Weekly Report for Week Ending September 13, 2001


 Exec. Comm. Agenda
Highlights
LSC
Administration
Hanford Observatory
Livingston Observatory
MIT
Caltech
Detector
40 Meter
TNI
LASTI
Data Analysis
LIGO II/Adv. R&D
Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  September 17, 2001 will be:

 (Meeting time: 10:30 am Pacific Time)

Open meeting 10:30 - 11:30

  1. Announcements
  2. LSC Issues (Weiss)
  3. Comments on Weekly Report
  4. WBS 1 LIGO I Construction (Lindquist)
  5. WBS 2 LIGO Lab Operations
  6. WBS 3 and 4  Advanced R&D and LIGO II (Sanders)
Executive Committee only 11:30 - noon   Topics:
 

Special Items:


Special Announcements:


Weekly Report Highlights
 


LSC Issues (Weiss)


no report


LIGO I Construction/LIGO Laboratory Administration (Lindquist)



 

WBS 1.2 LIGO Operations--Administration



LIGO Weekly Site Telecon (Lindquist)

The following topics were discussed during the site teleconference on Thursday, September 13, 2001.

The list of current actions revised to reflect the status of open actions assigned through September 13, 2001 may be found at ACTION LIST.

PROPERTY MANAGEMENT (Chargois)

From: Ed Chargois <chargois_e@ligo.caltech.edu>


DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner - turner@ligo.caltech.edu>

Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .

ACCOMPLISHMENTS

>From: Cleveland Mak <mak_c@ligo.caltech.edu>

ACTIVITY

Packages Faxes
In 36 37
Out 11 46

Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.


COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Kaufman)

From: Esther Cunningham <esther@ligo.caltech.edu>

Press here for ACCOUNTS PAYABLE HISTORY DATA.

From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

From: Florence Kaufman <fkaufman@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: irena@ligo.caltech.edu (Irena Petrac)

From: Ed Jasnow <jasnow@ligo.caltech.edu>

SUPPORT (Wood)

 
Dorothy Lloyd Rita Torres
  • A short report this week.  Spent most of my time chasing documentation for Pcard purchases.  Will have reconciled over 21 this period.  Placed a few more orders this week.  Did site trip updates.
  • Irene Baldon Elizabeth K. Wood

    Advanced LIGO (Frey)

    From: Thomas Frey <tfrey@ligo.caltech.edu>

    Progress Period from 09.07 to 09.13

    Accomplishments:

    Schedule 09.14 to 09.20:

    WBS 1.4.1.2   Project Controls (LIGO Construction)



    Reports (Lindquist)

    The end-of-August Quarterly Progress Report will be due at the end of September, and I have requested contributions by September 21.  This could be the last Quarterly Progress Report required under this Cooperative Agreement, although we will still have to provide some kind of Annual or Final Report.  Under the new Cooperative Agreement, we think that only an Annual Report will be required.



    Change Control/Contingency (Lindquist)

    The following Change Requests have been submitted.
     

    CR-010006 WBS 1.1.4 (OPS) Roof Shelter for Concrete Pad Adjacent to Erosion Control Pond (Livingston) M. Coles
    CR-010007 WBS 1.2.4 Core Optics Components, Repolish/Recoat Beamsplitter S. Whitcomb
    CR-010008 WBS 1.1.4 Five-Ton Crane for the Staging Building in Hanford O. Matherny
    CR-010009 WBS 1.4.2 (OPS) Additional 10-W Laser for PSL Lab S. Whitcomb
    CR-010010 Advanced R&D Seismic Isolation System PD ETF Mechanical Contract (APPROVED) D. Coyne/ G. Stapfer

    We scheduled a meeting of the LIGO Change Control Board for Tuesday, September 11, 2001, at 9:00 am PDT. An agenda was distributed electronically (LIGO-M010244-00-P).  This meeting was postponed in light of national events and will be rescheduled.

    Press for the latest Contingency Needs Projection.


    COST SCHEDULE CONTROL SYSTEMS (Duncan, Akutagawa)

    From: Kris Duncan <kris@ligo.caltech.edu>

    From: Cindy Akutagawa <cindy@ligo.caltech.edu>

    SUBCONTRACTS MANAGEMENT (Jasnow)

    From: Ed Jasnow <jasnow@ligo.caltech.edu>


    Quality/Safety (Tyler)

    >From: Bill Tyler <tyler@ligo.caltech.edu>

    No report this week.
     


