|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The LIGO Executive Committee Agenda for Monday October 1, 2001 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
Special Items:
From: Rainer Weiss <weiss@ligo.mit.edu>
Subject: Notes from last LSC Executive meeting September 21, 2001
Report from Spokesperson
------------------------
The large number of papers being submitted by
LSC members requires
an increase in the membership of the LSC Publications
and Presentations
Committee. Will ask Jim Brau, Peter Saulson and
Joe Romano to augment the
committee. The Amaldi Conference papers, to be
submitted to the reviewed
journal "Classical and Quantum Gravity", will
be superficially reviewed
by Weiss to maintain a schedule.
Report from the Data Coordinator
--------------------------------
Suggests that LSC and the Laboratory begin to address the special problems
associated with GRID computing systems, in particular, the security
questions.
The second iteration of the LSC Data Analysis White Paper is close to
completion and will be initially sent to all members of the LSC
Executive Committee for comment.
Analysis of TAMA data and proposal for a joint observing run with LIGO
----------------------------------------------------------------------
An offer made by members of TAMA to analyse old TAMA data by the LSC
was not considered interesting enough to divert effort from preparations
for LIGO/LSC data taking and analysis. However, the Committee encouraged
the Laboratory to investigate arrangments with TAMA for a joint run
and data analysis of new data from LIGO and TAMA.
Coordination of LSC computing capabilities
-------------------------------------------
The iVDGL (International Virtual Data Grid Laboratory,
onetime called
GRIPHYN) grid based computing initiative has
been funded. The LIGO
Laboratory, University of Wisconsin at Milwaukee,
Pennsylvania State
University and the University of Texas at Brownsille
are recipients
of a total of $2M over 5 years. Several of the
institutions are already
receiving funds for LIGO/LSC computing needs
through other channels.
One of the questions that has been raised is
how to coordinate the
new funds with existing ones to achieve the best
result for the
Collaboration. The White Paper on Data Analysis
gives some guidance.
A small group of LSC members will be pulled together
by Al Lazzarini
to formulate a strategy.
Proposal by K Riles to couple LIGO shift work with authorship of papers
-----------------------------------------------------------------------
The proposal made by Keith Riles at the last LSC meeting coupling
detector shift attendance to the number of authors per research group
was discussed again in the light of comments made by LSC members and
with
the benefit of an additional month of pondering. The Executive committee
has not reached consensus. There are still questions of what is the
currency should the idea be adopted. Is only shift work to be recognized?
Is work on other LSC joint facilities equivalent? How does one
count the designers and the builders? How does one treat
surrogates....etc. I have taken on the job of writing a document for
the
Executive Committee and clearly need to consult with a good crosssection
of the Lab and LSC.
Proposal by David Shoemaker and Ken Strain for LIGO III White Paper
-------------------------------------------------------------------
With advanced LIGO (LIGO II) research and development
program moving from a conceptual design into an engineering
research phase, it is important to maintain a long term program to
develop
concepts for further improvements. The proposal being made is
to begin to outline, in earnest, the long lead research directions
and
embody them in a LIGO III White Paper. The first draft projected for
October 2002.
Next LSC Executive Committee meeting Friday October 26, 2001 at 11AM EDT.
WBS 1.2 LIGO Operations--Administration
The following topics were discussed during the site teleconference on Thursday, September 27, 2001.
From: Ed Chargois <chargois_e@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .
ACCOMPLISHMENTS
ACTIVITY
| Packages | Faxes | |
| In | 35 | 33 |
| Out | 13 | 26 |
Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS PAYABLE HISTORY DATA.
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
From: irena@ligo.caltech.edu (Irena Petrac)
SUPPORT (Wood)
Ill today.
Rita Torres
Progress Period from 09.21 to 09.27
Accomplishments:
WBS 1.4.1.2 Project Controls (LIGO Construction)
I have received most of the input required for the end-of-August Quarterly Progress Report, and I am currently assembling the report.
