|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The LIGO Executive Committee Agenda for Monday September 17, 2001 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
Special Items:
no report
WBS 1.2 LIGO Operations--Administration
The following topics were discussed during the site teleconference on Thursday, September 13, 2001.
From: Ed Chargois <chargois_e@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .
ACCOMPLISHMENTS
ACTIVITY
| Packages | Faxes | |
| In | 36 | 37 |
| Out | 11 | 46 |
Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS PAYABLE HISTORY DATA.
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
From: irena@ligo.caltech.edu (Irena Petrac)
SUPPORT (Wood)
Irene BaldonA short report this week. Spent most of my time chasing documentation for Pcard purchases. Will have reconciled over 21 this period. Placed a few more orders this week. Did site trip updates.
Progress Period from 09.07 to 09.13
Accomplishments:
WBS 1.4.1.2 Project Controls (LIGO Construction)
The end-of-August Quarterly Progress Report will be due at the end of September, and I have requested contributions by September 21. This could be the last Quarterly Progress Report required under this Cooperative Agreement, although we will still have to provide some kind of Annual or Final Report. Under the new Cooperative Agreement, we think that only an Annual Report will be required.
The following Change Requests have
been submitted.
| CR-010006 | WBS 1.1.4 (OPS) | Roof Shelter for Concrete Pad Adjacent to Erosion Control Pond (Livingston) | M. Coles |
| CR-010007 | WBS 1.2.4 | Core Optics Components, Repolish/Recoat Beamsplitter | S. Whitcomb |
| CR-010008 | WBS 1.1.4 | Five-Ton Crane for the Staging Building in Hanford | O. Matherny |
| CR-010009 | WBS 1.4.2 (OPS) | Additional 10-W Laser for PSL Lab | S. Whitcomb |
| CR-010010 | Advanced R&D | Seismic Isolation System PD ETF Mechanical Contract (APPROVED) | D. Coyne/ G. Stapfer |
We scheduled a meeting of the LIGO Change Control Board for Tuesday, September 11, 2001, at 9:00 am PDT. An agenda was distributed electronically (LIGO-M010244-00-P). This meeting was postponed in light of national events and will be rescheduled.
Press for the latest Contingency Needs Projection.
From: Kris Duncan <kris@ligo.caltech.edu>
From: Ed Jasnow <jasnow@ligo.caltech.edu>
No report this week.
General Items:
--------------
(F. Raab)
We have cooled down the LVEA and work has begun to bring up the interferometers.
IOO/ISC Work (C.Gray)
Have completed assembling and aligning optic components on ISCT3; it
now
needs its enclosure and to be positioned near HAM3. Installed
additional
acoustic panels on enclosures for the 2k & 4k.
Sent an SOS tower and hardware to MIT for balancing of LASTI optic-work.
Detector: Optics and Installation: Installation of the door hardware for the Laser Safety Interlock system continues, as well as additional exterior security cameras at both ends. Ordered additional IR viewers, cards and lab hardware. Completed calibration of WFS-1. (Jonathan Kern)
LDAS - Yesterday I successfully got BigBrother to run under the configuration
that was decided upon for LDAS. I now have to create a configuration file
for each of the additional sites, which should not take very long since
they will be very similar. The next step is to integrate Tripwire and the
temperature monitoring scripts.
GC - Tom has still been working with LSU to get them to install the
second T1. It seems that we are not their top priority at this point. They
said that they have been having ongoing problems with their main router.
CDS - Nothing to report.
(Shannon Roddy)
CDS: We have completed an inventory of supplies in the lab. In general we are in pretty good shape. An inventory of all test equipment is ongoing and should be complete early next week. Disconnects have been installed on all the clean rooms. This allows for turning on the lights while leaving the fans off. We have installed new receptacles, video jacks, and ethernet connections along the back wall - across from the CDS racks. Installation of video cables, communication cables, and power for the new cameras, as part of the laser safety installation, is ongoing and should be complete in two weeks. (Rus Wooley)
|
|
|
|
Installation&
Commissioning:
|
Other
Science/EngineeringActivities:
|
See also the Installation web page
A quick estimate is that the
outgassing rate for water went up by about a factor of 5
during the 10 days that the
temperature was held high; this would mean that the one
week was the equivalent of two
months of pumping. The pressure is back to where it
was before the "bakeout" and
still dropping, indicating that at least some parts of the
stacks are still probably at
elevated temperatures.
