Weekly Report for Week Ending October 4, 2001


 Exec. Comm. Agenda
Highlights
LSC
Administration
Hanford Observatory
Livingston Observatory
MIT
Caltech
Detector
40 Meter
TNI
LASTI
Data Analysis
LIGO II/Adv. R&D
Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  October 8, 2001 will be:

 (Meeting time: 10:30 am Pacific Time)

Open meeting 10:30 - 11:30

  1. Announcements
  2. LSC Issues (Weiss)
  3. Comments on Weekly Report
  4. WBS 1 LIGO I Construction (Lindquist)
  5. WBS 2 LIGO Lab Operations
  6. WBS 3 and 4  Advanced R&D and LIGO II (Sanders)
Executive Committee only 11:30 - noon   Topics:
 

Special Items:


Special Announcements:


Weekly Report Highlights

LLO 4K achieves full recycled lock for 10 second stretches!

...and more....

...and at LHO, the 4K arm...


LSC Issues (Weiss)


No report


LIGO I Construction/LIGO Laboratory Administration (Lindquist)


No report.


LIGO Hanford Observatory (LHO) Operations (Raab)


General Items:
--------------
(F. Raab)
 

It appears 2K laser and digital suspensions are behaving better. Operators are attempting more challenging projects in support of commissioning. Most of these items are reported elsewhere. A new addition to operations staff is Cherl Vorvick, now in her second week at LHO. Cheryl ha her BS in physics from UW and will soon get her masters in EE from WSU.
 


LIGO Livingston Observatory (LLO) Operations (Coles)


Detector: Prepared for full interferometer locking by setting power levels on all
beam sensing tables for high power. After a few days of measuring the
optical/electronic properties of the separate parts of the IFO we put
these parameters into the lock acquisition program and late on Monday and
Tuesday observed the first flashes of full interferometer locking! The
system would occasionally lock for up to 10 seconds at power levels of
100x more than single arm levels and a few brief moments of build up as
high as 350x.(all)
 

Optics and Installation: Rus and I met with the representative of
Metropolitan Electronics, the vendor installing the Laser Safety Interlock
system as well as the new security cameras.  An installation schedule was
agreed upon wherein the system will be completely installed by Oct 26, and
programming and system shakedown should be completed 2 weeks following that.
Worked with an additional manufacturer to obtain an additional bid for the
installation of an acoustic enclosure surrounding our PSL.  The new
periscope is expected back from the anodizer this afternoon, and will be
installed tomorrow.  (Jonathan Kern)

CDS: After Rolf's visit and changes to DAQ system, I have been updating our CDS
Web-page especially the Redbook showing the new changes. We are also battling our
GPS receiver problems trying to locate the failed part. Made changes to the asc
database to limit the ETM's pitch and yaw bias to -1.0 and +1.0. These changes
were done to protect the super duper controllers from tripping out. Checking on
RDS not seeing the test points to record. (Chethan)

GC: We have ordered two additional Mathematica licenses, and are
checking to see which of our current licenses need to be
upgraded. (TOM)

LDAS: Attempted to flash the replaced hard drive in the Sun T3 with the
current firmware.  This failed and I am working with Sun on a solution.
The tape library that was sent in to cybernetics has come back and will
be tested to make sure it is functional.  Added the /etc/ldasname file
to all of the LDAS machines at LLO.  Big Brother is now up and running
at Hanford, Livingston, and ldas-sw. (Shannon)


Detector/Technical Support (Whitcomb, Coyne)


 
Installation& Commissioning:
Hanford
Livingston
Other Science/EngineeringActivities:
Design/Analysis/Fab
Issues/Concerns
See also the Installation web page

1.1 LHO INSTALLATION & COMMISSIONING

2km Commissioning

Rick Savage, Paul Schwinberg, Mark Guenther, Doug Cook, Dick Gustafson, Stan Whitcomb
The problem with the frequency jumps in the 2 km laser may have been tracked down (we hope).  The Lightwave documentation tells us in the fine print what should be gounded and what shouldn't, but we found that one of our EPICS channels violated their instructions. Disconnecting this channel stopped the jumps, though the result is still preliminary.

Betsy and Ski measured a whole raft of noise spectra for the suspension coil drivers in various configurations.  The nois elevel for an inactive coil driver (no damping, no ASC or LSC inputs enabled was a bit more than 10 nV/rtHz at the coil monitor point.  The ASC inputs have a large n x 16 Hz comb, an artifact of the ASC Pentek.  The ASC input filter would help this a lot.

