|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The LIGO Executive Committee Agenda for Monday December 17, 2001 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
Special Items:
no report
LIGO Operations--Administration
A Site Teleconference was held on Thursday, December 13, 2001. Discussion centered on the status of NSF funding and the establishment of FY 2002 accounts, as well as the status of building at the two sites.
The list of current actions revised to reflect
the status of open actions assigned through December 13, 2001 may be found
at
ACTION
LIST.
From: Ed Chargois <chargois_e@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .
ACCOMPLISHMENTS
ACTIVITY
| 12-06-01 | Packages | Faxes |
| In | 39 | 33 |
| Out | 6 | 44 |
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS PAYABLE HISTORY DATA.
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
From: irena@ligo.caltech.edu (Irena Petrac)
SUPPORT
Progress Period from 12.07 to 12.13
Accomplishments:
We are doing a standard Annual Report for the Construction Project as of the end of November. I have requested contributions from Task Managers by Friday, December 21, 2001.
The following change request has been submitted:
| CR-010012
Revision B |
WBS 1.4.4.1 | Closeout Construction Budgets for Initial Computer Equipment Complement at the Sites (Larry Wallace will argue for spending these funds on network connections) | P. Lindquist |
Press for the latest Contingency Needs Projection.
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
No report.
-------------
Facilities
-------------
For the LHO new building the stem walls and the footers are 80% complete,
rough grading is 100% complete, sewer pressure main is 80% complete.
The
irrigation main added by change order for $3200.00 is 100% complete.
Started on underground plumbing and fire protection.
----------------
LHO General
----------------
(Doug Cook)
Dedicated power sources
are being wired up for the laser safety hardware
panels. These panels will also house the loose components like the
modems
and shutter drivers etc. Next week we should complete a walk-through
and
start to commission the system.
We have a new procedure
and spreadsheet for calibrating the optical
levers for the core optics. We will null the QPDs to the aligned core
optics, adjusting the beam diameters and measuring the beam powers
at the
same time. The MEDM screen will display the angle per unit for the
power
level that it was calibrated for.
We are trying to better
stabilize the 2k laser cooling problems by
improving the heat transfer from the amplifier base. We will attempt
to
clean out the water channels in the amplifier heat sink with gun brushes
to
remove any scaling etc. We have been characterizing the PSL lasers
monthly,
checking visibilities of the PMC, the RC and tuning the alignment,
recording the power levels at various places, changing the oil etc.
and I
have been posting the assessments in the e-log.
CDS Software: Sucessfully ported the PEM Epics to the vacuum processor
in the mechanical room to add a dust monitor to the purge air line (so
we can monitor any infiltration in the lines the next time we vent. These
purge lines are a suspected source of the dust influx we observed during
the last vent). Working on making similar changes
at the end stations. Upgraded all except one of the control room
machines to 1GB memory. (Chethan)
Networking: We are working with LSU on the final stages of configuring our router, which connects to LSU over two T1 lines. The configuration is almost complete, but requires co-ordination with them to implement. (Tom Evans)
GC: The evaluation of CA's Unicenter software did not go well. There are several requirements that my salesman neglected to tell me about. It is somewhat excusable, as he is new to CA, however, My entire experience with Computer Associated has been less than pleasant. I would recommend to anyone in the computing group to look elsewhere before they evaluate CA's software.
LDAS: finished upgrading all of the kernels on the linux machines last week. Beowulf had some problems and had to be redone this week. Restarted LDAS last night due to a ssh problem with beowulf. Showed Jay where the CDS link will attach to the t3's that we have set aside for them. Adjusted the delay time for the Big Brother warning messages. I want to make sure that it works well, and then I will change the notification messages to go to the ldas_admin list. (Shannon Roddy)
CDS Electronics: Completed extensive testing on the Pentek D/A boards. Details of the result are in the e-log.Installed accelerometer cables in the corner station mechanical room for monitoring the blowers. Built the cross connect for the 1X6 digital suspensions. Fixed MC3 oscillation problems. (Rus Wooley)
Interferometer: We replaced the temperature controller for the reference
back with the old one since the new one with higher sensitivity and gain
was oscillating. We made measurements of the coil current noise going to
the test masses for various configurations of the digital signal processing
system that converts mixer error signals to control signals. We see a definite
increase in noise when the digital processing is engaged, but need to study
it further.