Both 10 W lasers were restarted on Monday and their
reference cavities stabilized in
temperature. The lasers for both interferometers
have been locke to their premodecleaner
and frequency reference cavities.
Rolf has been working on the digital suspension to
integrate the excitation and test
points, so the alignment of the 4 km interferometer
is on hold until that is completed.
In the meantime, Luca, Rick and Paul have been making
measurements of the
Pockells cell path transfer function on the 4 km laser.
Dick Gustafson has been investigating the Pentek DACs,
driving them with digital
ramps from the GDS, and looking at the analog output.
The output varies quite a
bit from channel to channel, with the best channels
looking pretty good, and the
worst ones showing uneven steps and even some deviations
from monotonic-ness.
Since we have many more DAC channels than we need
(a consequence of our
greater usage of ADC channels) there is probably some
benefit to selecting to the
"best" channels, assuming we can find the right measure
of "goodness".
The 2 km modecleaner has been aligned and locked.
The IO train and the PRM
have been roughly aligned. The next step would be
to use the arms for fine alignment,
but there is still enough drift (due to the cooling
stacks) that this doesn't look
practical today. Maybe tomorrow.
* continued refinement of the new servo boards
* installation of improved beam dumps on the laser
table
* removal of cooling loops to the NPRO
* tuning of the notch to remove the remaining vertical
bounce mode of the
mode cleaner
Net result is an improved noise spectrum which is
dominated by room
acoutic noise driving mechanical resonances in the
PSL in the 100 to
300 Hz band and the periscope beam resonance around
100Hz.
The Q of the coupled cross and the longitudinal modes
of the etmy was
measured. They are 0.9M, 2.9M and 6M, high enough
to not figure in the
internal thermal noise budget for LIGO I.
The drag wiping of all the cavity mirrors during the
most recent opening
has not increased the mirror scattering. The dominant
scattering is from
points.
We have tried to lock the recombined Fabry-Perot/Michelson
and not yet
succeeded.
Module production is as follows:
|
Module
|
Needed
|
Fab Complete
|
Tested
|
|
SUS PD Interface
|
29
|
34
|
20
|
|
Anti-Image
|
12
|
16
|
7*
|
|
Universal Dewhite
|
22
|
25
|
25
|
|
LOS Coil Driver
|
14
|
13
|
10
|
|
LOS Bias
|
14
|
17
|
14
|
|
SOS Dewhite
|
11
|
16
|
16
|
|
SOS Coil Driver
|
15
|
24
|
24
|
|
Opt. Lever Intface
|
15
|
16
|
16
|
We currently have enough modules to complete the LHO 2K. We should be fully complete by the 3rd week of Sept.
At LHO this week, trying to finish up testing and
debugging code which runs with GDS. As near as I can tell, all DSC TP/EX
are now functioning properly. A have a few more items I need to cleanup,
mostly cosmetic, and it should be ready to run.
Production of spares for ASC, SUS, LSC and PSL continues.
- The system wiring diagrams are 90% complete. Rack
numbers need to be added
before they can be completed and cross connect and
cable pull lists generated.
- The SEI Interface module has been designed and layout
complete. Boards are due
back by 9/14. They will be stuffed and tested next
in preparation for
installation and test if the system the week of 9/24.
These boards will also be
useful in the future for interfacing signals to the ADC inputs of a Pentek.
Rolf Bork
Lori has begun work on the primary functions required.
Next week,
I'll then link these with existing ASC code in preparation
for delivery
to LLO week of Sept. 24. (In light of recent
events, we may delay this
trip a week or two).
Tests are continuing. All resonances below 175 Hz are not associated with the periscope structure. With the mirror plate and mount removed, the basic structure has a symmetric bending mode at 200 Hz, x and y-bending modes at 240 Hz, and a torsional mode at 325 Hz. When the mirror plate and Optosigma mount with PZT mirror are added, the modes shift to lower frequencies with the lowest mode at 176 Hz. Side stiffener plates are being added, and the structure will be tested later this week with both the Optosigma mount and the Ultima mount. A shipping container has been built, and the periscope and the new PZT tilt platforms will be shipped to LLO as soon as the tests are completed; shipment is expected by 9/18. Quotations for the production of 3 more units have been received.
