Weekly Report for Week Ending May 10, 2001


 Exec. Comm. Agenda
Highlights
LSC
Administration
Hanford Observatory
Livingston Observatory
MIT
Caltech
Detector
40 Meter
TNI
LASTI
Data Analysis
LIGO II/Adv. R&D
Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  May 14, 2001 will be:

 (Meeting time: 10:30 am Pacific Time)

Open meeting 10:30 - 11:30

  1. Announcements
  2. LSC Issues (Weiss)
  3. Comments on Weekly Report
  4. WBS 1 LIGO I Construction (Lindquist)
  5. WBS 2 LIGO Lab Operations
  6. WBS 3 and 4  Advanced R&D and LIGO II (Sanders)
Executive Committee only 11:30 - noon   Topics:
 

Special Items:   How are the MDC and E4 going?


Special Announcements:


Weekly Report Highlights

The commissioning of the LHO 4 km interferometer began this period.

 the very  first search for |binary inspiral waveforms in LIGO data using LDAS


LSC Issues (Weiss)


no report


LIGO I Construction/LIGO Laboratory Administration (Lindquist)


no report received


LIGO Hanford Observatory (LHO) Operations (Raab)


General Items:
--------------
(F. Raab)
 

Installation/Rework is the main activity, but some 2-km IFO commissioning is ongoing.
Congratulations to Bill Butler for passing his oral candidacy exam at U.Rochester. We have begun weekly seminars to get people's heads tuned to astrophysics analyses.
 

4k installation and 2k retrofits and earthquake recovery
--------------------------------------------------------
(D. Cook & Co.)
 

The 4k installation still needs the ETMy optic, baffle and telescope
installed. This is being staged this week. The actual installation  may
start next week.
 

In general the 2k re-alignment is going well again. All the 2k optics are
installed, have their new OSEMs and safety stops in place.  All OSEM values
will be measured at the satellite boxes and recorded upon final alignment.
A few beam dumps need to be replacer, exit chamber tasks and optic cleaning
to follow. We hoped to finish up all of the core optics and be well into
the Mode Cleaner by Friday. We should be replacing doors and closing up by
the end of next week and starting to pump down.
 
Some 2k alignment details:  Installation tooling remains in BSC8 and will be removed today
and wrapped up for transporting to theY- end station.
 

ITMx-2k:  Re-aligned successfully from the WA-1A spool using the IAS total
station. Alignment was ~150 urads in both pitch and yaw from the last
alignment which was set from WBE-3A1 spool. The OSEM 50% open light settings were tweaked slightly during this alignment. PAMs were adjusted for final alignment <5 uradians both pitch and yaw. OSEM values taken at the satellite boxes at the time of the
final alignment will be posted in the e-log. The COS laser autocollimator replaced the total station and was aligned to the ITMx-2k. The beam was steered through the APS telescope and optics, through the Faraday isolator and out the APS viewport, by adjusting
the PAMs and OSEMs on the FMx-2k.
 

ITMy-2k: The optic was reprocessed and re hung to the proper balance angle
and was re-install Tuesday AM. Modifications to IAS tripod were needed to duplicate the  second setup in the Y arm WA-1B spool. The optic was installed and aligned to <5uradians using the IAS equipment and the OSEMs 50% open light settings maintained
to during the alignment. The second COS laser autocollimator replaced the total station
and was aligned to the ITMy-2k. The COS beam was then aligned to a target on MMT3 by steering
the FMy.
 

BS-2k: The BS-2k was aligned to steer the Y-Arm COS alignment beam
through the Faraday isolator and out through the APS port on HAM 10.
We then used both COS laser ACs to send beams simultaneously through the
APS port from each arm and checked the coincidence. The X-arm reticle pattern was
~50 uRadians off center in yaw. The FMx was tweaked to correct the alignment.
 

RM-2k: The elliptical baffle was reinstalled along with a set of new safety
stops. The optic was aligned to the Y-arm COS beam.
 

X-arm PO telescope: The X-arm PO mirror was adjusted to steer the X-arm COS
alignment laser through the X-PO telescope, its optics and out the viewport on HAM 9.
 

Y-arm PO telescope: The Y-arm PO mirror was adjusted to steer the Y-arm COS alignment laser
through the X-PO telescope, its optics and out the viewport on HAM 10.
 

BS PO telescope: The BS PO mirror was adjusted to steer the COS alignment laser through
the X-PO telescope, its optics and out the viewport on HAM 10.
 

