Weekly Report for Week Ending August
16, 2001
The LIGO Executive Committee
Agenda for Monday August 20, 2001 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
-
Announcements
-
LSC Issues (Weiss)
-
Comments on Weekly Report
-
WBS 1 LIGO I Construction (Lindquist)
-
Field Change Orders/Contingency Liens/Change Requests
-
WBS 2 LIGO Lab Operations
-
Administration (Lindquist)
-
Sites (Raab, Coles, Shoemaker, Sanders)
-
Detector (Whitcomb, Coyne)
-
Campus Research Facilities (Weinstein (40 Meter), Libbrecht (TNI), Zucker(LASTI))
-
Data Analysis and Computing (Lazzarini)
-
WBS 3 and 4 Advanced R&D and LIGO II
(Sanders)
Executive Committee only 11:30 - noon
Topics:
Special Items: MINORITY UNDERGRAD OUTREACH, LSC MEETING REPRISE
Special Announcements:
Weekly
Report Highlights
LSC Issues (Weiss)
no report
LIGO I Construction/LIGO Laboratory
Administration (Lindquist)
WBS 1.2 LIGO Operations--Administration
LIGO Weekly Site Telecon (Lindquist)
There was no site teleconference on Thursday, August
16, 2001.
The list of current actions revised to reflect
the status of open actions assigned through August 2, 2001 may be found
at
ACTION
LIST.
PROPERTY
MANAGEMENT (Chargois)
From: Ed Chargois <chargois_e@ligo.caltech.edu>
-
Nothing significant to report.
DOCUMENT
CONTROL CENTER (Turner, Mak)
>From: Linda Turner
- turner@ligo.caltech.edu>
Web pages for the
DCC give simple how-to's for document numbering, easy access to the latest
on-line documents, and search capabilities for the DCC database. Take
a look. . .
ACCOMPLISHMENTS
-
No report this week. Linda is at Hanford
for the LSC Meeting.
>From:
Cleveland Mak <mak_c@ligo.caltech.edu>
ACTIVITY
-
most of my efforts for
this period were geared toward handling/processing/printing/transferring
of LSC documents from the LSC Meeting at Hanford.
-
some progress was made
on auditing of PSI drawings.
|
Packages |
Faxes |
| In |
44 |
30 |
| Out |
9 |
31 |
Press here to access
the DOCUMENT CONTROL CENTER
WEB PAGE.
COST SCHEDULE
CONTROL SYSTEMS (Cunningham, Brambila, Kaufman)
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS
PAYABLE HISTORY DATA.
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
-
Completed new change orders on subcontracts to CSIRO, and Waveprecision
(General Optics). Awaiting acknowledgements of receipt of change
orders.
-
Added funds and extended performance periods through September 30, 2002
on blanket purchase orders to Newark Electronics, Pasadena Eye Medical,
and Red Wing.
-
Completed closing PO's through March 2001. Prior to March 2001, there
are only 11 purchase orders which remain open. There were a few with
nominal dollar amount encumbrances which have been submitted to Dorothy
for a decision whether those funds should be released and the PO's closed
or whether they should stay open for more activity.
-
Payment requests submitted for goods and services which normally would
be issued under a purchase order, the payment requests are now being processed
and issued under a purchase order.
-
The new subcontract to E.G.O. is still pending.
From: Florence Kaufman <fkaufman@ligo.caltech.edu>
-
Submitted Cost Transfers for costs charged to roll-up
task instead of correct sub-task.
-
Updated Visitor Program report for new visitors per
information provided by Donna.
-
Sent Finance a schedule of funding realignments required
for R&D program.
-
Prepared a revised calculation of projected underspend
for Operations based on increased spending in July.
-
Reviewed R&D report prepared by Cindy.
-
Prepared comparison schedule of FTE's budgeted vs
employees charged to Operations as of July.
-
Sent out inquiries to managers re encumbrances in
old Operations accounts to determine whether they need to be closed or
transferred to the new accounts.
SUBCONTRACTS MANAGEMENT (Petrac,
Jasnow)
From: irena@ligo.caltech.edu (Irena Petrac)
-
No report this week. Attending LSC Meeting
in Hanford.
