Weekly Report for Week Ending May 31, 2001


 Exec. Comm. Agenda
Highlights
LSC
Administration
Hanford Observatory
Livingston Observatory
MIT
Caltech
Detector
40 Meter
TNI
LASTI
Data Analysis
LIGO II/Adv. R&D
Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  June 4, 2001 will be:

 (Meeting time: 10:30 am Pacific Time)

Open meeting 10:30 - 11:30

  1. Announcements
  2. LSC Issues (Weiss)
  3. Comments on Weekly Report
  4. WBS 1 LIGO I Construction (Lindquist)
  5. WBS 2 LIGO Lab Operations
  6. WBS 3 and 4  Advanced R&D and LIGO II (Sanders)
Executive Committee only 11:30 - noon   Topics:
 

Special Items:   Joy Fan update, PAC meeting


Special Announcements:


Weekly Report Highlights

First (IR) light at the 40m!
 


LSC Issues (Weiss)


no report


LIGO I Construction/LIGO Laboratory Administration (Lindquist)



 

WBS 1.2 LIGO Operations--Administration



LIGO Weekly Site Telecon (Lindquist)

A site teleconference was held on Thursday, May  31, 2001. The following issues were discussed:

The next site telecon is scheduled for Thursday, June 14, 2001. There will be no site teleconference on Thursday, June 7, 2001.  The list of current actions revised to reflect open actions assigned through May 31, 2001 may be found at ACTION LIST.

PROPERTY MANAGEMENT (Chargois)

From: Ed Chargois <chargois_e@ligo.caltech.edu>


DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner - turner@ligo.caltech.edu>

Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .

ACCOMPLISHMENTS

From: Cleveland Mak <mak_c@ligo.caltech.edu>
 
Packages Faxes
In 33 24
Out 11 23

Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.


COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Akutagawa, Kaufman)

From: Esther Cunningham <esther@ligo.caltech.edu>

Press here for ACCOUNTS PAYABLE HISTORY DATA.

From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

From: Florence Kaufman <fkaufman@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: irena@ligo.caltech.edu (Irena Petrac)

From: Ed Jasnow <jasnow@ligo.caltech.edu>

Support (Wood)

 
Dorothy Lloyd

Not feeling well.

Graphic provided by C. Akutagawa.

Irene Baldon

  • I continue to catch up from my vacation.  I was able to process thirty-two (32) new trips (including Advance Checks written and hotel/car rental authorizations filled out and FAXed to appropriate vendors in various locations).  I have four (4) trips ticketed and awaiting processing, plus twenty-eight (28) trips in various stages of completion before ticketing.  ProTravel will be delivering several tickets this morning that were ticketed yesterday.
  • Jim Covington continued to work on Expense Reports.  Jim continued to work on the fifteen (15) reports he took on May 22nd.  I worked on several reports (6) that were problems and clarified a few more that Travel Audit was having trouble with.  There are fifty-four (54) reports to do done.
  • I have seventy-seven (77) items on my P-Card to be reconciled, including telephone calls to vendors who do not enter the traveler's name on their charges.  Assisted a few travelers with their reconciling and/or data entry.
  • Worked on the preparation and distribution of the Travel/Vacation Itinerary for May 29, 2001.  Performed normal recording and filing associated with Travel and Reimbursement.  Also performed miscellaneous duties as requested by various members of  the LIGO Project here at Caltech as well as from members of the staffs of each of the two (2) sites.   I continue to do MIT's travel to the sites for installation activities and also to assist them wherever possible.
Rita Torres
  • Checking weekly for incoming LSC reports and plans, no new reports this week.  Submitted several documents to the DCC for web posting.  Formatted some attachments from GEO.  FedEx letters and documents to obtain signatures:  ACIGA Attch. B, C, D & Z, LA Tech Attch. A & Z, IAP Attch. C & Z, and So. Univ. Attch. C & Z.
  • Obtained Oracle requisition numbers for: BF Goodrich (used to be HDOS), change order No. 3, and regular requisitions for Kepco, Inc., and Excel Electrical.
  • Unusually high Pcard activity this week as I chased documentation for several transactions, and arranged purchases for the optics and bridge groups.  Two mystery charges on my card required lots of sleuthing and the help of Muriel Lampe to solve.  Turns out there are vendors who bill under different names:  Rudolph Instruments bills as ATS, and Etrema as Edge Technologies.  Would be nice if they would apprise us of this fact when we place the order.
Elizabeth K. Wood
  • Began working with NSF’s FastLane system to enter the annual report.  Of course, FastLane has changed from the last time I entered an annual report.  I am now limited to 25 the number of new participants I can add and to 25 new publications.    The annual report section of FastLane was not designed for an organization the size of LIGO, that’s for sure.
  • As always, if you have had a paper published and the DCC, Barbara Kratochwill, or I don’t know about it, please oh please oh please let one or all of us know so we can include you in the LIGO publications databases.
  • Prepared some job requisitions for summer hires at the sites and here.