4km Commissioning

Corey Gray, Richard McCarthy, Josh Myers, Mike Landry, Bill Butler, Fred Raab, Betsy Weaver, Mark Lubinski, Robert Schofield, Stan Whitcomb
The main effort has been on trying to lock the X arm of the 4 km interferometer.  In the process, we have uncovered a small problem or two (the most amusing of which, though not perhaps the most important, is that the ETMX control signal goes to the Y end station...).  We have fixed or finessed  these and finally obtained real fringe stretching (or as some would say, "It locks for 0.3 seconds!")  Diagonalizing the position drives, hunting for the reason why it doesn't lock for longer.  The main suspect is excess length noise in the modecleaner, translating to excess frequency noise in the transmitted light.  Why?  We don't know yet.

Mike and his vrew are commissioning the WFS for the modecleaner with the now usual result that the input and Output matrices look totally screwy, but work to align it.  They will try it again, but having done a pretty careful job, they are bound to get the same basic answer.

Cabling up the various ISC tables. WFS picomotors cabled and tested.

1.2LLO INSTALLATION & COMMISSIONING

4 km Commissioning

Rai Weiss reporting
The interferometer was locked in the full design configuration for short periods upto 10 seconds duration and with a maximum power buildup of about 300. The input power was 1 watt. This is a significant event even though much work remains to extend the lock duration and to bring the power buildup to the design value. We now have the operating parameters with which to begin iterations.

Higher current test mass controllers were used in the end test masses during the full interferometer locking. The same controllers were first used on the input and end test masses of the y arm cavity. The single cavity lock is significantly more robust than before and the lock acquisition occurs typically within a second. We have not yet established the statistics for lock loss during typical daytime operation. It is clearly going to be better. We are going forward with converting two more controllers to high current operation and hope to finish their installation next week.

Misc.

Szabi Marka
I participated in the runs aimed to lock the LLO recycled Fabry Perot/ Michelson.

I installed the alarm manager and alarm handler in LLO and made LLO the configuration files. We are working with the subsystem experts to refine and improve the guidance information.

I installed the new Flash memory disk in the Q4128 datalogger in LLO, it works very well. We are testing the coil magnetometer performance with Shourov.

I was finishing up the Amaldi and Snowmass conference proceedings.

I produced the PCB design for microcontroller/driver controlling the shape memory actuators used on the STS-2 sensor of the active seismic isolation system. I am in the process to build a prototype.

2.0 OtherEngineering and Scientific Activities

2.1 Design/Analysis/Fab

Modeling

Erika D'Ambrosio
I started some calculations to design a flat top beam on a resonator as small as the LASTI facility allows. I am investigating the configuration with a flat mirror as input and a reshaped mirror at the end. For an appropriate choice of the parameters I could construct a flat top beam that has a flat intensity on both the mirrors although the wave front is obviously very different, since on the input mirror it is completely flat and on the end mirror it has a special form similar to the one found out in the design for the Ligo Fabry-Perot arms.

IOO PERISCOPE

Mike Smith, Ken Mailand
The prototype IO periscope is at LLO awaiting installation and testing.
Final working drawings for the revised production cross braces are complete. All components for 3 more periscopes are being fabricated, as well as holding fixtures for the welding operation. The fabricated parts are expected to be completed by 10/8. There are four outside vendors involved in the assembly and finishing of the periscope: Welder, anodizer, post insertion of pem nuts, and foot grinding. If there are no schedule conflicts between the vendors, we expect to have at least 2 periscopes completed by 10/19.

PSL

Peter King,
REO have finished coating the new pre-modecleaner mirrors.  Of the 28 super-polished substrates supplied, only 20 were coated because of scratches and pits in the other 8 substrates.  These substrates were sourced from Mindrum Precision.

NPRO S/N #170 was shipped off to LHO in case a decision is made to replace the master oscillator out of the 10-W laser.

Lee Cardenas

Rick Karwoski, Paul Russel
All efforts currently focused on tightening up the PSL electronics build-test cycle.  Test procedures are being worked on all PSL boards.

Sander Liu
In the process of writing the Acceptance Test Procedure for the FSS Servo Board.

LSC

Mike Zucker
Working on repair and characterization of RF photodetectors.

Rich Abbot, Mohana Mageswaran, Flavio Nocera

Mohana Mageswaran
I did some research on good temperature controllers. And I am testing my prototype circuit of the Laser Driver and the Temperature controller along with our new Crystalaser at the Lauritson lab. And the test has been going well. Soon I will be start designing a board which will serve as our new laser driver. I am also writing up the test procedures which some of the modules do not have.

