|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The LIGO Executive Committee Agenda for Monday August 27, 2001 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
Special Items:
no report
WBS 1.2 LIGO Operations--Administration
The following were discussed during the site teleconference on Thursday, August 23, 2001.
From: Ed Chargois <chargois_e@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .
ACCOMPLISHMENTS
ACTIVITY
| Packages | Faxes | |
| In | 34 | 40 |
| Out | 8 | 31 |
Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS PAYABLE HISTORY DATA.
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
From: irena@ligo.caltech.edu (Irena Petrac)
SUPPORT (Wood)
Progress Period from 08.17 to 08.23
Accomplishments:
Weekly Advanced LIGO Project Controls meeting held Monday, August 20th at 1pm at Large SCR. Focus of the meeting was the AOS Second MRE Cost and Schedule Review.
Advanced LIGO MRE Proposal (Highest Priority)
Project Web Site for posting schedule and progress related data continues to be updated with the latest and greatest.
Schedule 08.24 to 08.30:Next weekly Advanced LIGO Project Controls meeting scheduled for Friday, August 24th at 9:30am at Small SCR. Focus of the meeting will be the IO Second MRE Cost and Schedule Review.
Advanced LIGO MRE Proposal (Highest Priority Task)
Will continue the development of the Advanced LIGO Project Controls Guide Book.
WBS 1.4.1.2 Project Controls (LIGO Construction)
Currently revising the FY 2002 budget to reflect information provided. Final version pending receipt of MIT proposal numbers.
The following Change Requests have
been submitted.
| CR-010006 | WBS 1.1.4 (OPS) | Roof Shelter for Concrete Pad Adjacent to Erosion Control Pond (Livingston) | M. Coles |
| CR-010007 | WBS 1.2.4 | Core Optics Components, Repolish/Recoat Beamsplitter | S. Whitcomb |
Press for the latest Contingency Needs Projection.
From: Kris Duncan <kris@ligo.caltech.edu>
From: Ed Jasnow <jasnow@ligo.caltech.edu>
After many delays due to missing or incorrect hardware and electrician scheduling, the "overhead mount" projector installations are essentially completed in three LIGO conference rooms. The projectors are now functional, but some "fine tuning" remains to be completed (cabling lengths and connector types).
A draft agenda for the September 19 Hanford Safety Audit was submitted to LHO for comments and proposed revisions.
Arrangements were made with Pasadena Occupational Health Center (POHC)
to perform LIGO laser baseline and exit eye exams. Seems that POHC
has a "blanket" contract with Caltech to provide health support services
as requested and has done some exams for LIGO in the past (?), but has
always just billed to one Caltech "account" (mainly the Safety Office?).
The LIGO exam paperwork will be "labeled" with LIGO and the Task number
so the billing can be directed to LIGO for payment.
General Items:
--------------
(F. Raab)
Following E5 run and LSC meeting, we are getting
back to business of commissioning.
A problem revealed by the E5 run was that the
temperature control/readout system
for the PSL reference cavity was not adequate
for supporting tidal feedforward
compensation, so Rick, Hugh and Paul Schwinberg
are making changes (below) that will
hopefully lead to mK precision. (For WA2K, 1
mK at the reference cavity is
equivalent to 1 micron mirror displacements in
the arms.) Corey, Josh, Richard and
others are charging ahead on WA4K. Rolf, Dave
and Richard are fixing up numerous items
in controls. Nergis Peter and Daniel have been
pushing the Common-Mode servo
installation. Dennis is working with numerous
people to bring the WA4K beams down the
arms for the first time and to quickly shut the
gate valves again.
LSC/PSL TIDAL
-----------------------------
(Radkins, Savage, Schwinberg)
We received a new version of the PSL Temperature Box which we
installed in the LHO 4k on Friday. It increased the gains of
the RCTEMP
and RMTEMP channel by a factor of thirty and revealed a steady
oscillation of about a degree with a period of about 10 minutes on
the
reference cavity can. On Monday we found the MINCO PID controller
in an
underflow condition and the temperature of the cavity at about 65
degrees C. We replaced the new box with the old and confirmed
the 65
degree estimate. Examining the board revealed the source of the
problem: 1 missing resistor which allowed one component at a summing
junction to float up and an incorrect resistor which increased the
contribution of the float up. As the sum floated up it drove
the summed
current down and the MINCO up increasing the temp. Eventually
the MINCO
was getting no current (<6counts worth) and heat was full on.
Looks
like 65ish degrees C is max the reference cavity can achieve with the
current insulation. The 2k should go higher with its greater
insulation.
With the correct components installed we were under nice control
revealing our bit level was down to 0.0009 degrees C per bit from nearly
a tenth degree C/bit. Now we see a steady oscillation of about
10
mdegrees peak with a period of 5 to ten minutes; this envelope also
drifts up and down with about the same magnitude and 2 to 3 times the
period. This is equivalent to 10s of microns drift in the arms
but at
the period of the tides it may be only a minor problem. These
estimates
are rough because we haven't had trend data and have been monitoring
with StripTool. This could be from the PID itself or the limited
resolution on the in-loop sensors. We have again put the old
box back
in the loop and have made changes to the new box to the in-loop
temperature sensors to achieve similar gains in the control.
We will
undoubtedly need to retune the PID after that modification.
4k IOO/ISC Work
------------------------------
(C.Gray, R. McCarthy, J. Meyers....)