Advanced LIGO (Frey, Petrac)

From: Thomas Frey <tfrey@ligo.caltech.edu>

Progress Period from 05.25 to 05.31

Accomplishments:

Schedule 06.01 to 06.07:

WBS 1.4.1.2   Project Controls (LIGO Construction)



Reports (Lindquist)

David Shoemaker has provided a final draft of the Advanced R&D Annual Report.  Elizabeth Wood is currently entering the report into FastLane for transmittal to the NSF.  She is going to need some additional help where information is incomplete, e.g., certain publications that have not been submitted to the LIGO DCC.



Change Control/Contingency (Lindquist)

We held a meeting of the LIGO Change Control Board, Tuesday, May 29, 2001.  The following Change Request was approved.  Minutes have been prepapred and are being distributed (LIGO-M010167-00-P).
 

CR-010005 WBS 1.1.4 OSB East Building at Hanford O. Matherny

We held a Technical Review Board (TRB) on May 18th to discuss design and placement aspects of this building.  Minutes of the TRB are still being prepared.

Press for the latest Contingency Needs Projection.


COST SCHEDULE CONTROL SYSTEMS (Duncan, Akutagawa)

From: Kris Duncan <kris@ligo.caltech.edu>

From: Cindy Akutagawa <cindy@ligo.caltech.edu> The financial reports on the web provide supporting detail.
http://docuserv.ligo.caltech.edu/~fireport
http://docuserv.ligo.caltech.edu/~finance


SUBCONTRACTS MANAGEMENT (Jasnow)

From: Ed Jasnow <jasnow@ligo.caltech.edu>


Quality/Safety (Tyler)

>From: Bill Tyler <tyler@ligo.caltech.edu>

Sanders, Scislowicz, Zydowicz and Tyler conducted an annual safety audit at LLO with G. Stapfer and J. Kern.
Two items on the audit agenda were of particular importance to LIGO:

G. Sanders held an all-hands meeting with the LLO personnel at the end of the audit.
A draft audit report is expected to be available in about two weeks. This report will include other items discussed along with action items assigned.
 


LIGO Hanford Observatory (LHO) Operations (Raab)


no report received


LIGO Livingston Observatory (LLO) Operations (Coles)



 

The major focus of activity at LLO this week has been on the inspection and repair of the air handlers. Two of the fan units supporting the LVEA were found to have failed catastrophically resulting in their motor shafts being broken. A fan unit supplying the labs also is noisy and the bearings are suspect. These conditions probably resulted from long term wear of the shaft bearings that support the variable pitch fans. We believe the severe wear was due to inadequate maintenance lubrication of the fan bearings and overloading of the actuators which control the fan pitch. Investigation of the failed units has caused us to suspect that lubrication of the remaining operating motor units on the site may also have been improper and that other motors may now be on the verge of failure. To remedy this, we have begun a complete inspection of all of the air handlers, replacement of the failed motors with new motors, and motor rebuilds and other preventive maintenance on the remaining operating motors. The failure of these systems comes at a particularly bad time as it coincides with the planned service of the interferometer to replace OSEM's and plans to remedy some workmanship problems that are apparent with some of the SOS assemblies. To accomplish this work, we need to have a functioning and reliable clean air supply in the LVEA and the optics lab and vacuum prep lab so that the optics will not be contaminated. We have therefore had to defer the SOS work planned for this week and instead have placed the labs in a "buttoned up" state to minimize the impact of the air handlers being taken down for service. A service representative from the fan company is now on site, along with a team of riggers, members of the LLO staff, and Otto Matherny who has come from LHO to observe. Our work plan is the following:


Operators continuing cleaning efforts at the end stations in preparation for a future vent to do in vacuum re-work . Tooling has been staged in the LVEA for the possibility of removing the spool pieces on Friday. Precautions have been taken in the labs to protect in vacuum equipment during the building fan repair.
 

Optics and Installation: Ham 2's North door was removed last Friday and MC2 examined. We took it from the HAM table and into the vacuum prep lab. Visual inspection made and no grounding evident but we did find something interesting. The suspension wires were not trimmed, and one is 7-1/2" long.It is possible for the untrimmed wire to dangle into the tower and contact a suspension wire. Our examination of the tower is on hold, because of the air handler fan problem. When we learned on Tuesday that the lab fans were having problems we moved MC2 into the bake oven and roughed it down in order to keep it clean. The labs were secured yesterday, making sure everything was bagged and stored properly because airflow will be disrupted for a while during lab fan replacement. We're ready to go with OSEM replacement in the LVEA as soon as the air handlers are back on-line.