From: Ed Jasnow <jasnow@ligo.caltech.edu>
-
The installation of the laser safety system continues
at Livingston with the cable pulling nearly complete. There are still
a number of action items remaining to be completed at Hanford before their
system can be installed.
SUPPORT (Wood)
Irene Baldon
-
Processed the paper work for nine (9) new trips (including Advance Checks
written and hotel/car rental authorizations filled out and FAXed to appropriate
vendors in various locations). I have ten (10) trips in various stages
of completion before ticketing can be done. Worked on several trips
that were changed or modified and assisted several more travelers with
questions regarding their existing or potential travel.
-
Jim Covington returned nine (9) expense reports this week and has seventeen
(17) he is working on. I worked on one (1) that had extensive problems,
one (1) relocation/visitor covering six-months of receipts and clarified
a few more that Travel Audit or the traveler were having trouble with.
I completed twenty-eight (28) reports and there are thirty (30) reports
to be done. I'm holding one (1) report that needs a check and one
(1) that needs a Transaction Report from the traveler before submitting.
-
Reconciled thirty-six (36) of a total of 128 items on my P-Card which required
telephone calls to vendors who do not enter the traveler's name on their
charges. Assisted a few travelers with their reconciling and/or data
entry.
-
Worked on the preparation and distribution of the Travel/Vacation Itinerary
for August 13, 2001. Performed normal recording and filing associated
with Travel and Reimbursement. Also performed miscellaneous duties
as requested by various members of the LIGO Project here at Caltech
as well as from members of the staffs of each of the two (2) sites.
I continue to do MIT's travel to the sites for installation activities
and also to assist them wherever possible.
Dorothy Lloyd
-
Processed the usual requisitions, invoices and receiving on-line. For more
detail, see "Cost Schedule Control Systems" report by Esther Cunningham.
-
Tracked and followed up on invoice problems.
-
Reviewed and recorded payments processed by Esther the week of August 6.
-
Continue to monitor contract and blanket order encumbrance and notify task
managers when supplements are needed.
-
Began updating PO Log books for the period June through July (115 entries).
-
Jim continues with data entry in the LIGO database and supports Irene (travel)
in the mornings and Linda and Cleveland (DCC) in the afternoons.
Rita Torres
-
Placed several Pcard orders, and reconciled several after chasing down
the invoices. By end of today, will have reconciled 25 this period.
Picked up packages for people not here this week.
-
Spent some time trying to clarify a quote discrepancy with Penguin Computing
for an LDAS order, which is now on hold. The 16-week lead time item
finally arrived, but continue to follow up on other long-lead orders.
-
Helping to assemble material for upcoming design review. Did site
trip updates.
Elizabeth K. Wood
-
Attended a training session on how to enter data for the Annual Salary
increases. It is a web-based application and much in line with how
ORACLE wants it done.
-
Had an on-going battle with the library over getting after hours access
to Millikan. Turns out, it was all a question of checking out books.
Yes, it is possible for LIGO contract employees to get into Millikan after
hours. This is quite distinct from getting into Millikan and checking
out books---after hours. If this makes no sense to you, it didn’t
to me, either.
-
Made a request for a pre-award PTA to be set up for Gary’s Management School
account. We’ll probably get it sometime next week.
Advanced LIGO (Frey)
From: Thomas Frey <tfrey@ligo.caltech.edu>
Progress Period from 08.10 to 08.16
Accomplishments:
-
Weekly Advanced LIGO Project Controls meeting not held
this week due to schedule conflicts, LSC, and vacations.
-
Advanced LIGO MRE Proposal (Highest Priority)
-
Continuing the development of the Cost Estimate.
-
Continue to pursue all other sub system schedules.
-
Updated web site with latest schedule for meetings.
-
The following is a summary of status by sub system:
-
COC - Work on action items per second review continues.
-
PSL - Work on action items per second review continues.
Next step is for Peter King to complete BOE and for management to scrub
/ determine funding sources. Next meeting date has not been scheduled.
