Weekly Report for Week Ending June 7, 2001


 Exec. Comm. Agenda
Highlights
LSC
Administration
Hanford Observatory
Livingston Observatory
MIT
Caltech
Detector
40 Meter
TNI
LASTI
Data Analysis
LIGO II/Adv. R&D
Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  June 4, 2001 will be:

 (Meeting time: 10:30 am Pacific Time)

Open meeting 10:30 - 11:30

  1. Announcements
  2. LSC Issues (Weiss)
  3. Comments on Weekly Report
  4. WBS 1 LIGO I Construction (Lindquist)
      • Field Change Orders/Contingency Liens/Change Requests
  5. WBS 2 LIGO Lab Operations
      • Administration (Lindquist)
      • Sites (Raab, Coles, Shoemaker, Sanders)
      • Detector (Whitcomb, Coyne)
      • Campus Research Facilities (Weinstein (40 Meter), Libbrecht (TNI), Zucker(LASTI))
      • Data Analysis and Computing (Lazzarini)
  6. WBS 3 and 4  Advanced R&D and LIGO II (Sanders)
Executive Committee only 11:30 - noon   Topics:

Special Items:   Joy Fan update


Special Announcements:


Weekly Report Highlights
 


LSC Issues (Weiss)


no report


LIGO I Construction/LIGO Laboratory Administration (Lindquist)



WBS 1.2 LIGO Operations--Administration


LIGO Weekly Site Telecon (Lindquist)

No site teleconference was held on Thursday, June 7, 2001.

The next site telecon is scheduled for Thursday, June 14, 2001.  The list of current actions revised to reflect open actions assigned through May 31, 2001 may be found at ACTION LIST.


PROPERTY MANAGEMENT (Chargois)

From: Ed Chargois <chargois_e@ligo.caltech.edu>


DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Cleveland Mak <mak_c@ligo.caltech.edu>

Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .

ACCOMPLISHMENTS

Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.


COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Akutagawa, Kaufman)

From: Esther Cunningham <esther@ligo.caltech.edu>

Press here for ACCOUNTS PAYABLE HISTORY DATA.

From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

From: Florence Kaufman <fkaufman@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: irena@ligo.caltech.edu (Irena Petrac)

From: Ed Jasnow <jasnow@ligo.caltech.edu>

Support (Wood)


Dorothy Lloyd
  • Processed the usual requisitions, invoices and receiving on-line. For more detail, see "Cost Schedule Control Systems" report by Esther Cunningham.
  • Tracked and followed up on invoice problems.
  • Reviewed and recorded payments processed by Esther during the period of May 21 through June 1.
  • Continue to monitor contract and blanket order encumbrance and notify task managers when supplements are needed.
  • Jim continues with data entry in the LIGO database and supports Irene (travel) in the mornings and Linda and Cleveland (DCC) in the afternoons.
Irene Baldon
  • I was able to process nine (9) new trips (including Advance Checks written and hotel/car rental authorizations filled out and FAXed to appropriate vendors in various locations).  I have ten (10) trips ticketed and awaiting processing, plus nineteen (19) trips in various stages of completion before ticketing.
  • Jim continues to work on the fifteen (15) reports he took on May 22nd.  He returned 9 completed and has 7 that he is working on.  I worked on ten (10) that were problems and clarified a few more that Travel Audit or the traveler was having trouble with.  There are fifty-one (51) reports to be done.  I'm holding three (3) reports that need checks from the traveler.
  • I reconciled eighty-seven (87) items on my P-Card which required telephone calls to vendors who do not enter the traveler's name on their charges.  Assisted a few travelers with their reconciling and/or data entry.
  • Worked on the preparation and distribution of the Travel/Vacation Itinerary for June 4, 2001.  Performed normal recording and filing associated with Travel and Reimbursement.  Also performed miscellaneous duties as requested by various members of  the LIGO Project here at Caltech as well as from members of the staffs of each of the two (2) sites.   I continue to do MIT's travel to the sites for installation activities and also to assist them wherever possible.
Rita Torres
  • Checking weekly for incoming LSC reports and plans, no new reports this week.
  • Scanned: IUCAA's (India) MOU, Attachments A & Z, and progress reports for Univ. of Oregon, and Moscow State.  These two were submitted to the DCC out box.
  • Obtained Oracle requisition numbers for: WavePrecision (GO), change order No. 8, and  regular requisition for TMC for vibration control equipment.
  • Distributed the minutes from CCB meeting of 5/18/01.  Formatted the draft summary of LLO Annual Safety Audit; this is now in review.
  • Lots of Pcard activity this week, reconciled several after chasing the documentation, also arranged for more purchases.  After some sleuthing, I discovered that the vendor mislabeled one of our orders so that it went to the Quantum Optics group.  Thanks to the group's Beth Adams, we recovered the order intact.  Cleared up a misunderstanding with Graybar, they billed us instead of charging my card, even after I gave credit card info.  Called vendors regarding status of long-lead items.
Elizabeth K. Wood
  • Worked on the LIGO Annual Report and submitted it through NSF’s easy-to-use, user-friendly FastLane (TM, all rights reserved) system.  Followed that by submitting a milestone report via FastLane as well.
  • As always, if you have submitted a paper to a journal or if you have had a paper published, please oh please oh please let the DCC, Barbara K., or me know.  If you have reprints, please send copies to the DCC.
  • Dealt with a myriad of personnel issues.