General Computing: We have received three Sun Blade 100s, which we are setting up in the Computer User's Room. We have requested an additional T1 line from LSU, and are looking in to the details.
 


Detector/Technical Support (Whitcomb, Coyne)


 
Installation& Commissioning:
Hanford
Livingston
Other Science/EngineeringActivities:
Design/Analysis/Fab
Issues/Concerns
See also the Installation web page

1.1 LHO INSTALLATION & COMMISSIONING

2km

Stan reporting:
Betsy and Stan aligned the beams onto IOT7 and then began to align the modecleaner.  MC3 seems to have shifted its pitch during pumpdown, but the bias had enough range to bring it back.  The other 2 modecleaner optics seem to be ok. We got fringes and began hooking things up.  The reflected beam looks clipped  (current speculation is that the upper mirror on the PSL table periscope may be the culprit), but it does give decent fringes.  After tuning up the phase, it locked up with about 85% visibility.  The servo is not behaving especially well; it requires pretty high feedback to the modecleaner and doesn't like the boost gain to be turned up.  Still a bit of cussing and fussing to be done to get it really working.

Betsy, Rick and Dick adjusted the EOMs to minimize the rf AM on the light entering HAM7.  The residual AM is about 1e-5.

4-k Commissioning

Stan reporting:
After shutting down the cleanrooms in the LVEA, Nergis and Stan made measurements of the 4 km PSL frequency noise using the modecleaner.  The caomparison with the 2 km noise level is in the May 29 elog entry, but shows a clear improvement in the region between 100 and 1000 Hz.  This is most likely the result of the new PSL layout, and may be expected to improve still further as the LVEA gets quieter and we get sound insulationin place.

An accidental cycling of the power on the 10 W laser caused a fault with its internal shutter.  Mark Guenther and Rick spent some time debugging it, but it basically went away without any clear cause. We will continue to monitor it.

Mark Barton is working on the suspension tuning procedure for the small optics using the 4 km MC2.

Gerardo and Hugh have been making steady progress getting the optical levers installed, pointed and enclosed.

1.2LLO INSTALLATION & COMMISSIONING

Commissioning

Rai Weiss, et al.
The system was vented. We intend to: The Q and the seismic transfer function of the MC2 mirror was measured after the system was vented but before opening. Except for the anticipated reduction in Q due to the air viscosity, system still showed the same anamolies as under vacuum. The MC2 mirror was removed and placed on a table. Uncut pigtails of the suspension wire have been found to rub on the the suspension wires and are responsible for part of the non-linear behaviour. The Q was measured with both the pigtail touching and removed and demonstrated the non-linearity. The low Q is still not understood and we will measure the damping again when the OSEMS have been removed. The registration of the magnets in the OSEMS is poor.

The problems with the HVAC fans have stopped further installation activities.

Osems for LLO

Myron, Fred M, Peter F
Finished assembling another 18 long osems for the LLO retrofit, and shipped them to LLO for final clean & bake. We also settled on an acceptance level for the coil-body leakage current, which is <= 10 nA (corresponding to a resistance of >= 250 MOhm). Something like 20% of the osems show a leakage current in the 1-3 nA range (most are less than 1 nA).

IOO

David Tanner reporting
A number of UF-related persons will travel to LLO for work on the OSEM replacement and the PSL/IOO table. The present schedule looks like:
Guido Mueller                   6/14-19  (definite)
Stacy Wise                      6/14-19  (definite) (a new grad student at UF)
Michael Hannawald               6/14-26  (definite) (postdoc candidate for IOO)
Malik Rakhmanov         TBD

PSL

Peter King, Rana Adhikari, Hugh Radkins
A modematching scheme was figured out to modematch an NPRO laser to the modecleaner.  This is to co-align the NPRO beam with the current PSL beam to allow reworking of the PSL table.

2.0 OtherEngineering and Scientific Activities

2.1 Design/Analysis/Fab

Optics

Helena Armandula
The laminar flow bench in the OTF lab is being repaired and re-certified after a change of fluorescent lights went very, very wrong. The person assigned to change the lights, a trained maintenance-electrician, was unaware of how a laminar flow bench is/or works. The change of fluorescent tubes was attempted by trying to lift and remove the light cover to get access to the lights. (Lights are accessed by unscrewing and lifting the top of the bench) When there was not easy access because the cover is partially sealed to prevent dust from falling on the working area, the cover was pried open with a screw driver. Consequently, it broke.

An specialized laminar flow maintenance firm will replace the light cover, seal it accordingly, replace the ballast (that was the defective part), replace the lights and certify the   laminar flow bench as a Class 100.