    LIGO Hanford Observatory (LHO) Operations (Raab)


    General Items:
    --------------
    (F. Raab)
     

    We have cooled down the LVEA and work has begun to bring up the interferometers.
     
     

    IOO/ISC Work (C.Gray)
     

    Have completed assembling and aligning optic components on ISCT3; it now
    needs its enclosure and to be positioned near HAM3.  Installed additional
    acoustic panels on enclosures for the 2k & 4k.
     

    Sent an SOS tower and hardware to MIT for balancing of LASTI optic-work.
     
     


    LIGO Livingston Observatory (LLO) Operations (Coles)


    Detector: Optics and Installation: Installation of the door hardware for the Laser Safety Interlock system continues, as well as additional exterior security cameras at both ends. Ordered additional IR viewers, cards and lab hardware. Completed calibration of WFS-1. (Jonathan Kern)

    LDAS - Yesterday I successfully got BigBrother to run under the configuration that was decided upon for LDAS. I now have to create a configuration file for each of the additional sites, which should not take very long since they will be very similar. The next step is to integrate Tripwire and the temperature monitoring scripts.
    GC - Tom has still been working with LSU to get them to install the second T1. It seems that we are not their top priority at this point. They said that they have been having ongoing problems with their main router.
    CDS - Nothing to report.
    (Shannon Roddy)

    CDS: We have completed an inventory of supplies in the lab.  In general we are in pretty good shape. An inventory of all test equipment is ongoing and should be complete early next week. Disconnects have been installed on all the clean rooms. This allows for turning on the lights while leaving the fans off. We have installed new receptacles, video jacks, and ethernet connections along the back wall - across from the CDS racks. Installation of video cables, communication cables, and power for the new cameras, as part of the laser safety installation, is ongoing and should be complete in two weeks. (Rus Wooley)


    Detector/Technical Support (Whitcomb, Coyne)


     
     
    Installation& Commissioning:

    Hanford
    Livingston

    Other Science/EngineeringActivities:

    Design/Analysis/Fab
    Issues/Concerns

    See also the daily electronic logs for the installation and commissioning activities:

    Hanford Detector Log

    Livingston Detector Log

    See also the Installation web page

    1.1 LHO INSTALLATION & COMMISSIONING

    Commissioning

    The air conditioning was turned back on Monday after one week of "baking" the  LVEA.

    A quick estimate is that the outgassing rate for water went up by about a factor of 5

    during the 10 days that the temperature was held high; this would mean that the one

    week was the equivalent of two months of pumping.  The pressure is back to where it

    was before the "bakeout" and still dropping, indicating that at least some parts of the

    stacks are still probably at elevated temperatures.

    Both 10 W lasers were restarted on Monday and their reference cavities stabilized in

    temperature.  The lasers for both interferometers have been locke to their premodecleaner

    and frequency reference cavities.

    Rolf has been working on the digital suspension to integrate the excitation and test

    points, so the alignment of the 4 km interferometer is on hold until that is completed.

    In the meantime, Luca, Rick and Paul have been making measurements of the

    Pockells cell path transfer function on the 4 km laser.

    Dick Gustafson has been investigating the Pentek DACs, driving them with digital

    ramps from the GDS, and looking at the analog output.  The output varies quite a

    bit from channel to channel, with the best channels looking pretty good, and the

    worst ones showing uneven steps and even some deviations from monotonic-ness.

    Since we have many more DAC channels than we need (a consequence of our

    greater usage of ADC channels) there is probably some benefit to selecting to the

    "best" channels, assuming we can find the right measure of "goodness".

    The 2 km modecleaner has been aligned and locked.  The IO train and the PRM

    have been roughly aligned. The next step would be to use the arms for fine alignment,

    but there is still enough drift (due to the cooling stacks) that this doesn't look

    practical today.  Maybe tomorrow.

    1.2LLO INSTALLATION & COMMISSIONING

    Commissioning

    Rai Weiss reporting

    Work on the frequency stability of the Laser/Mode Cleaner system

    * continued refinement of the new servo boards

    * installation of improved beam dumps on the laser table

    * removal of cooling loops to the NPRO

    * tuning of the notch to remove the remaining vertical bounce mode of the

      mode cleaner

    Net result is an improved noise spectrum which is dominated by room

    acoutic noise driving mechanical resonances in the PSL in the 100 to

    300 Hz band and the periscope beam resonance around 100Hz.

    The Q of the coupled cross and the longitudinal modes of the etmy was

    measured. They are 0.9M, 2.9M and 6M, high enough to not figure in the

    internal thermal noise budget for LIGO I.