Data Acquisition

Rolf Bork
Believe Hongyu has fixed problem in dataviewer V5 having to do with 256Hz channels; Barker is testing at LHO.

Worked with Wooley at LLO on diagnosing DAQ reset problems encountered over last weekend; Problem was traced to faulty single-mode to multi-mode fiber optic converter in the X end station link

General CDS

Rolf Bork
Lori has written code so that we can begin testing some of our Pentek DAC outputs here at Caltech. We want to recreate tests begun by Gustafson at LHO which indicate some DAC outputs are better than others.

Have teleconference today with VMIC regarding their new VME processor boards (Dual 1.2 GHz Pentium) and new reflected memory boards (2Gbit/sec).  We also want to discuss possibility of faster VME I/O design ie improve performance of single VME read/writes.

New ADC/DAC modules

Jay Heefner
It has been decided to hold off on the development of a better ADC module for LIGO. This decision was made after discussion with some of the respondents to the RFP concerning some of the requirements that could not be met at this time. In lieu of the improved ADC we have begun to collect the requirements for a DAC module. The plan at this time is to send these requirements out to vendors as an RFI.

Digital Suspension

Jay Heefner
All modules needed for the LHO 2K and LLO 4K digital suspension systems are complete and ready for installation.

LLO Seismic Feed Forward

Jay Heefner
All hardware is installed and ready for test. Documentation has been updated and submitted to DCC.

Rolf Bork
Continued on code to allow changing filter coeffs on the fly and added excitation point capabilities; should be complete in next day or two.

Diagnostics

Daniel Sigg
Worked on the event analysis tool. Most of the software is now written (even so not tested); still work needed in the input/output and the plotting sections.

Data Monitoring Tool

John Zweizig
This week I finished the make files needed to build the new DMT software version from the consolidated gds cvs repository. The new make files and all the current version of the source code were commited to the repository. I started trying to build the DMT software from the new repository on the linux node alvar. As can be expected the several incompatibilities were found between the Solaris and Linux operating systems which I am now in the process of remedying.
 


40 Meter Interferometer (Weinstein)




Thermal Noise Interferometer (Libbrecht)


No report


LASTI (Zucker)


LASTI (Bayer, Fritschel, Harry, MacInnis, Mason, Miller, Mittleman,
Ottaway, Phinney, Rollins, Shoemaker, Zucker)
=======================================================================

Infrastructure:

The seismic support piers have been grouted and the
contractor has cleaned up and cleared off. The grout is expected to
attain sufficient strength by 10/10 to undertake the planned test
of free pier eigenfrequencies, requested by the hydraulic actuator
design team.

Due to the high bids received on the mezzanine structure for SEI/SUS
staging, we've decided to descope the weight capacity and do the design
in-house. The resulting delay will be accommodated by temporarily relocating
other equipment so we can use occupied floorspace for pending
assembly work; the mezzanine will still easily be in place well before
it is needed for adLIGO seismic installation (there's sufficient float
in the schedule).

We palletized and shipped a load of BSC SEI assembly equipment loaned
by LLO back to Livingston, to arrive Monday or so.  This frees up
some floor space in our high bay.

Hydraulic actuators:

Ken held a review of the mechanical design for
the hydraulic actuator supports and articulations.  The design was
received well.  Two issues raised were the capacity for coarse
adjustment (relatively easy to handle) and a subtle problem of torsion
due to spring unwinding (as of this morning Ken had a novel idea
which should fix this).

Joshua has begun assembling the hydraulic pump/accumulator/regulator
test skid in the machine shop.  After much deliberation we elected to
go with stainless Swagelock piping for the prototype for ease of
assembly.  We may later transition to VCR or brazed connections for
production.

CDS/DAQ/GDS:

Our GDS RAID disk tower was shipped back to the manufacturer.  Also two
failed drives from our other (CDS) RAID were returned to their
respective manufacturers. We set up two more Sun Blade 100 operator
consoles on the CDS network to support PSL commissioning and an
additional control room node.

PSL:

The PMC servo electronics were repaired and the PMC is again working.
The 10W MOPA arrived in good order from Caltech.  We expect our enhanced
safety enclosure will be in house shortly, at which time we'll
place the PSL table into final position and cut over
from the test NPRO to the MOPA.