It was discovered that the Lower (LR&LL) Coil Drivers on MMT2 were
bad.
After getting these guys fixed, a little bit of tweaking was required
to
regain alignment. Currently, the Mode Cleaner is attaining lock
fast and
easily; we also have everything aligned to get spots out of the IFO
REFL
and AS PORT viewports.
ISCT1 & ISCT4 were positioned and leveled to receive the beams mentioned
above. I have also begun stringing cable onto the tables for
the
electrical equipment (ie. detectors, shutters, etc.) . Presently,
we are
using the cameras on the table to help out w/ 4k IFO alignment (so
far so
good!).
Today - August 16, the X and Y arm gate valves were opened for the first time since the last vent period and the laser beam was directed down the arms. In each arm, the incident beam was nearly on the end test mass and was easily steered into alignment. This was the culmination of a superb installation and alignment effort associated with the OSEM replacement. Thanks to everyone who contributed to this effort.
Detector: Optics and Installation: Most of the cabling for the Laser Safety Interlock system has been pulled under the vacuum equipment in the LVEA, and the perimeter cabling in the VEAs is underway. Two vents have been installed in the roof of the PSL enclosure and the powered ventilators are now shut down. This allows convective cooling of the enclosure, and disabling the fan motors has measurably reduced the acoustic pickup we see on the table. Jonathan Kern
CDS: Replaced the Pentek on the ASC Crate last week. Modified the ASC WFS and the ISCT EO Shutter MEDM Screens and databases to be consistent with Hanford. Checked on the disk to disk backup of CDS disks and had to change backup script to accomodate increase in memory occupied by files. Created a writeup for the backup status at LLO. This is now publically available at: http://london.ligo-la.caltech.edu/cronjobs/backupwriteup.html
The current disk to disk backup status can be accessed on the web at: http://london.ligo-la.caltech.edu/cronjobs
Created a checklist to be included in the operator checklist for the above backups. Processing order for procurement of Frame Builder spare disks. Checked adminstration messages on CDS workstations to identify any erratic behavior of the work stations. Installing gv (an addition to ghostscript) on CDS machines. Planning to provide web interface for the Ligo Livingston medm screens.(Chethan Parameswariah)
PEM: Did some troubleshooting of the microphone power supplies
in preparation for installing microphones in the LVEA next week. Began
working on the template for the magnetometer reference web page. Found
and corrected the configuration problem with the accelerometers. So all
of LLO's accelerometers are operational as of 8/17/01. Found the cause
of the noise that was aliased into our 256 Hz channels in rack 1X5, please
see ilog entry on 8/17/01 for details. Doug Lormand
GC: We have upgraded our mail server to a faster machine. We
have had some network difficulties, which have been
traced to a problem with the Bell South T1 line, and which have been
repaired. We are expecting to have our second T1 line working tomorrow,
and we hope that, in addition to the increased bandwidth, a second line
will also give us improved
reliability. (Tom Evans)
LDAS: Controlmon and linuxbox1 were updated to RH 7.1 using the new scripts. They are both running OpenSSH now. Beowulf and Datacon were changed to OpenSSH also. Gregg's temperature monitoring script alarmed yesterday when the AC was cut off to the mass storage room for maintenance. The AC was cut off for approximately 30 minutes. Continuing work on Big Brother and the APC software. (Shannon Roddy)
Control room issues: All operators have been busy with commissioning
tasks this reporting period. I've been working with the RGA software (from
the control room) for most of the week. Met with James Finney (LSU) concerning
the weather
stations. Work now in progress include changing the dual 10 watt solar
panels with a single 30 watt regulated panel on all 3 towers, replacing
the small internal battery with an external gel-cell battery (all 3 towers),
and general tuning-up/cleaning-up of the towers. All efforts are aimed
at making our weather stations more robust with high reliability. Rich
Riesen
| Installation&
Commissioning:
Livingston |
Other Science/EngineeringActivities:
Issues/Concerns |
See also the Installation web page
WFS with the full interferometer. WFS 1 (antisymmetric port) has been used for some time to control the differential alignment of the ETMs. After setting up WFS 2 on the PRM, we tried it on the full interferometer. The differential ITM control seems to work well, but the common mode feedback pulls it away from the right point. Probably need to get the rest of the sensors (WFS 3 & 4) working as well.
Mode cleaner servo. Fixed several problems in the mode cleaner servo electronics having to do with slew-rate limiting distortion, and accompanying broadband noise generation, in several of the op-amps on the board. Also fixed an offset problem in the mc length path, and a gain peaking in the psl path. The mode cleaner now appears to work well, at least according to in-the-loop measurements: the unity gain frequency is ~100 kHz; the error point noise goes down with increasing loop gain. We were able to open up the EO shutter so that when the mc is locked, the shutter transmission is 100%, as intended.
Noise investigations. Studies of the full interferometer noise showed that the differential mode noise was coherent with the common mode noise over a few hundred Hz region around ~300 Hz; in this region there is a broad peak in the spectra of both channels, caused by gain peaking in one or both loops. We were able to reduce the differential mode noise in this region by about a factor of 2 by tuning the balancing of the ETMX-ETMY common mode drive.
Around 100 Hz, where there is little coherence between the common and differential modes, the differential mode noise appears to be close to the noise level of the Pentek DACs, which provide the ETM control signals.
