|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The LIGO Executive Committee Agenda for Monday July 16, 2001 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
Special Items:
no report
WBS 1.2 LIGO Operations--Administration
There was a teleconference on Thursday, July 12. The following were among the items discussed:
From: Ed Chargois <chargois_e@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .
ACCOMPLISHMENTS
ACTIVITY
| Packages | Faxes | |
| In | 31 | 37 |
| Out | 9 | 28 |
Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS PAYABLE HISTORY DATA.
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
From: irena@ligo.caltech.edu (Irena Petrac)
SUPPORT (Wood)
Progress Period from 07.06 to 07.12
Accomplishments:
WBS 1.4.1.2 Project Controls (LIGO Construction)
The end-of-May Quarterly Progress Report is due. I am currently assembling and editing material submitted.
The following Change Request has
been submitted:
| CR-010006 | WBS 1.1.4 (OPS) | Roof Shelter for Concrete Pad Adjacent to Erosion Control Pond (Livingston) | M. Coles |
Press for the latest Contingency Needs Projection.
From: Kris Duncan <kris@ligo.caltech.edu>
From: Ed Jasnow <jasnow@ligo.caltech.edu>
The Livingston Safety Audit report has now been released and distributed to the participants.
The second draft of the LIGO Vehicle Usage Policy has been distributed for review.
Caltech and LIGO Safety and QA (Scislowicz, Zydowicz and Tyler) met to consider revisions of the LIGO laser safety eye examination requirements for LIGO personnel, students and visitors. Tyler will prepare a "draft" of the new requirements/policy for LIGO eye examinations.
The conference room projector installation work is expected to be completed
in the next few weeks. The order for the remote cabling, preamps and wireless
mouse hardware was placed. The vendor indicated that all of this material
had been shipped to Caltech on the 11th of July.
A Service Request for Caltech electrician support will be initiated
after all the material is received. The conference rooms will be scheduled
for "down time" to complete the projector installations.
General Items:
--------------
(F. Raab)
We are preparing to vent the 4K to repair input optics misalignments
(see below)
and 2K commissioning proceeds. Lightwave is working on servicing the
4K PSL.
Hugh Radkins is anayzing earth tides in Livingston. Our teacher interns
are busy
developing LIGO outreach materials. Paul Schwinberg, formerly at U
of
Washington, will join the LHO staff on 7/16.
Controls:
---------
D. Barker
Investigating 4k LVEA Digital Suspension activities during the period
Thursday
and Friday June 28th - 29th. System apparently
shook all 4k LVEA optics for some
time during this time period. Reviewing code
and trend data to try to
reconstruct events.
Completed reflective memory network installation for 4k Data Acquisition system.
Investigating 2k LVEA ADCU problems in both suspensions and PEM systems.
Software and disk installations on the new hanford1 continues. Installation
of
improved security on all CDS gateway machines continues.
Detector: Optics and Installation: Mike Smith assisted
by LLO staff has completed the alignment of the Core Optic Components in
the vertex, and is working with Rana and Sany to align the Mode Matching
Telescope. We just opened the West end (ETM-x) for inspection, OSEM
replacement and realignment. Expectation is that we will complete the in-chamber
work by week's end, and will be able to initiate closeout procedures early
next week. (Jonathan Kern)
Electronics: 3 small optic controllers in the vertex and
that at ETM-y were removed, had test points repaired and have been checked
out and replaced. RF survey of the LVEA ongoing. (Rus Wooley)
Computing: Bell South has repaired our T1 line, and we
are now back online. There was a lightning storm here last Friday, and
a strike nearby caused damage to both the copper lines and the electronics
connected to them, so several things had to be repaired or replaced. A
network switch was also damage and has been identified and replaced. (Shannon
Roddy, Tom Evans)
Operations: Completed the particle shedding test on all
the different type clean room garments we use. See the report T010079-00-D.pdf,
"Comparisons of Particulate Matter Falling from Cleanroom Garb" filed in
the DCC (Rich Riesen)
Outreach: Steve McGuire led a tour of CAMD (a synchrotron
research center near the the LSU campus) for our SURF students and interested
staff Tuesday afternoon. Today, Joe Kovalik is hosting a visit by
CAMD staff at LLO.