We did lock statistics during the day. It seems a single arm can run
well during the day. On Thursday, 12/13/01, after several rain showers,
the ground noise was significantly lower than normal (40 counts/Hz^1/2
vs 200 counts/sqrt Hz at 2 Hz), and the full recombined interferometer
was locking all day long.
Preparation for E7: We are beginning preparations to support the E7 run. The E7 run is still two weeks away, but the holiday will take a lot of that time. We are updating and restructuring the operator shift checklist to reflect recent changes in the controls. An operator schedule for site staffing of E7 has been written, reviewed with site staff, and forwarded to Keith Riles.
A LIGO Holiday Party at the site is planned for the afternoon of Dec. 27, the day before the E7 run, so that our colleagues from out of town can enjoy the festivities.
no report
This week we turned our attention to the North Arm cavity in an
attempt to implement common-mode rejection of laser frequency and
seismic noise. The North cavity's noise is approximately ten
times
higher than that of the South cavity, and it does not exhibit an f^-0.5
spectrum anywhere in our region of interest. Ringdown tests of
the
North Output mirror give its Q at 700,000, somewhat better than the
South Output mirror's, placing the North cavity's expected thermal
noise
well below its observed noise floor. We are in the process of
trying
several strategies for reducing the noise in this cavity.
no report
End to End simulation (Bhawal)
==============================
E2E Physics Meeting
---------------------------
Luca Matone talked about 4K DSC system and the implementation of the
output matrix filters to reduce the coupling between actuation of the
mirror along the beam axis and its pitch.
Mechanical simulation
-------------------------------
(Virginio) Worked mainly on the HAM Stack simulation:
Using the beam object to simulate the coil springs the simulation was
able
to give a good result just for the vertical dof which is really the
easy
one. For the transverse and longitudinal dof it failed.
The reason of this is because the way how the beam is implemented is
not completely right. The coupling between the horizontal dof and the
angular dof is supposed to vanish when the beam is represented with
one
element. patches trying to modifying the beam code did not give a complete
right answer.
Qualitatively the longitudinal transfer function shows the same
shape of the measure transmissibility, but resonances and notches are
quite largely misplaced.
I'm working now to cure the problem by implementing a new object a
generalized spring to cure the problem.
Some objects like beams blades and the elastic line still need a
a quite deep debugging.
Started working seriously on the mse lib to be able to make substantial
modifications.
Lock acquisition in presence of mode mismatch
-----------------------------------------------
(Biplab, Hiro, Matt) Several methods have been tried to acquire lock
in presence
of mode mismatch in Han2k model. Sources of some problems have been
identified and are being looked into.
Code development & maintenance
---------------------------------
(Hiro) spent most of the time working on low level stuff of modeler.
Alfi
----
(Bruce)
- Finishing work on model for updating bookkeeping objects from changes
the user
makes in the GUI.
- Edit window updating nearing completion.
(Melody)
- Continuing on the node settings dialog and disabling menus based
on the view
and selection.
FFT papers by TAMA (nothing to do with e2e)
----------------------------------------------------------
TAMA group has written two draft papers using the FFT software. One
is an analysis of the
effect of the as-built TAMA mirrors, and the other is an estimation
of the thermal effect for
LCGT (future Japanese Cryogenic Interferometer). Both draft papers
were reviewed by
relevant LIGO scientists, mainly to make sure that the contributions
by LIGO is properly
quoted and acknowledged. Brett Bochner and Yaron Hefetz will be included
in the author
list of the first paper.
