Weekly Report for Week Ending October 25, 2001


 Exec. Comm. Agenda
Highlights
LSC
Administration
Hanford Observatory
Livingston Observatory
MIT
Caltech
Detector
40 Meter
TNI
LASTI
Data Analysis
LIGO II/Adv. R&D
Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  October 29, 2001 will be:

 (Meeting time: 10:30 am Pacific Time)

Open meeting 10:30 - 11:30

  1. Announcements
  2. LSC Issues (Weiss)
  3. Comments on Weekly Report
  4. WBS 1 LIGO I Construction (Lindquist)
  5. WBS 2 LIGO Lab Operations
  6. WBS 3 and 4  Advanced R&D and LIGO II (Sanders)
Executive Committee only 11:30 - noon   Topics:
 

Special Items:


Special Announcements:

I. From GHS:  Optics Responsibilities in the LIGO Laboratory

Most of you are aware that Jordan Camp has elected to take a position with Goddard Space Flight CEnter  in their gravitational research program. Although Jordan remains in our LIGO Scientific Collaboration and will continue to be associated with LIGO, most of his LIGO Lab responsibilities need to be re-assigned to others within the laboratory. These responsibilities, as well as a clarification of LIGO Laboratory personnel roles within the optics development area, are defined below.

1) Jordan Camp continues to lead the technical oversight committee for the Australian Gingin high-power test facility. This is really an LSC assignment but I mention it as one place where Jordan will continue to provide his expertise.

2) The Cognizant Scientist for the LIGO Laboratory optics activities is Bill Kells.

3) Sapphire Development:

In the interest of protecting proprietary information from our two contractors for sapphire materials development, we must take care to avoid inappropriate transfer of information between the two contractors. With this in mind, we have separate Technical Managers for each contractor. Thus:

        a) Technical oversight & management for sapphire development at SIOM is provided by Ren-Yuan Zhu.
        b) Bill Kells will provide science direction, from the LIGO Laboratory, for the sapphire development program at SIOM.

        c) Technical oversight & management of the sapphire development at Crystal Systems will be done by GariLynn Billingsley.
        d) Peter Fritschel will provide science support, from the LIGO Laboratory, for the sapphire development program at Crystal Systems.

        e) Bulk absorption measurements, in the materials research phase, will continue to be done by Alex Alexandrovski, Martin Fejer et. al. at Stanford. We are very lucky that they are continuing to provide this very skilled and expert measurement and analysis capability. The LIGO Lab liaison for this work is Peter Fritschel.

4) Coating Development:

        a) Technical oversight & management for coating development at SMA-Lyon, MLD and REO is provided by Helena Armandula.
        b) The Cognizant Scientist for the coating efforts is Greg Harry.
        c) Note the item on surface absorption in coatings below.

5) Polishing & Inhomogeneity compensation:
        Technical oversight & management by GariLynn Billingsley. This currently involves contracts with Goodrich and CSIRO.

6) Metrologyand other optical characterization:

        a) Phase map measurement will continue to be GariLynn Billingsley's responsibility.
        b) The transmission/reflection scanning and birefringence testing will be performed by Lee Cardenas and Bill Kells. (Note that this apparatus may be extended to enable surface absorption measurement as well.)
        c) Surface absorption measurement, in the coatings research phase, will be done by Alex Alexandrovski, Martin Fejer et. al. at Stanford. We are also grateful for this collaborative effort. The LIGO Lab liaison for this work is Bill Kells.

7) Contamination cavity/materials qualification: Lee Cardenas and Bill Kells.

8) Lasers:   Peter KIng will be responsible for this effort and will serve as the manager of all of our laser R&D and production contracts.

One consequence of the above separation of responsibilities is that GariLynn Billingsley is the single Technical Manager for all interactions with Crystal Systems, CSIRO, Goodrich and Veeco. Likewise, Helena Armandula is the single Technical Manager for all interactions with SMA, MLD and REO. All LIGO personnel should work through these individuals when they need the services of these vendors. If you have any questions regarding these assignments, please contact myself or Dennis Coyne.

II. From Phil: Policy on Charges to the Cost Accounts of Others

General:

Charges sometimes go through the LIGO Procurement System where the individual making the commitment uses an account number for which he or she is not responsible.  The intent of the following policy is to minimize mischarges as well as to ensure that the individual responsible for an account is informed regarding all charges against that account.

Policy:

It is LIGO Policy that when any procurement is made against an account number, the individual responsible for that account number must be notified of the commitment.  Project Controls is responsible for notifying the account manager of all purchase commitments against his or her account.  This is accomplished via a copy of the purchase request (PR) forwarded to the responsible manager.

