Weekly Report for Week Ending January
17, 2002
The LIGO Executive Committee
Agenda for Monday January 21, 2002 will be:
There will be no Executive
Committee Meeting on Monday, January 21 because of the holiday.
Special Announcements:
Weekly
Report Highlights
The
E7 data collection was stopped at noon CST this Monday.
LSC Issues (Weiss)
No report.
Next LSC Executive Committee meeting
-------------------------------------
Friday Jan 25, 2002 at 11:00AM ET (Please note change of day)
LIGO I Construction/LIGO Laboratory
Administration (Lindquist)
LIGO Weekly Site Telecon (Lindquist)
A Site Teleconference was held on Thursday, January
17, 2002. Discussion centered on the status FY 2002 costs-to-date,
of NSF funding and the Cooperative Agreement, the establishment and budgeting
of FY 2002 accounts, the FY 2002 Financial Reporting format, as well as
the status of the construction at the two sites. Administration is
moving towards restructuring the overhead application for fabricated equipment.
The biggest effect for LIGO will probably be for facilities fabricated
for intended eventual Government ownership. Florence will be assessing
the impact of the changes as best she can given that the information available
is limited.
A review of the recent E7 Engineering Run is scheduled
for February 4 in place of the Executive Committee Meeting. Mark
Coles and Fred Raab will be requested to summarize lessons learned.
The list of current actions revised to reflect
the status of open actions assigned through January 17, 2001 may be found
at ACTION
LIST.
PROPERTY
MANAGEMENT (Chargois)
From: Ed Chargois <chargois_e@ligo.caltech.edu>
-
Submitted Documentation to re-direct
a loss Vacuum Pump Cart originally scheduled for LHO (K. Ryan), This equipment
arrived a CIT on 1/2/02 no one at LIGO was notified of the misdirect shipment.
The vendor BOC Edwards is paying for the shipping Acct # EDHVABUFF002.
-
Assisted the Detector Group (H. Armandula)
with the packing and shipping of six (6) Substrates Serial Numbers 1, 2,
3, 4, 9, and 10, to MIT (G. Harry) via Federal Express 2 day Economy Rate
Account Number P15774
-
Assisted the Detector Group (J. Romie)
with the packing of 100 Clamps individually wrapped (items are not serialized)
and shipped to LHO (B. Rivera) via Federal Express. Account Number P204247.
-
Assisted the Detector Group (H. Armandula
with the packing and shipping of nine (9) Substrates Serial Numbers 0290,0342,0363,5046,5624,5635,5696,
5697 and 5716 to MLD Technologies (Don Curry) of Eugene , OR via Federal
Express 2 day Economy Rate. Account Number P157746.
DOCUMENT
CONTROL CENTER (Turner, Mak)
>From: Linda Turner
- turner@ligo.caltech.edu>
Web pages for the
DCC give simple how-to's for document numbering, easy access to the latest
on-line documents, and search capabilities for the DCC database. Take
a look. . .
ACCOMPLISHMENTS
-
Worked at reorganizing my office and
assessing some of the many piles of paper and boxes of documents that have
accumulated in the last several months. While doing so, went through
about 3 boxes of documents left behind by various staff members no longer
on the project. Found numerous documents, many of contractual nature,
that never had been submitted to the DCC. This was a bit disconcerting
as there are roughly 30 boxes of documents left from various individuals'
departures. REMINDER TO LIGO STAFF:
Please continue to submit documents in a timely manner. Inheriting
volumes of paper months or years down the road puts a tremendous strain
on the limited resources of the DCC to process and make accessible documents
that are important for retrieval.
-
Assembled monthly budget summary pages
of 5M501 from 1995-2000 for the DCAA audit.
-
Rearranged some storage in the sub-basement
to accommodate the influx of file boxes for processing/storage.
-
Continued research on a fax machine
replacement that will bring faxes in electronically, automatically routing
to individual staff folders.
-
Continued the task of scanning the last
few months of the IFIS reports. It appears that there are about 11
months left to scan before I begin burning CDs of the whole lot.
Then we can finally ditch the tons of paper currently stored in the ECR.
-
Continued work on an article for the
February LIGO newsletter.
>
From: Cleveland Mak <mak_c@ligo.caltech.edu>
ACTIVITY
-
Assisted in clearing out Larry Jones'
office. Made labels (listing contents) for the 16 boxes of documentation
accumulated. Transported these 16 boxes to storage in the sub-basement.
-
Assisted in locating and photocopying
documentation for audit support.
-
Progress continues on conversion of
old charge account files to electronic form.
-
Electronic document activity was very
busy for this period.
| 01/10/02 |
Packages |
Faxes |
| In |
32 |
39 |
| Out |
9 |
48 |
Click the link to access
the DOCUMENT CONTROL CENTER
WEB PAGE.
COST SCHEDULE
CONTROL SYSTEMS (Cunningham, Brambila, Kaufman, Akutagawa)
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS
PAYABLE HISTORY DATA .

From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
-
Working on transferring funds from FY2001
to FY2002 on the subcontracts. Yakama, Thomas Staffing, Butler, Benton
County, MCI, Heritage Landscape, MIT, Viking Office, Siemens, and Burns
have been transferred. I am currently working on Excel, and Support Services.
-
MIT's C/O 15 was submitted to management
for signatures and is awaiting approvals. I understand that General Counsel
must also approve it as it crosses the 8 million dollar benchmark.
-
Have several FY2001 transfers to FY2002
I need to accomplish.
-
Prepared the RFQ for the AV system for
the LLO Observatory. Sending out the Addendum today.
From: Florence Kaufman <fkaufman@ligo.caltech.edu>
-
All financial reports as of the end of December have been posted on the
network.
-
Will begin working on cost transfers required from fiscal period 2001 accounts
to the fiscal year 2002 accounts.
-
The reports can be found at: http://docuserv.ligo.caltech.edu/~fireport
SUBCONTRACTS MANAGEMENT (Petrac,
Jasnow)
From: irena@ligo.caltech.edu (Irena Petrac)
-
MIT: CO No. 15, incrementing funds for Dec., Jan., and Feb., was released
to Purchasing. An advanced copy of the authorizing PR was faxed to MIT.
-
SLU: CO No. 02, reflecting the appointment of Dr. Yoshida to faculty status
and associated reduction in required LIGO cost-share (to cover FY '02 and
'03 summer appointments only), was released to Purchasing.
-
HPD: CO No. 05, for a no-cost extension of the performance period through
end of May, 2002 was released to Purchasing..
