|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The LIGO Executive Committee Agenda for Monday June 4, 2001 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
Special Items: Joy Fan update, PAC meeting
no report
WBS 1.2 LIGO Operations--Administration
A site teleconference was held on Thursday, May 31, 2001. The following issues were discussed:
From: Ed Chargois <chargois_e@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .
ACCOMPLISHMENTS
| Packages | Faxes | |
| In | 33 | 24 |
| Out | 11 | 23 |
Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS PAYABLE HISTORY DATA.
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
From: irena@ligo.caltech.edu (Irena Petrac)
Support (Wood)
Not feeling well.
Graphic provided by C. Akutagawa.
Irene Baldon
Progress Period from 05.25 to 05.31
Accomplishments:
WBS 1.4.1.2 Project Controls (LIGO Construction)
David Shoemaker has provided a final draft of the Advanced R&D Annual Report. Elizabeth Wood is currently entering the report into FastLane for transmittal to the NSF. She is going to need some additional help where information is incomplete, e.g., certain publications that have not been submitted to the LIGO DCC.
We held a meeting of the LIGO Change Control Board, Tuesday,
May 29, 2001. The following Change Request
was approved. Minutes have been prepapred and are being distributed
(LIGO-M010167-00-P).
| CR-010005 | WBS 1.1.4 | OSB East Building at Hanford | O. Matherny |
We held a Technical Review Board (TRB) on May 18th to discuss design and placement aspects of this building. Minutes of the TRB are still being prepared.
Press for the latest Contingency Needs Projection.
From: Kris Duncan <kris@ligo.caltech.edu>
From: Ed Jasnow <jasnow@ligo.caltech.edu>
Sanders, Scislowicz, Zydowicz and Tyler conducted an annual safety audit
at LLO with G. Stapfer and J. Kern.
Two items on the audit agenda were of particular importance to LIGO:
no report received
The major focus of activity at LLO this week has been on the inspection and repair of the air handlers. Two of the fan units supporting the LVEA were found to have failed catastrophically resulting in their motor shafts being broken. A fan unit supplying the labs also is noisy and the bearings are suspect. These conditions probably resulted from long term wear of the shaft bearings that support the variable pitch fans. We believe the severe wear was due to inadequate maintenance lubrication of the fan bearings and overloading of the actuators which control the fan pitch. Investigation of the failed units has caused us to suspect that lubrication of the remaining operating motor units on the site may also have been improper and that other motors may now be on the verge of failure. To remedy this, we have begun a complete inspection of all of the air handlers, replacement of the failed motors with new motors, and motor rebuilds and other preventive maintenance on the remaining operating motors. The failure of these systems comes at a particularly bad time as it coincides with the planned service of the interferometer to replace OSEM's and plans to remedy some workmanship problems that are apparent with some of the SOS assemblies. To accomplish this work, we need to have a functioning and reliable clean air supply in the LVEA and the optics lab and vacuum prep lab so that the optics will not be contaminated. We have therefore had to defer the SOS work planned for this week and instead have placed the labs in a "buttoned up" state to minimize the impact of the air handlers being taken down for service. A service representative from the fan company is now on site, along with a team of riggers, members of the LLO staff, and Otto Matherny who has come from LHO to observe. Our work plan is the following:
Operators continuing cleaning efforts at
the end stations in preparation for a future vent to do in vacuum re-work
. Tooling has been staged in the LVEA for the possibility of removing the
spool pieces on Friday. Precautions have been taken in the labs to protect
in vacuum equipment during the building fan repair.
Optics and Installation: Ham 2's North door was removed last Friday and MC2 examined. We took it from the HAM table and into the vacuum prep lab. Visual inspection made and no grounding evident but we did find something interesting. The suspension wires were not trimmed, and one is 7-1/2" long.It is possible for the untrimmed wire to dangle into the tower and contact a suspension wire. Our examination of the tower is on hold, because of the air handler fan problem. When we learned on Tuesday that the lab fans were having problems we moved MC2 into the bake oven and roughed it down in order to keep it clean. The labs were secured yesterday, making sure everything was bagged and stored properly because airflow will be disrupted for a while during lab fan replacement. We're ready to go with OSEM replacement in the LVEA as soon as the air handlers are back on-line.