The following Change Requests have
been submitted.
| CR-010006 | WBS 1.1.4 (OPS) | Roof Shelter for Concrete Pad Adjacent to Erosion Control Pond (Livingston) | M. Coles |
| CR-010007 | WBS 1.2.4 | Core Optics Components, Repolish/Recoat Beamsplitter | S. Whitcomb |
| CR-010008 | WBS 1.1.4 | Five-Ton Crane for the Staging Building in Hanford | O. Matherny |
| CR-010009 | WBS 1.4.2 (OPS) | Additional 10-W Laser for PSL Lab | S. Whitcomb |
| CR-010010 | Advanced R&D | Seismic Isolation System PD ETF Mechanical Contract (APPROVED) | D. Coyne/ G. Stapfer |
We scheduled a meeting of the LIGO Change Control Board for Tuesday, September 11, 2001, at 9:00 am PDT. An agenda was distributed electronically (LIGO-M010244-00-P). This meeting was postponed in light of national events and will be rescheduled.
Press for the latest Contingency Needs Projection.
From: Kris Duncan <kris@ligo.caltech.edu>
From: Ed Jasnow <jasnow@ligo.caltech.edu>
Citadel Construction
$2,463,600
Apollo, Inc.
$2,579,072
George Grant Const.
$2,456,000
Chervenell Const.
$2,436,000
LIGO Estimate
$2,841,022
We have requested a Dun & Bradstreet on the
apparent low bidders, as well as financial satatements and subcontractor
lists. This information, along with the proposed subcontract, will
be submitted to the NSF for approval.
No report this week.
NO REPORT
Detector: Optics and Installation: Installation of the door hardware for the Laser Safety Interlock system is completed and we're waiting on some hardware that I'm told is delayed because of security issues at the Canadian border. Prepared general arrangement drawings of an acoustic enclosure for our PSL and contacted several manufacturers for quotes. Jonathan Kern
CDS: Rolf is visiting LLO for upgrade of DAQ system. Replaced
all the Baja Mips processors with Pentiums. Tom upgraded the OS on all
the mass storage machines to Solaris 8. Installed new reflective memory
cards on Frame broadcaster and frame builder. Installed new reflected memory
bypass switch unit. Alex
loaded up the FrameBuilder and Daniel is working on the Test point
manager and the GDS code. Dave helped setup the Framebroadcaster after
the new OS was
installed. We found the existing Gigabit Ethernet card doesn't have
a driver for the new OS. Daniel's shipping us a new GE card. New CDS server
is ready to go
once Rolf installs the code on it. Upgrade of London will be done later.
Battling some problems with the GPS clocks modules at the time of this
writing.
Chethan
LDAS - Shipped out the tape library to cybernetics to be inspected so
they can renew the service contract. Replaced a failed drive in t3-6. I
have bigbrother running at both ldas-sw and ldas.ligo-la. Pulled a fiber
channel card out of the data server to let Rolf use it in a blade1000
for t3 testing with CDS. Started configuring the backup scripts on
admin in order to do the disk to disk backups on the LDAS systems. Read
some of the documentation on restarting LDAS after a reboot of dataserver.
Shannon Roddy
GC: The router equipment for our second T1 line has been installed and we now have two operational lines. LSU is still performing some tests of the routing configuration, but so far there seem to be no problems.We are working on the upgrade of our user file server from an E3000 to a Blade 1000. We are going to take advantage of this opportunity to also upgrade our free-ware software packages. Tom Evans
PEM: Discussed additions and the direction of the PEM reference web pages with Szabi. Began adding new content to the seismic reference pages. Also discussed calibration routines for the seismometers. The two end station Guralp seismometers were reconnected to the DAQ Wednesday afternoon. They were down due to the fact that the Streckheisen seismometers were using the end station data channels for data collection. I have tested calibration routines using the y-end Guralp seismometer before its reconnection. The new version of the DTT has been placed on Decatur. I hope to begin testing the Lidax addition sometime next week after the work on the CDS system is finished. Doug Lormand
Control Room: I'm starting setting up of the electronics rack in the
control room, Doing P.M. and cleaning of the sites 3 weather station towers,
plus working with
the IFO commissioning team as time permits. Rich Riesen
Other: Edward Jackson, Chancellor of Southern University, toured LLO tuesday morning with Steve McGuire. Chancellor Jackson was very enthusiastic about the project and offered the assistance of his office should we need his help in any way.