Optical modeling

Bill Kells
I have been continuing on FFT and other model studies of the RF sideband behaviour in the interferometers. This has been motivated by the MELODY validation work but has evolved into puzzling issues pertinant to LIGO II. However it bears on the LIGO I experimental work: would hope to observe some essential features at LHO.

Erika D'Ambrosio
On "Flat Top Mode".
I found out the recycling mirror must be carefully designed when the flat beam (whose shape minimizes the thermoelastic noise) is excited inside the arms. Since the superposition of Gaussian modes that the flat beam consists of, will not be a superposition of Gaussian modes after the interaction with the ITM mirror, no simple calculation applies other than evaluating the result of that interation numerically. I am currently writing a piece of code assuming a flat surface for the AR-side. During the holiday weekend I documented myself with some papers on reshaped mirrors but coupled cavities were never mentioned. I found interesting experimental results and useful mathematical considerations.

On diffractional losses
I checked on the power gains obtained by the FFT-code when the diameter of the ETM mirror (where the spot size is planned to be pretty large) is shortened. I solved the problem in that parameter for the diffractional loss associated to the mirror and the numerical curve is ~2.5 times the curve generated by using the clipped light approximation.

PSL

Rick Karwoski
PSL Custom Boards : Status on spares and GEO installation.
Five Freq Ref boards built and ready for test
Remaining boards (two sets of PMC & Freq Stab Servo) kitted
Some parts shortages exist -- work is in process to resolve the matter
We are short RFPD(2)/FreqServo(1)/VCO(2) PC boards -- We will work to resolve the situation.


Ben Abbott
I still await testing of my intensity servo DC photodiode board while integrated with Rick's servo.

ISC

Mike Zucker
EO shutters: completed tests and writeup (w/J. Rollins) on the LaserMetrics EO shutter's sensitivity to alignment and temperature drift. These shutters are provided for fast protection of the photodiodes on loss of lock, but are in principle also capable of continuously variable attenuation.  We conclude that, with proper initial setup, the shutters are stable enough to use as variable attenuators for lock acquisition dynamic range scheduling.  Writeup is T010061-00.pdf, available shortly in the DCC.

LSC photodetectors: Tested and tuned 3 of 4 new photodetectors sent by Rich Abbott on their way to LHO for the 4k IFO.  They're now compensated to give less than 1 degree pk-pk change in RF response phase from <1 mW to over 150 mW detected power.  Transimpedance gains are nominal (around 4 kOhm), but two have slightly higher RF noise than we are used to (one is slightly over specification). The fourth PD (a refurbished one with a "checkered history" as they say) mostly works but seems to have a subtle problem with its bias control.  We are investigating.

Photon calibrators: consulted with Rich Mittleman and Peter Fritschel, who now have a revised quote for 1047 nm photon calibrator lasers. By delaying purchase until now we can get three times the power (1.5W vs. 0.5W) at one third the price ($2k/unit vs. $6k/unit).

LSC

Rich Abbott, Mohana Megeswaran, Flavio Nocera
Rich made installation and commissioning trip to LHO.  Activities included, installation and checkout of 4k LSC hardware and operator screen components, commissioning of 4k RF distribution system, trouble-shooting of 2k and 4k modecleaner servo and system.

Mohana received the boards for the DC readout module and will begin testing.

Flavio is putting together details regarding the timing system tests to diagnose a potential error in design involving the ICS110B ADCs.

ASC/LSC/Digital Suspensions

Rolf Bork
LHO4k system now connected to Digital Suspension Controllers (DSC). It has been noticed that the processing time increases after a few hours of operation. Presently trying to determine cause.

Jay Heefner
All boards and components for the upgrade of the LHO 2K and LLO 4K Digital Suspensions are being fabbed or ordered. Cross connect harnesses will be started and we should be ready to convert by early September.

It has been decided that for the time being the DAQ coil readouts for the LHO 4K Digital Suspensions  will be DC coupled. The cross connects and connections to the DAQ system are designed and should be installed next week. Once we get some operational experience with the system we can design a DAQ interface that has more optimal whitening.

All custom electronics for the 4K ASC has been built and tested. The cross connects and rack wiring are installed and ready for test. Testing of the system will occur as time permits over the next month.

AC OSEMs

Jay Heefner
5 stabilized oscillator satellite amps are tested and ready. The noise of the oscillator is ~5e-7, which is a factor of 2.5 above the requirement. A prototype for a better oscillator has been designed and should be ready for test by 6/1. If it works, it can be used in place of the on-board oscillators.

Data Acquisition

Rolf Bork
In process of setting up system at Caltech for shipment to MIT prior to June 25. I have run into a snag as both of the new GPS receivers which just came in are bad. One has already been shipped back to manufacturer, other will follow. These are two modules from order of four, which should have given us one for LASTI, a spare for each site, and one for Caltech development. With these being bad and the other two not yet received (these were ordered six months ago!), I am presently out of GPS receivers and therefore cannot proceed. (another new one is due to ship this week, but considering these two, ....)