LIGO Data Analysis System
=======================
Software System (Blackburn)
=======================
The week has been spent testing LDAS and fixing bugs in preparation
for
the alpha release of the version of LDAS to be used in the E7 engineering
run. So far about 15 bugs have been identified and fixed. Almost all
bugs
have been in code that required us to restart from the beginning all
of
the test suites. There is still a very big bug in the mpiAPI which
is a
source of concern. This causes jobs to timeout and jobids to be confused
when the frequency of dataPipeline searches is high. It looks like
we
will need a couple of extra days to finalize the release. This has
been
passed on to the LAL/LALwrapper development groups. They will begin
working
with our pre-release images of LDAS starting tonight so as to not hold
up
there plans for testing search codes with this release of LDAS.
An additional discovery made this week was that the custom memory manage-
meant tool (dlmalloc) that is being distributed and built with LDAS
was not
properly configured for inclusion in the running LDAS system. What
was
happening was that the LDAS systems were picking up the memory management
tools associated with the operating system. The first attempt to correct
this problem identified bugs in the dlmalloc software. We have begun
the
investigation of newer releases of dlmalloc and will be testing these
with
the hopes of having a working dlmalloc for the next release of LDAS.
The implementation of the resampling functionality in the frameAPI proved
to be too unstable to support in this release of LDAS. It will be in
the
distribution released for E7 but no documentation to enable it will
be
made public. If we identify specialized needs for this functionality
in
the E7, then experts can be brought in to use it in controlled environments,
otherwise, users will be able to use the full resampling functionality
found in the dataConditionAPI.
We have had a very active will of meetings with the LSC as plans are
being developed for running search codes on line at the sites during
E7.
There are still a lot of questions but actions are being generated
to see
to it that we are ready to carry out searches online during the E7
run.
The modifications to the metadataAPI to allow fully threaded requests
to
the database were completed and tested this week. This will improve
our
ability to respond to database requests during the engineering run.
The database table designs were updated for all LIGO LDAS systems this
week to incorporate the requested changes to the periodic search table
design as recommended by that search's upper limits group.
LDAS System Administration (Anderson)
=====================================
Caltech
-------
(Dan Kozak)
Continued to migrate data from (mostly) 3590 tapes to 9940 tapes.
Did
some work with Redwoods (i.e. lots of LIGO and Pulsar data) as well,
but the larger size of the Redwood tapes makes them not not work as
smoothly (because it takes longer to stage them to disk, the first
files on the tape often get purged before the whole tape has been
staged to disk;this causes the change class of service thread to grind
to a crawl). Am reworking the scripts to get around this problem.
It's still possible to run Encina out of memory (from queuing up too
many change class of service requests), but less likely that it was
before.
All the LIGO-purchased 9940 tape cartridges have been labeled and put
in the silo. Importing them into HPSS continues.
Assisted with install of Sunfire 880 and associated equipment in Powell
Booth.
(Al Wilson)
Completed and did some minor tweeks at some site on the Linux kernel
upgrade. All sites are now running 2.4.9-12. Will complete the week
with a
practice rpm build. The machine tester (gwave-75) is now going to be
the
ldas systems test machine.
(Stuart Anderson)
Worked with Sun to diagnose and replace some bad memory in one of the
new
SF880 servers which is now working well.
Coordinating the effort to get the LDAS disk storage reorganized for
the
E7 data run.
Reconfigured the LDAS admin machines to support a unified location for
system administration scripts.
Ordered and installed a Sun 18.1" LCD monitor in the ldas-test system.
Installed 2 5000VA UPS units
Finished ingesting the E6 raw frames, still working on the trend frames.
MIT
---
(Keith Bayer)
updated all linux node kernels to 2.4.9-12
Livingston
----------
(Shannon Roddy)
finished upgrading all of the kernels on the linux machines last
week. Beowulf had some problems and had to be redone this week.
Restarted LDAS last night due to a ssh problem with beowulf.