|
|
|
|
Installation&
Commissioning:
Livingston |
Other
Science/EngineeringActivities:
Issues/Concerns |
See also the Installation web page
See also 2km LSC characterization below
The recombined Fabry-Perot/Michelson was locked
successfully. The changes that enabled the locking were:
* Control asserted on the beam splitter rather than
on the input test masses to lock the Michelson. The beam splitter independently
controls the differential Michelson path length without changing the arm
cavity lengths.
* Increased the light on the photodetectors thereby
reducing the relative amplitudes of 60 Hz pickup relative to the optical
signal.
A set of changes in the CDS hardware and software were made to bring the Livingston site to the same level as Hanford. These changes included installation of faster Pentium processors and hardware for the common mode servo system and software upgrades of the LSC and GDS code.
(See details below)
The wiring for the feed forward system on the fine actuators at the end stations was completed. The system is intended to compensate for the tides and the microseismic peak and may be used to reduce the 1- 3 Hz excess noise at Livingston.
Completed
a noise hunt for ~530kHz and ~910kHz noise components in the PSL that were
causing high frequency slew rate limiting in the MC servo. The noise was
tracked to the digital components in the NPRO laser head. Made a phase
noise measurement on the PSL VCO
1) Upgrade DAQ sun stations to Solaris 8.
2) Install Pentium processors in place of all
MIPS processors,
including the DAQ controller.
3) Install new reflected memory boards in DAQ
controller and Sun
stations (FrameBuilder, etc.)
4) Installed fiber channel board in SunBlade
Framebuilder, which will
then connect to LDAS T3 drives. Shannon will
load drivers and make
fiber connection to LDAS in next couple of days.
5) All new software installed throughout
2) Installed new ASC code, which includes the
microseismic
feedforward, and ran some preliminary I/O tests. Did
not get around to
completing the code which allows reload of filter
coeffs. while running,
as ran out of time this week.
3) Installed new LSC code, which includes the
common mode servo as in
LHO2k, along with an addition Matt requested.
I hadn't been forewarned
of any LSC updates here, so it took a few hours to
get the code
together. Matt, etal, are testing this now.
everything on it remotely and, during a shutdown,
we will switch over
from the current CDS server.
Didn't quite finish by Thursday morning, as I had
hoped, as there were
glitches along the way. Primary problem was
getting the GPS receivers
in the Mass Storage Room (MSR) to lock. Without
this, the DAQS, and
therefore not much of anything, runs. Sat for
over an hour waiting for
it to lock last night. Finally, Rich and Jay
pulled an antenna off the
roof and we ran a BNC cable from the MSR to the antenna
placed outside
the back door. GPS modules came right
up using this method. This
morning, Russ ran some new cables, which seem to work,
but then we ran
into another problem. One of the GPS modules
blew its VME interface
chip. Unfortunately, the symptom was that all the
front panel lights on
the second GPS module (the one which works) would
go out whenever the
DAQ software would try to read it. This strange
symptom caused us to go
down the wrong road for a while (thought that module
or crate was bad).
All told, we lost about 4 hours this morning between
troubleshooting
this and running new cables.
Anyway, I think things are now in a somewhat running
state. All the DAQ
indicators are green, and ASC/LSC are up. We
spot checked some DAQ
signals, but someone still needs to further verify
the system after
we're gone.
APS Optical Train
Mike
Smith
The APS telescope optical train was modeled to determine the beam vignetting at the Faraday isolator and at the final steering mirror as a function of the displacement and tilt of the APS beam from the BS. A horizontal tilt of >150 microradian will cause vignetting at the final steering mirror at the 100ppm radius. However, a tilt of 200 microradian can cause vignetting at the 1/e^2 radius at the Faraday isolator; so the Faraday isolator is the limiting aperture.