Clearly this will be implemented when, and only when, the account manager responsible for the account has not explicitly requested or approved the procurement.
 


Weekly Report Highlights

The Livingston 4K interferometer was able to achieve and hold lock in a power recycled configuration during night time operation Wednesday evening.

"The big news comes in this message from Nergis and Rana: "


LSC Issues (Weiss)


No report.


LIGO I Construction/LIGO Laboratory Administration (Lindquist)



 

WBS 1.2 LIGO Operations--Administration



LIGO Weekly Site Telecon (Lindquist)

There was a teleconference on Thursday, October 25.  Items discussed included:

The list of current actions revised to reflect the status of open actions assigned through October 25, 2001 may be found at ACTION LIST.

PROPERTY MANAGEMENT (Chargois)

From: Ed Chargois <chargois_e@ligo.caltech.edu>


DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner - turner@ligo.caltech.edu>

Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .

ACCOMPLISHMENTS

>From: Cleveland Mak <mak_c@ligo.caltech.edu>

ACTIVITY

Packages Faxes
In 24 34
Out 8 36

Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.


COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman)

From: Esther Cunningham <esther@ligo.caltech.edu>

Press here for ACCOUNTS PAYABLE HISTORY DATA.

From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

From: Florence Kaufman <fkaufman@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: irena@ligo.caltech.edu (Irena Petrac)

From: Ed Jasnow <jasnow@ligo.caltech.edu>

SUPPORT

 
Irene Baldon
PLEASE NOTE:  This report only covers four (4) working days.
Dorothy Lloyd Rita Torres

Advanced LIGO (Frey)

From: Thomas Frey <tfrey@ligo.caltech.edu>

Progress Period from 10.18 to 10.25

Accomplishments:

Schedule 10.26 to 11.01:

WBS 1.4.1.2   Project Controls (LIGO Construction)



Reports (Lindquist)

The end-of-August Quarterly Progress Report has been sent to the NSF.  We were expecting DCAA to initiate an audit of our revised proposal for LIGO Operations this week, but it was cancelled or, at least, postponed.



Change Control/Contingency (Lindquist)

There are no change requests currently in the queue.

Press for the latest Contingency Needs Projection.


COST SCHEDULE CONTROL SYSTEMS (Akutagawa)

From: Cindy Akutagawa <cindy@ligo.caltech.edu>



SUBCONTRACTS MANAGEMENT (Jasnow)

From: Ed Jasnow <jasnow@ligo.caltech.edu>


Quality/Safety (Tyler)

>From: Bill Tyler <tyler@ligo.caltech.edu>

Finalized travel arrangements for the Hanford Safety Audit (November 8th) team members.

Conducted computer fire suppression system discussions and walk through of room 215, Synchrotron with representatives of CalProtection. Turns out that this is also the company which provides the fire protection support services for Caltech.  They will submit a bid by early next week. A second vender is planned for a visit next week.  A major challenge (cost) to installing a suitable O2 depletion system in room 215 will be the cost/difficulty in making the room "air tight".  An alternative would be to build a separate room within 215 surrounding the computers which could be easily sealed off if the fire suppression system were activated.

Arrangements have been made for getting cost estimates next week for increasing the raised floor area in room 215.
 


LIGO Hanford Observatory (LHO) Operations (Raab)


General Items:
--------------
(F. Raab)
 

Commissioning activities (reported elsewhere) are the main activity this week, with efforts continuing to involve operators more as hardware set-up needs decrease. Attendance of operators at commissioning meetings is now the default. We experienced a day of 50+ mph winds this week that effectively shut down most commissioning activities. Even the transmitted beam on the PSL reference cavities were visibly "hopping" around in the camera views and gusting winds often threw the mode cleaners out of lock. We may want to consider, for the future, steps to "harden" the WA interferometers against such interruptions. I would not fancy explaining to NSF why bad weather caused us to miss a nearby supernova.
 


LIGO Livingston Observatory (LLO) Operations (Coles)


The Livingston 4K interferometer was able to achieve and hold lock in a power recycled configuration during night time operation Wednesday evening. Multiple lock periods of around 10 minutes have been demonstrated. The high current LOS controllers at the end stations were used for this work. High current controllers for the ITM's have also been installed but were not utilized for these initial studies. We will now see how we can extend the capabilities of the interferometer to lock during the day by using these additional controllers. We are also modifying the controller boards for the BS and RM so that we will have the same control authority over them. We still have a lot to learn about the interferometer, especially some features of the side band power and asymmetry in the PRM that are not yet understood, but this achievement is an important milestone in the commissioning effort here. Congratulations to everyone for their contributions towards this achievement.