New DAQ controller is having problems coexisting with the test point manager (TPM) at LHO. Controller sending timing interrupts to TPM kills it; TPM getting timing interrupts from GPS module results in controller GPS module blacking out. Had hopes of testing/troubleshooting offline here at Caltech until I found that our new GPS modules don't work.

Sander Liu
Delivered 32 850Hz filter modules to 40m. Ordered 25 LEMO version DAQ antialiasing boards as well as 10 front panels. Obtained a quote for 240 850Hz filter modules from Frequency Devices.

GDS

Daniel Sigg
Most of the time spent preparing for the DMT camp next week.

DMT

John Zweizig
This week I spent preparing for the LDAS/DMT boot camp, and attempting to make the DMT software a bit more bomb-proof. This included compiling the new version of root (v3.01/03) and saving the root version number with the compiled DMT libraries to allow version compatibility checks.
 


40 Meter Interferometer (Weinstein)




Thermal Noise Interferometer (Libbrecht)


This week we have continued trying to improve the hold time of our
arm-cavity lock.  We have been focusing mainly on studying lock
acquisition in our mode cleaner using actuation only on one of the
mirrors.  This system is very similar to our arm cavities, but its lower
finesse and lower mirror mass make lock acquisition much easier.  By
studying what works and what doesn't for the mode cleaner, we hope to
gain a better understanding of the lock acquisition and hold process in
a suspended cavity and eventually apply that knowledge to the arm
cavities.
 

So far we have observed three things:
 

1) We can reproduce the arm cavity's 10 to 20ms transient locks in the
mode cleaner.
 

2) We can extend the mode cleaner's lock to hold times of an hour or
more, with feedback going only to the mirror. The difference between a
stable lock and a transient lock appears to be in the amount of
low-frequency gain.
 

3) The 28Hz peak, mentioned in last week's report, appears to be the
dominant noise source when the mode cleaner is locked using only
mirror-path feedback.
 

We are currently working to improve the performance of our servo, as
well as reducing the 28Hz noise peak.
 
 


LASTI (Zucker)


LASTI (MacInnis, Gray, Laliberty, Miller, Radkins, Shoemaker, Rollins,
Mittleman,
Harry, Ottaway, Mason, Mason, Zucker)
 
 

Hugh Radkins and Corey Gray have arrived from LHO and we are in an all
out effort to complete the final HAM and BSC seismic installation. Both
of these chambers will not include a stack, they will be built up in
preparation for the active seismic isolation prototypes.
 

BSC Chamber
The Dome was removed using the clean room skirts. Dome covers were
installed and the cartridge clean room placed over the opening. All
parts, hardware and fixturing were gathered and cleaned. The BSC piers
have been leveled and aligned.
 

HAM Chamber
The HAM door was removed. All parts, hardware and fixturing have been
prepared. The piers, scissor table adapters, and air bearing adapters
have been aligned and leveled previously. We have opened the support
tube blankoff plates in preparation for installing the support tubes.


Data Analysis and Computing (Lazzarini)


Simulation and Modeling (Bhawal)

LIGO I action items
-------------------
Based on the meeting on 22 May, Hiro has revised the e2e action items. That
now includes the action items we, simulation group, are going to
take, and the actions we are going to ask detector group people to
take. The revised note will be uploaded to e2e home page, and will be
sent to detector people who are going to help us by providing
necessary information.

Weekly Physics meeting
----------------------
In this week's Physics meeting Alain Weinstein talked about simulation
activities for Advanced LIGO that he and his student Michel are pursuing
with a model of 40 m IFO. The minutes ares available at
http://www.ligo.caltech.edu/~e2e

Realistic servo & Alignment sensing and control
-----------------------------------------------
Among the majors issued discussed in the kickoff meeting on 22nd were
(1) the implementation of more realistic servos in the simulation so
that it can be used to study the servo characteristics and noise
propagation. and (2) the implementation of ASC.

After the kickoff meeting, Luca Matone volunteered to work on the LSC
part and Andrea Vicere on the ASC part. To get this activity start
rolling, there was a meeting held on May 30th, having Nergis as the
detector expert/advisor. People attended were Luca, Andrea, Matt,
Nergis, Hiro and Biplab.