-
AOS - Finished revisions to the schedule, cost sheets
and items. Action items for others are still outstanding. Second
review is scheduled for August 20th at 1pm at LSCR.
-
IO - Continue work on cost sheet and cost item changes.
Second Review is scheduled for Friday August 24th at 9:35am at LSCR.
-
SUS - Continuation of second review is scheduled for
Friday September 7th at 9am. Work on action items per second review
continues.
-
SEI - Efforts continue on action items. Next review
date has yet to be scheduled.
-
All other subsystems have yet to be scheduled for their
first review. These dates are pending per direction from Gary Sanders
and Dennis Coyne.
-
Continue to update the TNI Schedule and incorporate
any changes.
-
Continue to update the LASTI Schedule and incorporate
any changes.
-
Project Plan for the 40-Meter Lab Upgrade continues.
-
Continue to test the Cost Book Tool.
-
Continue to work with BK executing current action items.
-
Finished work on BOE table and Detailed Task table. Running tests
on reports using AOS data.
-
Mapping and formatting of OPS cost data for input on
hold pending additional changes to budget data per NSF re-submit.
-
Development of the Advanced LIGO Project Controls Guidebook
continues.
-
Project Web Site for posting schedule and progress related
data continues to be updated with the latest and greatest.
Schedule 08.17 to 08.23:
-
Next weekly Advanced LIGO Project Controls meeting scheduled
for Monday, August 20th at 1pm at Large SCR. Focus of the meeting
will be the AOS Second MRE Cost and Schedule Review.
-
Advanced LIGO MRE Proposal (Highest Priority Task)
-
Highest priority is the development of the Cost Estimate.
-
Will continue to pursue all other sub system schedules.
-
PSL - Continue to input data per comments from Dennis Coyne in preparation
for next meeting TBD.
-
Prepare for AOS second MRE review - cost reports and
schedules.
-
Finish input of changes to the IO cost sheets and schedule
per comments of review meeting.
-
Continue inputting changes to SUS and prepare for next
meeting scheduled for September 7th.
-
Continue inputting changes to SEI and prepare for next
meeting TBD.
-
Will follow up with Garilynn B. regarding status of COC cost and schedule.
-
Will import cost data and complete schedule integration.
-
Will Continue to update the TNI Schedule and incorporate
any changes.
-
Will update the plan with progress as of 08.17.01 and
post to site by the 21st.
-
Will Continue to update the LASTI Schedule and incorporate
any changes.
-
Will update the plan with progress as of 08.17.01 and
post to site by the 21st.
-
Will continue updating the 40 meter schedule and incorporate
any changes.
-
Will update the plan with progress as of 08.17.01 and
post to site by the 21st.
-
Cost Book Tool development continues. (Highest
Priority Task)
-
Will continue ops cost data input.
-
Will continue to work with BK importing data and executing
action items.
-
Will continue the development of the Advanced LIGO Project
Web Site.
Will continue the development of the Advanced LIGO
Project Controls Guide Book.
WBS 1.4.1.2 Project Controls (LIGO Construction)
Reports (Lindquist)
Gary and I met with the NSF on Wednesday, August
8, 2001.
-
We should proceed with a request for a no-cost extension.
One letter will be sufficient, but should identify MRE and Operating funds
separately.
-
The NSF wants a separate budget form for each of
the five years of the proposed Operations. I will need a five year
proposal from MIT to support this (at least the approved budget forms).
This proposal, to be submitted via FastLane, will have to be provided to
the NSF before they can act on our request for FY 2002 funds.
-
No formal response to the DCAA Audit Report is required.
A memo to OSR is the proposed course of action.
Change Control/Contingency (Lindquist)
The following Change Requests have
been submitted. CR-010007 is new, submitted this week by Stan Whitcomb
for reploishing and recoating the beamsplitter optic.
| CR-010006 |
WBS 1.1.4 (OPS) |
Roof Shelter for Concrete Pad Adjacent to Erosion Control Pond (Livingston) |
M. Coles |
| CR-010007 |
WBS 1.2.4 |
Core Optics Components, Repolish/Recoat Beamsplitter |
S. Whitcomb |
Press for the latest Contingency
Needs Projection.
