|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The LIGO Executive Committee Agenda for Monday September 3, 2001 will be:
CANCELLED DUE TO HOLIDAY
no report
WBS 1.2 LIGO Operations--Administration
The following were discussed during the site teleconference on Thursday, August 30, 2001.
From: Ed Chargois <chargois_e@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .
ACCOMPLISHMENTS
ACTIVITY
| Packages | Faxes | |
| In | 47 | 35 |
| Out | 12 | 54 |
Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS PAYABLE HISTORY DATA.
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
From: irena@ligo.caltech.edu (Irena Petrac)
SUPPORT (Wood)
Graphic provided by Cindy.
Progress Period from 08.24 to 08.30
Accomplishments:
WBS 1.4.1.2 Project Controls (LIGO Construction)
The end-of-August Quarterly Progress Report will be due at the end of September, and I have requested contributions by September 21. This could be the last Quarterly Progress Report required under this Cooperative Agreement, although we will still have to provide some kind of Annual or Final Report. Under the new Cooperative Agreement, we think that only an Annual Report will be required.
The following Change Requests have
been submitted.
| CR-010006 | WBS 1.1.4 (OPS) | Roof Shelter for Concrete Pad Adjacent to Erosion Control Pond (Livingston) | M. Coles |
| CR-010007 | WBS 1.2.4 | Core Optics Components, Repolish/Recoat Beamsplitter | S. Whitcomb |
| CR-010008 | WBS 1.1.4 | Crane for the Staging Building in Hanford | O. Matherny |
We have tentatively scheduled a meeting of the LIGO Change Control Board for Tuesday, September 11, 2001, at 9:00 am PDT in the Science Conference Room (SCR). Anyone requiring a telephone hookup should let us know.
Press for the latest Contingency Needs Projection.
From: Kris Duncan <kris@ligo.caltech.edu>
From: Ed Jasnow <jasnow@ligo.caltech.edu>
No report this week.
4k IOO/ISC Work
------------------------------
(C.Gray, B.Kells, M.Landry, G.Moreno, & others.... )
In order to squeeze in work before the "short-term bakeout" of the LVEA,
there has been of flurry of activity, on the 4k, focused on the ISC
system
and the Mode Cleaner.
Bill has been working on getting the Anti-Symmetric Port Photo diode
on-line;
this will greatly help out when we get the next chance to work on alignment
of the interferometer. The work required for this involves getting
much of
the LSC electronics also on-line.
We've also been working on measuring the internal resonance Q's for
the
Mode Cleaner mirrors. This has been done by exciting the mirror's
Coil
Drives (UL,LL,UR,&LR); monitoring the optics via the "PSL Out Mon";
removing the excitation and recording the ring down on a scope.
We have
looked (and are still looking) at modes within a range of 20kHz to
55kHz.
Preliminary results are showing Q's from 3 x10^5--1 x10^6. We will
post a
table in the e-log when work is complete.
Detector: Optics and Installation: The cabling for the Laser Safety Interlock system has been completed and the installation of the hardware will begin next week. Russ and I conducted a walkthrough with the vendor, Metropolitan Electronics this morning and signed off on the cables. We found last weekend that the ETM transmission beam failed to exit the COS viewport on BSC-4; it missed the window by ~1/2". We effected one of the easier fixes we've been able to do to correct this clipping. Allen and Kerry backfilled the Y-end Tuesday morning, in less than 1/2 hour the viewport was replaced with a larger optical window and by day's end the vessel was back down to 10^-8. Late news - the Y end is now locking well since about 5 pm Thursday afternoon. (Jonathan Kern)
LDAS: Started the tape script to make a new copy of the E5 data. The
first copy was lost by UPS. After a couple of restarts, the script seems
to be writing data to the tapes now. Reading documentation on the Stow
utility. Looking at ways of integrating BigBrother with Stow and the directory
structure used by LDAS. After looking at the scripts/config files last
night, I think this can be done very easily. Received an email from APC
concerning monitoring multiple UPSs with one machine. According to them,
this cannot be done using their software. If we choose to stick with monitoring
the UPSs over the network rather than serial ports, we will have to look
at custom software via SNMP.
GC: Discussed with Tom several ways of setting up the network with
the new T1. Also some long term plans with the network configuration and
organization.