From: Ed Jasnow <jasnow@ligo.caltech.edu>
CONSTRUCTION:
-
A pre-bid conference was held on Tuesday,
January 15, for the audio/visual equipment for the Livingston Staging Building
auditorium. Three contractors attended and received copies of the Invitation
for Bid. The contractors then toured the facility and reviewed the installation
requirements. During the tour, it was discovered that the junction boxes
for the LCD projectors were in the rear walls instead of the ceiling. After
lengthy discussion, it was agreed to issue an addendum to the IFB which
would require the A/V contractor to run conduit from the wall junction
boxes to the ceiling, where mounting plates would be installed behind the
tiles, and the projectors could be mounted from the ceiling as originally
planned. The addendum will be issued on Thursday, January 17, with bids
scheduled to be received Tuesday, January 29.
-
Ed Jasnow attended the weekly construction
meeting in Livingston on the Staging Building. Several items remaining
to be performed were discussed with the president of Brunt Construction,
Michael Ragusa. These were further emphasized in a walkthrough of the building.
The revised schedule calls for completion of the building by March 1, 2002.
OPERATIONS:
-
The performance of the sites during
the E7 run will be discussed in a special "lessons learned" session to
be given by the two site heads, Fred Raab and Mark Coles, on Monday, February
4. This will lead to a discussion of 24/7 operations to be held at the
Site Teleconference scheduled for Thursday, February 7.
SUPPORT
Irene Baldon
-
Processed the paper work for six (6)
new/revised trips. I have nine (9) trips in various stages of completion
before ticketing can be done and paper work completed.
-
Completed twenty-four (24) Expense Reports
and there are three (3) reports yet to be done. I'm not holding any reports
requiring checks to close at this time. I have two (2) 2001 trips still
outstanding. Each traveler has been contacted and I'm told they are on
the way.
-
Reconciled twenty-eight (28) items on
my P-Card, requiring numerous telephone calls to vendors to track down
which traveler incurred each charge.
-
I'm waiting for further information
and scheduling of a meeting with Montrose. As of today I have not heard
further. I'll keep everyone posted as new information becomes available
to me.
-
Worked on the preparation and distribution
of the Travel/Vacation Itineraries for January 14, 2002. Performed normal
recording and filing associated with Travel and Reimbursement. Also performed
miscellaneous duties as requested by various members of the LIGO Project
here at Caltech as well as from members of the staffs of each of the two
(2) sites.
-
I continue to do MIT's travel to the
sites for installation activities and also to assist them wherever possible.
Dorothy Lloyd
-
Concentrated on coordination of transferring
contracts, blankets and POs to FY02 POETAs with Ruth and Gina. There are
approximately 18-25 invoices on hold pending these changes, with invoices
coming in daily. Followed up on a couple of invoice problems.
-
There were a small amount of reqs that
came in this week and they were processed as usual, with Gina and Ruth
working them in between the FY02 transfers.
-
Jim is now working for the DCC in the
mornings and with me in the afternoons.
Rita Torres
-
Scanned LSC documents for CACR and Penn
State, and updated the database with their respective Attachments Z. Please
note: The software for the 3rd floor scanner has changed so that I must
now crop the output pages. This caused me to re-record some files as I
adjusted to the new method. Formatted three reports from Stanford, then
assigned LIGO numbers before submitting to the DCC.
-
Sent out a test version of the LIGO
Roster, am now collecting responses regarding errors and corrections to
the data.
-
Completed the electronic travelers to
49 boards that will ship from Wilson House. Prepared a couple more travelers
for boards to ship from Bridge.
-
Along with V. Kondrashov, helped prepare
name badges for participants of workshops taking place 1/18 & 1/19.
Title: Project Science Workshop Management of Large Scientific Projects.
-
Arranged a few telecons. Updated site
trips. Helped to box files from the office space that was Fred Asiri's.
-
Placed a few Pcard orders and reconciled
some, did a total of 11 this period.
Advanced LIGO (Frey)
From: Thomas Frey <tfrey@ligo.caltech.edu>
Progress Period from 01.11 to 01.17
Accomplishments:
-
Weekly Advanced LIGO Project Controls meeting was not
held this week. Sent out request to schedule a date for January as
requested by Gary Sanders. Still waiting for date to be set.
-
Advanced LIGO MRE Proposal (Highest Priority)
-
Continuing the development of the Cost Estimate.
-
Continue to pursue all other sub system schedules.
-
Updated web site with latest data.
-
The following is a summary of status by sub system:
-
COC - Work on action items per second review continues.
Next meeting date has not been scheduled.
-
PSL - Issued cost and resource loaded reports and awaiting
comments. Next meeting date has not been scheduled.
-
AOS - Work on action items continues. Inputting
/ reviewing data provided by David S. Next meeting date has not been
scheduled.
-
IO - Work on action items continues. Next
meeting date has not been scheduled.
-
SUS - Working with SUS group to incorporate current
comments. Next meeting date has not been scheduled.
-
SEI - Work on action items continues. Next meeting
date has not been scheduled.
-
ISC - Continue to review data.
-
All other subsystems have yet to be scheduled for their
first review. These dates are pending per direction from Gary Sanders
and Dennis Coyne.
-
Continue to update the TNI Schedule and incorporate
any changes.
-
Updated the plan with progress as of 01.11.02 and
posted to site.
-
Sent out update data requests for progress as of 02.01.02.
-
Continue to update the LASTI Schedule and incorporate
any changes.
-
Updated the plan with progress as of 01.11.02 and
posted to site.
-
Sent out update data requests for progress as of 02.01.02.
-
Project Plan for the 40-Meter Lab Upgrade continues.
-
Updated the plan with progress as of 01.11.02 and
posted to site.
-
Sent out update data requests for progress as of 02.01.02.
-
Continue to test the Cost Book Tool.
-
ROSTER DATABASE:
-
Continued work on procedures for data gathering.
-
Continue working with Rita to input the roster data. Assisted Rita
with some responses to her test run / request for data.
-
COST BOOK DATABASE:
-
Continue to run tests on reports using other sub-system data.
-
Continue review of changes and updates to procedures / online help.
-
Cost Calculation Review received from BK. In process of making corrections
as she has noted and rerunning tests.
-
Mapping and formatting of OPS cost data for input on
hold pending finalization of co-operative agreement.
-
DCAA - Prepared 3 revised transmittals at the request of PL for responses
to DCAA requests.
-
Followed-up on incident with Primavera regarding actual finish dates for
finish milestones being dropped from the update files through email. (No
Change or Solution yet).
-
Development of the Advanced LIGO Project Controls Guidebook
continues.
-
Project Web Site for posting schedule and progress related
data continues to be updated with the latest and greatest.
Schedule 01.18 to 01.24:
-
Next weekly Advanced LIGO Project Controls meeting to
be scheduled. Date to be set for month of January.
-
Advanced LIGO MRE Proposal (Highest Priority Task)
-
Highest priority is the development of the Cost Estimate.
-
Will continue to pursue all other sub system schedules.
-
PSL - Will schedule next meeting.
-
AOS - Continue inputting changes to and prepare for
next meeting TBD. (New data from David to be input).