General Computing: We have received three Sun Blade 100s, which
we are setting up in the Computer User's Room. We have requested an additional
T1 line from LSU, and are looking in to the details.
| Installation&
Commissioning:
Livingston |
Other Science/EngineeringActivities:
Issues/Concerns |
See also the Installation web page
Betsy, Rick and Dick adjusted the EOMs to minimize the rf AM on the light entering HAM7. The residual AM is about 1e-5.
An accidental cycling of the power on the 10 W laser caused a fault with its internal shutter. Mark Guenther and Rick spent some time debugging it, but it basically went away without any clear cause. We will continue to monitor it.
Mark Barton is working on the suspension tuning procedure for the small optics using the 4 km MC2.
Gerardo and Hugh have been making steady progress getting the optical levers installed, pointed and enclosed.
The problems with the HVAC fans have stopped further installation activities.
Guido Mueller 6/14-19 (definite)
Stacy Wise 6/14-19 (definite) (a new grad student at UF)
Michael Hannawald 6/14-26 (definite) (postdoc candidate for IOO)
Malik Rakhmanov TBD
An specialized laminar flow maintenance firm will replace the light cover, seal it accordingly, replace the ballast (that was the defective part), replace the lights and certify the laminar flow bench as a Class 100.
Erika D'Ambrosio
On "Flat Top Mode".
I found out the recycling mirror must be carefully designed when the
flat beam (whose shape minimizes the thermoelastic noise) is excited inside
the arms. Since the superposition of Gaussian modes that the flat beam
consists of, will not be a superposition of Gaussian modes after the interaction
with the ITM mirror, no simple calculation applies other than evaluating
the result of that interation numerically. I am currently writing a piece
of code assuming a flat surface for the AR-side. During the holiday weekend
I documented myself with some papers on reshaped mirrors but coupled cavities
were never mentioned. I found interesting experimental results and useful
mathematical considerations.
On diffractional losses
I checked on the power gains obtained by the FFT-code when the diameter
of the ETM mirror (where the spot size is planned to be pretty large) is
shortened. I solved the problem in that parameter for the diffractional
loss associated to the mirror and the numerical curve is ~2.5 times the
curve generated by using the clipped light approximation.
Five Freq Ref boards built and ready for test
Remaining boards (two sets of PMC & Freq Stab Servo) kitted
Some parts shortages exist -- work is in process to resolve the matter
We are short RFPD(2)/FreqServo(1)/VCO(2) PC boards -- We will work to resolve the situation.
Ben Abbott
I still await testing of my intensity servo DC photodiode board while
integrated with Rick's servo.
LSC photodetectors: Tested and tuned 3 of 4 new photodetectors sent by Rich Abbott on their way to LHO for the 4k IFO. They're now compensated to give less than 1 degree pk-pk change in RF response phase from <1 mW to over 150 mW detected power. Transimpedance gains are nominal (around 4 kOhm), but two have slightly higher RF noise than we are used to (one is slightly over specification). The fourth PD (a refurbished one with a "checkered history" as they say) mostly works but seems to have a subtle problem with its bias control. We are investigating.
Photon calibrators: consulted with Rich Mittleman and Peter Fritschel, who now have a revised quote for 1047 nm photon calibrator lasers. By delaying purchase until now we can get three times the power (1.5W vs. 0.5W) at one third the price ($2k/unit vs. $6k/unit).
Mohana received the boards for the DC readout module and will begin testing.
Flavio is putting together details regarding the timing system tests to diagnose a potential error in design involving the ICS110B ADCs.
Jay Heefner
All boards and components for the upgrade of the LHO 2K and LLO 4K
Digital Suspensions are being fabbed or ordered. Cross connect harnesses
will be started and we should be ready to convert by early September.
It has been decided that for the time being the DAQ coil readouts for the LHO 4K Digital Suspensions will be DC coupled. The cross connects and connections to the DAQ system are designed and should be installed next week. Once we get some operational experience with the system we can design a DAQ interface that has more optimal whitening.
All custom electronics for the 4K ASC has been built and tested. The cross connects and rack wiring are installed and ready for test. Testing of the system will occur as time permits over the next month.
New DAQ controller is having problems coexisting with the test point manager (TPM) at LHO. Controller sending timing interrupts to TPM kills it; TPM getting timing interrupts from GPS module results in controller GPS module blacking out. Had hopes of testing/troubleshooting offline here at Caltech until I found that our new GPS modules don't work.
Sander Liu
Delivered 32 850Hz filter modules to 40m. Ordered 25 LEMO version DAQ
antialiasing boards as well as 10 front panels. Obtained a quote for 240
850Hz filter modules from Frequency Devices.