CDS: I ordered & received a tape drive to replace the GC Mammoth
drive that had been placed on CDS. The replacement drive is a AIT2 external
drive. (Shannon Roddy)
Other GC news: We have recently received two Blade 1000s. One was set
up as a general
computing number cruncher, and we are in the process of setting the
other
one up as a replacement for our fileserver.
We have installed CD writers in several machines available to general
users, including one Sun workstation. We have ordered current versions
of CD writer software, and are waiting for it.
We expect LSU to come next week to install the temporary router needed
to enable our second T1 line. They have been delayed due to networking
emergencies on campus. (Tom Evans)
PEM: Installed two microphones in the LVEA, one on BSC2 (beam splitter)
and the other
on BSC3 (ITMX). I mounted another microphone on BSC1 (ITMY) but problems
with
the microphone power supplies prevent it from being connected to the
DAQ system.
Will trouble shoot the B & K microphone power supplies to correct
the problem
that is common to all six units. Will install one more microphone on
HAM3 by the
end of day Friday and once the power supply problems are dealt with
the
remaining four microphones will be installed.
Setting up templates for all of the PEM reference web pages. I hope
to have the
sensor documentation for each sensor up by the end of next week. (Doug
Lormand)
|
|
|
|
Installation&
Commissioning:
Livingston |
Other
Science/EngineeringActivities:
Issues/Concerns |
See also the Installation web page
Nergis Mavalvala,Daniel Sigg
The common-mode servo, which comprises feed back paths from the REFL_I signal to the ETMs, the modecleaner length and the error point of the MC servo was made to work after much grief. We commissioned it using the AS_I signal from a single arm cavity. One change to note: the AS whitening gains were increased from 24 dB to 42 dB!!!
I. Summary of the important measurements/fixes
* setting MCL/MCAO relative gains and signs
* eliminating noise due to ~1 MHz oscillations in some opamps on MC servo board
* tailoring filters on the CM board for better stability and to lower HF noise
* implementing CM switch for ETM path gain and filtering with the LSC front end
* further filtering MCL path above 10 kHz to eliminate ring up of 49 kHz internal mode of MC2
* writing script to automate CM loop engaging (so our fingers don't get sore)
details here (username: reader, password: readonly)
Bill Kells
We are still trying to fully understand the alignment situation of the 4k core optics. Most time however has been spent in wrestling with the new digital suspension and LSC electronics. The Michelson has been locked, but in a very shaky state, due to several remaining bugs/mysteries in the LSC servo chain.
Measured the ETMy Q to be ~10^6. Dip on reflection for the y-arm is ~3%
Explored small optic suspension bounce modes in the mode cleaner length control signal, by looking at the coherence of SUS sensors and the MC frequency noise signal. There is clear evidence of coupling of some SOS on the same optics table.
Wavefront sensing has been implemented on the mode cleaner. The reflected DC reduced by ~30% and the reflected spot is visibly more stable.
Dataloggers: We installed a new UDP/IP communications package on the Quanterra
dataloggers which allow us to transfer the real time data into shared memory on
fortress(LHO) and decatur(LLO) where it will be available for LIGO software (e.g.
frame converter, DTT, etc.) This way we minimize the load on the station's CPU and
ensure real time access to data and allow for real time merging of VBB seismic data
from both observatories.
Magnetometers: As Robert also pointed out there is a correlation between the
hard-disk head movement (probably due to the embedded stepper motor) and the
saturated spikes visible on the coil magnetometer signals. We choose not to move the
datalogger, but to replace the hard disk with a completely electronic FlashMemory
disk. We are acquiring compatible (drop-in) narrow SCSI FlashDisks as replacements. I
contacted the datalogger manufacturer/guru and they agreed that indeed it is a nice
solution. I expect that we will have one disk on hand within two weeks.
(Robert Busby (GPS), Szabi Marka)
[Hacker/Worm update]
LHO: We restricted the access to the datalogger [granite] in LHO at the firewall. It
seems that it helped a lot. (Thanks, Christine)
LLO: There is a new hacker phenomena which can cause the datalogger [clay] to hang-up
and requires physical power disconnect to regain control for a short time.(I have to
thank Tom for his help!) Until the firewall is up in LLO we have to stop the services
most often scanned, which seemed to help on other units. Therefore, e.g. the
web-interface will be turned off until further notice on the LLO datalogger.
Some details about similar attacks are available. Please contact me if interested.
The pre-modecleaner servo in the PSL Lab was debugged. It
was found that one of the right-angle PCB-mount LEMO connectors was faulty.