The spare VCO shipped to LLO had an incorrect capacitor installed for the 1.6/40 Hz pole-zero pair combination. This will be remedied when the correct capacitor is shipped from campus.
Lee Cardenas
The laser 126 MOPA S/N 110 received from Lightwave
(destined for LASTI) is already installed on the optical table and making
the changes necessary (install and align in place a Pockels Cell ) and
operating procedures is on the way.
20 pcs of PZT housing for the new generation of PMC
has been baked and they are ready.
The new baking chamber 24 inches long x 10 inches
in diameter it is as well baked and clean, ready to be used if anybody
needs it.
I finally have laser light ( from a NPRO laser) going through the ref. cavity.
Rick Karwoski, Sander Liu
LHO Spares
Two RFPDs tested and ready for shipment.
LLO Spares
Two RFPDs tested and ready for shipment. Still short one PMC
-- We expect delivery of the new PMC has been delayed by the crisis on
the East Coast.
Further Detail Provided by Sander:
Finished writing the RFPD Acceptance Test Procedure.
GEO/LASTI/CAmpus Spares
GEO 80 MHz VCO was delivered this week and is ready for testing. Work
continues on the kitting/stuffing of the remaining spares. Don and Rita
are managing the parts pipeline. No major issues.
PSL Schematic Effort
In the meantime the final leg of the PSL document up-date endeavor
is in process. All schematics should be rev'd and in DCC with
appropriate ECNs on everything by week's end.
- Flavio has taken over the Common Mode servo and
is overseeing the building and testing. He is simultaneously doing
the evaluation of the timing system re-design and the seismic feed forward
solution. Flavio and Rich will be at LLO in the next week or so.
- Mohana has resumed work on the photon recoil calibration
system and at the same time is tracking the changes with the MC servo from
a CAD standpoint.
- Mohana did a tourof the PSL lab with Bill Tyler, Caz & Hack at the Lauritsen Lab, with the intent of adding the photon calibrator laser into the SOP. Bill Tyler will be making the arrangements for me to get the goggles and I will be soon start working on the photon calibrator.
no report
no report
Simulation and Modeling (Bhawal)
Mode mismatch
--------------
Hiro's calculation: The modal field in a FP cavity was calculated to
validate
the e2e code. One case was that the curvature of the mirror does not
match the
field wave front curvature, and the other is the mirror tilt. Due to
the coupling
to various modes, the TEM00 amplitude becomes like:
1 / ( 1 - R*exp(i 2 phi) ( 1 - del ) )
where phi is the phase gain per trip and del is the correction due
to mode mixing.
For these two cases, it is shown that del to the second order of the
distortion:
del = I A + ( 1 - R ) B
where A and B are values of the second order of distortion. By the
locking
mechanism, imaginary part of del (I A) can be canceled out. This way,
the
TEM00 power on resonance becomes:
1 / ( 1 - R ( 1 + (1-R)B ) = 1 / ( (1-R) ( 1 + B ) )
i.e., the effect of the disturbance is independent of the finess of
the cavity.
Biplab is working on similar issues related to beam-shifting and mirror-tilts
and making consistency checks using both analytical calculations and
e2e runs.
A '+/-' sign bug in the part of mirror tilt originating from its lateral
shift was
found and eliminated.
Mechanical simulation
---------------------
(Virginio) working to fit better the psd and the tf I got from my measurements
of the suspension system at MIT.
Alfi
----
(Bruce)
- Finishing the initial implementation of all Alfi bookkeeping class
methods.
(Melody)
- Continuing on implementating of graphics portion of alfi5. Worked
on
the window manager and drawing of the primitive nodes and ports
LIGO Data Analysis System
Software Systems (Blackburn)
Most of this week was focused on supporting the Mock Data Challenge
for
LDAS, the burst and the stochastic upper limits groups. All search
codes
(power, cluster, slope, ifo-ifo, ifo-bar) were successfully run within
the LDAS system by the weekend. LDAS performed particularly well with
only
a handful of minor issues coming up. It was never necessary to change
any
thing other than interpreted TCL script code to support or fix functionality
needed at the MDC. Other issues that came up that did not require immediate
attention have already begun to be implemented in the post-MDC LDAS
system
running at CIT's development site.
One issue that came up at the MDC was the handling of search codes running
on the beowulf which had terminal failures such as a segmentation violation
on search nodes. The current wrapperAPI master design waits indefinitely
for
a search node to respond. This is being change to have a ~5 minute
limit at
which time the search will be terminated to avoid the lose of available
nodes
in the queue which was witnessed during the MDC.