This week we have continued trying to improve the hold time of our
arm-cavity lock. We have been focusing mainly on studying lock
acquisition in our mode cleaner using actuation only on one of the
mirrors. This system is very similar to our arm cavities, but
its lower
finesse and lower mirror mass make lock acquisition much easier.
By
studying what works and what doesn't for the mode cleaner, we hope
to
gain a better understanding of the lock acquisition and hold process
in
a suspended cavity and eventually apply that knowledge to the arm
cavities.
So far we have observed three things:
1) We can reproduce the arm cavity's 10 to 20ms transient locks in the
mode cleaner.
2) We can extend the mode cleaner's lock to hold times of an hour or
more, with feedback going only to the mirror. The difference between
a
stable lock and a transient lock appears to be in the amount of
low-frequency gain.
3) The 28Hz peak, mentioned in last week's report, appears to be the
dominant noise source when the mode cleaner is locked using only
mirror-path feedback.
We are currently working to improve the performance of our servo, as
well as reducing the 28Hz noise peak.
LASTI (MacInnis, Gray, Laliberty, Miller, Radkins, Shoemaker, Rollins,
Mittleman,
Harry, Ottaway, Mason, Mason, Zucker)
Hugh Radkins and Corey Gray have arrived from LHO and we are in an all
out effort to complete the final HAM and BSC seismic installation.
Both
of these chambers will not include a stack, they will be built up in
preparation for the active seismic isolation prototypes.
BSC Chamber
The Dome was removed using the clean room skirts. Dome covers were
installed and the cartridge clean room placed over the opening. All
parts, hardware and fixturing were gathered and cleaned. The BSC piers
have been leveled and aligned.
HAM Chamber
The HAM door was removed. All parts, hardware and fixturing have been
prepared. The piers, scissor table adapters, and air bearing adapters
have been aligned and leveled previously. We have opened the support
tube blankoff plates in preparation for installing the support tubes.
Simulation and Modeling (Bhawal)
LIGO I action items
-------------------
Based on the meeting on 22 May, Hiro has revised the e2e action items.
That
now includes the action items we, simulation group, are going to
take, and the actions we are going to ask detector group people to
take. The revised note will be uploaded to e2e home page, and will
be
sent to detector people who are going to help us by providing
necessary information.
Weekly Physics meeting
----------------------
In this week's Physics meeting Alain Weinstein talked about simulation
activities for Advanced LIGO that he and his student Michel are pursuing
with a model of 40 m IFO. The minutes ares available at
http://www.ligo.caltech.edu/~e2e
Realistic servo & Alignment sensing and control
-----------------------------------------------
Among the majors issued discussed in the kickoff meeting on 22nd were
(1) the implementation of more realistic servos in the simulation so
that it can be used to study the servo characteristics and noise
propagation. and (2) the implementation of ASC.
After the kickoff meeting, Luca Matone volunteered to work on the LSC
part and Andrea Vicere on the ASC part. To get this activity start
rolling, there was a meeting held on May 30th, having Nergis as the
detector expert/advisor. People attended were Luca, Andrea, Matt,
Nergis, Hiro and Biplab.
The following are the summary of the discussions:
(1) Time domain simulation of the servo noise will be necessary
because of the complexity of the system, even though the lowest order
estimation can be done (semi-)analytically in the frequency domain.
(2) There are many uncertainties of noise sources, so the model will
use the measured spectrum as the noise source at an appropriate point
and refine it when things change (reduced by hardware refinement,
understanding the physics origin, etc).
(3) The simplest model of LSC is: detector -> mixing -> whitening ->
AtoD
-> [whatever the digital system ] -> DtoA -> de-whitening -> actuation.
At each stage, noise (from measured spectrum) could be added.
(4) the triangular mode cleaner simulation will be necessary to
simulation the amplitude noise induced by the length fluctuation.
(5) First will be the implementation of the simplest LSC model ( (3)
above ) with a very simplified (with a parameterized frequency noise)
laser coming into COC.
(6) Luca will go to Hanford to gather necessary information with the
help of Nergis.
(7) Part of the ASC model will be a copy of the same building blocks
developed for LSC, although N time more circuit lines.
(8) ASC is a moving target now, there are some things that are hard
to understand.
Maybe simulation can help to understand them.
