|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The LIGO Executive Committee Agenda for Monday September 10, 2001 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
Special Items: REVIEW OF FY2001 CARRY FORWARD TO FY2002 BUDGET
no report
WBS 1.2 LIGO Operations--Administration
There was no site teleconference on Thursday, September 6, 2001.
The budget to be sent to the NSF so that they can release funds for FY 2002 has been approved internally and entered into FastLane. We are waiting for the MIT proposal, which is to be attached. Meanwhile, Florence has prepared a report for the FY 2001 Operations costs for the end of August. The projected carry-forward is dwindling. I propose an early review (Monday, September 10 Executive Committee Meeting).
The list of current actions revised to reflect
the status of open actions assigned through August 30, 2001 may be found
at
ACTION
LIST.
From: Ed Chargois <chargois_e@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .
ACCOMPLISHMENTS
ACTIVITY
| Packages | Faxes | |
| In | 32 | 29 |
| Out | 11 | 31 |
Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS PAYABLE HISTORY DATA.
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
From: irena@ligo.caltech.edu (Irena Petrac)
SUPPORT (Wood)
Progress Period from 08.31 to 09.06
Accomplishments:
WBS 1.4.1.2 Project Controls (LIGO Construction)
The end-of-August Quarterly Progress Report will be due at the end of September, and I have requested contributions by September 21. This could be the last Quarterly Progress Report required under this Cooperative Agreement, although we will still have to provide some kind of Annual or Final Report. Under the new Cooperative Agreement, we think that only an Annual Report will be required.
The following Change Requests have
been submitted.
| CR-010006 | WBS 1.1.4 (OPS) | Roof Shelter for Concrete Pad Adjacent to Erosion Control Pond (Livingston) | M. Coles |
| CR-010007 | WBS 1.2.4 | Core Optics Components, Repolish/Recoat Beamsplitter | S. Whitcomb |
| CR-010008 | WBS 1.1.4 | Five-Ton Crane for the Staging Building in Hanford | O. Matherny |
| CR-010009 | WBS 1.4.2 (OPS) | Additional 10-W Laser for PSL Lab | S. Whitcomb |
We have scheduled a meeting of the LIGO Change Control Board for Tuesday, September 11, 2001, at 9:00 am PDT in the Science Conference Room (SCR). An agenda has been distributed electronically (LIGO-M010244-00-P). Anyone requiring a telephone hookup should let us know.
Press for the latest Contingency Needs Projection.
From: Kris Duncan <kris@ligo.caltech.edu>
From: Ed Jasnow <jasnow@ligo.caltech.edu>
No report this week.
All electronics are down in the LVEA as we bake the room to 100F to
clear water from the chambers. We are working on a veriety of background
tasks that do not require the LVEA or could not be done because of
their
impact on commissioning. Nothing really noteworthy in the mix.
Detector: Optics and Installation: Installation of the hardware for
the
Laser Safety Interlock system began this morning. We will also install
additional cameras at each end station, as suggested in the LHO proposal.
Assembled a jig to calibrate and aligning wave front sensors off the
ISC
tables, using the Modulated 980 nm RF Detector Test Laser. Peter King
and I
began the calibration this afternoon. (Jonathan Kern)
LDAS: LDAS: Updated all of the passwords at LLO. Uploaded
Big Brother to
ldas-sw and working the last of the bugs out of it. I will have
to
write a script to check the initial configuration and directory
structure the first time big brother is run at an individual site.
Spent some time working on paper work from my trip a couple weeks
ago.
I noticed a couple of problems on controlmon last night, and
will
contact Al about it this afternoon. (Shannon Roddy)
GC; Nothing to report
CDS: Nothing to report
PEM: Built four single pin to four pin LEMO cables and connected the
coil monitor
outputs of the four face coils of each test mass to the Daq chassis.
ITMY, ITMX,
and ETMY are using the designated coil channels while ETMX is using
a temporary
channel setup.
Discovered the problem with the microphone power supplies waiting for
spare
parts before beginning repairs.
