Weekly Report for Week Ending September 27, 2001


 Exec. Comm. Agenda
Highlights
LSC
Administration
Hanford Observatory
Livingston Observatory
MIT
Caltech
Detector
40 Meter
TNI
LASTI
Data Analysis
LIGO II/Adv. R&D
Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  October 1, 2001 will be:

 (Meeting time: 10:30 am Pacific Time)

Open meeting 10:30 - 11:30

  1. Announcements
  2. LSC Issues (Weiss)
  3. Comments on Weekly Report
  4. WBS 1 LIGO I Construction (Lindquist)
  5. WBS 2 LIGO Lab Operations
  6. WBS 3 and 4  Advanced R&D and LIGO II (Sanders)
Executive Committee only 11:30 - noon   Topics:
 

Special Items:


Special Announcements:


Weekly Report Highlights
 


LSC Issues (Weiss)


From: Rainer Weiss <weiss@ligo.mit.edu>

Subject: Notes from last LSC Executive meeting September 21, 2001
 

Report from Spokesperson
------------------------
The large number of papers being submitted by LSC members requires
an increase in the membership of the LSC Publications and Presentations
Committee. Will ask Jim Brau, Peter Saulson and Joe Romano to augment the
committee. The Amaldi Conference papers, to be submitted to the reviewed
journal "Classical and Quantum Gravity", will be superficially reviewed
by Weiss to maintain a schedule.
 

Report from the Data Coordinator
--------------------------------
Suggests that LSC and the Laboratory begin to address the special problems
associated with GRID computing systems, in particular, the security
questions.
 

The second iteration of the LSC Data Analysis White Paper is close to
completion and will be initially sent to all members of the LSC
Executive Committee for comment.
 

Analysis of TAMA data and proposal for a joint observing run with LIGO
----------------------------------------------------------------------
An offer made by members of TAMA to analyse old TAMA data by the LSC
was not considered interesting enough to divert effort from preparations
for LIGO/LSC data taking and analysis. However, the Committee encouraged
the Laboratory to investigate arrangments with TAMA for a joint run
and data analysis of new data from LIGO and TAMA.
 

Coordination of LSC computing capabilities
-------------------------------------------
The iVDGL (International Virtual Data Grid Laboratory, onetime called
GRIPHYN) grid based computing initiative has been funded. The LIGO
Laboratory, University of Wisconsin at Milwaukee, Pennsylvania State
University and the University of Texas at Brownsille are recipients
of a total of $2M over 5 years. Several of the institutions are already
receiving funds for LIGO/LSC computing needs through other channels.
One of the questions that has been raised is how to coordinate the
new funds with existing ones to achieve the best result for the
Collaboration. The White Paper on Data Analysis gives some guidance.
A small group of LSC members will be pulled together by Al Lazzarini
to formulate a strategy.
 

Proposal by K Riles to couple LIGO shift work with authorship of papers
-----------------------------------------------------------------------
The proposal made by Keith Riles at the last LSC meeting coupling
detector shift attendance to the number of authors per research group
was discussed again in the light of comments made by LSC members and with
the benefit of an additional month of pondering. The Executive committee
has not reached consensus. There are still questions of what is the
currency should the idea be adopted. Is only shift work to be recognized?
Is work on other LSC joint facilities equivalent? How does one
count the designers and the builders? How does one treat
surrogates....etc. I have taken on the job of writing a document for the
Executive Committee and clearly need to consult with a good crosssection
of the Lab and LSC.

Proposal by David Shoemaker and Ken Strain for LIGO III White Paper
-------------------------------------------------------------------
With advanced LIGO (LIGO II) research and development
program moving from a conceptual design into an engineering
research phase, it is important to maintain a long term program to develop
concepts for further improvements. The proposal being made is
to begin to outline, in earnest, the long lead research directions and
embody them in a LIGO III White Paper. The first draft projected for
October 2002.
 

Next LSC Executive Committee meeting Friday October 26, 2001 at 11AM EDT.


LIGO I Construction/LIGO Laboratory Administration (Lindquist)



 

WBS 1.2 LIGO Operations--Administration



LIGO Weekly Site Telecon (Lindquist)

The following topics were discussed during the site teleconference on Thursday, September 27, 2001.

The list of current actions revised to reflect the status of open actions assigned through September 27, 2001 may be found at ACTION LIST.

PROPERTY MANAGEMENT (Chargois)

From: Ed Chargois <chargois_e@ligo.caltech.edu>


DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner - turner@ligo.caltech.edu>

Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .

ACCOMPLISHMENTS

>From: Cleveland Mak <mak_c@ligo.caltech.edu>

ACTIVITY

Packages Faxes
In 35 33
Out 13 26

Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.


COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman)

From: Esther Cunningham <esther@ligo.caltech.edu>

Press here for ACCOUNTS PAYABLE HISTORY DATA.

From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

From: Florence Kaufman <fkaufman@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: irena@ligo.caltech.edu (Irena Petrac)

From: Ed Jasnow <jasnow@ligo.caltech.edu>

SUPPORT (Wood)

 
Irene Baldon

Ill today.

Rita Torres

Dorothy Lloyd Elizabeth K. Wood

Advanced LIGO (Frey)

From: Thomas Frey <tfrey@ligo.caltech.edu>

Progress Period from 09.21 to 09.27

Accomplishments:

Schedule 09.28 to 10.04:

WBS 1.4.1.2   Project Controls (LIGO Construction)



Reports (Lindquist)

I have received most of the input required for the end-of-August Quarterly Progress Report, and I am currently assembling the report.



Change Control/Contingency (Lindquist)

The following Change Requests have been submitted.
 

CR-010006 WBS 1.1.4 (OPS) Roof Shelter for Concrete Pad Adjacent to Erosion Control Pond (Livingston) M. Coles
CR-010007 WBS 1.2.4 Core Optics Components, Repolish/Recoat Beamsplitter S. Whitcomb
CR-010008 WBS 1.1.4 Five-Ton Crane for the Staging Building in Hanford O. Matherny
CR-010009 WBS 1.4.2 (OPS) Additional 10-W Laser for PSL Lab S. Whitcomb
CR-010010 Advanced R&D Seismic Isolation System PD ETF Mechanical Contract (APPROVED) D. Coyne/ G. Stapfer

We scheduled a meeting of the LIGO Change Control Board for Tuesday, September 11, 2001, at 9:00 am PDT. An agenda was distributed electronically (LIGO-M010244-00-P).  This meeting was postponed in light of national events and will be rescheduled.

Press for the latest Contingency Needs Projection.


COST SCHEDULE CONTROL SYSTEMS (Duncan, Akutagawa)

From: Kris Duncan <kris@ligo.caltech.edu>

From: Cindy Akutagawa <cindy@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Jasnow)

From: Ed Jasnow <jasnow@ligo.caltech.edu>


Quality/Safety (Tyler)

>From: Bill Tyler <tyler@ligo.caltech.edu>

No report this week.
 


LIGO Hanford Observatory (LHO) Operations (Raab)


NO REPORT


LIGO Livingston Observatory (LLO) Operations (Coles)


Detector: Optics and Installation: Installation of the door hardware for the Laser Safety Interlock system is completed and we're waiting on some hardware that I'm told is delayed because of security issues at the Canadian border. Prepared general arrangement drawings of an acoustic enclosure for our PSL and contacted several manufacturers for quotes. Jonathan Kern

CDS: Rolf is  visiting LLO for upgrade of DAQ system. Replaced all the Baja Mips processors with Pentiums. Tom upgraded the OS on all the mass storage machines to Solaris 8. Installed new reflective memory cards on Frame broadcaster and frame builder. Installed new reflected memory bypass switch unit. Alex
loaded up the FrameBuilder and Daniel is working on the Test point manager and the GDS code. Dave helped setup the Framebroadcaster after the new OS was
installed. We found the existing Gigabit Ethernet card doesn't have a driver for the new OS. Daniel's shipping us a new GE card. New CDS server is ready to go
once Rolf installs the code on it. Upgrade of London will be done later. Battling some problems with the GPS clocks modules at the time of this writing.
Chethan

LDAS - Shipped out the tape library to cybernetics to be inspected so they can renew the service contract. Replaced a failed drive in t3-6. I have bigbrother running at both ldas-sw and ldas.ligo-la. Pulled a fiber channel card out of the data server to let Rolf use it in a blade1000
for t3 testing with CDS. Started configuring the backup scripts on admin in order to do the disk to disk backups on the LDAS systems. Read some of the documentation on restarting LDAS after a reboot of dataserver.  Shannon Roddy

GC: The router equipment for our second T1 line has been installed and we now have two operational lines. LSU is still performing some tests of the routing configuration, but so far there seem to be no problems.We are working on the upgrade of our user file server from an E3000 to a Blade 1000. We are going to take advantage of this opportunity to also upgrade our free-ware software packages. Tom Evans