Showed Jay
where the CDS link will attach to the t3's that we have set aside for
them. Adjusted the delay time for the Big Brother warning messages.
I
want to make sure that it works well, and then I will change the
notification messages to go to the ldas_admin list.
(Igor Yakushin)
* Visiting LHO;
* Read The Solstice DiskSuite Users Guide and The Solstice DiskSuite
Reference Guide to understand what metadevices are and how to configure
them;
* Installed, together with Greg, Solaris 8 on the new Sun Fire
machine and configured mirror metadevice;
* Learnt about tape control tools and scripts;
* Learnt about controlMonitor tool.
Hanford
-------
(Greg Mendell)
1) AIT 2 tapes have been received for the E7 run.
2) The operating system on all LDAS linux computers were upgraded to
the
2.4.9-12 or 2.4.9-12smp Redhat Linux 7.1 kernel.
3) Igor Yakushin, the new LDAS staff scientist at LLO, visited LHO this
week. I worked with Igor on LDAS issues.
4) Installed Solaris on the new Sun Fire 880 server, with Igor.
Igor
then set up a mirror of the root file system.
5) Contacted Sun about missing items in the Sun Fire 880 order.
Sun is
tracking down these items.
6) Updated script to synchronize times between T3s and ldas admin box.
7) Preparations to archive the E7 data are under way. The LDAS T3 file
systems and tapecontrol script will be upgraded and reconfigured. We
should be testing the system by the middle of next week.
General Computing (Wallace)
========================
MIT:
(Keith)
-Investigated vnc and cygwin/xfree86 as windows X server apps
cygwin/xfree86 appears to be easier to use / install
-Investigating networking over to NW22
spec-ing out fiber converters / switches
-Updated software on lancelot for J.Z.
-Added users to PortMaster modem server
Livingston:
(Shannon)
-The evaluation of CA's Unicenter software did not go well. There
are several requirements that my salesman neglected to tell me about.
It is somewhat excusable, as he is new to CA, however, My entire
experience with Computer Associated has been less than pleasant.
I
would recommend to anyone in the computing group to look elsewhere
before they evaluate CA's software.
Hanford:
(Christine)
- Completed comments to Albert's Security document.
- Continued trying to get the new tape robot and new backup software
talking to each other.
- Continued installing memory in Ultra 10s.
- Started writing "How To" and "Where is it?" documentation for Lisa
and
others to use while I am on medical leave.
CIT:
(Mike)
-Performed ghost backups of multiple user computers, for restore purposes
in
case of hardware or software failures.
-Printer problems on the 6th floor of Millikan
HP4500N color, fuser needed replacement.
Irene's printer just needs to be replaced.
-Loading software on a laptop to put back into loaner pool.
-Issued a New Dell Laptop to Virginio S..
-Loaded all engineering and general computing software on to a Dell
for
engineering support.
(Veronica)
- Updated various parts of the LIGO website.
- Posted updates to the Project Science website.
- 2002 GWADW Conference: working with the Organizing Committee on the
contents and structure of the conference website. Tested various
graphics/layouts. Have set up a registration submit-form; linked it
to a
database to write to; configured the (new) Amaldi server to host the
new
website. Waiting for a written permission to use proprietary images
on the
website. I've prepared 2 layouts, with and without the images; depending
on whether (and when) this permission is granted, I'll use either one.
- CaJAGWR: The seminars schedule for the Spring '02 term is shaping
up.
Will record the Dec 14th seminar; this is a JPL talk, so I will need
to
wait for clearance before posting it on the CaJAGWR website. The previous
talk by a JPL LISA team is still in the process of getting the clearance;
will post it as soon as this is complete.
(Lisa)
- Fixed the daily backups for the NTs
- Looked into whether our backup software will support win2k.
It does.
Currently working with sun to get a support contract for it.
- Restored Albert's crontab on canopus.
- Installed pcard updates for various users.