    The drag wiping of all the cavity mirrors during the most recent opening

    has not increased the mirror scattering. The dominant scattering is from

    points.

    We have tried to lock the recombined Fabry-Perot/Michelson and not yet

    succeeded.

    2.0 OtherEngineering and Scientific Activities

    2.1 Design/Analysis/Fab

    Digital Suspension Upgrade (LHO 2K & LLO 4K)

    Jay Heefner

    Module production is as follows:
     
    Module
    Needed
    Fab Complete
    Tested
    SUS PD Interface
    29
    34
    20
    Anti-Image
    12
    16
    7*
    Universal Dewhite
    22
    25
    25
    LOS Coil Driver
    14
    13
    10
    LOS Bias
    14
    17
    14
    SOS Dewhite
    11
    16
    16
    SOS Coil Driver
    15
    24
    24
    Opt. Lever Intface
    15
    16
    16

    We currently have enough modules to complete the LHO 2K. We should be fully complete by the 3rd week of Sept.

    Digital Suspension (LHO 4K)

    Rolf Bork

    At LHO this week, trying to finish up testing and debugging code which runs with GDS. As near as I can tell, all DSC TP/EX are now functioning properly. A have a few more items I need to cleanup, mostly cosmetic, and it should be ready to run.

    Spare Electronic Modules

    Jay Heefner, Rich Abbott, Rick Karwoski, et. al.

    Production of spares for ASC, SUS, LSC and PSL continues.

    LLO Micro-Seismic Feed Forward

    Jay Heefner

    - The system wiring diagrams are 90% complete. Rack numbers need to be added 

    before they can be completed and cross connect and cable pull lists generated.

    - The SEI Interface module has been designed and layout complete. Boards are due 

    back by 9/14. They will be stuffed and tested next in preparation for 

    installation and test if the system the week of 9/24. These boards will also be 

    useful in the future for interfacing signals to the ADC inputs of a Pentek.

    Rolf Bork

    Lori has begun work on the primary functions required.  Next week,

    I'll then link these with existing ASC code in preparation for delivery

    to LLO week of Sept. 24.  (In light of recent events, we may delay this

    trip a week or two).

    IO Periscope

    Mike Smith, Ken Mailand, Mark Barton

    Tests are continuing. All resonances below 175 Hz are not associated with the periscope structure. With the mirror plate and mount removed, the basic structure has a symmetric bending mode at 200 Hz, x and y-bending modes at 240 Hz, and a torsional mode at 325 Hz. When the mirror plate and Optosigma mount with PZT mirror are added, the modes shift to lower frequencies with the lowest mode at 176 Hz. Side stiffener plates are being added, and the structure will be tested later this week with both the Optosigma mount and the Ultima mount. A shipping container has been built, and the periscope and the new PZT tilt platforms will be shipped to LLO as soon as the tests are completed; shipment is expected by 9/18. Quotations for the production of 3 more units have been received.

    PSL

    Peter King

    The spare VCO shipped to LLO had an incorrect capacitor installed for the 1.6/40 Hz pole-zero pair combination. This will be remedied when the correct capacitor is shipped from campus.

    Lee Cardenas

    The laser 126 MOPA S/N 110 received from Lightwave (destined for LASTI) is already installed on the optical table and making the changes necessary (install and align in place a Pockels Cell ) and operating procedures is on the way.

    20 pcs of PZT housing for the new generation of PMC has been baked and they are ready.

    The new baking chamber 24 inches long x 10 inches in diameter it is as well baked and clean, ready to be used if anybody needs it.

    I finally have laser light ( from a NPRO laser) going through the ref. cavity.

    Rick Karwoski, Sander Liu

    LHO Spares
    Two RFPDs tested and ready for shipment.

    LLO Spares
    Two RFPDs tested and ready for shipment.  Still short one PMC -- We expect delivery of the new PMC has been delayed by the crisis on the East Coast.

    Further Detail Provided by Sander:
    Finished writing the RFPD Acceptance Test Procedure.

    GEO/LASTI/CAmpus Spares
    GEO 80 MHz VCO was delivered this week and is ready for testing. Work continues on the kitting/stuffing of the remaining spares. Don and Rita are managing the parts pipeline.  No major issues.