The following are the summary of the discussions:

(1) Time domain simulation of the servo noise will be necessary
because of the complexity of the system, even though the lowest order
estimation can be done (semi-)analytically in the frequency domain.
(2) There are many uncertainties of noise sources, so the model will
use the measured spectrum as the noise source at an appropriate point
and refine it when things change (reduced by hardware refinement,
understanding the physics origin, etc).
(3) The simplest model of LSC is: detector -> mixing -> whitening -> AtoD
-> [whatever the digital system ] -> DtoA -> de-whitening -> actuation.
At each stage, noise (from measured spectrum) could be added.
(4) the triangular mode cleaner simulation will be necessary to
simulation the amplitude noise induced by the length fluctuation.
(5) First will be the implementation of the simplest LSC model ( (3)
above ) with a very simplified (with a parameterized frequency noise)
laser coming into COC.
(6) Luca will go to Hanford to gather necessary information with the
help of Nergis.
(7) Part of the ASC model will be a copy of the same building blocks
developed for LSC, although N time more circuit lines.
(8) ASC is a moving target now, there are some things that are hard to understand.
Maybe simulation can help to understand them.
(9) Andrea will first understand the ASC design. The first
implementation can adopt the simple method used in the current LSC
model - no digitization etc, and the complex structure can be
embedded later on top of it.

Dual recycling code
-------------------
Malik has provided us a formula of the dual recycling cavity field
evolution. He sent us a matlab code as well. The formula will be
validated by comparing the matlab code with a simulation using e2e
primitives. This code is pure adiabatic approximation. We need to
implement a linear interpolation, which is a very complicated
calculation. In order to use this result in the e2e simulation, we
need to write a C++ code implementing this formula. The date for this
implementation is not scheduled yet.

Frame interface
---------------
(Andrea) The frame-E2E interface: I have almost finished it and hope to
test it extensively the next week.

E2E at CACR
-----------
(Hiro) Worked with Ed and Sharon of CACR trying to port the simulation
code to CACR HP clusters. After trying 3 compilers with various options
and identifying various bugs ( gcc 2.95.2 for HP gives NaN when a complex
number is divided by a double less than 1), now aCC (HP native compiler)
seems to be the candidate. There are still several things to be solved.
One is the size limit of the library builder. Another is that the compiler
crashes when compiling several of the adlib codes.
When Hiro had a meeting with Sharon about this compiler issue, he
found that it is possible to run a very long jobs, longer than 12
hours, if we ask them to set up.

Alfi
----
(Ed Maros)
  1. Reviewed Hiro's ALParser problem of bad directive quote_begin
     ( result of not having a proper LD_LIBRARY_PATH)
  2. Fixed the error message "/ldcg/bin/autoheader: Symbol
     `PTHREADS_IN_UNISTD' is not covered by"
  3. Added --enable-modeler flag for configure to control if
     modeler code is to be build. It is enabled by default. To disable,
     either specify --enable-modeler=no or --disable-modeler.
  4. Corrected header Alfi/lmbtb.h to conform to wxWindow'ss
     parameters for base class method AddTool.
  5. Make sure multiline change is in repository
  6. Make sure bundle change is in repository
  7. Build and install into Alfi-Dev (v 4.1.1)
  8. Change from input port to output port not reflected
     immediately.
  9. Create dialog prompt box for path resolution.
 10. Worked on getting ALParser compilable by aCC on CACR's HP
     systems.

(Bruce)
  - Finishing work on initial implementation of connection junctions.
  - Conducting full tests of connections, ports, and junctions for
    inclusion of the new junction code in next release of Alfi.
 

LIGO Data Analysis System
 

Software Systems (Blackburn)

Having almost recovered from the last MDC, the LDAS group is now busily
preparing for the so called LDAS/LAL/DMT camp that starts next week. It
is expected that there will be 22 to 24 participants with roughly 2:1
coming for LDAS/LAL vs. DMT.

We have also begun testing upgrades to our basic software development
tools. The two major upgrades are to GNU's GCC 2.95.3 compiler and to
the new 6.5.2 release of LAM for our MPI functionality. The LAM upgrade
appears to have gone without a hitch. However, the GCC upgrade revealed
some configuration problems for E2E. These have now been resolved and
we standardize on GCC 2.95.3 early next week. This will require a complete
testing of LDAS so we will plan a new release of LDAS after this testing.
This will also have the benefit of capturing all the bug fixes exposed
during the last MDC in a release. Documentation has been updated to reflect
the new required baseline code.

A minor problem with the new XML C++ parser library was discovered and
fixed this week. Testing of the lightWeightAPI with this new library is
pretty much complete now and we are comfortable with the Apache based
implementation. However, testing did discover a minor problem with
iterative translation of ilwd -> xml -> ilwd data formats which has now
been fixed.

The inspiral MDC did not conduct its final "challenge" test during the
scheduled week. In the inspiral upper limits group meeting it was decided
that this should be carried out in roughly two weeks allowing the MDC
to have closure in the minds of all contributors.