The push-fit brass ground pins had an intermittent connection. A
closed loop transfer function indicated that the gain was approximately
75 dB at 10 Hz.
An NPRO laser is in the process of being setup for the PSL.
An error was made during the fabrication of the PZT holders for the pre-modecleaner. They are in the process of being remade.
Currently I am working on a small bandpass amplifier to be used in characterizing the 35.5 MHz RF photodetector.
Lee has wrapped up a vacuum chamber that will be used as a small item bake oven. The initial bake load was to be the above-mentioned PZT holders.
Lee Cardenas
LHO Spares
We delivered the following boards to LHO:
1 PMC servo
1 PMC Freq Ref
1 FS Freq Ref
1 80 MHz VCO
1 FS servo
Currently RFPDs for LHO and LLO are in test. ETC: next week some time.
LLO Spares
The following are ready for delivery:
1 FS Freq Ref
1 PMC Freq Ref
1 80 MHz VCO
1 FS servo
We are short PMC PCB blanks but we have completed a PMC re-layout incorporating fixes and updates. We will send out for fab directly and begin the stuff-and-test cycle once we receive the fabricated boards.
Further Detail Provided by Sander:
Finished building (added missing components) and testing a spare set
of PMC and FSS boards for LHO.
For the LLO spare set, we did patch up work (added missing and/or replacing
incorrect value components) to finish building and testing the 21.5 MHz
Reference board, the 35.5 MHz Reference board, 80MHz VCO and FSS Servo
card. Worked with Rita to come up with a spreadsheet to track inventory
and board status for the next four sets of PSL boards being build for GEO,
LASTI, 40M and Bridge Lab. Currently, we are in the process of completing
four (4) RFPD boxes.
EPICS-Based Intensity Stabilization Servo Circuitry
The a prototype for the main servo compensation network and associated
EPICs-controlled circuitry has been layed out and will be sent out for
fab.
MC Clenaer Servo
Mohana Megeswaran
I am incorpoarting all the changes of the MC Servo from the detector log, and I am doing the simulation for our next new design. The one old MC Servo has been stuffed and tested. It will be send to Livingston today. I am also implementing a source code which was written for C6211 DSK board. So that it could run in our C6711 DSK Board.
1) removes fixed stopband and cheby filters in CARM, making them user
defineable.
2) adds detection+common mode selection to LSC mode switch.
3) adds CARM filter switching matrix tied to mode switch.
4) adds common mode gain factor.
5) adds manual on/off of common mode hardware.
- Working w/Kells and Mccarthy on getting LHO 4k running; fixed a couple of bugs in communications to LVEA large optic digital suspensions. Bill is continuing to test.
- Working on mods to EPICS interface software to reduce the load on the EPICS CPU.
Jay Heefner
Module production is as follows:
Module Needed Fab Complete Tested
SUS PD Interface 29 34 15
Anti-Image 12 16 7*
Universal Dewhite 22 25 25
LOS Coil Driver 14 13 2**
LOS Bias 14 17 10
SOS Dewhite 11 16 16
SOS Coil Driver 15 24 24
Opt. Lever
Intface
15
16
16
*Anti-image filters are on order and due mid Sept.Remaining 9 module will be tested when they arrive. 7 modules will complete the LHO 2K.
**All LOS Coil drivers are in chassis and ready to be tested beginning next week.
- 18 Penteks have been received and are being modified for external clock input.
1. WFS PD amps- We have 7 without PDs. The PDs are due 9/15. When these amps are complete each site will have at least 1 "hot" spare for each frequency.
2. WFS demod- We have ordered new boards that are due next week.
3. WFS White/Interface- building 5 more Rev B boards.
4. Sus Satellite amp- Two modules being tested and should be ready next week. 5 more being fab'd.
5. MC Alignment servo- Unit at CIT is complete and awaiting test.
- We are putting together a final list of commercial modules spares to be ordered for the sites. It should be ready by next week.
This week I have continued to prepare for the burst and stochastic
MDC at
MIT next week. This has included installing and testing code that will be
used in the DMT section of the MDC, and installing the complete DMT system
on to lancelot, the MIT DMT machine.
no report
no report
Simulation and Modeling (Bhawal)
E2E for LIGO-I Meeting
----------------------
This month's 'E2E for LIGO-I' meeting among simulators and hardware
people took place on 28th, Tuesday.