COST SCHEDULE CONTROL SYSTEMS (Duncan,
Akutagawa)
From: Kris Duncan <kris@ligo.caltech.edu>
-
Continued working on the July 2001 monthly CSSR.
Calculating earned value for the Detector and LDAS groups.
-
Continued with construction contract/work package
close out.
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
SUBCONTRACTS MANAGEMENT (Jasnow)
From: Ed Jasnow <jasnow@ligo.caltech.edu>
-
Ed Jasnow met in Livingston with the president of Brunt Construction, Michael
Ragusa, to discuss progress on the Livingston Staging Building. The
building is approximately two months behind schedule. The contractor
indicated that he would finish by the contract completion schedule, which
is now February 14, 2002, as a result of the addition of the elevator for
the handicapped. The progress of the contractor will be checked again
in three months, which is halfway to the completion point.
-
The final draft of the Invitation for Bid for the Hanford OSB East Building
has been submitted by NTD Architects. This IFB is being reviewed
by Ed Jasnow and Otto Matherny. It is scheduled to go to print on
August 21, and be released on August 24.
Quality/Safety (Tyler)
>From: Bill Tyler <tyler@ligo.caltech.edu>
No report this week.
LIGO Hanford Observatory (LHO) Operations
(Raab)
no report
LIGO Livingston Observatory (LLO) Operations
(Coles)
The cryo pumps at the vertex were regenerated this week and the RGA's
are being prepped in anticipation of opening the gate valves down the arms
for a quick "peek" while Stan is at LLO next week.
We have gotten a price from LSU for the router for our second T1 line.
They should be out here next Tuesday to install a temporary router, which
they will loan us until ours arrives.
Most of the SURF students have completed their summer projects and gave
their final presentations to the LLO staff during the last week. Many of
the staff are away this week on vacation, at the LSC meeting, or at professional
training classes. A fuller report will be sent next week.
Detector/Technical Support (Whitcomb,
Coyne)
1.1 LHO INSTALLATION & COMMISSIONING
2km Commissioning
Matt Evans, Nergis Mavalvala, Stan Whitcomb
Modified the gains in the QPD heads for the 2 km interferometyer to
reduce the total range available, but to give more uniform coverage of
the region that we do use. Then used these new gains to set QPDY
so that it was not saturating during the largest build-ups.
The master (Matt) remeasured the gain coefficients and normalizations
for the lock acquisition code, and this seemed to give good performance:
lock acuisition in about one minute typically, lock durations of ~ one
hour, recycling build-up typically in the 15-20 range. We didn't
see any of the periods of poor locking (as observed during E5), but we
didn't have as much time trying to lock as we had during E5 either.
Matt used the full interferometer (State 4) to remeasure the gain coefficients
for the lock acquisition code; this is supposed to give the same values
as the ones measured in states 2 and 3, and amazingly enough, it did!
4km Commissioning
Luca Matone, Betsy Weaver, Corey Gray, Nergis Mavalvala, Stan Whitcomb
Presently, we have 1W of incident power going to the 4k MC, the lock
to the laser is robust and stable with a unity gain frequency of 50 kHz
at most. We want to push the MC bandwidth to higher frequencies (~100kHz),
and breathing of the error/control signals was observed around 10kHz.
The MC high frequency actuator is the VCO in the PSL system, so we began
to carefully address the PSL system since it is tied to the MC system.
A few things were noticed:
i. the PSL bandwidth was limited to ~300kHz instead of
the designed 1 MHz;
ii. the PSL error/control system was also breathing around 10kHz.
Measurements of the PSL electronics (alone) showed that the PC path
was eating phase by 40 deg at 100kHz. An improvement in bandwidth for both
PSL and MC systems could be achieved if this delay is decreased.
Furthermore, the breathing observed in the error/control signals for
both the MC and PSL systems, also showed up in the 1/(1+OL) PSL measurements.