I have been carefully studying
the Parametric Oscillatory Instability
reading the paper by Braginsky,
Strigin and Vyatchanin and William Kells'
Ligo note on the subject. I
have been accurately checking on all the
calculations and found that
not only the instability factor is greatly reduced
as shown by Kells, but also
that the stability condition is always satisfied,
basically because there is a
minus sign in front of the critical parameter.
I am going to double check this
result when there is a small detuning
and try to understand the physical
meaning of the analytical properties
in the frequency domain of the solutions.
Lee has installed and aligned the phase-correcting Pockels cell
inside the 10-W laser destined for LASTI. The
M-squared was measured after
the installation and was found to be better than the
value Lightwave
reported when the laser was shipped. After a
tweak to the laser alignment
the output power was also higher.
40m Lab PSL: A problem was reported with SN #118 in
that the NPRO laser would go
into standby after a certain period of time.
This was tracked down to a
gummed up needle valve that regulates the cooling
water to the NPRO laser.
LASTI PSL: The 10-W laser was shipped off.
Sander Lui
Ordered 20 100 uF metalized mylar capacitors for the
PSL VCO. Delivery is approximately 3 to 4 weeks.
Ordered and received 9 neutral density filters from
ThorLab. Paul is building an adapter to make the diode laser
test set for the RFPD eye save at any input power
level.
Rita is in the process of buying trimming capacitors
from Johanson to replace the ones used on the RFPD boards at hand.
Rick Karwoski
PSL Electronics: Detailed test procedures for PSL boards are in process.
ISS Efforts – Hanford: Progress on our endeavor to work the mode
cleaner into the intensity stabilization electronics was hindered by a
laser malfunction on the 2km PSL. The symptoms may be indicative of end
of life for the NPRO pump diode (according to the manufacturer).
Michelson. One set consists of various closed loop
tf measurements
(1/(1+OL)) from which we were able to infer the OL
tf. Since
the LSC electronic chain has been recently characterized
and modeled,
we factored it out from the OL measurement. Assuming
that the
sensor has a flat response at low frequency, the result
is a first estimate of the response of the coil driver
and pendulum
transfer function for the folding mirror FMX. A 1/f^2
behavior
was observed from ~40Hz-200Hz (outside that frequency
range the
measurement was noisy).
A second set of measurements was made again on the
2k simple
Michelson in a first attempt to do a DC calibration
on one of the
optics (in this case H2:LSC-FMX) keeping the error
well below 10%.
We locked the Michelson on dark fringe and we recorded
the
trend data for
i. the DC power on the anti-symmetric port;
ii. the control signal being sent to the coil drivers.
16s trend data sampled at 256Hz allowed us pinpoint
the mean
value of H2:LSC-FMX to within 1%.
The idea is now to invert the sign of the control
loops when
the Michelson is still locked on dark fringe. If done
carefully,
the transition from dark to bright fringe is lambda/4.
In units
of counts, the difference of mean values (x) for the
control signal
is found to be, for 6 measurements,
#
x (counts)
----------------------------------------
1
384.51 +- 3.66
2
272.7 +- 2.9
3
968.5 +- 4.0
4
653.2 +- 4.3
5
99.125 +- 4.270
6
110.884 +- 4.491
which is not consistent with each other. Close inspection
of the
trend data shows that indeed in the transition period,
the
system oscillated from dark to bright, and the transition
cannot be
assumed to be lambda/4.
epics data have been created. All that remains is
generation of second
order sections for filters and final check out of
signal paths.
preparation for installation.
- All other modules for the upgrade are complete,
with the exception of
the a few Anti-Image modules are ready for installation.
The filters for
the Anti-Image are due any day. Once they are received
the modules will
be tested.
This week I continued to write make files to build DMT libraries
and
executables from the new GDS cvs repository. With
this almost done, the
next step is to test the new versions and commit it all to cvs.
This week we balanced and aligned the new, lower-finesse South Arm
Cavity. Some residual steering of the output beam is still needed,
but we
have the transmitted spot on a camera.