Details will be available in http://www.ligo.caltech.edu/~e2e
LIGO simulation
---------------
(Hiro) Finalizing the expanded version of Han2k, which includes
(1) thermal noise (2) full stack (6x6) (3) easy switch of input power
(4) many internal improvements for ease of development, maintenance
and
speed.
W2k LSC characterization effort
------------------------------
(Luca) After having measured the noise performance and filtering properties
of most of the LSC system (analog and digital, reflected port), we
began
to model (analytically) its filtering properties with Matlab.
Each analog board was modeled, analytically, according to its
schematics. The model's filtering parameters were adjusted to best
fit
the xfer fn measurements of the board in question. Each digital filter
(included or not on the LSC control screen) was also modeled and
compared to measurements.
As a result, the xfer fn measurement between the Whitening and Anti-Imaging
board allowed us to estimate the delay in the ADC/DAC process. Good
agreement was found between this measurement and what the model predicts
if a delay of 80us was assumed.
To do list:
o Write a technical note summarizing the characterization completed
so far;
o Understood origin of digital stop-band filter at ~9.5 kHz
-> still need to include it in the Matlab model;
o Two new digital filters in place at Hanford;
o Analysis of one-arm E5 data (E5 control configuration?):
- Estimate mirror motion. How?
- Estimate frequency noise. How? Correlation between MC_F
and arm
control signal?
- Virginio will work together.
o Measurements of Open Loop xfer fn in Closed-Loop of "simple" systems
(Michelson, One-Arm) -> quantify coil-driver/pendulum
xfer fn
- This will be done with Michael Landry
Mode mismatch
-------------
(Biplab & Hiro) Comparison with FFT brought out some differences
in results.
We're trying to understand how the modal model calculation up to 2nd
order
in e2e simulation could differ from an exact solution. We're deriving
analytical expressions at steady states when a mismatched beam enters
a very high finesse cavity and trying to understand this situation
and
some critical issues related to the cavity resonance conditions through
various e2e runs.
Noise issue
-----------
(Hiro) Worked with Bill Butler to resolve issues related to psd of
simulated noise curve.
Alfi
----
(Bruce)
- Continuing implementation of Alfi box and primitive file parser
for Alfi5.
- Completed initial implementation of main Alfi class (ALFINode).
(Melody)
- Implementation of graphics portion of alfi5 is proceeding as planned.
- Worked on creating and displaying new nodes. Also worked on
the
popup menus and window functions for the editor frames.
- Working on displaying ports and the primitives.
LIGO Data Analysis System
Software Systems (Blackburn)
This week has been focused on closing out development of LDAS
at a stable point which will support the requirements of the
Burst & Stochastic MDC next week at MIT.
There have been a significant number of last minute requests for
new functionality as search code are only just now coming on
line and usage models for what LDAS must provide are seeing
first light in the community. We have responded very well to
these but will have to leave all that showed up after Monday
of this week as impossible to add the new functionality in time
for a stable release. Probably the largest of these is the
ability to return results in the multiDimData from the search
codes in frame file format.
We have been able to get LDAS up and running on the MIT system.
It is currently running a pre-release version for the MDC. A
minimal number of tests have been performed on this system to
demonstrate that basic functionality is working. However, the
full testing is waiting for the remaining bug fixes needed by
Tuesday Morning next week.
There have been daily problems during this release cycle. We
have been able to resolve each new problem this week. The latest
problem showed up last night in with the eventMonitorAPI hanging
for an hour at a time. This is coupled to the wrapperAPI not
starting on the beowulf and is most likely related to the NFS
delays in starting jobs on a system that has dropped its auto-
mount points. This cascades into the mpiAPI and then into the
eventMonitorAPI. A possible fix has been identified but it will
not be tested in time for this report.
The LDAS-TEST system was also brought back into line, now
having a a working pre-release version of LDAS fo rthe first
time in nearly three months. The test system is still being
dedicated to hardware testing, but it is closer now to being
configured for running LDAS than it has been since the
migration to openSSH and Redhat Linux 7.1
The dataConditionAPI has run remarkable well this week. This
is mostlikely due to kernel changes made to the datacon and
beowulf hosts over the past two weeks. It does still on a
daily basis fail from a thread problem and we are still using
the known non-thread safe release of GCC.
Hardware Systems (Anderson)
LDAS Administration
-------------------
Caltech
-------
(Dan Kozak)
Lots of HPSS hand-holding--constant tape re-packing, a couple of bad
tapes needing recovery, added some Redwood tapes using recycled
labels (off old bad tapes).
