|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The LIGO Executive Committee Agenda for Monday October 8, 2001 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
Special Items:
LLO 4K achieves full recycled lock for 10 second stretches!
No report
No report.
General Items:
--------------
(F. Raab)
It appears 2K laser and digital suspensions are behaving better. Operators
are attempting more challenging projects in support of commissioning. Most
of these items are reported elsewhere. A new addition
to operations staff is Cherl Vorvick, now in her second week at
LHO. Cheryl ha her BS in physics from UW and will soon get her masters
in EE from WSU.
Detector: Prepared for full interferometer locking
by setting power levels on all
beam sensing tables for high power. After a few days of measuring the
optical/electronic properties of the separate parts of the IFO we put
these parameters into the lock acquisition
program and late on Monday and
Tuesday observed the first flashes of full
interferometer locking! The
system would occasionally lock for up to 10
seconds at power levels of
100x more than single arm levels and a few
brief moments of build up as
high as 350x.(all)
Optics and Installation: Rus and I met with the representative of
Metropolitan Electronics, the vendor installing the Laser Safety Interlock
system as well as the new security cameras. An installation schedule
was
agreed upon wherein the system will be completely installed by Oct
26, and
programming and system shakedown should be completed 2 weeks following
that.
Worked with an additional manufacturer to obtain an additional bid
for the
installation of an acoustic enclosure surrounding our PSL. The
new
periscope is expected back from the anodizer this afternoon, and will
be
installed tomorrow. (Jonathan Kern)
CDS: After Rolf's visit and changes to DAQ system, I have been updating
our CDS
Web-page especially the Redbook showing the new changes. We are also
battling our
GPS receiver problems trying to locate the failed part. Made changes
to the asc
database to limit the ETM's pitch and yaw bias to -1.0 and +1.0. These
changes
were done to protect the super duper controllers from tripping out.
Checking on
RDS not seeing the test points to record. (Chethan)
GC: We have ordered two additional Mathematica licenses, and are
checking to see which of our current licenses need to be
upgraded. (TOM)
LDAS: Attempted to flash the replaced hard drive in the Sun T3 with
the
current firmware. This failed and I am working with Sun on a
solution.
The tape library that was sent in to cybernetics has come back and
will
be tested to make sure it is functional. Added the /etc/ldasname
file
to all of the LDAS machines at LLO. Big Brother is now up and
running
at Hanford, Livingston, and ldas-sw. (Shannon)
| Installation&
Commissioning:
Livingston |
Other Science/EngineeringActivities:
Issues/Concerns |
See also the Installation web page
Betsy and Ski measured a whole raft of noise spectra for the suspension coil drivers in various configurations. The nois elevel for an inactive coil driver (no damping, no ASC or LSC inputs enabled was a bit more than 10 nV/rtHz at the coil monitor point. The ASC inputs have a large n x 16 Hz comb, an artifact of the ASC Pentek. The ASC input filter would help this a lot.
Mike and his vrew are commissioning the WFS for the modecleaner with the now usual result that the input and Output matrices look totally screwy, but work to align it. They will try it again, but having done a pretty careful job, they are bound to get the same basic answer.
Cabling up the various ISC tables. WFS picomotors cabled and tested.
Higher current test mass controllers were used in the end test masses during the full interferometer locking. The same controllers were first used on the input and end test masses of the y arm cavity. The single cavity lock is significantly more robust than before and the lock acquisition occurs typically within a second. We have not yet established the statistics for lock loss during typical daytime operation. It is clearly going to be better. We are going forward with converting two more controllers to high current operation and hope to finish their installation next week.
I installed the alarm manager and alarm handler in LLO and made LLO the configuration files. We are working with the subsystem experts to refine and improve the guidance information.
I installed the new Flash memory disk in the Q4128 datalogger in LLO, it works very well. We are testing the coil magnetometer performance with Shourov.
I was finishing up the Amaldi and Snowmass conference proceedings.
I produced the PCB design for microcontroller/driver controlling the shape memory actuators used on the STS-2 sensor of the active seismic isolation system. I am in the process to build a prototype.