Interferometer common mode servo. Given the coherence between the common and differential modes, we have begun to implement the common mode servo, with feedback to the laser frequency. This will greatly reduce feedback to the ETMs in the frequency of interest, and hopefully gain additional frequency stability as well. Transfer functions of each of the three paths in this servo have been measured using a single arm cavity. The implementation of the servo on an arm cavity has had mixed results: the MC additive offset path is seen to be effective, but we haven't yet achieved stability when also using the MC length path.
Testing and manufacturing of silicate bonds is "on hold" until the work is finished.
Here is my idea. I suggest that an investigation of optical stability of a resonator having one mirror of flat top kind is a good start. The other mirror will be truly flat so that the corresponding cavity is the equivalent of half a full resonator. There are indeed several advantages that I am listing if such a cavity will give the answers we would like.
For the whole interferometer:
What about the bump?
Investigations are going on to check on the impact of removing the bump in the middle of the mirror.
Since the flat top beam has been constructed as a superposition, the associated phase profile is a sort of superposition too, and watched from a side there are two spherical surfaces overlapped.
The convexity has a physical meaning and there are many ways to interpret that.
I dare say that the photons hitting the central area and the anular region are in interaction. This interference guarantees the flatness of the power and that can be easily corrupted.
The bump is around lambda/10 and a mismatch of this order of magnitude is very important. What is the impact of this change in amplitude over the termoelastic noise must be evaluated.
We recommend that we stop testing of the prototype periscope at CIT and ship it to LLO for an actual frequency noise test mounted to their PSL table, before we produce any more periscopes. In the meantime, we can evaluate the Ultima mount resonance without needing the periscope.
The pre-modecleaner servo down in the PSL Lab is also being checked out, prior to some modifications that will hopefully allow the bandwidth to be increased. Now that the high voltage power supplies have been returned from the 40m Lab, we are now able to run the pre-modecleaner.
Rick Karwoski
PSL Custom Boards: Site Spares
We will be delivering the following spare modules to LHO this week:
80 MHz VCOWe will concentrate on Spares to Livingston
FS Servo
FS Reference (21.5 MHz)
PMC Servo
PMC Reference (35.5 MHz)
Two RF photo detectors to follow mid next week.
Sander Liu
Repaired and retested the PMC servo card. The unit is ready for delivery.
Designed a 31.5KHz notch filter for use in the future.
2) Finished building 4kASC VME crate and loaded new code (compatible with digital suspensions) and ran some preliminary tests.
3) Upgraded digital suspension (DSC) code to version which supports GDS TP/EX in both LVEA and end stations.
4) Split digital suspension supervisor to two MIPS processors, as one was overloaded.
5) Connected all of the above together and began integrated testing.
6) Replaced 2K LSC CPU with 1GHz Pentium; bus analyzer is installed
to verify timing during noise studies.
7) Went back to standard Clock Driver Modules in 2k LVEA data acquisition crates.
Added the capability to read the names of data sets and their description
(consisting of time intervals and channel lists) to the lidax program.
This allows to query and download frame data from the archive. This feature
is built on top of the data flow manager and lars.
This week we concentrated on recovering the sensitivity that was lost
last
week when we installed new mode cleaner servo electronics to boost
the
servo gain. We had little difficulty in recovering our former
3e-17m/rHz
level after we identified a cross coupling between the north and south
arm
cavities. We are currently eliminating this coupling by
de-tuning the
south cavity so that it does not resonate with the north cavity locked.
This is obviously a temporary solution, but it has allowed us to identify
one prominent noise source and to start thinking about strategies for
reducing it.
Further shaping of the feedback filters has produced an improvement
of
about a factor of 2 in displacement sensitivity at 3kHz. Our
sensitivity
is now 1.7e-17m/rHz at that frequency,
compared with a little over
3e-17m/rHz before. Sensitivity at 1kHz is also improved, albeit
not quite
as much. We are now measuring the individual noise contributions
from
various sources, mostly electronic, to try and find out which one is
dominant.
We also have good news on the sapphire front, in that Crystal Systems
reports the successful production of our fourth and final boule.
This
transmissive optic meets our original, rather stringent specs including
a
hemex core. The sapphire blanks are now having their o.d.'s and
bevels
ground and polished at Insaco.
Seiji Kawamura has returned to Tokyo. Many
thanks to him for all his help
and patient teaching!
no report
Simulation and Modeling (Bhawal)
This week:
Weekly Physics Meeting
----------------------
Hiro summarized the pros and cons of the computation of power spectral
density
by E2E's 'psd_out' module and proper way of using the module.
Bill Butler presented his progress in generating noise curves from
the darkport
outputs of E2E's Han2k model. A long discussion followed on how to
include BSC/HAM
model inside the Han2k model and pass seismic noise (with correlations
among
various stations properly taken into account) through it and the suspension
system,
how to include realistic angular fluctuations, etc.
Sensitivity curve and psd
-------------------------
Hiro worked with Bill Butler during the LSC meeting last week. Bill
could
simulate to calculate a proper sensitivity curve based on the existing
Han2k model plus the thermal noise module developed by Biplab. Bill
is
improving the noise model.
After Hiro came back to Caltech, he did some modification to improve
the
performance of psd, and updated the e2e primitive module document to
describe the psd module, and caviats when using the psd module.
