Weekly Report for Week Ending December 6, 2001


 Exec. Comm. Agenda
Highlights
LSC
Administration
Hanford Observatory
Livingston Observatory
MIT
Caltech
Detector
40 Meter
TNI
LASTI
Data Analysis
LIGO II/Adv. R&D
Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  December 10, 2001 will be:

 (Meeting time: 10:30 am Pacific Time)

Open meeting 10:30 - 11:30

  1. Announcements
  2. LSC Issues (Weiss)
  3. Comments on Weekly Report
  4. WBS 1 LIGO I Construction (Lindquist)
  5. WBS 2 LIGO Lab Operations
  6. WBS 3 and 4  Advanced R&D and LIGO II (Sanders)
Executive Committee only 11:30 - noon   Topics:
 

Special Items:


Special Announcements:


Weekly Report Highlights
 


LSC Issues (Weiss)


no report


LIGO I Construction/LIGO Laboratory Administration (Lindquist)



 

LIGO Operations--Administration



LIGO Weekly Site Telecon (Lindquist)

A Site Teleconference was held on Thursday, December 6, 2001.  The following items were discussed:

The list of current actions revised to reflect the status of open actions assigned through December 6, 2001 may be found at ACTION LIST.

PROPERTY MANAGEMENT (Chargois)

From: Ed Chargois <chargois_e@ligo.caltech.edu>


DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner - turner@ligo.caltech.edu>

Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .

ACCOMPLISHMENTS

>From: Cleveland Mak <mak_c@ligo.caltech.edu>

ACTIVITY


COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman, Akutagawa)

From: Esther Cunningham <esther@ligo.caltech.edu>

Press here for ACCOUNTS PAYABLE HISTORY DATA.

From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

From: Florence Kaufman <fkaufman@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: irena@ligo.caltech.edu (Irena Petrac)

From: Ed Jasnow <jasnow@ligo.caltech.edu>

SUPPORT

 
Irene Baldon Dorothy Lloyd Rita Torres

Advanced LIGO (Frey)

From: Thomas Frey <tfrey@ligo.caltech.edu>

Progress Period from 11.30 to 12.6

Accomplishments:

Schedule 12.07 to 12.13:

Reports (Lindquist)

We are doing a standard Annual Report for the Construction Project as of the end of November.  I have requested contributions from Task Mamagers by Friday, December 21, 2001.



Change Control/Contingency (Lindquist)

The following change request has been submitted:
 

CR-010012
Revision B
WBS 1.4.4.1 Closeout Construction Budgets for Initial Computer Equipment Complement at the Sites (Larry Wallace will argue for spending these funds on network connections) P. Lindquist

Press for the latest Contingency Needs Projection.


Human Resources (Akutagawa)

From: Cindy Akutagawa <cindy@ligo.caltech.edu>


Quality/Safety (Tyler)

>From: Bill Tyler <tyler@ligo.caltech.edu>

Distributed list (draft) of the Hanford Safety audit actions items/recommendations for discussion at weekly site telecon.  The draft list was accepted as distributed. The final audit summary report is in work and will include the AI/recommendation list.

Requested cost estimates from the Caltech Engineering and Estimating (E&E) group for the LDAS proposed modifications of room 215, Synchrotron.  Cost estimates have already been obtained from other vendors for the same room modifications.  It is planned to review all of the cost estimates with Caltech E&E next week to select a recommended design approach and cost.
 


LIGO Hanford Observatory (LHO) Operations (Raab)



 
 


LIGO Livingston Observatory (LLO) Operations (Coles)


Interferometer: The common mode servo was installed and is ready for check out (Kovalik). We have been having problems with the thermal stabilization of the PSL reference cavity with the new high gain temperature measurement board - the system oscillates unacceptably when it is implemented. Rich Abbott and Flavio have been here this week working on it and have  proposed fix which we will test as soon as there is a point in the commissioning where we can do this with minimum disruption. The intensity stabilization servo is installed. We are making measurements of the noise at the coil monitors of the ITMs and ETMs to assess the electronic noise in the LSC. See the ilog for details.

GC: Installed office 2000 on the machine in Bonnie's office. Investigated some leftovers of the Nimda worm. Worked on price quotes for various needed equipment in the new building here. Gave Ed Daw access to one of my "testing" computers here so that he can try and build LDAS on a RH 7.1 system without affecting the machine that he uses on a daily basis. Contacted hummingbird software to ask some questions about our license/maintenance renewal. Thinking about the advantages/disadvantages of using cygwin to replace hummingbird. It would be free to use (GPL'd) rather than paying ~$1100 annually for license renewals.

LDAS: Finished troubleshooting the backup script on LDAS. The problem was with the permissions on one of the ssh files. The backup script now works as it is supposed to.Once I edit the configuration, backups can be added to the cron on admin.
Shannon Roddy

Safety Issues: Optics and Installation: Programming of the Laser Safety Interlock system is (still) ongoing. Hopefully we'll be issuing cards soon to begin system testing using LLO staff. Gerry and I are preparing the LLO Personal Accountability SOP for the Laser Safety Interlock System, as well as a Safety tutorial for the Machine Shop.  Jonathan Kern

Other: Igor Yakushin is at Caltech this week to learn more about the LDAS system.


Detector/Technical Support (Whitcomb, Coyne)


 
Commissioning:

Hanford
Livingston

Science & Engineering Support
Details are available in the daily electronic logs for the installation and commissioning activities:

Hanford Detector Log

Livingston Detector Log

LHO COMMISSIONING

High winds (sustained gusts of 80 mph) for much of Saturday made the interferometers unusable and caused brief power outages which rebooted the detector systems. Recovery for the 2k interferometer was quick, still has problems apparently associated with the power interruption.

2km Commissioning

Dennis Coyne reporting:
Efforts on getting robust power recycled lock by have been plagued by apparent alignment drifts. Significant time has been spent going through re-alignment procedures and re-establishing lock acquisition parameters in the hope of increasing the side band power (SPOB) and arm cavity power (PTRT & PTRR), generally without much success. Emphasis has intentionally shifted away from attempts at full interferometer locking to study the behavior in single arm cavity lock and to get the wavefront sensors working since they should improve lock stability.

The PSL laser head was found to be running warm, despite low temperature cooling water on the return path, as though efficiency in the heat exchanger has dropped. The chiller was temporarily set close to the PSL (adjacent to the racks, which will cause some vibrational noise). The flow rate increased slightly (~10%) but the head is now at its nominal temperature set point. Means to chemically or mechanically scour the flow path in the heat exchanger are being looked into. The intent is to do this work in situ. The 2k PSL continues to experience intensity noise bursts at low frequency. The frequency of this non-stationary noise seemed to have subsided when the chiller was set close to the head, and a more nominal head temperature established. The intensity stabilization servo (ISS) was working reasonably well and similarly to the 4k PSL, with the exception that the frequent low frequency intensity noise bursts cause the ISS to ‘hit its head’.We may be faced with a decision to switch to the spare 10W laser prior to the E7 run. Of course we have no history with the spare, so there is some risk in switching.

A dominant factor in the frequency noise was found to be coil driver noise in the mode cleaner; The noise level is 150 nV/rHz, 300 nV/rHz and 1000 nV/rHz for the three mode cleaner suspensions. The cause is under investigation (it may be the pending CMOS switch terminations). Engaging the 35 Hz ASC filters was found not to help at all (decreased the noise by < 2x at 20 Hz but increases noise 3-4 x from 500 – 2000 Hz) and to cause a significant yaw shift in MC3. The oscillation (350kHz) in an elliptical filter stage of the ITMy suspension controller was fixed. A determination as to whether this fix should be applied to the other controllers is pending.