Eric visited Wave Precision on Wednesday, meeting with Ken Scribner,
John
Tardiff, and Dennis Hotchkiss. Sapphire fabrication appears to
be
proceeding smoothly, and at its present rate we hope to be able to
install
the first Sapphire Arm Cavity in January of next year.
LASTI (Fritschel, Harry, MacInnis, Mason, Miller, Mittleman,
Ottaway, Phinney, Rollins, Shoemaker, Zucker)
=======================================================================
Infrastructure:
Grouting of the BSC/HAM piers has slipped to end of
this week due to contractor availability. Meanwhile the LLO HAM and
BSC pier/support tube installation equipment no longer needed
has been
staged and palleted for reshipment to LLO (date TBD but shooting for
early next week). Myron will coordinate with Gary and Harry to
receive at the LLO end.
A cleaning crew has been lined up after grouting is completed to
scrub everything down and restore our low particle counts. We
expect
this will enable incursion into HAM13 for test cavity suspension
installation week of 10/8.
Ken received detailed drawings and fabrication bid on the mezzanine
designed to support assembly of the SEI/SUS cartridge at BSC flange
level. Due to the (upward) revised estimated weight of
the adLIGO SEI
platform plus SUS assembly fixtures and personnel, the steel structure
is about twice as expensive as previously estimated. We are considering
rebidding but have not concluded a course of action.
Hydraulic pre-isolators:
Ken is working on a drawing set for review
this week. Joshua is still furiously ordering miscellaneos parts
for
the test stand (motor starter/overloads for the pump, NEMA enclosures,
pipe fittings) and expects everything to be in week after next ('just
add oil...'). The piping distance from LVEA mechanical rooms
to BSC
actuators at both sites were estimated from site drawings, and will
be
simulated with coils of tubing; subject to acoustic noise
considerations, we're now planning to temporarily situate the
hydraulic pump skid next to BSC0 in the MIT high bay.
Prestabilized laser:
THE LASTI PMC HAS BEEN LOCKED! Jamie
and Dave managed to work around
the electronic problems reported last week to achieve this very
satisfying result. In other good news, our repaired MOPA checked
out
"better than fine" (more than 11 W with a near perfect Gaussian output
beam) at Caltech, and was shipped this week by Lee Cardenas and Peter
King, to arrive here momentarily. In the bummer department,
electronics and wiring problems continue, with a blown PA-85 being
the
latest issue. We're consulting with Rick K. about how to deal
with
it.
Environment:
The local contractors have been showing more respect and restraint this
week, although there is still a good deal of shaking from the pile
driving. We are told this activity will wind up by end of next
week
"weather permitting".
Simulation and Modeling (Bhawal)
E2E for LIGO I meeting
----------------------
The monthly E2E for LIGO I meeting was held on Tuesday among
hardware and
detector experts and the e2e team. The details are available
in e2e
homepage
http://www.ligo.caltech.edu/~e2e
LSC characterization
--------------------
(Luca) The Matlab model reproducing the filtering properties
of the LSC
electronic chain now agrees to within 1dB and 2deg below 1kHz,
and 5dB and 5deg below 8kHz.
A Matlab function is now set to give the transfer function of
the
LSC electronics for any digital combination enabled.
The response of the coil driver and pendulum tf for FMX was
inferred from a closed loop transfer function measurement recently
obtained and the model described above.
Mode Mismatch
-------------
(Biplab) Running Han2k model and a corresponding hi-finesse cavity
and
doing
some analytical calculations to study resonance points in presence
of
mismatched beams.
E2E @ LLO
---------
(Ed Maros) Installed e2e-1.7.2 at Livingston.
Alfi
----
(Bruce)
- Completed Alfi5 parser read methods.
- Starting work on the display elements of Alfi5.
(Melody)
- Continued working on displaying member nodes in alfi5.
LIGO Data Analysis System
Software Systems (Blackburn)
Began developing code within the dataConditionAPI to support
the
emerging one-sided power spectrum standard.