PEM: Discussed additions and the direction of the PEM reference web pages with Szabi. Began adding new content to the seismic reference pages. Also discussed calibration routines for the seismometers. The two end station Guralp seismometers were reconnected to the DAQ Wednesday afternoon. They were down due to the fact that the Streckheisen seismometers were using the end station data channels for data collection. I have tested calibration routines using the y-end Guralp seismometer before its reconnection. The new version of the DTT has been placed on Decatur. I hope to begin testing the Lidax addition sometime next week after the work on the CDS system is finished. Doug Lormand

Control Room: I'm starting setting up of the electronics rack in the control room, Doing P.M. and cleaning of the sites 3 weather station towers, plus working with
the IFO commissioning team as time permits. Rich Riesen

Other: Edward Jackson, Chancellor of Southern University, toured LLO tuesday morning with Steve McGuire. Chancellor Jackson was very enthusiastic about the project and offered the assistance of his office should we need his help in any way.


Detector/Technical Support (Whitcomb, Coyne)


 
 
Installation& Commissioning:
Hanford
Livingston
Other Science/EngineeringActivities:
Design/Analysis/Fab
Issues/Concerns
See also the daily electronic logs for the installation and commissioning activities:
Hanford Detector Log

Livingston Detector Log

See also the Installation web page

1.1 LHO INSTALLATION & COMMISSIONING

2km Commissioning

Rick Savage, Doug Cook
The laser has gone into the mode (observed earlier this year) where it transitions between two states.  The jumps between states are characterized by a change of ~5 MHz in the frequency occuring over about a 1 second time-scale.  These are more troublesome now, because the diodes installed in the frequency servo limit the range of the fast actuator to less than this, causing the laser to lose lock.  We now also see these two states in the intensity of the master oscillator, and (apparently) the intensity of its pump diode.  Perhaps the most surprising feature is that these jumps don't take place if the laser shutter between the NPRO and the amplifier is closed, suggesting that it is some sort of feedback.  We are trying to contact Tom Kane to see if he has ever seen anything like this before. In the meantime we are evaluating various things we might do to fix it.

See also 2km LSC characterization below

4-k Commissioning

Bill Kells has been leveling the modecleaner.

1.2LLO INSTALLATION & COMMISSIONING

Commissioning

Rai Weiss reporting


The recombined Fabry-Perot/Michelson was locked successfully. The changes that enabled the locking were:

* Control asserted on the beam splitter rather than on the input test masses to lock the Michelson. The beam splitter independently controls the differential Michelson path length without changing the arm cavity lengths.

* Increased the light on the photodetectors thereby reducing the relative amplitudes of 60 Hz pickup relative to the optical signal.

A set of changes in the CDS hardware and software were made to bring the Livingston site to the same level as Hanford. These changes included installation of faster Pentium processors and hardware for the common mode servo system and software upgrades of the LSC and GDS code.

(See details below)

The wiring for the feed forward system on the fine actuators at the end stations was completed. The system is intended to compensate for the tides and the microseismic peak and may be used to reduce the 1- 3 Hz excess noise at Livingston.

Completed a noise hunt for ~530kHz and ~910kHz noise components in the PSL that were causing high frequency slew rate limiting in the MC servo. The noise was tracked to the digital components in the NPRO laser head. Made a phase noise measurement on the PSL VCO

DAQ

Rolf Bork
Essentially upgraded the system to be same as LHO. This included:

  1) Upgrade DAQ sun stations to Solaris 8.

  2) Install Pentium processors in place of all MIPS processors,

including the DAQ controller.

  3) Install new reflected memory boards in DAQ controller and Sun

stations (FrameBuilder, etc.)

  4) Installed fiber channel board in SunBlade Framebuilder, which will

then connect to LDAS T3 drives.  Shannon will load drivers and make

fiber connection to LDAS in next couple of days.

  5) All new software installed throughout

ASC/LSC

Rolf Bork
  1) Replaced end station and LVEA LSC processors with newer 1GHz CPU.

  2) Installed new ASC code, which includes the microseismic

feedforward, and ran some preliminary I/O tests. Did not get around to

completing the code which allows reload of filter coeffs. while running,

as ran out of time this week.

  3) Installed new LSC code, which includes the common mode servo as in

LHO2k, along with an addition Matt requested.  I hadn't been forewarned

of any LSC updates here, so it took a few hours to get the code

together.  Matt, etal, are testing this now.

CDS Server

Rolf Bork
  1) Installed new Sun server. In the next few weeks, I will load

everything on it remotely and, during a shutdown, we will switch over

from the current CDS server.