| Installation&
Commissioning:
Livingston |
Other Science/EngineeringActivities:
Issues/Concerns |
See also the Installation web page
Some bugs in the LSC electronics were found en route locking the power recycled Michelson. We were, however, unable to lock the PRM, some offsets in the error signals still need to be understood. We did notice that the resonant spot in the PRM was decentered by about 5 cm in the horizontal direction on the beamsplitter. We have corrected the alignment of the input beam and further work on locking continues.
Luca Matone
On the 2k, we diagonalized the Core optics in the LVEA and set up the
PRM.
Data for the 2k electronic characterization was taken. In particular, the whiteneing filter tf was measured and its noise floor. Also, the electronic tf including the AA, pentek and AI was measured, together with the time delay. Each digital filter was also measured.
The 4k large optics were also driven by the crazed DSC, but seem to be okay.
The 4 km 10 W laser is getting a tune-up from Lightwave.
ALIGNMENT OF BS, APS beam
A 500mw COS autocollimator (AC) was projected along the y-arm direction
through the APS output port, and the HAM4 table was tilted in pitch and
yaw by shifting weights on the table (7/6/01) in order to center the projected
reticle pattern within the FOV of the APS port. Similarly, a 4W COS AC
was projected along the x-arm direction, reflected from the BS mirror,
through the APS output port, and the BS was aligned so that the x-arm AC
reticle pattern was superimposed with the y-arm AC reticle pattern. A second
(weaker ) reticle pattern was observed adjacent to the bright reticle
pattern in the FOV at the APS port when the BS was aligned. In an
attempt to eliminate the double image of the reticle pattern, HAM5 door
was pulled for access to the Faraday isolator on HAM4 and the Faraday isolator
was translated a small amount normal to the incident beam until the largest
circular FOV was obtained (this represented the best alignment of the Faraday
isolator). The double image did not disappear, and remained in the same
relation to the primary image during the tilting and translation of the
Faraday isolator. This indicated that the second image was not caused by
internal reflections in the Faraday isolator. We verified that the reticle
pattern traversed unimpeded through most of the APS optical train by viewing
the pattern with a video camera by looking toward the projector placed
sequentially after each optical element in the train up to the final steering
mirror; we couldn't access the path after the final steering mirror. The
second image appears to be due to reflections from the AR side of the steering
mirrors on the HAM4 table.
The BS position on the BSC2 table was checked by sighting a 1mm dia vertical rod placed on the BS LOS structure at the beam centerline position with the y-arm theodolite; the BS LOS is positioned within 1.5 mm of the desired centerline position.
ITMX PO BEAM:
The ITMX PO beam reticle pattern was centered in the FOV of the output
port by adjusting the ITMx POmirror. During this procedure, a second dimmer
image was observed to the left of the bright reticle pattern. It was apparent
that the second, dimmer reticle pattern was a reflection from the back
surface of the steering mirror.
BS PO BEAM:
The BS PO beam reticle pattern was already centered in the FOV of the
output port, and the BS POmirror did not need adjustment.
ITMY PO BEAM:
The ITMyPO beam reticle pattern was centered in the FOV of the output
port by adjusting the ITMy POmirror.
MMT3
The 4W COS AC in the y-arm was projected onto a target at the center
of the MMT3 mirror and the center of the reticle pattern was approx. 5mm
to the right and 5mm above the center of the MMT3.
MMT3 was aligned to project the reticle pattern onto the center of a target placed at the center of MMT2 within <0.5 mm.