(9) Andrea will first understand the ASC design. The first
implementation can adopt the simple method used in the current LSC
model - no digitization etc, and the complex structure can be
embedded later on top of it.
Dual recycling code
-------------------
Malik has provided us a formula of the dual recycling cavity field
evolution. He sent us a matlab code as well. The formula will be
validated by comparing the matlab code with a simulation using e2e
primitives. This code is pure adiabatic approximation. We need to
implement a linear interpolation, which is a very complicated
calculation. In order to use this result in the e2e simulation, we
need to write a C++ code implementing this formula. The date for this
implementation is not scheduled yet.
Frame interface
---------------
(Andrea) The frame-E2E interface: I have almost finished it and hope
to
test it extensively the next week.
E2E at CACR
-----------
(Hiro) Worked with Ed and Sharon of CACR trying to port the simulation
code to CACR HP clusters. After trying 3 compilers with various options
and identifying various bugs ( gcc 2.95.2 for HP gives NaN when a complex
number is divided by a double less than 1), now aCC (HP native compiler)
seems to be the candidate. There are still several things to be solved.
One is the size limit of the library builder. Another is that the compiler
crashes when compiling several of the adlib codes.
When Hiro had a meeting with Sharon about this compiler issue, he
found that it is possible to run a very long jobs, longer than 12
hours, if we ask them to set up.
Alfi
----
(Ed Maros)
1. Reviewed Hiro's ALParser problem of bad directive quote_begin
( result of not having a proper LD_LIBRARY_PATH)
2. Fixed the error message "/ldcg/bin/autoheader: Symbol
`PTHREADS_IN_UNISTD' is not covered by"
3. Added --enable-modeler flag for configure to control if
modeler code is to be build. It is enabled
by default. To disable,
either specify --enable-modeler=no or --disable-modeler.
4. Corrected header Alfi/lmbtb.h to conform to wxWindow'ss
parameters for base class method AddTool.
5. Make sure multiline change is in repository
6. Make sure bundle change is in repository
7. Build and install into Alfi-Dev (v 4.1.1)
8. Change from input port to output port not reflected
immediately.
9. Create dialog prompt box for path resolution.
10. Worked on getting ALParser compilable by aCC on CACR's HP
systems.
(Bruce)
- Finishing work on initial implementation of connection junctions.
- Conducting full tests of connections, ports, and junctions
for
inclusion of the new junction code in next release
of Alfi.
LIGO Data Analysis System
Software Systems (Blackburn)
Having almost recovered from the last MDC, the LDAS group is now busily
preparing for the so called LDAS/LAL/DMT camp that starts next week.
It
is expected that there will be 22 to 24 participants with roughly 2:1
coming for LDAS/LAL vs. DMT.
We have also begun testing upgrades to our basic software development
tools. The two major upgrades are to GNU's GCC 2.95.3 compiler and
to
the new 6.5.2 release of LAM for our MPI functionality. The LAM upgrade
appears to have gone without a hitch. However, the GCC upgrade revealed
some configuration problems for E2E. These have now been resolved and
we standardize on GCC 2.95.3 early next week. This will require a complete
testing of LDAS so we will plan a new release of LDAS after this testing.
This will also have the benefit of capturing all the bug fixes exposed
during the last MDC in a release. Documentation has been updated to
reflect
the new required baseline code.
A minor problem with the new XML C++ parser library was discovered and
fixed this week. Testing of the lightWeightAPI with this new library
is
pretty much complete now and we are comfortable with the Apache based
implementation. However, testing did discover a minor problem with
iterative translation of ilwd -> xml -> ilwd data formats which has
now
been fixed.
The inspiral MDC did not conduct its final "challenge" test during the
scheduled week. In the inspiral upper limits group meeting it was decided
that this should be carried out in roughly two weeks allowing the MDC
to have closure in the minds of all contributors.
We began work on a new "trivial" user interface which allows users to
type in their requested ldasjob commands into a graphical user interface
front end which provide step by step menu options for connecting to
the
different LDAS sites and for entering required information such as
LDAS
user and authentication.
We also began exploring a graphical user interface called XMPI for studying
the coarse behavior of the wrapperAPI jobs on the Beowulf. The code
is a
bit buggy, but may have turned up some interesting message passing
behavior
in the inspiral search code on the slaves. A problematic Barrier in
the
wrapperAPI was replace when it was discovered that sending large data
sets
in non-blocking sends was actually using a blocking send behind the
scene.