- Pushed out a new access table to the wireless APs.
- Resolved some .cshrc problems for Hongyu.
- Installed and compiled sendmail 8.12.1 on becrux. Currently
working on
creating a cf file.
- Updated the DNS tables.
- Installed hp web jetadmin on kuma.
(Larry)
-Worked on a video conference setup with the NSF. Presently, their
ISDN system
works better than the IP (H.323) system which we use. We are testing
out
different s/w products that are H.323 compliant to see if performance
can be
improved.
We have tested a number of small web cams and have found one that has
acceptable
quality. We will have a few more people test it out before we distribute
it out
to those that travel extensively.
-Resolved a couple of procurement issues. This has become a standard
item the
past few months. The latest vendor to have a problem blamed it on their
transition to Oracle.
-Setting up another web server for internal use.
-Reviewing documentation covering policy and security.
-Installed new OS on a couple of SUN boxes. Spent a little time working
on the
new SUNFire box that will be the new sargas (sand box) unit. All of
the internal
hardware has been installed and now working on the disk system. It
looks like a
pretty good box.
-Working with the group to get a few more tools in place to handle
viruses and
other security related issues. Along with e-mail configuration changes.
From: Helena Armandula <ahelena@ligo.caltech.edu>
Coating effect on mechanical "Q"
Received 4 substrates from Wave Precision; they need to have their "Q" measured for before coating.
Sent 4 substrates coated by 4 different vendors to have the film structure
analyzed by Scanning Electron Microscope. The instrument has also
x-ray capabilities that can give some information on surface composition.
The work will take place next Friday.
Ergonomic arm
We had a preliminary meeting with the possible manufacturer of the
ergonomic arm to be used to handle Advanced LIGO Optics.
A teleconference is scheduled for next Monday to finalize the specs
and the different applications for this tool.
From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>
@ Pasadena
Charlotte
Measuring more thermal conduction of existing glassy metal and maraging
samples.
Finally converged on old problem of ribbon effective flex joint.
Charlotte, Riccardo, Gianni
Designed reed Q-factor measuring setup, now in production
Creep measurement ongoing.
Jan
Preparing to melt this week the first four samples of MoRoB, they will
go to Carnegie Mellon for spin cast into ribbons before Christmas
Hareem
LVDT paper submitted to NIM.
@ Pisa
Alessandro, (Riccardo), Francesco
Ultra Sound Milling Machine in construction by Faimond .
Alessandro, Franco Frasconi, Gianni
Refurbishing the Virgo stress strain machine for ribbon measurements
.
Alessandro
Continuing tests on thinning of glassy metal ribbons by
electro-polishing with alternative solutions. Getting ready for
differential etching of shaped flex joint using photoresist provided
by
Rita Torres and with conventional photoresist photoresist and
alternative etching solutions. Testing different brazing techniques.
Alessandro, Riccardo, Gianni
Almost engineered flex joint structure for mirror hook-up.
@ Hongo
Akiteru, Ida
First lock TAMA-SAS Michelson interferometer.
Only one mirror is
suspended and seismic isolated while the Beam Splitter and second end
mirror are on shaky ground. The DSP controlled hierarchical mirror
controls system in SAS, designed for low frequency operation, has hard
time providing enough bandwidth to lock the suspended mirror to the
moving target of the grounded mirror. The 100 Hz bandwidth is
barely
sufficient while in Virgo, locking between suspended mirrors is
done
with 30 Hz bandwitdh and a very large safety margin. Life
will be
different when operating the Fabry Perot between two SAS towers in
the
full 3 meter experiment.
Nishi, Riccardo
Commissioning the second SAS tower for FP tests with both suspended
mirrors.
Kenji, Riccardo
Discussing quartz mirror improvement prospects.
Kimio, Akiteru, several others and Riccardo,
Discussing technical problems for implementation in TAMA 300.
For additional information about this report, contact sanders@ligo.caltech.edu