From another message from Mark:

From: Mark Coles <coles@ligo-la.caltech.edu>
Subject: Lock of the LLO 4K Interferometer

At approximately 9 pm Thursday evening, the LLO 4K interferometer began locking in a power recycled state for durations of several minutes of continuous locked operation! The locks were interspersed with brief unlocked periods and then the interferometer would quickly reacquire. Power buildups in the arms exceed 1000.

The interferometer is operating with the "zipped up" ETM controllers. (Zippy ITM controllers, also installed, have not yet been utilized. Wave front sensing for LOS control has also not yet been implemented.) Ground seismicity is around 20 counts at 20 Hz in the vertical direction at the Y end station (vs 200 during the day).

Congratulations to everyone for their help achieving this important milestone.
 

Optics and Installation: Laser Safety Interlock hardware installation is completed. The new surveillance cameras have been installed, and about half are functioning as of today. Balance should be online by week's end. They we begin programming the system logic. PSL table legs were removed, and the original leveling screws have been replaced by HD machine wedges. Completing modification of PSL safety enclosure to accommodate new acoustic enclosure. Manufacturer of PSL acoustic enclosure promises engineering drawings early next week. Made swept sine measurements of the new PSL periscope, driven acoustically. See i-log. (Jonathan Kern)
 

GC: Spoke with Computer Associates about some software that may make GC more reliable and ease some of the time requirements of Tom and I.
Trying to track down a Nimda infection at LLO. A couple files are getting copied to shared directories on a windows machine that are infected.
LDAS: Gathered all of the information for the QFS licenses and sending the information on. I have prepared a document on installing BigBrother in the ldasadm home directory. I have it installed in this manner on ldas-la. I am using ldas-sw as the machine to create the documentation from. This machine has not had a local install of bigbrother so it is easier to use for the documentation. Shannon Roddy
 


Detector/Technical Support (Whitcomb, Coyne)


 
Commissioning:

Hanford
Livingston

Science & Engineering Support
See also the daily electronic logs for the installation and commissioning activities:

Hanford Detector Log

Livingston Detector Log

LHO COMMISSIONING

2km Commissioning

(Bill Butler, Fred Raab, Betsy Weaver, Mark Lubinski)

Mode cleaner leveling continued.  The situation for the bounce modes in the 2 km interferometer has proven substantially more complex than for the two 4 km interferometers.  Each of those interferometers showed peaks clearly associated with the bounce modes of the individual MC optics, though in a couple of cases the MC bounce mode was coupled to the bounce mode of another optic and clear splitting was observed.  Here the bounce modes of the optics on HAM7 seem to all be coupled.  The MC_F signal in the 16 Hz region shows at least seven peaks (one for each optic on HAM 7 plus MC2) and they don't seem to be associated with single optics but rather with multiple optics, typically three or more.Attempts to realign the MC to bring down one peak typically cause one or two of the others to increase.  In the end we have minimized the one which is farthest in frequency from the others and attempted to notch the remaining ones.  The rms contribution from the 16 Hz peak is now comparable to that of the 12 Hz stack mode, so we are calling a temporary halt to the levelling and starting to bring the 2 km interferometer back.

Betsy and Ski remeasured the noise in the coil drivers for the 2 km LOS controllers, to see the effects of the changes that were made two weeks ago.  Details are in the elog, but the main result is that in our normal operating configuration (bias and dampings on), the noise at 100 Hz has dropped by more than a factor of 100.

4-k Commissioning

(Bill Kells, Rick Savage, Dick Gustafson, Richard McCarthy, Josh Myers, Paul Schwinberg, Luca Matone, Corey Gray, Gerardo Moreno, Stan Whitcomb)

The process of hook-up and checkout for the electronics continues as we get ready for locking the full interferometer.  A photodiode has been installed, aligned and cabled for the SPOB signal, as well as the normal BS pickoff rf signals.  The various whitening gains and filters have been set.  QPD signals are now present on both arms and being read by the software to produce the arm cavity transmitted light signals.  Rf phase setting is in progress.  We are revisiting some of these items after replacing a faulty EOM; the originally installed EOM had an open connection internally and produced very little modulation.  (as it turns out, all of the locking done to date was done using the little bit of capacitive coupling that comes from the pockells cell housing!)

The power recycling cavity has been locked and the power levels look normal.  A video camera has been aligned to look at the recycling cavity beam.