Added more content to the PEM reference web pages (not posted yet). (Doug Lormand
Discovered that Sponsored Research hadn’t submitted Albert’s proposal before the due date despite our frantic efforts last week to get everything ready for them to push the button in a timely manner.
| Installation&
Commissioning:
Livingston |
Other Science/EngineeringActivities:
Issues/Concerns |
See also the Installation web page
Luca Matone
I've begun writing a technical note on the LSC charaterization work
done so far. I've prepared a talk for the e2e meeting on the LSC
charaterization effort.
While the Y arm cavity was in resonance, the Q of the bullet mode of the ETMY was remeasured and found to be about 7x10^5 rather than 7000 as had been previously reported. The suspicion is that the earlier measurements had not been on the bullet mode resonance.
Work is in progress to bring the mode cleaner wavefront sensors into operation.
The new PSL servo boards have been installed and the system is being tested.
The mode cleaner was leveled and the contribution to the frequency noise from the vertical oscillations of the mirrors was reduced by about a factor of 30. The excitation pattern was also simplified to involve only one vertical oscillation frequency.
AmaldiAlso have completed a re-analysis of the putative parametricinstability of Braginsky, et al.
Core optics (Jordan)
40m Recycling
MELODY paper (Beausoleil)
In a related problem, the GAP2000 InGaAs photodiodes ordered have a higher capacitance than the EG&G C30642G. In the RF photodetector circuit these could not be tuned to 35.5 MHz with the available components. As a result, some of the 21.5 MHz photodetectors have the GAP2000 photodiodes installed and the 35.5 MHz photodetectors have the C30642G installed.
The PZT holders for the pre-modecleaner have been re-made. They are currently being baked in the small vacuum-chamber bake oven in the PSL Lab.
Rick Karwoski, Paul Russel, Don Clausen
LHO Spares
Currently short two RFPDs -- further detail provided by SanderLLO Spares
The following have been shipped:Currently short two RFPDs and one PMC -- further detail provided by Sander.
1 FS Freq Ref
1 PMC Freq Ref
1 80 MHz VCO
1 FS servo
We have completed a PMC re-layout and submitted it for fab. We are expecting new boards from the vendor early next week.
GEO/LASTI/CAmpus Spares
Work continues on the kitting/stuffing of the these spares. No major issues.Sander Liu
Fixed and tuned two each of the 21.5 MHZ and 35.5 MHz RFPD. Once the mistake in the housing has been corrected, they will be packaged and shipped to LHO and LLO respectively.
Working on a preliminary draft for the RFPD testing procedure.
Module
Needed Fab
Complete Tested
SUS PD Interface 29
34
15
Anti-Image 12
16
7*
Universal Dewhite 22
25
25
LOS Coil Driver 14
13
6
LOS Bias
14
17
12
SOS Dewhite 11
16
16
SOS Coil Driver 15
24
24
Opt. Lever
Intface
15
16
16
We currently have enough modules to complete the LHO 2K. We should be fully complete by the 3rd week of Sept.
10 ea VMIC3113A
5 ea VMIC4116
10 ea. Xycom 220
10 ea Xycom 212
10 ea. MVME162
6 ea. VMIC5579-500
2 ea VMIC5579-501
6 ea Pentium
One satellite amplifier has been sent to each site as a spare. 5 more are in fab. Two satellite amps have been tested and shipped to MIT.
This week we have been working on bringing our second arm cavity into
operation. Of the four OSEM controllers we have for our test
masses, only
two have broadband inputs for actuating on the mirrors. For our
previous
work, both of these were used on the north cavity, leaving the south
cavity
without actuation. This week we restored the south cavity's output-mirror
controller, allowing us to actuate on it, and we verified that the
north
cavity still locks with its input controller replaced. We have
also
verified that we can remove the pzt feedaround servo after lock
acquisition, leaving the north cavity locked using only mirror feedback
and
freeing the pzt servo for use in the south cavity.
no report
Simulation and Modeling (Bhawal)
E2E Physics Meeting
-------------------
Luca Matone discussed his recent work on characterization and modeling
of the
Length Sensing and Control (LSC) system. After that, a short discussion
followed
on issues for a realistic modeling of the mirror motion: measuring
ground
motion correlation and modeling the correlation or using the measured
data
stream.