REO has a new cleaning procedure and an improved clean room, free of dust. All cleaning is done under a class 100 flow bench that has an ionizing bar to take care of electrostatic charge during the cleaning. Dust has been completely eliminated which is great. The optics get soaked in hot Alconox and scrubbed while hot until the water sheets off the surface. They get rinsed very well and they allow the water to dry by itself. The fringes can bee seen while the water dries. The DI water system is like ours and has a .2 micron filter; the water should be particle free. Because they do not have a dark field microscope I was not able to see that there are not microscopic particles. The substrates looked really clean and free of smears when inspected in a dark room under a high intensity lamp.
One problem that we encountered after the first pair of mirrors came out, was some coating flaking from the bevel of the optic. When the mirrors were re-polished, the bevels were not. When new coating got sprayed on the bevels some of it flaked. I thought that something like that may happen, however, when I mentioned to Dale, he did not share my concerns and was confident that the coating was going to adhere to the bevel without problems. Also, the parts fit on the coating fixtures a bit different because after the new polishing the bevels are smaller. It does not seem to have affected the actual mirror coating. The problem is confined to the bevel.
Tomorrow I will be meeting with the consultant that designed the new cleaning system for REO (the one used for the telecom parts and now idle) . He may have some suggestions on how to approach the cleaning for LIGO II parts.
Friday, the coating chamber will get calibrated for the AR coating.
This is not unexpected, because I went through the notes by Robert Spero who had done similar calculations for Ligo using spherical mirrors. I used his curves to test my procedures in the case of a Gaussian beam, so I made some runs just with a view to a comparison with results obtained by a different method and shown in his ligo technical note.
I know how to disentangle the problem of diffraction losses and mismatch at the internal mirror when one mirror is titled; still I need to discuss this with Kip because my analytical calculations using perturbation theory techniques give an important factor 1/(4 sin^2(theta_guoy/2)) in front of the expression he got. It seems reasonable to me since for degenerate cavities (that is small shift phases between different modes) tilt has a more important impact than in non-degenerate cavities. This kind of problem doesn't emerge when geometrical optics approaches are used and this may explain the discrepancy between the FFT-code data and the predictions by Prof. Vyatchanin and Strigin regarding the losses caused by tilt.
REO have commenced coating of the curved mirror used in the pre-modecleaner (PMC). These should be finished by week's end.
I have been trying to clean a set of old PMC mirrors. After soaking in a hot Liquinox solution for the better part of 3 days, water still does not glide off the surface of the optic.
40m Lab & LASTI : I checked out a few problems related to the PMC and its alignment. Firstly the polarizer in the main beam was not properly aligned, resulting in the beam being distorted - the beam looked almost like two spots. In addition it appeared that a quarter-waveplate was installed in front of the PMC RF photodetector thus not allowing the light level to be reduced. As a result the photodetector output was heavily saturated.
A problem was noticed with the NPRO oscillator going into standby after operating for a period of approximately 30 minutes. Suspecting that the NPRO went into a thermal shutdown, the valve controlling the cooling water to the master oscillator was opened up. I have not heard of a recurrence of the problem since. It is likely that the needle valve was gummed up with something from the water cooling hoses.
Rick Karwoski
LASTI Efforts: Slight postponement of PSL installation. Our plans
are now to visit MIT the week of July 29.
40m.: Efforts underway to improve robustness and extend bandwidth of the PMC servo.
ISS: Continuation of Circuit refinements. We will be building a second set of electronics for the 4K @ LHO
Sander Liu
In the process of getting quote for a 19 inch half rack for building
a VMEbus test set.
This week we vented and opened our vacuum chamber and realigned both
arm
cavities. Last week we were able to lock all three cavities (the mode
cleaner, the north arm, and the south arm) simultaneously, but the
arm
cavities would only lock to high-order modes. On Monday we opened the
chamber, realigned the cavities, closed up, and began pumping back
out. By
Tuesday afternoon the chamber was down to the 10^-5 torr regime, and
we were
able to lock all three cavities in their respective TEM00 modes. Both
acquisition frequency and hold times are greatly improved over last
week's
results, with all three cavities routinely staying locked for 5 minutes
or
more. One remaining problem is that the locks tend to oscillate around
800Hz
to 1kHz, making noise floor measurements problematic.