4-k Commissioning

Given the problems to date in getting the 4km IFO fully locked, the instability (of the alignment and lock acquisition calibrations) and the short time remaining till the E7 run, we have decided to setup the LHO 4km IFO in a recombined configuration for the E7 run. Since the IFO reflected signal level is low for the recombined configuration (double pass through the RM), we removed the attenuator in front of the IFO reflection port RFPD and setup the EO shutter trigger to protect against the RM being inadvertently set back into alignment. We started to measure the lock acquisition gains for the recombined configuration and briefly attempted to lock the x-arm with the REF_I signal while adjusting the whitening gain. Locks were brief (~1 sec) and rare in the ~10 minutes of trying.

At this point we realized that the extremely clipped beam at the anti-symmetric port should be fixed before proceeding with further lock acquisition parameter measurements. The clipping was first noticed Sunday after the MC was again locked after the power outage. We have established that the clipping occurs on the faraday isolator aperture in the input optics section. The only reasonable explanation is that the MC axis has shifted as a result of the power outage. Trends of coil monitor and OSEM signals for the MC suspensions did not reveal definitive pre- to post power outage shifts larger than the shifts observed when the MC alignment was good. Attempts to shift the MC axis, and follow it with the input beam, to walk back into the center of the input faraday isolator have yet to be successful.

LLO COMMISSIONING

Rai Weiss reporting

We made the decision to stop work on recycling the interferometer

until after the E7 run. The effort is now concentrating on

reducing the noise and improving the duty cycle of the recombined

Fabry-Perot/Michelson interferometer.

The system can now be locked when the seismic noise velocity at

the LVEA, and two endstations is below 0.7 microns/sec/sqrt(Hz).

These conditions apply between 5 PM to 6:30AM on most days(except

for one hour and a half during the trains) and on Saturday and

Sunday all day. Without further improvement the duty cycle of the

instrument can be about 0.62. We are still studying why the

interferometer breaks lock. The analysis of the lock break

transients is pointing to noise build up and instability in the

Michelson interferometer control loop. The loop is very sensitive to

the RF phase of the discriminant signal since the common mode arm signal

is in quadrature to the differential Michelson arm signal. Last night

it was discovered that a glint off the recycling mirror could be a problem.

There is also a good chance that reducing the common mode excursions of

the interferometer with the common mode servo will improve the

interferometer stability. An additional strategy to improve the duty

cycle is to use the pick off signals from the x and y arms to attain a

discriminant dependent only on the resonance of the arm cavities. These

signals will offer useful diagnostics and may also be effective in an

alternative locking strategy.

Significant progress has been made in understanding and reducing the noise

in the interferometer. The noise has been reduced by about a factor of 10

between 100 to 1000Hz. The latest noise spectrum shows a minimum strain

spectral density of 2 x 10^-19/sqrt(Hz) between 500 to 2000 Hz.

[Aside: This is equal to the beststrain performance of the 40m experiment. D.Coyne]

The principal noise sources are:

* excess A/D conversion noise in the length control loop - reduced by

  increasing the signals before the conversion.

* excess frequency noise due to intensity fluctuations producing radiation

  pressure fluctuations on the mode cleaner mirrors - reduced by

  incorporating an amplitude stabilization servo holding fractional intensity

  fluctuations to 10^-7/sqrt(Hz) between 100 to 1000 Hz.

* excess frequency noise due to current noise from the OSEM and filter circuits

  in the mode cleaner mass controller coils - in the process of being changed.

* excess noise in the D/A conversion in the length control servo - thinking about

  how to address this noise.

SCIENCE & ENGINEERING SUPPORT

Additional information:

CDS Hardware Problem Resolution web page

CDS Problem Reporting & Tracking System (Gnats)

Digital Suspension Upgrade (LHO 2K & LLO 4K)

Jay Heefner

We are in the process of shipping all required modules to LHO and LLO. They should arrive next week. The upgrades of the LHO 2K and LLO 4K are scheduled for after the E7 run.

Advanced LIGO DAC

Jay Heefner

A draft spec is out for review. Following the review we plan to issue an RFI to vendors. It should be out in the next two weeks.

LSC/ASC/Digital SUS

Jay Heefner

A final schematic for the 2 omega I&Q demod board is out for review. Layout should start next week.

Final discussions for the new SOS output chain should be complete this week. After this a new coil driver, pole/zero module and Bias/fast input module will be designed and built for the mode cleaner mirrors.

LOS Digital Suspension Control (DSC) Software Upgrades

Rolf Bork

Working on requested upgrades to LOS digital suspensions. Dewhite and Run/Acquire filters and switching are complete. I still need to add filter bank for LSC and ASC at input of digital suspensions. Expect to complete by 12/6.

Digital Suspension Controllers (DSC)

Ben Abbott, Luca Matone

The beginning of the week consisted in getting ourselves familiar with the LHO 4k DSC system, focusing in particular on ITMY. The objective is to commission the imminent changes to the DSC front-end code:changes to the architecture, changes of filters and gain and the implementation of the output matrix filters (the requested changes are described in T01040-01-D by P.Fritschel).

So far, we have measured:

        o the effective Q for ITMY to be ~10 (local damping on);

        o the filtering between the Anti-Aliasing and the

          Anti-Imaging boards and individually verified

                - the Anti-Aliasing filter response;

                - all the digital filters (3:0.0, 40:1, 30HzE, White,

                  the AC coupling z @ DC and p @ 3 Hz

By doing so, we verified the architecture of the system and became comfortable in its functionality.

With the existing front-end code, we succeeded in loading the new output matrix filters: the objective of these filters is to minimize the coupling of force-to-pitch and torque-to-position. We measured the couplings with and without the filters enabled and so far have not observed a conclusive improvement. However, the filter coefficients will have to be modified because the filters themselves introduce a substantial peak at ~740mHz, regardless of the mirror drive frequency (even when we stop driving the mass, the 740mHz excitation, arising from the filter, continues for ~15 min before it dies).

This forced us to step back and study the coupling between position and pitch/yaw. One way to quantify this frequency dependent coupling is to drive the LSC position input and measure the optical lever pitch and yaw. We are presently measuring this TF in order to estimate what these filters 'should' look like. Once the picture is clear, we will revisit the filter design.

Multi-processor version of EDCU

Hongyu Ding, Lori Robison and Rolf Bork

Working on a multi-processor version of EDCU. Will undergo testing/debug, after the DSC changes.

LSC RF Photodiodes

Mike Zucker

Still wrestling with two vexing problems. Apparent "quenching" behavior of detector s/n 22 has still not been reproduced on the bench, even for extreme overloads. Trying to replicate conditions found at the site more and more closely to see if there is some unexpected interaction. Next step is to rig the excitation to give an admixture of omega and 2omega in the applied photocurrent.

This was set aside temporarily to look into a second problem, poor signal-to-noise in a recent batch of detector modules. The cause seems to be excess loss in some RF component near the photodiode, but a painstaking witch-hunt (desoldering and characterizing each component one by one) has failed to yield a culprit. For reference, the effective transimpedance on these units measures only 2 kOhm, whereas we expect 4 kOhm (our pass/fail spec is 2.5 kOhm or greater).

RFI/EMI/ground loops

Mike Zucker

[Note: Mike Zucker has been requested to lead an effort to review RFI, EMI/EMC and grounding practices/design at the observatories.]

Szabi Marka has generously offered to help me and Jay Heefner measure and assess electronic interference problems in situ at the sites.

EO Shutter Controller

Sander Liu

In the process of refurbishing the two units returned from the field for repair and rework

Rolf Bork

PSL Frequency Stabilization Servo (FSS)

Mike Zucker

[Note: Mike Zucker, as part of the LASTI PSL effort, has generously offered to coordinate frequency stabilization servo investigations/improvements at the 4 PSL locations. D. Coyne]

Collected information on field mods and dynamic range measurements from various FSS installations (LLO, LHO, CIT). Began developing a collective idea where we want to go with this; started assembling materials to test the concept on the LASTI FSS.

