Weekly Report for Week Ending July 12, 2001


 Exec. Comm. Agenda
Highlights
LSC
Administration
Hanford Observatory
Livingston Observatory
MIT
Caltech
Detector
40 Meter
TNI
LASTI
Data Analysis
LIGO II/Adv. R&D
Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  July 16, 2001 will be:

 (Meeting time: 10:30 am Pacific Time)

Open meeting 10:30 - 11:30

  1. Announcements
  2. LSC Issues (Weiss)
  3. Comments on Weekly Report
  4. WBS 1 LIGO I Construction (Lindquist)
  5. WBS 2 LIGO Lab Operations
  6. WBS 3 and 4  Advanced R&D and LIGO II (Sanders)
Executive Committee only 11:30 - noon   Topics:  DISCUSSION OF E6 SCHEDULE
 

Special Items:


Special Announcements:


Weekly Report Highlights
 


LSC Issues (Weiss)


no report


LIGO I Construction/LIGO Laboratory Administration (Lindquist)



 

WBS 1.2 LIGO Operations--Administration



LIGO Weekly Site Telecon (Lindquist)

There was a teleconference on Thursday, July 12.  The following were among the items discussed:

The list of current actions revised to reflect the status of open actions assigned through July 12, 2001 may be found at ACTION LIST.

PROPERTY MANAGEMENT (Chargois)

From: Ed Chargois <chargois_e@ligo.caltech.edu>


DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner - turner@ligo.caltech.edu>

Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .

ACCOMPLISHMENTS

>From: Cleveland Mak <mak_c@ligo.caltech.edu>

ACTIVITY

Packages Faxes
In 31 37
Out 9 28

Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.


COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Akutagawa, Kaufman)

From: Esther Cunningham <esther@ligo.caltech.edu>

Press here for ACCOUNTS PAYABLE HISTORY DATA.

From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

From: Florence Kaufman <fkaufman@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: irena@ligo.caltech.edu (Irena Petrac)

From: Ed Jasnow <jasnow@ligo.caltech.edu>

SUPPORT (Wood)

 
Irene Baldon
  • Due to vacation and a day of sick leave, I have no report at this time.
Dorothy Lloyd
  • Processed the usual requisitions, invoices and receiving on-line. For more detail, see "Cost Schedule Control Systems" report by Esther Cunningham.
  • Tracked and followed up on invoice problems.
  • Reviewed and recorded payments processed by Esther the weeks of June 25 and July 2.
  • Continue to monitor contract and blanket order encumbrance and notify task managers when supplements are needed.
  • Jim continues with data entry in the LIGO database and supports Irene (travel) in the mornings and Linda and Cleveland (DCC) in the afternoons.
Rita Torres
  • Formatted a report from GEO, it's now in review.  Worked on a web page (with Barbara's help) to post for advance review some documents describing the work planned by a few universities.  Posting is almost complete.
  • Edits to Draft 2 of the Vehicle Usage Policy, distributed for further review.  Final edits to LLO Safety Audit Report, did distribution.  Helped to match name and number information related to voice mail accounts.
  • Clarified for Lase-R Shield (our prescription eye wear vendor) that, in most cases, glasses must be delivered to Pasadena Eye Medical Group so that these can be properly fitted on the wearer.  Recently someone requested that the glasses be sent directly to LIGO.
  • Arranged a few Pcard purchases, reconciled a few after chasing down invoices.  Coordinated with E. Chargois for the return of a couple of items.
  • My move from 357WB to 251WB is now complete.  Many thanks to the General Computing Group, especially Mike Pedraza, for getting my tools back on-line.  For a few days I did not have access to the conference room calendars, my many mailboxes, or the Pcard tool.  Everything is working nicely now.  Thank you: Mike, Larry, Lisa, Wendy, Mick
Elizabeth K. Wood
  • Spent some time tracking down where some phones and phone lines are located that LIGO has been blissfully paying for.  It turns out we’ve been paying for one line that isn’t even attached to a phone/fax/modem.  I have made a list of as many lines as I have discovered (fax lines, modem lines, ISDN lines, extra phone lines) which should help us when it comes time to change account numbers again.
  • I have been helping Criselda, the pcard guru, in gathering information for the forthcoming travel instruction book.
  • ATTENTION Pcard users:  Effective immediately, for all single purchases over $5,000, you are required to fill out a justification in the “Comments” field of the purchasing log.  This justification should include the need for the item being purchased, and if it’s noncompetitive, why.