Didn't quite finish by Thursday morning, as I had hoped, as there were

glitches along the way.  Primary problem was getting the GPS receivers

in the Mass Storage Room (MSR) to lock.  Without this, the DAQS, and

therefore not much of anything, runs.  Sat for over an hour waiting for

it to lock last night.  Finally, Rich and Jay pulled an antenna off the

roof and we ran a BNC cable from the MSR to the antenna placed outside

the back door.  GPS modules  came right up using this method.  This

morning, Russ ran some new cables, which seem to work, but then we ran

into another problem.  One of the GPS modules blew its VME interface

chip. Unfortunately, the symptom was that all the front panel lights on

the second GPS module (the one which works) would go out whenever the

DAQ software would try to read it.  This strange symptom caused us to go

down the wrong road for a while (thought that module or crate was bad). 

All told, we lost about 4 hours this morning between troubleshooting

this and running new cables.

Anyway, I think things are now in a somewhat running state.  All the DAQ

indicators are green, and ASC/LSC are up.  We spot checked some DAQ

signals, but someone still needs to further verify the system after

we're gone.

2.0 OtherEngineering and Scientific Activities

2.1 Design/Analysis/Fab

IO Periscope

Mike Smith, Ken Mailand
Testing was completed; the foot pads were lapped flat, and the new IO periscope prototype, and mirror mounting plates were shipped to LLO. An assembly drawing is being prepared. A bottom mirror mount pedestal for an Ultima mount was sent to LHO. Final working drawings for the revised production cross braces are in process.

APS Optical Train

Mike Smith 

The APS telescope optical train was modeled to determine the beam vignetting at the Faraday isolator and at the final steering mirror as a function of the displacement and tilt of the APS beam from the BS. A horizontal tilt of >150 microradian will cause vignetting at the final steering mirror at the 100ppm radius. However, a tilt of 200 microradian can cause vignetting at the 1/e^2 radius at the Faraday isolator; so the Faraday isolator is the limiting aperture.

Optical modeling

Erika D’Ambrosio

I have been carefully studying the Parametric Oscillatory Instability

reading the paper by Braginsky, Strigin and Vyatchanin and William Kells'

Ligo note on the subject. I have been accurately checking on all the

calculations and found that not only the instability factor is greatly reduced

as shown by Kells, but also that the stability condition is always satisfied,

basically because there is a minus sign in front of the critical parameter.

I am going to double check this result when there is a small detuning

and try to understand the physical meaning of the analytical properties

in the frequency domain of the solutions.

PSL

Peter King


Lee has installed and aligned the phase-correcting Pockels cell

inside the 10-W laser destined for LASTI.  The M-squared was measured after

the installation and was found to be better than the value Lightwave

reported when the laser was shipped.  After a tweak to the laser alignment

the output power was also higher.

40m Lab PSL: A problem was reported with SN #118 in that the NPRO laser would go

into standby after a certain period of time.  This was tracked down to a

gummed up needle valve that regulates the cooling water to the NPRO laser.

LASTI PSL: The 10-W laser was shipped off.

Sander Lui

Ordered 20 100 uF metalized mylar capacitors for the PSL VCO. Delivery is approximately 3 to 4 weeks.

Ordered and received 9 neutral density filters from ThorLab. Paul is building an adapter to make the diode laser

test set for the RFPD eye save at any input power level.

Rita is in the process of buying trimming capacitors from Johanson to replace the ones used on the RFPD boards at hand.

Rick Karwoski

PSL Electronics: Detailed test procedures for PSL boards are in process.

ISS Efforts – Hanford: Progress on our endeavor to work the mode cleaner into the intensity stabilization electronics was hindered by a laser malfunction on the 2km PSL. The symptoms may be indicative of end of life for the NPRO pump diode (according to the manufacturer).

LSC

Luca Matone
A set of measurements has been recently taken on the 2k simple

Michelson. One set consists of various closed loop tf measurements

(1/(1+OL)) from which we were able to infer the OL tf. Since

the LSC electronic chain has been recently characterized and modeled,

we factored it out from the OL measurement. Assuming that the

sensor has a flat response at low frequency, the result

is a first estimate of the response of the coil driver and pendulum

transfer function for the folding mirror FMX. A 1/f^2 behavior

was observed from ~40Hz-200Hz (outside that frequency range the

measurement was noisy).

A second set of measurements was made again on the 2k simple

Michelson in a first attempt to do a DC calibration on one of the

optics (in this case H2:LSC-FMX) keeping the error well below 10%.

We locked the Michelson on dark fringe and we recorded the

trend data for

i. the DC power on the anti-symmetric port;

ii. the control signal being sent to the coil drivers.

16s trend data sampled at 256Hz allowed us pinpoint the mean

value of H2:LSC-FMX to within 1%.

