Weekly Report for Week Ending February 14, 2002


 Exec. Comm. Agenda
Highlights
LSC
Administration
Hanford Observatory
Livingston Observatory
MIT
Caltech
Detector
40 Meter
TNI
LASTI
Data Analysis
LIGO II/Adv. R&D
Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  February 18, 2002 will be:

 CANCELLED DUE TO HOLIDAY


Special Announcements:


Weekly Report Highlights
 


LSC Issues (Weiss)


no report


LIGO I Construction/LIGO Laboratory Administration (Lindquist)



 

LIGO Operations--Administration



LIGO Weekly Site Telecon (Lindquist)

A Site Teleconference was held on Thursday, Frebruary 14, 2002.  Discussion included the status of FY 2002 costs-to-date, of NSF funding and the Cooperative Agreement, the establishment and budgeting of FY 2002 accounts, the FY 2002 Financial Reporting format, as well as the status of the construction at the two sites.

The list of current actions revised to reflect the status of open actions assigned through February 14, 2001 may be found at ACTION LIST.

PROPERTY MANAGEMENT (Chargois)

From: Ed Chargois <chargois_e@ligo.caltech.edu>


DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner - turner@ligo.caltech.edu>

Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .

ACCOMPLISHMENTS

> From: Cleveland Mak <mak_c@ligo.caltech.edu>

ACTIVITY

Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.


COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman)

From: Esther Cunningham <esther@ligo.caltech.edu>

Press here for ACCOUNTS PAYABLE HISTORY DATA .

From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

From: Florence Kaufman <fkaufman@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: irena@ligo.caltech.edu (Irena Petrac)

From: Ed Jasnow <jasnow@ligo.caltech.edu>

CONSTRUCTION:

OPERATIONS:

SUPPORT (Baldon, Torres, Lloyd, Tischler)

 
>Irene Baldon >Dorothy Lloyd >Rita Torres >From: Ryan Tischler <rtischle@ligo.caltech.edu>

Advanced LIGO (Frey)

From: Thomas Frey <tfrey@ligo.caltech.edu>

Progress Period from 02.08 to 02.14

Accomplishments:

Schedule 02.15 to 02.21:

Reports (Lindquist)

We are doing a standard Annual Report for the Construction Project as of the end of November.  The first edit is nearly complete.



Change Control/Contingency (Lindquist)

The following change request has been submitted:
 

CR-010012 
Revision B
WBS 1.4.4.1 Closeout Construction Budgets for Initial Computer Equipment Complement at the Sites P. Lindquist

Press for the latest Contingency Needs Projection.


Human Resources (Akutagawa)

From: Cindy Akutagawa <cindy@ligo.caltech.edu>


Quality/Safety (Tyler)

>From: Bill Tyler <tyler@ligo.caltech.edu>

Stringing/pulling of the new 50 micron multi-mode cables for LDAS has been completed.  Installation of the cables went fairly well, but this type of cable required special attention to how it was handled when "pulling" and placing in the tunnels and cable trays.  Terminating the cables is in-progress and may be completed in another week.

The first phase of room 215 Synchrotron fire suppression system modification work is about to start. PMA has provided the POETA to Physical Plant. The storage cabinets have been moved for removal of the floor tiles and elevator door.

The final version of the 40M audit report was signed off and distributed.
 


LIGO Hanford Observatory (LHO) Operations (Raab)


------------------
LHO Facilities
-----------------
Experienced a power outage to the two arms while the PUD connected
the power to the new build transformer. This caused much hardship
to the interferometer commissioning work. Perhaps we should entertain
some un interruptible power system so future outages would be less
painful.

The contractor cleaned of all the anchor bolts on the new building
in anticipation of the building steel arrival on the 18th of February.


LIGO Livingston Observatory (LLO) Operations (Coles)


Optics and Installation: Removed three of the hard mounts of the PSL table and installed air pads. Did not appreciably reduce the noise. Made a new fixture and assisted Peter in optically contacting PMC bodies. (Jonathan Kern)

LDAS: Wrote a perl script to keep the last N database backups, to figure out which logs should be kept for possible recovery from these backups and to delete the rest. Helped to fix an LDAS problem at LLO found by Julien. Configured LHO's metaserver for everyday backup of DB2 databases. Trying to configure a test federated database on sunbox1 and linuxbox1. (Igor)

Staging building: Seats are now being placed in final location. We met with the AV contractor to discuss and recommend alternates for inclusion in the contract.

We have been able to lock repeatedly in a power recycled configuration at night. We are now working on an integrated schedule to address noise problems and functionality in the interferometer.

WLL-TV New Orleans aired a favorable segment about LIGO on New Orleans area TV. A copy of the video will be placed in the DCC.

This was a short week due to the Mardi Gras holiday. Next week LLO will operate on a normal schedule, including Monday Feb. 18 which is a Caltech holiday.


Detector/Technical Support (Whitcomb, Coyne)


 
Commissioning:
Hanford
Livingston
Science & Engineering Support
See also the daily electronic logs for the installation and commissioning activities:
Hanford Detector Log

Livingston Detector Log

LHO COMMISSIONING

2km Commissioning

Stan Whitcomb reporting
The emphasis has been on understanding high power effects in the interferometer.The first thing that has occupied time was the discovery of increased noise in the modecleaner locking signal due to parasitic light returning from the recycling mirror.Tests are underway to see whether the interference path goes all the way back to the laser ("easily" fixed by adding a Faraday isolator on the PSL table) or whether it is a more difficult to fix problem in the vacuum system.

The second effect is apparently due to heating from the recycling mirror reflected beam.This is seen in the REFL photodiode, and manifests itself as a change in light level, in the worst case observed (not necessarily the worst case normally encountered!) up to a factor of 3 change.There appear to be both beam pointing and polarization effects going on.

Rolf Bork

Supporting ASC work on LHO2k.Primarily this has been adding the WFS phase shifts.

4-k Commissioning

Stan Whitcomb reporting
Continued to work toward achieving reliable full locking, but with limited success.A survey of the beams on the ISC tables showed that a few were too large for their photodiodes, and this has been fixed.A new round of lock acquisition parameters is required to compensate for the changes in light levels.

New coil drivers and pole-zero modules were installed on the modecleaner mirror digital suspension.These have reduced the noise from the DACs driving the mirrors and has resulted in a 10 db reduction in the MC_F signals above about 30 Hz.

Ben Abbott

I have been doing some noise measurements on the optical levers in the LVEA.With the optical lever dampening disabled, Josh and I took noise spectra from all four quadrants of the optical lever QPDs on ITMX, ITMY, and BS.The spectra had a noise floor of up to several millivolts per root Hertz, and pronounced peaks at around 40 Hz, and their associated harmonics. We then took the same measurements while blocking the optical lever laser.These measurements had a floor of several microvolts, and the only peaks that were visible were 60Hz and harmonics.The 40Hz peaks were completely removed.This tends to show that the 40Hz is coming fromthe laser light itself, and not bleeding through the power cables.This brings up the question of how to fix this problem.Whether it means that we need to find a new laser, or if a miniature intensity servo could be implemented, isn't clear at this point.

Jay Heefner

We completed the installation of the new mode cleaner suspension output chain. The new chain includes the 0.1Hz/1.0Hz pole/zero module and new coil drivers. The hardware and software are functional and operate as designed. The new design appears to have improved the mode cleaner noise performance for freq>20Hz. See 2/13/02 elog for more details.