Advanced LIGO (Frey)

From: Thomas Frey <tfrey@ligo.caltech.edu>

Progress Period from 07.06 to 07.12

Accomplishments:

Schedule 07.13 to 07.19:

WBS 1.4.1.2   Project Controls (LIGO Construction)



Reports (Lindquist)

The end-of-May Quarterly Progress Report is due.  I am currently assembling and editing material submitted.



Change Control/Contingency (Lindquist)

The following Change Request has been submitted:
 

CR-010006 WBS 1.1.4 (OPS) Roof Shelter for Concrete Pad Adjacent to Erosion Control Pond (Livingston) M. Coles

Press for the latest Contingency Needs Projection.


COST SCHEDULE CONTROL SYSTEMS (Duncan, Akutagawa)

From: Kris Duncan <kris@ligo.caltech.edu>

From: Cindy Akutagawa <cindy@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Jasnow)

From: Ed Jasnow <jasnow@ligo.caltech.edu>


Quality/Safety (Tyler)

>From: Bill Tyler <tyler@ligo.caltech.edu>

The Livingston Safety Audit report has now been released and distributed to the participants.

The second draft of the LIGO Vehicle Usage Policy has been distributed for review.

Caltech and LIGO Safety and QA (Scislowicz, Zydowicz and Tyler) met to consider revisions of the LIGO laser safety eye examination requirements for LIGO personnel, students and visitors. Tyler will prepare a "draft" of the new requirements/policy for LIGO eye examinations.

The conference room projector installation work is expected to be completed in the next few weeks. The order for the remote cabling, preamps and wireless mouse hardware was placed. The vendor indicated that all of this material had been shipped to Caltech on the 11th of July.
A Service Request for Caltech electrician support will be initiated after all the material is received. The conference rooms will be scheduled for "down time" to complete the projector installations.
 


LIGO Hanford Observatory (LHO) Operations (Raab)


General Items:
--------------
(F. Raab)

We are preparing to vent the 4K to repair input optics misalignments (see below)
and 2K commissioning proceeds. Lightwave is working on servicing the 4K PSL.
Hugh Radkins is anayzing earth tides in Livingston. Our teacher interns are busy
developing LIGO outreach materials. Paul Schwinberg, formerly at U of
Washington, will join the LHO staff on 7/16.

Controls:
---------
D. Barker

Investigating 4k LVEA Digital Suspension activities during the period Thursday
and Friday June 28th - 29th. System apparently shook all 4k LVEA optics for some
time during this time period. Reviewing code and trend data to try to
reconstruct events.

Completed reflective memory network installation for 4k Data Acquisition system.

Investigating 2k LVEA ADCU problems in both suspensions and PEM systems.

Software and disk installations on the new hanford1 continues. Installation of
improved security on all CDS gateway machines continues.


LIGO Livingston Observatory (LLO) Operations (Coles)


Detector: Optics and Installation:  Mike Smith assisted by LLO staff has completed the alignment of the Core Optic Components in the vertex, and is working with Rana and Sany to align the Mode Matching Telescope.  We just opened the West end (ETM-x) for inspection, OSEM replacement and realignment. Expectation is that we will complete the in-chamber work by week's end, and will be able to initiate closeout procedures early next week. (Jonathan Kern)
 
Electronics:  3 small optic controllers in the vertex and that at ETM-y were removed, had test points repaired and have been checked out and replaced.  RF survey of the LVEA ongoing. (Rus Wooley)
 
Computing:  Bell South has repaired our T1 line, and we are now back online. There was a lightning storm here last Friday, and a strike nearby caused damage to both the copper lines and the electronics connected to them, so several things had to be repaired or replaced. A network switch was also damage and has been identified and replaced. (Shannon Roddy, Tom Evans)
 
Operations:  Completed the particle shedding test on all the different type clean room garments we use. See the report T010079-00-D.pdf, "Comparisons of Particulate Matter Falling from Cleanroom Garb" filed in the DCC (Rich Riesen)
 
Outreach:  Steve McGuire led a tour of CAMD (a synchrotron research center near the the LSU campus) for our SURF students and interested staff Tuesday afternoon.  Today, Joe Kovalik is hosting a visit by CAMD staff at LLO.