PSL ISS @ LLO

Flavio Nocero, Rich Abbott
While at LLO we installed and tested the (inner loop) intensity stabilization servo (ISS). We dressed in all the cables and wired it to the PSL rack power. Only one odd thing happened in that there is no on/off switch to the board so we have to plug it in hot. When we plug the module in, it has to be done quickly or else one supply comes up faster than the other and the board will go into a latchup with the combination of 15 volt and 5 volt chips on board. Once we figured this out, there are no apparent snags. We added (with Joe Kovalik's help) a half wave plate and beam splitter cube to allow the light level to be adjusted to the DCPD (a modified PDA55).

PSL ISS @ LHO

Rick Karwoski, Paul Russell (reported by Dennis Coyne)
While at LHO Rick & Paul installed and tested the (inner loop) intensity stabilization servo (ISS). on the 4k PSL and swapped out the previous version of the ISS. On the 2k PSL. (The new version is functionally the same but has offset adjust capability and a few other minor changes, and like the original is packaged in a separate box, not a VME module.) Much effort was expended in tracking down noise issues associated with powering the ISS from a rack supply, inadvertent grounding of the PSL table, etc. As of Thursday good performance was being achieved on both the 2k and 4k systems with power supplied from a dedicated unit (not from the rack) and no connections to the DAQ system. However, the 2k PSL still has non-stationary, low frequency intensity noise bursts which cause the ISS to hit its head with ~1mW of power on the modified PDA55. (unlike the LLO installation, the power level is fixed.). No out of the loop measurements have been made as yet; A spectrum with the “ in the loop” is in the elog.

PSL Reference Cavity Temperature Control @ LLO

Rich Abbott, Flavio Nocero

We are preparing to study the PID controller to understand the settings. We have a spare controller that we are going to use offline to get a better feel for its transfer function and not crush the day to day operations.

Peter King

With the arrival of the voltage reference, a temperature sensor interface module has been completed.I have been trying to recall how we derived the EGUL and EGUF fields for the Minco process controller and I suspect I made a factor of 2 mistake in the fields but am not certain. Hope to clarify this with Rich soon.

Reworked PMC

Peter King

The re-worked PMC mirrors from REO arrived. A quick look at their spectrophotometer data suggested that another coating mistake was made but that was not the case, as the data provided was for a normal incidence scan, not 45 degrees.I checked this with Bill Grant, who re-assured me that the parts were within specification.

Optics Metrology

GariLynn Billingsley

All transmission, absorption and phase map data for the WA4K are now available by clicking the "Data" link under the "LIGO Data" column from the COC optic index page. Access the index page at:

http://www.ligo.caltech.edu/~gari/COCAsBuilt.htm

You can also get to this page by following the link from the LIGO home page through the Research Bulletin Board, Core Optics Components, Optic Index

Optical modeling

Erika D’Ambrosio

I finalized the preliminary studies on the sidebands imbalance by creating some plots in order to compare the values obtained by simulations with the predictions based on a very simple model 2X2 that William Kells and I have been working on lately. The agreement is very good for a difference between the radii of curvature of the ITM mirrors up to 1000m. and the perturbations are supposed to be asymmetrical. This results in a rapid decrease of the carrier power going through the bright port and this is also mathematically evaluated.

DMT

John Zweizig

This week I ran the Livingston PEM "Deep-Mine". This involved running monitors configured to detect glitches with low thresholds off line on E5 data. The results will be examined by members of the LSC Burst analysis group to quantify transient noise, to determine better settings for the Monitors for E7 and to determine which environmental noise is likely to appear as busts in the interferometer data.

I also wrote a program that might be useful for scanning the triggers generated for the deep mine. This displays the raw data around the trigger time for a list of triggers selected by guild.

Burst Summit

Szabi Marka

I worked on external triggers and prepared for the Burst Summit coming this weekend. The External Triggers working group (Burst) had a fruitful meeting this week. We discussed the GRB-GW analysis plans for E7. (Soumya Mohanty, Soma Mukherjee of GEO and Rauha Rahkola, SzabiMarka of LIGO)

I spent time with E6 - PDM related analysis.

CAD conversion

Janeen Romie

Working on LIGO I documentation (before the anticipated IDEAS licensing and

upgrade issues on January 1st.)

[Note: In intial LIGO we used both IDEAS and AutoCad (including a little Mechanical Desktop). In LIGO operations and advanced LIGO we are transitioning to AutoCad/Mechanical Desktop and SolidWorks. However we have some legacy IDEAS CAD that we will need to convert or maintain for a while. D. Coyne]


40 Meter Interferometer (Weinstein)




Thermal Noise Interferometer (Libbrecht)


>Since our last report, we have made considerable progress in both lock
>acquisition and data analysis.
>For lock acquisition, we had been using a servo that took around two
>hours to catch but was quite stable thereafter.  We had successfully
>increased the bandwidth of the servo, reducing the average acquisition
>time to around nine seconds, but we had also encountered some rather
>serious, unexpected unity-gain frequency oscillations.  Up to that time
>we had been modelling our servos almost entirely algebraically, using
>pen-and-paper calculations to predict unity-gain frequencies and phase
>margins.  These models were very quick to develop and use, and they had
>nearly always accurately predicted the behavior of the system.  Now,
>however, we had begun to push the unity-gain frequency up into the
>region where our passive notch filter begins to eat phase, and we needed
>a more precise, quantitative model to understand the system.
>
>Last week we began to develop a computer model that describes both the
>behavior of the servo and the calibration of the instrument.  As soon as
>the model was ready, we tested it by locking the system in an old
>configuration (with a two-hour lock acquisition time but no
>oscillations), measuring the open-loop transfer function, and comparing
>the measurement with the prediction of the model.  The agreement between
>the two is quite good, and the improved resolution of our model in
>phase-margin allowed us to understand two previous puzzles:  "Why
>couldn't we simply push the gain of the old servo up to increase its
>bandwidth?", and "What causes the apparent unity-gain frequency
>oscillations in our wideband servo?"  The answer to both questions is,
>"The passive notch filter eats more phase than our pen-and-paper model
>predicted."  Once we understood this, we were quickly able to modify our
>new servo to eliminate the unity-gain frequency oscillations, preserving
>the ~10 second lock aquisition time.  This is a major breakthrough.
>However, we have now begun to excite some higher-frequency internal
>modes.  Our first active notch filter, built by Flavio Nocera, performs
>admirably, neatly removing the first modes at 27.5kHz.  It is apparent
>that we need some more of these filters to remove additional resonances
>at 30.7kHz and possible around 40kHz.
>
>Another thing our new model allows us to do is to quantitatively
>calibrate the instrument accross a wide range of frequencies.  (We had
>previously been limited to approximately 900Hz to 5kHz.)  This week, we
>took data from 10Hz to 100kHz and, using the calibration obtained with
>our new computer model, converted it to displacement sensitivity.  The
>resulting curve agrees well with our previous data in the 900Hz to 5kHz
>range, and it allows us to see where the seismic wall appears at low
>frequencies and where electronic noise limits us at high frequencies.
>
>This displacement noise curve shows some interesting features.  First,
>it appears to scale approximately as f^-0.5 in the decade of 300Hz to
>3kHz, just as we expect internal thermal noise to do.  Second, it is no
>more than a factor of three above where we expect to see thermal noise,
>based on the Q of one of the mirrors as measured by the ringdown time of
>its lowest-frequency internal mode (f0=27.5kHz).  The attached plot
>shows the displacement noise in the South Arm cavity of the TNI, along
>with two estimates of the mirror internal thermal noise.  The red curve
>is the expected thermal noise in the South Output mirror, based on its
>measured Q of 100,000.  This should be considered a lower bound.  The
>green curve is the thermal noise that would be produced by two identical
>mirrors with Q's of 21,000 each, or a single mirror with a Q of 15,000.
>This should be considered an upper bound on the thermal noise in this
>cavity.  These estimates of the thermal noise are based solely on
>internal Q's and do not take into account coating losses.
>
>It's too early to say with certainty that we have observed thermal
>noise, but it does look like we are at least close.