The biggest changes to LDAS during the MDC were the determination of
a
need to have a "search" type identification column in the burst tables
of the database and a fix to allow more than 5000 events to be inserted
into the database by a single search code job. Both were easy fixes
which
did not require rebuilding/compiling of LDAS.
A concentrated effort went into configuring a single computer to run
all
of LDAS (all APIs, the DB2 database and the parallel search codes).
This
effort has resulted in marginal success with only minor issues still
in
the way of declaring victory and providing a complete guide for LSC
members to configure and run LDAS on their personal computers.
A modified guild that can operate through a "mapping" router (one
that translates IP addresses) or a firewall, using a proxy service
was set up and is running at Caltech.
Looked into the Thread extension provided with Tcl 8.3 and 8.4 as an
alternative to running threads in our own C++ procedures. The Thread
extensions allows a Tcl interpreter to be started in its own thread
which can be used to perform a script, giving the result back to the
parent. However, full functionality is only provided in Tcl 8.4 which
we
have not been able to get to work with LDAS yet.
Hardware Systems (Anderson)
LDAS Administration
-------------------
Caltech
-------
(Dan Kozak)
Lots of HPSS handholding--constant tape repacking, bad tapes needing
recovery. Added tapes to storage classes to support the ingestion
of
E5 data.
Testing of the "big rig" QFS system showed aggregate read bandwidth
of
120-130Mb/sec (133 Mb/sec with 7 processes being the peak). Questions
are in to LSC/Sun about what configuration would give us more.
(Al Wilson)
Finished changing the remaining LDAS passwords at Caltech.
Debugging a few stability problems with m71.
Re-arrange LDAS machine room to support the new Griphyn related PC.
(Stuart Anderson)
After UPS lost the initial shipment of E5 data from LLO a second
copy was made from the LDAS disk cache, sent via FedEX, and
successfully archived into HPSS at Caltech. Since government property
is not eligible for insurance the estimated reimbursement from UPS
is $100 for over a $1000 worth of equipment.
The web based interface to the LDAS software mirroring scripts was
enhanced to provide automated refresh capabilities.
MIT
---
(Keith Bayer)
wrote up BTU counts for all systems in ldas lab room
reset passwords on E450/T3
troubleshot/replaced failed T3 drive
monitored temps while a/c work done on roof unit
mdc support
Livingston
----------
(Shannon Roddy)
LDAS - Yesterday I successfully got BigBrother to run under the
configuration that was decided upon for LDAS. I now have to create
a
configuration file for each of the additional
sites, which should
not take very long since they will be very similar. The next
step is to
integrate Tripwire and the temperature monitoring scripts.
Hanford
-------
(Greg Mendell)
1) Continued work on the known pulsar search code DS0. The code
currently
takes the input data given to it by the stand alone wrapper from
an ilwd data file (later to be supplied by an LDAS pipeline command)
and extracts out the gravity wave channel time series. From this
data
it computes SFTs. Sky position and spin down parameters from the command
line are used to compute a demodulated DFT using LALComputeSky and
LALDemod.
The maximum and mean power of the result are recorded, for the database.
The code compiles and runs without errors, but does not yet produce
reasonable numbers. Debugging is underway.
2) Finished connecting fb3 (the new framebuilder) to the Sun T3 disk
farm.
Ran some simple test of the connection which showed a stable 21-24
MB/s
write capability between fb3 and the T3s. Alex started the framebuilder
on fb3 for further testing.
3) Installed Solaris 8 on sunbox1 and ran test of the cfdef
configuration script.
4) Started a backup script as a cron job on the LHO LDAS network.
Root
file systems (and soon the db2 file system) have a full backup every
week,
and are incrementally backed-up every day. Tested Linux dump
and restore
command and Solaris ufsdump and ufsrestore commands. These passed
for
backing up and restoring individual files.