Detector/Technical Support (Whitcomb, Coyne)


 
Installation& Commissioning:
Hanford
Livingston
Other Science/EngineeringActivities:
Design/Analysis/Fab
Issues/Concerns
See also the Installation web page

1.1 LHO INSTALLATION & COMMISSIONING

2km Commissioning

Nergis Mavalvala, Bill Butler, Luca Matone, Stan Whitcomb, ....
Bill Butler has begun work on leveling the 2k mode cleaner. To this end, he has a shaker set up under either HAM7 or HAM8. he drives the HAM stack at the 16.25 Hz vertical resonances of the mode cleaner optics and minimizes the transfer coefficient of this drive to the mode cleaner length control signal (MC_L).

Some bugs in the LSC electronics were found en route locking the power recycled Michelson. We were, however, unable to lock the PRM, some offsets in the error signals still need to be understood. We did notice that the resonant spot in the PRM was decentered by about 5 cm in the horizontal direction on the beamsplitter. We have corrected the alignment of the input beam and further work on locking continues.

Luca Matone
On the 2k, we diagonalized the Core optics in the LVEA and set up the PRM.

Data for the 2k electronic characterization was taken. In particular, the whiteneing filter tf was measured and its noise floor. Also, the electronic tf including the AA, pentek and AI was measured, together with the time delay. Each digital filter was also measured.

4km Commissioning

Luca Matone, Mark Barton, Dave Barker, Richard McCarthy, Rick Savage, Nergis Mavalvala, Stan Whitcomb
In the process of realigning the mode cleaner, Luca noticed that he was unable to move the MC2 and MC3 mirrors in pitch and that they barely moved in yaw. We confirmed that the (analog) drive signals to the coils were being applied, but we could see little response on either the osem sensors or an external optical lever beam. Detailed studies of the "pendulum" modes of the optics by Mark Barton showed that the optics were indeed not freely hanging. This was found to be that case, to a greater or lesser extent, on all small optics controlled by the digital suspensions. Dave Barker then studied the history of the DSC signals in the DAQ and found that fast data from the DSCs were lost on June 28. Trend data from the epics channels for osem sensors and coil drivers showed that the optics were driven to the rails for the next 11 or hours, until the problem was discovered the following morning and the DSCs were rebooted. A reflective memory card had to be replaced. We noticed that as the optics were driven rail-to-rail, the mean position of the optics (as seen on the osem sensors) shifted. Presumably, they were hitting the stops and their equilibrium resting point was being displaced. The sad outcome of this is that a vent is being planned for middle of next week to go in repair most of the 4k small optics.

The 4k large optics were also driven by the crazed DSC, but seem to be okay.

The 4 km 10 W laser is getting a tune-up from Lightwave.

Suspension tuning

Mark Barton
I did a lot of investigation to determine the scope of a problem with the 4k small optics (see log entries for 7/9 and 7/10). It turns out that MMT1, MMT2, MC2 and MC3 are misaligned in pitch to the point of resting on their stops. This is apparently due to damage they sustained in an incident last Thursday/Friday, when the digital suspension controller went berserk and bashed them against their stops for 11 hours. MC1 and SM1 were also knocked around but seem to be entirely healthy. Fortunately for me, MC1 is suitable for my suspension controller diagonalization work and I have it all to myself, so (with lots of help from Rick Savage and Richard McCarthy) I made a setup using the WFS1 photo diode as an optical lever and continued trying to validate the sensor version of the output matrix tuning procedure against the optical lever version.