LASTI (Zucker)


LASTI (Bayer, Fritschel, Goda, Harry, Laliberty, MacInnis, Mason,
Miller, Mittleman, Ottaway, Phinney, Rollins, Shoemaker, Zucker)
=======================================================================
HAM13 SOS INSTALLATION:  Dave O., Myron, Fred and Jamie got both SOS
optics for the short test cavity installed in HAM13.  Their OSEMS,
wiring and feedthrough connections are installed and checked.  The
stack optics table was counterweighted and rebalanced. One door has
been replaced on the HAM and coarse alignment is proceeding well, using
a visible diode laser pilot beam.
 

HYDRAULIC ACTUATORS:  Ken continues detailing the actuator structural
interface design and would like to hold a design review in the next few
weeks.  Joshua moved the prototype pump/accumulator skid setup out of
the machine shop into the student lab to improve cleanliness, and is
continuing experiments to understand its dynamics.
 

CDS/DAQ/GDS: No significant problems to report.
 

PSL:  This week and last we've been fortunate to have had the expert
support of Lee Cardenas from Caltech, working with Dave O., Myron and
Jamie.  The 10W Lightwave Laser has been installed and tested; its
output power has only marginally degraded during shipping (still above
spec, though). The reference cavity has been installed and its vacuum
chamber pumped down.  MZ and Jamie have ordered components and test
equipment to support commissioning and upgrade of the frequency
stabilization controls, and are collecting a rich dossier on regional
and historical variants.
 

        #MZ Reminder for Visitors: the LASTI high bay is a DUAL-
        WAVELENGTH laser hazard zone when warning signs are
        illuminated.  Contact Mike ( zucker_m@ligo.mit.edu ) to be sure
        your personal eyewear is suitable if you're planning a visit;
        if it isn't, we can help you out.  We run a 10 W Nd:YAG MOPA
        at 1064 nm and a 15 W CO2 laser at 10.6 microns, often
        simultaneously.


Data Analysis and Computing (Lazzarini)


Simulation and Modeling (Bhawal)
E2E Physics Meeting
---------------------------
Hiro talked about a number of new features added to e2e. For example, a hard switch, a  rotational
operator, bundle for data set, direct macro settings and macro handling etc.

Han2k seismic model
-------------------
(Hiro) At LHO, Hiro worked with Bill to use Bill's seismic motion model in Han2k
by writing a module to rotate coordinate systems. Bill made a configuration for
the Mode Cleaner with LSC and correlated seismic motion. This was developed to
study the frequency noise of MC due to the seismic motion.

Documentation
---------------
(Hiro) e2e primitive manual was updated to reflect various recent changes, all of
which are necessary for the next major rewrite of Han2k.

Installation
------------
(Ed Maros) Built latest version of E2E for Hanford

Alfi
----
(Bruce)
- Continuing work on model for updating bookkeeping objects from changes the user
  makes in the GUI.

(Melody)
- Continuing on the node settings dialog.
- Also updating the member node widget implementation to fit it in with the event-listener model.

LIGO Data Analysis System

Software Systems (Blackburn)

The periodic MDC being carried out at Hanford is nearing its completion. The MDC
did, as usual, generate a number of problem reports. However, it is being
considered a tremendous success in that the scope outline by the MDC plan
was completed successfully with only minor issues which will easily be fixed
in the next couple of LDAS releases.

The group at Hanford also began working on a new search code to run under
LDAS which will search for coincidences between gamma ray bursts and GW
bursts. This code will be integrated into the Burst Upper Limits Group's
strategy.

LDAS is planning a new code development freeze this Friday, December 7th. It
is in anticipation of the next release of LDAS which will be used during the
E7 run and is being closely coordinated with the LAL/LALwrapper release. Due
to time constraints, we have determined that it will not be possible to have
a diskCacheAPI in this release. The option to allow data decimation using an
FIR filter in the upstream frameAPI may also have to be removed from this
release. If we are able to get this into the release, then there are two very
nice advantages to this release:

1) ability to get longer time intervals of data into data analysis pipelines
2) reduced computational and network loads on downstream APIs in pipelines

While exploring the possibility of supporting decimation in the frameAPI a
non-thread safe aspect of the dlmalloc memory management code was discovered.
A fix for this has been added to the dlmalloc released with LDAS and is now
being tested. This could possibly explan some of the thread issues seen in
the dataConditionAPI.

A problem with disconnected sockets in the dataCondtionAPI interfereing with
the start up of wrapperAPI parallel jobs on the beowulf cluster was discovered.
The cause of the disconnected sockets is unclear but a clean up routine has
been added and the problem is no longer seen on the development system.

The latest release of LAM, version 6.5.6 has been installed on all the Lab
LDAS system. All the necessary patch files and documentation have been added
to the CVS repository and posted on the development webpages.

In an effort to read in frequency domain data stored in process frames for
post processing steps it was discovered that the dataConditionAPI was unable
to ingests these data types. Code to support frequency domain data is now in
place and being tested with process frames from the periodic and stochastic
search codes' output.

The -returnprotocol option for naming and directing output data products from
LDAS jobs has been fully implemented to support local files, anonymous FTP, and
http access. This effects all LDAS job commands.
 

The lightWeightAPI has been updated to support multiple threaded requests
for LDAS jobs. This elimenates the serial bottleneck that existed previously.
A similar sirialization bottleneck was found in the metaDataAPI and new C++
code to support more threading has been added. The TCL layer to take advantage
of these new threaded functions is being developed and will be available in
the next LDAS release.

The documentation for a single cpu LDAS system has been updated and is now
being verified. It will appear in the next release of LDAS.

All the mpi and inspiral MDC scripts have been updated to use the new "cleaned
up" -frameQuery syntax. We communicated with the UWM group on these changes
and await their okay to submit the changes to the MDC CVS repository.

Hardware Systems (Anderson)

Caltech
-------
(Dan Kozak)

Continued to migrate data from (mostly) 3590 tapes to 9940 tapes.

The main problem with Encina (running out of memory) has been fixed.  I
helped identify another problem (bug in dumppv_pvl) that caused Encina
to crash.  A patch has been applied to dumppv_pvl and Encina has
remained up since.

Continued to label and import LIGO-purchased 9940 tape cartridges.

Dealt with some problems that were a function of conflicts between the
migration work and ingesting new data (i.e. running out of disk
cache).  Convinced James Patton that temporarily disabling LIGO access
to HPSS was not the solution to the problem.

(Al Wilson)

This week
working on makeing our own RPM from scratch. Also help Igor with seting up
linux systems.

(Stuart Anderson)

Received and installed Solaris 8 on the 6 new Caltech SF880 servers.

Determined that a single 2200VA UPS is the right size for the new SF880 servers
configured as they are with 4 out of 8 CPUs and 6 out of 12 internal disks.

Started configuration of new central LDAS server--upgrading from E220R to E450.

Working on certifying the cfdef perl script to handle LDAS Solaris system
configuration management in addition to the previously working support
for Linux.

Help setup second Sun equipment rack and UPS in Powell-Booth to support
the LDAS archive system.

Begun ingestion of E6 data into the Caltech archive--approximately 50% complete.

MIT
---
(Keith Bayer)

setup BigBrother as per Shannon's instructions
(adjusted repeat warnings in etc/bbwarnsetup.cfg)
investigating kernel upgrade for linux boxes
received Sun shipment of SunFire 880 / T3 Raid Array
Moved ldas equipment around so that ldas lab floor could be waxed
Ordered Solaris 8 media (latest revision) through Caltech

Livingston
----------
(Shannon Roddy)

Finished troubleshooting the backup script on LDAS.  The problem
was with the permissions on one of the ssh files.  The backup script now
works as it is supposed to.  Once I edit the configuration, backups can
be added to the cron on admin.