Carefully went through the problem tracking system and closed
out
roughly 20 open problems.
Discovered that the LINUX build of GCC 2.95.3 was faulty. It
was
left over from the Redhat 6.2 and depended on those libraries.
The
compiler has been rebuilt with Redhat 7.1 and all depended software
has been rebuilt and rsync'ed to the sites. This has introduced
a
need to deliver a new LDAS release as soon as possible. This
bug
also explained strange build behavior reported at several LDAS
development sites within the LSC.
LDAS hosted Antony Searle from ANU and Duncun Brown from UWM
this
week. Both worked extensively on setting up custom LDAS systems
on laptops and in addition on tracing down and fixing problems.
Peter Shawhan worked with Antony and Isaac to get the LDAS database
up and running under RedHat Linux 7.1. The web page of instructions
to cover installation of DB2 on both Solaris and Linux are being
up-
dated.
A minor set of modifications were made to the wrapperInterfaceDatatype.h
file used by both LDAS and the LALwrapper. This has migrated
into both
the LDAS and LALwrapper CVS repositories. New versions of LDAS
and LAL
and LALwrapper based on these changes should be available at
UWM and CIT
later this week.
Revised the "SeqInsert" utility in LIGOtools to allow John to
direct
DMT triggers to different databases.
Added support to the dataConditionAPI to ingest results of arbitrary
database queries into the dataPipeline for use by the dataConditionAPI
or search codes running under the wrapperAPI.
New version of SWIG tried and whole LDAS system compiled using
it.
System needs to be tested before new SWIG can be made default.
Will be
performing unit test on genericAPI, not exhaustive. We will
also have
to examine new SWIG-generated code for memory leaks.
Added new user commands addUser, updateUserInfo and createFtpDirectory
to the set of understood managerAPI commands.
The domain over which LDAS runs will no longer be determined
using the
unix domainname command. Instead a new mechanism will be implemented
based on a system configuration file.
Finished up nodes monitor function changes by splitting nodes
into pages
to handle all nodes on a system. Looked into cpu data displayed
by
snapSysData but no changes are made since the info from vmstat
is correct.
Tried with top also but top in batch mode did not produce any
cpu usage
data ( 0% idle ). Miscellaneous fixes for cntlmon; closed all
cntlmonAPI
problem reports.
Working on metadataAPI issues: created a script dbUniqueIds to
generate
the uniqueId file for metadataAPI by querying databases for
the primary
keys. A generic dbUniqueIds file is used for all databases that
have the
same schema, and specific one used for each database that is
different.
Removed database specifics on pkgIndex.tcl (Makefile.am); working
on
script
to generate site specific LDASdsnames.ini so user does not have
to copy
the
released LDASdsnames file to edit. Added the key functions to
db2utils lib
file db2static.tcl to add the info to schema web page.
Hardware Systems (Anderson)
Caltech
-------
(Dan Kozak)
Some HPSS handholding, reseting error warnings and
adding remaining
tapes to storage classes mostly.
Labeled about half of the (CACR) 9940 tapes and got
them into the
silo.
Worked on a remaining Red Hat sendmail issue--still
looking for a
solution.
Met with Sun regarding SAN topology and T3/QFS performance
issues.
(Al Wilson)
moves moves and more moves. installed a new system
for alex. m27 (an old
PII) was swapped out for a shinny brand new m27
(2gig P4) it will also
be
the new build machine. We got replacement for the
LCD monitor in the
machine room. very fast turn around. Thanks sun.
But alas the memory for
the alpha is on back order.
(Stuart Anderson)
Working with Sun on configuring the next major LDAS
hardware purchase
of servers and storage equipment. With the help
of Sun engineers we
where finally able to demonstrate linear scaling
of I/O performance
as the number of T3 RAID systems in a single filesystem
was increased.
Enabled software mirroring of pre-built LDAS software
to LSC members.
MIT
---
troubleshot managerAPI failure
Livingston
----------
(Shannon Roddy)
LDAS - Shipped out the tape library to cybernetics
to be inspected so
they can renew the service contract. Replaced
a failed drive in t3-6.