Data Analysis and Computing (Lazzarini)


Simulation and Modeling (Bhawal)
 

Weekly Simulation Physics Meeting
------------------
Luca talked about his preliminary work on characterization of actuators and
sensors. Virginio gave an update of mechanical simulation and validation of
MSE code and Mark Barton showed us the Mathematica model for the advanced
suspension system and various modes. Biplab reported about mode mismatch
simulation and finally Erika gave a presentation of her study of flat-top
beam using FFT code.

Mode mismatch
-------------
(Biplab) Han2k and equivalent high finesse 2-mir cavity are properly locked
and beams at various ports are looked at. TEM00 carrier power inside
IFO/cavity is lower than the analytical expectation for higher values of
longitudinal shift in beam position. However, TEM20 & 02 power and sideband
power (in all modes) in recycling cavity matches well with analytical result.

Alfi
----
(Bruce)
- Working on port and connection widgets for the Alfi5 display.

(Melody)
- Continued working on displaying member nodes in alfi5.
 

LIGO Data Analysis System
 

Software Systems (Blackburn)

  Began implementing the one sided power spectrum estimator
  within the dataConditionAPI to supplement the existing two
  sided PSD.

  Began developing a translator library to prepare data products
  generated in the dataCondtionAPI for casting into process
  frames in the frameAPI.

  Tested the new functionality in the dataConditionAPI to pass
  through arbitrary SQL results from the LDAS database for use
  in search codes running under the wrapperAPI. Initial tests
  indicated an issue which is being fixed.

  Updated some of cmonClient's documentation: status pages.
  Minor fixes to cmonClient.

  Working on metadataAPI issues: fixed problem with dbUniqueIds
  not writing out correct foreign key uniqueId cols.
  Had to bypass sngl_transdata and coinc_sngl since these
  are special cases. Created tk script dbDsnames to
  prompt user for database user name and passwords to
  create a customized LDASdsnames.ini in /ldas_outgoing.

  Fixed metadata tests to run on ldas-dev due to
  use of new var LDAS_SYSTEM for domainname: getMetaData and
  insertion test; also ran datasock test on dataserver,
  sunbox1, controlmon and linuxbox1 to completion for
  testing ilwd binary transfers.

  Fixed database utilities db2utils, dbDsnames,
  and dbUniqueIds to use new var for domainname.

  Installed custom LDASdsnames.ini and dbUniqueId files at
  sites after ldas mirroed software was copied to each site..
 

  Created a new scratch test database, ldas_tst, at the sites.

  Extended dataConditonAPI to handle arbitrary sql
  derived inputs and format them for use by the
  wrapper API.

  Added support to frame API for all simulated data
  types and attributes.

  Refactored the base 64 tcl code to meet the
  requirements of rfc #2045 fixing a bug reported
  during the standalone workstation installation
  of LDAS.

  Tested newly installed *current* development version
  of LDAS at Hanford, Livingston, and MIT.

  Fix for 'finalizing' message introduced a bug when
  'CREATE_DUMMY_MDD' and 'CREATE_DUMMY_STATE' debug flags are
  enabled. Fixed the problem.

  Working on resource file for the wrapperAPI. This file
  includes all ex-configure flags used for debugging. Changing
  the code to use these resource file flags instead of
  preprocessor macros.

  Tried to build LAL with new libtool and automake. This fails,
  but Milwaukee is working on the necessary changes.

  Worked on improving LDAS build process. Modified config and make code to
  work with new versions of libtool and automake and eliminate the need to
  set LD_LIBRARY_PATH environment variable.

  Worked with Sergei Klimenko (briefly) to fix his LDAS build problems on
  his dual-cpu computer. Uncovered our own documentation bug: required
  binutils version should be 11.2 and not 10. Fixed the document.
 

  Tested LDAS builds exhaustively under the new libtool and automake.

  LDAS is now running on a single LINUX workstation (all APIs) here at
  Caltech. A sample dataPipeline ran to completion including the
  insertion of search code results into the DB2 database on that
  single workstation.
 

Hardware Systems (Anderson)

Caltech
-------
(Dan Kozak)

Did some HPSS stuff (repacking tapes in the 3590 classes, setting up
users on johnny to use HSI).

Obtained 3 quotes for the first order of 500 LIGO archive tapes (STK9940).

Worked on QFS benchmarking in the wake of Sun's visit.

(Al Wilson)

Cleaned up after realizing that Sun sent a replacement T3 drive with
old firmware on it.