Optical levers have been modified to get pitch and yaw readouts going the correct direction

Careful measurements of the fss electronics are being made to identify where the phase shifts that limit the gain are coming from.

LLO COMMISSIONING

Rai Weiss reporting

The big news comes in this message from Nergis and Rana: The highlight of this 

week's work is that the Livingston interferometer is now power-recycled 

with typical lock stretches of 2 to 3 minutes and the longest of 9 minutes. 

With good alignment we typically see power buildups of 1000, but have seen 

some buildups in excess  of 1400. The power fluctuations are typically 50 

to 80%.

To get to this point a lot of time was spent measuring the lock acquisition 

parameters and debugging our often inconsistent results. The big break on 

that came when we found a saturation problem in the LSC whitening filters 

(by design they are supposed to have high frequency gain, which we did not 

account for correctly). Other things we had to carefully set up were the 

ISC table alignments, and, of course, alignment of the full interferometer. 

Some mysteries persist in the optical behavior of the RF sidebands; a lot 

of effort was put into measuring the RF sideband components of the light 

using scanning Fabry-Perots  at the reflection and antisymmetric ports, 

with confounding results.

--------------------------------------------------------------------------

The wavefront sensor at the antisymmetric port is now working -  a

significant accomplishment  as it shows the way to bringing the other

wavefront sensors into operation. There is a strong hunch that the

wavefront sensors (with some increase in servo bandwidth) will be needed

to allow operation of the full interferometer during the day.

Attempts are being made to lock the power recycled Michelson and a single

cavity during the day time. This is stage 3 of the acquisition process and

must go smoothly if there is to be any hope of locking the full

interferometer during the day. The higher current coil controllers have

now been installed in the ITM as well as the ETM. Work is underway to

ready these controllers for the recycling mirror and the beam splitter.

Spectra are being taken to understand fully the 200 Hz mode of the new

periscope on the laser table.

SCIENCE & ENGINEERING SUPPORT

Pentek DACs and ADCs

Jay Heefner

- We have completed the testing of the pentek ADCs here at CIT and have found 

that a few have bad channels. These bad channels were previously suspected to be 

bad at LHO and were sent to CIT for confirmation. The modules that have good 

channels are very consistent. The input referred noise is ~15uV/rtHz with a 

small hump around 4KHz. This is consistent with the measurements we made on the 

original units in 1997.

- We are in the process of developing a circuit that will allow us to use a 

delayed 16384 sample clock for the DAC output. This will allow us to set the 

total delay through the system to a minimum without turning up the sample clock 

to rates where output noise is a problem.

- The code to test input and output noise on the penteks while they are in place 

at the sites is ready. We can use it to test each channel of each pentek in-situ 

without disassembling the system.

SOS Coil Driver

Jay Heefner

- I am in the process of collecting the proposed revisions for the SOS Coil 

Driver module. Once the list is collected I will distribute it for approval and 

rev the boards. Anyone with changes should email them to Jay.

LSC RF PD

Mike Zucker

Drafted test & RF compensation procedure for LSC RF photodetectors.

Preparing for next week's visit by Nathan Hindman to begin his Jedi

Training, so that he can do this testing at Hanford

Optical modeling

Erika D’Ambrosio

I am back on validating Melody: perturbing the geometry of the two ITM mirrors

one sideband is an order of magnitude larger than the other while the results

obtained by the FFT-code for the same distortions give an imbalance of 10%. If

the common and differential lengths are changed by offsets introduced by hand,

both the dark and bright port drop in power and no consistency with the output

of the FFT-code is achieved. I have been changing the positions of the mirrors

and the beamsplitter without finding a better convergence toward the FFT-code

results. In the meantime I am developping a simple model that explains how the

imbalance between the sidebands is generated, when the Schnupp asymmetry and a

geometrical asymmetry that makes the two branches different are both included.

EO Shutter Controller

Sander Liu

EO Shutter Controller

Prepared DCN (LIGO-E-010188-00-C) to add termination resistor.

Redrawn Schematic (D980264) into one single sheet

Ordered long lead items for repair and new controllers

Obtained a quote from DEI on two pulsers

PSL

Peter King

REO have accepted to coat another batch of substrates, since they

got the coating wrong on the pre-modecleaner mirrors.  The substrates were

sent out on Monday.

40m Lab PSL: The 21.5 MHz photodetector was replaced with a modified Thorlabs

PDA-55 photodetector.  The laser frequency was swept through the reference

cavity resonance and the frequency servo mixer monitor signal looked clean.