Photo detector simulation
-------------------------
(Hiro) Responses of finite non-uniform photo detectors is calculated
by an
application "detmap", and the data file created by it is used by the
simulation program during simulation runs. The intergration method
used
was not appropriate, and it introduced a large error for a detector
with
a large radius. It is fixed.
(Biplab) ran several cases for PSL's FSS model using RFPD to estimate
the
frequency noise levels.
Alfi
----
(Bruce)
- Continuing implementation of Alfi box and primitive file parser for
Alfi5.
Completing initial implementation of main ALFINode code for
bookkeeping.
- Discussing with other Alfi5 programmer a schedule of code completion
of
Alfi5 system.
(Melody)
- Continued on setting up the unit testing framework for the project.
Looking into using JUnit and the java.awt.Robot classes.
- Figuring out how to extend the JGo classes.
Last Week (LSC Week):
Mode Mismatch
-------------
(Biplab)
(i) Checked that the effects of mode-mismatch simulated in full
LIGO model
including recycling summation cavity match
well with analytical derivation.
(ii) MIT's FFT: With help from Bill Kells sorted out several
issues about FFT runs.
Started running FFT code and comparing results
with full LIGO e2e runs.
Results of comparison at this initial stage
are encouraging but I see need
of more detailed understanding of how FFT
code runs corresponding to a
same-parameter run in e2e or vice versa in
order to sort out differences.
CVS Archive
------------
(Ed Maros) Moved the CVS archive for the e2e work onto ldas-sw.
Gave presentation on how to use the CVS archive
in its new location.
Alfi
----
(Bruce) Continuing implementation of Alfi box and primitive file parser
for Alfi5.
(Melody)
- Discussed Java coding conventions with Bruce. Currently modifying
the
existing code to comply with the conventions.
- Reorganizing the Java code packages. The code should be checked back
in by
COB Thursday.
Mechanical simulation work (from July upto last week)
-----------------------------------------------------
(Virginio) This is my report with just the main activities about the
mechanical
simulation. I apologize for including in a single weekly report
the activity
of the entire month of July (almost).
- Three-dimensional LIGO I Suspension simulation is ready to be
plugged into
e2e. The simulation includes a realistic topology of the actuators
and sensors
also. Geometrical suspension asymmetries can be easily introduced.
The cross
check with an experimental spectrum using a set of OSEMs suspension
has been
successfully done with an agreement of about 2%. To obtain a
better
characterization of the suspension local controls, a set of new
measurements
needs to be done.
- A simple way to introduce the Hytec models of the BSC stack
is under study.
At first look it seems necessary to introduce some new functionalities
to MSE
to allow the possibility to merge two separate state space representations.
- Some tests have been done to introduce the suspension violin
modes also.
Boston week: (Assembly/Installation)
Worked mainly with Calum Torrie, Norna Robertson and Rich Mittleman
to assemble
the second quadruple pendulum chain. Thanks the work I made during
the weekend
I was able to run some measurements to characterize one chain
of the suspension.
I worked essentially on the reacting chain because we didn't
have any OSEM really
aligned yet.
- Mounted three LVDTs which allowed to measure the longitudinal
transfer
functions from the "new" mass to the "upper" mass and to the
"middle" mass,
using the upper most stage as mechanical compliance. The sensor
parts were
attached to the suspension masses by using a pretty good double
sided scotch tape.
- Mounted also another coil actuator (an old and bigger OSEM)
between the two
upper masses acting against the reacting chain but I was not
able to make it
work using the control box inputs (pin out incompatibilities).
Measurements:
I took several sensors spectral densities hoping to be able to
make some
frequency mode characterization. I did not have time to do a
more accurate
system identification.
I measure the t.f. which seems to be reasonably good.
Those measurements are affected by a large cross coupling with
all the DOF
because the chain was not properly aligned yet and because of
the
orientation of the sensors and the actuators. The actuation was
done using
the control box longitudinal input.
Observations:
The LVDTs seem to work fine and particularly good for t.f. measurement
(good sensitivity and large dynamic range)
It is clear that it is not easy to measure the t.f. using the
OSEMs
because of the small dynamic range of the sensor and because
of the small
clearance between the magnets and the coils. All the coils need
to be
quite well aligned to be able to shake enough the mass. This
alignment
doesn't seem to be critical for the damping of the suspension.
I didn't have time to measure any t.f useful for the study of
the performance
of the active damping. The LVDT can probably be used to verify
the efficiency
of the damping for the lower stages.
The most important result is that the results obtained show the
possibility
to measure the transfer function of the entire chain (4 stages)
using the
LVDTs as sensors.
Last week
Worked with Giancarlo Cella to fix some library bugs. The following
ones
seem to be solved:
- The phase lag going through the mechanical resonances is now
properly
computed when a viscous damping is plugged into the simulation.
- The simulation bug on the violin modes of a wire under tension
(without
the flexural contribution) seems to be solved. The Library now
works
properly to compute the right frequency spectrum of a simple
suspension made
of a wire and a bob. This approximation works reasonably well
(applicable)
when the wire tension is high compared the flexural restoring
force.
Comparison with a real experimental data gives a good result
less than 10%
of discrepancy in the frequency spectrum. Next step which is
under progress
also is to check the violin mode simulation inside a more complex
system.
- Wrote a simple program to check the class which implements the
flat Blade
(a la Virgo) to finally have the description of all the main
internal modes
of the advance LIGO suspension.