I have bigbrother running at both ldas-sw and ldas.ligo-la.
Pulled a
fiber channel card out of dataserver to let Rolf
use it in a blade1000
for t3 testing with CDS. Started configuring
the backup scripts on
admin in order to do the disk to disk backups on
the LDAS systems. Read
some of the documentation on restarting LDAS after
a reboot of
dataserver.
Hanford
-------
(Greg Mendell)
1) Upgraded knownpulsardemod DSO code to either output
the SFT data in
frame format or to demod the SFTs
and output statistics to the
SGNL_DPERIOD database table.
(In both case, when run under the
stand-alone wrapper, the output
goes into an ilwd file.)
2) Added code to generate test data. A simple
test verifies that a
signal is detected when the command
line template parameters match
the
test data parameters.
3) Submitted knownpulsardemod DSO code to the lalwrapper
cvs archive.
4) Performed routine sys admin tasks.
Data Analysis Activities
(Philip Charlton)
- Finished and submitted FCT group paper for Amaldi 4 proceedings.
- Worked on comparing recovery of SNR via FCT and exact templates,
both in
code and analytically. Currently working on code
to study the effect
of oversampling by taking fixed-length chirps in
the time domain and
padding with zeroes to achieve a longer time-series.
General Computing (Wallace)
MIT:
- Moved machines back into offices (from MDC)
- Added new users (grad students / postdocs)
- Setup Ultra10 machine for postdoc
- Investigated permanent locations for wireless hubs
- Various paperwork:
MIT property tags
P.O. changes for equipment sent back to Dell
- Investigated laptop prices/specs for postdoc
Livingston:
(Tom)
- The router equipment for our second T1 line has been installed and
we
now have two operational lines. LSU is still performing some
tests of
the routing configuration, but so far there seem to be no problems.
- We are working on the upgrade of our user file server from an E3000
to a Blade 1000. We are going to take advantage of this opportunity
to also upgrade our freeware software packages.
Hanford:
(Christine)
- Installed the latest patches on all Solaris systems. Copied
most of
the CDS security measures onto all GC Solaris systems.
- Started setting up a Windows 2000 server. Installed a trial
version
of the Quick Restore backup software to be used to backup PCs
to the
tape robot connected to the Solaris file server.
- Installed the new tape robot onto the new file server. Started
installing the latest version of the Quick Restore backup software
on
the new server.
CIT:
(Barbara)
- Began work on newest items on costbook to-do list. Updated
the posted
reports using the 2002 indirect cost, GRA, and staff benefit
rates. Wrote
a query to update the cost codes. Began working on report
changes.
- Worked with Mike on the rebuild of pc72 and the replacement for pherkab.
- Made web site changes -- LSC reports and talks, postdoc position,
publications.
(Wendy)
- Installed Office on a PC, then worked on other problems with that
PC.
- Inventoried the computers in Synchrotron and updated the inventory
map.
- Installed windows patches on a few PCs
- Inventoried a few laptops--the laptops on the list I was given are
mostly
traveling at this time, so these will need to be found at some
later time
(Mick)
- Continued working on inventory data
- Modified web FAQs
- Addressed problem with Helena's ZIP drive, eventually replacing it
- Helped Mike and Larry install new rack-mount PC to become pherkab
- Reconfigured Liz's computer to get her e-mail, rather than Rita's
- Learning to restore files from the daily backups
(Mike)
- Getting user and share information together to reload PHERKAB
- Work with Larry to make adjustments on server rack to make room for
rack
mount servers.
- Loaded 2Ghz with all General Computing software and engineering packages
- Working on upgrading ANSYS server to 5.7.1 waiting on License code
from
ANSYS.
- PHERKAB, reloaded with NTSRV 4.0 the administrative server which
is now
back-up and running.
- Various user support that included software, hardware issues and
printer
problems.
(Lisa)
- Working on sendmail compile on becrux. This requires gcc to
be installed
locally. ver. 8.11.6 compiles fine but I'm getting make
errors with
8.12.0.