Mode mismatch
-------------
(Biplab & Hiro) We are trying to understand some crucial issues
related to
the cavity resonance conditions especially when a mode-mismatched beam
enters
a cavity and we are performing some consistency checks regarding handling
of gouy phase in
cases of mirror reflections and base changes.
LSC Characterization
--------------------
(Luca) began writing a technical note on the LSC characterization work
done so
far.
Alfi
----
(Bruce)
- Continuing implementation of Alfi box and primitive file parser for
Alfi5.
- Added ALFINode tree for tracking container hierarchy of nodes.
(Melody)
- Continuing on implementation of graphics portion of alfi5. Worked
on
window and menu components this week. Also investigated
on possible
graphics format to display the primitives.
LIGO Data Analysis System
Software Systems (Blackburn)
The LDAS version (0.0.20) for the Burst and Stochastic MDC was release
on Friday of last week. It was installed on the LDAS development, test,
MIT, LHO and LLO systems.
The Burst & Stochastic MDC is currently underway at MIT. New versions
of LAL and LALwrapper are being installed at a rate of about twice
a
day in support of the rapid development of that code base. So far this
has work out very well with the management of these code bases handled
at CIT and then pushed to MIT and the sites. LDAS staff at MIT for
this
MDC have assisted with LAL and LALwrapper code development and with
the
writing of test scripts and documentation for the MDC.
A couple of issues have shown up with the LDAS code during the MDC.
They
have mostly been associated with the metaDataAPI and the database.
All of
these issues have been resolved and patches have been incorporated
into
the running systems of LDAS. There was a small issue with the mpiAPI
and
the eventMonitorAPI. These were also fixed.
A need for a "search" column in the sngl_burst table similar to the
"search" in the sngl_inspiral table was identified and changes to the
test databases on the LDAS development and MIT systems have been made
to support the MDC.
Work is underway to establish a single CPU version of LDAS capable of
running full wrapperAPI jobs is underway. This is a mode of running
LDAS that has been requested at both the LSC meeting in Hanford and
here at the MDC at MIT.
Hardware Systems (Anderson)
LDAS Administration
-------------------
Caltech
-------
(Dan Kozak)
Lots of HPSS handholding--constant tape repacking,
bad tapes needing
recovery.
Most of the week QFS testing was on hold while we acquired extensions
to our eval licenses. Once these arrived we were up and running
again.
Testing of the "big rig" QFS system continues, with the aggregate
performance of multiple writing processes being good in terms of
bandwidth, but highly unstable (i.e. individual processes vary
_greatly_ in performance). I'm going to try larger writes (i.e.
larger
than 8 second frame sized files) and test reader performance.
LSC's
response to my questions about performance was basically "it depends"
so I'll pursue getting a better answer from them.
LSC's response to my question about the "blackout" of access to the
QFS
while one of the shared reader or writer was rebooted was that this
was
to be expected, but the more detailed questions (i.e. will the blackout
be longer with more T3s and that kind of thing) were being referred
to
others within the LSC organization.
(Al Wilson)
m71 still crashing. and is notsimply a logout condition as was
the case before I lowered the
screen resolution. This is a full kernel crash (i.e., it locks up the
system). I have
rebuilt the kernel (2.4.6) and might try 2.4.9 to see if it helps.
Starting to looking like hardware.
All ldas systems have the new passwords.
The ldas-test system was used to refine the systemimagers program. Found
some helpful hints that will make the process go a bit smoother. Will
update the html doc. Also will incorporate the info from Mendell (LHO)
and Roddy (LLO).
(Stuart Anderson)
Re-wrote the LDAS rsync script for added functionality to support
internal LDAS Beowulf mirrors, mirroring directly between two sites
without referencing the main LDAS software server, and supporting
the new LDAS MIT system.