1.2LLO INSTALLATION & COMMISSIONING

LLO VERTEX ALIGNMENT

Mike Smith, Gary, Harry & Joe

ALIGNMENT OF BS, APS beam
A 500mw COS autocollimator (AC) was projected along the y-arm direction through the APS output port, and the HAM4 table was tilted in pitch and yaw by shifting weights on the table (7/6/01) in order to center the projected reticle pattern within the FOV of the APS port. Similarly, a 4W COS AC was projected along the x-arm direction, reflected from the BS mirror, through the APS output port, and the BS was aligned so that the x-arm AC reticle pattern was superimposed with the y-arm AC reticle pattern. A second (weaker ) reticle pattern  was observed adjacent to the bright reticle pattern in the FOV  at the APS port when the BS was aligned. In an attempt to eliminate the double image of the reticle pattern, HAM5 door was pulled for access to the Faraday isolator on HAM4 and the Faraday isolator was translated a small amount normal to the incident beam until the largest circular FOV was obtained (this represented the best alignment of the Faraday isolator). The double image did not disappear, and remained in the same relation to the primary image during the tilting and translation of the Faraday isolator. This indicated that the second image was not caused by internal reflections in the Faraday isolator. We verified that the reticle pattern traversed unimpeded through most of the APS optical train by viewing the pattern with a video camera by looking toward the projector placed sequentially after each optical element in the train up to the final steering mirror; we couldn't access the path after the final steering mirror. The second image appears to be due to reflections from the AR side of the steering mirrors on the HAM4 table.

The BS position on the BSC2 table was checked by sighting a 1mm dia vertical rod placed on the BS LOS structure at the beam centerline position with the y-arm theodolite; the BS LOS is positioned within 1.5 mm of the desired centerline position.

ITMX PO BEAM:
The ITMX PO beam reticle pattern was centered in the FOV of the output port by adjusting the ITMx POmirror. During this procedure, a second dimmer image was observed to the left of the bright reticle pattern. It was apparent that the second, dimmer reticle pattern was a reflection from the back surface of the steering mirror.

BS PO BEAM:
The BS PO beam reticle pattern was already centered in the FOV of the output port, and  the BS POmirror did not need adjustment.

ITMY PO BEAM:
The ITMyPO beam reticle pattern was centered in the FOV of the output port by adjusting the ITMy POmirror.

MMT3
The 4W COS AC in the y-arm was projected onto a target at the center of the MMT3 mirror and the center of the reticle pattern was approx. 5mm to the right and 5mm above the center of the MMT3.

MMT3 was aligned to project the reticle pattern onto the center of a target placed at the center of MMT2 within <0.5 mm.

2.0 OtherEngineering and Scientific Activities

2.1 Design/Analysis/Fab

Core Optics

Helena Armandula
SPETM04 and 08 have their Side 1 coated (HR). SPETM01 and 02 are getting their Side 1 (HR) coated at this time.

REO has a new cleaning procedure and an improved clean room, free of dust. All cleaning is done under a class 100 flow bench that has an ionizing bar to take care of electrostatic charge during the cleaning. Dust has been completely eliminated which is great. The optics get soaked in hot Alconox and scrubbed while hot until the water sheets off the surface. They get rinsed very well and they allow the water to dry by itself. The fringes can bee seen while the water dries.  The DI water system is like ours and has a .2 micron filter; the water should be particle free. Because they do not have a dark field microscope I was not able to see that there are not microscopic particles. The substrates looked really clean and free of smears when inspected in a dark room under a high intensity lamp.

One problem that we encountered after the first pair of mirrors came out, was some coating flaking from the bevel of the optic. When the mirrors were re-polished, the bevels were not. When new coating got sprayed on the bevels some of it flaked. I thought that something like that may happen, however, when I mentioned to Dale, he did not share my concerns and was confident that the coating was going to adhere to the bevel without problems. Also, the parts fit on the coating fixtures a bit different because after the new polishing the bevels are smaller. It does not seem to have affected the actual mirror coating. The problem is confined to the bevel.

Tomorrow I will be meeting with the consultant that designed the new cleaning system for REO (the one used for the telecom parts and now idle) . He may have some suggestions on how to approach the cleaning for LIGO II parts.