Nevertheless, on Tuesday night we were able to
get a "one-armed" sensitivity
curve. Sometimes the arm cavities will lock without
exhibiting these ~1kHz
resonances, and on one of these occasions we
took a spectrum of the North
cavity's error signal. (The South cavity was
not locked.) During this lock
we sent a calibration signal into the broadband
Pockels cell after the mode
cleaner, and from the resulting peak in our error
signal we are able to do a
preliminary calibration of the instrument. We
observed a flat noise floor
from about 5kHz to 15kHz that corresponds to
a displacement sensitivity of
2.1x10^-17m/rHz, and we observed a series of
peaks from 15kHz up to 100kHz
(or highest measurement frequency) that appear
to correspond to mechanical
resonances. We also measured the open-loop transfer
function of the
arm-cavity servo, near the unity-gain frequency,
and were able to do an
alternate calibration by fitting our expected
transfer function to this
curve. This second, and presumably independent,
calibration yielded a noise
floor consistent with the first estimate.
Next we hope to stabilize the lock, by eliminating the ~1kHz resonances,
and
to begin reducing our noise floor and increasing its bandwidth.
LASTI (Harry, Mason, Mason, MacInnis, Miller, Mittleman,
Ottaway, Robertson, Rollins, Romie, Shoemaker, Torrie, Zucker):
Quad pendulum prototype: Some minor interference and tolerance issues
have required a fair bit of rework in the shop, but the end is in
sight. Blade springs have been preloaded and the aluminum dummy
masses
were temporarily suspended, with no serious surprises.
PSL: Optical table assembly is proceeding rapidly and we will begin
laser operations this week using an NPRO to stand in for the 10W MOPA
(still in repair queue at Lightwave).
SOS for test cavity: Continuing vacuum prep of test cavity
suspension parts.
Controls: Rick Karwoski and Peter King have made tentative plans
to come out from Caltech and complete the PSL controls installation
week after next. Still waiting on in-vacuum wiring harnesses
and satellite boxes.
End to End simulation ( B. Bhawal )
=====================
Mode Mismatch
-------------
(Biplab & Hiro) An exact equation for the elements of the amplitude
transformation matrix due to change in basis (waist-size and/or
distance
to waist) of the Gaussian beam is derived.
Signal Generation
-----------------
(Kathy) Kathy has done most of the coding and suplementary caclulation
for
the JAVA program to generate the signal coming compact binary sources.
She
continues to implement the Supernovae signal. The output of this program
will be fed into e2e.
Simulation engine
-----------------
Hiro is imporving the code which will be released together with the
updated Han2k. Another care taken is that the code is modified to
make it compilable CACR machine.
Alfi
----
Discussions are going on for the design of the architecture and the
clarifying the scope of the new alfi. The alfi requirement and
implementation document will include these, as well the grammer of
the
description of the simulation setup passed between alfi and the simulation
program. Meeting participants are Bruce, Ed, Hiro and Melody.
(Bruce) Completing initial design for the new version of Alfi and writing
associated documents.
(Ed Maros)
Continuing work on making alfi4 work smoother.
(Melody)
- Continuing on developing base classes which are known to be necessary
for the new alfi.
(Hiro)
- Writing "alfi requirements and implementation document"
LDAS Software (K.Blackburn)
=============
The dataPipeline command has been extended to support retrieval of
spectra data from the database API for the data conditioning API.
Changes were made to the database API to support the retrieval process.
With the Internal Light Weight Data format finalized for the data being
transferred from the data base API to the data conditioning API, the
data conditioning API is being modified to read this data and convert
it
into UDT types to be used within the data conditioning API.