-
IO - Continue inputting changes to and prepare for next
meeting TBD.
-
SUS - Continue inputting changes to and prepare for
next meeting TBD.
-
SEI - Continue inputting changes and prepare for next
meeting TBD.
-
COC - Work on action items by Garilynn continues. Anticipate schedule
changes prior to next meeting TBD.
-
ISC - Finish review of data. Input data and change WBS as requested.
-
Will issue updated meeting minutes for every subsystem
as action items from most recent review are completed.
-
Will Continue to update the TNI Schedule and incorporate
any changes.
-
Will update the plan with progress as of 02.01.02 and
post to site by the 7th.
-
Will Continue to update the LASTI Schedule and incorporate
any changes.
-
Will update the plan with progress as of 02.01.02 and
post to site by the 7th.
-
Will continue updating the 40 meter schedule and incorporate
any changes.
-
Will update the plan with progress as of 02.01.02 and
post to site by the 7th.
-
Roster Database
-
Will continue work on actions items.
Cost Book Tool development continues. (Highest
Priority Task)
-
Will continue ops cost data input when available.
-
Will continue to work with BK importing data and executing
action items.
-
Will continue to provide support to PL for DCAA audit.
-
Will continue the development of the Advanced LIGO Project
Web Site.
-
Will continue the development of the Advanced LIGO Project
Controls Guide Book.
Reports (Lindquist)
We are doing a standard Annual Report for the
Construction Project as of the end of November. I have received all
expected contributions and am working on the report. This effort
has been interrupted to work on responses to DCAA Audit requests.
Change Control/Contingency (Lindquist)
The following change request has been submitted:
CR-010012
Revision B |
WBS 1.4.4.1 |
Closeout Construction Budgets for Initial Computer Equipment Complement
at the Sites |
P. Lindquist |
Press for the latest Contingency
Needs Projection.
Human Resources (Akutagawa)
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
-
Working with Rita Torres on updating
the LIGO personnel directory (Roster). Rita will be doing all the
updating from now on.
-
Various personnel/payroll /HR related
work.
Quality/Safety (Tyler)
>From: Bill Tyler <tyler@ligo.caltech.edu>
No report this week.
LIGO Hanford Observatory (LHO) Operations
(Raab)
2K PSL: (Doug & Rick) We are making preparations to increase
the 2K PSL power into the IFO from 1 Watt to 6 Watts. We peaked up the
laser alignments, Reference Cavity and pre-mode cleaner visibilities. We
are installing added attenuation to the ISC/IO tables to maintain the same
light levels on WFSs and to set light levels to the trigger PDs etc.
We are placing the light pipes back over the beam path on the 2k PSL .
We have added a BNC bulkhead terminal strip to the 2K PSL table and terminated
all the CCD cameras and PDs outputs. This gives a central point for
measurements without the risk of changing alignments when connecting/disconnecting
cables. We have cleaned up some of the wire routing on the tables as well.
I will be installing the laser safety shutters on the PSL tables and
wiring in the PSL shutters soon to complete the laser safety hardware installation.
We will do a final walk through, approve the new SOP, begin training and
final commissioning as time allows.
Facility: (Otto) Only the slopped portion of the auditorium floor
is not concreted. All the other floors for the building have the slab on
grade. There is only a very minor work left on all the utilities. All the
pipes, wires and conduits are in the ground and back filled only a few
connections need to be made. We are expecting structural steel to arrive
on site the 11th of February.
LIGO Livingston Observatory (LLO) Operations
(Coles)
Interferometer: Immediately following the conclusion of the
E7 run, the laser was shut off and electrically disconnected so that the
acoustic isolation chamber could be installed around the PSL table. The
chamber erection is nearing completion and should be completely finished
this week.
CDS: Upgrading the control room machines to Solaris 8. Working
on the CDS Red book for Livingston. Also today we are working to change
the time server back to the True Time Server in the mass storage room.
I will also look into changing the bad disk on the Frame Builder. Downloaded
a software patch for london to deal with latest security issue with the
CDE desktop on solaris. Completed the CDS diagnostics medm screens and
epics interface for the mass storage room machines. This needs to be added
to the checklist. (Cheithan)
GC: We are working with LSU to put the final touches on the installation
of our new router and firewall.We are doing some maintenance and upgrading
on our servers, which had been on hold over the E7 run.
Detector/Technical Support (Whitcomb,
Coyne)
See
also the daily electronic logs for the installation and commissioning activities:
E7
Run
Szabi Marka, Daniel Sigg
The E7 data collection was stopped at noon CST this
Monday. We received feedback from several people, all very positive and
encouraging. We should all be very happy with the results! The end of the
data collection is the start of the intensified data analysis effort, which
should be our focus for the weeks to come. We would like to express the
gratitude of the collaboration to the people who made it possible to have
such a successful run! A great "Thank You" is due to everybody who participated
in the building and commissioning effort to get us to this point of operation;
especially to the observatory staff.
Lock statistics for the E7 Run, based on a preliminary
report from Gaby Gonzalez, are below; More data is available in the
report and will become available as the GEO and ALEGRO availability is
compared to the LIGO instruments.
Single:
L1
Total locked time: 284 hrs
Duty cycle: 70.7 %
Total time locked with
locks longer than 15min: 249 hrs
Duty cycle for long locks:
62 %
H1
Total locked time: 294 hrs
Duty cycle:
72 %
Total time locked with
locks longer than 15min: 231 hrs
Duty cycle for long locks:
56.6 %
H2
Total locked time: 214 hrs
Duty cycle: 52.5 %
Total time locked with
locks longer than 15min: 157 hrs
Duty cycle for long locks:
38.5 %
Double:
H1 and H2
Total locked time: 180 hrs
Duty cycle: 44.1 %
Total time locked with
locks longer than 15min: 111 hrs
Duty cycle for long locks:
27.3 %
L1 and H2
Total locked time: 160 hrs
Duty cycle: 39.3 %
Total time locked with
locks longer than 15min: 98.8 hrs
Duty cycle for long locks:
24.2 %
L1 and H1
Total locked time: 227 hrs
Duty cycle: 55.6 %
Total time locked with
locks longer than 15min: 154 hrs
Duty cycle for long locks:
37.8 %
Triple:
L1, H1 and H2
Total locked time: 140 hrs
Duty cycle: 34.5 %
Total time locked with
locks longer than 15min: 71.5 hrs
Duty cycle for long locks:
17.6 %
LHO COMMISSIONING
Rolf Bork
Alex made a number of changes to the DAQS controller.
One primary change was to prevent the controller from being overloaded
when framebuilders make requests for configuration updates, which could
cause the controller to go into a synch fault. This was also needed to
support the new multi-CPU Epics Data Collection Unit (EDCU). The new code
is now running and being tested at LHO.