Data Analysis Activities
Charlton:
In the week since last Thursday until Monday afternoon I was supporting
the MDC:
* helping DSO writers with coding issues:
- interfaces between wrapperAPI and DSO and DSO
and LDAS database
- Tcl scripting for LDAS pipelines
- anlysing problems with DSOs and LDAS
* helping administrate LDAS at MIT
* running some MDC tests
During this week:
* spent some time with Massimo Tinto, Jeff Edlund discussing the next
stage of work for the FCT, and changes to the FCT paper being submitted
to
the Amaldi proceedings
* looked into the Thread extension provided with Tcl 8.3 and 8.4 as
an
alternative to running threads in our own C++ procedures. The Thread
extensions allows a Tcl interpreter to be started in its own thread
which can be used to perform a script, giving the result back to the
parent. However, full functionality is only provided in Tcl 8.4 which
we
have not been able to get to work with LDAS yet.
General Computing (Wallace)
MIT:
(Keith)
-Wrote backup utility for new fileserver.
-Helped with CDS equipment
rebuild aneirin (after failed fan on motherboard)
fsckd disks on framebuilder
-Setup packages on pc for Marie Woods (new)
-Setup machines for new grad students
-Worked on the video conferencing.
Livingston:
(Tom)
-Still working with LSU to get them to install the second T1.
It seems that we are not their top priority at this point.
They said that they have been having ongoing problems with their
main
router.
Hanford:
(Christine)
-Working as an operator this week.
CIt:
(Mike)
-Worked on audio for Video Conferencing, connecting to POLYCOM to computer
to used TCP/IP to transmit audio input and out transmission.
-Updated webpage for Albert who mentioned there were multiple editorial
adjustments needed for clarity, plus he requested additional information
to
be included.
-Setup a U10 workstation with Lisa.
-Setup a PC with video camera for VRVS conference on the west bridge
third
floor conference room.
-Donna, installed and configured citrix client software to connect
to Oracle
Discoverer server, and worked printer issues.
-Mike Smith, troubleshooting printer issues to get him connected to
color
printer located on second floor, this turned out to be a bad ethernet
cable.
-Rick Karwoski, correct some networking problems he was having with
his
workstation in his office.
-Riccardo DeSalvo, went with him to Downs building to troubleshoot
some PC
problems that he is having when he runs LabView software.
-Started working on setting up Ghost Network server.
(Wendy)
- password protected BIOS on PCs with Mick
- updated virus definitions on a few PCs and then manually scanned
them
- ran virus removal tools on infected computer
- updated inventory map--there were quite a few changes while I was
gone
(Lisa)
- I've been teaching Mick and Mike how to install sol8 and configure
a
workstation for GC. We've rebuilt 2 workstations so far.
- Did a full security audit on the inetd.conf files of every (at least
I hope
every) unix workstation at CIT. Things look pretty good right now.
- Spent 8 hours working on getting Cadence to run on Windows 2000 using
the unix
license server. The windows licensing and installation is nowhere
near as
robust as on unix.
- Finished configuring the bdl gateway and took that up to the bdl.
- Did a full tape backup of becrux in preparation for a rebuild.
- Generated a bunch of nis+ rootkeys for LDAS.
(Barbara)
- Continued efforts on roster web page and search tool. Fixed
problems
with certain combinations of data and missing data.
- Posted videoconferencing pages, new fellowships, meetings, updated
FAQs
for GC, employment, ...
- Working with DMC on the Kamionkowski tape.
- Fixed problem with web services on antares. Compacted DCC databases.
- Did a lot of housekeeping on the LIGO web site.
(Mick)
-Continued work on formatting inventory data and resolving inventory
gaps.
-Installed Win2000 on m55 to test cadence.
-Password protected a number of PCs (BA23 and 3rd, 2nd floor)
-Addressed problem with hpcolor2 with Mike - recrimped end of network
cable.
-Loaded cor, including installation of Solaris 8, configuration, FLASH
PROM, and MU.
(Larry)
-Ordered a few more computers to upgrade some of the older PC's. Once
the new
units arrive we should have a computer for every seat. Working on a
number of
maintenance contract changes. Working out the details for the GIGE
network
upgrade. That order should be started by the end of next week.
A number of the vendors have informed me that orders will be delayed
because of
the closure of the airports.
-Started things going to get the single mode fiber installations done
at the 40M
and Wilson House to Bridge. This is part of getting things moved to
a GIGE
backbone.
-Worked with Mike on a number of the video conferencing issues. We
still have
some logistics to work out but it is looking pretty good. Mike has
a pretty good
web page that he is posting.
-Worked on a number of virus issues. We've had a few machines that
were infected
because of infected e-mail being opened, infected files transferred
and not up
to date virus definition files. However, most people are working on
keeping
their machine secure.