(Igor Yakushin)

* Visiting Caltech
* Learning to run LDAS jobs
* Learning to build LDAS systems

Hanford
-------
(Greg Mendell)

1) The November 2001 Known Pulsar Demodulation Mock Data Challenge was
run from Nov 27-30 at LHO.  All problem reports opened during the MDC
have been closed, or have been analyzed and will be closed after the
next release of LDAS.

2) E6 data was untarred and made available to ldas jobs and
investigations
at the sites last week.

3) A "Cache memory parity error" was reported by t3-7 causing the fb3
framebuilder to crash.  Sun replaced the controller (which includes
the cache) on t3-7 on the morning of Dec 4. Everything has been
running normally since then.

4) AIT2 tapes have been ordered for the E7 run.

5) A simple script was written and sent to
ldas_admin_all@ligo.caltech.edu
that synchronizes the times on the T3s with that on the admin machine.

General Computing (Wallace)
(Keith)
-Moved gc equipment around so that basement floors could be waxed
-Ordered Mathematica software upgrade
-Investigated MIT purchasing requirements for capital expenditures
-Setup new laptop for for postdoc
installed software
setup wireless card
-Investigating VNC remote display through SSH
-Adding users to PortMaster modem server

Livingston:
(Shannon)
-Installed office 2000 on the machine in Bonnie's office.
-Investigated some leftovers of the Nimda worm.
-Worked on price quotes for various needed equipment in the new building
here.
-Gave Ed Daw access to one of my "testing" computers here so that he can
try and build LDAS on a RH 7.1 system without affecting the machine that
he uses on a daily basis.
-Contacted hummingbird software to ask some questions
about our license/maintenance renewal.  Thinking about the
advantages/disadvantages of using cygwin to replace hummingbird.  It
would be free to use (GPL'd) rather than paying ~$1100 annually for
license renewals.

Hanford:
(Christine)
- Installed a new Photoreader on the new guest PC.  The old one was too
old, ie. no compatible drivers were available.
- Re-built the old guest PC to pass it on to a new user.
- Worked on comments to Albert's Security Plan.
- Installed patches for Solaris 8 AdminSuite, so the nis+ passwords
would work.
- Reviewed Larry's latest GC Policies and Procedures.
- Installed the new tape robot on the new file server and installed the
latest version of the backup software.
- Started installing more memory in all the GC Ultra 10s.

CIT:
(Veronica)
- Posted updates to LIGO website (MOU's, Fellowships/postdoc positions,
Conference participations).
- 2002 GWADW Conference: working with the Organizing Committee on the
contents/structure of the conference website. Started on making graphics
for the website.
- CaJAGWR: finalizing the seminars schedule for the Spring '02 term;
negotiating the room reservations.

(Mike)
-Updated all algor users with current update file date 11-20 file size
431MB. Engineers were having problems with software when running a stress
test through the network. Once file was copied to local computer the all
stress tests ran fine.
-Loaded Win98 on top of Ken Mailand's PC's current configuration,
because he insisted that he needed a complete rebuild but talked him into
doing a reload first. After reloading his computer software seems to be working fine.
Ken's computer is not up to speed with solid works, after coming back from
his training classes and has figured out on how to master this software,
he has showed me the problems he is having with his current PC and it looks
like he is going to need a updated computer, we ran tests on Dennis
Coyne's engineering workstation and the software works just fine. Ken mentioned to
me that Solid Works Reps, are recommending a 1.4 Ghz computer with a
tested video card that is listed on their website in order to get full
functionality of Solid Works software.
-Loaded a new Laptop for Peter Shawhan with all General Computing
software, issued him a wireless card and configured it.
-Ligo project was spammed by campus sending out a virus to all; users
informed me about this matter and asked if I would check this out to make
sure it was removed from the LIGO systems.
-Norton has the current update and a fix tool for the goner virus.
Users called for me to make sure that their computer was cleaned and
protected from any viruses as I attended to their requests, I ran the
goner tool and so far the LIGO_CIT users are okay. Thumbs Up!
-I ran multiple ghost backups of administration computers; I still have a
few more computers to add to ghost server.
-Updated access points with new MAC addresses.
-User support onsite and phone support by multiple users; as everyone
knows
I am the LONE RANGER this week and yes I am very busy.

(Lisa)
-Attending the LISA conference but did get the Monthly backups run before
leaving for the conference.

(Larry)
-Worked a number of procurement issues and ordered some more equipment for
various users.
-Worked on a couple of the policy statements. Received some feedback and
will work on the changes next week. Once the group agrees on the content
we will then get approval from Gary and have it checked over by Caltech to
make sure we are not putting in anything we shouldn't be.
-Worked on some hardware installations.
-Attending the LISA conference. Some of the interesting points so far:
A number of companies are putting in SUN servers and using PC's as
clients. One University group that I talked to really likes Solaris for
Intel.
LDAP is still not mature and has a number of stability problems. SUN
IPlanet version was touted as being the most stable but lacked some
features. It appears to be at the level NIS+ was about 6 years ago.
Only 1200 attendees. Less than 1/2 of last year. Sept. 11th hurt the
conference as far as attendee and vendor participation.
-Worked with Barbara, Mike and Veronica in getting some of the DCC and NT
web server issues cleared up. So far testing has proven the problems have
been resolved, people are now getting the latest copies of the documents.
 


LIGO II/Advanced R&D (Sanders)


From: Helena Armandula <ahelena@ligo.caltech.edu>

Procured 2 types of heavy glass frit samples, 1 kg ea. from Viox  to test melting behavior and casting processes.
Sem Com in Toledo , Ohio will do the casting. The parts will be formed into 1/2"dia. substrates.
The glasses are: formula V1586 - density 4.07 gms/cc and Formula #24935 - density 6.77 gms/cc

"Q" Substrates shipped to Lyon from Caltech on Nov 14th were received on Nov 29th.
Coating of those parts will take place Dec.12th.

Gregg and I scheduled a visit to MLD on January 4th.

Adv. LIGO PSL
Peter King
Advanced LIGO PSL
A meeting was held at Lightwave Electronics to discuss the
approaches to increasing the output power of laser #104 to 20W.  It appears
that the preferred approach would be to add an additional amplifier to the
output of the laser.  The amplifier would be identical to the one currently
in the 10-W laser.
 

PSL @ LASTI
Lee Cardenas
·       The 10 watt Laser is ON and the power is 10.50 watts.
·       The Ref. Cavity is fully assembled and hung. The chamber is pumping and the ion pump will be switched on tomorrow.
 

Advanced LIGO SUS: Modelling and Testing for Prototype Suspensions
Calum Torrie, Janeen Romie
We had a very productive conference call with Mike and Eoin in Glasgow and Norna at Stanford. We discussed the work we have been doing for the design of a new blade and sorting out what we need for our testing, that will start in January. (Norna Robertson will be visiting us for the month of January.)
Continuing work on updating version of triple pendulum model as well as continuing with designs for the LIGO MC suspension.
We have sorted out the problems we were having between ALGOR and AutoCAD.
(We can now transfer existing 3D .dwg files from AutoCAD 2002 to Mechanical desktop 6 and then to ALGOR 12, with November updates.)
Next week we are attending classes in SOLIDWORKS.
Calum will visit the IGR group in Glasgow, on the 20th and 21st December, to borrow some material, blades and wire used in GEO so I can compare with new material and parts we have ordered. This will also be a good opportunity to speak to the various people about the status of the prototype suspension design.
Janeen is also working on finding a vacuum compatible LED and photodiode.

Adv. LIGO SUS Dynamics Modeling
Mark Barton
I continued validating my suspension model against Calum's Matlab
version. So far the only significant differences to surface have been in
the interpretation of the input parameters. The Matlab interprets values
of wire length in the model definition as stretched lengths, whereas my
model naturally prefers to be given unstretched lengths. Similarly the
Matlab uses stretched lengths in calculating the elasticity of wires,
whereas by default mine uses the unstretched lengths. Thus for
comparability I added options to use the alternative interpretation. With
no fudging beyond that, the mode frequencies agree at the 1-2% level,
except for two relatively high frequency modes where the top two masses
move in longitudinal and pitch. I suspect there must be a minor error in
the way I've specified one of the top masses, so I've been working to
isolate it.