Advanced LIGO (Frey)

From: Thomas Frey <tfrey@ligo.caltech.edu>

Progress Period from 06.01 to 06.07

Accomplishments:

Schedule 06.08 to 06.014:

WBS 1.4.1.2   Project Controls (LIGO Construction)


Reports (Lindquist)

David Shoemaker has provided a final draft of the Advanced R&D Annual Report.  Elizabeth Wood has "submitted it through NSF’s easy-to-use, user-friendly FastLane (TM, all rights reserved) system."



Change Control/Contingency (Lindquist)

We held a Technical Review Board (TRB) on May 18th to discuss design and placement aspects of an office/laboratory building at Hanford.  Minutes of the TRB have been prepared and distributed (LIGO-T010065-00-P).

Press for the latest Contingency Needs Projection.


COST SCHEDULE CONTROL SYSTEMS (Duncan, Akutagawa)

From: Kris Duncan <kris@ligo.caltech.edu>

From: Cindy Akutagawa <cindy@ligo.caltech.edu> The financial reports on the web provide supporting detail.
http://docuserv.ligo.caltech.edu/~fireport
http://docuserv.ligo.caltech.edu/~finance


SUBCONTRACTS MANAGEMENT (Jasnow)

From: Ed Jasnow <jasnow@ligo.caltech.edu>


Quality/Safety (Tyler)

>From: Bill Tyler <tyler@ligo.caltech.edu>
No report this week.

LIGO Hanford Observatory (LHO) Operations (Raab)


No report received


LIGO Livingston Observatory (LLO) Operations (Coles)


The LVEA and lab air handles have been running well since Monday.  Motors from the  west end stations are at the motor repair shop to have bearings replaced and re-packed. We have learned that the bearings within the motors, which are original equipment, are not the same grade of bearing as called out by the manufacturer on the motorplate but are a lower tolerance bearing (ABEC 3).  We were able to locate the bearing specified by the motorplate (ABEC 5). Motors from the south end station are already installed after having been rebuilt.  Rich Riesen oversaw the bearing replacement of the 4 air handler motors at the Electric Motor Service Co. assuring replacement was done to factory spec. The actuators which control the blade pitch on the fans have been temporarily set at max-air flow. We still need to investigate what prevents the 4-20 mA controllers from operating the pitch control. Also, there is some concern about the effectiveness of the lubricant used in the bearings, a teflon slurry in a low vapor pressure fluorene base with the trade name Braycote. We have received various and conflicting reports about the effectiveness of this and how it should be packed into the bearings. We believe a study by the project of this or alternates is warranted so that we don't have a recurrence of this problem. We understand that JPL has some experience with this material and recommend that the project contact JPL to learn what their experience has been.

Following the re-start of the LVEA HVAC, the LVEA X-arm spool piece was removed. Moved IOT1 and ISCT1 for HAM 1 door removal. The spare rubber tips for the earthquake stops were machined. ISC survey equipment is being set up on the LVEA  X-arm. The small bake oven is being assembled and  checked out before an upcoming OSEM bake. OSEM photo diode response characterization is in progress.  Removal of the MC1 and MC3 is now in progress.

We have experienced a major rain storm at LLO which dropped about 6 inches of rain on the site in about 12 hours. By late Wednesday, the rain had overtopped the state provided access road, and the road was submerged by several inches by Wednesday evening. This confirms our suspicion that the height of the road may be less optimal. However, in spite of the heavy rain, the site erosion control system of collection ponds and pumps worked very well so that there was no flooding problem on-site.