Much effort has been put forth in understanding why the data
conditioning API crashes under Linux Redhat 7.1. After several more
fixes to the code which allowed for the running of the data
conditioning under Redhat 7.1 for brief periods of time, efforts shifted
to running the data conditioning API under Solaris because of its better
support for debugging threads. Running a static set of jobs continuously
under Solaris periodically caused the segmentation violation. Looking
at
the core file gave insight to possible data corruption in multi-threaded
environment. Running the same test under Redhat 7.1 with just a single
thread never caused the segmentation violation.
Other APIs continue to be modified. The event and monitoring API has
been extended o support conversion of multiDimData to the frame AdcData.
The wrapper API is being enhanced to not terminate unexpectedly when
memory has been exhausted.
Testing this week focused mostly on MDC and dataPipeline tests at LHO.
By Wednesday night, all the MDC tests and several dataPipeline commands
ran. The dataPipeline commands were run prior to installing the
enhancements for retrieving the spectra from the database. New tests
will be done once the spectra functionality is verified to be working.
LDAS sys-admin weekly (S. Anderson)
=====================
MIT
--- Scheduled major LDAS installation work
for July 18-20.
Started base operating system
installation on some of the LDAS
machines.
LLO
--- Further investigation of BigBrother as
a sys-admin monitoring and
notification package.
LHO
--- Upgraded software to temporarily run LDAS
at LHO as a development
system to evaluate the suitability
of upgrading the LDAS reference
platform from RedHat6.2
to RedHat7.1 in conjunction with a change
in the reference compiler
from gcc-2.95.2 to gcc-2.95.3.
CIT
--- Continued evaluation of QFS filesystem.
Operating system upgrades
and tuning to help debug datacondAPI.
General Computing (L.Wallace)
=================
MIT:
-Some research on wireless setup for MIT (not done yet)
Ldas installation work
-Ordered Y cables to connect Intel machines to switch
-Ordered power strips for cluster
-Ordered 3 Intel machines for GC
Livingston:
(Shannon and Tom)
-Worked a number of problems because of the network outage caused by
local
thunderstorms.
-Working on the installation of the second T1 line.
-Installing and upgrading software.
-Building a new data storage unit from scratch.
Hanford:
(Christine)
-Working on logistics to support the LSC meeting.
-Working a number of issues concerning the additional bandwidth needed
at Hanford. Working with Richard M. and Larry W.
CIT:
(Wendy)
- Finished inventorying computers in Bridge and Millikan with Mick
- Composed database of inventoried computers in Bridge and Millikan
- Booted up computers with Lisa and Mick after power outage
- Installed Printer Driver on computer
- Learned to and installed P-card software
- Copied installation CDs (SSH, utilities)
- Got Mathematica from ITS lab, installed in West Bridge subbasement
lab and on a computer in Lauritsen
- Inventoried subbasement of West Bridge
- Tested performance of various access points in Bridge and Millikan
on
wireless cards
- Learned to configure access points
(Mike)
-Reloaded four PCs, this included hardware upgrade and full software
install.
-Laptop added additional hardware and software.
-Work on a PC with a hardware problem floppy drive was out.
-Worked on documentation for Inventory.
-Trouble shooting on web server corrupted OS. Multiple errors and could
not access admintools or windows explorer.
This looked like this server had to be reloaded but after a complete
two-hour shutdown enforced by school officials the server came up fine
^A'yes'.
We are planning a regular schedule to start rebooting our NTSRV's,
just to
be safe to prevent this from happening again. Our uptime on this was
about
six-months.
-Loaded Nt Server 4.0 as a stand alone for a backup server. Working
on
setting this up to enable network client installs loading ghost images
to
and from server.
-Had a problem with AutoCAD converting .DWG drawing to a .PDF after
discussing this with Larry he mentioned that we had to print to a file
using a postscript print driver, then convert to a .PDF document. This
seems to work just fine.
(Lisa)
- Have gotten Solstice Backup successfully autoloading and dumping
daily/weekly dumps. This requires my old ufsdump scripts to be
completely disabled. If you use ufsdump with the cybernetics, you have
to
power cycle the robot and reboot the server in order for Solstice Backup
to be able to control the scsi device without throwing up I/O errors.