_____________________________________________
LSC LASERS WORKING GROUP
Minutes of telecon Dec. 6st, 2001:
participants: morning call: Peter Veitch, Maik Frede, Martina Brendel, Ralf Wilhelm,
Benno Willke
evening call: Martina Brendel, Maike Frede, Ralf Wilhelm, Gary Sanders,
Peter Fritschel, Shally Saraf, Peter King, Benno Willke
1) updates
Adelaide:
- still working on the problem that a too strong negative thermal lens develops when pump
power increases
- found huge variation (up to a factor of two) in power behind fibre between the different
pump diodes and tracked the problem down to a dependency of “the power out of the
fibre” on “the angle under which the fibre leaves the SMA connector” which is used to
connect the fibre to the laser diode
- now they optimise this angle for each diode
- Ralf Wilhelm will check if he can simulate the lens causes by an inhomogeneous pumped
slab
- LZH will check if their pump diodes show the same effect as soon as they arrive
LZH
- consider different pumping schemes for rods
- model compared to first fluorescence measurement shows good agreement of spatial
pump distribution in rod
- first 10 laser diodes will arrive latest next Monday
- rods for 100W system arrived and will be coated in house (either EBS of IBS coatings,
they try to get IBS)
- two 23W lasers delivered to VIRGO
- birefringence is included in the modelling, however convergence and agreement with
earlier measurements is not very good
Stanford
- finalized design of new slabs, order placed (?)
- no experiments towards the 100W system done
Caltech-Stanford
- discussed with Lightwave how to increase power of 10W system, different options
(increase NPRO and ampl. power, add additional amplifier stage, redesign system) are
under consideration, Peter King and Shally Sharaf will try to get upgraded system as soon
as possible  (GHS note: We will likely procure an added amplifier stage for this)
 
 

Date: Thu, 06 Dec 2001 20:56:42 -0500
From: David Shoemaker <dhs@ligo.mit.edu>
Subject: SWG: Summaries and Agenda; Telecon Friday 6 Dec, 9am Pacific

SWG Telecon, Friday 6 Dec, 9am Pacific

Agenda:

Organization and Schedule

Accelerated pace for seismic remediation at Livingston for initial LIGO

Coating losses on Sapphire: need for a test program

Discussion of Summaries (I am personally truly impressed at the amount and variety of progress)

================================

Suspensions Report from Norna Robertson covering GEO Glasgow and NAR at Stanford.

A. Materials

1) Algor modelling of sapphire masses including anisotropy completed for analysis of coated sample. (David Crooks).
Coating loss results being analysed by Sheila Rowan (Stanford) and David - some anomolies to be resolved

2) Measurements of mechanical loss of 6 silica samples (LIGO) for coating by Mackowski in Lyon now complete. 4 have been despatched to Lyon, and 2 more will be despatched next week. Loss factors are around 1 x 10^-7 for most modes but there is noticeable variation between masses (Peter Sneddon). .
Return of one annealed mass and 3 coated masses is awaited. Algor analysis of masses underway to allow interpretation of coating results.

3) Further work on ear design to demonstrate lower peeling stress for tapered ears - both by Algor and polarimetry with plexiglass models. (Eoin Elliffe).

4) Measurement of bond strength (silica to heavy glass) carried out on only sample currently available. Result falls within range measured for silica/silica bonds. (Eoin Elliffe).

5) Sample of REO high reflector coating sent to colleagues in Newcastle for measurement of coating modulus by contacting afm method (Eoin Elliffe).

B. Other Suspension Matters

1) Further investigation of blade behaviour underway  aimed at allowing more accurate prediction of deflection under load. Comparison of IDEAS finite element model, calculations based on equations from VIRGO, and experimental data on various blades (Eoin Elliffe, Mike Plissi, + Calum Torrie, Caltech)

2) Further consideration of blade internal modes  thermal noise level at peaks. Most important is lowest in chain, which has less isolation (but also highest frequency since supporting less mass). If allow higher stress than used in GEO, damping probably not necessary to reduce noise level below sapphire internal level. (Norna Robertson + Peter Fritschel, MIT)

3)  Consideration quantitatively of difference between hanging pendulum suspension from “ground” and active isolation table. Simple analysis suggests effect on frequency and Q of actively damped suspension is of order 1% or less for  reasonable values of mass ratios, frequencies, gains. (Norna Robertson)

=========================
 

Suspension design: (Janeen and Calum)

Cantilever Blades
Janeen has ordered some maraging steel, type 250 from a US manufacturer. We also have quotes from the French company that supplies GEO with maraging steel through a NY distributor.
We spoke with Giles Hammond about experience from the Stiff group on their blades.
Janeen and I have been working with the Glasgow group and Norna at Stanford on the design of the cantilever blades. (After many problems we can now transfer existing 3D .dwg files from AutoCAD 2002 to Mechanical desktop 6 and then to ALGOR 12, with November updates)
Tests
We have a set of AutoCAD drawings in workshop and various parts have been ordered to allow us to carry out various pre-prototype tests. We should be ready to start work in the lab in January, this will coincide with Norna Robertson's visit.
I am visiting the IGR group in Glasgow, on the 20th and 21st December, to borrow some material, blades and wire used in GEO so I can compare with new material and parts we have ordered. This will also be a good opportunity to speak to the various people about the status of the prototype suspension design.
LIGO Mode Cleaner Suspension
The AutoCAD drawings of masses/ small parts near completion - looking at a coil holder structure/upper mass catcher, based on GEO design. (We are both going to classes in SOLIDWORKS next week for a week)
Janeen has been looking at the design of a support structure for this suspension, in particular its natural mode frequencies.
Modelling
Mark Barton has a set of parameters from me for a quadruple pendulum, to allow him to compare his model with the existing one. I have been working with Norna to update the GEO triple pendulum model closer to the version we use for the quadruple pendulum.

=======================

Quad Suspension Tests (Rich Mittleman)

The "measuring the modes" phase of the characterization of the
prototype all metal quadruple suspension is nearing an end. In this work
we have been driving the chain at the top mass (#1) using the actuators
supply by the Glasgow group. The transfer function to various points on
the chain are then measured using either the actuators themselves (for the
top mass) or one of six Kaman position sensors. The latest set of data
can be found at http://tintagel.mit.edu/~richard/Rotation/. In these
measurements the rotational degree of freedom is excited at Mass #1, and
then measured on all masses by taking differences between two sensors,
positioned horizontally symmetrical from the approximate center of mass.
In all of the plots the vertical dotted line represents the predicted
frequency from Calum Torrie's model.
The NoDamping plot shows data from all four masses and the model. The
data has been scaled to make the Mass #4 data and prediction amplitudes
agree. No Damping means no Rotational Damping, the other direction have
damping in some runs.
The other four plots (Mass #1-4) show the effects of damping. In this
data the damping gain was either set at zero or 50% of full scale.
A little bit more data on this degree of freedom still needs to be
gathered, the Mass #1 data is very skimpy. A tentative identification of
the four rotational modes based on these plots is
Model Frequency Measured Frequency
(Hz) (Hz)
0.6544 0.6835 +/- 0.001
1.4691 1.5255 +/- 0.0005
2.8538 2.7944 +/- 0.0002
3.9300 4.1711 +/- 0.0003

The last measurements in this phase involve finding the highest
frequency bounce and roll modes, which weren't visible the first time
around.
It should be noted that great care has not been taken to make the
excitation of measurement system orthogonal. That is the excitation is
probably not limited to the degree of freedom of interest and the
measurements aren't preformed exactly at the correct position and angle.
The result of this is that was a significant contamination the data
sets with modes associated with other degrees of freedom.