Preliminary tests of the new cooling fan chassis are encouraging in that we could not see any induced noise on the coil driver signals, but a more detailed study is needed.

LLO COMMISSIONING

Rai Weiss reporting


The interferometer has been been locked in the full recycled configuration on two nights. The maximum power build up has been 1500 and is more typically 1000 - 1200. The first night locked sections were of the order of minutes duration. On the second night the lock was only broken by the tides and trains, this constitutes a record for Livingston. The instability of the sideband amplitudes in the power recycled Michelson has been reduced by increasing the low frequency gain in the servos holding the Michelson lengths.

Prior to the recycling: The electro optic shutters at the symmetric and anti-symmetric ports were brought into operation.

The new LSC code and the capability to read 16 second frames was installed.

The laser table was floated on air mounts to reduce suspected seismic coupling to the periscope. The periscope motions remained unaffected.

Peter King

The water hoses for the chiller were flushed out. After the flushing and replacement of the cooling water, the laser temperature fell from approximatley 33 degrees to 28.5 degrees.This is still 9 degrees above the setpoint.I am still trying to figure out what is causing the temperature differential.

Rolf Bork

ASC code updated to properly select hardware whitening/dewhitening filters. Note that these are presently being used for Optical Lever signals, not WFS.

LSC code updated and tested.

SCIENCE & ENGINEERING SUPPORT

Seismic Retrofit Project

Dennis Coyne reporting
Testing for the in-line accumulator shows that it is not as good as a “conventional” accumulator (despite lower inductance). Stanford (Jeremy) will specify a short neck (low inductance) conventional accumulator for the pump station and the load end of the hydraulic transmission line.

The large prototype springs (sized to hold the entire ~12,000 lb BSC load at a 8 Hz resonance) have been received. They do not match the specified profile. Marcel will perform a finite element analysis on the revised geometry to see if the localized stresses are too high. A set of acceptance criteria for the springs will be established for group review. A spring test stand and test plan are being prepared.

New nozzles have been ordered from the Stanford machine shop (Amite). These nozzles will be tested in the DY2PS pneumatic differential valve bodies in about 2 weeks. The intent is to push up the flow rate at which the laminar to turbulent transition occurs. Currently the transition occurs at ~ 15 AU (laminar to turbulent) when increasing the flow and then at ~5 AU (turbulent to laminar) when decreasing the flow. We need to operate at ~5.5 AU (arbitrary units).

MIT (Rich) has tested micro-epsilon inductive position sensors (of various sizes) and compared them to the Kaman inductive (eddy current) sensors. The Kaman sensors have a 5 to 10 times lower noise floor (and are more expensive). The Kaman sensors have a noise floor of ~ 1.5 e-9 m/rHz at ~1 Hz, which is approximately equal to the ambient noise level at Hanford at night. We plan to use the Kaman sensors. However, we need to make sure that these sensors can fit with the L4C geophone in the hydraulic actuator assembly; Stanford (Corwin) is checking to see if this is the case. (The baseline inductive sensor to date was a 2 Hz, smaller geophone.)

The large electro-magnetic forcer from BEI that was chosen for the ETF prototype of the ‘stiff” system for advanced LIGO appears to be a good choice as an alternate actuator to the hydraulic actuator. A spare unit and new driver (designed by Rich A.) will be shipped to MIT (David S.) for evaluation in this application.

Riccardo, Virginio and Szabi have progressed on a mechanical design for adaptation of the SAS LVDT and voice coil for internal damping of the BSC seismic stack. Rough drawings of the method for mounting have been developed. Parts have been ordered. They plan to build a HAM-like stack at CIT in air, with initial LIGO constrained layer springs, for initial testing. Custom front end analog electronics wil be built by the CDS group. There is some question about whether we can get a D-space, or similar controller quickly enough to support our schedule.

The schedule continues to be refined and reviewed with more realism as the planning proceeds. A start of installation in October appears to be very difficult; still under review.

SEI HYDRAULIC PUMP STATION:

Ken Mailand

CONSTRUCTION: Materials and Components are arriving for the assembly of the test pump station. Assembly has started.

WORK SPACE: CES work space is finished, power etc. is in.

LAYOUT DRAWING: I have started a layout drawing of the location of the components on the granite base, and configuration of the plumbing.

MANIFOLDS: Station 1 and 2 and test load have not been started yet.

LONG TUBE RUN: Design of a method to assemble, support and isolate the 360 foot tubing run is in progress.Test taps at the 60 foot mark [shortest run] and 180 foot mark.

Additional parts and hardware have to be located and ordered. Final word on the accumulator, electronic pressure sensors, resistor configuration, and test load requirement from the Stanford group is hoped for soon, final layout and parts purchase require these components be defined.

Rich Abbott

Specified the work to be completed in order to finish a six channel +/- 10 amp voice coil driver as a back up plan for the seismic feed forward effort.Ordered parts for the same

Met with Riccardo DeSalvo to gather information about the seismic feedback/forward electronics he will need built.A plan is in place with names next to the action items to supply him the boards he needs.

Sander Liu

Finalized remote interface box schematic design. PCB and hardware design in progress. Started preliminary design for the Post Processor.

Differential Driver & Receiver Modules for the Penteks

Jay Heefner
In the process of hunting down noise on the LHO 4K suspensions we discovered several sources. The first is similar to that discovered on the 2K ASC biases and is caused by the polling of the pentek module. Hopefully the new timming modules will eliminate the need to poll the penteks and eliminate the noise. The other noise source comes from the connection of the pentek (single-ended output) to the anti-image board (single-ended input). It was found that the noise on the signals could be reduced signifcantly by using shielded twisted-rolled ribbon and a differential driver/receiver in the signal path. I have sketched up designs for a prototype system and circulated them for comment. I hope to complete the designs and fab the first prototypes starting next week. If you have any comments or suggestions, please get them to Jay ASAP.

New DAC Module RFQ Response

Jay Heefner
Vendor responses to the Request For Quotation (RFQ) for the development of an improved DAC module have been received and are being evaluated. We should have complete details and a summary by next week.

CDS Software

Rolf Bork
Lori has begun testing the CDS standard filter software. I hope to start incorporating it into new ASC software next week.

Alex has been working on drivers for the loaner 2Gbit/sec reflected memory link and testing with our DAQ system. Using this link, we were able to increase the DAQ system capacity from present 10MByte/sec to 25MByte/sec. Limiting factor now appears to be DAQ controller VME transfers. I'm not sure that we need to switch over to the new modules at this point (present load at LHO is ~9MByte/sec). I just wanted to ensure we had an upgrade path, if needed, and that we could develop the Solaris drivers (not supported by vendor). 

New models of VME Pentium boards due to ship from vendor Feb. 26. These will be tested with LSC code in hopes of squeezing out some more performance.

Optical Metrology

Helena Armandula
Taking surface figure data on spare LIGO optics.

Lee Cardenas, Liyuan Zhang, Bill Kells

OTF Lab, Contamination Cavity # 2

A complete and new alignment has been made but could not lock the cavity for long period.

Finally decided to make a new mode match, in the process we decided to change the beam waist on the EOM .

After calculation for maximum transmission, the new EOM beam waist changed from 0.20mm to 0.435mm beam waist and mode match made to the cavity. Alignment is in progress.