We began work on a new "trivial" user interface which allows users to
type in their requested ldasjob commands into a graphical user interface
front end which provide step by step menu options for connecting to the
different LDAS sites and for entering required information such as LDAS
user and authentication.

We also began exploring a graphical user interface called XMPI for studying
the coarse behavior of the wrapperAPI jobs on the Beowulf. The code is a
bit buggy, but may have turned up some interesting message passing behavior
in the inspiral search code on the slaves. A problematic Barrier in the
wrapperAPI was replace when it was discovered that sending large data sets
in non-blocking sends was actually using a blocking send behind the scene.

A problem has suddenly appeared in which the frameAPI and the dataConditonAPI
crash while connected through a socket communication. This is thought to
be due to an incompatibility in the objectSpace socket library on the sun
and on linux which as of this week are compiled differently while we sorted
out the problems with the E2E code using GCC 2.95.3.
 

The controlMonitorAPI now has support for monitoring of the tape writing
scripts without requiring a password. However, the password is however
required still to control the script, such as stopping the tape writer.
 

Hardware Systems (Anderson)

The LDAS Engineering run Beowulf at LHO is fully installed and undergoing
final configuration. The LLO system is currently being installed.

A new 19" equipment rack was installed for the ldas-test system and the
two T3 RAID boxes for that system moved into the new rack to enable better
air flow.

Extra network switches have been identified and ordered to support the
LDAS bootcamp at Caltech next week.

Research into the proper environmental controls for the LDAS computer
facilities has been carried out and is now in the hands of the site
managers.

A new Sun Solaris LDAS test box has been established for testing new
pre-release versions of LDAS software. Currently under investigation
is upgrading to a new version of the the gcc compiler.

The first T3 disk has failed at LHO, but being a RAID system this initial
failure did not result in any system downtime. However, there was an
unexplained system outage when the failed drive was physically removed
that needs further investigation.

Network security has been increased on most of the LDAS Sun machines
by removing a few more unused services.
 

Data Analysis Activities
 

* Data analysis: Andrea Vicere': I worked with Sanjeev on network analysis. I spent two days re-doing the computations in his paper on CB analysis with a network of detectors, in order to figure out all the details. There are several interesting things I was able finally to grasp. The method he proposes for network analysis requires that the individual instruments adopt a "common" template bank, placing the templates according to the requirements of network analysis in the space {\xi, \theta, \phi} where \xi specifies the chirp characteristics and \theta,\phi the direction of the source.
This can be done either collecting all the data in a single center and producing the template outputs for each of them, or asking each detector to produce the outputs of the template analysis for specified values in the {\xi} subspace and then combine.
The second is unrealistic because: If the need of exchanging, for each possible arrival time, all the template outputs! The first strategy is feasible from the point of view of the band, as discussed in February. Given that this is the optimal strategy, the question is what I lose if I go for a suboptimal strategy in which the detectors exchange only candidate above a certain threshold. This is tricky in network analysis, because of the effect of the antenna patterns a network "event" is built using the direction in the sky and the outputs of both the "in-phase" and "in-quadrature" filters from each detector. "event" can be small on a detector, but when summed coherently with the others can go above the network threshold: therefore the threshold on individual detectors are to be lowered, and I figuring out how much. Further, the way in which "cuts" on the analysis, done in individual detectors, propagate on the detection probability of the network is not trivial, and must be evaluated: I am working on this analytically now, and I shall probably have to do some simple Monte Carlo test.
 

General Computing (Wallace)

MIT:
-Configuring a IDE raid array on the Solaris system.
-Preparing to attend the LDAS boot-camp.
-Put in a order for the 15 PC units needed for LDAS.
-Looking at the RRDtool to be used with MRTG.

Livingston:
(Tom)
-We have received three Sun Blade 100s, which we are setting up in
the Computer User's Room.
-Along with the Blade 100s, we are preparing for summer students.
-We have requested an additional T1 line from LSU, and are looking
in to the details.
-We have received an additional Dell laptop.

Hanford:
Nothing to report at this time.

CIT:
(Lisa)
-Returned from Hanford where I was giving Greg Mendell a hand.
-Working on trying to get the modem pool ISDN lines back up.  I'm certain the
problem is with the line itself.  I am working with the Caltech phone office to
resolve the problem.
-Starting to learn about epics.
-Spending some time helping Michael get familiar with various items.

(Mike)
-Performed 6 full software installs on desktops
-Loaded a laptop with all software for loaner purposes.
-Rebuilt two desktops that had hardware problems.
-Loaded additional software for additional clients.
-Setup a computer for a student in number 35WB
-Doing some checking on Microsoft XP operating system.
Just as a note that there may be some problems with WIN2K patch level 2
and Autocad.