If the 1/(1+OL) measurement is non-stationary, then the gain of the system
is non-stationary. The symptoms seem to indicate that the crossover between
the FAST and PC path changes over time, causing, at times, the system to
go instable. When the control is instable, that's when you observe the
rising broad peak in the error/control signals in the MC/PSL systems. Since
in the 1/(1+OL) measurementthe UGF never changes despite this non-stationary
behavior, then something non-stationary is happening in the FAST path of
the PSL.
Once the PSL/MC situation was assesed, we proceeded in aligning the
transmitted MC beam to the 4k PRM. At the moment, we have found the reflected
beam off of RM, the reflected beam off of ITMX and ITMY, and we began observing
Michelson fringes.
Suspension Tuning
Mark Barton
This week I was at the LSC meeting and did some training with the LHO
control room operators on doing ring-down tests of the pendulum modes.
1.2LLO INSTALLATION & COMMISSIONING
New MC Servo
Peter King, Rich Abbott, Rana Adhikari
Completed installation of the LLO modecleaner servo
PSL
Peter King
During installation of the new modecleaner servo a problem was noticed
with the XY212 module. The input resistors for the XY212 were swapped
out to allow operation with 5V inputs. As I recall, after this was
done everything seemed okay but I could be wrong. The new MEDM screens
were moved from the testing area to the release area.
2.0 OtherEngineering and Scientific Activities
2.1 Design/Analysis/Fab
Core Optics
GariLynn Billingsley
Bob Oreb of CSIRO visited Wednesday. We discussed the beamsplitter
specification for the two beamsplitters currently at CSIRO for repolish
(one for first polish.) I suggested the possibility of changing the
required sag of the parts to account for the roughly known change in sag
due to coating stress and non-uniformity. If we assume that these
two pieces will be re-coated at REO we can have them pre-shaped at CSIRO
so that they will be closer to flat once they are coated.
Optical modeling
Bill Kells
Back now at CIT, I have been working on FFT simulations of matching
under various conditions, to better understand the Arm coupling efficiency
for LIGO-II.
Suspension Design
Janeen Romie
Working on BS and test mass suspension and fixture designs for 40m
IFO
IOO PERISCOPE
Mike Smith, Ken Mailand
The prototype (1st article) periscope body has been welded and the
feet pads have been lapped to a common flat surface. The structure will
be at CIT on 8/16 for the mounting plate holes to be drilled. The mirror
mounting plate and accessory bracketry are being fabricated, and are expected
to be available for testing at CIT the week of Aug 20. A vibration analysis
will be performed with the periscope/top mirror mounted on a Newport optics
table in the OTC lab in W. Bridge.
PSL
Peter King
Another trickle of super-polished substrates from Mindrum Precision
has arrived, leaving 8 on back order. Of the 40 substrates inspected
to date, identifying the super-polished side of 13 of them is near impossible
because of the lack of distinguishing marks.
40 m PSL: The optical spectrum analyzer arrived, along with the 29 MHz
Pockels cell used for locking the modecleaner.
Lee Cardenas
-
PMC mode matching continue on.
-
New NPRO S/N 259 received from Lightwave. It will be tested
soon
-
(13) more super polished substrate received from Mindrum Precision Inc.
-
The new pump unit and the RGA unit for the baking has been brought back
from 40m. Lab.
Rick Karwoski
PSL Custom Boards: GEO and Site Spares: We are working to cover the
GEO and spares requirements for sites.
-
80 MHz VCOs -- GEO/LHO spare: tested
-
FS Servos -- GEO/LHO spare; tested
-
PMC servo (LHO Spare) recently damaged @ the 40m. being repaired
-
Frequency Reference Boards: GEO/LHO spare: in test
-
RFPDs: GEO/LHOspare being built
Additionally we are in the process of putting together a full set of spares
for Livingston/LASTI/40m
Intensity Stabilization
-
Schematics for the EPICS/Interface ISS servo are nearing completion. A
design review is scheduled for Friday.
Sander Liu
Completed checking couple of 80 MHz VCOs. Both units are for future
delivery. Finished testing couple to FSS servo boards. Both units are ready
for delivery. In the process of repairing one PMC servo board that were
damaged in the 40M by accident.