Seismic Systems
---------------------
(H.Radkins, G.Moreno, M.Guenther, C.Gray)
 

Fine Actuators
All ETM optical tables are being held in place by the PZT actuators except
at the Ymid; we will wait until there is a beam down the arm to insure the
alignment is not disturbed by installation and to provide before and after
noise measurements.  The mid stations had been on the PZTs but were taken
off to allow transfer to CDS power.
 

Coarse Actuation System
The portable CAS assembly is being completed and we will test on the Yend
SEI prior to ETM installation.
 

LSC
-----
(H.Radkins, F.Raab, R.Savage, D.Barker)
 

Common Mode Tides
The common mode tidal sequencer is currently running on both LHO PSLs.  The
prediction parameter values were fine tuned by fjr using the E2 carm and
darm control signals.  The reference cavity parameters have been estimated
and the current version of the sequencer only shifts in time and transforms
the strain to strian/temp for input to the reference cavity temperature
control.  The next version will apply the reference cavity inverse filter
to the data; this should track the tide better.  Without the modecleaner or
a full arm, there isn't a good measure of the results yet.  We hope to
start fine tuning that soon.  Thanks to Dave Barker for lots of help with
state sequencers and C code.
 

ISC
-----
(H.Radkins, G.Moreno)
 

Lots of initial alignment activity in the x-mid and corner station for
realignment of the 2k core optics.
 

ASC
------
(H.Radkins, D.Cook, G.Moreno, C.Gray)
Optical Levers
 

Finally the 4k MMT3 Optical Lever is online and laser safe too!  The other
levers are all functioning but don't have light pipes yet for safety.
These should fall shortly.
 

FACILITY
-----------
(F.Raab, H.Radkins, A.Rohay, S.Marka)
Eucon Mining operation
 

Rohay (PNNL) and Radkins collected a days worth of seismometer data with
base station and roving units to measure the mining operation effects at
LHO.  Rohay is still working up the data but preliminary analysis suggests
the current location and the equipment used will not be a problem for LHO.
Thanks to Szabi for providing data from the STS-2.
 

2k-Input Optics work
--------------------------
(Corey Gray, Betsy Weaver)
 

Assisting w/ the COS alignment has been the main focus this week.
 

Currently on the PSL table, we have 3 optical components which will need to be swapped out at some point:  a polarizer and the two PZT periscope mirrors.  The polarizer was sent out to Karl Lambrecht to be tested (it was thought to be defective); it has been returned and has been given an "optical clean bill of health" [it was noticed that the casing for the polarizer might have been damaged, but it didn't affect the polarizer].  We will swap out these components when time allows, all the while maintaining alignment of the input beam to HAM7.
 

Other IO activities have been "back ground activities" (ie. installing optical lever steering mirrors).  We are awaiting hand off from the COS group to finish the IO alignment & installation.
 

ISC Table work
--------------------------
(Corey Gray, Betsy Weaver)
 

Installation and Alignment of optics on ISCT4 started this week.


LIGO Livingston Observatory (LLO) Operations (Coles)


This week was spent primarily preparing for the E4 run. Operator training for running in a recombined state began Monday evening and has continued each evening this week. We are unable to lock the interferometer during the day because of construction noise. All required PEM channels have been checked out and are operational.
 

Staging of clean rooms and preparation of clean tools is now largely complete in anticipation of venting the interferometer following E4.
 

We experienced a hacker attack last week and are now revisiting the issue of site security. Damage is largely repaired. All user passwords have been changed at LLO. Infrequent users will need to contact Tom Evans to obtain a new password.
 
 


Detector/Technical Support (Whitcomb, Coyne)


 
Installation& Commissioning:
Hanford
Livingston
Other Science/EngineeringActivities:
Design/Analysis/Fab
Issues/Concerns
See also the Installation web page

1.1 LHO INSTALLATION & COMMISSIONING

2km Earthquake repairs

Doug Cook, Betsy Weaver, Corey Gray, Mike Smith, Ken Mailand, Mark Lubinski, Hugh Radkins, Gerado Moreno, John Worden, Kyle Ryan, Josh Myers, Richard McCarthy, etc.