    PSL Schematic Effort
    In the meantime the final leg of the PSL document up-date endeavor is in process.  All schematics should be rev'd and in DCC with appropriate ECNs on everything by week's end.

    LSC

    Rich Abbott, Mohana Mageswaran, Flavio Nocero

    - Flavio has taken over the Common Mode servo and is overseeing the building and testing.  He is simultaneously doing the evaluation of the timing system re-design and the seismic feed forward solution.  Flavio and Rich will be at LLO in the next week or so.

    - Mohana has resumed work on the photon recoil calibration system and at the same time is tracking the changes with the MC servo from a CAD standpoint.

    - Mohana did a tourof the PSL lab with Bill Tyler, Caz & Hack at the Lauritsen Lab, with the intent of adding the photon calibrator laser into the SOP. Bill Tyler will be making the arrangements for me to get the goggles and I will be soon start working on the photon calibrator.


    40 Meter Interferometer (Weinstein)




    Thermal Noise Interferometer (Libbrecht)


    no report


    LASTI (Zucker)


    no report


    Data Analysis and Computing (Lazzarini)


    Simulation and Modeling (Bhawal)
     

    Mode mismatch
    --------------
    Hiro's calculation: The modal field in a FP cavity was calculated to validate
    the e2e code. One case was that the curvature of the mirror does not match the
    field wave front curvature, and the other is the mirror tilt. Due to the coupling
    to various modes, the TEM00 amplitude becomes like:
    1 / ( 1 - R*exp(i 2 phi) ( 1 - del ) )
    where phi is the phase gain per trip and del is the correction due to mode mixing.
    For these two cases, it is shown that del to the second order of the distortion:
    del = I A + ( 1 - R ) B
    where A and B are values of the second order of distortion. By the locking
    mechanism, imaginary part of del (I A) can be canceled out. This way, the
    TEM00 power on resonance becomes:
    1 / ( 1 - R ( 1 + (1-R)B ) = 1 / ( (1-R) ( 1 + B ) )
    i.e., the effect of the disturbance is independent of the finess of the cavity.
     

    Biplab is working on similar issues related to beam-shifting and mirror-tilts
    and making consistency checks using both analytical calculations and e2e runs.
    A '+/-' sign bug in the part of mirror tilt originating from its lateral shift was
    found and eliminated.
     

    Mechanical simulation
    ---------------------
    (Virginio) working to fit better the psd and the tf I got from my measurements
    of the suspension system at MIT.
     

    Alfi
    ----
    (Bruce)
    - Finishing the initial implementation of all Alfi bookkeeping class methods.
     

    (Melody)
    - Continuing on implementating of graphics portion of alfi5. Worked on
      the window manager and drawing of the primitive nodes and ports
    LIGO Data Analysis System
     

    Software Systems (Blackburn)
     

    Most of this week was focused on supporting the Mock Data Challenge for
    LDAS, the burst and the stochastic upper limits groups. All search codes
    (power, cluster, slope, ifo-ifo, ifo-bar) were successfully run within
    the LDAS system by the weekend. LDAS performed particularly well with only
    a handful of minor issues coming up. It was never necessary to change any
    thing other than interpreted TCL script code to support or fix functionality
    needed at the MDC. Other issues that came up that did not require immediate
    attention have already begun to be implemented in the post-MDC LDAS system
    running at CIT's development site.
     

    One issue that came up at the MDC was the handling of search codes running
    on the beowulf which had terminal failures such as a segmentation violation
    on search nodes. The current wrapperAPI master design waits indefinitely for
    a search node to respond. This is being change to have a ~5 minute limit at
    which time the search will be terminated to avoid the lose of available
    nodes
    in the queue which was witnessed during the MDC.
     

    The biggest changes to LDAS during the MDC were the determination of a
    need to have a "search" type identification column in the burst tables
    of the database and a fix to allow more than 5000 events to be inserted
    into the database by a single search code job. Both were easy fixes which
    did not require rebuilding/compiling of LDAS.
     

    A concentrated effort went into configuring a single computer to run all
    of LDAS (all APIs, the DB2 database and the parallel search codes). This
    effort has resulted in marginal success with only minor issues still in
    the way of declaring victory and providing a complete guide for LSC
    members to configure and run LDAS on their personal computers.
     

    A modified guild that can operate through a "mapping" router (one
    that translates IP addresses) or a firewall, using a proxy service
    was set up and is running at Caltech.
     