LSC
Rich Abbot, Mohana Mageswaran, Flavio Nocera
-
Helped clarify some PSL related tests in the 40 meter lab
-
Flavio continues to work on the timing system, the more he looks the more
bizarre things get.
-
Mohana has begun the fabrication of additional MC servo cards and is writing
test procedures for this servo.
CDS/DAQ/ASC/LSC/Digital Suspensions
Rolf Bork
Working on preparations for LHO visit next week. List of work
for next week and status:
1) Install/test latest digital suspension (DSC) code, which provides
support for GDS excitation/test points:
-
Code for LVEA processors is ready.
-
Completing end station software, which also requires modifications to the
ASC software. Test points are in the code; now adding excitation.
Should be ready by Friday.
-
Upgrade will require update of DAQS configuration file to include these
~340 additional excitation/test point channels.
2) Install/test 4k ASC system:
-
Parts have been shipped (though we may be short a few working pentek modules,
but we can work around this for now. Next shipment of pentek odules
is due in three weeks.)
-
Working on code additions to support DSC end station GDS (as noted above).
3) Upgrade 2k LSC processor to 1GHz pentium:
Part shipped. Will test and tune code next week.
4) Assemble the 4k suspension data collection unit.
Since a whitening board to interface between coil driver monitors and
DAQS was never specified, we would need to assemble a fair number of generic
DAQ interface modules to connect the coil signals. I have to check
on how many we have available.
5) Run mid station DAQS with GDS arbitary waveform generator code to
drive ICS115 DAC outputs:
Having some difficulties getting this to run in our test setup.
Appears though all communications to DAC are correct, but get no output
voltages. Lori will continue to work on solving the problems with
this.
40 Meter Interferometer (Weinstein)
-
PSL (Abbott R., Abbott, B., King, Ugolini, Vass):
-
While taking a transfer function measurement of the PMC servo, we discovered
that the large 62.6 kHz oscillation previously thought to be a resonance
of the mirror PZT was actually a harmonic of an enormous 31.3 kHz resonance
of unknown origin. Rich and Ben Abbott fashioned a simple notch filter
tuned to this frequency with spectacular results. We now see 80 dB of gain
at 10 Hz with a unity gain frequency of 3 kHz, and the PMC remained locked
overnight for the first time.
-
With our PMC now locking more robustly, we have measured 85% visibility
and 65% transmission in the cavity.
-
With Peter's assistance, SURF student Andrea deMichele has recalibrated
the in-loop frequency noise and found a much more reasonable result, though
we still cross above the LIGO specification at about 100 Hz.
-
After Ben added a couple of wires to the PMC servo board, we are now reading
all fast channels into our DAQ.
-
We have received our new Tropel and all of the optics necessary to test
the long-term stability and drift of the laser (QPDs, steering mirrors,
etc). Mike Smith will help us setup this experiment, and the measurement
will begin on Friday.
-
Please be advised that the 40m PSL is now *always on*. Safety glasses are
required at all times in the clean room.
-
Vacuum Envelope (Vass, Ugolini):
-
Steve has determined that our total leak plus outgassing rate is 2*10^-4
torr L/second, within a factor of two of the rate measured before the installation
of the mode cleaner envelope.
-
Steve installed a nipple for our new RGA, and has been measuring it's cleanliness
with our old RGA to see if it needs to be baked (probably not).
-
Dennis has finished the IOC chamber gate valve cabling, and is still ferreting
out a problem with the ion pump control code.
-
Optical Layout (Mike Smith): Mike has updated his main integrated facility
drawing, and is satisfied with the current position of the PSL table. He
has also moved the pickoff optical tables at the EV and SV to match the
location where they were installed last week. He is currently finalizing
drawings and parts lists for the ISC tables.
-
Suspension Controllers (Abbott B.) Ben has finished the drawings of the
two suspension controller racks sited along the east arm. Next are the
two end racks, followed by a reannotation of Jay's connection and cabling
diagrams.