LIGO Data Analysis System
Software Systems (Blackburn)
This week:
LDAS is readying itself for the next MDC to take place at
MIT the week after Labor Day Weekend. This MDC will exercise
LDAS, two stochastic background search codes, an excess power
search code, the so called TF Cluster search code, and the
so called slope detection search code. Participation will
include CIT, MIT, UWM, PSU, LSU, UTB and Loyola - a really
big turn out.
Getting the dataConditionAPI ready for this MDC has proven
rather difficult. A new library was added to LDAS, the "MIME"
type library to support the inserted BLOB data objects into
the database by the search codes preparing for the next MDC.
This library has introduced a very difficult and rare in-
stability into the API which is proving hard to track down.
In addition, this large a group of search classes have place
a lot of new functional demands on the dataConditionAPI which
are rapidly being added in the true spirit of "just-in-time"
interpretation.
Several of the new search codes, including the stochastic
codes being developed for this MDC have requested the ability
to produce output data products in the form of frames. In
keeping with the frame specification, the eventMonitorAPI is
formulating ILWD data object which are a representation of
the FrProc (processed data structure). However, it was soon
discovered that the frameAPI did not have a true implementation
to support the frame specification. And these previously
unused data structures were all being treated as FrADC data
structures in several unfortunate ways. The frameCPP and the
frameAPI.so are being re-worked to correctly handle FrProc
data structures, though it is not yet clear if this will be
available in time for the MDC.
The frameAPI.tcl code has been enhanced to support a broader
level of frame query. It is now possible to read in data
from both LLO and LHO at the uniquely over user specified
GPS times. This will support the needs of the MDC.
A code freeze of LDAS will go into effect either Thursday
night or Friday depending on the staff's ability to stabilize
the dataConditionAPI. Expectations are to have the next
release of LDAS (0.0.20) by next Thursday. We are working
very closely with the LSC this week to coordinate changes
in the wrapperAPI, LAL, and LALwrapper so that a single
coherent release of all of these packages will be made
available at the same time.
The effort to migrate to GCC 3.0.1 has stalled. There is
little chance this will happen before the fall of this
year and may have to be delay until winter due to several
short-comings of the GCC 3.0.1 compiler (lack of support
for long long and still unable to handle C++ exceptions
properly).
Last Week (LSC Week):
In expectation of a new release of GCC, version 3.0.1, due out this
week, LDAS was once again built against the buggy but more standardized
GCC 3.0. There were several source code changes required as part of
this
migration test which have now been made. The biggest surprise was the
discovery of a bug in the I/O handlers for unsigned integers in the
new
GCC compiler.
A new patched version of LDAS 0.0.19 compatible with the openSSH shell
was placed on the development server and rsync'ed to the sites. This
was necessary to continue to have a running version of LDAS at Hanford
which is now using the new openSSH.
LDAS was enhanced this week to more fully support translation of out-
put results into frames. Several test were made using various LDAS
API data products as sources for frame data.
The frameAPI was also upgraded to support more complex frame data
queries of the form suggested by Sam Finn. These will be needed for
the next MDC. One of the test completed involved taking the multiDim-
Data from search codes running inside the wrapperAPI and casting these
to frames.
There were a few software issues that came up this week involving inter-
API deadlocks. Code changes have been made to the genericAPI and have
been tested and shown to resolve the earlier problems.
a new patch file was created for using the latest release of LAM's
message passing interface library. LDAS will officially migrate to
this version of LAM with the next release of GCC.
Hardware Systems (Anderson)
This week:
LDAS Administration
-------------------
Caltech
-------
(Dan Kozak)
I did the usual HPSS stuff (unjamming tapes, restarting servers,
repacking tapes, adding users, etc.). Mostly repacking tapes,
since
we're once again using them up at a furious pace. In the case
of the
Redwood tapes, this is directly LIGO related as the E5 data is being
ingested.
I set up the links for the E5 trend data.
I did some cursory testing of the T3s with QFS using separate T3s for
metadata/data and trying out the shared mode. This showed a slight
improvement in performance over using the internal Sun disks for
metadata (as one might expect), averaging ~80Mb/sec for reads.
And the
shared mode seems to work fine--in general the reader can read faster
than the writer can write.
But since it's not likely that we'll use that configuration (since it
would involve dedicating a whole T3 to metadata), I went back to using
a single T3, now with 2 partitions, one 1Gb partition for metadata
and
the rest of the disk for data. I'm still working with this, but
it
seems to be about a 12% performance hit on reads (i.e. about 70Mb/sec)
for 48Mb blocks and much worse for small blocks (e.g. <2Mb/sec;I'm
triming the number of tests I run because it's taking a forever to
run
the typical tests at that speed).
---- Forwarded message from Dan Kozak -----
Tested the shared reader/writer QFS configuration using a single T3
for
both data and metadata. Haven't calculated averages for all the
runs
yet, but here are some preliminary results.
With the T3 cache on and the reader and writer in synch with each
other, write speeds of 8 second frame sized files were ~70Mb/sec, read
speeds were ~60Mb/sec. With a delay to simulate the behavior
of the
framebuilder (i.e. only writing an 8 second frame sized file once every
8 seconds) the reader easily kept up with the writer.
With the T3 cache on but the reader and writer out of synch gave writes
averaging ~62Mb/sec but with more variation in throughput between runs
(46-80Mb/sec). Reads hovered around 34Mb/sec.