Contamination Cavity # 1

We decided to start from scratch. Lenses replaced for the new mode match. Alignment and beam quality check is in progress.

Optical modeling

Erika D’Ambrosio
Melody is not matching the predictions of the model I am working on, using the 

same modes but it does if run with more modes. Why the same physical situation

described using the same basis vectors is not represented in the same way? The

puzzle is related with the properties of the optical operators and the scalar

product of their eigenvectors.

Briefly, if the vector

v_phys = {a_1, a_2, ... , a_N, ... a_Infinity}

is the one we are interested in and we look for a vector defined by the first

N components as in

v_model = {c_1, c_2, ... , c_N}

that be the closest one to v_phys, the natural choice c_i=a_i tends to be good

when N->Infinity and when losses->0. This is related with a lot of mathematics

that I have been studying in the past two months: when the eigenvectors cannot

be inverted upon time-reversal they do not define an orthogonal system and as

a consequence, the distance between two vectors is not simply minimum when the

distance between each component is minimum. This happens when we can trace the

projection from one point to the axis in an orthogonal frame and we know that

that projection gives the coordinate of the point according to that axis. When

the axes are inclined this doesn't work, although the projection is the method

for having minimum distance.

The loss is crucial.

Let's say v_phys is produced by the finite diameter of a mirror so that there

is less power in the first modes and more power in the higher order modes. The

simple cut of v_phys to the first modes will take into account only the first

of these two effects.

Bill has been independently finding a similar effect for the shift and we are

keeping on doing separate investigations and discussing a lot about our ideas.

PSL

Peter King


A number of attempts have been made at optically contacting the

pre-modecleaner (PMC) prism to the body, with perhaps only one try that was

partially successful.At just over 3000 sq. mm in area, the largest area

that was nicely contacted was approximately 150 sq. mm.The two surfaces

in question are the largest that I have dealt with.With the fixture to

hold the body aligned with the prism, I am quite paranoid about applying a

strong force in case something slips and scratches the other polished

surfaces.This is a work in progress.

Varaible Timing Delay Board

Rich Abbott, Mohana Megeswaran, Flavio Nocera


Went through details of timing system boards and prioritized action items. It is our goal to get the variable timing boards complete by the end of March to allow time at the sites for testing before S1. Mohana is working full time on this with Flavio consulting as needed.

Varaible Timing Delay Board

Rich Abbott
Finished writing a test procedure for the LSC whitening board.Testing of these boards can now begin.Sent a preliminary board to LHO for their immediate use.The partial test of the board was noted on the traveler.

DMT

John Zweizig
This week I started to fix some of the problems with the DMT software 

and associated documentation that were identified during the E7 run.

Specifically, I modified the trend class to repair many little problems

that have been dogging its use. I also changed the way trend file names

generated by the class to meet the new frame file name standard. I have

also started setting up the make files to build the documentation for the

GDS software.


40 Meter Interferometer (Weinstein)



 



Thermal Noise Interferometer (Libbrecht)


no report


LASTI (Zucker)


no report


Data Analysis and Computing (Lazzarini)


Simulation and Modeling (Bhawal)
Weekly Physics meeting
-----------------------
Virginio Sannibale talked about simulation of LIGO spring and some problem he encountered
while taking into account the shear effect of the spring in horizontal directions. Later
Matt talked about the addition/improvement he is making on the Han2k model.

LIGO I simulation system
--------------------------
(Matt) completed the detection mode LSC sub-system and currently testing the LOS sub-system.

Modal Model
------------
(Hiro,Biplab,Matt) discussed and did calculations to determine the exact relationship between
the phase change due to the curvature mismatch and the change of the guoy phase due to a
mismatching input beam. Performing tests to verify our analytical calculations and guesses.

Code development and maintenance
---------------------------------
(Biplab) Did various null tests to ascertain if signs for e2e's tilt angles are conforming
with its standard notation. Found that the yaw should be negative of what it had been so far.

(Hiro) made some changes in AdlibMM.

Alfi
----
[Last week, by mistake, the "Beta" release of Alphi5 was reported. It should be "alpha" release]

(Bruce)
- General debugging of Alfi5.
- Reworking graphics update messenging from the bookkeeping to have a more clear
   and robust methodology.

(Melody)
- Addressed problem reports for the alpha version of alfi5.

LIGO Data Analysis System

Software Systems (Blackburn)
cntlmonAPI utilities: fixed directory problems with logscan,
db2utils and coreWatch. Have logscan supply a default subject
and email instead of not emailing at all. Fixing other
utilities due to path changes in api rsc files.

metadataAPI: fixed problem with -returnformat validation; read
back -outputformat to getMetaData.meta. Responded to several
request at sites to check on metadataAPI being hung: turns out
database server was not up. Filed problem report to better notify
when condition happens.

cmonClient updates: have node-balance work with the mpi functions
to add, delete and update node changes.

The lexical parser for channel names in the wrapperAPI has been
implemented and unit tested. A full system test will require a new
version of the lal and lalwrapper libraries which should be available
today.

A new cron job was added to nightly build process to cleanup any
of the nightly builds more than one week old. In addition, the
nightly build process has been enhanced to include the construction
of tarballs for the individual components of LDAS. This is allow
better syncronization of users of the development system with the
newer functionality found in the development system.

The LDAS CVS respository was corrupted by an incompatibility in
versions of rsync roughly two weeks ago. It was discovered this
week that the corruption extended beyond what was recognized at
the time of the rsync. A careful analysis of the log files identified
107 files. These files were inspected by hand and all understood
changes made to restore the repository.

Support for the FrDetector structure was found to be missing in the
frameCPP and the frameAPI. This was added and we have tested the
passing of detector geometry frameAPI to the dataConditionAPI.

Hardware Systems (Anderson)
Caltech
-------
(Al Wilson)

* Further refinements of big brother.

* Starting to integrate tripwire into the BB reporting system.

* Got word from SUN about the sun blade that look like it was running hot.
  They report that everything is fine. Until it start spitting out error
  messages there is no need to be concern. The CPU is at a temp of 70c. After
  some winning to sun they told me that the upper limit is 72c.

* Rebuilding a laptop for Phillip to take overseas.

* Did some last minute tiding over in synchrotron. Construction was to start on
  02/13/02. They have started with the new fiber run.
 

(Stuart Anderson)

* Brought the first new SunFire 880 server into production in the ldas-dev
  system as the dedicated frame data server.

* Working on integrating the new SunFire 880 server and T3 RAID unit at MIT
  into the ldas-mit system.

* The HPSS web data catalog is back on-line at a new more permanent location,
http://www.ldas-sw.ligo.caltech.edu/archive/hpss

MIT
---
(Keith Bayer)

* Freed up ldas-sundev1 to go back to ldas lab.

* Continuing to load E7 data from tapes .

* Working on stripping off certain frames.

* Ordered SC-SC multimode fiber cable.

* Borrowed and hooked up an SC-SC cable for the short-term.

Livingston
----------
(Igor Yakushin)

* Wrote a perl script to keep the last N database backups, to figure
  out which logs should be kept for possible recovery from these backups
  and to delete the rest.

* Helped to fix an LDAS problem at LLO found by Julien.

* Configured LHO's metaserver for everyday backup of DB2 databases.

* Trying to configure a test federated database on sunbox1 and linuxbox1.