Upgraded m71 to Linux-2.4.10 kernel to evaluate stability.

Installed video switch in the 6th floor conference room to allow for
more convenient use of the projector system.

Converted and rebooted the ldas-dev system to use the new /etc/ldasname
identification scheme instead of the old NIS domainname.

Fixed disk drive problem in m27.

(Stuart Anderson)

Investigated IEEE standards for optical Gigabit Ethernet and Fiber Channel
and found that 50um multi-mode fiber should be long enough for most
of our needs. This contradicts the conclusion from earlier this year
that we would need to use more expensive 9um single-mode fiber to get
past the limitations of the commonly installed 62.5um multi-mode fiber.

Continuing to work on the configuration for the next LDAS procurement.

Cleaned up the LIGO Data Computing Group software distribution (/ldcg)
to reduce it from 609 to 487 packages.

MIT
---
(Keith Bayer)
 
made ldasname change
read greg's backup script (will install)

Livingston
----------
(Shannon Roddy)

Attempted to flash the replaced hard drive in the Sun T3 with the
current firmware.  This failed and I am working with Sun on a solution.
The tape library that was sent in to cybernetics has come back and will
be tested to make sure it is functional.  Added the /etc/ldasname file
to all of the LDAS machines at LLO.  Big Brother is now up and running
at Hanford, Livingston, and ldas-sw.

Hanford
-------
(Greg Mendell)

Worked on incorporating fssnap into backups on Sun machines on the
ldas network.  The Solaris 8 fssnap command takes a snapshot of a file
system.  The snapshot version of the file system is held read only, and
can be safely backed up, while I/O continues on the original file
system.  However, while fssnap is running, output is suspended, and
files written to during this time will appear incomplete in the
snapshot.  (The good news is that files are not corrupted; i.e., no
dangling ionode pointers occur.)   The time it takes fssnap to run is,
e.g., 5 sec on a 5 GB file system that was 16% used.
 

Data Analysis Activities
 

(Greg Mendell)
1) Worked on knownpulsardemod DSO code.  A few minor bugs were fixed in
the code.  Most of the time has been spent
updating lal, lalwrapper, and ldas to use wrapperInterfaceDatatypes.h,
automake-1.5, and libtool-1.4.2.
 

(Peter Shawhan)
  I have been working on "hardware" signal injection using the GDS
excitation
  channels.  Daniel and I worked out a scheme in which a client program
  streams data to the front end "arbitrary waveform generator" (awg) in
blocks
  using RPC; he made the necessary changes to the awg API functions and to
the
  front-end code, and I created a client-side library which provides a
simple
  interface.  I also made a client program which reads waveform data from a
  file and injects it; I tested this with a NS-NS inspiral chirp, and saw it
  (with dataviewer) appear on the excitation channel I had specified.

  I also got a copy of Matlab for Linux (under the regular Caltech site
  license) and used it to build the MEX-files in LIGOtools (frextract,
  frgetvect, mkframe, readMeta) which had previously only been built for
  Solaris.  I released new Linux versions of the Fr and dataflow packages
  which include these MEX-files.

  (Philip Charlton)
  Began working on the code to analyse template overlap which will
  compare the FCT with conventional template methods for inspiral
  searches.
 

(Lazzarini)
I attended a weekend meeting (29, 30 Sept) at Virgo's Cascina site to discuss GWIC activities on network analysis. GEO was represented by Sathyaprakash. All Italian bar groups were also represented.
The 2-day meeting focused on status of various project-level activities. Benoit and I gave a review of what has been accomplished at LIGO; similar status was provided by Virgo. I had invited Ewa Deelman, from USC/Info Sci Inst, who is working on GriPhyN-LIGO interfaces, to attend, since she was already in Italy for a GridForum and Itlaian GridLab meeting in Rome. She gave an excellent "what is grid computing and how canit be applied toLIGO/Virgo" talk that was well received by Virgo. We agreed to work for a next phase of implementation that would include the gridftp package for exchanging data. GEO has made a commitment to be ready "soon" to be included in the  data exchanges. They will replicate what we are already doing in order to save effort.
 

I also learned that GEO is going to perform an evaluation of LDAS versus their currently planned software implementation to see the relative performance/robustness merits of the two options.
 

A set of minutes will be drafted using extensive notes taken by Sathyaprakash during the meeting.
 