NPRO S/N #170 was shipped off to LHO in case a decision is made to replace the master oscillator out of the 10-W laser.
Lee Cardenas
Sander Liu
In the process of writing the Acceptance Test Procedure for the FSS
Servo Board.
Rich Abbot, Mohana Mageswaran, Flavio Nocera
Worked with Wooley at LLO on diagnosing DAQ reset problems encountered over last weekend; Problem was traced to faulty single-mode to multi-mode fiber optic converter in the X end station link
Have teleconference today with VMIC regarding their new VME processor boards (Dual 1.2 GHz Pentium) and new reflected memory boards (2Gbit/sec). We also want to discuss possibility of faster VME I/O design ie improve performance of single VME read/writes.
Rolf Bork
Continued on code to allow changing filter coeffs on the fly and added
excitation point capabilities; should be complete in next day or two.
No report
LASTI (Bayer, Fritschel, Harry, MacInnis, Mason, Miller, Mittleman,
Ottaway, Phinney, Rollins, Shoemaker, Zucker)
=======================================================================
Infrastructure:
The seismic support piers have been grouted and the
contractor has cleaned up and cleared off. The grout is expected to
attain sufficient strength by 10/10 to undertake the planned test
of free pier eigenfrequencies, requested by the hydraulic actuator
design team.
Due to the high bids received on the mezzanine structure for SEI/SUS
staging, we've decided to descope the weight capacity and do the design
in-house. The resulting delay will be accommodated by temporarily relocating
other equipment so we can use occupied floorspace for pending
assembly work; the mezzanine will still easily be in place well before
it is needed for adLIGO seismic installation (there's sufficient float
in the schedule).
We palletized and shipped a load of BSC SEI assembly equipment loaned
by LLO back to Livingston, to arrive Monday or so. This frees
up
some floor space in our high bay.
Hydraulic actuators:
Ken held a review of the mechanical design for
the hydraulic actuator supports and articulations. The design
was
received well. Two issues raised were the capacity for coarse
adjustment (relatively easy to handle) and a subtle problem of torsion
due to spring unwinding (as of this morning Ken had a novel idea
which should fix this).
Joshua has begun assembling the hydraulic pump/accumulator/regulator
test skid in the machine shop. After much deliberation we elected
to
go with stainless Swagelock piping for the prototype for ease of
assembly. We may later transition to VCR or brazed connections
for
production.
CDS/DAQ/GDS:
Our GDS RAID disk tower was shipped back to the manufacturer.
Also two
failed drives from our other (CDS) RAID were returned to their
respective manufacturers. We set up two more Sun Blade 100 operator
consoles on the CDS network to support PSL commissioning and an
additional control room node.
PSL:
The PMC servo electronics were repaired and the PMC is again working.
The 10W MOPA arrived in good order from Caltech. We expect our
enhanced
safety enclosure will be in house shortly, at which time we'll
place the PSL table into final position and cut over
from the test NPRO to the MOPA.
Simulation and Modeling (Bhawal)
Weekly Simulation Physics Meeting
------------------
Luca talked about his preliminary work on characterization of actuators
and
sensors. Virginio gave an update of mechanical simulation and validation
of
MSE code and Mark Barton showed us the Mathematica model for the advanced
suspension system and various modes. Biplab reported about mode mismatch
simulation and finally Erika gave a presentation of her study of flat-top
beam using FFT code.
Mode mismatch
-------------
(Biplab) Han2k and equivalent high finesse 2-mir cavity are properly
locked
and beams at various ports are looked at. TEM00 carrier power inside
IFO/cavity is lower than the analytical expectation for higher values
of
longitudinal shift in beam position. However, TEM20 & 02 power
and sideband
power (in all modes) in recycling cavity matches well with analytical
result.
Alfi
----
(Bruce)
- Working on port and connection widgets for the Alfi5 display.
(Melody)
- Continued working on displaying member nodes in alfi5.
LIGO Data Analysis System
Software Systems (Blackburn)
Began implementing the one sided power spectrum estimator
within the dataConditionAPI to supplement the existing two
sided PSD.