The idea is now to invert the sign of the control loops when

the Michelson is still locked on dark fringe. If done carefully,

the transition from dark to bright fringe is lambda/4. In units

of counts, the difference of mean values (x) for the control signal

is found to be, for 6 measurements,

        #         x (counts)

----------------------------------------

        1       384.51  +- 3.66

        2       272.7   +- 2.9

        3       968.5   +- 4.0

        4       653.2   +- 4.3

        5        99.125 +- 4.270

        6       110.884 +- 4.491

which is not consistent with each other. Close inspection of the

trend data shows that indeed in the transition period, the

system oscillated from dark to bright, and the transition cannot be

assumed to be lambda/4.

Seismic Feed Forward System

Jay Heefner, Rich Abbott
All hardware is installed and ready for test. Operator screens for

epics data have been created. All that remains is generation of second

order sections for filters and final check out of signal paths.

Digital Suspension Controls Upgrade

Jay Heefner
- All LOS Coil Drivers, including spares have been sent to the sites in

preparation for installation.

- All other modules for the upgrade are complete, with the exception of

the a few Anti-Image modules are ready for installation. The filters for

the Anti-Image are due any day. Once they are received the modules will

be tested.

DMT

John Zweizig


This week I continued to write make files to build DMT libraries and

executables from the new GDS cvs repository. With this almost done, the

next step is to test the new versions and commit it all to cvs.


40 Meter Interferometer (Weinstein)



 



Thermal Noise Interferometer (Libbrecht)


This week we balanced and aligned the new, lower-finesse South Arm
Cavity.  Some residual steering of the output beam is still needed, but we
have the transmitted spot on a camera.
 

Eric visited Wave Precision on Wednesday, meeting with Ken Scribner, John
Tardiff, and Dennis Hotchkiss.  Sapphire fabrication appears to be
proceeding smoothly, and at its present rate we hope to be able to install
the first Sapphire Arm Cavity in January of next year.


LASTI (Zucker)


LASTI (Fritschel, Harry, MacInnis, Mason, Miller, Mittleman,
Ottaway, Phinney, Rollins, Shoemaker, Zucker)
 

=======================================================================
 

Infrastructure:
 

Grouting of the BSC/HAM piers has slipped to end of
this week due to contractor availability. Meanwhile the LLO HAM and
BSC  pier/support tube installation equipment no longer needed has been
staged and palleted for reshipment to LLO (date TBD but shooting for
early next week).  Myron will coordinate with Gary and Harry to
receive at the LLO end.
 

A cleaning crew has been lined up after grouting is completed to
scrub everything down and restore our low particle counts.  We expect
this will enable incursion into HAM13 for test cavity suspension
installation week of 10/8.
 

Ken received detailed drawings and fabrication bid on the mezzanine
designed to support assembly of the SEI/SUS cartridge at BSC flange
level.  Due to the (upward) revised  estimated weight of the adLIGO SEI
platform plus SUS assembly fixtures and personnel, the steel structure
is about twice as expensive as previously estimated. We are considering
rebidding but have not concluded a course of action.
 

Hydraulic pre-isolators:
 

Ken is working on a drawing set for review
this week.  Joshua is still furiously ordering miscellaneos parts for
the test stand (motor starter/overloads for the pump, NEMA enclosures,
pipe fittings) and expects everything to be in week after next ('just
add oil...').  The piping distance from LVEA mechanical rooms to BSC
actuators at both sites were estimated from site drawings, and will be
simulated with coils of tubing; subject to acoustic noise
considerations, we're now planning to  temporarily situate the
hydraulic pump skid next to BSC0 in the MIT high bay.
 

Prestabilized laser:
 

THE LASTI PMC HAS BEEN LOCKED!  Jamie and Dave managed to work around
the electronic problems reported last week to achieve this very
satisfying result.  In other good news, our repaired MOPA checked out
"better than fine" (more than 11 W with a near perfect Gaussian output
beam) at Caltech, and was shipped this week by Lee Cardenas and Peter
King, to arrive here momentarily.  In the bummer department,
electronics and wiring problems continue, with a blown PA-85 being the
latest issue.  We're consulting with Rick K. about how to deal with
it.
 

Environment:
 

The local contractors have been showing more respect and restraint this
week, although there is still a good deal of shaking from the pile
driving.  We are told this activity will wind up by end of next week
"weather permitting".