Apart from the low RF output from the 21.5 MHz reference card, the other

signals appeared okay.  The RF output was about a third of what it should

be.  The distorted discriminator signal reported last week was due to the

RFPD not working properly. Heater jackets for the reference cavity vacuum chamber have been ordered.

Sander Liu
In the process of finalizing the acceptance test procedure for the FSS servo board

Rick Karwoski
I have set the levels, re-tested and burned in both Frequency Reference boards for the LASTI installation. Both units were shipped overnite yesterday, complete with the new board Travelers.  Test results are included in the traveler package. I have completed test procedures for both Freq Ref boards, the PMC servo and the VCO.  The Freq Ref ATPs have been submitted to DCC. DCNs for all PSL boards have been completed and submitted to DCC.

ISS Electronics: A second prototype unit has been completed and is undergoing testing.

Optical Metrology

Lee Cardenas

Picking up where Jordan left-off last at the sub-basement in bridge.

reviving the scatterometer.

I checked and turned on the NPRO S/N 190 , made a fast alignment check.

I have turned on the vacuum pump and allow the chamber to be cleaned. (pressure gauge and rga needed)

Lab needs put things in order, cleaning, fixing cable rack, tool box needed, attach and secure many of the power strips.

All of these are ongoing.

LSC

Rich Abbott, Mohana Megeswaran, Flavio Nocera
No report. Lots in progress – will be added to next week’s report.

IO Periscope

Mike Smith

One periscope was received at LHO. The second one is being shipped to LHO on10/25. The next unit for LATI is in fabrication.

GDS

Daniel Sigg

Continued to add the dtt code to the new gds archive and compile it under

linux; this week the lidax (LIGO data access) tool was moved. 

Some of the dtt crashed people experienced can probably be attributed

to insufficient memory. Ordered and installed an additional 512kB of 

memory on most of the control room machines. In the process noticed that 

some of the machines out in the LVEA have 64MB of RAM only! 

Ordered some second hand (i.e., cheap) ATM equipment to move the 

control room machines to 100bT (they are current at 10bT). Some 

preliminary tests with the new frame size indicates rates well above 1MB/s 

for NDS access. Also ordered two additonal 10bT expansion modules for 

the LVEA, since we are running out of ports there.

DMT

John Zweizig

This week I continued working on the new gds software version, and

preparing for the Burst analysis group 'PEM Deep Mine' study.


40 Meter Interferometer (Weinstein)




Thermal Noise Interferometer (Libbrecht)


This week we closed the vacuum chamber and pumped down.  The pressure is
now in the mid 1e-6 torr range, and we have begun measuring transfer
functions in preparation for attempting lock.


LASTI (Zucker)


LASTI (Bayer, Fritschel, Harry, MacInnis, Mason, Miller, Mittleman,
Ottaway, Phinney, Rollins, Shoemaker, Zucker)
=======================================================================

INFRASTRUCTURE:

The modifications to the cartridge clean room has been completed. The
modifications made were to make the leg height adjustable and provide
openings in the top to allow the stack masses to be lifted with a crane
and dropped into place.

A meeting was held with Harry Overmeier and Gary Traylor from Livingston
in preparation for their trip to MIT to assist in the assembly of the
BSC stack on 11/5 thru 11/9.

HYDRAULIC ACTUATORS:

A schedule for the hydraulic isolators has been completed by Ken Mason
and Brian Lantz and handed out to members of the seismic isolation team.

A finite element analysis of the springs designed for the hydraulic
isolators revealed stress concentations on the ID of the spring. Design
refinements are being done to reduce this excess stress.

The prototype pump stand is nearing completion in the shop. Josh machined
the flow resistors and plumbing adapters and finished the motor
electrical panel.

CDS/DAQ/GDS:

Our GDS RAID disk woes will be temporarily resolved by swapping in a
spare unused "old style" unit from LHO (thanks Dave!).  The
manufacturer's firmware revision which disabled Sun support on all the
newer units is still being worked.

NOISE BUDGET:

Gregg H. went through the noise model and checked it against all the
factor-of-two errors that have been found in bench recently.  Everything was
fine, except there was an extraneous two on thermoelastic damping that was
removed.  So the internal mode thermal noise estimate for sapphire mirrors on
the graphs shown at our LSC review were a factor of root 2 too high.

PSL:

This week the commisioning of the PSL has been delayed while we wait for
delivery of electronics and the enclosure. The electronics have arrived so
commisioning of the PSL will become a major focus for next week.
Preparations continue for the installation of the SOS optics in HAM 13 in
the near future.