Finished testing of the shared reader mode of QFS with a single T3.
Discovered that putting the metadata on a separate LUN (i.e. a 1+1
mirrored arrangement for metadata and a 6+1 RAID 5 set up for data)
helped with consistency. There's still some variation in performance
caused (I believe) by contention for metadata access by the reader
and
writer, but this arrangement brought the worst case for write speeds
up
from ~30Mb/sec to ~47Mb/sec. The best case remained ~70Mb/sec.
Set up a QFS configuration using all the T3s in the test system and
the
loaner FC cards from Sun. Despite trying a bunch of different
configurations in terms of where the metadata lives (separate LUN or
partition of a T3) and how the T3s are striped in QFS (one stripe group
across all, two stripe groups so that it never talks to two T3s in
the
same zone at the same time) I was unable to get more than 110Mb/sec
writes. This seems low and I'm asking Sun for a response.
The best performance was with 5 T3s striped in one group with a 1+1
LUN
from the 6th T3 for metadata. The other 7 drives on the 6th T3
went
unused.
(Al Wilson)
Keeping on top of the cfdef files and makeing sure that MIT is ready
to go
for the MDC, also trying to see if VA Linux System Imager could be
made
a bit more automatic and test some adds to the beowulf cfdef files.
(Stuart Anderson)
LDAS is now running at MIT and integrated into the distrubted administration
tasks of LDAS.
Worked on an upgraded rsync script to offer finer control over what
software
is mirrored from one LDAS system to another.
Began planning the upgrade of the existing LDAS Fiber Channel disk storage
into a Storage Area Network (SAN) to provide higher speed access from
the CDS frame builder and mutliple high speed read-only clients (DMT?).
After a technical meeting with Sun it was determined that this is possible
without a potentially expensive upgrade to the existing disk units.
However,
additional Fiber Channel switches will be needed to connect additional
servers.
MIT
---
(Keith Bayer)
Assisted in bringing up ldas system at MIT.
Hooked up AIT-2 tape drive to E450
Received 2 penguin computers
partially setup computers
Received flat screen sun monitor
Ordered pc cables for extra pc's and sun monitor.
Copied reduced data set frames onto ldas T3
Livingston
----------
(Shannon Roddy)
Started the tape script to make a new copy of the E5 data. The
first copy was lost by UPS. After a couple of restarts, the script
seems to be writing data to the tapes now. Reading documentation
on the
Stow utility. Looking at ways of integrating BigBrother with
Stow and
the directory structure used by LDAS. After looking at the
scripts/config files last night, I think this can be done very easily.
Received an email from APC concerning monitoring multiple UPSs
with one
machine. According to them, this cannot be done using their software.
If we choose to stick with monitoring the UPSs over the network
rather
than serial ports, we will have to look at custom software via SNMP.
Hanford
-------
(Greg Mendell)
1) The primary work has been writing dynamic shared object (DS0) shared
object code to search for known pulsars, to run under LDAS. This
week I
installed the latest versions of /ldcg, LAL, LALWrapper, and LDAS and
debugged the part of my code that generates FFTs.
2) Discussed with Maria Alessandra specification for producing short
time baseline FFTs (SFTs). We are working on a short document
to
distribute to PULG.
3) Worked on usual system administration tasks. This last week
the
admin box crashed, but restored itself on reboot, and the beowulf server
was upgraded to RedHat 2.4.6smp kernel.
4) Assisted with getting RDS data from fortress onto tape, and the start
of the rewriting of E5 raw frame data at LLO (which is now underway).
Also tested the latest cmonClient GUI for running and monitoring the
tapecontrol script.
Data Analysis Activities
[Vicere':]
* I continued my work on an algorithm for burst detection. I have
extended the method to a network of detectors in presence of correlated
noise, and for arbitrary noise color. I am in the process of completing
a report on this work, which may eventually become a publication.
The next step shall be to code the algorithm and test it on the PEM
data exchanged between LIGO and VIRGO.
* I started working with M.Tinto on the optimization of the multi
template search algorithm for coalescing binary events.
* I am working with A.Lazzarini on modeling the correlation of
power lines across the Livingston and Hanford detectors, trying to
estimate the level of residual noise, applicable for instance to
a search for stochastic GW signals.