    Looked into the Thread extension provided with Tcl 8.3 and 8.4 as an
    alternative to running threads in our own C++ procedures. The Thread
    extensions allows a Tcl interpreter to be started in its own thread
    which can be used to perform a script, giving the result back to the
    parent. However, full functionality is only provided in Tcl 8.4 which we
    have not been able to get to work with LDAS yet.
     

    Hardware Systems (Anderson)
     

    LDAS Administration
    -------------------
    Caltech
    -------
    (Dan Kozak)
     

    Lots of HPSS handholding--constant tape repacking, bad tapes needing
    recovery.  Added tapes to storage classes to support the ingestion of
    E5 data.
     

    Testing of the "big rig" QFS system showed aggregate read bandwidth of
    120-130Mb/sec (133 Mb/sec with 7 processes being the peak).  Questions
    are in to LSC/Sun about what configuration would give us more.
     
     
     

    (Al Wilson)
     

    Finished changing the remaining LDAS passwords at Caltech.
    Debugging a few stability problems with m71.
    Re-arrange LDAS machine room to support the new Griphyn related PC.
     
     
     

    (Stuart Anderson)
     

    After UPS lost the initial shipment of E5 data from LLO a second
    copy was made from the LDAS disk cache, sent via FedEX, and
    successfully archived into HPSS at Caltech. Since government property
    is not eligible for insurance the estimated reimbursement from UPS
    is $100 for over a $1000 worth of equipment.
     

    The web based interface to the LDAS software mirroring scripts was
    enhanced to provide automated refresh capabilities.
     
     
     

    MIT
    ---
    (Keith Bayer)
     

    wrote up BTU counts for all systems in ldas lab room
    reset passwords on E450/T3
    troubleshot/replaced failed T3 drive
    monitored temps while a/c work done on roof unit
    mdc support
     
     
     

    Livingston
    ----------
    (Shannon Roddy)
     

    LDAS - Yesterday I successfully got BigBrother to run under the
    configuration that was decided upon for LDAS.  I now have to create a
    configuration file for each of the additional     sites, which should
    not take very long since they will be very similar.  The next step is to
    integrate Tripwire and the temperature monitoring scripts.
     
     
     

    Hanford
    -------
    (Greg Mendell)
     

    1) Continued work on the known pulsar search code DS0.  The code currently
    takes the input data given to it by the stand alone wrapper from
    an ilwd data file (later to be supplied by an LDAS pipeline command)
    and extracts out the gravity wave channel time series.  From this data
    it computes SFTs. Sky position and spin down parameters from the command
    line are used to compute a demodulated DFT using LALComputeSky and LALDemod.
    The maximum and mean power of the result are recorded, for the database.
    The code compiles and runs without errors, but does not yet produce
    reasonable numbers.  Debugging is underway.
     

    2) Finished connecting fb3 (the new framebuilder) to the Sun T3 disk farm.
    Ran some simple test of the connection which showed a stable 21-24 MB/s
    write capability between fb3 and the T3s.  Alex started the framebuilder
    on fb3 for further testing.
     

    3) Installed Solaris 8 on sunbox1 and ran test of the cfdef
    configuration script.
     

    4) Started a backup script as a cron job on the LHO LDAS network.  Root
    file systems (and soon the db2 file system) have a full backup every week,
    and are incrementally backed-up every day.  Tested Linux dump and restore
    command and Solaris ufsdump and ufsrestore commands.  These passed for
    backing up and restoring individual files.
     

    Data Analysis Activities
     

    Charlton:
     

    In the week since last Thursday until Monday afternoon I was supporting
    the MDC:
     

    * helping DSO writers with coding issues:
        - interfaces between wrapperAPI and DSO and DSO and LDAS database
        - Tcl scripting for LDAS pipelines
        - anlysing problems with DSOs and LDAS
     

    * helping administrate LDAS at MIT
     

    * running some MDC tests
     

    During this week:
     

    * spent some time with Massimo Tinto, Jeff Edlund discussing the next
    stage of work for the FCT, and changes to the FCT paper being submitted to
    the Amaldi proceedings
     

    * looked into the Thread extension provided with Tcl 8.3 and 8.4 as an
    alternative to running threads in our own C++ procedures. The Thread
    extensions allows a Tcl interpreter to be started in its own thread
    which can be used to perform a script, giving the result back to the
    parent. However, full functionality is only provided in Tcl 8.4 which we
    have not been able to get to work with LDAS yet.
     