Data Analysis and Computing (Lazzarini)


Simulation and Modeling (Bhawal)
 

E2E for LIGO-I meeting
----------------------
Luca gave a talk on his recent progress in characterization and modeling
of LSC. There was discussion on Stan's questions (from last week's e2e
Physics meeting) and how and who to follow those up. Details are available
from http://www.ligo.caltech.edu/~e2e
 

Modal Model
-----------
(Hiro) In process of summarizing the analytic calculation of fields in a FP cavity when
 curvature mismatch and tilt exist, up to 4th order, and adding them to
 the e2e ModalModel document (T990081). This note explicitly discusses how a few
 of the null tests that are used actually work, and can may used for the validation of the e2e code.
 

(Biplab) Did a null test for the effect of waist size mismatch of the input
 light with that of the eigenmode of a cavity. A back-of-the-envelope
calculation shows that the effect should be same as sending a beam of matched waist-size
 but of different wavelength so that the Rayleigh range remains to be same
 (Note that the round trip phase should be appropriately adjusted to get the resonance condition to be the same for both cases). E2E passed this test nicely.
Doing other mismatch studies.
 

Mechanical Simulation
----------------------
(Andrea) Written a document (T010126) which outlines a proposal to integrate
 existing mechanics simulation models in e2e. This has been prepared to provide
 a starting point for the discussion in a future meeting on this topic. This
 document will soon (in a week) be submitted to DCC and circulated.
 

(Virginio) Rewriting the code for the LIGO2 suspension simulation because of the
 necessity to have a better code maintenance ( No more C/C++ mixed code).
 Some very minor bugs need to be fixed.
 

 Implementing just one leg of the HAM stack to evaluate the feasibility of using
 MSE to simulate the entire stack. The aim of this simulation is to have a tool
 able to estimate the effects of short-circuiting one of the attenuation stages.
 The expected benefit is a reduction of the rms displacement noise. This
 modification can improve the stability of the Livingston mode cleaner. The
 seismic attenuation should not be endangered because in this case the HAM stacks have ample performance margin.
 
 Beam object still under debugging.
 

 Next week I'll have some freshman students playing with an inverted pendulum
 prototype I designed (60cm long) for the freshman lab course.
 see http://m8.ligo.caltech.edu/Phy003 for more details.
 

PSD Estimator
-------------
(Andrea) still working on the modifications to the E2E spectral estimation
 routines to implement automagic whitening and de-whitening.
 

Code maintenance and improvement
--------------------------------
 Biplab tested the parallelized runs with ordinary runs and found differences.
 Hiro fixed a bug in the simulation engine when threads are used for
parallelization. After that results matched with each other.
 

(Hiro) Fairly extensive modification of the simulation engine is completed
 and all changes will be committed to cvs very soon. This will be the base
 of the next release of e2e.
 

CVS
----
(Ed Maros) Created CVS account for Andrea Vicere.
 

Alfi
----
(Bruce) Continuing work on Alfi 5 port and connection widgets.
 

(Melody)
- Worked on event processings for the member nodes (displaying internal and
  external view, popup menus, etc)
- Worked on the alfi5 schedule and submitted it to Hiro.
 

LIGO Data Analysis System
 

Software Systems (Blackburn)
 

The long awaited new release of LDAS will happen later today.
A final freeze for source code and scripts took place earlier
and only two more documentation changes will be made before
the LDAS CVS repository is tagged for release 0.0.21. New in
this release are the following:
 

a) the ability to generate a quality channel base on an SQL
   query's result using DMT metadata.
 

b) the ability to send N-tuples of simple data sets in the
   form of flat tables (N - sequences) to the search codes.
 

c) the ability to extract spectra from the database for use
   in search codes.
 

d) the ability to enable debugging modes in the wrapperAPI
   without recompiling through a resource file.
 

e) a DB2-ready metaDataAPI from the /ldas rsync site.
 

f) a much much more stable multi-parallel job handling
   environment through significant changes to the mpiAPI.
 

g) a release of LDAS which is "nearly" compatible with the
   new libtool standard adopted for lal and lalwrapper code
   development. (one issue reported for the framecpp and a
   patch is needed to the libtool distribution).
 

h) first draft of documentation for building a full complement
   of ldas on a single computer (not distributed across hardware).
 

i) supports for new one-sided power spectral density standards
   in the dataConditionAPI.
 

j) support for returning data products from the dataCondtionAPI
   to the users in the form of processed frames.
 

k) better handling of frame file directory caches.
 

This is a significant amount of new functionality and we have
worked very hard to test it all and get the bugs out. Of course
there are still some bugs and the problem tracking captures these
however, we do feel that this is a release we can be proud of
even if it was significantly delayed in its delivery. This new
version should be available at all sites tomorrow.
 