Friday, the coating chamber will get calibrated for the AR coating.

Optical modeling

Erika D'Ambrosio
I am studying the flat top beam problem with every tool I can think of. When the mirrors are aligned I compared the diffraction losses obtained by analysing the results from the FFT-code, with the results of another method that looks for the eigenvalues of the kernel for the propagation inside that cavity. They agree and are slightly different from the clip approximation:
        FFT-code Simulation     Eigenvalue Problem      Clip Approximation
Diffr.
Losses          18ppm           18.5ppm                 21ppm

This is not unexpected, because I went through the notes by Robert Spero who had done similar calculations for Ligo using spherical mirrors. I used his curves to test my procedures in the case of a Gaussian beam, so I made some runs just with a view to a comparison with results obtained by a different method and shown in his ligo technical note.

I know how to disentangle the problem of diffraction losses and mismatch at the internal mirror when one mirror is titled; still I need to discuss this with Kip because my analytical calculations using perturbation theory techniques give an important factor 1/(4 sin^2(theta_guoy/2)) in front of the expression he got. It seems reasonable to me since for degenerate cavities (that is small shift phases between different modes) tilt has a more important impact than in non-degenerate cavities. This kind of problem doesn't emerge when geometrical optics approaches are used and this may explain the discrepancy between the FFT-code data and the predictions by Prof. Vyatchanin and Strigin regarding the losses caused by tilt.

LHO INTEGRATED LAYOUT DRAWINGS

Mike Smith, Ken Mailand
The D970308 integrated layout drawings (six sheets) for the LHO interferometer are being revised to reflect the current as-built design configuration.

PSL

Peter King
A partial shipment of the super-polished fused silica substrates from Mindrum Precision has arrived.  Only 33 out 100 substrates were shipped. No delivery date was given for the remainder.

REO have commenced coating of the curved mirror used in the pre-modecleaner (PMC).  These should be finished by week's end.

I have been trying to clean a set of old PMC mirrors.  After soaking in a hot Liquinox solution for the better part of 3 days, water still does not glide off the surface of the optic.

40m Lab & LASTI : I checked out a few problems related to the PMC and its alignment. Firstly the polarizer in the main beam was not properly aligned, resulting in the beam being distorted - the beam looked almost like two spots.  In addition it appeared that a quarter-waveplate was installed in front of the PMC RF photodetector thus not allowing the light level to be reduced.  As a result the photodetector output was heavily saturated.

A problem was noticed with the NPRO oscillator going into standby after operating for a period of approximately 30 minutes.  Suspecting that the NPRO went into a thermal shutdown, the valve controlling the cooling water to the master oscillator was opened up.  I have not heard of a recurrence of the problem since.  It is likely that the needle valve was gummed up with something from the water cooling hoses.

Rick Karwoski
LASTI Efforts: Slight postponement of PSL installation.  Our plans are now to visit MIT the week of July 29.

40m.: Efforts underway to improve robustness and extend bandwidth of the PMC servo.

ISS: Continuation of Circuit refinements.  We will be building a second set of electronics for the 4K @ LHO

Sander Liu
In the process of getting quote for a 19 inch half rack for building a VMEbus test set.

ISC

Mike Zucker
Repairing/retuning RF photodiodes #21 (will go to 2k MC refl) and #27 (was 2k REFL, developed logic fault).

LSC

Rich Abbott, Mohana Megeswaran, Flavio Nocera

Data Acquisition

Sander Liu
Antialiasing filters - received 240 filter modules from Frequency Devices. Will ship 50 units to LASTI and 24 unites to 40M.
 


40 Meter Interferometer (Weinstein)



Thermal Noise Interferometer (Libbrecht)


This week we vented and opened our vacuum chamber and realigned both arm
cavities. Last week we were able to lock all three cavities (the mode
cleaner, the north arm, and the south arm) simultaneously, but the arm
cavities would only lock to high-order modes. On Monday we opened the
chamber, realigned the cavities, closed up, and began pumping back out. By
Tuesday afternoon the chamber was down to the 10^-5 torr regime, and we were
able to lock all three cavities in their respective TEM00 modes. Both
acquisition frequency and hold times are greatly improved over last week's
results, with all three cavities routinely staying locked for 5 minutes or
more. One remaining problem is that the locks tend to oscillate around 800Hz
to 1kHz, making noise floor measurements problematic.
 