Detector/Technical Support (Whitcomb, Coyne)


Installation& Commissioning:
Hanford
Livingston
Other Science/EngineeringActivities:
Design/Analysis/Fab
Issues/Concerns
See also the Installation web page

1.1 LHO INSTALLATION & COMMISSIONING

2km

Whitcomb reporting:
(Weaver, Shoemaker, Worden, Lubinski, McCarthy, Myers, Barker, Cook, Savage, Gustafson, Whitcomb)

Late last week, we discovered that one of the OSEM wires had drooped into the reflected beam. We estimated that it was obstructing enough light that it could be a danger to the optics at high power and would interfere with proper operation of the wavefront sensing alignment system for the modecleaner. On Monday we vented the diagonal section removed the west door from HAM7 and tied up the wire so that it was out of the way. The system was closed up again and pumped down. The vacuum returned to the previous level in about 2 days, so the time lost until we can open to the beamtubes is minimum.

The operation was a success. The clipping has been eliminated and the modecleaner alignment did not change at all. The total time at atmosphere was less than 3 hours and the modecleaner was locked again less than 3.5 hours after Betsy took her hands off the table. Could be that we are getting better at these things.

A brief summary of the commissioning highlights:

The PSL has started to show large frequency shifts. These occur at the rate of several per hour and occur over a time of several seconds. These shifts don't cause loss of lock, but are still under investigation.

4-k Commissioning

Whitcomb reporting:
(Savage, McCarthy, Myers, Barker, Cook, Gustafson, Schofield, Guenther, Whitcomb)

The 4 km PSL and modecleaner are back on line. The PSL premodecleaner gave up this weekend, when its piezo mirror broke loose from its epoxy bond. This premodecleaner was scheduled for replacement anyway, due to high losses, so Rick swapped it out and realigned the beam into it.

1.2LLO INSTALLATION & COMMISSIONING

Commissioning

Coyne reporting …
Following resolution of the building ventilation fan problems and associated humidity control regulation problems, the vacuum system was opened in preparation for the replacement of all sensor/actuator heads (alias OSEMs). A large spool section in the X-arm vacuum manifold was removed and chamber doors are in the process of being removed.

Malik Rakhmanov and Sany Yoshida are both at LLO to help with the IOO work. They are preparing to make  measurements on the mode matching telescope with a Shack-Hartman wavefront sensor.

In preparation for the re-alignment associated with the OSEM replacement, Mike Smith and Ken Mailand shipped a COS autocollimator camera mount, a laser adapter, two tripod/ video camera mounting assemblies to LLO. The SOP for the 4Watt laser in the LLO LVEA was revised.

All OSEMs for LLO have been received. Approximately 20 units are to be vacuum baked this week.

It has been determined that the MC2 mirror must have its magnet/standoff assemblies stripped off. The MC2 suspension is in the optics lab. Re-processing will start soon.

2.0 OtherEngineering and Scientific Activities

2.1 Design/Analysis/Fab

Optics

GariLynn Billingsley
Wave Precision (formerly General Optics) has the optics for rework of several of the mode cleaner mirrors. We have one spare 4KMCCM at CIT which apparently has high scatter, the only other spare 4KMCCM is headed for re-work at WP, it also has high scatter. One of the Mirrors (a 2KMCCM) has significant divets, enough that WP thinks it's cheaper to start with a new blank rather than try to re-work this one. These type of glass blanks run ~$300, perhaps we should have a supply on hand since glass manufacturing times are long. [Comment by Coyne & Whitcomb: Good idea; We will do so.]

Physical plant will be lowering the sprinkler heads in the Metrology lab to below the level of the false ceiling. I am trying to persuade them that they don't need to cut a hole in the metrology tent to put a sprinkler inside the enclosure.

PSL

Peter King EO Shutter Controller

Sander Liu

Placed an order of one high voltage pulser from DEI for LHO
Anti-aliasing boards

Sander Liu

SUS Diagonalization

Mark Barton

I spent several days up at LHO struggling largely unsuccessfully with the 4k DAQ system, trying to get suspension controller tuning validated for the SOS. I've also been writing up some results on the effect of the magnetic Kovar seals in the photodiode and LED devices in the OSEMs for David Shoemaker.
Data Acquisition