Turning off the T3 cache but with the reader and writer in synch gave
~46Mb/sec write and ~50Mb/sec reads, with a bit more variation in
throughput between runs. Are we seeing the effects of the disk's
own
caching here?
The worst case scenario (T3 cache off, reader and writer out of synch)
gave ~35Mb/sec writes and ~45Mb/sec reads.
I think contention between the reader and writer for metadata (and
data?) plays a part in these numbers.
----- End of forwarded message from Dan Kozak -----
(Al Wilson/Stuart Anderson)
An informative meeting with Sun has uncovered a low-cost solution to
sharing the large LDAS disk cache at LHO and LLO to additional CDS/GDS
machines without having to do an expected major upgrade of disk controllers.
The software to enable this will be officially available around January
or February of 2002. An interim solution with 1 or 2 shared T3's will
be implemented much sooner.
The LDAS operating system configuration software (cfdef) has been setup
for controlling Solaris machines as well as Linux and is undergoing
initial
testing as the MIT Sun servers are being initially configured.
The LIGO archive has all of the trend frames from E5 and all of the
LHO full frames successfully ingested. However, UPS has lost the shipment
of data from LLO so it will have to be re-written from the disk cache
at LLO
and shipped again via, FedEX!
The ldas-dev Beowulf was upgraded to the linux kernel 2.4.6 to fix,
"critical shortage of bounce buffers." An 18" flat screen monitor
has been installed and is working in the cramped quarters in the
machine room.
The ldas-test system has been upgraded to RH7.1/openssh but is still
being used for QFS testing. A 3rd 2200VA UPS has been installed to
run the 2 E450's in 215 Synchrotron providing enough overhead to
allow a simultaneous power up of all LDAS equipment.
MIT
---
(Keith Bayer)
Trouble-shot E450 reboots w/ sun
Sun came out and change CPU#2 on E450
Installed powerstrips on back of cluster rack
(this replaces the ad-hoc power strips we were using)
Starting to install Caltech images on ldas equipment
data conditioning server
Livingston
----------
(Shannon Roddy)
LDAS is now up and running under RH7.1/openssh.
Controlmon and linuxbox1 were updated to RH 7.1 using the new scripts.
They are both running OpenSSH now. Beowulf and Datacon
were changed to
OpenSSH also. Gregg's temperature monitoring script alarmed yesterday
when the AC was cut off to the mass storage room for maintenance.
The
AC was cut off for approximately 30 minutes. Continuing work
on Big
Brother and the APC software.
Hanford
-------
(Greg Mendell)
0) LDAS is now up and running under RH7.1/openssh.
1) Assisted in upgrading linuxbox1 and controlmon to RedHat 7.1.
2) Assisted in switching from ssh to openssh on the ldas network.
(This
change has no effect on Guild or users running jobs from outside the
ldas network.)
3) Sunbox1 has been renamed tapecontrol. The LHO LDAS network
temporarily has no sunbox1. We do have a Sun Ultra 10 formerly
used as
datacon or beowulf) that will be come the new sunbox1.
4) Dell has replaced LHO beowulf node 11's hard drive. I am currently
re-running the burn-in test and configuring the node. It should
return
to service by the end of today.
5) Worked with CDS to get minute and second trend data collection
stabilized, after repeated disk failures on the CDS IDE raid box that
stored trends. For now, we will use a combination of a loaner
D1000
local the framebuilder and the one of the T3s on the ldas network to
store trend data.
6) Worked on developing the DSO for the known pulsar search within
ldas. Mostly this involved upgrading the OS and packages on my
laptop,
and starting to initiate planning for the requirements for generating
short time baseline FFTs of the data (SFTs).
Data Analysis Activities
This week:
Last Week (LSC Week):
Vicere':
* I have continued developing a method for blind burst detection,
which takes into account the correlations due to the colored
noise. I should be able soon to start writing the code and test
it on PEM data: the goal is to have the analysis ready for the
network meeting in September.
General Computing (Wallace)
This week:
MIT:
-Working on setting things up for the MDC. Includes setting up
video conferencing as well as a wireless network.
Livingston:
(Tom)
-We have upgraded our mail server to a faster machine.
-We have had some network difficulties, which have been
traced to a problem with the Bell South T1 line, and
which have been repaired.
-We are expecting to have our second T1 line working
tomorrow, and we hope that, in addition to the increased
bandwidth, a second line will also give us improved
reliability.
(Shannon)
-Nothing to report as I am switching roles to dedicate time 100% to
LDAS
except in case of emergency.
-I will be preparing a report on information that I learned at the
USENIX
Security Symposium in Washington. I plan on taking Monday and
Tuesday
next week to prepare this.
Hanford:
(Christine)
- Busy cleaning up after the LSC Conference. All projectors and
laptops
have been packed and mailed back to the sites they were borrowed from.
- The Sun technician came out to repair an Ultra 60 that had been DOA.
It is working fine now.
- Purchased a replacement disk for an Ultra 10 that can no longer access
its disk.
- Requested information from Ed Chargois as to how to dispose of several
monitors which no longer function. Also, how to dispose of outdated
software.
- Prepared an estimated budget for FY 2002, as well as reviewing current
expenditures and comparing them to the financial reports for
discrepancies.
- The wireless network was a big hit with everyone, as was DHCP.
I
have several on site staff who have requested wireless cards for their
laptops instead of the ethernet connection.