Hanford
-------
(Greg Mendell)

* A script was run on the directory listing of the raw full frame E7
  data stored in HPSS. The outputs from the script are at this URL:
http://apex.ligo-wa.caltech.edu/~gmendell/FrameListingReports/E7/.
  The reports shows

  a) the GPS times when the gaps and size changes occur in the data.

  b) that the number of files in HPSS is exactly equal to the number of
     files that were sent to Caltech on tape. So all tapes were ingested.

  c) The LHO reports shows 7 gaps in time (from 80 to 272 seconds) and 3
     changes in the frame size.  The time gaps were due to ADC reboots. As
     for the size changes, Dave Barker told me the number of channels in the
     frames changed several times during the E7 run.

  d) The LLO reports shows 5 gaps in time, and no frame size changes. The
     last gap is the missing 10 hours when fb2 at LLO was not running. The
     other gaps are 32 seconds, suggesting the framebuilder dropped a 16
     second frame file. I'm told that the framebuilder will drop frame files
     if it becomes too busy.

* A planned power outage occurred on the morning of Tue Feb 12. LDAS
  software and hardware where shutdown and restarted without problems,
  except restarting of the database manager.  This problem has been
  addressed.

* Scripts are finished which drive knownpulsardemod jobs in LDAS to
  produces SFTs:

  a) Automate the running and tracking of jobs.  The scripts log and
     record information for each job run, allowing the scripts to restart
     from the last job run, and to rerun jobs that have failed.

  b) Generate a quality channel from segment files (e.g., GPS intervals of
     locked data) and sends it to the LDAS job.

Data Analysis Activities (Lazzarini)
Prof. Nobuyuki Kanda has arrived for a 5 week visit to Caltech. He will be staying with the data and computing group.

A revision of the Frame Format specification was approved (in principle) by the LSC SW Configuration Control Board. Several iterations are still required with Virgo (B. Mours) to better define some of the changes we want to make to the frames. We hope to take advantage of next week's visit by Mours to LLO (to test GPS timing boards) to have him come by Caltech for one final face-to-face meeting on the subject. Alex Ivanov will be implementing the changes for LIGO.

General Computing (Wallace)
MIT:
(Keith)
-Continued to install MU6 on Sun machines
-Put first machine onto NW22 fiber link
-Spec'd out/ordered desktop PC
-Re-installed/configured laptop for wireless
-Updated ligotools on lancelot
-Rebuilt root / gds software on lancelot

Livingston:
(Tom)
-We have received three new PCs, two of which will be used to
process video signals.
-We are continuing to work on improvements in the network,
primarily to provide services for the upcoming conference.

-Locations for the T1 network usage information:
http://kahuna.net.lsu.edu/mrtg/remrouters/ligo-t1-1.html
http://kahuna.net.lsu.edu/mrtg/remrouters/ligo-t1-2.html

Hanford:
(Christine)
- With less than 24 hours notice, prepared for a site wide power outage
by securing all computer systems on the site and testing UPSs for the
main servers and network routers.  Then an hour before the outage was to
happen, it didn't.  Went around and powered up all the computers that
had been secured.  Dealt with several problems of systems not coming
back properly and processes not starting automatically like they should
have.
- Still in the process of replacing old PCs with new ones.  Requires
installing base configuration software and helping users transfer files
between computers.
- Created some new user accounts, did some purchasing, replaced the
power supply on one Sun, called the Sun technician about an Ultra60 that
won't boot, discovered how to install HP network printers on Win2K
without a print server and tested some software for documenting server
configurations.

CIT:
(Mike)
-NTServer's; testing all NTSRV's for security holes with Bryan from
ITS.CALTECH.EDU He is checking vulnerability from the outside or internal
unauthorized access to our NTSRV's. Began tightening up security holes on all
servers. I still have a lot of patches to install and button up some services
that are running but I have to do some research before I attempt to make these
changes.
-Amaldi; the original server that had gone down due to hardware problems
was ready for me to load. I still have a full operational temp server up and
running that is servicing the Elba website.
-pherkab; I ran ghost backups on Pherkab one of the admin web server's for
this server is having problems freezing up this might be leading into
another hardware problem it turns out that this server is identical to the
Amaldi server same exact hardware configuration which is a 1.4 Ghz
according to HPC they have been having problems with this style of
processor they end up getting to hot which causes the CPU to freeze up.
Intel has change the size of the chip to a much smaller size with more
horse power and this has seem to run a lot cooler their for preventing the
CPU from getting so hot.
-Laptop; I had to load some additional software on a laptop, to get ready
for a user to borrow from the loaner pool.
-40 Meter; I got a PC ready for Lee Cardenas to put transfer to the 40 meter.
-Helena; I worked on a PC loaded with NT4.0 that was having printer
problems. Looks like I have to reinstall the drivers;
-Printers; I had to do maintenance on multiple printers which included
swapping out drum kits, fuser, paper jams, and toner cartridges. I also
blew out the access powdered ink with compressed air for they were real dirty.
-Fred Mann's PC was having problem's,  the system files were
corrupted due to the goner virus. His computer was virus free but the
damage had already been done and the only way to correct this problem was
to reload. I set Fred up with a temporary computer until I get his old one
reloaded.
-User Support; I had a whole lot of onsite and phone user support this
week, that include e-mail, printing problems, networking problems and
software problems.

(Lisa)
-Worked with the Foundry rep on configuring the new switches.
-Set Gary up for PDASync on Solaris.  For people with old calendars, the
calendar file must be converted into version 4 format using "sdtcm_convert -v 4
username".
-Did some more work with ssh and agents.  Looked at a script for maintaining
keys.
-Started looking at how to install grid.
-Doing some diagnostic work on the backup tape hardware and media.

(Veronica)
- LIGO website: posted updates to various parts (LSC, MOUs, Employment,
Student Undergraduate programs). Posted updates on Elba 2002 GWADW
website; keep working on graphics. Keep working through the CVS manual.
- CaJAGWR: will tape Phinney's talk on Friday. Re-compressed and posted one
of the previous talks.

(Larry)
-Worked on a number of procurements. Mainly, upgrades to PC's and a new server
SUN box for Wilson House. Filtered a couple of sales people for Stuart, boy they
are starting to get aggressive. Worked with accounts payable on getting some
issues resolved with Foundry.
-Foundry was out to start going over the GigE network. The equipment has the
preliminary configuration. As soon as the rest of the edge switches arrive we
will get them installed and work on upgrading the configuration from a layer 2
to layer 3 in the future. With some of the present schedule issues we need to
get the equipment installed ASAP.
-All of the new fiber installations for Bridge are finished. The edge areas are
still being worked on but should be finished by the end of next week.
-Wrapping up the GC Usage Policy statement. It should be ready for the sign off
cycle next week.
-Resolved a number of web policy issues. Just need to let people know that there
are a number of things that have to be approved before the changes are made to
the WEB.
-Debugged a few network issues. Also, working on some of the security audit
issues with Bryan and Mike.
 
 


LIGO II/Advanced R&D (Sanders)


40m
Helena Armandula
Ordered air bake oven.
Getting maintenance performed on the DI water system (changing filters, purging system) in preparation to optic's cleaning.

40m
Janeen Romie
Another box of mechanical parts will be sent to LHO for cleaning and baking tomorrow. I have received all the fixtures. Only counterbored screws to finish. Helena has submitted the order for the air bake oven for the So. Annex. Looking at how the magnet gluing fixture can be changed to fit the thinner ITMs. Made up a list of things needed for the suspension work and assigned each to a category - have already, need to buy, provided by site.