Now
I need to test the restore.
- Ran ghost on Win2k laptop. The ghost boot floppies don't seem
to work
with win2k, but if you use a win98 boot floppy then load a ghost floppy
it
works fine.
- Helped Wendy install Mathematica and Matlab on a couple of PCs
- Showed Mick, Wendy and Mike how to setup an orinoco access point.
- Replaced algol (ultra1 with ext. drive) with a blade 100.
- Did some benchmarks on our various wireless AP with Wendy.
- Began loading the new version of Cadence.
- Got in at 4am on Tuesday to shut the servers down for the building
power
outage. There is just nowhere in Pasadena to get breakfast at 5am.
What's
up with that?
(Barbara)
- Completed and installed changes to Costbook Detail report printed
version. Posted new versions on web page. Started
adding comments field
to web forms.
- Completed and installed changes to Publications web pages.
Now all are
generated dynamically from Pubs database.
- Completed and installed changes to LDAS Equipment web forms requested
by
Ed Chargois.
- Developed and installed form for LSC meeting registration
- Posted transparencies from PAC meeting
- Made web site changes for LSC working groups, research bulletin boards
- Recovered from pc problems by restoring missing .dll file, prepared
to
rebuild pherkab in case it didn't start up on Tuesday morning after
the
power outage
- Helped restart servers after power outage and did some housekeeping
with
accounts, files, passwords, etc.
- Helped Rita with web page and mapping to roster and LSC databases
- Fixed a bug Janeen found in the costbook web forms
(Mik)
-With Wendy, completed inventory Bridge basement, 2nd and 3rd floors,
and
most of Millikan 6th floor
-With Lisa, learned to set up a modem pool account
-With Mike, diagnosed user problem with floppy drive, determining it
is
most likely an error in the controller card
-With Lisa, removed one SPARC station(algol) from service, giving its
IP
and host identity to another
-Assisted in bringing network back up after power-out: turned on hubs,
printers, etc.
-Loaded one PC, and ghosted an image onto USB portable hard
drive; currently attempting to fix a shutdown problem
-Assembled a computer cart
-With Wendy, inventoried computers in Bridge Optics Lab (058), and
installed Mathematica on two there
-Learned to configure ORiNOCO 1000 Wireless AP
(Bruce Sears)
- General maintenance on Ilog.
(Larry)
-Ordered memory upgrades for most of the computer systems on the 6th
Floor
of Millikan. The memory has arrived. Mike and crew will start installing
them this week.
-Ordered a couple more PC's. These are upgrades for existing units.
The NT
server units will also be getting upgraded in the next month or so.
-Spent a great deal of time dealing with the power take down to the
building.
There were a few minor glitches. The edge switches in Millikan needed
to
be reset. The air-conditioning in the basement went out and it took
most
of the day to get it back on-line. Fortunately, the existing unit in
the
computer room was not affected and was able to handle the load.
The group as a whole spent time making sure equipment was shutoff before
the power outage and that things were brought backup after the power
was
restored to the building.
-Went over the Orinoco setup along with everyone else. Ran into the
same
problem with wireless setup as we did on setting up the unit with it
being
hardwired.
The PC programming the Orinoco needs to be on the same sub-net as the
Orinoco unit.
-Spent time trying to find a vendor that still sales an outdated disk
drive. We need the unit for data recovery from a crashed PC but so
far no
luck.
-Worked a couple security issues with Shannon.
-Worked a couple more LSC mtg. issues.
-Went over a number of procurement issues with Gina.
-Spent time with Liz trying to help her get a number of phone line
issues
cleared up.
-Investigating a couple of e-mail issues.
-Finally, getting some responses from vendors to get a GIGE switch
installed.
-We had a number of people that received e-mail with viruses attached
but
once again the virus-scan s/w had kept them out of trouble.
-The usual of setting up accounts and changing e-mail aliases.
no report
For additional information about this report, contact sanders@ligo.caltech.edu