- Requested the latest version of the Pcard software be sent to us
on
CDROM. Found out that we are several versions behind Caltech.
- Helped several users get access to the Caltech ITS site licensed
software for Norton Antivirus and AutoCAD.
- Requested quotes and used my pcard to purchase some supplies for
the
site CDS network.
CIT:
(Mick)
-With Mike and Wendy, assembled new rack and prepared for movement
of PC
servers
-From Lisa, learned to configure a new hard disk in UNIX
Learned to configure a new hard disk in UNIX
-Loaded ascella and new Blade 100 (cdsbdl)
-Compiled updated instructions for loading GC UNIX workstations; working
on
CDS instructions
-Assisted Lisa restoring Mohana's email from daily backups and
reconfiguring Eudora
-Compiled list of LIGO PCs to keep track of which we have images of.
-Began Tape Restoration Project - this one is going to be a doozy.
Older
tapes are inconsistently and inconveniently labeled. Managed
to restore 1
tape completely and most of another. Current status: temporary
restore
destination drive is full.
(Mike)
-Performed maintenance work on multiple printers, which included paper
jams
changing drum kits and toner cartridges.
-Charlotte Py, I loaded Mechanical Desktop this has the .IGES translator.
-Worked in the server room cleaning out some more items getting ready
to move
NT servers into server room.
-Loaded a PC for 40meter 200Mhz P11 with 64 MB of ram.
-Barry Barish, his office PC power failure, the switch was burnt out
the
case had to be replace.
-Dr. Barish, Laptop ran a disk and tape backup and setting up multiple
network configurations for travel, using a program called net switcher.
-Assembled a Blade 1000, installed 4Gig of ram and DVDROM.
-Donna's, PC software glitch that corrupted OS, must reload OS. Backed
up
users DATA.
-Worked with Larry and Keith on setting up video conferencing.
(Lisa)
- Spent some more time working with the Solstice Backup software.
The backups
are running very well. I've done some restores, which are soooo much
easier than
with ufsrestore. The NT's are now backed up daily -- except Pherkab
which for
some unknown reason can't talk to the server.
- Changed the mount point on op140m in the 40meter.
- Fixed up Flavio's pc which had some residual corruption after a virus.
- Usual round of account and alias creation.
- Figured out a way for people to use the ITS site licenses for Matlab
if all
licenses are taken on Ligo. Contact me if you would like details.
- Put an OS on a blade100. The final configuration for the workstation
is not
yet determined.
- Fixed some funky e-mail problems for Irene and Mohana.
- Fixed a weird problem with dial-up to the 800 number. A note
to those who use
the modem pool: if you aren't using DHCP, you really should be.
It avoids
weird configuration errors.
- Spent some time working out some detail level issues with using Ghost.
(Wendy)
- loaded Solaris on Vega for practice
- ghosted a few drives
- tested a hard drive
- installed Exceed on a Wilson House PC
- edited/updated inventory map
- checked on PCs at Wilson House
- put in new toners and drum in printers in Millikan and Bridge with
Mike
- old M30 died, configured new M30 in terms of IP address, additional
software, printers, etc.
- in the process of rebuilding loaner laptops and imaging them
(Larry)
-The usual procurement issues. So far just making some equipment and
supplies
purchases no major items to track down. Working on SUN maintenance
contract for
the servers.
-Received a couple of budgetary quotes for the GIGE network and will
be
requesting a few more from a couple of other companies that have equipment
here
on campus.
-Worked with Mike and Keith on the video conferencing system. We found
the same
problem here that we had at Hanford. The units the camera is connected
to and
running the VRVS software needs to have at least 256MB of ram for it
to run
cleanly. Also, having a clean install of the OS, meaning that the OS
was not
upgraded but loaded on from scratch, improves the reliability of the
video
conference session. We've found the VRVS SW to have some difficulties
if it
needs to be re-installed.
Work on the video conferencing will continue.
-Discussed the wireless and DHCP situation with the other Sysadmins
at the sites
and have decided that the MAC address of the machines will now have
to be
recorded in order to track down problems. This information will also
probably
become part of the information needed for conference attendees.
-The general items of fixing PC's, updating accounts and e-mail aliases.
(Barbara)
- Fixed problems with search tools when searching for names with apostrophes.
- Fixed a couple of problems with the costbook reports. Reposted
the PDF
versions.
- Install new LSC rosters. Now any database changes are reflected
immediately in the rosters. Began working with Rita so the LIGO
roster
will be the same.
- Installed LDAS site changes for LDAS MIT.
- Continued posting LSC transparencies -- 90 so far.
- Make other web site changes to Travel, Fellowships, LSC, TNI.
Last Week (LSC Week):
*** MIT ***
(Keith)
- Installed DHCP on SB100 router
- Installed NAT on SB100 router
- Brought up wireless network at MIT
Investigating various configurations
- Installed video software/hardware on PC
(all in prep of MDC)
- Tracking down SCSI bus errors on new file server
*** Livingston ***
(Tom)
We have gotten a price from LSU for the router for our second
T1 line. They should be out here next Tuesday to install a
temporary router, which they will loan us until ours arrives.
*** Caltech ***
(Larry)
-Purchased a number of items for the LSC. Mostly cables and converters
for
the Video broadcast and network.