40m South annex
Lee Cardenas
New bake chamber is fully prepared to bake.  We are waiting on the new free oil pump station.
The small bake oven is also ready and operating.

40m
Rich Abbott
Ordered parts needed for the 40 meter lab frequency distribution system.

From: Mark Barton <mbarton@ligo.caltech.edu>

This week I've been at MIT getting some hands on experience with the quad
prototype and working with Rich Mittleman to try and sort out some
puzzles with the measured mode frequencies and controller performance. A
big chunk of the confusion turned out to be different versions of the
modelling software in different places. As part of this effort I got
around to rederiving all the matrix elements used in the Matlab quad
model. (I had previously reported errors in the longitudinal/pitch
elements.) The vertical and yaw elements were correct, but the
transverse/roll elements had some moderately significant errors
sufficient to change the predicted mode frequencies by up to 10%.
Unfortunately it's longitudinal/pitch that we're most concerned with in
the short term and there the errors are too small to explain the observed
discrepancies.

From: Janeen Hazel Romie <romie_j@ligo.caltech.edu>

AdLIGO Suspensions
Working on RM suspension layout and providing interations to Phil for suspension parameters.
Working on budgets with Thomas, specifically organizing the cost book into segments for the budget meeting tomorrow.

From: Helena Armandula <ahelena@ligo.caltech.edu>

Advanced LIGO - Coating
Arranging to include in the next absorption coating run at MLD  (Ta2O5/Al2O3) some "Q" measured substrates.

ERGO (ERGOnomic mechanical large optics' handler)
Approved specs and requirements during a meeting with the immediate ERGO users and Mike Gerfen from CES.
Mike will manufacture one unit as prototype.

From: ctorrie <ctorrie@ligo.caltech.edu>
Suspensions

Norna, Mark and I met again, via the conference phone, with Rich and Peter at MIT with regard to work being carried out on the quadruple pendulum at MIT. This was very productive and we were able to go through all of the work Rich has done in detail and suggest what other things he could do so that we can compare both the electronics and the behaviour of the suspension directly to the MATLAB model.
I believe that after a further call yesterday we can now say that the damping in the longitudinal direction agrees with what is predicted in the model.
Norna and I are using the Simulink quadruple pendulum model to predict why we are seeing some problems with the damping of the pitch modes. In the mean time Rich is going to measure the damping in the other degrees of freedom allowing us to compare these with the predictions.
 

Mike Plissi and Stefan Gosler at GEO were investigating why the Bean Splitter suspension was not damping as well as predicted. With my help we were able to solve this problem using the existing GEO triple pendulum model. Mike and Stefan sent me the frequencies that they measured from the suspension, these were different from what we had originally predicted. Changing various parameters in the model I was able reproduce the measured frequencies and could therefore suggest what parameters to check on the suspension. It turned out that the break off point of the wires on the upper mass was larger than  predicted due to a hidden interference. Mike and Stefan were able to use the model to tie up the poor damping they were seeing and are now making changes to the upper mass to solve this interference issue.
 

I have finished a set of drawings and an assembly for a planned single pendulum experiment in SolidWorks. Information gathered from this will be very useful for adding various effects to the pendulum models. This has been a very good exercise for learning SOLIDWORKS.
 

Using SOIDWORKS we were able to create curved blades and transfer them to ALGOR for analysis. Jannen and I are currently working on what is the correct set of parameters to use in ALGOR for loading the blade!
 

Janeen and I have began iterating the drawings of her cage design with my pendulum design for the LIGO Mode cleaner suspensions. We plan to concentrate on this and the Recycling suspension design in the next few weeks and months.

From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>

Akiteru, Szabi, Iida, Nishi.@ Hongo
Commissioning the suspended Fabry Perot.
 

Szabi
TAMA-SAS: I assembled and tested the my drift servo module for the
second tower, which is very close to completion. This servo is one of
the LIGO contributions to the project. We have near term plans to extend
 

the capabilities of the module (software extensions).Work continuing.
 

Akiteru, Iida
Calculating effects of angularly stiff suspension wires.
 

Hareem, Riccardo @ Pasadena
Dropped (Riccardo) and broken sample insertion tool, waiting for
replacement, testing software on the sample inside the chamber.
 

Jan, Bill, Riccardo, Hareem @ Pasadena
Prepared AuSn braze material, conditioned in 2 mm wires, unfortunately
still not very useful for precision brazing, waiting for 0.5 mm
capillaries to condition it in useful, less than 0.5 mm diameter brazing
wire.
At Carnegie Mellon failed to spin cast MoRuB, considered to go that and
transfer to them the know how gathered years ago on that technique.
Found a better solution in spat cooling.  Spat cooling hypercooles a
drop of MoRuB falling from a R.F. levitation melter clapping it between
two polished copper hands.  Produces 2 cm diameter 50 micron thick
disks.  The advantage of the higher thickness is  that the flex joint
will be stiffer in the unthinned brazing region making brazing easier
and reducing the danger of buckling.  The desired 15-10 micron thickness
can still be obtained from the 50 micron samples by electropolishing.
 

Alessandro @ Pisa
Received from Carlo, G&M, the mechanics of the Q-factor glassy metal
setup, introduced some minor modifications, back to G&M for
modifications before shipping to Pasadena.  Suspension hook mechanical
prototype ongoing waiting for braze.
 

Riccardo, Szabi, Virginio, Luca
Working a remedial internal damping scheme for the LIGO I stacks.
Will build a quick  test HAM at Pasadena using spare LIGO I springs and
optical bench to test the scheme.  Procuring all long lead materials
 

Riccardo @ Pasadena, Tania  @ Bientina
Designing the mechanics of the new remedial internal damping scheme for
the LIGO I stacks.  Full LASTI design should be ready early next week.
Actuator yoke design already finished and sent to G&M for prototyping.
 

Carlo G&M @ Lucca
Building actuator prototypes.
 
 

Riccardo @ Pasadena, Gianni  @ Bientina, Alessandro @ Pisa
Looking at the theoretical possibility to design negative stiffness
suspension for the piers to passively neutralize the ill effects of the
bellows and isolate the LIGO stacks.
Testing over compensated GAS compensating the stiffness of an external
spring mounted in parallel with the GAS.
 

From: Benno Willke <bfw@mpq.mpg.de>

here is the status report from Stanford.

Stanford was unable to attend your teleconference this week because the
laser physicists were at the Advanced Solid State Laser
meeting held in Quebec, Canada.  However, we did make some progress on
discussions with LIGO regarding upgrading the LIGO laser
at Stanford as an input to the slab amplifier chain.
 

I have attached an email letter to Peter King requesting that we have
access to one of the to be delivered laser amplifiers so that we will
have adequate input power to power the current slab amplifiers to
greater than the 100W power level.  If the amplifiers are not made
available, then we requested an upgrade of the LIGO laser at Stanford to
the 18W power level.
 

Our plan prior to the LSC meeting is to set up the slab YAG gain
elements that we now have on hand and to measure input and output
power and beam parameters.  This should give us a good indication of the
performance that can be expected from the end pump YAG
slab amplifiers that have been ordered and are now being fabricated.
 