    General Computing (Wallace)
     

    MIT:
    (Keith)
    -Wrote backup utility for new fileserver.
    -Helped with CDS equipment
      rebuild aneirin (after failed fan on motherboard)
      fsckd disks on framebuilder
    -Setup packages on pc for Marie Woods (new)
    -Setup machines for new grad students
    -Worked on the video conferencing.
     

    Livingston:
    (Tom)
    -Still working with LSU to get them to install the second T1.
    It seems that we are not their top priority at this point.
    They said that they have been having ongoing  problems with their main
    router.
     

    Hanford:
    (Christine)
    -Working as an operator this week.
     

    CIt:
    (Mike)
    -Worked on audio for Video Conferencing, connecting to POLYCOM to computer
    to used TCP/IP to transmit audio input and out transmission.
    -Updated webpage for Albert who mentioned there were multiple editorial
    adjustments needed for clarity, plus he requested additional information to
    be included.
    -Setup a U10 workstation with Lisa.
    -Setup a PC with video camera for VRVS conference on the west bridge third
    floor conference room.
    -Donna, installed and configured citrix client software to connect to Oracle
    Discoverer server, and worked printer issues.
    -Mike Smith, troubleshooting printer issues to get him connected to color
    printer located on second floor, this turned out to be a bad ethernet cable.
    -Rick Karwoski, correct some networking problems he was having with his
    workstation in his office.
    -Riccardo DeSalvo, went with him to Downs building to troubleshoot some PC
    problems that he is having when he runs LabView software.
    -Started working on setting up Ghost Network server.
     

    (Wendy)
    - password protected BIOS on PCs with Mick
    - updated virus definitions on a few PCs and then manually scanned them
    - ran virus removal tools on infected computer
    - updated inventory map--there were quite a few changes while I was gone
     

    (Lisa)
    - I've been teaching Mick and Mike how to install sol8 and configure a
    workstation for GC.  We've rebuilt 2 workstations so far.
    - Did a full security audit on the inetd.conf files of every (at least I hope
    every) unix workstation at CIT. Things look pretty good right now.
    - Spent 8 hours working on getting Cadence to run on Windows 2000 using the unix
    license server.  The windows licensing and installation is nowhere near as
    robust as on unix.
    - Finished configuring the bdl gateway and took that up to the bdl.
    - Did a full tape backup of becrux in preparation for a rebuild.
    - Generated a bunch of nis+ rootkeys for LDAS.
     
     
     

    (Barbara)
    - Continued efforts on roster web page and search tool.  Fixed problems
    with certain combinations of data and missing data.
    - Posted videoconferencing pages, new fellowships, meetings, updated FAQs
    for GC, employment, ...
    - Working with DMC on the Kamionkowski tape.
    - Fixed problem with web services on antares.  Compacted DCC databases.
    - Did a lot of housekeeping on the LIGO web site.
     

    (Mick)
    -Continued work on formatting inventory data and resolving inventory gaps.
    -Installed Win2000 on m55 to test cadence.
    -Password protected a number of PCs (BA23 and 3rd, 2nd floor)
    -Addressed problem with hpcolor2 with Mike - recrimped end of network
    cable.
    -Loaded cor, including installation of Solaris 8, configuration, FLASH
    PROM, and MU.
     

    (Larry)
    -Ordered a few more computers to upgrade some of the older PC's. Once the new
    units arrive we should have a computer for every seat. Working on a number of
    maintenance contract changes. Working out the details for the GIGE network
    upgrade. That order should be started by the end of next week.
    A number of the vendors have informed me that orders will be delayed because of
    the closure of the airports.
    -Started things going to get the single mode fiber installations done at the 40M
    and Wilson House to Bridge. This is part of getting things moved to a GIGE
    backbone.
    -Worked with Mike on a number of the video conferencing issues. We still have
    some logistics to work out but it is looking pretty good. Mike has a pretty good
    web page that he is posting.
    -Worked on a number of virus issues. We've had a few machines that were infected
    because of infected e-mail being opened, infected files transferred and not up
    to date virus definition files. However, most people are working on keeping
    their machine secure.
    -Worked on a number of e-mail issues, including setting up new alias groups. We
    are still looking at different programs that will perform a virus scan on the
    e-mail server.
     