Nevertheless, on Tuesday night we were able to get a "one-armed" sensitivity
curve. Sometimes the arm cavities will lock without exhibiting these ~1kHz
resonances, and on one of these occasions we took a spectrum of the North
cavity's error signal. (The South cavity was not locked.) During this lock
we sent a calibration signal into the broadband Pockels cell after the mode
cleaner, and from the resulting peak in our error signal we are able to do a
preliminary calibration of the instrument. We observed a flat noise floor
from about 5kHz to 15kHz that corresponds to a displacement sensitivity of
2.1x10^-17m/rHz, and we observed a series of peaks from 15kHz up to 100kHz
(or highest measurement frequency) that appear to correspond to mechanical
resonances. We also measured the open-loop transfer function of the
arm-cavity servo, near the unity-gain frequency, and were able to do an
alternate calibration by fitting our expected transfer function to this
curve. This second, and presumably independent, calibration yielded a noise
floor consistent with the first estimate.
 

Next we hope to stabilize the lock, by eliminating the ~1kHz resonances, and
to begin reducing our noise floor and increasing its bandwidth.


LASTI (Zucker)


LASTI (Harry, Mason, Mason, MacInnis, Miller, Mittleman,
Ottaway, Robertson, Rollins, Romie, Shoemaker, Torrie, Zucker):
 

Quad pendulum prototype: Some minor interference and tolerance issues
have required a fair bit of rework in the shop, but the end is in
sight.  Blade springs have been preloaded and the aluminum dummy masses
were temporarily suspended, with no serious surprises.
 

PSL: Optical table assembly is proceeding rapidly and we will begin
laser operations this week using an NPRO to stand in for the 10W MOPA
(still in repair queue at Lightwave).
 

SOS for test cavity: Continuing vacuum prep of test cavity
suspension parts.
 

Controls: Rick Karwoski and Peter King have made tentative plans
to come out from Caltech and complete the PSL controls installation
week after next. Still waiting on in-vacuum wiring harnesses
and satellite boxes.
 
 


Data Analysis and Computing (Lazzarini)


End to End simulation ( B. Bhawal )
=====================
 

Mode Mismatch
-------------
(Biplab & Hiro) An exact equation for the elements of the amplitude
 transformation matrix due to change in basis (waist-size and/or distance
 to waist) of the Gaussian beam is derived.
 

Signal Generation
-----------------
(Kathy) Kathy has done most of the coding and suplementary caclulation for
the JAVA program to generate the signal coming compact binary sources. She
continues to implement the Supernovae signal. The output of this program
will be fed into e2e.
 

Simulation engine
-----------------
Hiro is imporving the code which will be released together with the
updated Han2k. Another care taken is that the code is modified to
make it compilable CACR machine.
 

Alfi
----
Discussions are going on for the design of the architecture and the
clarifying the scope of the new alfi. The alfi requirement and
implementation document will include these, as well the grammer of the
description of the simulation setup passed between alfi and the simulation
program. Meeting participants are Bruce, Ed, Hiro and Melody.
 

(Bruce) Completing initial design for the new version of Alfi and writing
 associated documents.
 

(Ed Maros)
 Continuing work on making alfi4 work smoother.
 

(Melody)
- Continuing on developing base classes which are known to be necessary
  for the new alfi.
 

(Hiro)
- Writing "alfi requirements and implementation document"
 
 

LDAS Software (K.Blackburn)
=============
 

The dataPipeline command has been extended to support retrieval of
spectra data from the database API for the data conditioning API.
Changes were made to the database API to support the retrieval process.
With the Internal Light Weight Data format finalized for the data being
transferred from the data base API to the data conditioning API, the
data conditioning API is being modified to read this data and convert it
into UDT types to be used within the data conditioning API.
 