A key element of our longer term support for LIGO in laser engineering
is a successful funding of a large DARPA sponsored laser
research program.  The program is now in review.  We expect to learn
about the outcome over the next month and so see funding begin
by mid May, 2002.
 

The operation of a LIGO laser/amplifer at the 20W power level will also
allow us to pursue studies of thermal loading of the
pre-modecleaner and to test in detail the MELODY code written by Ray
Beausoleil.
 

From: David Shoemaker <dhs@ligo.mit.edu>
SWG Telecon, Friday, 9am Pacific

Agenda:

The Usual Generalities

Upcoming LSC meeting -- topics?

*** I have invited Valery Mitrofanov to talk about Sapphire

Pre-Isolator status  (Coyne)

Coating losses program status (Rowan/Harry)

Plans for tests on a Sapphire-fiber-Silica prototype (Robertston/Hough)
 
 

Summaries:

=================================

SWG Monthly progress Report for the Syracuse Group
submitted 31 January 2002 by Peter Saulson
Q of fused silica flame-drawn rods:
It has proven difficult to ring up the 3 kHz mode
of our 8 mm silica rod. This has been the focus of some
effort, because there is some reason to believe that there
is an interesting frequency dependence in thick samples at
high frequencies. Andri remembered the frequency dependence
reported by the Japanese group for their blocks, and pointed
out that our 3.5 mm rod showed a similar decrease in Q with
increasing frequency. Stay tuned.
Annealing status report:
Steve Penn will soon modify a surplus annealing oven to be
able to hold fibers vertically. (Right now it is set up for long
thin samples held horizontally, no use to us.) When that is
done, we'll measure the effect of annealing a thin fiber, to
go after surface effects. We'll also anneal a thicker rod, to
see whether the cooling history affects its Q.
We did use a different annealing oven to try to reduce the
birefringence of a silica sample for the anelastic experiment.
We used one with large birefringence (due to some brute-force
welding.) The good news was that the overall level of
birefringence was reduced substantially. The bad news was that
the small-scale gradients weren't reduced; since those are
what give us false signals due to sample motion, annealing
didn't really help us against that systematic error.
Anelastic experiment:
Scott Kittelberger tried a new sample configuration that
seems promising: a block standing on one edge on a flat steel
support, squeezed by only a single PZT that pushes down from
the top of the sample. Scatter of the data was pretty low.
Scott is now compiling a database of the many different
configurations that he's tried, to prepare for a detailed
comparison.
Coating experiment:
Steve has been measuring the Q of a thin blank that has
been coated. Preliminary result: Q is approximately 500,000.
The good news is that this is about what Gregg Harry is seeing
in his measurements.
Violin mode monitor:
Andri has started recording long data sets, and is analyzing
thermal noise data in earnest. He can find the power in any of
about a dozen modes, track it on various time scales, and
form the histogram of the power to check for Gaussian noise
versus excess noise.
Personnel notes:
Andri's start date at LLO is now set for 1 April.
Undergrad Josh Smith will be attend graduate school at
the University of Hannover next fall, where he will keep working on gravitational wave detection.

==========================================================

Stanford Coating Losses (Sheila Rowan)

Attached are two excel files. One contains our raw data (a) for the Q measurements of a silica sample with a 30 layer SiO2 /Ta2O5 coating and (b) for a sample with a 2 layer (courtesy of Peter Sneddon).

The data is plotted on two charts - one showing the before and after coating Q's for 3 modes of both masses (the modes which have the highest uncoated Q's) and the other showing the same data for all five modes.
Eyeballing this chart suggests immediately that the 2 layer coating is having less effect than the 30 layer.

The second file contains more detailed analysis of the results.

We believe that the right way to analyse the data is to subtract the measured losses for each mode of the 2-layer coated mass from the measured loss for each corresponding mode of the 30-layer coated mass as this removes any effect of annealing on the intrinsic loss.
Using the loss values obtained by doing this we then performed a regression analysis, as for the previous silica masses we studied, to obtain a value for coating loss. We find that of the various ways it is possible to analyse the data this gives the best to date.
We include this fit, and also the numbers for an analysis using the 30 layer on its own (phi_30 - phi_uncoated), the 2 layer on its own (phi_2 - phi_uncoated) as well as the (30-2) layer analysis. The phi_uncoated in each case is the actual phi as measured and shown in Peter's histograms.

Note 2 things:

1. The 5 point fit has an intercept still, but it is small and we are interpreting this as the difference in the intrinsic phis of the 2 masses after the annealing they went through associated with being coated
2. The error seems higher when the fit is used from when the simple numbers are used. We think that for some reason which is not yet clear the error in the fit is too high.
There is quite a lot of information here which we can discuss in more detail tomorrow
 

=================================================

MIT Coating Losses (Harry)

We have gotten Q data on a coated sample. Sample 3, which had a Q of 23
million before coating, was coated with 30 layers of alternating SiO_2 and
Ta_2/O_5, with layers lambda/4 thick. Initially the two modes were 150 Hz
apart. After coating, the higher mode had moved from 2728 Hz to 2732 Hz,
4 Hz. The lower mode moved from 2580 Hz to 2246 Hz, 334 Hz. The higher
mode had a Q of 530,000 and the lower 218,800 after coating.
Using the 530,000, the theory developed in the coating papers, and the
coating energy David Crooks calculated for the old thick Syracuse sample
(scaled to the thin samples S/V ratio), we estimate a coating phi of
1.5 10^-4. This is in good agreement with the 1.0 10^-4 on the thick
Syracuse sample with a similar coating, and the Glasgow sapphire sample
with the same coating.
The question remains why the lower mode changed in frequency so much and
why its Q is so much worse than the higher mode. One hypothesis is that
the coating created a non-symmetric stress which has a great impact on the
thin sample. We are looking for the first drumhead mode of this coated
sample to see how a radially symmetric mode compares. A comparison with
the nominally identical sample currently at Syracuse can test this stress
hypothesis. We may try to reanneal these samples to change/fix the stress
to see how this effects Q.
We will hang sample 4, which has two layers of the same coating, after we
are done with the drumhead mode of 3.

===============================================

GEO Suspensions Report from Norna Robertson covering GEO Glasgow and NAR at
Caltech.
 

A. Materials
Measurements on coating losses (to be reported by Sheila Rowan for
Stanford/Glasgow)
B. Other Suspension Matters
1) Continuing work on blade behaviour at Glasgow in collaboration with
Caltech, to allow more accurate prediction of deflection under load for
wide variety of lengths and thicknesses.
Experimentally: deflection vs. mass for 4 different pre-curved and one
flat blade so far. Work is ongoing to compare to finite element
analysis. Work on transferring CAD drawings into finite-element packages
is also ongoing. Experience so far: it is possible to import Autocad
drawings in IDEAS with suitable STEP translator. Work on Autocad to
Algor - awaiting required Algor update.
(E Elliffe, R Jones, A Grant, M Plissi)
2) Work on design and costings of electronic and associated parts for
local control for prototypes at Caltech and LASTI.
Updating of coil former,holder,clamps etc used in MIT quad: CIT has sent
to Glasgow Autocad assembly drawings for production of engineering
drawings to be used for obtaining quotes and prototypes (R Jones and E
Elliffe)
3) Work on design of modecleaner prototype for LASTI ( NAR w/ CIT at
Caltech - to be reported elsewhere)
4) Information concerning heavy glass learnt at visit to SEM-COM (HA and
NAR)
i)The highest density lead glass they are happy working with is 6.5
gm/cc (c.f. sapphire 3.98 gm/cc). We had aimed to use something close to
twice sapphire for 10Hz design. We obtained small samples with 7.2 gm/cc
in Glasgow for initial bonding experiments, but this has cadmium in it
(as well as lead) which some companies do not want to work with.
ii) High lead content material more difficult to cast - is softer and
can have problems w/ cracking. So learning curve will be needed for
making large pieces.
A suitable company has not yet been identified who are willing and able
to polish the flats on large heavy glass pieces.