Data Analysis and Computing (Lazzarini)



 
 

Simulation and Modeling (Bhawal)
 

 E2E for LIGO I meeting
 ----------------------
 The monthly E2E for LIGO I meeting was held on Tuesday among hardware and
 detector experts and the e2e team. The details are available in e2e
homepage
 http://www.ligo.caltech.edu/~e2e
 

 LSC characterization
 --------------------
 (Luca) The Matlab model reproducing the filtering properties of the LSC
 electronic chain now agrees to within 1dB and 2deg below 1kHz,
 and 5dB and 5deg below 8kHz.
 A Matlab function is now set to give the transfer function of the
 LSC electronics for any digital combination enabled.
 The response of the coil driver and pendulum tf for FMX was
 inferred from a closed loop transfer function measurement recently
 obtained and the model described above.
 

 Mode Mismatch
 -------------
 (Biplab) Running Han2k model and a corresponding hi-finesse cavity and
doing
 some analytical calculations to study resonance points in presence of
 mismatched beams.
 

 E2E @ LLO
 ---------
 (Ed Maros) Installed e2e-1.7.2 at Livingston.
 

 Alfi
 ----
  (Bruce)
- Completed Alfi5 parser read methods.
- Starting work on the display elements of Alfi5.
 

  (Melody)
- Continued working on displaying member nodes in alfi5.
 

LIGO Data Analysis System
 

  Software Systems (Blackburn)
 

  Began developing code within the dataConditionAPI to support the
  emerging one-sided power spectrum standard.
 

  Carefully went through the problem tracking system and closed out
  roughly 20 open problems.
 

  Discovered that the LINUX build of GCC 2.95.3 was faulty. It was
  left over from the Redhat 6.2 and depended on those libraries. The
  compiler has been rebuilt with Redhat 7.1 and all depended software
  has been rebuilt and rsync'ed to the sites. This has introduced a
  need to deliver a new LDAS release as soon as possible. This bug
  also explained strange build behavior reported at several LDAS
  development sites within the LSC.
 

  LDAS hosted Antony Searle from ANU and Duncun Brown from UWM this
  week. Both worked extensively on setting up custom LDAS systems
  on laptops and in addition on tracing down and fixing problems.
  Peter Shawhan worked with Antony and Isaac to get the LDAS database
  up and running under RedHat Linux 7.1. The web page of instructions
  to cover installation of DB2 on both Solaris and Linux are being up-
  dated.
 

  A minor set of modifications were made to the wrapperInterfaceDatatype.h
  file used by both LDAS and the LALwrapper. This has migrated into both
  the LDAS and LALwrapper CVS repositories. New versions of LDAS and LAL
  and LALwrapper based on these changes should be available at UWM and CIT
  later this week.
 

  Revised the "SeqInsert" utility in LIGOtools to allow John to direct
  DMT triggers to different databases.
 

  Added support to the dataConditionAPI to ingest results of arbitrary
  database queries into the dataPipeline for use by the dataConditionAPI
  or search codes running under the wrapperAPI.
 

  New version of SWIG tried and whole LDAS system compiled using it.
  System needs to be tested before new SWIG can be made default. Will be
  performing unit test on genericAPI, not exhaustive. We will also have
  to examine new SWIG-generated code for memory leaks.
 

  Added new user commands addUser, updateUserInfo and createFtpDirectory
  to the set of understood managerAPI commands.
 

  The domain over which LDAS runs will no longer be determined using the
  unix domainname command. Instead a new mechanism will be implemented
  based on a system configuration file.
 

  Finished up nodes monitor function changes by splitting nodes into pages
  to handle all nodes on a system. Looked into cpu data displayed by
  snapSysData but no changes are made since the info from vmstat is correct.
  Tried with top also but top in batch mode did not produce any cpu usage
  data ( 0% idle ). Miscellaneous fixes for cntlmon; closed all cntlmonAPI
  problem reports.
 

  Working on metadataAPI issues: created a script dbUniqueIds to generate
  the uniqueId file for metadataAPI by querying databases for the primary
  keys. A generic dbUniqueIds file is used for all databases that have the
  same schema, and specific one used for each database that is different.
  Removed database specifics on pkgIndex.tcl (Makefile.am); working on
script
  to generate site specific LDASdsnames.ini so user does not have to copy
the
  released LDASdsnames file to edit. Added the key functions to db2utils lib
  file db2static.tcl to add the info to schema web page.
 

  Hardware Systems (Anderson)
 

    Caltech
    -------
    (Dan Kozak)
 

    Some HPSS handholding, reseting error warnings and adding remaining
    tapes to storage classes mostly.
 

    Labeled about half of the (CACR) 9940 tapes and got them into the
    silo.
 

    Worked on a remaining Red Hat sendmail issue--still looking for a
    solution.
 

    Met with Sun regarding SAN topology and T3/QFS performance issues.
 