Much effort has been put forth in understanding why the data
conditioning API crashes under Linux Redhat 7.1. After several more
fixes to the code which allowed for the running of the data
conditioning under Redhat 7.1 for brief periods of time, efforts shifted
to running the data conditioning API under Solaris because of its better
support for debugging threads. Running a static set of jobs continuously
under Solaris periodically caused the segmentation violation. Looking at
the core file gave insight to possible data corruption in multi-threaded
environment. Running the same test under Redhat 7.1 with just a single
thread never caused the segmentation violation.
 

Other APIs continue to be modified. The event and monitoring API has
been extended o support conversion of multiDimData to the frame AdcData.
The wrapper API is being enhanced to not terminate unexpectedly when
memory has been exhausted.
 

Testing this week focused mostly on MDC and dataPipeline tests at LHO.
By Wednesday night, all the MDC tests and several dataPipeline commands
ran. The dataPipeline commands were run prior to installing the
enhancements for retrieving the spectra from the database. New tests
will be done once the spectra functionality is verified to be working.
 
 

LDAS sys-admin weekly (S. Anderson)
=====================
 

MIT
---     Scheduled major LDAS installation work for July 18-20.
        Started base operating system installation on some of the LDAS
        machines.
 

LLO
---     Further investigation of BigBrother as a sys-admin monitoring and
        notification package.
 

LHO
---     Upgraded software to temporarily run LDAS at LHO as a development
        system to evaluate the suitability of upgrading the LDAS reference
        platform from RedHat6.2 to RedHat7.1 in conjunction with a change
        in the reference compiler from gcc-2.95.2 to gcc-2.95.3.
 

CIT
---     Continued evaluation of QFS filesystem.
        Operating system upgrades and tuning to help debug datacondAPI.
 
 

General Computing (L.Wallace)
=================
 

MIT:
-Some research on wireless setup for MIT (not done yet)
Ldas installation work
-Ordered Y cables to connect Intel machines to switch
-Ordered power strips for cluster
-Ordered 3 Intel machines for GC
 
 

Livingston:
(Shannon and Tom)
-Worked a number of problems because of the network outage caused by local
thunderstorms.
-Working on the installation of the second T1 line.
-Installing and upgrading software.
-Building a new data storage unit from scratch.
 

Hanford:
(Christine)
-Working on logistics to support the LSC meeting.
-Working a number of issues concerning the additional bandwidth needed
at Hanford. Working with Richard M. and Larry W.
 
 

CIT:
(Wendy)
- Finished inventorying computers in Bridge and Millikan with Mick
- Composed database of inventoried computers in Bridge and Millikan
- Booted up computers with Lisa and Mick after power outage
- Installed Printer Driver on computer
- Learned to and installed P-card software
- Copied installation CDs (SSH, utilities)
- Got Mathematica from ITS lab, installed in West Bridge subbasement
lab and on a computer in Lauritsen
- Inventoried subbasement of West Bridge
- Tested performance of various access points in Bridge and Millikan on
wireless cards
- Learned to configure access points
 

(Mike)
-Reloaded four PCs, this included hardware upgrade and full software
install.
-Laptop added additional hardware and software.
-Work on a PC with a hardware problem floppy drive was out.
-Worked on documentation for Inventory.
-Trouble shooting on web server corrupted OS. Multiple errors and could
not access admintools or windows explorer.
This looked like this server had to be reloaded but after a complete
two-hour shutdown enforced by school officials the server came up fine
^A'yes'.
We are planning a regular schedule to start rebooting our NTSRV's, just to
be safe to prevent this from happening again. Our uptime on this was about
six-months.
-Loaded Nt Server 4.0 as a stand alone for a backup server. Working on
setting this up to enable network client installs loading ghost images to
and from server.
-Had a problem with AutoCAD converting .DWG drawing to a .PDF after
discussing this with Larry he mentioned that we had to print to a file
using a postscript print driver, then convert to a .PDF document. This
seems to work just fine.
 