- Worked on clearing up disk space on sirius and helping the 40meter
manage
their file distribution.
- Rebooted kuma. This required all of the printers to be re-set.
- Made dns and nis+ host changes for the nt servers.
(Larry)
- Started the paperwork for the Foundry order. This was the hardware
chosen
to
replace the ATM backbone system for the LIGO CIT network.
- Resolved a couple of disk related issues. Working on increasing the
disk
storage but also we need people to clean off a lot of their
old files.
There
will be a list generated of old dead accounts, that will be
passed around
for
approval to have those accounts removed from the system. This
should
happen
in the next two weeks.
- Working with a group of people along with the Sysadmin group on getting
some of
the computer security procedures documented.
- Still working on upgrading and getting a few more support servers
on-line.
- Checked on the equipment at Downs in the area that had been flooded.
One
of
the LIGO edge switches was ruined from water dripping on it
from the
ceiling,
other than that things looked OK.
- There was a e-mail message sent to everyone on the project asking
for
assistance in some sort of money scheme. This was turned over
to Caltech
security who informed me that the FBI was already working on
this problem.
Everyone that received the message should just delete it.
Adv LIGO SUS
Mark Barton
This week I continued developing a model for use in detailed design
of
the Advanced LIGO suspension. I added tools for making easy-to-read
tables and 3D plots of mode shapes, and for doing transfer function
plots
and published a version 1 at <http://www.ligo.caltech.edu/~mbarton/>SUSmodels>.
Since then I've working on adding angular restoring force of
wires near pivot points and improving the calculation of damping and
thermal noise.
From: Helena Armandula <ahelena@ligo.caltech.edu>
"Q" measurements - 3"dia. x .100" thick substrates
Expect to ship 2 thin fused silica substrates to Lyon around October
1st.
The substrates' "Q" has been measured by Gregg Harry and Steve Penn
at Syracuse.
Formalized manufacturing specs for sapphire substrates to be used in "Q" studies and sent them to Crystal Systems.
"Q" measurements - 3"dia. x 1" thick substrates
At Sheila's request I am shipping to Glasgow the two extra 3"dia. x
1" thick fused silica substrates that we have at Caltech.
The aim is for Sheila to measure with Jim Hough all 4 substrates in
Glasgow during her visit in October.
Advanced LIGO Coatings
Shipped 1" dia. fused silica substrates to MLD for the first run to
evaluate coating absorption.
We should receive these parts coated with Ta2O5/SiO2 and annealed at
3 different temperatures within 4 weeks.
From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>
Both Lia and Florian flown out home.
Charlotte
Problems in getting the effective bending point of flex joints under
different stresses
Studied maximum stress versus connecting radius of flex joint blade
to
bulk above and below the joint.
Lia, Riccardo
The data acquisition card that showed signs of instability suddenly
went
completely sick on us, small sudden steps are visible in the DAQ that
mask the logarithmic creep behavior visible the first week The data
of
the week appears to be a complete waste. A new DAQ card was ordered
and
installed.
Charlotte, Virginio, Lia
Found same problems also in new card, installed new card driver
software, maybe less but still jumps are visible. Also installed
witness LVDTs and found them to drift (creep-like).
The jumps seem to be a software problem (they jump both high and low
so
they are not catastrophic creep events), maybe an offset file
overwrite. We will try to replace the computer in case its memory
has
problems.
For the witness LVDT “creep” only explanation may be that to save on
costs we made them of nylon instead of Peek or Ceramics. They
may be
drying and shrinking in the dry environment of the creep oven.
Will
replace all of them with Peek ones.
Akiteru, et al. @ Hongo
At Okinawa for the JPS meeting.
Alessandro @ Pisa
Getting bids for the NC-US machine.
Testing the mechanics of a prototype of vertical accelerometer.
Working
fine down to 0.3 Hz.
Broken the last prototype of horizontal accelerometer with ground flex
joints at the end of machining. Need to revise procedure and
remake.
For additional information about this report, contact sanders@ligo.caltech.edu