    (Al Wilson)
 

    moves moves and more moves. installed a new system for alex. m27 (an old
    PII) was swapped out for a shinny brand new m27 (2gig P4) it will also
be
    the new build machine. We got replacement for the LCD monitor in the
    machine room. very fast turn around. Thanks sun. But alas the memory for
    the alpha is on back order.
 

    (Stuart Anderson)
 

    Working with Sun on configuring the next major LDAS hardware purchase
    of servers and storage equipment. With the help of Sun engineers we
    where finally able to demonstrate linear scaling of I/O performance
    as the number of T3 RAID systems in a single filesystem was increased.
 

    Enabled software mirroring of pre-built LDAS software to LSC members.
 

    MIT
    ---
 

    troubleshot managerAPI failure
 

    Livingston
    ----------
    (Shannon Roddy)
 

    LDAS - Shipped out the tape library to cybernetics to be inspected so
    they can renew the service contract.  Replaced a failed drive in t3-6.
    I have bigbrother running at both ldas-sw and ldas.ligo-la.  Pulled a
    fiber channel card out of dataserver to let Rolf use it in a blade1000
    for t3 testing with CDS.  Started configuring the backup scripts on
    admin in order to do the disk to disk backups on the LDAS systems.  Read
    some of the documentation on restarting LDAS after a reboot of
    dataserver.
 

    Hanford
    -------
    (Greg Mendell)
 

    1) Upgraded knownpulsardemod DSO code to either output the SFT data in
       frame format or to demod the SFTs and output statistics to the
       SGNL_DPERIOD database table.  (In both case, when run under the
       stand-alone wrapper, the output goes into an ilwd file.)
 

    2) Added code to generate test data.  A simple test verifies that a
       signal is detected when the command line template parameters match
the
       test data parameters.
 

    3) Submitted knownpulsardemod DSO code to the lalwrapper cvs archive.
 

    4) Performed routine sys admin tasks.
 

  Data Analysis Activities
  (Philip Charlton)
  - Finished and submitted FCT group paper for Amaldi 4 proceedings.
 

  - Worked on comparing recovery of SNR via FCT and exact templates, both in
    code and analytically. Currently working on code to study the effect
    of oversampling by taking fixed-length chirps in the time domain and
    padding with zeroes to achieve a longer time-series.
 
 

General Computing (Wallace)
 

MIT:
- Moved machines back into offices (from MDC)
- Added new users (grad students / postdocs)
- Setup Ultra10 machine for postdoc
- Investigated permanent locations for wireless hubs
- Various paperwork:
  MIT property tags
  P.O. changes for equipment sent back to Dell
- Investigated laptop prices/specs for postdoc
 

Livingston:
(Tom)
- The router equipment for our second T1 line has been installed and we
  now have two operational lines. LSU is still performing some tests of
  the routing configuration, but so far there seem to be no problems.
- We are working on the upgrade of our user file server from an E3000
  to a Blade 1000. We are going to take advantage of this opportunity
  to also upgrade our freeware software packages.
 

Hanford:
(Christine)
- Installed the latest patches on all Solaris systems.  Copied most of
  the CDS security measures onto all GC Solaris systems.
- Started setting up a Windows 2000 server.  Installed a trial version
  of the Quick Restore backup software to be used to backup PCs to the
  tape robot connected to the Solaris file server.
- Installed the new tape robot onto the new file server.  Started
  installing the latest version of the Quick Restore backup software on
  the new server.
 

CIT:
 

(Barbara)
- Began work on newest items on costbook to-do list.   Updated the posted
  reports using the 2002 indirect cost, GRA, and staff benefit rates.  Wrote
  a query to update the cost codes.  Began working on report changes.
- Worked with Mike on the rebuild of pc72 and the replacement for pherkab.
- Made web site changes -- LSC reports and talks, postdoc position,
  publications.
 

(Wendy)
- Installed Office on a PC, then worked on other problems with that PC.
- Inventoried the computers in Synchrotron and updated the inventory map.
- Installed windows patches on a few PCs
- Inventoried a few laptops--the laptops on the list I was given are mostly
  traveling at this time, so these will need to be found at some later time
 

(Mick)
- Continued working on inventory data
- Modified web FAQs
- Addressed problem with Helena's ZIP drive, eventually replacing it
- Helped Mike and Larry install new rack-mount PC to become pherkab
- Reconfigured Liz's computer to get her e-mail, rather than Rita's
- Learning to restore files from the daily backups
 

(Mike)
- Getting user and share information together to reload PHERKAB
- Work with Larry to make adjustments on server rack to make room for rack
  mount servers.
- Loaded 2Ghz with all General Computing software and engineering packages
- Working on upgrading ANSYS server to 5.7.1 waiting on License code from
ANSYS.
- PHERKAB, reloaded with NTSRV 4.0 the administrative server which is now
  back-up and running.
- Various user support that included software, hardware issues and printer
  problems.
 