[Marka:]
External Data Triggers:
We created a new database table called External_Triggers. It is up
and available at
DEV:CIT_test.
We are testing it with real time ALLEGRO events (based on data from
2000) and GCN GRB
alerts recently received. The table was designed to be flexible enough
to accept
events from a wide range of outside sources, including GRB, neutrino,
optical
observatories, bar detectors and other possible sources. The TCP/IP
communication
code connecting ALLEGRO is being tested and seems quite reliable. The
DMT class to
access the table is being developed based on John's TrigEnv class.
(Szabi Marka, Peter Shawhan, Hareem Tariq)
[Lazzarini:]
I attended a meeting at NSF convened by Marv Goldberg to look
at strategies for PMA to take advantage (beyond GriPhyN) of the next round
of ITR2002 monies that were announced today. Scott Koranda (UWM&NCSA)
and Erik Katsavounidis also attended. We will draft a memo for circulation
to the Lab. and LSC leadership.
General Computing (Wallace)
MIT:
(Keith)
-Assisted in bringing up ldas system at MIT.
-Hooked up AIT-2 tape drive to E450
-Received 2 penguin computers
-Partially setup computers
-Received flat screen sun monitor
-Ordered pc cables for extra pc's and sun monitor.
-Copied reduced data set frames onto ldas T3
-Worked with LIGO CIT in setting up the VRVS system.
More testing will be done even though the first tests worked out.
Livingston:
(Shannon)
-Discussed with Tom several ways of setting up the network with the
new T1. Also some long term plans with the network configuration
and
organization.
-I ordered & received a tape drive to replace the GC Mammoth drive
that had been placed on CDS. The replacement drive is a AIT2
external
drive.
(Tom)
-We have recently received two Blade 1000s. One was set up as a general
computing number cruncher, and we are in the process of setting the
other
one up as a replacement for our fileserver.
-We have installed CD writers in several machines available to general
users, including one Sun workstation. We have ordered current versions
of CD writer software, and are waiting for it.
-We expect LSU to come next week to install the temporary router needed
to enable our second T1 line. They have been delayed due to networking
emergencies on campus.
Hanford:
(Christine)
- The main file server, rainier, is being replaced with a new computer.
There will be periodic down time on 8/29 through 8/30 and again on
9/3.
During the down times there will not be any email, web access, or user
login.
- Made some changes to the access list for the TRINET computer.
CIT:
(Mike)
-Donna's computer was locking up; solution I ended up reloading the
OS
and software plus restored all users data.
-Tried to get a Seagate backup tape drive to work there is something
with
this software that is causing the tape drive to hang up. Still looking
into
this problem.
-Went over with Windy on ghosting laptops.
-Millikan, installed more memory on a sparc for Stuart.
-Working on video conference software; we are having a big problem
with
run-time errors, I am still working this problem out. The computer
needs
to be completely reset once you get the error.
-Moved NTSRV's out of PC room into server room with Larry .
-Dennis Coyne, had a problem with the registry computer would not boot
OS.
Solution I had to reload his engineering workstation; OS and general
computing software and additional needed software.
-Created accounts for Mathieu's and Charlotte on the engineering
workstation M6 to run AutoCAD and Ansys software from M6.
-Millikan, reloaded computer in conference room to load VRVS software
plus
added an addition hard drive for LINUX.
-Loaded SSH software on Laptop for Melody to work from home.
-Onsite and phone support with users that included printing problems
and
working out minor glitches with there computers.
(Wendy)
-On vacation--worked on loading/imaging laptops a bit before leaving
though.
(Barbara)
- Installed new version of the public document search tool so that
it is
updated daily rather than monthly. I had an overnight revelation
awhile
back about an easy way to do it.
- Installed a change to the roster database to support multiple staff
locations for the directory. Rita is about finished with the
entry and the
new roster should be available soon.
- Posted more LSC transparencies.
- Began working on an entry form for new line items in the Access view
of
the costbook.
(Mick)
-Compiled list of LIGO PCs to keep track of which have been ghosted.
Rebuilt m55, successfully loading old ghost image; updated settings,
installed NAV and created an updated ghost image. 48x CD drive
still out
of order.
-Tracked down some inventory ghosts brought up by property audit.
-Moved equipment: tape cabinet, etc., to free up space in server room.
-Worked on properly formatting the inventory data file to be used as
a database.