General release of rsync server on ldas-sw for mirroring the /ldcg
software to non-laboratory computers.
MIT
---
(Keith Bayer)
Setup cables and flat screen on ldas console completed
Move guinevere and both dead Ultra1's out of ldas lab completed
Wireless testing with other laptop completed
Added AIT-2 tape drive to LDAS E450.
Julien needs data from tapes onto ldas completed
Livingston
----------
(Shannon Roddy)
Updated all of the passwords at LLO. Uploaded BigBrother to
ldas-sw and working the last of the bugs out of it. I will have
to
write a script to check the initial configuration and directory
structure the first time big brother is run at an individual site.
Spent some time working on paper work from my trip a couple weeks
ago.
I noticed a couple of problems on controlmon last night, and
will
contact Al about it this afternoon.
Hanford
-------
(Greg Mendell)
1) Continued work on the known pulsar search code DS0. I am currently
incorporating calls to the LALDemod function into the code, to stitch
together short time baseline FFTs into coherent longer time baseline
FFTs.
2) Started testing backups of the file systems on the LDAS LHO network;
this had been put on the back burner since last June.
3) Set up a spare Sun Ultra 10 as sunbox1 on the LHO LDAS network.
This
box will be used for testing scripts for installing LDAS Sun boxes
using
cfdef, and verifying backups are working using ufsdump and ufsrestore.
4) Worked with Dave Barker to get a fiber channel connection between
fb3
(the new framebuilder) and the Sun T3 disk farm.
Data Analysis Activities
Vicere':
* I am estimating the effect of power line noise on the signal
correlation Livingston and Hanford detectors, in an attempt
to evaluate the effect of frequency fluctuations on the broadband
noise floor. This is work in progress.
General Computing (Wallace)
MIT:
(Keith)
-Setup equipment and accounts for the MDC
-Reworked a number of computers both hardware and software.
-Setup items for E2E.
-Working on network performance issues.
-Setup wireless network.
-Installed new s/w pkgs. on various machines.
-Setup printer services and fixed a few printer problems.
-Regular user support and purchases.
Livingston:
(Tom)
-Still working on the second T1 line installation. LSU is having to
work through a number of logistical issues.
-Setting up a new server and working on the in-house built disk storage
unit with Shannon.
-The usual work of setting up accounts and regular maintenance.
Hanford:
(Christine)
- After a failed attempt to swap our file server to a new computer
on
Monday, I hope to get the swap done Thursday, 9/6. I am not copying
over old application software and in-fact the new file server will
only
serve the home accounts and will not have any application software
on
it. This may cause a problem for some people who maybe used some
of the
old application software or maybe were accustomed to logging in to
rainier to run applications. I will send out a list of other
computers
that are available at LHO. If application software is missing,
please
let know what is needed and I will install the latest version on our
application server.
- Trying to get as much Sys. Admin. stuff done this week as I can in
preparation for spending next week as a Control Room Operator and
working from 1 to 9 p.m. I will not be available for Sys. Admin.
(except emergencies) during my operator support next week.
CIT:
(Mike)
-Running various tests with VRVS software we seem to have this program
up
and running. The fix for 'vic.exe' and 'runtime errors' is as
follows I
ended up downloading a third party software called unload.exe which
is up
on Sirius in the pcapps directory; to kill the VRVS mbone video process
look for AVICAP.DLL then used the unload button to kill this process,
you
then have to reboot the computer.
-I'm finishing up with the step-by-step instructions for VRVS registered
user webpage to connect to a scheduled conference, on request by Albert,
which he implied that I make some modifications and additional information.
-The external tape drive is now working on Donna's PC there was a problem
with
USB port.
-I upgraded ANSYS licensing server and users everything seems to be
working
fine.
-Loaded some General computing software on a new PC that was purchased
for
the west bridge 3rd floor conference room, and added additional hardware
for video conferencing.