2km Commissioning
Jay Heefner
We have discovered that the noise seen on the 2k ASC
bias inputs to the suspension controllers is caused by ground bounce during
VME polling of the penteks. The noise can be reduced by appropriate grounding
and filtering, but we should consider a LIGO wide solution as part of the
EMI/noise investigations. See the LHO 1/15/02
elog
entry for a description of the noise (user: reader, password: readonly).
4km Commissioning
Rolf Bork
1) Fixed problem on 4k DAQ where the two LVEA data
acq units were limited to only acquiring a few (8) channels before experiencing
VME bus errors. These units are now operating at their intended capacity
of 55 and 97 channels. This adds approx. another 0.5MByte/sec of data collection
at LHO above that recorded for E7.
2) Problem with Digital Suspension Control (DSC)
test points was a mismatch in TP names between GDS and DAQ. This has been
corrected and we will reload and test this tomorrow AM.
3) Loaded new DSC code in end stations, which incorporates
the new filters and other changes requested last month (same as LVEA large
optics, previously installed prior to E7).
LLO
COMMISSIONING
Rai Weiss reporting
The commissioning group at Livingston has not had an organizational
meeting since the end of the E7 run so the plans described last week have
not changed. Currently, the acoustic isolation chamber around the PSL is
being installed and there is a good chance that the laser will again be
on by Friday Jan 18. While the laser has been off, noise, saturation and
the transfer functions of electronics is being characterized and measured
by Mike Zucker, Rana Adhikari, Szabi Marka and others.
SCIENCE
& ENGINEERING SUPPORT
Improved Digital to Analog Converter (DAC) Module
Jay Heefner
The letters to vendors for the RFI should go out this
week. We have asked for responses by the first week of February.
2 Omega I&Q Demod Board
Jay Heefner
Two boards have been stuffed and tested. One was sent
to each site. The remaining modules are stuffed and awaiting test.
RF Photodiodes
Rich Abbott
Finished characterization of all RF photo-diodes in
our inventory. Data has been transmitted to Perkin Elmer for their investigation
into the failure mechanisms & causes. Measured series resistance and
capacitance at nominal bias. Preparing a diode at 29.5 MHz for shipment
to LHO today. Continuing research into RFPD's and trying to get the last
remaining diodes tested and out of the shop.
MC Servo
Rich Abbott
Completed CAD of prototype variable gain amplifier
for use in the MC length path in the MC servo. It will go to the
board house today (01/17)
Timing System, Clock Driver Boards
Rich Abbott
In the process of checking the boards out for the
new timing system clock driver boards. The boards have some stuffing errors
and will require testing. Several are going through an accelerated test
for immediate shipment to Rolf/Stan at LHO.
EO Shutter Controller
Sander Liu
Three new controllers are in various stage of completion.
One should be ready for delivery sometime next week.
LEMO version Anti-aliasing Filter Chassis
Sander Liu
10 housings were received last week. We are waiting
for the circuit boards and electronic components to make kits for Accu-Asembly
to assemble. 20 each of the 16 channel data cables were on order but not
received. A quotation for 200 each D68L8EX-850 Hz lowpass filter modules
were received and an order will be placed next week.
Seismic Signal Conditioning
Sander Liu
In the process of finalizing the conceptual design
document. The document will be sent out to the CDS weekly meeting group
for comment and review.
GEO PSL Boards
Rick Karwoski, Paul Russell
The three main PSL boards (FSS, 80MHz VCO and 21.5
MHz Frequency Reference modules ) have all been tested and burned in. The
Freq Ref and FSS have been boxed up with the appropriate traveler paperwork.
The 80MHz VCO will have its paperwork completed tomorrow. It will be boxed
up and ready for delivery.
Optical contamination testing cavities (OTF)
Lee Cardenas
Preparing the optical contamination cavities for advanced
LIGO materials testing. The first optical contamination testing chamber
is in standby and waiting on Jordan's visit this Friday. Jordan will advise
and be able to provide some other information needed to continue. Another
contamination chamber has been prepared, optics have been aligned (with
exception of a needed 1/4 wave plate), mode matching is in progress.
Data Viewer
Rolf Bork
Hongyu Ding is working on updating dataviewer to allow
it to directly read new 16sec frame files such that it can read archived
E7 data
ASC Code
Rofl Bork
Lori has begun modifying ASC code such that it is
similar to LSC w/configurable filters, etc.
DMT
John Zweizig
Writing code to emulate the LSC on-line software. Comparing the
emulated results to the results of the on-line software recoded in the
data frames will demonstrate that the on-line software is functioning correctly.
Any discrepancies could point out occasional failures such as precision
errors or timing errors if they exist
Seismic Isolation Improvement
Dennis Coyne reporting
·Much
of the team will be meeting at MIT 12/28 through 2/6 to review progress,
design and complete planning. A requirements & preliminary design review
will be held in February
·Rai
Weiss and Joe Giaime are preparing requirements definition. Robert Schofield
has prepared some Hanford wind induced seismic noise data that is being
reviewed.
·Ken
Mason has nearly completed the mechanical design and detailing for the
structure which integrates the actuators into an assembled pair atop each
pier. A set of drawings will be generated in the next couple of weeks for
review by the team.
·Marcel
Hammond has designed a spring tester for the large custom helical springs
and is working with the fabricator. The springs should be delivered for
testing at LLO next week.
·Ken
Mailand spent last week at Stanford to get up to speed on the hydraulic
pump station design and components. He is gathering together a complete
parts lists and will soon be ordering all of the parts to build up a complete
pump station (includes the motor, pump, accumulator, flow resistors, active
diverter valve and controls and transmission line, filters, pressure transducers,
etc.) Plan to design, assemble and test within 3 months at CIT.
·Joshua
Phinney is finishing a report on the transmission line modeling and testing
that he performed at MIT.
·Peter
Fritschel and Rich Abbott are preparing an electronics requirements document
for the hydraulic pre-isolation system.
·David
Shoemaker has been exploring linear electric motor and solenoid alternatives
to the hydraulic actuator. The intent is that they be “plug & replace”
compatible with the integrated actuation assembly that Ken Mason has designed.
Optical Modeling
Erika D’Ambrosio
I studied the formalism of complex-valued Hermite-Gaussians
to understand how operators are supposed to be transformed when biorthogonality
must be applied. Doing so I finally tackled the last puzzle William Kells
and I have been left with: how to switch from an initial TEM basis to the
basis of modes defined by the symmetric combination of the two perturbed
arms. This issue is a "matter of principle" since in reality we have to
deal with the feeding beam basis and we have already explored the consequences
of this on the "sidebands imbalance". The problem of understanding whether
the imbalance is an intrinsic physical effect or the result of using a
driving beam that breaks the symmetry was important. I still have to discuss
my results with Bill but they clearly show that there is an intrinsic balance
of the two sidebands if the basis is chosen according to the eigenmodes
of the common perturbation plus (since the Guoy phase of the eigenmodes
is redefined) the beamsplitter must be moved in such a way that the eigenmode
we choose to be the resonating one has no loss out of the dark port.