Began developing a translator library to prepare data products
generated in the dataCondtionAPI for casting into process
frames in the frameAPI.
Tested the new functionality in the dataConditionAPI to pass
through arbitrary SQL results from the LDAS database for use
in search codes running under the wrapperAPI. Initial tests
indicated an issue which is being fixed.
Updated some of cmonClient's documentation: status pages.
Minor fixes to cmonClient.
Working on metadataAPI issues: fixed problem with dbUniqueIds
not writing out correct foreign key uniqueId cols.
Had to bypass sngl_transdata and coinc_sngl since these
are special cases. Created tk script dbDsnames to
prompt user for database user name and passwords to
create a customized LDASdsnames.ini in /ldas_outgoing.
Fixed metadata tests to run on ldas-dev due to
use of new var LDAS_SYSTEM for domainname: getMetaData and
insertion test; also ran datasock test on dataserver,
sunbox1, controlmon and linuxbox1 to completion for
testing ilwd binary transfers.
Fixed database utilities db2utils, dbDsnames,
and dbUniqueIds to use new var for domainname.
Installed custom LDASdsnames.ini and dbUniqueId files at
sites after ldas mirroed software was copied to each site..
Created a new scratch test database, ldas_tst, at the sites.
Extended dataConditonAPI to handle arbitrary sql
derived inputs and format them for use by the
wrapper API.
Added support to frame API for all simulated data
types and attributes.
Refactored the base 64 tcl code to meet the
requirements of rfc #2045 fixing a bug reported
during the standalone workstation installation
of LDAS.
Tested newly installed *current* development version
of LDAS at Hanford, Livingston, and MIT.
Fix for 'finalizing' message introduced a bug when
'CREATE_DUMMY_MDD' and 'CREATE_DUMMY_STATE' debug flags are
enabled. Fixed the problem.
Working on resource file for the wrapperAPI. This file
includes all ex-configure flags used for debugging. Changing
the code to use these resource file flags instead of
preprocessor macros.
Tried to build LAL with new libtool and automake. This fails,
but Milwaukee is working on the necessary changes.
Worked on improving LDAS build process. Modified config and make
code to
work with new versions of libtool and automake and eliminate
the need to
set LD_LIBRARY_PATH environment variable.
Worked with Sergei Klimenko (briefly) to fix his LDAS build problems
on
his dual-cpu computer. Uncovered our own documentation bug:
required
binutils version should be 11.2 and not 10. Fixed the document.
Tested LDAS builds exhaustively under the new libtool and automake.
LDAS is now running on a single LINUX workstation (all APIs)
here at
Caltech. A sample dataPipeline ran to completion including the
insertion of search code results into the DB2 database on that
single workstation.
Hardware Systems (Anderson)
Caltech
-------
(Dan Kozak)
Did some HPSS stuff (repacking tapes in the 3590 classes, setting up
users on johnny to use HSI).
Obtained 3 quotes for the first order of 500 LIGO archive tapes (STK9940).
Worked on QFS benchmarking in the wake of Sun's visit.
(Al Wilson)
Cleaned up after realizing that Sun sent a replacement T3 drive with
old firmware on it.
Upgraded m71 to Linux-2.4.10 kernel to evaluate stability.
Installed video switch in the 6th floor conference room to allow for
more convenient use of the projector system.
Converted and rebooted the ldas-dev system to use the new /etc/ldasname
identification scheme instead of the old NIS domainname.
Fixed disk drive problem in m27.
(Stuart Anderson)
Investigated IEEE standards for optical Gigabit Ethernet and Fiber Channel
and found that 50um multi-mode fiber should be long enough for most
of our needs. This contradicts the conclusion from earlier this year
that we would need to use more expensive 9um single-mode fiber to get
past the limitations of the commonly installed 62.5um multi-mode fiber.
Continuing to work on the configuration for the next LDAS procurement.
Cleaned up the LIGO Data Computing Group software distribution (/ldcg)
to reduce it from 609 to 487 packages.