-With Lisa, reloaded and configured two 40m Blade 100s to be put on
Martian
network, installing 100 Mb Fast Ethernet card into one.
-Wrote up a new webpage with Eudora-ssh tunneling instructions.
-Began webpage for NAV setup instructions.
(Larry)
-Worked on a number of orders. We now have a couple of workstations
as well as
more disks for home accounts on order. Took care of updating the licenses
for
Ansys and Ghostview. Purchased another PC workstation to be used with
the VRVS
system on the 3rd floor of WestBridge.
-Spent some time with Ed C. working on the equipment audit being performed
by
Caltech.
-Worked on the VRVS system with Mike and Keith. So far things are looking
pretty
good. The systems ran well for a few days and then crashed when trying
them from
the 6th Floor of Millikan, two systems crashed and one of them twice.
Mike was
able to figure out how to get the systems completely reset without
rebuilding
them from scratch. Once the vic.exe error started we could no longer
get things
to run without completely resetting everything.
The quality of the video is much better with the EVI cameras than with
some of
the other cameras we were using. Using the polycom phones for sound
has
presented some problems because of sensitivity and feedback and that
problem is
being worked on.
-Working on the Blade1000 replacement for Sargas. Installed the latest
MU
(maintenance update pkg. 5) on the unit and a couple of other machines.
Installation on the Blade1000 takes about 2 hours and on the Ultra
10's about 4
hours.
-Delegated more of the documentation out. Presently, everyone in the
group now
has some items they need to work on, that are to be incorporated into
the WEB
pages.
-Moved a number of home accounts to a larger disk system over the weekend.
-Worked with Mike on a number of PC issues.
-Worked with different members of the group moving equipment, desks
and
cabinets.
-Still receiving notices from people getting viruses via e-mail but
so far no
major problems this past week. The virus-scan s/w appears to be picking
up the
problems.
(Lisa)
- Created a shared samba disk on sirius to use for backing up PCs before
a
rebuild. This is a much needed administrative resource.
- Tried to get the USB harddrive recognized during ghost, but there
is no DOS
driver available from the manufacturer
- Helped Mick inventory the synchrotron server room
- Regular round of user account/alias maintenance
- Rebuilt 2 blade 100s in the 40meter. These were on the GC network
for the
summer. They are now configured for the 40m CDS martian network.
- Put together a pile of equipment for surplus and gave the list to
Ed.
-Moved out of Bill Tyler's office into room 36.
LASTI
Jay Heefner
- Two satellite amps are being tested and should be shipped by 8/31.
- 64 conductor cable for the connection between the controllers and
the satellite amps has been shipped to MIT.
Advanced LIGO Optics Modeling
Bill Kells
worked on FFT modeling of stability (Guoy phase choice) and mode matching
design for LIGO II -like ifos.
Advanced LIGO Suspensions
Mark Barton
I did more stuff in support of the advanced LIGO suspension design:
a
calculation of the effect on path length of tilt of optics such as
FM
which aren't normal to the beam, and more reverse-engineering (and
commenting) of the suspension model.
From: GariLynn Billingsley
Dennis and GariLynn spoke with Bob Oreb and Achim Leistner of CSIRO
about polishing for the flat top beam.
Achim feels confident that CSIRO could take a good shot at that sort
of thing. The important issue is the tolerance and the aperture of
interest. They will be able to respond better if they know how exactly
the surface must replicate the stable flat top beam. They currently
polish to within 10 nm of our desired surface figure. A complex surface
might well need a looser tolerance. They are willing to give it a
try if we can come up with some definition.
Goodrich has promised an official quote this week (today actually, but I still haven't got it.) Over the phone Joel Askinazi told me that the quote for compensating polish will come in at $46,662.
From: Helena Armandula
Silicate bonding
Sapphire/sapphire bonds:
Sapphire/sapphire (1/2" dia.) bonds made with sodium silicate solution
are very strong when tested under tension.
Bonded substrates were pulled to an average of 160 kg.
Even bonds made with substrates that were not flat, on which fringes
could be seen after bonding, proved to be very robust taking a pulling
force of 117 kg before coming apart.
Tested the effects of baking at 120 degrees C for a 24 hr period on:
Silica/silica bonds
Baked bonds are stronger than un-baked bonds.
Sapphire/silica bonds:
Baked sapphire/silica bonds showed prominent stress, however, they
were considerably stronger than the un-baked bonds.
For additional information about this report, contact sanders@ligo.caltech.edu