These two ingredients are not independent of course
and the analysis has been pretty complicated but roughly speaking there
is a maximization procedure for one eigenvalue that I can use for choosing
the "differential length" and then I formally evaluate the eigenmode for
the corresponding common perturbation and tune the common length. This
basically corresponds to having only the mode orthogonal to the resonating
one at the dark port. If the feeding beam exactly matches that resonating
mode everything is trivial and this choice corresponds to the minimum power
of the carrier at the dark port and all our intuitions are reconciled with
formalism.
40 Meter Interferometer (Weinstein)
Bill Tyler et al have completed a draft of the 40m Annual LIGO Safety
Audit Report. We have already acted on their primary recommendations, and
will act on them all before long. A response (to questions, etc) is being
formulated.
PSL (Abbott, Ugolini, Vass, Smith, King): Our PSL 126MOPA laser power
is now down to 2.5 watts. We hope to swap it for a newly refurbished 700
mW NPRO, early next week, with Peter King's help. Soon thereafter, we will
re-layout our PSL table, with new mode matching lenses and new layout for
the beam diagnostics.
Suspensions (Romie): The mechanical parts for the SOS suspensions have
been cleaned and baked at LHO, and are now back at our lab.
Mode cleaner sensing and control:
-
Smith: The optical layout and a parts-list was finalized; purchase requisitions
were generated for the following beams on the external optical tables:
IO, IMC_R, IMC_T. Mike has drawings for all LIGO-designed parts, and will
draw up the new custom parts; most notably, the periscope assembly from
the PSL table to the IFO.
-
Heefner (from last week): The wiring diagrams for the IO ASC and LSC are
complete and have been sent around for comments. Parts are being ordered.
Fabrication will begin after the suspension racks are complete.
-
The IO ASC controls scheme (digital) requires a redesign of the PZT driver
for the input mirrors. The change mostly involves the addition of a front
panel connector for the inputs. Anyone knowing of any other desired changes
for the driver should let Jay know in the next 2 weeks.
-
Rich Abbott came by to talk about, and inventory, all the parts needed
for the IO LSC, and in the future, the full IFO LSC.
Suspension controllers (Ben Abbott, Jay Heefner):
-
The suspension wiring diagrams for the 40m suspensions (3 MC optics and
7 core optics) are ostensibly complete. The final copy has been reviewed
by Alan and his suggestions have been incorperated.
-
Electronics for the 40m suspensions are still moving along. I have made
a list of all the parts that are needed from modules down to connectors
and cables (including the IO LSC/ASC). A big order went out for VMIC modules.
Ben is working with Todd Etzel to keep the flow going, and to ascribe priority
to the near-term modules.
-
Some cabling is being shipped to Ben from Hanford to help in the 40m efforts.
South Annex Bake oven chambers (Vass, Taylor, Cardenas):
-
Cardenas: The bake oven dedicated for Fluorel parts has been baked again
at 182C for 48 hours and it is cooling down. We'll RGA the oven again to
compare notes with previous RGA scan. Then it will be leak check again.
-
Fluorel parts given to me by Larry Jones are in process of being cleaned
as procedure (E960022).
-
We are waiting for the pictures/schematics of bake oven plumbing from LHO
(Kyle) so we can make the same for the two new bake oven. Bob Taylor has
ordered casters for the new bake ovens as well as some other miscellaneous
parts needed for the lab.
-
I requested to have installed a PC in the south annex for the new Dycor
RGA PC version. Mike Pedraza will complete the installation by January
22. A purchase requisition for two new complete turbo pump station from
VARIAN has been submitted. These new pump stations will be dedicated for
the two new bake oven.
-
Bob has been cleaning up and organizing the South Annex lab, making room
for all the bake ovens.
Facilities (Vass, Jones, Smith, AJW):
-
We continue to explore how to get the particle count in the lab to be less
strongly correlated with the outside air.
-
We received 5 of the 9 optical viewports from Cascade Optical; they scratched
some of the others, and have to repolish them. The tilted flanges for these
windows are completed at CES.
-
We expect shipment of the connectors and feedthrough flanges for the in-vacuum
cabling, from MDC, by next week. Larry has asked Todd Etzel to have the
cables built and tested, in time to be cleaned and baked for installation
in March.
-
Larry is assembling loads of in-vacuum equipment (assembled cables, feedthrough
flanges, cable clamps, optical port flanges & windows, hardware) to
be shipped to Hanford for clean and bake. In the next couple of months,
Bob Taylor will be able to clean and bake small loads here at Caltech.
-
Larry continues to convert his hundreds of IDEAS mech drawings to ACad.
-
We shoot for installing the 2 remaining seismic stacks, all in-vacuum cables,
clamps, feedthroughs, optical ports in March.
-
A computer projector has been installed in the 40m control room.
Dennis is up at LHO (back next week). He continues his studies of correlated
noise with CorrMon, helped Rolf and Dave Barker reconfigure the DAQ to
solve a PEM problem, helped diagnose misalignment in the 2K X-arm, and
assisted or observed in many other tasks.
Thermal Noise Interferometer (Libbrecht)
Since our last report we have made progress in a number of different
areas. We have ruled out two candidate noise sources in the North
Arm cavity: OSEM controller electronic noise and "defocus" noise in the
photodetector. We received the fourth and final sapphire optic from
Crystal Systems and shipped all of the optics off to REO to be coated.
Flavio Nocera was kind enough to build us three more notch filters for
the South cavity. And we further reduced the laser frequency noise
by increasing the gain of the mode-cleaner servo, with the result that
we now see a noise floor in the South cavity that scales as f^-0.5 over
an additional kilohertz at high frequencies.
The fact that, by reducing the laser frequency noise, we can uncover
more of a noise spectrum that looks like thermal noise is encouraging.
Our baseline goal for the TNI was to have a fused-silica-based, thermal-noise-limited
interferometer by Dec. 18, 2001. We first began to see this f^-0.5
noise spectrum on Dec. 3, and its level is approximately that predicted
by the fluctuation-dissipation theorem, based on the measured Q of the
South Output mirror. There is an additional factor of 2 or 3 that
might be accounted for by coating thermal noise (Gregg Harry, private communication).
Moreover, the noise level in the North cavity is substantially higher than
its predicted thermal noise, and it does not exhibit an f^-0.5 spectrum
anywhere, so a spurious source of f^-0.5 noise does not seem likely.
It is still too early to positively identify our data as thermal noise,
but the tests we have performed since Dec. 3 have strengthened the case
for thermal noise rather than weakened it.