==================
 

Report for SWG call from Stanford  (Sheila Rowan)

SWG related activities this month:

Using updated anisotropic models for sapphire, and subsequent updated energy ratios the Q measurements for a coated sapphire test mass were re-analysed.  (collab. with Glasgow, D. Crooks)) To get a consistent value for coating loss requires rejecting the data point for the highest Q mode  this is not a solution we are happy with. Ryan Lawrence has shipped this coated sample back to Stanford from MIT for some more study.

An m-axis sapphire sample previously measured in Glasgow had a highest Q of ~4 x 10^6  lower than expected (P. Sneddon).  Preliminary measurements in Stanford to check this have given a Q of ~ 5 x10^6 slightly higher. A companion c-axis piece will be measured to check whether suspension technique is at fault or whether there is a difference between these samples.

First of the 5 fused silica coating samples installed in tank at Stanford for pre-coating measurements.

=============================

Gregg Harry

The coating Q program is proceeding. We have preliminary measurments from
both thin samples that were cleaned and annealed at SMA/Virgo in Lyon. The
concern was that this process might hurt the Q and thereby compromise the
results from coated samples. We found that this is not true, as the Q's
were near 20 million before going to Lyon and over 40 million afterwards.
There are still a few details to be worked out getting Q's for all modes,
and doing the best fit to the data, but the trend is clear. This seems in
general agreement with the results from Numatat et al, that show that the
Q of fused silica can depend on annealing. It may also suggest a strategy
to improve the loss in the coating material itself, although the Ta_2O_5
does not stand up well to annealing.
We are measuring before Q's on other samples now, and will send two more
thin samples to Lyon December 17. We expect the first samples to be
coated in early January, two thin samples and one thick. A second thick
sample will be cleaned and annealed. It will be interesting to see what
happens to it. The first coated samples should be back in our hands
somtime in January.
We have also at MIT had some discussions about coating loss on sapphire.
Given that sapphire looks increasingly likely to be the test mass
material, and the first round of coating Q measurements don't rule out
rubbing between substrate and coating as a loss mechanism, it may be wise
to do some more planning for measuring coated sapphire samples.

===============================

Heavy intermediate glass (Helena Armandula)

Procured 2 types of heavy glass frit samples, 1 kg ea. from Viox to test melting behavior and casting processes.
Sem Com in Toledo , Ohio will do the casting. The parts will be formed into 1/2"dia. substrates.
The glasses are: formula V1586 - density 4.07 gms/cc and Formula #24935 - density 6.77 gms/cc

===============================

Thermal Noise Interferometer (Eric Black)

The Thermal Noise Interferometer appears to be approaching a thermal-noise limited sensitivity in its South Arm cavity. Our most recent sensitivity curve displays, in the range of 300Hz to 3kHz, a slope (f^-0.5) consistent with mirror internal thermal noise. The amplitude of this noise curve is also approximately consistent with mirror thermal noise, based on ringdown measurements of the Q of the lowest-frequency mode in the output test mass. This ringdown measurement is currently very rough, but with it we are able to set an approximate upper bound on the output mirror's Q of 100,000, which would produce, in our interferometer, a thermal noise of about 1e-18 m/rHz at 1kHz. Our observed noise floor is 3e-18 m/rHz at 1kHz, which indicates that the mirror's Q must be at least 15,000, or about 20,000 if both mirrors have the same Q. We are currently working on a more accurate measurement of the Q's of both the input and output mirrors in an attempt to refine our estimates of the expected thermal noise.
That the Q of at least one mirror is no larger than 100,000 is somewhat disappointing. It may not, however, be surprising. The mirrors in the TNI right now have visibly rougher polishes on their outside diameters than our first set of mirrors (for the higher-finesse cavities). We do not expect this to affect our ability to measure Braginsky noise in sapphire, since the level of that noise is expected to be comparable to the noise level currently exhibited by the TNI.

===============================

Phil Willems

Fused silica fiber research:
----------------------------
I have measured the unloaded Q's of the fiber in my violin mode suspension to be
~1.1e7 above the thermoelastic damping peak (4 modes measured). This value is
about 2x better than expected based on the line in the Gretarsson-Harry plot. I
believe the difference to be the use of hydrogen in my torch, compared to
methane at Syracuse. This makes the line in the Gretarsson-Harry line a
conservative estimate and safer to use in predicting adLIGO performance.
After plugging this intrinsic Q into the experimentally verified dilution factor
formulas, I generated the following plot comparing my measured Q's to the linear
and nonlinear thermoelastic theories
(http://www.ligo.caltech.edu/~willems/exp_paper/Figure7.ps); the pink dots are
data, the black dots NTE, the blue dots LTE. You couldn't ask for better
verification of LTE. While not conclusive, this plot seems to me to scream that
NTE must be verified before we can design fibers/ribbons for adLIGO.
An article summarizing this work has been drafted and is being reviewed by the
authors.
Silicate bonding research:
--------------------------
Helena, Mathieu and I have polarimetrically measured the stress distribution in
a sapphire/silica bond that has been heated to 125 degrees C and returned to
room temperature. While quantitative results will require more work, we clearly
see that stress induced by differential thermal expansion as the sample is
heated relaxes quite quickly at high temperature- in fact all visible stress is
gone in ten minutes or so. This may signify thermally activated plastic or
viscous flow. Or it may represent a one-time curing process. When the sample
returns to room temperature a large amount of stress is then frozen in that
apparently never decays. This is in bonds that are months old before heating.
Work continues.
Coating loss research:
----------------------
Not much to report. I have ordered a spectrometer and some coated samples with
which to measured the Young's moduli of thin film mirror materials. Delivery is
expected in January.

==================================

SWG Monthly Progress Report for the Syracuse Group
submitted 5 December 2001 by Peter Saulson

Q of fused silica flame-drawn rods:
Steve Penn and Sasha Ageev have now measured the Q's of a number
of modes of two rods made out of Suprasil 312. A 3 mm rod had Q's in
the the low 60 millions, and an 8 mm rod has one mode (its lowest,
around 750 Hz) with a Q of 81 million.
There are several lessons to draw from this.
1) 81 million is a new record Q for fused silica.
2) This is the first time we've measured 312 in our lab, so we
confirm that it also has good Q.
3) The bad Q's we were finding with our last sample of
Suprasil 2 must have been due to bad quality of that sample, and not
to any features of our new apparatus.
If 312 should behave like Suprasil 2, and if the trend with diameter
that we saw (and attributed to surface loss) had continued, we would
have expected even better Q for this thickest sample, by about a
factor of 2. Sasha and Steve will try one thicker sample still, to
see if we are leveling off at something we might call the bulk Q.
One further remark: The 8mm sample was rapidly cooled after being
drawn. (The glassblower cooled it with pressurized air.) If the
temperature history of the sample is important, as seems more and more
likely, this rapid cooling might have affected the Q.

Q of coating substrates:
Steve Penn and Luis Lopez have measured the Q of a thin coating
substrate that the Lyon lab had cleaned and annealed, but not coated.
Preliminary measurements show a Q of around 43 million, a
substantial improvement over the pre-treatment Q. Annealing seems
to be good! (Gregg Harry's report will mention his even better number.)

Comment on annealing, surface loss, etc.:
Our Japanese colleagues were the first to show that annealing could
improve the Q, and now these coating substrates are giving even more
exciting results. Exciting because the Q's are so high (Gregg's
sample in particular), and also because they were achieved
in samples with rather extreme surface-to-volume ratios. This means
that the surface loss in them is much smaller than we would have
expected from measurements of other samples. It appears that whatever it
is that annealing does includes repair of surface damage.
The effects of annealing are profound enough that we have to think
again about the way we interpreted our Q vs. diameter results as a
simple manifestation of a surface loss effect. Perhaps the different
thermal history of rods of different diameters plays a role. (Thinner
rods/fibers cool more quickly, so they are more nearly quenched after
fabrication.) We will anneal some thin samples and see what we can
learn.