-
Cabling (Larry Jones): Larry has relaxed the flexibility requirement on
our cabling, and has contacted the braiding company to assemble three twisted-pair
samples, one with the original 48-gauge wire, one with thicker wire/fewer
strands, and one with the teflon Cooner wire used in the Mark II 40m. Larry
has also finished preliminary drawings of the cable clamps and requested
a quote from Molding Solutions.
-
PEM: Now that the appropriate cables and connectors have arrived, we plan
to install our weather station and two GPS antennae on the roof on Friday.
SURF student Victor Tsai has completed the EPICS code and screens to readout
the weather information. We are still unable to communicate with STACIS
via our VME processor, and have contacted the manufacturer for assistance.
-
DAQ: Two of the disks in our 500GB RAID array have failed in the last week.
Rolf has taught us how to replace a bad disk and has ordered five more
spares. Data taking has not been interrupted.
-
SURF: Our students are finishing their papers, and arguing passionately
over the exact distance between the LIGO sites.
Thermal Noise Interferometer (Libbrecht)
This week we encountered our first setback in noise reduction. After
much
initial success reducing laser frequency noise by increasing the gain
of
the mode cleaner, we implemented additional gain boosts at low frequencies
and saw the noise increase. We are currently working on resolving
this
problem. Many thanks to Rick Karwoski and
Sander Liu at CDS for loaning us
a VCO!
LASTI (Zucker)
LASTI (Harry, Mason, Mason, MacInnis, Miller, Mittleman, Ottaway,
Rollins, Shoemaker, Zucker):
This week we concentrated on preparing for the LASTI review at the
LSC meeting. The baseline optical layout, interferometer parameter
choices and associated noise budget, PSL and
infrastructure progress, and near-term test plan options were among
the
highlighted items. Ken also showed a conceptual design for fitting
hydraulic seismic pre-isolators under the HAM13 stack. Overall
the review was very productive, and the committee provided useful guidance
through questions and comments. Presentation graphics will shortly
be available under LIGO-G010269-00; Peter Saulson, committee chair,
will
assemble and submit a formal report in a week or so.
Meanwhile in the lab Myron and Fred continued preparing lab infrastructure
and parts for cleaning, bakeout, assembly and balancing
of SOS suspensions for the short
cavity test. We've tentatively arranged a visit from Betsy Weaver in
mid-September (after her honeymoon!) to train us in the SOS preparation
and balancing process.
Data Analysis and Computing (Lazzarini)
_______________
E2E MODELLING:
_______________
Mode Mismatch
-------------
(Biplab)
(i) Checked that the effects of mode-mismatch simulated in full
LIGO model
including recycling summation cavity match
well with analytical derivation.
(ii) MIT's FFT: With help from Bill Kells sorted out several
issues about FFT runs.
Started running FFT code and comparing results
with full LIGO e2e runs.
Results of comparison at this initial stage
are encouraging but I see need
of more detailed understanding of how FFT
code runs corresponding to a
same-parameter run in e2e or vice versa in
order to sort out differences.
CVS Archive
------------
(Ed Maros) Moved the CVS archive for the e2e work onto ldas-sw.
Gave presentation on how to use the CVS archive
in its new location.
Alfi
----
(Bruce) Continuing implementation of Alfi box and primitive file parser
for Alfi5.
(Melody)
- Discussed Java coding conventions with Bruce. Currently modifying
the
existing code to comply with the conventions.
- Reorganizing the Java code packages. The code should be checked back
in by
COB Thursday.
Mechanical simulation work (from July upto last week)
-----------------------------------------------------
(Virginio) This is my report with just the main activities about the
mechanical
simulation. I apologize for including in a single weekly report
the activity
of the entire month of July (almost).
- Three-dimensional LIGO I Suspension simulation is ready to be
plugged into
e2e. The simulation includes a realistic topology of the actuators
and sensors
also. Geometrical suspension asymmetries can be easily introduced.
The cross
check with an experimental spectrum using a set of OSEMs suspension
has been
successfully done with an agreement of about 2%. To obtain a
better
characterization of the suspension local controls, a set of new
measurements
needs to be done.