Rolf Bork

ISC/LSC

Mike Zucker

Rolf Bork
LHO4k further modified to operate with Digital Suspension System (DSC). Major change is to remove the ISC supervisor processor and to install a Motorola162 CPU directly into the LSC front end crate to act as the EPICS interface. Primary reason for this is to remove EPICS traffic from the LVEA ISC reflected memory network (this is how the ISC supervisor communicated EPICS data to/from the LSC/ASC front ends), since this network now carries real-time control data to the DSC from the LSC and ASC front ends.
Rich Abbott ISC/ASC

Rolf Bork

DMT

John Zweizig

On Monday, Daniel and I installed a Blade-1000 at Caltech that will be the DMT development and offline detector characterization platform at CIT. This machine is being used this week by DMT Trainees at the LDAS/DMT boot camp. The rest of this week has been devoted to instructing the Boot-Camp attendees.
Integrated Layout Drawings

Ken Mailand, Mike Smith

The D970308 integrated layout drawings (six sheets) for the LHO interferometer are being revised to reflect the current as-built design configuration.

40 Meter Interferometer (Weinstein)



PSL (King, Cardenas, Karwoski, Russell, Ugolini, Abbott): DAQS (Rolf Bork): Waiting for Rolf to put a few more bells and whistles onto our otherwise well-functioning DAQS system, and set up our Frame Broadcaster (which awaits an ethernet card).

PEM (Ugolini, Abbott, AJW): The IOC for the particle counter and other misc RS232-readout devices is back in service. Work on other devices (weather station, STACIS controllers, RGA, etc) begins next week.

Vacuum control system (Ugolini, Vass):

Vacuum envelope and hardware (Larry Jones): Optical layout (Mike Smith): The output beams and ISC controls beams were re-routed so that they bypass the PSL/input table. The main beam monitor system was repositioned on the PSL table to give more room between it and the PSL optical components. The 40m PSL /input beam monitor table layout drawing was annotated with a parts list. The optomechanical layout drawing was revised to place the South arm beam tube sections in the proper order, and to correctly locate the overhead cable trays and the positions of the electronic racks.

ISC (Mike Smith): The WBS dictionary, development plan for the AOS, ISC, and IO sections of the 40m IFO Upgrade are being revised to better represent the division of effort on the 40m project.

Facility (Vass, Abbott): Fixes to control room chairs should be hear in a week. Ben and Dennis assembled the last control room desk.
Computing: Two new PCs arrived at the lab, and monitors for our sun blades are expected any day now. One of our old PCs needed a system rebuild; thanks to Mike Pedraza for doing that. John Zweizig will help set up our DMT machine as soon as the computers are set up, and the Frame Broadcaster is up.


Thermal Noise Interferometer (Libbrecht)


No report received.


LASTI (Zucker)


LASTI (MacInnis, Gray, Laliberty, Miller, Radkins, Shoemaker, Rollins, Mittleman, Harry, Ottaway, Mason, Mason, Barker, Zucker):

HAM seismic installation: Internal support table, support tubes and bellows are all installed.  Everything went smoothly except for two dinged bellows flange seals, which were reworked and polished out.  HAM is now waiting for leakcheck to complete the external support assembly.

BSC seismic installation: Support tubes and bellows are all installed and big ends on bellows are now being torqued. One flange ding was repaired on the BSC as well. External support structure is complete.  The BSC dome has been replaced and bolts are being tightened.  Pumpdown for leakcheck on HAM and BSC support tube bellows is scheduled for first thing Thursday morning 6/7.

MZ comment: Special thanks to Richland pros Hugh and Corey!

Cleanrooms and SEI/SUS assembly infrastructure: In the process of doing the BSC installation we found an unplanned interference which may complicate lifting of a future combined SEI/SUS assembly over the support structure.  Given the success of our structural steel cleanroom/work platform around the BSC, we're now thinking to extend the work surface southward, building out a mezzanine over the south beam tube.  This will greatly simplify the lift to bring an assembled SEI/SUS unit over the BSC, with the moderate inconvenience of doing the assembly and test work "upstairs."  Sketches and quotes are in the
works.

Controls: Dave Barker met with David Shoemaker and definitized the plans for control computer networking and installation (a.k.a. the "CDS side").  Dave B. has tentatively scheduled a visit to MIT for week of 6/25 to build the system infrastructure.

PSL: Dave O. is working through a list of boards/modules with Rick K. from Caltech to plan out the controls assembly.  Our laser is apparently still stuck at Lightwave waiting for service.


Data Analysis and Computing (Lazzarini)


Simulation and Modeling (Bhawal)

A new C++ programmer, Melody Araya has joined the E2E team..

