
optics that were coated for Q testing at MIT. Helena is following up
with Jean Marie
Mackowski (JMM).
- JMM reports that they have seen that the coating characteristics
depend on the initial conditions
(polishing) of the substrate. They notice changes in coating absorption;
not yet sure if
mechanical Q is affected in any way.
- MLD is currently working on a Ta2O5 / Al2O3 coating run.
- CIT has developed a prototype ergonomic arm for lifting large optics.
2) Polishing Status (Gari)
- Goodrich has finished the compensating polish on the 25 cm sapphire
substrate. They achieved
a wavefront of ~ 14 nm RMS measured in single pass. This exceeds the
required specification of
20 nm, but doesn’t meet the goal of 10 nm. They claim that the process
is repeatable and
controllable. Data is being sent to CIT.
- CSIRO has finished their feasibilities studies of different spot
polishing methods for sapphire.
Of the three methods, ion beam etching works the best. They demonstrated
a 1 cm profile and
can get to 5 mm. Compensating polishing also worked well. Fluid polishing
gave too low a
material removal rate to be useful.
- Peter and GariLynn visited Crystal Systems (CSI) last month. CSI
produced a 15 inch diameter
boule (m-axis), but it will be difficult to core out substrates with
the desired AdL thickness. CSI
is asking LIGO to think about changing the aspect ratio of the substrates…
3) Sapphire Absorption (Roger)
- The final chapter in the continuing saga of the Stanford 1600 deg.
furnace: After numerous
problems over the past few months, the furnace is finally operational.
- the 1400 deg. furnace is baking some of the CSI windows for comparative
absorption studies.
Some discussion is taking place with CSI concerning confusing data
about surface aborption
caused by different surface preparation results. Nevertheless, Stanford
reports a 10 ppm
reduction in the center of the windows (from 65 to 55 ppm) after baking
for 200 hrs. Some
questions arose about the feasibility of doing large components; as
of now, Stanford is limited by
the diameter of the alumina tube in the oven. It should be possible
to do 3” x 1” pieces with
minimal modifications, though. Also, at 1400, no evidence of surface
deformation is seen. This
will be checked again at 1600 deg.
- Vlad is working on fused silica and Nb2O5 / SiO2 coatings. He is
still working on getting a
good calibration for fused silica. Also, sees anomalously large absorption
in the Nb coatings, 40-60
ppm. Helena is going to send a tantalum coated piece (4 ppm absorption)
for comparison.
Addendum from Roger Route, 2/19: The initial estimate of the optical
loss in the Ta2O5/SiO2
coating contained a computational error which made the apparent optical
loss significantly
higher than it really is. The correct value is on the order of a ppm.
We are in the process of
refining the calibration and will report the results at the next COWG
telecon.
4) Q measurements (Sheila, Gregg)
- Glasgow has measured a the Q of a number of different fused silica
coated Ta2O5 / SiO2
samples:
- annealed substrates
- 2 layer sample: lambda /4 Ta2O5 , lambda /4 SiO2
- 30 layer sample: lambda /4 Ta2O5 , lambda /4 SiO2
- 30 layer sample: lambda /8 Ta2O5 , lambda /8 SiO2
5 modes measured in all samples; measurements also made before coating.
The data analysis
subtracts the intrinsic loss, however, the annealing changes the intrinsic
loss, so some care must
be taken to properly extract the coating loss. The observations:
- annealing increases the Q of the C4 (butterfly) mode of the optics,
but reduces
(roughly equally?) the Q of the fundamental mode. In order to unfold
this,
details about how the annealing was done are needed. In particular,
how was
the optic held during heating?
- The 30 layer piece had a loss of 2.5(+/- 0.4) x 10 -4 , larger then
the 2 layer
piece (??).
- The 60 layer piece showed a loss of 3.0(+/- 0.3) x 10 -4 , roughly
equivalent to
the 30 layer case.
- A coated sapphire mass has also been measured (this mass had coating
spilling over to the
barrel). Again, 5 modes were measured before and after coating. A (large)
coating loss of 9 x
10 -4 was measured. Again, anomalous behavior in the different modes
is seen.
- MIT and Syracuse have measured 2 layer and 30 layer samples. They
find similar behavior as
reported by Glasgow, but some strange behavior is also seen. MIT and
Syracuse see large
differences in the butterfly modes. Some discussion of the effects
of annealing on the welds that
are used to support the sample took place. MIT also looked at a 30
layer sample of 3lambda/4 Ta2O5 /
lambda /4 SiO2. They see a slight drop in Q as compared with the matched
layer sample, indicating that
the Ta layer may be more lossy.
5) Wrap up, upcoming deadlines
- None, per se.
5:30 pm PST Telecon
UF: Davd
UWA: David B., Ju Li
Gingin: Zhou, Yonglan
Adelaide: Peter V.
- UWA: A report on Gingin: preliminary results on test mass suspension
controllers have been
achieved. Using electrostatic comb capacitors as actuators, tests on
the angular DOFs were
performed using Labview-based software.
- Adelaide: The optical configuration for the Gingin High Power Facility
has been specified. A
meeting of the Gingin Advisory Committee (scheduled for next week)
will go over the plans.
Thermal loading calculations using Melody have been performed on the
proposed configuration
to examine thermal loading issues. A Hartmann wavefront sensor is under
development for in
situ measurement of thermal distortions.
For additional information about this report, contact sanders@ligo.caltech.edu