A problem has suddenly appeared in which the frameAPI and the dataConditonAPI
crash while connected through a socket communication. This is thought
to
be due to an incompatibility in the objectSpace socket library on the
sun
and on linux which as of this week are compiled differently while we
sorted
out the problems with the E2E code using GCC 2.95.3.
The controlMonitorAPI now has support for monitoring of the tape writing
scripts without requiring a password. However, the password is however
required still to control the script, such as stopping the tape writer.
Hardware Systems (Anderson)
The LDAS Engineering run Beowulf at LHO is fully installed and undergoing
final configuration. The LLO system is currently being installed.
A new 19" equipment rack was installed for the ldas-test system and
the
two T3 RAID boxes for that system moved into the new rack to enable
better
air flow.
Extra network switches have been identified and ordered to support the
LDAS bootcamp at Caltech next week.
Research into the proper environmental controls for the LDAS computer
facilities has been carried out and is now in the hands of the site
managers.
A new Sun Solaris LDAS test box has been established for testing new
pre-release versions of LDAS software. Currently under investigation
is upgrading to a new version of the the gcc compiler.
The first T3 disk has failed at LHO, but being a RAID system this initial
failure did not result in any system downtime. However, there was an
unexplained system outage when the failed drive was physically removed
that needs further investigation.
Network security has been increased on most of the LDAS Sun machines
by removing a few more unused services.
Data Analysis Activities
* Data analysis: Andrea Vicere': I worked with Sanjeev on network analysis.
I spent two days re-doing the computations in his paper on CB analysis
with a network of detectors, in order to figure out all the details. There
are several interesting things I was able finally to grasp. The method
he proposes for network analysis requires that the individual instruments
adopt a "common" template bank, placing the templates according to the
requirements of network analysis in the space {\xi, \theta, \phi} where
\xi specifies the chirp characteristics and \theta,\phi the direction of
the source.
This can be done either collecting all the data in a single center
and producing the template outputs for each of them, or asking each detector
to produce the outputs of the template analysis for specified values in
the {\xi} subspace and then combine.
The second is unrealistic because: If the need of exchanging, for each
possible arrival time, all the template outputs! The first strategy is
feasible from the point of view of the band, as discussed in February.
Given that this is the optimal strategy, the question is what I lose if
I go for a suboptimal strategy in which the detectors exchange only candidate
above a certain threshold. This is tricky in network analysis, because
of the effect of the antenna patterns a network "event" is built using
the direction in the sky and the outputs of both the "in-phase" and "in-quadrature"
filters from each detector. "event" can be small on a detector, but when
summed coherently with the others can go above the network threshold: therefore
the threshold on individual detectors are to be lowered, and I figuring
out how much. Further, the way in which "cuts" on the analysis, done in
individual detectors, propagate on the detection probability of the network
is not trivial, and must be evaluated: I am working on this analytically
now, and I shall probably have to do some simple Monte Carlo test.
General Computing (Wallace)
MIT:
-Configuring a IDE raid array on the Solaris system.
-Preparing to attend the LDAS boot-camp.
-Put in a order for the 15 PC units needed for LDAS.
-Looking at the RRDtool to be used with MRTG.
Livingston:
(Tom)
-We have received three Sun Blade 100s, which we are setting up in
the Computer User's Room.
-Along with the Blade 100s, we are preparing for summer students.
-We have requested an additional T1 line from LSU, and are looking
in to the details.
-We have received an additional Dell laptop.
Hanford:
Nothing to report at this time.
CIT:
(Lisa)
-Returned from Hanford where I was giving Greg Mendell a hand.
-Working on trying to get the modem pool ISDN lines back up.
I'm certain the
problem is with the line itself. I am working with the Caltech
phone office to
resolve the problem.
-Starting to learn about epics.
-Spending some time helping Michael get familiar with various items.
(Mike)
-Performed 6 full software installs on desktops
-Loaded a laptop with all software for loaner purposes.
-Rebuilt two desktops that had hardware problems.
-Loaded additional software for additional clients.
-Setup a computer for a student in number 35WB
-Doing some checking on Microsoft XP operating system.
Just as a note that there may be some problems with WIN2K patch level
2
and Autocad.
(Barbara)
- Installed updates to the LDAS equipment web forms including improved
navigation, new security features, and ad-hoc reporting.
- Imported revised PSL data into the costbook.
- Made the Costbook Resource reports selectable by WBS number or System.
- Began efforts on printed costbook reports.