Now about the North Cavity. Its noise level is higher than that
of the South cavity, and we would like to know why. We have listed
a number of potential candidates for this excess noise and are in the process
of systematically eliminating them. One of the first things we noticed
was that the error signal for the North Cavity is approximately a factor
of 100 smaller than that of the South Cavity. We thought at first
that the beam falling on the photodetector was defocused, and that that
might be causing the discrepancy. As it turns out, both beams are
tightly focused on their respective photodetectors, so that at least is
not a problem. Next we will check the intensities of each beam using
an independent photodetector and, if those are the same, we will check
the response of each RF photodetector.
Another difference between the North and South cavities is their OSEM
controllers. We have seen evidence in the past that not all of our
controllers have the same noise level, and we suspected that one of the
North Cavity's controllers might be introducing a significant amount of
noise. The most reliable way to check this, if not the most elegant,
is to simply swap the controllers, putting the North Cavity controllers
on the South Cavity and vice versa. We did this, and observed no
change in the noise levels of either cavity. All four controllers
give us a nice, low noise level on the South Cavity and a fairly high level
on the North, so we conclude that controller noise is not the problem in
the
North Cavity.
Our models suggest that the noise level in the South Cavity may already
be low enough to observe Braginsky noise in Sapphire mirrors, but we are
still trying to reduce the noise level in our all-fused-silica interferometer
in preparation for sapphire. We would very much like to have the
North Cavity's noise comparable to the South's, so that we might have two
separate measures of displacement noise in sapphire.
Over winter break, we ran a 700 mW LightWave 126-1064-700 laser and
an InnoLight Mephisto 800E laser near the center of their operating ranges,
as indicated by the manufacturer's calibration sheet. The intensities of
both lasers were measured with New Focus photodiodes, and recorded with
a SR785 spectrum analyzer. No lenses or mirrors were between the lasers
and the photodiodes. Consequently, the voltages measured in the two channels
are slightly different, because of the different spot sizes of the two
beams.
Before and after the 3-week period, we recorded time series and frequency
spectra of both lasers. At the beginning, the Mephisto laser appeared to
have slightly less intensity noise. At the end, the LightWave laser was
dead, and the Mephisto laser looked much as it had before.
LASTI (Zucker)
LASTI (Bayer, Fritschel, Goda, Harry, Laliberty, MacInnis, Mason, Mason,
Miller, Mittleman, Ottaway, Phinney, Rollins, Shoemaker, Zucker)
VACUUM ENVELOPE: Still leak checking after R&R of the leaking
bellows seal last week.
HYDRAULIC ACTUATORS: (10) Fabrication drawings have been completed.
(2) are partially completed, waiting for final results of FEA.
A finite element model of the weldment which sits on the pier holding
the springs and actuators has been completed. A modal and deflection analysis
is running. Results should be available thursday.
CDS/DAQ/GDS: No problems to report.
PSL: This week we continued with our efforts to shake down the
FSS servo. Jamie has started to modify the spare FSS board to test candidate
design improvements. Once the vacuum system leak check is completed we
will commence locking the one meter test cavity.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Bhawal)
Weekly Physics meeting: Luca Matone talked about "Calibration
procedures: e2e and observations" focussing on DC calibrations of ITMs
using two methods: (i) counting of fringes (ii) toggling control loop signals.
Comparison with results using e2e model was presented. Details available
at http://www.ligo.caltech.edu/~e2e
Lazzarini note: I thought it was an excellent exposition in how Luca
has been reconciling measurement with models.
Locking LIGO in presence of mode mismatch: (Biplab) Using the
E2E model of LIGO 2km with all its spatial mode mismatches (coming from
the as-built, measured differences in radii of curvature of the corresponding
mirrors in two arms and from recycling mirror curvature designed to be
matching in the hot state but not in cold) it was shown that model
would achieve lock.
LIGO I simulation system: (Matt) Working on the LIGO1 simulation
system (upgrade from Han2k). I have decided upon and implemented a top
level design and am currently working on subsystem design.
LSC characterization: (Luca) Prepared and verified a new version
of Han2kControl.box, compatible to Matt's original Han2k model, containing
all the new filtering measured in the past few months.
Mechanical Simulation: (Virginio)
-
Started working on the definition of a state-space representation to interface
e2e-mse to other simulation.
-
Found some new bugs in one of the mse object. Most of the stuff which are
not working will be fixed by the new mse version which will allows a better
and easier description of the internal modes of wires and beams.
Code Maintenance: (Ed Maros) Started work on porting e2e code to
GCC 3.0.3. This is preliminary work.
Alfi: (Bruce) Implementing various menu item options.
LIGO Data Analysis System
Software Systems (Blackburn)
A job submission summary has now been added to the controlMonitorAPI.
It has a graphical interface which includes the statistics (number submited,
number failed) and a graph of the GPS time vs the total jobs submitted
in the user specified time interval for any LDAS user (including all).
It even has color coding, showing the jobs that failed on the graph in
red along the total curve.
The problem reported during the engineering run in the metadataAPI whereby
slave interpreters were being killed by users without properly removing
the threads within the slave interpreter has been fixed.
The issue of having more than 5 pending socket connections for the server
in the eventMonitorAPI which was causing some wrapperAPI jobs to terminate
has been resolved by adding more servers to the eventMonitorAPI and by
adding several re-tries to the wrapperAPI to increase robustness.
Work continues on the separation of the disk caching functionality found
in the frameAPI for previous releases into the new separated diskCacheAPI.
Some minor testing has begun, but there is still a weeks worth of effort
here.
The problem that was discovered during the engineering run whereby the
job resultant subdirectories were filling up and not allowing any more
results to be written to disk has been fixed in the development version
of LDAS by implementing a hierarchical subdirectory naming system.
LDAS now compiles with the new GCC 3.0.3 compiler, but it has yet to
be tested with this new build. This effort began today with pressing urgency
on a one CPU Linux Box. Hope to know how well it does by tomorrow.
Several modifications to the rules for building packages used by LDAS
have been made to make LDAS more inline with the more ANSI/ISO compliant
compiler.
Made several modifications to LDAS to support Beowulf clusters with
100 or more nodes.
Hardware Systems (Anderson)
Caltech:
(Dan Kozak)
-
Caught up on lots of HPSS account creations (still some to do).
-
HPSS data migration to 9940s continues.
-
The first two LIGO owned STK9940 tape drives have been installed into the
LIGO tape silo for testing the SAM-QFS mass storage software.
-
Fixed various breakages in HPSS (deleted core files, restarted servers,
added tapes to storage classes)
-
Worked on getting the Ultra10 that controls the STK9310 swapped out.
Dothill and STK have figured out where the bureaucratic problem is (STK
never billed us for the support, it seems). Now waiting on a technical
response.
-
Came up with "fix" (haven't heard back from users yet) for sendmail problem
on LIGO Linux boxes.