(Barbara)
- Installed updates to the LDAS equipment web forms including improved
navigation, new security features, and ad-hoc reporting.
- Imported revised PSL data into the costbook.
- Made the Costbook Resource reports selectable by WBS number or System.
- Began efforts on printed costbook reports.
- Made several web changes for LSC, SURF projects, conferences, etc.
- Working on 40meter things (epics, shared disks, printer).

(Sam)
-Worked on updating some documentation.
-Worked on a couple of PC's including a laptop that
is giving us a number of problems.

(Larry)
-Resolved a couple of calendar issues. Mainly, just needed to update/fix
some of the scripts used for the WEB calendar generation.
-Configured and debugged a FORE 2810 network switch that will be put on a
single mode fiber. So far the testing has worked out so it should be installed
at location for more testing today.
-Worked a number of PC issues. As a note here we would appreciate it if those
who borrow the laptops would inform us if they have a problem with them so we
can resolve the issue in a timely manner(hopefully before they are loaned
out again). Also, we do not support LINUX on the laptops nor any other special
configurations.
-Worked on a number of procurements and worked with different people concerning
equipment configurations and quotes. Gradually, working my way out of the
procurement business. Some people are now being assisted by Rita with their
purchases and Bill Tyler has also been helping out.
-Ordered a few computers and memory for the 40M. So far the memory has arrived
and the computers should show up in a couple of weeks.
-Working on updating some of the GC documentation.
--
 
 


LIGO II/Advanced R&D (Sanders)


From Peter King:
 

40m Lab & LASTI
The 40m Lab pre-modecleaner was fabbed. The laser has been
installed on the optical table. The water cooling has been plumbed in.
 

Advanced LIGO PSL
The VME cards for the PSL were ordered. Delivery is expected
around mid-July.
 

On the 200-W laser development front, LZH have apparently sketched out a
draft design for a rod-based power amplifier.
 

From Janeen Romie:
New osems for 40m, LASTI, PNI etc.: I should have the new
rectangular connectors ready by Friday. Pal Pilot found the lost 100
connectors and sent them to us.
 

Advanced LIGO: Helena and I are working with Thomas Frey on schedule and
cost data for Advanced LIGO.
 

From Jay Heefner:
LASTI
=========================
- Jay and Dave will be going to MIT in late June to install and test the DAQ,
EPICS and suspension controls for LASTI.
 

From Rich Abbott:
2. The capacitance position sensors are finished with the specification phase and I am about to place an order for a first article. Delivery of first system is scheduled for the end of July. Additional systems can be delivered 12 weeks ARO.
3. Rich is looking at ADC requirements for the capacitance position sensors which appear to fit well with the proposed advanced LIGO ADC proposal that Jay and Rolf are putting together.

From: Helena Armandula <ahelena@ligo.caltech.edu>

Silicate bonding:

Performed a quick test on a sodium silicate bond made between a !/2" flat fused silica substrate and a 1/2" sapphire substrate that was flat only on 80% of the surface.
This bond showed prominent voids around the edges because the contact area was around 80% of the surface. However, it has been loaded with ~37.5 lb for the last 6 days.

Received the reworked 1/2" sapphire substrates.

From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>

Florian
Diagonalization exercises.
 

Alessandro
Ultra sound cutting of joints tests at Faimond advancing.
Designing mini-GASFS for Newtonian noise vertical accelerometer
prototype.
 

Riccardo
Ordered sapphire machining from Sonic mill.
Making proper ballast weights for IP.
 

Kimio
Providing commercial vacuum feedthrough.
 

Riccardo, Yukioshi, Yukiko
Replaced magnets in actuator, reduced strength by a factor of 28 (the
remaining factor of 3 will come from electronics gain reduction), but
obtained different saturation and a 0.5%/mm gradient,  re-shimmed yoke,
brought back gradient below 0.25%/cm.
Rest of gain reduction (another factor of 3-5) to be obtained reducing
electrical gain and possibly rolling off gain above 3 Hz.  Electronics
and re-injected actuator noise now both below IP performance (below
10-11 at 1 Hz). Strength still sufficient to damp Olympia earthquake.
Reduced Q-factor of recoil mass from 3000 to 10.  All suspensions now
properly damped.
 

Yukioshi, Yukiko
Small cabling.
 

Akiteru, (Virginio, Roberto)
DSP ADC DAC operating.  Problems were misplaced pull-up resistor in
backplane and missing driving data file.  Now compiling filters
correctly.  Preparing to drive second ADC and DAC from DSP for driving
IP and suspensions at same time.
 

Szabi
Found some stepping motor drivers mis assembled, driver burned by wrong
voltages, replaced them and operating IP positioning stepping motor
drivers.
 


For additional information about this report, contact sanders@ligo.caltech.edu