General Computing (Wallace)

MIT:
(Keith)
-Spec'd out laptop for new postdoc
-Built Solaris SB100 for gc
-Started investigating modem equipment
-LASTI work:
 built two Solaris SB100 nodes for CDS network
 built accounts and nfs mounts
 ran wires
-Investigating vnc
-Investigating laptop to projector settings

Livingston:
(Tom)
-Have ordered two additional Mathematica licenses, and are
checking to see which of our current licenses need to be
upgraded.
-Second T1 line is installed and working.

Hanford:
Unable to report this week.

CIT:
(Mick & Wendy)
-Finished up some documentation and started school.

(Barbara)
- Sent a revised version of the costbook detail report for review.  This
version displays all WBS definitions in the hierarchy and has placeholders
for all activity sheets.
- Created query to update cost codes for costbook line items and researched
the exceptions.  Investigated impact of new discipline codes.
- Fixed overnight jobs on pherkab to point to the D drive.
- Added photos to About LIGO web pages.
- Reworked the LDAS maps for UWM.
- Web site changes for meeting attendees, fellowships, seminar, many mou
attachments and reports.
- Wrote some documentation and did some associated housekeeping.

(Lisa)
- Figured out what needed to be done to get SunPCI 2.x installed and running on
solaris 8.  There were persistent core dumps that required a kernal patch and
mouse driver errors that are solved with ver 2.2.2 of the sunpci software.
- Did extensive testing of the backup system.  I am still looking into some
drive incompatibility questions between the drives on our robot and an external
stand alone drive.  I tried to get the remote user feature of solstice backup to
work as well.  The software said it would do its thing but wouldn't restore any
files.  The answer is that restores need to be initiated from the client rather
than from a remote server.
- Helped get the rack mount servers into the rack.
- Building rana as a development web server.
- Worked on some miscellaneous printer problems and user account stuff.

(Mike)
-Installed two rack mounted servers with Larry & Lisa.
-Complete reload and upgrading hardware and all General
Computing software.
-Sub-basement cleaned up by un-installing unnecessary software that was
slowing down the performance of PC to make workable for engineers and students.
-Loaded 2Ghz PC for a new visitor this included all General computing
software and engineering software.
-Upgraded ANSYS license server to 5.7.1 and upgrade the 5.7.1 software on
users workstations.
-Millikan conference room PC, having problems booting after troubleshooting
turns out slaved 6 GIG  hard drive is dead, restored win98 on the primary 10GIG
hard drive from a ghost image with different partitioning scheme to make this
drive dual bootable to win98 and LINUX.
-Onsite user and phone support, that included fixing minor software glitches
and hardware issues.

(Larry)
-Worked a number of procurements. Put through the maintenance contracts on SUN
equipment and Hummingbird s/w. Placed equipment orders for the 40M and LDAS. The
big order for the Foundry system went through and the equipment has already
started showing up.
-Spent a little time fixing/setting up some of the web locations dealing with
the financial side of the house. Also, assisted a number of other people working
on different documentation issues.
-Resolved some disk space problems. We now have users generating large data
files which required more disk purchases, which have been done. To accommodate
the users we have moved a few directories around until we get the new disk
systems put on-line.
-Worked a number of e-mail issues. Mainly, spam complaints. Vendors and the
companies providing the e-mail services have been contacted. Along the same line
there is still work being done to modify the LIGO-CIT e-mail services to allow
more filtering and virus checking.


LIGO II/Advanced R&D (Sanders)


From: Helena Armandula <ahelena@ligo.caltech.edu>

Silicate Bonding
Bonded 2 prisms (ears) of different design on a large fused silica substrate.
After attaching fibers to them, the ears will be loaded to evaluate their performance under stress.

"Q" measurements
Received 4 re-polished thin substrates from Wave Precision.
2 of them went to Gregg Harry (MIT) and the other 2 to Steve Penn (Syracuse) for "Q" measurements.
I expect to receive 2 measured thin substrates shortly. They will be sent to J.M.Mackowski for processing.

From Mark Barton:
 

This week I continued work on my quad suspension model. I got working some old code in my framework for calculating matrices of damping coefficients. (I hadn't exercised it for a while so it had gotten out of date.) I also redid the expressions for the potential energy of the wires to include bending elasticity. The new version is based on the full solution for a bent beam, reduced to a power series in the angles at the end of the wires, assumed small.
 

From Rich Abbott:
 

Began stuffing of prototype voice coil driver. There are still some parts that have not come in, but within a week the circuit will be operational to supply the +/- 10 amp drive required by the coils.
 


For additional information about this report, contact sanders@ligo.caltech.edu