-Worked on a number of e-mail issues, including setting up new alias
groups. We
are still looking at different programs that will perform a virus scan
on the
e-mail server.
From: Helena Armandula <ahelena@ligo.caltech.edu>
Subject: Weekly report
Cc: coyne@ligo.caltech.edu, willems@ligo.caltech.edu
"Q" measurements / coating
These parts are reworks from Mindrum. Wave Precision had some trouble
with them also, maybe there was a problem with that particular batch of
glass.
According to Wave Precision hopefully the thick parts will be finished
by Wednesday 12th and shipped. If not, they definitely will be finished
and shipped by Friday.
About the thin parts - they are still working on them. They might not
be within the flatness spec, but will be somewhere in the neighborhood.
Generated and delivered prints to Mackowski indicating bevel size and
masking areas on the thin substrates.
Silicate bonding:
Monitoring substrate stress at different baking temperatures.
40m system
Rolf Bork
- DAQ: Tried to install framebroadcaster last Friday. The reflected
memory network board is seeing data and interrupts from the DAQ
controller, but the CPU is not getting the interrupts. Will continue
work on this when I get back to Caltech next week.
- CDS server: Began creating the same CDS directory structure as
exists at the sites and moving all CDS code into those areas. Once
this
is done, we will load the appropriate scripts to get auto backup/restore
operational. Again, this will probably not complete until next week.
Adv LIGO Optical Modeling
Bill Kells
I have been working on the final issues of comparison
of the FFT code results with equivalent MELODY results.
We are trying to get the paper which has been in draft on
this for some time finished up this week. It seems that final
issues of Thermal lensing in both codes have been reconciled.
Also I have concentrating on finishing up the matching questions
for LIGO II. That is, with large thermal lensing, how much carrier
power is going to be actually coupled into the arms? This has proved
to be a rather subtle problem. The simple modal models are not
directly applicable without modification (they typicall assume
ideal matching between the RC and arm cavities, a very good approx.
for the LIGO I carrier).
Adv LIGO COC
Helena Armandula
Just received the CO2 cleaner for the 40m lab.
MIT should have the one ordered for them.
Adv LIGO SUS
Janeen Romie
Working on 40m TM suspension design.
Working on AdLIGO SUS BOE.
Mark Barton
I did various calculations in support of the Advanced LIGO
Suspensions.
Adv LIGO SEI
Rich Abbott
- Worked on the specifications to the voice coil actuator driver with
a focus on the thermal issues that the coarse actuator presents in vacuum.
- Evaluated some LVDT based position sensors for use in the seismic
feed forward scheme.
- Working on the packaging for the electronics associated with the
capacitance position sensors. This consists mainly of procurement and specifying.
From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>
Lia, Charlotte, Riccardo
Finalized Creep facility and FINALLY started first measurement round
with 8 maraging 250 blades at different stress levels.
The blades have high Q and are excited by the air re-circulation fan
up
to amplitudes of several microns, we get substantial aliasing noise
from
the DAQ time slots.
Over the week end we tried several DAQ strategies to minimize aliasing
noise: sampling at 250Hz and averaging online over 4s gives 2-3 micron
noise, averaging offline over 100 s gives 0.3 microns (obviously still
dominated by aliasing noise). Better results obtained by fitting
the
main harmonic component and keeping the constant term, but the method
is
cumbersome. May need to fit all 3 harmonics online.
For now running 4 second DAQ windows with simple online averaging,
this
will be sufficient for now.
Started a first run with 5 temperature palliers each 3 weeks long.
After that we will try other samples, possibly of different materials.
On Sunday afternoon we sustained an interesting, small (4.2 Richter)
earthquake (epicentre in Hollywood).
The synchrotron crane bridge made an interesting noise when it landed
back on its rails.
The SAS chain close by was observed NOT to be moving by any visible
amount immediately after the quake.
Chenyang
Setting up electrostatic actuator.
Akiteru, et al. @ Hongo
Assembling a small Michelson with one mirror on the SAS tower.
Yukioshi, Tatsuo
Measuring the double pendulum control transfer function.
Akiteru
Working on feedforward on IP.
Some residual problems with accelerometer diagonalization traced to
the
IP excitation method.
Alessandro @ Pisa
Organizing for more flex joint machining with UltraSounds.
For additional information about this report, contact sanders@ligo.caltech.edu