-Installed the video card and camera on the computer assigned to the
presentation computer. The computer needed more memory. A minimum of
256MB
is needed for things to work correctly. The camera worked with the
VRVS
software for some time but gradually degraded to where the s/w will
not
even reload. After some testing it was concluded the system needs a
complete rebuild. Used a different s/w pkg. for the LSC
mtg. Tues. session.
The VRVS system looks to be a good way to do video conferencing.
Thanks to Mike P. who spent a great deal of time remotely on the setup
of
the system.
-Still fighting virus issues.
-Setup a couple of computers for the LSC, got Linda Turner up
and running
and assisted a number of other attendees with their setups.
-The Hanford group, Christine, Dave, Richard and others did a great
job in
preparing for the meeting. Many positive comments on the wireless and
DHCP
setup, so Christine should be pleased with the effort to make things
work.
(Mike)
- Loaded a PC with full General Computing software installation.
- Power outage on Friday morning that caused multiple sparc stations
not to boot to their last state; file system was corrupted. I had to run
fsck command to get these systems back up.
- Helping Larry setup a video conference, broadcasting out of Hanford.
- Set up Net Meeting with Larry Wallace for LSC meeting on my computer,
and then set this program up on Dr. Drever's computer. I had to not only
installed Net Meeting but I also had to download video capture software
for win98 'directx8 plug-in'.
- Working in the server room with Mick and Windy supervising moving
furniture around making room for new rack and moving out tape cabinet from
original spot. Removing back doors off existing computer racks. Then we
setup a new computer rack, which includes assembling shelves and drilling
holes in the top of rack to run ethernet cables threw and setting up power
strips & UPS. We are just about ready to move NTSRV's into server room
but well wait until Larry's return on Monday.
- Worked with surf students trying to get IGES translator installed
no luck on this.
- Added some more memory to a few computers.
- Going over tape restore project with Lisa.
(Wendy)
- Moved furniture around with Mike
- Moved surplus equipment to subbasement with Mick
- Successfully printed out computer map on the plotter
- Learned to ufsdump and ufsrestore
- Learned to scan documents for OCR software usage
- With Mick, installed new server rack and wired it
- Loaded one PC
- Tested memory sticks, and installed memory stick in computer M30
(Mik)
- assisted Mike loading vega
- with Mike and Wendy, assembled rack in server room, and prepared
for
movement of PC servers
- began addressing tape restoration project (learning how to correctly
use
ufsrestore, currently writing script to ease process)
- learned to configure a new hard disk in UNIX
(Lisa)
- built an ultra2 with an ext. hard drive and tape drives for the tape
restoration project. Trained Mick, Wendy and Mike on what all
was involved.
Got the restoration underway.
- created a couple of modem pool accounts
- worked on some small unix problems in the 40meter.
- tried to setup a black list on the mail server. I got part
of it but I don't
think we are configured use the m4 pre-processor. Larry and I
are going to work
on it when he gets back.
- setup an ntp server on rana for the 40meter.
(Barbara)
- Continued efforts on automating web LSC roster to be data-driven
web pages.
- Modified costbook detail report for basis of estimate and task list.
- Began posting LSC transparencies. Updated Publications pages.
Installed reworked News, Travel, and Calendar pages. Began migrating
to a new style sheet.
Fram Janeen Romie:
Working on 40m TM suspension design.
Working on AdLIGO SUS blade spring analysis.
From Rich Abbott:
Wrote initial requirements for voice coil actuator design
Put together information to order 12 more of the capacitance position
sensors with the help of Marcell Hammond.
From: Francesco Fidecaro <fidecaro_f@ligo.caltech.edu>
Akiteru, Alessandro, Florian in Hongo.
Great exciting news. Accelerometer loop now closed and IP damping clearly
visible on spectra. Residual motion above 0.02 Hz at IP platform level
is expected to be well below fringe spacing. In attachment the effect of
damping is clearly seen.
Lia
Analyzed 2+4 days of LVDT data. Found 2 LVDT with primary that slipped
from support. Will test with improved primary binding. Is performing test
with external, stable, signal generator.
Mathieu
Varied wire length to see effect of torque on stress. Found it to be
very small. Stress accumulates on sharp edges. Will try to smooth junction
between wires and prism. Also tried a split cone instead of a prism, but
the connection to the suspension wire is unclear.
Charlotte
200 micron x 5 mm x 10 mm joint, Delta T is now 3.4 K with 4 K reservoir.
Max stress is now 109 MPa, allowed max 150 MPa, using tensile strength
300-400 MPa times 0.5 safety factor. Using 180, 200, 300 micron joint thicknesses,
studied max allowed angle for bending. Found linear behaviour. Worked on
analytical model on rectangular rod to check heat flow calculations. Numerical
and semi-analytic model with T^3 conductivity coincide within 10^-3 K.
Model of cylindrical flex joint for Inverted Pendulum. Elastic constant
37 kN/m in given geometry. Study of thermal conductivity with sink at 4
K and 250 mW power to be dissipated. Low and constant T gradient achieved
over the 2 flex joints. Also tried with 20 mK sink, effect of T^3 conductivity
clearly visible. Need AUTOCAD extension for IGES format (this format is
now required for all contractors of US administration, according to the
IGES web site...).
Francesco
Fruitful LSC meeting in Hanford. Exploring gravity gradients at low
frequency, in particular from atmospheric origin.
For additional information about this report, contact sanders@ligo.caltech.edu