(Lisa)
- Have gotten Solstice Backup successfully autoloading and dumping
daily/weekly dumps.  This requires my old ufsdump scripts to be
completely disabled. If you use ufsdump with the cybernetics, you have to
power cycle the robot and reboot the server in order for Solstice Backup
to be able to control the scsi device without throwing up I/O errors.  Now
I need to test the restore.
- Ran ghost on Win2k laptop.  The ghost boot floppies don't seem to work
with win2k, but if you use a win98 boot floppy then load a ghost floppy it
works fine.
- Helped Wendy install Mathematica and Matlab on a couple of PCs
- Showed Mick, Wendy and Mike how to setup an orinoco access point.
- Replaced algol (ultra1 with ext. drive) with a blade 100.
- Did some benchmarks on our various wireless AP with Wendy.
- Began loading the new version of Cadence.
- Got in at 4am on Tuesday to shut the servers down for the building power
outage. There is just nowhere in Pasadena to get breakfast at 5am.  What's
up with that?
 

(Barbara)
- Completed and installed changes to Costbook Detail report printed
version.   Posted new versions on web page.  Started adding comments field
to web forms.
- Completed and installed changes to Publications web pages.  Now all are
generated dynamically from Pubs database.
- Completed and installed changes to LDAS Equipment web forms requested by
Ed Chargois.
- Developed and installed form for LSC meeting registration
- Posted transparencies from PAC meeting
- Made web site changes for LSC working groups, research bulletin boards
- Recovered from pc problems by restoring missing .dll file, prepared to
rebuild pherkab in case it didn't start up on Tuesday morning after the
power outage
- Helped restart servers after power outage and did some housekeeping with
accounts, files, passwords, etc.
- Helped Rita with web page and mapping to roster and LSC databases
- Fixed a bug Janeen found in the costbook web forms
 

(Mik)
-With Wendy, completed inventory Bridge basement, 2nd and 3rd floors, and
most of Millikan 6th floor
-With Lisa, learned to set up a modem pool account
-With Mike, diagnosed user problem with floppy drive, determining it is
most likely an error in the controller card
-With Lisa, removed one SPARC station(algol) from service, giving its IP
and host identity to another
-Assisted in bringing network back up after power-out: turned on hubs,
printers, etc.
-Loaded one PC, and ghosted an image onto USB portable hard
drive; currently attempting to fix a shutdown problem
-Assembled a computer cart
-With Wendy, inventoried computers in Bridge Optics Lab (058), and
installed Mathematica on two there
-Learned to configure ORiNOCO 1000 Wireless AP
 

(Bruce Sears)
- General maintenance on Ilog.
 

(Larry)
-Ordered memory upgrades for most of the computer systems on the 6th Floor
of Millikan. The memory has arrived. Mike and crew will start installing
them this week.
-Ordered a couple more PC's. These are upgrades for existing units. The NT
server units will also be getting upgraded in the next month or so.
-Spent a great deal of time dealing with the power take down to the
building.
There were a few minor glitches. The edge switches in Millikan needed to
be reset. The air-conditioning in the basement went out and it took most
of the day to get it back on-line. Fortunately, the existing unit in the
computer room was not affected and was able to handle the load.
The group as a whole spent time making sure equipment was shutoff before
the power outage and that things were brought backup after the power was
restored to the building.
-Went over the Orinoco setup along with everyone else. Ran into the same
problem with wireless setup as we did on setting up the unit with it being
hardwired.
The PC programming the Orinoco needs to be on the same sub-net as the
Orinoco unit.
-Spent time trying to find a vendor that still sales an outdated disk
drive. We need the unit for data recovery from a crashed PC but so far no
luck.
-Worked a couple security issues with Shannon.
-Worked a couple more LSC mtg. issues.
-Went over a number of procurement issues with Gina.
-Spent time with Liz trying to help her get a number of phone line issues
cleared up.
-Investigating a couple of e-mail issues.
-Finally, getting some responses from vendors to get a GIGE switch
installed.
-We had a number of people that received e-mail with viruses attached but
once again the virus-scan s/w had kept them out of trouble.
-The usual of setting up accounts and changing e-mail aliases.


LIGO II/Advanced R&D (Sanders)


no report


For additional information about this report, contact sanders@ligo.caltech.edu