(Lisa)
- Finally got cdssol8 (ultra10) finished with its rebuild and back
over to
wilson house.
- cdssol20 (blade1000) was throwing up kernel notices. I ran
MU5 on it and told
Rolf to let me know if it barfs again.
- Re-did the mount points in the 40meter again. Added a 75G IDE
hard drive to
op140m (blade100) for /cvs/cds. That is now automounted out to
all unix boxes
on the 40m martian network.
- Created a configuration CD for the 40meter martian PCs. This
was not a big
deal, but it has jetadmin, sftp, ssh and a hosts file so that these
things are
handy whenever they put up a new pc. Mick and I are working on
a configuration
CD for the unix boxes as well.
-Configured the gateway blade100 for the bdl.
- Regular round of accounts and aliases maintenance.
(Mick)
-Installed ssh on gemma (new Blade 100)
-With Lisa, took cdssol8 to Wilson, brought up and configured network
interface
-Worked with Mike on VRVS remote camera control
-JetAdmin on 40m PC
-With Lisa, installed new 70 Gb hard drive on op140m; also configured
mount
points for new drive (/cvs/cds) on all 40m machines
-With Lisa, installed Fast Ethernet and reflexive memory card on 40m
Ultra
10
-Made and ran Ethernet cable in the 40m
-Continued working on inventory information for database
(Larry)
-Spent some time working on the last maintenance update for the SUN
equipment. The Blade 1000 units take about 2 hours for the upgrade
and
the Ultra 10's around 4 hours. It will be some time before we get this
latest update installed on all of the workstations.
-Received a number of purchases and started installing the new computers
and related equipment.
-The PC on the 3rd Floor of WestBridge has been getting more usage.
Performed
some regular maintenance tasks. So far most people have not played
with the
settings on the unit so we have not had any real major problems with
it.
-Spent a deal of time working with Mike on the VRVS installation. Most
of
the s/w issues have been worked out. A number of the problems were
the result
of things changing(hardware being moved, cables being removed) after
things
were up and working. The two test units that have been stationary and
not
have had any changes have been running with very few problems.
-Checking on the costs to have single mode fiber runs done for the
40M and
Wilson house in-order to get a GIGE backbone going for the LIGO-CIT
net.
-Met with Foundry systems to see what they want to charge us for their
equipment
for the GIGE backbone.
-Solved a couple of printer issues. One problem with the color printers
is that there
are formats that they can't handle and it asks to recycle the power
to clear out
the problem. Just turning off the printer doesn't clear out the prolbem,
it needs
to be unplugged from the power source and then the error will clear
out of
memory.
-Working on some e-mail configuration issues.
(Barbara)
- Continued efforts on the new LIGO roster. Made changes for
printability
and other formatting changes.
- Continued efforts on Access form to add a costbook line item.
Resolved
problem with missing object types.
- Reviewed the Kamionkowski video.
- Fixed small problems with LSC roster and DCC number reservation tool.
From: Albert Lazzarini <lazz@ligo.caltech.edu>
Report from the GriPhyN LIGO Applications Group (CIT, ISI, UWM):
I. Talks and Publications
UWM Reports:
"LIGO Data Analysis on the Grid: The Grid Physics Network (GriPhyN)",
at the LSC meeting in Hanford, WA, August 13-16, 2001. This was an
overview of the LIGO-GriPhyN efforts and in particular the prototype
being developed for SC2001, and was presented during one of the ASIS
sessions.
"CondorG Academy", at NCSA in Champaign-Urbana, August 27, 2001. This
was a full-day workshop I presented along with 2 people from the
UW-Madison Condor group. Although the presentations were not GriPhyN
centric, because CondorG is part of the VDT and because GriPhyN
scientists are expected to be DTF users I mention it. During the
presentations a number of references were made to the GriPhyN project.
II. Tool Development and Software Changes
UWM Reports:
I have made two trips to UW-Madison to work with the Condor team and
have provided input on Condor DAGman.