    LIGO II/Advanced R&D (Sanders)


    From: Helena Armandula <ahelena@ligo.caltech.edu>
    Subject: Weekly report
    Cc: coyne@ligo.caltech.edu, willems@ligo.caltech.edu
     

    "Q" measurements / coating
     

    These parts are reworks from Mindrum. Wave Precision had some trouble with them also, maybe there was a problem with that particular batch of glass.
     

    According to Wave Precision hopefully the thick parts will be finished by Wednesday 12th and shipped. If not, they definitely will be finished and shipped by Friday.
    About the thin parts - they are still working on them. They might not be within the flatness spec, but will be somewhere in the neighborhood.
     

    Generated and delivered prints to Mackowski indicating bevel size and masking areas on the thin substrates.
     

    Silicate bonding:
    Monitoring substrate stress at different baking temperatures.

    40m system
    Rolf Bork
    - DAQ: Tried to install framebroadcaster last Friday. The reflected
    memory network board is seeing data and interrupts from the DAQ
    controller, but the CPU is not getting the interrupts. Will continue
    work on this when I get back to Caltech next week.
    - CDS server: Began creating the same CDS directory structure as
    exists at the sites and moving all CDS code into those areas. Once this
    is done, we will load the appropriate scripts to get auto backup/restore
    operational. Again, this will probably not complete until next week.
     

    Adv LIGO Optical Modeling
    Bill Kells
    I have been working on the final issues of comparison
    of the FFT code results with equivalent MELODY results.
    We are trying to get the paper which has been in draft on
    this for some time finished up this week. It seems that final
    issues of Thermal lensing in both codes have been reconciled.
    Also I have concentrating on finishing up the matching questions
    for LIGO II. That is, with large thermal lensing, how much carrier
    power is going to be actually coupled into the arms? This has proved
    to be a rather subtle problem. The simple modal models are not
    directly applicable without modification (they typicall assume
    ideal matching between the RC and arm cavities, a very good approx.
    for the LIGO I carrier).
     

    Adv LIGO COC
    Helena Armandula
    Just received the CO2 cleaner for the 40m lab.
    MIT should have the one ordered for them.
     

    Adv LIGO SUS
    Janeen Romie
    Working on 40m TM suspension design.
    Working on AdLIGO SUS BOE.
     

    Mark Barton
    I did various calculations in support of the Advanced LIGO
    Suspensions.
     

    Adv LIGO SEI
    Rich Abbott
    - Worked on the specifications to the voice coil actuator driver with a focus on the thermal issues that the coarse actuator presents in vacuum.
    - Evaluated some LVDT based position sensors for use in the seismic feed forward scheme.
    - Working on the packaging for the electronics associated with the capacitance position sensors. This consists mainly of procurement and specifying.
     

    From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>

    Lia, Charlotte, Riccardo
    Finalized Creep facility and FINALLY started first measurement round
    with 8 maraging 250 blades at different stress levels.
    The blades have high Q and are excited by the air re-circulation fan up
    to amplitudes of several microns, we get substantial aliasing noise from
    the DAQ time slots.
    Over the week end we tried several DAQ strategies to minimize aliasing
    noise: sampling at 250Hz and averaging online over 4s gives 2-3 micron
    noise, averaging offline over 100 s gives 0.3 microns (obviously still
    dominated by aliasing noise).  Better results obtained by fitting the
    main harmonic component and keeping the constant term, but the method is
    cumbersome.  May need to fit all 3 harmonics online.
    For now running 4 second DAQ windows with simple online averaging, this
    will be sufficient for now.
    Started a first run with 5 temperature palliers each 3 weeks long.
    After that we will try other samples, possibly of different materials.
     

    On Sunday afternoon we sustained an interesting, small (4.2 Richter)
    earthquake (epicentre in Hollywood).
    The synchrotron crane bridge made an interesting noise when it landed
    back on its rails.
    The SAS chain close by was observed NOT to be moving by any visible
    amount immediately after the quake.
     

    Chenyang
    Setting up electrostatic actuator.
     

    Akiteru, et al. @ Hongo
    Assembling a small Michelson with one mirror on the SAS tower.
     

    Yukioshi, Tatsuo
    Measuring the double pendulum control transfer function.
    Akiteru
    Working on feedforward on IP.
    Some residual problems with accelerometer diagonalization traced to the
    IP excitation method.
     

    Alessandro @ Pisa
    Organizing for more flex joint machining with UltraSounds.


    For additional information about this report, contact sanders@ligo.caltech.edu