Anelastic experiment:
Annealing is in the air. Scott Kittelberger concluded that one of
the limiting systematic errors in the anelastic experiment is the
signal that comes from fixed birefringence gradients in his sample,
visible because of motions excited by the release of the vise.
Over Thanksgiving, Scott began annealing one of his silica blocks, then
gradually cooled it to try to reduce the birefringence gradients.
(He learned a lot from folks at Corning about how to anneal silica.)
We'll see soon whether this made any difference.

Violin mode monitor:
Andri Gretarsson has cleaned up the input optics of his violin mode
monitor, to increase the light power. The extra light reflected from
his fiber caused his laser to become noisy, so he also added a classic
quarter wave plate plus PBS circulator to remove the reflected light.
Now he is implementing a simple Michelson interferometer to perform
an absolute calibration of the motions of his focusing lens. Soon
he'll take a more extensive set of data on his metal fiber.

Personnel note:
Congratulations to Andri, who has just accepted a postdoctoral
position at LLO. He has told Barry that he hopes to start
March 1, so he'll be working hard to finish up the violin mode monitor.
 

==================================

From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>

One month worth of weekly!  I have been lazy.

@ Pasadena
Charlotte
Measuring thermal conduction of existing glassy metal and maraging
samples.

Charlotte, Riccardo, Gianni
Designing reed (diving board) Q-factor measuring setup between 2 and
400oK, calculating double oscillator support geometry to achieve
sufficient reed mechanical isolation factors within the 2.5cm diameter,
7.5 cm length available sample volume.
Testing some shadow meter components.
Preparing a coarse glassy metal stress strain measurement.
Creep measurement ongoing. Problems with data transfers due to
firewalls.
Received all mechanical parts to upgrade the creep measurement setup.
New electronics still lags.  Anycase installation of new components will
have to wait for end of present measurement.

Charlotte, Bill Johnson, Jan, Riccardo
Preparing melt and spin cast of ribbons optimized for mirror suspensions
(non magnetic, high yield, high internal Q-factors).

Riccardo, Hareem
LVDT paper ready to be submitted to NIM, will appear under P010035-00-D

Also previously submitted
Szabi
Submitted “Anatomy of the Seismic Attenuation System for TAMA300(TAMA
SAS)” for Amaldi conference proceeding, P010034-00-D
Akiteru
Submitted “Mirror Suspension System for the TAMA SAS” for Amaldi
conference proceeding, P010033-00-D
Riccardo
Submitted “Path-finding towards a cryogenic interferometer for LIGO” for
Amaldi conference proceeding, P010032-00-D
Virginio, Giancarlo
Completing MGASF theory paper.

Virginio
Writing MGASF result paper

Szabi
Completing IP result paper, promised for soon!

@ Pisa
Francesco, Riccardo
Organizing University of Pisa/LIGO grad student exchanges, there might
be students available for different locations in LIGO and or Virgo/LIGO.
Please enquire if you need a student.

Alessandro, Riccardo, Francesco
Ultra Sound Milling Machine will be built by Faimond and paid in
partnership with INFN and INFM of Italy, the machine will reside and be
further developed in the INFM locals of Universita’ di Pisa.  It will
produce sapphire flex joints for LIGO.  Other INFM scientists to join
the development.

Alessandro, Riccardo, Franco Frasconi, Gianni
Refurbishing an old Virgo stress strain machine for precision
measurements of elastic and Poisson modulus, hysteresis and yield points
in Glassy metals.

Alessandro, Riccardo
Tested thinning of glassy metal ribbons by electro-polishing and
successfully thinned existing 30 micron ribbons to 10 microns.
Developing differential etching to shape the flex joint; failed with
conventional photoresist available in house and gold plating, will
procure ad hoc photoresist and solve the problem.  Testing different
brazing techniques.

Alessandro, Riccardo, Gianni
Engineering flex joint structure for mirror hook-up.

Alessandro, Francesco
Advancing on vertical accelerometers.

@ Hongo
Akiteru  et al.
Starting with the one tower TAMA-SAS Michelson measurement.  Will get
some results soon.
Riccardo going to Hongo next week to assist on second tower
commissioning.

==================================

Advanced LIGO Seismic Group Update (Joe Giaime)

The Advanced SEI group once again is concentrating on two things,
preparations for the ETF active platform test, and a test of an
external hydraulic pre-isolation stage to be carried out at LASTI.
Also, the final "feature" of the LIGO-I seismic isolation system has
been implemented at LLO.

Stanford:
Amit/Brian: new valve (designed for pneumatic use) received, test in
progress. Seems to function, but detailed tests not yet done.
Corwin/Brian: geophone received, under evaluation.
Jeremy/Hua: inductive displacement sensor received and calibrated, noise
performance under evaluation.
Corwin/Norna/Brian: Control of hydraulic test stand using vertical
"supersensor" achieved improvement over most of 0.1 - 10 Hz range.
Next: Characterize improved bellows stiffness, then build up new
design actuator with new bellows and new valves.
Hua/Brian: continued work on two-stage "rapid" prototype, and
characterizing the candidate displacement sensor for the hydraulic
stage.

JILA:
Giles has gone back to the UK having contributed a great amount in the
past two years, most recently the day-to-day oversight of the HPD's
design and fab of our ETF prototype parts and the spring/flexure
detailed design. Delivery from HPD may be delayed (at our request)
until some time in January to allow a complete fit check with all
blade springs.

MIT:
There has been much preparation for the upcoming LASTI hydraulics
test, including the installation of a LIGO-I BSC stack (with the help
of a crew from LLO), as well as some dynamic tests and modelling of
the BSC piers and a hydraulic pump. (Joshua, Mike, ?). Ken is working
on the design of a large extension spring and interface hardware to
support the weight of the in-vacuum payload and allow hydraulic
actuation.

LLO:
Marcel has continued overseeing production of the small (inner stage)
seismometer pods for the ETF prototype, and (with Szabi) the locking
mechanisms. Also, a shop that can fabricate the large springs for the
LASTI hydraulics test has been identified in New Orleans.

LSU/LLO:
Ed, Rana and I have implemented the microseismic feed-forward system
at LLO. We see an 85% reduction in the microseismic displacement
among the test masses, pretty much meeting the system goal. At
http://www.ligo.caltech.edu/~dhs/SWG/microseism-init-ligo-correction.pdf
is a two-page summary I prepared for last week's PAC meeting.

=====================================

LASTI (Bayer, Fritschel, Goda, Harry, Laliberty, MacInnis, Mason,
Miller, Mittleman, Ottaway, Phinney, Rollins, Shoemaker, Zucker)
 

HAM13 SOS INSTALLATION: Dave O., Myron, Fred and Jamie got both SOS
optics for the short test cavity installed in HAM13. Their OSEMS,
wiring and feedthrough connections are installed and checked. The
stack optics table was counterweighted and rebalanced. One door has
been replaced on the HAM and coarse alignment is proceeding well, using
a visible diode laser pilot beam.

HYDRAULIC ACTUATORS: Ken continues detailing the actuator structural
interface design and would like to hold a design review in the next few
weeks. Joshua moved the prototype pump/accumulator skid setup out of
the machine shop into the student lab to improve cleanliness, and is
continuing experiments to understand its dynamics.

PSL: This week and last we've been fortunate to have had the expert
support of Lee Cardenas from Caltech, working with Dave O., Myron and
Jamie. The 10W Lightwave Laser has been installed and tested; its
output power has only marginally degraded during shipping (still above
spec, though). The reference cavity has been installed and its vacuum
chamber pumped down. MZ and Jamie have ordered components and test
equipment to support commissioning and upgrade of the frequency
stabilization controls, and are collecting a rich dossier on regional
and historical variants.
 
 


For additional information about this report, contact sanders@ligo.caltech.edu