A.L. NOTE: Kent and the LDAS team should be very proud of their accomplishment. The full benefit of the investment in the infrastructure is starting to manifest itself by the way in which substantially new functionality can now be added as the need is identified and requirement is defined.
 

Hardware Systems (Anderson)

Caltech
-------
(Dan Kozak)
(Al Wilson)
(Stuart Anderson)

The order for the next set of 8 LDAS servers was placed with Sun with the
exceptional help of Gina Salone.

A semi-permanent floor space allocation was obtained in the CACR machine
room for 3 racks of LDAS equipment. The first installation was to move
1 rack of disk storage from the ldas-test system across campus to operate
as the cache for the LIGO archive system.

Started testing RedHat 7.2 and a recent kernel patch to RedHat 7.1 to
determine the next upgrade path for LDAS Linux machines.

Added additional software mirroring functionality (rsync) via a secure
web interface.

MIT
---
(Keith Bayer)

ordered cables/converters from NTI
patched Solaris machines
installed Greg's backup script (w/o fssnap) into cron

Livingston
----------
(Shannon Roddy)

Gathered all of the information for the QFS licenses and sending
the information on.  I have prepared a document on installing BigBrother
in the ldasadm home directory.  I have it installed in this manner on
ldas-la.  I am using ldas-sw as the machine to create the documentation
from.  This machine has not had a local install of bigbrother so it is
easier to use for the documentation.

Hanford
-------
(Greg Mendell)

1) Worked with Stuart Anderson, Dan Kozak, Shannon Roddy, Dave Barker,
and Sun to obtain QFS licenses and install QFS.  Currently working on
configuring QFS on the LDAS dataserver and CDS fb3 hosts.

2) Completed changes to backup script to turn off xntpd while running
fssnap on Solaris hosts. Sent script to ldas_admin_all.

3) Logged a memory problem on metaserver with Sun.  Sun will replace the
suspect CPU if the problem occurs again.

4) A leak in the valve that brings water to the Liebert AC unit's
humidifier was shutoff by someone, and fixed by Otto. This cause the
Liebert unit to shut down its humidifier when the bulb associated with
the humidifier became too hot.  The LCD display does not show this (it
still showed the humidifier was running), even though the humidity
dropped from 43% to 21%. However, a reset button underneath the water
pan must be pushed to restart the humidifier when this happens. The unit
is now working and the humidity is now back up to normal and within
Sun's specifications for data centers.

General Computing (Wallace)

MIT:
(Keith)
-MIT PPP dial in service now operational.
-Ordered laptop for new postdoc.
-Investigating wireless options for use in building next door.
 

Livingston:
(Shannon)
-Spoke with Computer Associates about some software that may make GC
more reliable and ease some of the time requirements of Tom and I.
Trying to track down a Nimda infection at LLO.  A couple files are
getting copied to shared directories on a windows machine that are
infected.
 

Hanford:
(Christine)
- Investigating a problem with slow disk access when running Framemaker,
compilers, and Matlab.  Appears to be related to having the application
software and files on separate computers and then accessing each of
those computers from a third computer.
-  Setup a new travel laptop.
-  Investigating using encrypted passwords with Samba.
 

CIT:
(Mike)
-Daily administration on the NTSRV's, keeping up with system logs and
keeping up with security; created an additional website for Veronica on the
Amaldi server.
-Hard Drive failure on the Steve Vass PC, replaced his hard drive then reload PC
with all General Computing software.
-Jay's laptop is broadcasting what looks like the Red Worm virus that was
affecting the Caltech community. LIGO was not affected by this virus, which
means that our users are keeping their virus software updated.
I downloaded red-worm utility to clean this from user laptop and installed
service pack 2 and critical updates.
Users on the LIGO project must install the critical updates then install
service pack 2; this well prevent being affected by the red-worm virus or
any other security problems.
-Installed Solid Works for multiple users that included,
Ken Mailand, Janeen Romie 'having a problem with her SUNPC card running solid
works', we are still looking into this problem.
Dennis Coyne's and Calum Torrie also have the s/w installed.
-Problems with office 2000 causing Mike Smith's computer to freeze up on him, I
uninstalled office and system works that was running on his computer also
then reinstalled office and things seem to be okay for now.
-Instructed a user on how to run exceed to launch XMGR for him to plot.
-This week I had a lot of onsite and phone support to take care of.
This is a good thing, users are letting me know right away when they are
having software and hardware problems with their PC's before matters get worse.
 