=====================================================

Caltech Suspensions: Hazel, Torrie, Robertson

Report from Calum Torrie (CIT) Janeen Romie (JHR) and Norna Robertson
(NAR) at Caltech.

1)Cantilever Blades
Prototype cantilever blades, similar to those used for GEO Signal
Recycling
suspension, are being made here at Caltech. We will be testing 2
different
types of maraging steel.
We have measured the deflection on several cantilever blades. For
comparison we now plan to model the blade with its pre-stressed radius
of
curvature and load it in ALGOR to make it flat. (CIT, JHR, NAR)
2)LIGO_MC Suspension
Now have completed assembly drawing of the upper mass including the
various
clamps, blades and detailed positioning of the coils & magnets.
We have been looking at the detailed design of the pendulum with respect
to
the support structure and the required footprint. As a result of this
the
upper blades will have to be crossed and other dimensions changed from
the
original GEO signal recycling design on which the MC design is based
(see
point below). We have a preliminary structure design and have checked
the first resonance.
CIT has been working with Glasgow on design of coil formers clamps and
coil
holders (see report from Glasgow.)

3)Modelling
We have been looking again in detail at the pendulum model of the
LIGO_MC
design, following the changes noted above. We now have a working design
which can be taken forward in order to create a full set of engineering
and
assembly drawings.
The one outstanding issue is the blade design. Work is ongoing as
mentioned
in point 1.
(CIT, NAR)
We have now established that Mark Barton's triple model and the original
GEO model agree under the same initial conditions.
4) Schedule
We are planning to deliver a MC Controls prototype to LASTI in
mid-September. We're scheduling to have the parts procured, fabricated
and delivered to Caltech by mid-July. That leaves two weeks to assemble,
a month to test and two weeks to pack and ship to MIT. We are planning
to deliver a RM suspension a couple of months later. Pending available
personnel, we hope to deliver a quad pendulum a few months after that.
5) Software
CIT and JHR attended a Solidworks training class two weeks ago and are
enthused about the software. Theoretically, we can connect models from
Solidworks to Algor for analysis but we have found problems. Our licence
for Ideas expires tomorrow and Larry Wallace has not heard from them
about a licence extension so we will work to get Algor working better.
STEP translators work between AutoCAD, Mech. Desktop and Solidworks. We
do not have the STEP translator for Ideas - it is not part of the
educational package. L. Wallace is finding out the cost.

==================================================================

Caltech Suspensions: Willems

Suspension Design:
------------------
Given that magnets and coils can drive the mode cleaner mirror directly (as
communicated by Peter Fritschel), it appears that a reaction chain for the mode
cleaner suspension is unnecessary. This is because: 1) the seismic platform
will be very quiet, 2) the mode cleaner noise requirements are not very strict,
3) the force required on the mirror is not very large, and 4) the force on a
magnet by a coil does not strongly depend on magnet/coil spacing.
It appears likely that reaction chains will not be needed for any of the other
HAM optics, either, but we are still looking at the numbers.

Fused silica fiber research:
----------------------------
The dumbbell-shaped fiber analysis has been extended to analysis of loss due to
pins at the fiber ends a la Braginsky. The results agree well with the results
they presented in talks last year, but also show that for thicker fibers the
loss due to pins can be larger due to the couple exerted on the pin by the
fiber. The losses due to pins/attachment prongs deserves attention. These and
the dumbbell fiber analysis have been written up for publication. The dumbbell
fiber analysis is available in document LIGO-T020003-00.
We have submitted for LSC review a paper entitled, "Investigations of the
Dynamics and Mechanical Dissipation of a Fused Silica Suspension," summarizing
the last two years of such research at Caltech. The main results we report are:
1) the measurement of the temperature dependence of the Young's modulus
of fused silica to be (dE/dT)/E=1.52e-4/K (previously reported in
LIGO-T000188-00),
2) the independent measurement of the dilution factor by the temperature
dependence of the violin frequencies, with results matching theoretical
predictions,
3) measurement of Q's for the violin modes of 400-500 million, very high
but not quite up to predicted values,
4) measurement of the Q's of unloaded fibers of up to 11 million,
5) evidence that the thermal expansion coefficient of fused silica
fibers may be less than 4e-7/K.
The coauthors of this paper are Virginio Sannibale, Valery Mitrofanov, Phil
Willems, and Jaap Weel. Jaap is a SURF student who is seeing his work
published, and who just might transfer to Caltech thanks to the experience.
Based in part on the work in this paper, we are composing a database of fused
silica properties relevant to thermal noise, in an effort to unify the ranges of
values we currently use. This will be a joint effort of Moscow, Glasgow,
Syracuse, and Caltech, and we intend to present our findings at the 2002
Livingston LSC meeting. All those with data to share please contact Phil
Willems.

==================================================

Caltech Suspensions: Armandula

Mechanical loss studies
The first part of the SMA/VIRGO Collaboration is complete.
The first step was to evaluate "Q" substrates after cleaning and annealing only, without coating.
Later, we received 2 substrates of each type (thin and thick) coated as follows:
a) 2 layers - 1/4 wave - Ta2O5 / SiO2
b) 30 layers - 1/4 wave - Ta2O5 / SiO2
c) 30 layers - 3/8 wave - 1/8 wave - Ta2O5 / SiO2
d) 60 layers - 1/8 wave - Ta2O5 / SiO2
The absorption measured on some of the coated thick samples was ~0.2 ppm
Web pages are posted with substrate information and measurement results respectively.
Future work will be planned at the LSC meeting after the current results are analyzed.
MLD revised their quote to provide a 30 layer - 1/4 wave - Ta2O5 / SiO2 coating run to compare their coatings to the Lyon's coatings.
The revision was to account for the extra fixture required to handle the masking on the thin samples.
I asked them to optimize their coatings for mechanical loss and absorption on these samples.
(GariLynn) Placed the polishing order for 10 extra thick and thin fused silica "Q" substrates plus 2 Suprasil 311 SV substrates. (low water content)
Materials - High density glass
Visited Sem Com, the company that may cast the special glass and form the Advanced LIGO penultimate masses.
Although Sem Com is a small family run operation they have the equipment and technical expertise to do the job.
They formed four 1/2"dia samples free of charge made from Glass #24935.
I expect to get those samples polished shortly to be used in bonding experiments.
Found a second possible source to cast and form glass parts, Glass Specialty in Florida.
A company representative will be in the LA area next Feb 6th and may visit Caltech.
Silicate Bonding - Stress Distribution
We performed an experiment to observe the stress distribution on the bonded surface of a prism (ear) using a polariscope.
We silicate bonded a prism, made from an old Glasgow design, to a flat polished on a fused silica disk. Welded fibers to the prism and suspended weights to the fibers.
One of the fibers broke while being loaded.
With the other fiber loaded with a few grams, we saw the stress distribution on the bond.
As the weight increased, we observed several stress points where stress was expected from the design analysis.
A few seconds after reaching 2.5 kg of load, one part of the prism's leg broke matching the shape of the stress distribution seen at the time.
The experiment will be repeated again to be able to determine if the leg broke because of stress induced during welding fibers, a flaw on the glass or a design problem.
Two more prisms have been bonded to the disk and are curing.
 