(Lisa)
- Working on sendmail compile on becrux.  This requires gcc to be installed
  locally.  ver. 8.11.6 compiles fine but I'm getting make errors with
8.12.0.
- Worked on clearing up disk space on sirius and helping the 40meter manage
  their file distribution.
- Rebooted kuma.  This required all of the printers to be re-set.
- Made dns and nis+ host changes for the nt servers.
 

(Larry)
- Started the paperwork for the Foundry order. This was the hardware chosen
to
  replace the ATM backbone system for the LIGO CIT network.
- Resolved a couple of disk related issues. Working on increasing the disk
  storage but also we need people to clean off a lot of their old files.
There
  will be a list generated of old dead accounts, that will be passed around
for
  approval to have those accounts removed from the system. This should
happen
  in the next two weeks.
- Working with a group of people along with the Sysadmin group on getting
some of
  the computer security procedures documented.
- Still working on upgrading and getting a few more support servers on-line.
- Checked on the equipment at Downs in the area that had been flooded. One
of
  the LIGO edge switches was ruined from water dripping on it from the
ceiling,
  other than that things looked OK.
- There was a e-mail message sent to everyone on the project asking for
  assistance in some sort of money scheme. This was turned over to Caltech
  security who informed me that the FBI was already working on this problem.
  Everyone that received the message should just delete it.


LIGO II/Advanced R&D (Sanders)


Adv LIGO SUS
Mark Barton

This week I continued developing a model for use in detailed design of
the Advanced LIGO suspension. I added tools for making easy-to-read
tables and 3D plots of mode shapes, and for doing transfer function plots
and published a version 1 at <http://www.ligo.caltech.edu/~mbarton/>SUSmodels>. Since then I've working on adding angular restoring force of
wires near pivot points and improving the calculation of damping and
thermal noise.

From: Helena Armandula <ahelena@ligo.caltech.edu>

"Q" measurements - 3"dia. x .100" thick substrates
Expect to ship 2 thin fused silica substrates to Lyon around October 1st.
The substrates' "Q" has been measured by Gregg Harry and Steve Penn at Syracuse.

Formalized manufacturing specs for sapphire substrates to be used in "Q" studies and sent them to Crystal Systems.

"Q" measurements - 3"dia. x 1" thick substrates
At Sheila's request I am shipping to Glasgow the two extra 3"dia. x 1" thick fused silica substrates that we have at Caltech.
The aim is for Sheila to measure with Jim Hough all 4 substrates in Glasgow during her visit in October.

Advanced LIGO Coatings
Shipped 1" dia. fused silica substrates to MLD for the first run to evaluate coating absorption.
We should receive these parts coated with Ta2O5/SiO2 and annealed at 3 different temperatures within 4 weeks.
 

From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>

Both Lia and Florian flown out home.
 

Charlotte
Problems in getting the effective bending point of flex joints under
different stresses
Studied maximum stress versus connecting radius of flex joint blade to
bulk above and below the joint.
 

Lia, Riccardo
 

The data acquisition card that showed signs of instability suddenly went
completely sick on us, small sudden steps are visible in the DAQ that
mask the logarithmic creep behavior visible the first week The data of
the week appears to be a complete waste.  A new DAQ card was ordered and
installed.
 

Charlotte, Virginio, Lia
Found same problems also in new card, installed new card driver
software, maybe less but still jumps are visible.  Also installed
witness LVDTs and found them to drift (creep-like).
The jumps seem to be a software problem (they jump both high and low so
they are not catastrophic creep events), maybe an offset file
overwrite.  We will try to replace the computer in case its memory has
problems.
For the witness LVDT “creep” only explanation may be that to save on
costs we made them of nylon instead of Peek or Ceramics.  They may be
drying and shrinking in the dry environment of the creep oven.  Will
replace all of them with Peek ones.
 

Akiteru, et al. @ Hongo
At Okinawa for the JPS meeting.
 

Alessandro @ Pisa
Getting bids for the NC-US machine.
Testing the mechanics of a prototype of vertical accelerometer.  Working
fine down to 0.3 Hz.
Broken the last prototype of horizontal accelerometer with ground flex
joints at the end of machining.  Need to revise procedure and remake.


For additional information about this report, contact sanders@ligo.caltech.edu