(Lisa)
-Rebuilt canopus (internal ftp server) with solaris 8.  Helped users set up
their ssh connections to canopus after the rebuild.
-Resolved an ssh1 problem with sargas.
-Chased down a laptop that had code red worm running. Mike did the
disinfection.
-Built an ultra30 as the frame broadcaster for the 40meter martian network.
-Troubleshooting license issues with solid works on sunpci.  Once I got past
the licensing problem, we discovered a video incompatibility.  I'm currently
trying to find a fix for that.
-Looking into wireless security issues.
-Updated more pcard users for travel.
-Added a couple of new FAQs to the GC web pages.
-Was really grateful that Larry came back from SANS.
 

(Bruce S.)
 Gnats maintenance:                             (2.0 days)
- Ongoing attempt to set up gnats for the detector hardware group.
 

(Larry)
-Spent time working with Veronica trying to get her up to speed on things.
There is quite a learning curve and it will be some time before she learns
all of the logistical procedures one has to go through on the WEB servers.
-Worked a number of procurement issues. Mainly updating service contracts.
-Returned from the SANS conference. A lot of things are happening in the
computer security world. There are number of things we will have to start
investigating in more detail. Two of them being; the new laws related to
computer usage and security, and home usage. We are working on some steps
for users to apply when using their home computer and that will be on-line
the first of next week.
-Worked on a couple of servers and network hardware.
-Worked a couple of virus issues. Just a reminder that everyone using
MS should keep their virus-scan s/w up to date.
 

(Lazzarini)
- I convened a meeting among General Computing, LDAS, and CDS this week to discuss the network topology we wish to implement across the laboratory sites (with the exception of MIT). The discussion focussed on how to create secure firewall protection at several levels without impeding people's work. We have a rough draft in mind That separates out www services from user directory services from LDAS, from CDS, and from GDS in a way that will allow users who need to access these LIGO  subnets to do so while providing the benefits of programmable protection via a firewall.
 


LIGO II/Advanced R&D (Sanders)


From: Helena Armandula <ahelena@ligo.caltech.edu>

Q measurements
Two more thin substrates have been measured at Syracuse.
There is a new coating schedule that will be discussed with Mackowski. After his review, it will be implemented.

AdvLIGO PSL
Peter King
I received information from Shally Seraf about the current state of
the 10-W laser (SN #104) and contacted Lightwave about an upgrade. I have
not heard from them as yet.
 

AdvLIGO SUS
Calum Torrie
I spoke with about 10 machine shops in the Los Angeles area and a few in northern California about the possibility of doing work for us. I am waiting to receive brochures and a list of there capabilities.
The design for the mode cleaner suspension is very close to the design for the signal recycling design in GEO 600. I have been having a lot of contact with both Both Mike Plissi and Harald Luck in GEO group and have obtained several engineering drawings and sketches of these suspensions.
This is not a complete set that could be sent to a vendor immediately, there are several reasons for this including the fact that the signal recycling suspension has not yet been installed in GEO. My priority is to work on these in order to obtain a complete set, in English, for our prototype.
Started discussions with Eoin Ellife in Glasgow to model the curvature of the blades we will use in the first prototype.
 

Mark Barton
This week I got the wire-bending parts of my model mostly debugged,
in the sense of producing plausible results that pass assorted
consistency checks. Unfortunately the fix for one bug that I found cause
the recalculation time to go up significantly (about an hour for
producing the matrix elastic constants). However that shouldn't be a
showstopper because the wire-bending terms make little difference to the
normal mode shapes and frequencies, so they can be left out of most runs
and only included to check the thermal noise. And there are several
points where more optimization could probably be done if necessary. I
also reverse-engineered the Bench program to extract the parameters it
uses and the thermal noise estimates it produces and am in the process of
doing detailed comparisons.
 

Q measurements
Helena Armandula
Two more thin substrates have been measured at Syracuse.
There is a new coating schedule that will be discussed with Mackowski. After his review, it will be implemented.
 

From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>

Charlotte
Study of metal diving boards samples.

Charlotte, Riccardo
Update on creep, please see report
LIGO-T-10123-00-R.
Gathering informations on glassy metals.

Riccardo
we submitted to NIM the actuator paper (after long delay), can find
under
LIGO-P010026-00-D.
Going Nov 4 to 14 to Italy to start Ultra Sound Milling Machine
construction at Faimond

Akiteru @ Hongo
Now we have a tower completed and get started with the Michelson
measurement in a few days.

Alessandro @ Pisa
Participating to the Fermi 100th anniversary celebration.
Happy birthday Enrico


For additional information about this report, contact sanders@ligo.caltech.edu