- A simple way to introduce the Hytec models of the BSC stack
is under study.
At first look it seems necessary to introduce some new functionalities
to MSE
to allow the possibility to merge two separate state space representations.
- Some tests have been done to introduce the suspension violin
modes also.
Boston week: (Assembly/Installation)
Worked mainly with Calum Torrie, Norna Robertson and Rich Mittleman
to assemble
the second quadruple pendulum chain. Thanks the work I made during
the weekend
I was able to run some measurements to characterize one chain
of the suspension.
I worked essentially on the reacting chain because we didn't
have any OSEM really
aligned yet.
- Mounted three LVDTs which allowed to measure the longitudinal
transfer
functions from the "new" mass to the "upper" mass and to the
"middle" mass,
using the upper most stage as mechanical compliance. The sensor
parts were
attached to the suspension masses by using a pretty good double
sided scotch tape.
- Mounted also another coil actuator (an old and bigger OSEM)
between the two
upper masses acting against the reacting chain but I was not
able to make it
work using the control box inputs (pin out incompatibilities).
Measurements:
I took several sensors spectral densities hoping to be able to
make some
frequency mode characterization. I did not have time to do a
more accurate
system identification.
I measure the t.f. which seems to be reasonably good.
Those measurements are affected by a large cross coupling with
all the DOF
because the chain was not properly aligned yet and because of
the
orientation of the sensors and the actuators. The actuation was
done using
the control box longitudinal input.
Observations:
The LVDTs seem to work fine and particularly good for t.f. measurement
(good sensitivity and large dynamic range)
It is clear that it is not easy to measure the t.f. using the
OSEMs
because of the small dynamic range of the sensor and because
of the small
clearance between the magnets and the coils. All the coils need
to be
quite well aligned to be able to shake enough the mass. This
alignment
doesn't seem to be critical for the damping of the suspension.
I didn't have time to measure any t.f useful for the study of
the performance
of the active damping. The LVDT can probably be used to verify
the efficiency
of the damping for the lower stages.
The most important result is that the results obtained show the
possibility
to measure the transfer function of the entire chain (4 stages)
using the
LVDTs as sensors.
Last week
Worked with Giancarlo Cella to fix some library bugs. The following
ones
seem to be solved:
- The phase lag going through the mechanical resonances is now
properly
computed when a viscous damping is plugged into the simulation.
- The simulation bug on the violin modes of a wire under tension
(without
the flexural contribution) seems to be solved. The Library now
works
properly to compute the right frequency spectrum of a simple
suspension made
of a wire and a bob. This approximation works reasonably well
(applicable)
when the wire tension is high compared the flexural restoring
force.
Comparison with a real experimental data gives a good result
less than 10%
of discrepancy in the frequency spectrum. Next step which is
under progress
also is to check the violin mode simulation inside a more complex
system.
- Wrote a simple program to check the class which implements the
flat Blade
(a la Virgo) to finally have the description of all the main
internal modes
of the advance LIGO suspension.
LIGO II/Advanced R&D (Sanders)
From Mark Barton:
I also did more reverse-engineering of the Glasgow Matlab model of
the Advanced LIGO reference design
From Rich Abbott
Worked on the specifications and implementation for the next generation
capacitance position sensors with the vendor
Received the new voice coil actuators from LLO and have begun the process
of characterization in order to best design or buy a driver.
From: GariLynn Billingsley <Billingsley_G@ligo.caltech.edu>
Bob Oreb of CSIRO visited Caltech on the 15th. Bob reports that
sub Angstrom measurements of the microroughness of polished sapphire have
been obtained while experimenting with different polishing approaches.
From: HELENA ARMENDULA
Silicate bonding
Recent tests on silica/sapphire bonds show that, when
the bonded substrates are baked at 120 degrees C,
there is a considerable amount of stress on the silica
glass causing it to brake in most cases.
We investigated bonds that were baked shortly after
manufactured as well as 60 day old bonds with the same
results.
Strees is not observed on un-baked bonds.
For additional information about this report, contact sanders@ligo.caltech.edu