II. Testbed Activities
ISI Reports:
XML/Request Manager interface:
We are able to take the XML request sent by Roy to our web server either
via a web page or through the command line interface and can write
the
XML in a file at the web server end, parse the xml using a perl
parser
XML:PARSER built around the Expat C parser. The parser currently returns
the o/p in name value pairs and stores them in an o/p file. This will
be
changed to be given as a command instead, to the Request manager.
Currently instead the o/p is shown back as name value pairs of the given
XML back to either the web browser or the command client stdout.
Authentication : Installation of My-proxy is currently in progress
Replica Catalog :
Up and running on ldap://dc-user.isi.edu:9129. Need to populate the
replica catalog with files and the organization of the replica has
to be
decided.
Condor-G :
Installed and tested Condor-G with dummy jobs with a Gram gatekeeper
on
Jupiter.isi.edu. Test was done by doing condor_submit of
a single
script file and also by constructing a diamond dag and creating 4 scripts
and using condor_submit_dag to submit the dag to the dagman and execute
it on Jupiter. (Tests were successful.)
An apache web-server is working on dc-user.isi.edu.
Have tried doing the same with dataserver.phys.uwm.edu but have not
been
able to make it work as of yesterday. (Need to spend some time on it
with
Scott on Monday.)
Caltech Reports:
The ISI, Milwaukee, and Caltech groups have been collaborating extensively
to devise and implement an end-to-end Virtual Data system for LIGO
data,
whihc we hope to demonstrate at the SC01 convention in Denver in November.
For LIGO, the use of Globus provides both security and wide-area data
distribution. Each invocation of LDAS (LIGO Data Analysis System) will
communicate to the world only through two interfaces:
-- a Globus job manager (aka GRAM server), and
-- a Globus data port (aka GridFTP server)
There is a Request Manager module under construction at ISI that receives
Virtual Data requests, and decides which LDAS installation should run
to
complete the request, which data should be used as input, and where
the
output should go. Input data is moved to the local disk of a LDAS instance
via the data port, the LDAS job is constructed and sent via the Globus
gatekeeper, and the output moved from local disk to where it should
be on
the Grid. The request manager uses the Condor system to schedule and
execute
these actions.
The request received by the request manager may be on that has been
recently
answered, in which case it may be stored in the cache (aka replica
catalog)
of the manager. In this case, no LDAS is used, but the replica data
is
fetched to answer the request.
There is an XML-formatted virtual data request document, using the LIGO-LW
(LIGO lightweight data) specification. This specification has been
agreed by
the collaboration, and tools have been built to both create such requests
from a client-side form on a web browser, and also to parse and implement
such requests on the request manager.
UWM Reports:
As part of the GriPhyN-LIGO prototype work being done in preparation
for SC2001 I have begun building and installing a GridFTP (gsi-wuftpd)
server on ldas-test.ligo.caltech.edu. In addition I have installed
a
version of LDAS locally in Milwaukee so that I can begin working on
a
GRAM jobmanager for LDAS.
Locally in Milwaukee I have setup the machine dataserver.phys.uwm.edu
with a Globus gatekeeper, GridFTP server, and GSI-enabled SSH server.
In addition I have installed, configured, and tested Condor version
6.3.0 on the UWM Linux cluster, as well as the UWM Alpha cluster.
I have also put together a package named LDR (Ligo Data Replicator),
which is being used locally at UWM to replicate data from the CACR
HPSS to UWM.
IV. Demos
No activity to report.
V. Outreach Activities
No activity to report.
VI. Miscellaneous
Caltech Reports:
Marv Golberg convened a meeting at NSF on 29 August 2001. The subject
of the meeting was the ITR 2002 Announcement and future scientific computing
initiatives within the MPS Division. The LIGO Program manager at
NSF (Vic Cook) asked LIGO to participate and LIGO Laboratory and the LSC
asked Lazzarini and Koranda to attend. In addition Prof. E. Katsavounidis,
from the MIT LIGO group, was asked to attend by LIGO Laboratory management.