Planning
---------
(Hiro) The details of the works to be carried out with the help of the detector experts were written and discussed with Dennis. A list of explicit item list will be sent to people supporting simulation asking for comments/suggestions/real works. All related information is available in the e2e web, action page, www.ligo.caltech.edu/~e2e/actions.

Weekly Physics meeting
----------------------
In this week's Physics meeting Virginio Sannibale presented his recent work on mechanical simulation of suspension system.  The minutes will be available in http://www.ligo.caltech.edu/~e2e.

Mode Mismatch
-------------
(Biplab & Hiro) sorted out what seemed to be a difference between theoretical prediction and E2E's results for mode mismatch in a Fabry-Perot cavity.   Conclusion is that both the theoretical derivation and E2E's results are correct and consistent with each other. As a rough idea, a 5% relative error in reflected 2nd order spatial mode power is observed for a 15% shift in the waist position from its ideal place. For smaller shifts, the relative error goes down.
Summation cavity results agree with those from a model using primitive modules (... and also theory) in both cases of 'on' and 'off' control loop.

PSD Estimator
-------------
(Andrea) Started to write down a PSD estimator based on a pre-whitening filter estimated using a linear predictor (Burg algorithm): this should make possible to automatically prevent biases in the estimation due to high spectral dynamics.

Frame interface
---------------
(Andrea) The Frame-E2E interface: Made it ready. Testing the code.

Alfi
----
(Hiro) The future of alfi was discussed. Because of the expansion of the scope of the alfi, it is clear that a revision from the groud-up is necessary. It was decised that the current version of alfi will be feature frozen on June 16th, and after that, only those bugs will be fixed which can be reproducible.  Major effort will go to a new version of alfi written in Java. The first version will have all the features of the current alfi, except for a few features which are rarely used and make alfi fragile. The class structure design will be done by Bruce, and Melody is gathering information of Java classes which can be used to draw items.

(Ed Maros) 1. Fixed problem where name of port was always dialog.
                   2. Put in file checking for absolute path resolution.

(Bruce) - Completion of initial implementation of Alfi path junctions.
            - Full test of new junction code.
            - Review of current implementation of full Alfi system.
            - Start design of new implementation of Alfi system.

(Melody) Started looking at the Alfi code and tried running the simulation program. Researched graphical packages for the Alfi  Java implementation.

LIGO Data Analysis System

Software Systems (Blackburn)
There have been two major efforts underway this week for the LDAS software group. One has been the ldas/lal/dmt workshop. The other is the pre-release QA and testing for the LDAS 0.0.18 release.

The software workshop has gone very well. There have been some start-up issues associated with available disk space and CPUs. A decision was made to use local disk space on the 6th floor Linux computers since 22 users of the sirius file server was too slow.  There was also an unexpected restriction to just linux computers for the attendees due to the lalwrapper software release for this camp not working on solaris. We shared 5 linux machines with close to 30 people which has worked nicely. Lots of good questions are being asked and it looks like the ldas/lal agenda will cover the desired scope of topics in their entirety.

Philip Charlton put in a heroic effort, learning how to develop a new search code for the lalwrapper this week for the workshop.  He will be lecturing on development of search codes using his search engine Friday. It calculates a different statistical moment based on the rank of the node it is running on within the LDAS wrapperAPI and sends the results to the statistics table in the LIGO database.

The release of LDAS has been a bit problematic. An old issue with user accounts and ssh configuration which originally showed up in the last MDC has re-surfaced mysteriously. Once it was understood that it was a system configuration problem and not the prerelease software that was the cause we were able to get back on track and do the testing.

There will be a thread safe version of the eventMonitorAPI which was worked out this week. The eventMonitorAPI was timing out a lot in the previous MDC and this was causing several started jobs to fail. With the new threading the time outs should be removed removing the eventMonitorAPI from the check list of candidate problems when a dataPipeline job fails.

Several logging problems with the controlMonitorAPI client were also fixed for this release. A couple of thread library support routines were also fixed up in the generalAPI shared object's library.

This will also be the first release of LDAS which requires the new tools in ldcg which were fully updated on Monday night of this week. We have moved to gcc 2.95.3 on both solaris and linux, having now rebuilt all the supporting tools and LDAS with this version. We also upgraded the LAM MPI library to version 6.5.2.  Both the gcc and the lam still require minor patching from us to provide a stable version of LDAS. [NOTE: we would not be able to make these kinds of minor but necessary customizations if we were using commercial compilers and libraries]. We also took this time to upgrade as many other development packages as possible (and were shown to work with LDAS).  The new "how to build LDAS" webpage will contain all the details on these new required tools once the release is finalized and pushed to the sites.