MIT
---
(Keith Bayer)
made ldasname change
read greg's backup script (will install)
Livingston
----------
(Shannon Roddy)
Attempted to flash the replaced hard drive in the Sun T3 with the
current firmware. This failed and I am working with Sun on a
solution.
The tape library that was sent in to cybernetics has come back and
will
be tested to make sure it is functional. Added the /etc/ldasname
file
to all of the LDAS machines at LLO. Big Brother is now up and
running
at Hanford, Livingston, and ldas-sw.
Hanford
-------
(Greg Mendell)
Worked on incorporating fssnap into backups on Sun machines on the
ldas network. The Solaris 8 fssnap command takes a snapshot of
a file
system. The snapshot version of the file system is held read
only, and
can be safely backed up, while I/O continues on the original file
system. However, while fssnap is running, output is suspended,
and
files written to during this time will appear incomplete in the
snapshot. (The good news is that files are not corrupted; i.e.,
no
dangling ionode pointers occur.) The time it takes fssnap
to run is,
e.g., 5 sec on a 5 GB file system that was 16% used.
Data Analysis Activities
(Greg Mendell)
1) Worked on knownpulsardemod DSO code. A few minor bugs were
fixed in
the code. Most of the time has been spent
updating lal, lalwrapper, and ldas to use wrapperInterfaceDatatypes.h,
automake-1.5, and libtool-1.4.2.
(Peter Shawhan)
I have been working on "hardware" signal injection using the
GDS
excitation
channels. Daniel and I worked out a scheme in which a
client program
streams data to the front end "arbitrary waveform generator"
(awg) in
blocks
using RPC; he made the necessary changes to the awg API functions
and to
the
front-end code, and I created a client-side library which provides
a
simple
interface. I also made a client program which reads waveform
data from a
file and injects it; I tested this with a NS-NS inspiral chirp,
and saw it
(with dataviewer) appear on the excitation channel I had specified.
I also got a copy of Matlab for Linux (under the regular Caltech
site
license) and used it to build the MEX-files in LIGOtools (frextract,
frgetvect, mkframe, readMeta) which had previously only been
built for
Solaris. I released new Linux versions of the Fr and dataflow
packages
which include these MEX-files.
(Philip Charlton)
Began working on the code to analyse template overlap which
will
compare the FCT with conventional template methods for inspiral
searches.
(Lazzarini)
I attended a weekend meeting (29, 30 Sept) at Virgo's Cascina site
to discuss GWIC activities on network analysis. GEO was represented by
Sathyaprakash. All Italian bar groups were also represented.
The 2-day meeting focused on status of various project-level activities.
Benoit and I gave a review of what has been accomplished at LIGO; similar
status was provided by Virgo. I had invited Ewa Deelman, from USC/Info
Sci Inst, who is working on GriPhyN-LIGO interfaces, to attend, since she
was already in Italy for a GridForum and Itlaian GridLab meeting in Rome.
She gave an excellent "what is grid computing and how canit be applied
toLIGO/Virgo" talk that was well received by Virgo. We agreed to work for
a next phase of implementation that would include the gridftp package for
exchanging data. GEO has made a commitment to be ready "soon" to be included
in the data exchanges. They will replicate what we are already doing
in order to save effort.
I also learned that GEO is going to perform an evaluation of LDAS versus
their currently planned software implementation to see the relative performance/robustness
merits of the two options.
A set of minutes will be drafted using extensive notes taken by Sathyaprakash
during the meeting.
General Computing (Wallace)
MIT:
(Keith)
-Spec'd out laptop for new postdoc
-Built Solaris SB100 for gc
-Started investigating modem equipment
-LASTI work:
built two Solaris SB100 nodes for CDS network
built accounts and nfs mounts
ran wires
-Investigating vnc
-Investigating laptop to projector settings
Livingston:
(Tom)
-Have ordered two additional Mathematica licenses, and are
checking to see which of our current licenses need to be
upgraded.
-Second T1 line is installed and working.
Hanford:
Unable to report this week.
CIT:
(Mick & Wendy)
-Finished up some documentation and started school.