(Al Wilson)
-
Moved ldas-pcdev2 to rm602b
-
Have a working nis-utils RPM will be doing test on kitalpha
-
Also on kitalpha will be testing RH7.2
-
Testing the latest sendmail fix from Dan Kozak.
-
Removing SSH v1 protocol from LDAS machines at caltech
(Stuart Anderson)
Met with Sun Microsystems to discuss there near-term plans for new Fiber
Channel equipment. The most important update is that the firmware to support
the desired LDAS storage network topology is now available.
Ingesting E7 data into the HPSS archive.
Wasted a day due to a "planned" power outage in Millikan library tracking
down a bug in the Solaris network table management on multi-homed machines.
Replicated a few hours of "standard" E6 and E7 test data to all Lab
LDAS systems and working to make it available on LSC LDAS systems as well.
Investigated and reported bug to gcc related to Solaris file I/O performance
degradation in the latest version of the compiler (gcc-3.0.3).
Installed new AMD Athlon 1900+ Linux machine to evaluate next generation
platforms for LDAS.
Enabled web access to all CVS software repositories on ldas-sw, i.e.,
CDS, GDS, E2E, DSO, as well as the already accessable LDAS. To browse see
http://www.ldas-sw.ligo.caltech.edu/cvsweb.cgi.
MIT:
(Keith Bayer)
-
Installed cards on SF880
-
Ran full diagnostics on SF880
-
Installed OS on SF880
-
Drilled out brackets off of rack mount for T3
-
Compiled BTU numbers for facilities
-
Investigated admin server crash
-
Turned off SSH v1 on gateway
Livingston:
(Igor Yakushin)
-
Tapes: shipped all E7 data (70 tapes) to Caltech.
-
SunFire 880: performed a diagnostics boot, installed the graphics card,
installed Solaris 8 and configured metadevice.
-
Built a stand-alone LDAS system to play with.
-
Talked to Chethan about an fb2 status indicator for operators: he just
added it to the webpage that operators are checking.
-
Wrote a perl script to extract data rate time series from log files in
a format that can be used , for example, in gnuplot. Wrote corresponding
gnuplot script to generate a postscript plot.
-
Started playing with control monitor on LDAS standalone system ...
-
Returning back to playing with DB2, LDAS jobs, TCL ...
-
Studied first 9 chapters from DB2 Administration guide: Planning.
-
Started reading DB2 Administration guide: Implementation.
-
Shannon and I installed UPS for SunFire.
(Shannon Roddy)
Ordered the UPS for the SF880.
The Cybernetics tape library came back from repairs and is in the Mass
Storage Room. After the run is over, I will reinstall the unit, return
the GC unit to decatur, and test the LDAS unit.
Igor and I installed the UPS for the new SF880 in the Mass Storage room.
Hanford:
(Greg Mendell)
1) Two shipments of tapes with the LHO full frame E7 data have been
or are about to be sent to Caltech. These contain about the first
250 hours of the run.
2) The process writing data from the fb3 framebuilder T3 disk cache
to tape at LHO is falling behind. It will need to be switched to
write data from the archived E7 T3 disk cache to tape to get the last 3-4
days of the run. This is not a major problem for this run, and no
data will be lost. However, the disk to tape write speed will need
to be increased for future runs. The archiving of E7 data to tape
is keeping up with the data at LLO.
3) The copying of E7 data from the framebuilders' disk cache to the
archived E7 T3 disk cache has proceeded without problems since the beginning
of the run.
4) Worked two shifts in the control room.
5) Performed daily monitoring of the ldas systems at LHO and assisted
in solving problems as they arose.
Data Analysis Activities: (Lazzarini)
Worked through the properties of the LSC servo in order to understand
(with Luca's help) the conceptual foundation of the calibration procedure.
Worked on software to automate the discovery of clean locked segments,
by scanning the 'conlog' logs. This function will be added to the
conlog web interface, so that it can be done on demand. (It was done
manually by scientists on shift during the E7 run.)
Operations support activities: (Lazzarini)
-
Created a 'gpsclock' utility so that people in the observatory control
rooms have an easy way to see the current GPS time, and to convert between
GPS, UTC and local time.
General Computing (Wallace)
MIT: (Keith)
-
Installed o/s on laptops
-
Ordered dell desktop
-
Investigating samba for printer services
-
Investigated printer problem from PC (needed new drivers from Adobe)
-
Removed dtspcd from inetd on several older Suns
Livingston:
(Tom)
-
Working with LSU to put the final touches on the installation of our new
router and firewall.
-
Performing maintenance and upgrading on our servers, which had been on
hold over the E7 run.
(Shannon)
-
Installed a web page for us to track IP allocations. The list that
we were using was on paper and had gotten very out of date and inaccurate.
-
Checked all of the PCs around and made sure that I have an accurate accounting
now. I will be reassigning some IPs in the next few weeks to better
allocate the subnet so that we can have a pool reserved for DHCP.
-
Purchased two wireless bridging access points so that we can get a
temporary network connection to the new building.
-
Worked a couple of security issues on the Solaris servers here due to a
new exploit for CDE.
Hanford: (Christine)
-
This is my first week back at work after my carpal tunnel surgery.
I spent the first few days catching up on emails and news. Also spent
several days helping Caltech figure out how much to pay me for my time
away.
-
Installed the latest patches on all GC Sun systems.
-
Installed the latest Norton Antivirus and liveupdate software from Caltech's
site license on all PCs.
-
Put a laptop that had been put on the wireless network back onto an ethernet/modem
card.
-
Moved files around to build a new computer for one of the users.
-
Investigated a problem with a slow network between here and Caltech.
-
Discovered "gamers" using our Anonymous FTP site. This was probably
the cause of the network slow down. Our FTP server was overloaded
with FTP processes downloading large game files that had been put on our
server by the "gamers". I blocked all FTP network access to the FTP
server at the router. This allows users on site to use the FTP for
file transfers, but prevents anyone from off site using it. We will
discuss a solution to this problem, perhaps instead of an Anonymous FTP,
we will setup a guest FTP site which requires a password.
CIT:
(Veronica)
-
LIGO website: posted various updates (Undergraduate Programs for 2002;
Fellowships/Postdoc Openings; Employment listings).
-
Worked with Rita on updating the new LIGO roster. Posted the announcement
about the upcoming LSC meeting and workshop for creating source working
groups.
-
Working on the graphics and scripting for webpages for the Elba conference.
Posted the Elba registration form. Made several minor changes to the LIGO
home page.
-
Project Science website and workshop: posted updates to the website (maps,
graphics, updates to the participants list, general information).
Added a page for the ppt/pdfs of presentations (unpublished until after
actual talks). Have daily meetings with Sydney regarding the final details
of the workshop preparations. Arranged for name badges. General support
(registration etc.) on Friday and Saturday during the workshop. The presentations
webpage will be made public on Saturday as soon as the workshop is over.