Hardware Systems (Anderson)
The LDAS general computing network on the 6th floor of Millikan has been upgraded so that switch closet is now fully labeled and all wall jacks are fully active as 10/100 auto-sensing ports. All ports are now also able to support more than 4 addresses so that small network hubs can be installed anywhere they are needed.

The MIT LDAS Engineering run Beowulf cluster has been ordered and is due to arrive at MIT next week.

The first T3 RAID disk failure has been repaired and understood.  There is a "feature" in the T3 that complains if you replace a bad drive with itself, or possibly another bad drive, i.e., it assumes that once you have removed a faulty drive that the next unit installed in that slot is a working disk drive, otherwise it incorrectly blames additional working drives for the resulting fault.

Additional network switches and cables where ordered and installed to support the LDAS and CDS bootcamps at Caltech this week.

Data Analysis Activities
Vicere': Data analysis: I went on working with Sanjeev Dhurandhar on the network analysis for coalescing binaries, taking advantage of his presence here.

Network Data Analysis Server(NDAS) Prototype (Benoit Mours, Szabi Marka, Roy Williams)

We developed a prototype NDAS system to start transferring, merging and archiving data from multiple IFOs. Presently the system connects and receives data Hanford, Livingston and VIRGO, while the central server is located at CIT. Other sites (e.g. GEO) can be added quickly and simply as soon as they can provide data. The system is based on a star geometry with the possibility of two way transfer for each node(observatory). We use double buffered transfers for optimal bandwidth utilization. To provide maximum portability between different platforms and flavors of UNIX we used standardized unix tools, ssh and C code to implement the system.

The data route starts at the observatories where a local servers (DMTs for LIGO) write the network dataset into local directories. These datasets must be greatly reduced due to practical bandwidth limitations.  They should cover the PEM channels with the highest chance of intersite coincidence (seismic, electromagnetic, line) and some form of the h channel. Practice shows that we should not count on bandwidths over 60Kb/s, which still gives us fair amount of reserve considering the ~20Kb/s rate of data written on disks. We use large datafiles (to optimize transfer rate) of 1000 1 second long frames per file.  The central server at CIT downloads the recent data from the observatories once in every 20 minutes, stores them on a local disk and merges the frames from the observatories into one single frame. The scripts also prepare exhaustive debug and overview information of the transfer and data, which is posted on the Web. All of the participating servers have access to the data on the central server to be able to prepare their own merged datasets and minimize bandwidth consuming duplicate transfers. The merged data than will be moved to the CACR archive for permanent storage. To maintain a robust system, which is insensitive to internet problems we have sufficient buffer space for 1-2 days worth of data at all nodes including the central server.

The implementation of the system will soon be moved to a HPSS node. We are also working on version utilizing Globus (GRID) software.

General Computing (Wallace)

MIT: (Keith)
-Attending ldas camp this week
-Installed RH7.1 on laptops
-Ordered Sun's for gc and cds project

Livingston: (Tom)
-We are setting up facilities for the summer students and guests.  We have received three Sun Blade 100s, and have ordered an additional three, for general use. Most of them will be installed in the Computer User's Room, where they will be available for general use.
-We are getting prices for an additional T1 line. So far it looks like the cost will be an additional $674 per month plus an installation charge.

Hanford: (Christine)
- Did a lot of purchasing for CDS, GDS, and GC.
- Helped users having problems with Norton Antivirus liveupdate.
- Restored several files from backups for several users.
- Restarted remote shell (rsh) on the main file server as a temporary measure to accommodate some file transfers using remote copy (rcp).
- Started looking into installing MRTG for network traffic monitoring.
- Cleaning up a couple of PCs that are being moved from one user to another.
- Cleaned off and setup another large bookcase for additional GC software and spares storage.