(Barbara)
- Sent a revised version of the costbook detail report for review.
This
version displays all WBS definitions in the hierarchy and has placeholders
for all activity sheets.
- Created query to update cost codes for costbook line items and researched
the exceptions. Investigated impact of new discipline codes.
- Fixed overnight jobs on pherkab to point to the D drive.
- Added photos to About LIGO web pages.
- Reworked the LDAS maps for UWM.
- Web site changes for meeting attendees, fellowships, seminar, many
mou
attachments and reports.
- Wrote some documentation and did some associated housekeeping.
(Lisa)
- Figured out what needed to be done to get SunPCI 2.x installed and
running on
solaris 8. There were persistent core dumps that required a kernal
patch and
mouse driver errors that are solved with ver 2.2.2 of the sunpci software.
- Did extensive testing of the backup system. I am still looking
into some
drive incompatibility questions between the drives on our robot and
an external
stand alone drive. I tried to get the remote user feature of
solstice backup to
work as well. The software said it would do its thing but wouldn't
restore any
files. The answer is that restores need to be initiated from
the client rather
than from a remote server.
- Helped get the rack mount servers into the rack.
- Building rana as a development web server.
- Worked on some miscellaneous printer problems and user account stuff.
(Mike)
-Installed two rack mounted servers with Larry & Lisa.
-Complete reload and upgrading hardware and all General
Computing software.
-Sub-basement cleaned up by un-installing unnecessary software that
was
slowing down the performance of PC to make workable for engineers and
students.
-Loaded 2Ghz PC for a new visitor this included all General computing
software and engineering software.
-Upgraded ANSYS license server to 5.7.1 and upgrade the 5.7.1 software
on
users workstations.
-Millikan conference room PC, having problems booting after troubleshooting
turns out slaved 6 GIG hard drive is dead, restored win98 on
the primary 10GIG
hard drive from a ghost image with different partitioning scheme to
make this
drive dual bootable to win98 and LINUX.
-Onsite user and phone support, that included fixing minor software
glitches
and hardware issues.
(Larry)
-Worked a number of procurements. Put through the maintenance contracts
on SUN
equipment and Hummingbird s/w. Placed equipment orders for the 40M
and LDAS. The
big order for the Foundry system went through and the equipment has
already
started showing up.
-Spent a little time fixing/setting up some of the web locations dealing
with
the financial side of the house. Also, assisted a number of other people
working
on different documentation issues.
-Resolved some disk space problems. We now have users generating large
data
files which required more disk purchases, which have been done. To
accommodate
the users we have moved a few directories around until we get the new
disk
systems put on-line.
-Worked a number of e-mail issues. Mainly, spam complaints. Vendors
and the
companies providing the e-mail services have been contacted. Along
the same line
there is still work being done to modify the LIGO-CIT e-mail services
to allow
more filtering and virus checking.
From: Helena Armandula <ahelena@ligo.caltech.edu>
Silicate Bonding
Bonded 2 prisms (ears) of different design on a large fused silica
substrate.
After attaching fibers to them, the ears will be loaded to evaluate
their performance under stress.
"Q" measurements
Received 4 re-polished thin substrates from Wave Precision.
2 of them went to Gregg Harry (MIT) and the other 2 to Steve Penn (Syracuse)
for "Q" measurements.
I expect to receive 2 measured thin substrates shortly. They will be
sent to J.M.Mackowski for processing.
From Mark Barton:
This week I continued work on my quad suspension model. I got working
some old code in my framework for calculating matrices of damping coefficients.
(I hadn't exercised it for a while so it had gotten out of date.) I also
redid the expressions for the potential energy of the wires to include
bending elasticity. The new version is based on the full solution for a
bent beam, reduced to a power series in the angles at the end of the wires,
assumed small.
From Rich Abbott:
Began stuffing of prototype voice coil driver. There are still some
parts that have not come in, but within a week the circuit will be operational
to supply the +/- 10 amp drive required by the coils.
For additional information about this report, contact sanders@ligo.caltech.edu