-
CaJAGWR: made arrangements for this week's talk (reserved a room, arranged
and set up a projector, set up a video and recorded the talk). Posted
a video and a pdf of the talk by the JPL LISA team (finally, the clearance!)
(Mike)
-
Upgraded several computers at Wilson House with more memory; the majority
of these PC's over there are upgraded to 256MB's of RAM.
-
Replaced a CDROM wasn't reading data.
-
Replaced Virus scan software that had been was corrupted.
-
Worked on VNC software with Larry by enabling a VNC server for clients
to connect to. This seems to work with know problems. When you install
VRVS the VNC software loads also; all you have to do is enable it by
1.Install WinVNC service
2. Run VNCviewer (Connection detail box) will pop-up
VNC server: type in ip address or registered domain name.
Put in password, that's it, you are connected.
To download the VNC software without installing VRVS here is the URL http://www.uk.research.att.com/vnc/
then precede to download.
To setup a server all you have to do is click on the icon that is located
on your tool bar
(WinVNC: Current User Properties) will open; then just put a check
mark in the (Accept Socket Connections)
(Display Number) you can limit the amount of connections or put a check
mark in the (auto) option.
(password:) you must put in a password, make sure you disable remote
keyboard & pointer remote and local.
(UPDATE Handling) I have everything checked, this seems to work for
me; you can play with these settings if you like.
APPLY settings and click OKAY.
Done deal.
-
On the NT servers Compact database and system administration looking into
log errors and updating virus scan software.
-
Backed up Liz Woods old computer with ghost image.
-
Shuffled around several computers, ultra 10's, and monitors within West
Bridge plus moving users from Millikan to West Bridge, with the help of
Larry Wallace.
-
Upgraded the Ghost server from 7.0 to 7.5 this is a big plus because this
version allows me to run a single cast specifying one IP address rather
than before with 7.0 you can only run a multibroadcast which floods the
wireless network, and drives the network switches nuts. I still have to
run a few more tests to make sure things are working
(Lisa)
-
Updated and reconfigured dhcp servers.
-
Rebuilt tiger
-
Rebuilt jabbah
-
Put mu6 and the latest recommended security patch cluster on sirius
-
Set up jabbah for bruce sears
-
Installed pcard for mark barton
-
Worked on php scripts for inventory
-
Put in some of the lesser wireless access points on the 3d floor of bridge
until we can get orinoco's purchased.
(Larry)
-
Actually performed a few interesting (fun) tasks this past week. Cleaned
up a couple of network problems. The big news though is gsparc is now unplugged.
It is the last of the old legacy system.
-
Worked a number of procurement issues. A couple of the maintenance contracts
that were renewed had to be corrected. A few items from last years procurements
are being cleared up.
-
Worked with Mike on the computer move, VNC testing.
-
Upgrading the OS and security patches on a number of the servers. Along
that line I have been testing out the new home server and it should be
ready for production in a couple of weeks when the new network is in place.
-
Worked some of the logistics on the Hanford WAN connection with Richard
M., NoaNet and Energy-Northwest. There will be a telecom the first week
of February for a status report.
-
Reworking the Computer User Policy. Worked on the wrong version over the
Holidays but most of the changes will still be incorporated in the latest
version that Albert had prepared.
LIGO II/Advanced R&D (Sanders)
From: Helena Armandula <ahelena@ligo.caltech.edu>
Silicate Bonding: We performed an experiment to observe the stress
distribution on the bonded surface of a prism (ear) using a polariscope.
We silicate bonded a prism, made from an old Glasgow design, to a flat
polished on a fused silica disk. Welded fibers to the prism and suspended
weights to the fibers. One of the fibers broke while being loaded.
With the other fiber loaded with a few grams, we saw the stress distribution
on the bond. As the weight increased, we observed several stress
points where stress was expected from the design analysis. A few
seconds after reaching 2.5 kg of load, one part of the prism's leg broke
matching the shape of the stress distribution seen at the time. The
experiment will be repeated again to be able to determine if the leg broke
because of stress induced during welding fibers, a flaw on the glass or
a design problem.
>From: Peter Fritschel <pf@ligo.mit.edu>
CSI: Gari B and I visited Crystal Systems on 16 Jan to
review the status of the sapphire development. The most significant development
is that they have produced the first sapphire boule from their 15" diameter
furnace (ie, the boule is 15" diam). Their intent is to develop production
capability of this size, from which the AdLIGO test masses would be made
(their current largest production size is 13.5" diam, a bit too small for
our desired 40kg test masses). They haven't yet done any quality characterization
of this piece, but at least they were able to produce this size without
cracks/fracture in the bulk. They plan on growing 4-5 more 'experimental'
boules of this size over the next ~6 months to tune the process. We agreed
that they should grow these pieces along the a-axis, as our limited data
indicate its homogeneity is better than m-axis material (the first boule
is actually m-axis, but the second one underway is a-axis). There are no
real developments on their end regarding absorption (they are waiting for
samples from Stanford).
>From: Phil Willems <willems@ligo.caltech.edu>
Fused silica fiber research: We have submitted for LSC review
a paper entitled, "Investigations of the Dynamics and Mechanical Dissipation
of a Fused Silica Suspension," summarizing the last two years of such research
at Caltech. The main results we report are:
-
the measurement of the temperature dependence of the Young's modulus of
fused silica to be (dE/dT)/E=1.52e-4/K (previously reported in LIGO-T000188-00),
-
the independent measurement of the dilution factor by the temperature dependence
of the violin frequencies, with results matching theoretical predictions,
-
measurement of Q's for the violin modes of 400-500 million, very high but
not quite up to predicted values,
-
measurement of the Q's of unloaded fibers of up to 11 million,
-
evidence that the thermal expansion coefficient of fused silica fibers
may be less than 4e-7/K.
The coauthors of this paper are Virginio Sannibale, Valery Mitrofanov,
Phil Willems, and Jaap Weel. Jaap is a SURF student who is seeing
his work published, and who just might transfer to Caltech thanks to the
experience.
Based in part on the work in this paper, we are composing a database
of fused silica properties relevant to thermal noise, in an effort to unify
the ranges of values we currently use. This will be a joint effort
of Moscow, Glasgow, Syracuse, and Caltech, and we intend to present our
findings at the 2002 Livingston LSC meeting. All those with data
to share please contact Phil Willems.
>From: ctorrie <ctorrie@ligo.caltech.edu>
Suspensions
No report.
>From: Rich Abbott <abbott@ligo.caltech.edu>
-
The prototype driver boards for the +/- 10A voice coil actuator are being
sent to the board house 01/17. They will be back 01/21 for test.
>From: Janeen Hazel Romie <romie_j@ligo.caltech.edu>
No report.
>From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>
No report.
For additional information about this report, contact sanders@ligo.caltech.edu