CIT: (Mike)
-Computer (M18) had a problem with 98 shutting down ended up having to flash the BIOS after loading all OS patches.
-Upgraded (M45) with more RAM this is P11 200 Mhz with simm slots only.  Liz Woods computer had problems shutting down. I installed the shutdown
patch for win98. It worked 'yes'
-Irena Petrac, had a compatibility problem with FrameMaker 6.0 users were not able to view her files because they are running FrameMaker 5.5. I installed 5.5 on her computer she is now running both versions.
-Florence Kaufman, computer (M51) I reloaded another computer for her with a full install plus configured her Oracle discoverer client and Webster.
Instructions for just go to this link https://tahoe.caltech.edu/oowa/ExpSrv620/dbxwascode/runwebsite?_XWA_1455 and download the citrix client and the install instructions.  Webster go to this link https://tahoe.caltech.edu/oowa/ExpSrv620/dbxwascode/runwebsite?_XWA_1455 and just create a shortcut to the users desktop or bookmark it.
-40meter, computer (M93) I reloaded OS win98 and full software install and setup a shared printer.
-Nergis Mavalvala, laptop (M89) I reloaded OS win98 and full software install.
-Ken Mailand, computer (M15) compatibility problem with Y2K pro and Autocad. I loaned Ken a computer loaded with Autocad until I reload his old computer in the morning with win98 install. Win98 seems to work fine with Autocad.

(Lisa)
-Ran the monthly backups.
-Installed the Pcard s/w for Nergis on her laptop.
-Rebuilt a number of Sparc 5 units. Three of which have been sent to Hanford at the request of Dave B..
-Worked with Larry on a couple of DNS issues.
-Reworked a couple of Ultra 10's and put them in their respective locations.
-Added a few more users (SURF students) and worked with Larry on adding a number of users for the LDAS workshop.
-Reinstalled the OS on the Blade 1000 for the LDAS workshop.

(Sam)
-Wow, This is my last one.  It is hard to believe.  My week has been full of stuff, mostly non ligo but nevertheless very full.
-I am currently trying to take my two finals that are required for me to graduate.  I have little enthusasium for the process, but alas it must be done.
-I went to work a number of days this week.  I fixed the CD rom in Phil's computer.  I fixed the Cd rom in Gina's computer.
-I worked on documentation.
-Worked on putting together anything that I have ever done that will make things easier.
-Slept.  Ahhh, this one is so nice:-)
-I think that is all folks,

(Larry)
-Worked a number of procurement issues. Including items for the 40M, Wilson House, and LDAS.
-Setup a number of accounts for the LDAS workshop. One item of interest was that the computer(sirius) was not able to handle the number of users all wanting to compile at the same time. This helps support our model of using multiple machines and having the users spread out over those machines for compute intensive work.
-Restored a number of directories and files for different people.
-Worked on a few calendar issues.
-Took care of a few printer problems as well as a number of PC issues.
-Helped Mike and Lisa move computers to various locations.
-Worked a number of network issues including setting up a new hub for the third floor.
-Worked on a number of issues concerning the laptops. Presently, all of the units have been checked out and we are working on rebuilding one more to add to the pool. The only operating system we support on the laptops at this time is Windows98.

(Barbara)
- Completed the costbook detail and summary reports.
- Installed web site changes for PAC meeting, LSC documents.
- Compacted the DCC databases and installed a new version of PubDocs.

[Bruce Sears]
-Ilog maintenance -- General maintenance.


LIGO II/Advanced R&D (Sanders)


PSL (Peter King)

New OSEMs for 40m, LASTI, TNI etc. (Janeen Romie)

1. Installation: Hanford and Livingston

Nothing significant to report.
2. Commissioning : Hanford & Livingston
Nothing significant to report.
3. Other Engineering and Science Issues:
New osems for 40m, LASTI, TNI etc.: I dropped off pigtail parts to So. California Braiding on Friday. Taking a preliminary look, the representative said that it might cost more (~2x) to hand-twist and braid the partials from Pal Pilot than to make from scratch. We have an order in for more pigtail wire but do not expect to receive it until July 3 at the earliest. I'm scheduled to talk with the rep. again on Friday to determine what to do next. TNI needs their new osems by the last week in June and So. California Braiding has enough wire to make their pigtails. Todd Etzel will head to MIT next week to learn the osem assembly techniques from Myron and Peter. I'm waiting to hear from Mike Zucker about LASTI's osem delivery requirements.
Advanced SUS (Janeen Romie, Helena Armandula)
:Helena and I are working with Thomas Frey on schedule and cost data for Advanced LIGO. The schedule, development plan and WBS dictionary are in good shape. Thomas needs to make some small changes to the schedule. We will start inputing cost data as soon as Thomas is available.
Sapphire Optics (GariLynn Billingsley)

CSIRO is reporting on their polishing of our first "high quality polish" of a sapphire optic.