- Made several web changes for LSC, SURF projects, conferences, etc.
- Working on 40meter things (epics, shared disks, printer).
(Sam)
-Worked on updating some documentation.
-Worked on a couple of PC's including a laptop that
is giving us a number of problems.
(Larry)
-Resolved a couple of calendar issues. Mainly, just needed to update/fix
some of the scripts used for the WEB calendar generation.
-Configured and debugged a FORE 2810 network switch that will be put
on a
single mode fiber. So far the testing has worked out so it should be
installed
at location for more testing today.
-Worked a number of PC issues. As a note here we would appreciate it
if those
who borrow the laptops would inform us if they have a problem with
them so we
can resolve the issue in a timely manner(hopefully before they are
loaned
out again). Also, we do not support LINUX on the laptops nor any other
special
configurations.
-Worked on a number of procurements and worked with different people
concerning
equipment configurations and quotes. Gradually, working my way out
of the
procurement business. Some people are now being assisted by Rita with
their
purchases and Bill Tyler has also been helping out.
-Ordered a few computers and memory for the 40M. So far the memory
has arrived
and the computers should show up in a couple of weeks.
-Working on updating some of the GC documentation.
--
From Peter King:
40m Lab & LASTI
The 40m Lab pre-modecleaner was fabbed. The laser has been
installed on the optical table. The water cooling has been plumbed
in.
Advanced LIGO PSL
The VME cards for the PSL were ordered. Delivery is expected
around mid-July.
On the 200-W laser development front, LZH have apparently sketched out
a
draft design for a rod-based power amplifier.
From Janeen Romie:
New osems for 40m, LASTI, PNI etc.: I should have the new
rectangular connectors ready by Friday. Pal Pilot found the lost 100
connectors and sent them to us.
Advanced LIGO: Helena and I are working with Thomas Frey on schedule
and
cost data for Advanced LIGO.
From Jay Heefner:
LASTI
=========================
- Jay and Dave will be going to MIT in late June to install and test
the DAQ,
EPICS and suspension controls for LASTI.
From Rich Abbott:
2. The capacitance position sensors are finished with the specification
phase and I am about to place an order for a first article. Delivery of
first system is scheduled for the end of July. Additional systems can be
delivered 12 weeks ARO.
3. Rich is looking at ADC requirements for the capacitance position
sensors which appear to fit well with the proposed advanced LIGO ADC proposal
that Jay and Rolf are putting together.
From: Helena Armandula <ahelena@ligo.caltech.edu>
Silicate bonding:
Performed a quick test on a sodium silicate bond made between a !/2"
flat fused silica substrate and a 1/2" sapphire substrate that was flat
only on 80% of the surface.
This bond showed prominent voids around the edges because the contact
area was around 80% of the surface. However, it has been loaded with ~37.5
lb for the last 6 days.
Received the reworked 1/2" sapphire substrates.
From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>
Florian
Diagonalization exercises.
Alessandro
Ultra sound cutting of joints tests at Faimond advancing.
Designing mini-GASFS for Newtonian noise vertical accelerometer
prototype.
Riccardo
Ordered sapphire machining from Sonic mill.
Making proper ballast weights for IP.
Kimio
Providing commercial vacuum feedthrough.
Riccardo, Yukioshi, Yukiko
Replaced magnets in actuator, reduced strength by a factor of 28 (the
remaining factor of 3 will come from electronics gain reduction), but
obtained different saturation and a 0.5%/mm gradient, re-shimmed
yoke,
brought back gradient below 0.25%/cm.
Rest of gain reduction (another factor of 3-5) to be obtained reducing
electrical gain and possibly rolling off gain above 3 Hz. Electronics
and re-injected actuator noise now both below IP performance (below
10-11 at 1 Hz). Strength still sufficient to damp Olympia earthquake.
Reduced Q-factor of recoil mass from 3000 to 10. All suspensions
now
properly damped.
Yukioshi, Yukiko
Small cabling.
Akiteru, (Virginio, Roberto)
DSP ADC DAC operating. Problems were misplaced pull-up resistor
in
backplane and missing driving data file. Now compiling filters
correctly. Preparing to drive second ADC and DAC from DSP for
driving
IP and suspensions at same time.
Szabi
Found some stepping motor drivers mis assembled, driver burned by wrong
voltages, replaced them and operating IP positioning stepping motor
drivers.
For additional information about this report, contact sanders@ligo.caltech.edu