===================================================

MIT Quad Suspension Tests (Rich Mittleman)
 

I have been continuing the work on characterizing the suspension
modes. A set of data on the Longitudinal-Pitch modes has been posted at
http://tintagel.mit.edu/~richard/longpitch/
There is a MSword document LongPitch Modes.doc which has some
explanations and numerical details.
One disturbing feature that should be noted is that some of the modes do
not damp as well as expected, with Qs over 100 when the damping is on.
This is currently being investigate through a number of different avenues,
the model is being rechecked, the electronics is being rechecked to make
sure that it is giving the damping in the model and I have taken some new
transfer function data with high damping settings.
The plots in this folder are;
M3LTF, M4LTF, M3PTF, M4PTF - Transfer functions from actuators #1
and #2 (Longitudinal Motion) to Mass #3 and #4 Longitudinal and Pitch
Motions.
LongNoDamping, PitchNoDamping, Resonance Peak Amplitudes taken from
the data in the previous MXYTF plots.
Mass X Pitch/Longitudinal, using the same data the Qs of the modes are
plotted under different damping settings

====================================================

Caltech Isolation/Materials (DeSalvo)

SAS@ Hongo
Akiteru, et al. are preparing the final SAS Fabry Perot after
successfully locking one tower against the rest of a grounded Michelson.

Glassy metals.
Still no measurements done, but we expect ribbons and brazes and
mechanics for tests to be available soon. The expectations are that the
new non ferromagnetic and non hydrogen hungry strips should be as
resilient as metallic strips (like the 20 micron FeNiB glass that we
have) but with higher strength (5GPa, 4GPa useful) and high internal Q
(>10^4). The limitations are expected to come from thermoeleastic
noise, itself reasonably small due to the ~10 micron thickness of the
finished flex joints.
Szabi, Virginio, Alessandro, Akitero, Virginio
Following an idea from Szabi we are evaluating the possibility to apply
viscous damping using the LVDTs and constant force actuators directly
across the LIGO I stacks to eliminate the ill effects of their
resonances.
The main problem is that this is violating our own basic tenet of
isolation, which is to make attenuation in steps and relegate the
damping to the initial step. The danger is to effectively short circuit
the stack attenuation properties at high frequency.
The actuators seem to be adequate to completely meet LIGO I
requirements, we still have doubts on the sensors, we can easily make a
nanometer over root Hertz, but are bot sure that we can roll it off fast
enough. Then we have to study the viscous damping loop feasibility. If
interested, please consult in DCC our recent papers on LVDT and
constant force actuators.
This study is getting first priority, over everything else that we are
doing.
It is a large enterprise, but it has the potential of putting a rapid
patch on LIGO locking problems. We are presently in a fast exploratory
phase, but if this will be positive we will need help and support from
many people. Everybody will be welcome to help us as soon as we will be
told to give full power.
Given the long lead time of some components we have already ordered some
peek to make UHV compatible LVDTs and some horizontal accelerometers
which, in any evenience, can be recycled for the TAMA interferometer or
the thermal noise facility at Hongo.
About the last item mentioned, Kenji Numata decided to spend the last
half of his thesis studies converting the Hongo 3 m Fabry Perot into a
thermal noise facility. We will contribute by sending to Hongo the
first prototype of small SAS tower that will be used to support the
thermal noise bench (the 3 m FP being used as a mode cleaner). Being
equipped with low frequency isolation, the facility may turn out to be
good enough for suspension thermal noise measurements.
 

===================================================

Seismic Isolation Upgrade (Dennis Coyne)
 

This is a somewhat programmatic summary, from my perspective, of the efforts of many others (principally Brian Lantz, Joe Giaime, Corwin Hardham, Ken Mason, Dan DeBra, and many more)

The performance testing for the first generation of prototype hydraulic actuator was completed at Stanford. 1 DOF isolation of a factor of ~10, limited by the displacement sensing in this prototype, was achieved over a bandwidth > 10 Hz. (see attached noise spectrum). A second generation of hydraulic actuator has now been installed on the Stanford test stand and is undergoing testing. This unit incorporates a modified bellows for higher breathing mode frequency and will (eventually) incorporate a more effective bypass network.
An alternate (less expensive) eddy current position transducer has been obtained for evaluation. The displacement noise spectrum is comparable to the (baselined) Kaman sensors. Further evaluation will be done before selecting.
Characterization of the differential, Wheatstone bridge valve (DYP2S) continues at Stanford. The transition to turbulent flow was found to occur at flow rates less than required for our application. Initial modifications to the nozzle geometry are promising, but do not yet yield an acceptable margin.
The detailed design and procurement for the prototype hydraulic pump station to be used in the LASTI testing has begun at CIT, based on the earlier prototypes at Stanford and MIT. This unit will be tested for pressure noise spectrum with a simulated load before shipping to LASTI for integrated testing.
The assembly structure atop each BSC pier for integrating the sensors/hydraulic actuator assemblies and providing the spring support for the crossbeams, is in detailed design. We expect to release the drawings for prototype fabrication soon. A similar unit will be designed for a LASTI HAM prototype, with the alternate actuator (EM linear motor or piezo)
Fabrication of the prototype springs has nearly been completed. We were only able to find one company capable and interested in the spring fabrication. A spring tester is also being fabricated and will be available soon for measuring the spring rate.
In addition to the external pre-isolation approach (with either hydraulic or EM actuators), we are beginning to explore the use of in-vacuum sensing and actuation (across the stack from the support structure to the table). This later approach has the potential to actively damp stack modes, in combination with active isolation from the external pre-isolator. The internal sensing & actuation might be based on the units developed for TAMA, or other commercial sensors (e.g. geophones and the EM linear motors being developed for advanced LIGO).
A working meeting of the external pre-isolation team is being held at MIT this week. Key is to get a statement of the requirements defined, status/revision to the plan and schedule and establish a date for a project requirements & design review. Attached is a chart indicating the various approaches considered and then dismissed or being pursued.

=======================================

LASTI (Fritschel, Harry, MacInnis, Mason, Miller, Mittleman,
Ottaway, Phinney, Rollins, Shoemaker, Zucker)
 

Vacuum system: A number of battles with bellows leaks have taken place. The system
is now in a useable state and pumped down. Viewports for light access to the cavity
have been installed.

SOS Test Cavity: The two SOS (small optic suspensions, LIGO 1 style) have been installed
and the cavity is ready for use.

Pre-Stabilized Laser: The system is installed, and locked to the reference cavity. It is presently
being used to do pathfinding on an alternative topology for the fast control loop which may
prove advantageous for the observatories.

Pre-isolation: Significant progress has been made in the design of the structure which interfaces the actuators
to the support pier and support tubes. A design summit is taking place at MIT this week, January 31-Feb 1.
 

 comparison.xls_1-1feb021.pdf
 

 Coating_analysis_summary1feb021.pdf
 

 hyd_noise.pdf
 

 Strategies1.pdf
 


For additional information about this report, contact sanders@ligo.caltech.edu