ROC
They hit the sag goal within 5 nm.  The requirement was within 10nm. (the spec is written in terms of a zernike, Z3, which is half the actual sag over the defined aperture, we asked for Z3 of 26 nm, this means a sag of 52 nm.  They report a Power, or sag of 47nm)

Surface Error
We asked for <0.8 nm over the central 120mm, we got 1 nm rms. We asked for <0.4 nm over the central 80mm, we got .6 nm rms
Keep in mind that they measured the central 80mm of (the LIGO1) 4ITM06 to be 0.62 nm rms and we measured it to be 0.18nm rms, which is at the noise floor of our interferometer.  So they may be getting a significant contribution from interferometer noise.

Microroughness
Our Goal was <0.1nm rms, our requirement was <0.2 nm rms.  The average microroughness over the surface was 0.18 nm rms, the report has a caveat about noise in the measurement, they feel the number is closer to 0.12 nm.

The CSIRO polishing report can be found at: http://docuserv.ligo.caltech.edu/docs/internal/C/C010237-00.pdf

A picture of the surface phase map taken at CSIRO can be found at: http://www.ligo.caltech.edu/~gari/LIGOII/sapphia1.gif

The spec can be found at: http://www.ligo.caltech.edu/docs/E/E000041-A.pdf

LASTI Data Acquisition System (Rolf Bork)

Continuing to build up LASTI system. In the process, making some code fixes/adds. Primary change is to get the system to reconfigure on command (button has always been there, but not functional because EDCU did not always respond properly). This required an extension to EDCU code and restart/reconfig code in data collection units (DCU). This code appears to be functioning properly and will be moved to the 40m system and ship with the LASTI system. Updates at sites are TBD.

SEI Position Sensor (Rich Abbott)

Rich is talking to the people at ADE Inc. in an effort to get the delivery of the first prototype Capacitance Position Sensor moved up. Also, there is an ongoing discussion as to how to do initial testing on the prototype.

TAMA SAS (Szabi Marka)

I spent 10 days at Tokyo University helping the 3m interferometer commissioning. During the second week I developed the prototype of DC control module for the 4 actuators (3 horizontal, 1 vertical) per tower. These DC Control Modules (DCCM) are used to balance the small, very low frequency variations in the IP and MGASF equilibrium positions due to environmental effects. The low frequency shifts are taken up by the voice coil actuators until the offsets reach a threshold, at which point they must be corrected by readjusting the balance spring tensions. Each DCCM module can digitize 8 analog signal inputs (4 differential) to read the coil currents. The stand alone microcontroller continuously monitors the load on all the coils. When the offsets are outside of the desirable region, it balances the system at the next lock loss or on a operator command. The motor drivers (4 to 8 per module) are controlled via an internal bus. The high resolution stepper motors are used in a microstepped mode, achieving 3200 steps/revolution. I submitted the final PCB designs for manufacturing and already received the microstepper boards. We expect to receive the microcontroller board Friday and finish the assembly of the production models early next week.

From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>

Our friends with their bigger brothers in Virgo have achieved 100 second locking in the central interferometer.  They beat us on having the first superattenuator or SAS suspended interferometry.  They are now going for hour long locks, and then they will soon replace the temporary injection bench with the independently tested  real one.  The superattenuators achieved less than 100 nm residual motion on the resonances!!!!  Congratulations to them for their success and get energized by them!  Giovanni will bring us lots of experience and ideas for the SAS startup in July.  Good news also for LCGT,  Virgo has proved before we could do it, that LCGT made a good choice in baselining SAS .

Florian
Moved to Hongo.

Virginio
will go around June 15th

Riccardo, Alessandro
Waiting for machined sapphire from Sonic mill and Faimond

Szabi working on 8 channel stepping motor controller board.

Yukioshi
Calculations on IP, measuring long term IP drift.  1 micron r.m.s. over minute(s)

Akiteru, (and others)
Schedule still slipping some,  now do not expect to have interference before Amaldi anymore.  Ordering some parts, finishing permanent IP Counterweights, got two ADC and DAC working on same DSP for full tower damping and mirror controls.  Replaced new coils in LVDTs.  Expected to have 1 tower completely operational by June 15th when Virginio arrives to help implement full feed back controls.  Laser injection bench is OK, will need little refurbishing.

Hareem
Analysing old Q-measurement data for GASFs.

Brett
Designing Memory metal actuator for IP.

Virginio,
Got GASF paper back from review panel, will submit it;  starting paper on MGASFs

Szabi
Work on IP paper.

Riccardo
prepared actuator paper, circulated to collaborators for comments.


For additional information about this report, contact sanders@ligo.caltech.edu