Minutes of the meeting should be forthcoming from Marv Goldberg. Marv's
title for the meeting was:
"WHERE DO WE GO FROM HERE? SCIENCE; COMPUTATION; EDUCATION; INDUSTRY"
In attendance were:
Lawrence Gibbons Ikg@mail.lns.cornell.edu
Chris Jones
cdj@mail.lns.cornell.edu
Jae Vu
vu@fnal.gov
Miron Livny
miron@cs.wisc.edu
Geoffrey Fox
gcf@indiana.edu
Stefan Westerhoff
westerhoff@nevis1.nevis.columbia.edu
Irwin Gains
gaines@fnal.gov
Scott Koranda
skoranda@gravity.phys.uwm.edu
Albert Lazzarini
lazz@ligo.caltech.edu
Erik Katsavounidis
kats@ligo.caltech.edu
Sarah Eno
eno@physics.umd.edu
Steve Chapin
chapin@ecs.syr.edu
Lothar Bauerdick
bauerdick@fnal.gov
John Huth
HUTH@huhepl.harvard.edu
Saskia Mioduszewski saskia@bnl.gov
Giulio Varsi
Giulio. Varsi@hq.nasa.gov
Vicky White
Vicky.White@science.doe.gov
Glen Crawford
Glen.Crawford@science.doe.gov
Brad Keister
bkeister@nsf,gov
Vic Cook
vcook@nsf.gov
Richard Isaacson
isaacson@nsf.gov
Alex Firestone
afiresto@nsf.gov
Marv Goldberg
mgoldber@nsf.gov
Also invited but not attending:
Alex Szalay
szalay@pha.jhu.edu
Vern Pankonin ypankoni@nsf.gov
Jack Lightbody
jwlightb@nsf.gov
From Peter King:
2.3 Advanced LIGO PSL
The boards originally designated
as being for GEO were re-directed
to being site spares. It is expected that replacements will be
available
(fabricated, debugged and tested) by October.
From Mark Barton:
This week I did various calculations for the Advanced LIGO suspension
requirements, learning about the Mathematica package Optica in the
process.
From: GariLynn Billingsley <Billingsley_G@ligo.caltech.edu>
Goodrich has started the compensation polish on the 25 cm sapphire substrate. They are shipping the 15 cm substrate back to Caltech. This piece was used to calibrate the material removal rate of m-axis sapphire. The estimated time to completion is 2 months.
From: Helena Armandula <ahelena@ligo.caltech.edu>
Silicate Bonding:
Performed a few more tests confirming that baked sodium silicate bonds between sapphire and silica are very strong, even when there is marked evidence of stress.
Tested in tension some old bonds made with KOH solution.
As before, even after they aged for ~ 109 days, these bonds were very
weak.
A surprising result (to me) from tests that involved
sapphire substrates is that they are very sensitive to thermal shock.
Much more sensitive than fused silica.
From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>
Riccardo back from Pisa to Pasadena, Francesco back from
Pasadena to
Pisa, (thanks for running the group for me, I appreciated Ric), Florian
back from Hongo in Pasadena, Alessandro back from Hongo, in vacation
in
Mexico, going back to Pisa.
Akiteru
the preparation for the mirror control is going well. We have
installed the suspension, on which Florian and Yukiyoshi have been
working,
into the other tower and preparing electronics for the measurement.
The
measurements should be done by middle of September.
In the mean while, I am trying to test new control scheme for the
inverted
pendulum. Mounting an accelerometer on it for monitoring completely
changed
the IP eigen modes. Then redoing diagonalization process, which takes
quite
bit of time. But we should be able to test the feed forward technique
by
the
second week of the next month.
Lia
LVDT stabilization problems, may not be in the linear zone of the
readout,
Measuring the “S” and then check circuits again. Getting help from
Charlotte.
Mathieu
Wedge ear strain calculations for the quartz mirror suspensions.
Charlotte
Studying effective bending point of folexures under load
Florian
Working on end of stage final report
For additional information about this report, contact sanders@ligo.caltech.edu