The 4watt COS autocollimator was set up in the spool piece near the x-arm and was aligned by autocollimating from ITMx. A Sony video camera viewed the reticle pattern projected through the APS port window at HAM10. The FMx mirror was adjusted to center the reticle pattern through the APS optical train, which is limited by the aperture of the Faraday isolator. A second Sony video camera viewed the reticle pattern projected through the ITMx PO port output window at HAM9. The ITMx PO mirror was adjusted so that the projected reticle pattern was centered on the ITMx PO optical train aperture. Two sets of mounting structures and laser adapters are being fabricated, and two zoom lenses are being ordered for two new COS autocollimators. Two tall tripods will be ordered for viewing the output beams with the COS autocollimator at LLO during the vertex re-alignment.

ITMY came out of the bake oven and was resuspended and reinstalled in BSC8.  It was realigned using the laser autocollimator from the spool location near the Y arm cryopump.  The COS autocollimator was moved ito the Y arm spool and used to align the FMY to point the beam at MMT3.  This was followed by alignment of the BS and then the RM.

We have had two 2km suspension controller failures, ITMY and BS.  We continue to limp along by moving optics to different controllers, and the failed units are being repaired.

4-k Commissioning

Stan reporting:
The commissioning of the LHO 4 km interferometer began this period.  The EPICS system for locking the modecleaner was installed and checked out.  The modecleaner was locked initially using the 2 km servo amp.  Lock acquires quickly and looks stable.

This configuration was used to get a first look at the PSL fequency noise by analysing the feedback signal to lock it to the modecleaner.  Qualitatively it looks similar to the noise from the 2 km laser; given the high acoustic noise due to cleanroom, pumps, etc, this may be a good sign.

Testing of the 4 km servo amp started, and a couple of quick mods were identified.  The board is expected back tomorrow for continued testing.

Cameras and illuminators installed and working.
 

1.2LLO INSTALLATION & COMMISSIONING

Commissioning

Rai Weiss, et al.
The major activities have been preparation for the E4 run and preparations for opening the system after the E4.

The interferometer will be operated as a recombined Fabry-Perot Michelson without recycling during the E4 run. The system remains in lock for about an hour before dropping out due to tidal strain and is reacquired in minutes.

Attempts to run the full recycled system may be resumed after the E4 run and before opening the system. There is some evidence that the compromise in dynamic range due to the non functioning coils on both end test masses and the relatively large seismic noise in the critical 1 to 3 Hz band at Livingston is the cause of the difficulties in locking the entire system. One of the things that will be fixed when the system is opened are these coils.

Before opening, another attempt will be made to measure the losses in the cavities and to independently establish the length of the two arms using the cavity resonances.

MC2, the curved "distant" mirror in the mode cleaner, is suspected of being badly suspended at Livingston. Pendulum Q measurements of this mirror show non-linear amplitude dependent losses. The mirror is possibly the source of seismically driven excess frequency noise at low frequencies. Diagnostic procedures are currently being tested to establish the state of the suspension when changes are made to it on opening the instrument.

The computer situation has stabilized at Livingston but it is still prudent to work on global security measures and a standardized reliable backup technique.

2.0 Other Engineering and Scientific Activities

2.1 Design/Analysis/Fab

Input Optics Spares

Helena Armandula
While at Stanford, we took the LIGO coated optic from the chamber (where Q measurements were taken), cleaned the optic and shipped it to Caltech.

PSL

Peter King
Lightwave reported that the only thing they noticed amiss about NPRO #170 was that the output power was low and that was because the diode current was set low.  After re-communicating that the problem was not the output power but the frequent frequency glitches they said that they had no way to test this.  I recently received an estimate for #170's repair, which is to replace the pump diode.  The repair would be around $3800-$4000. Still haven't been told about NPRO #259 nor 10-W laser #110.

The relative intensity noise from a standard NPRO laser was compared to that of an "enhanced" NPRO laser.  As I recall the relative intensity noise of the "enhanced" NPRO was quieter by about 10dB above 1kHz.

More testing of the intensity stabilization servo took place.  Some offset problems were encountered with the servo.  Some circuit modifications, mimicking the modecleaner 4kHz pole, were in the process of being carried out.

Lee Cardenas

Rick Karwoski, Paul Russell
This week has been spent hammering down electronics noise and managing DC offsets throughout the servo.  We are achieving -150... -155db relative intensity noise on a regular basis.

Sander Liu
PSL - In the process of repairing  and testing 80 MHz VCOs. Current status on the units are:

1. Serial Number BL2002 is now completely bench tested. It is packaged in VCO hardwares and ready for system test and delivery.

2. S/N BL2003 and BL2004 boards are both partially tested. They are waiting for parts (5V reference diode, AT1 and AT2 attenuators, and power resistors) before we can continue.

LSC

Rich Abbott, Mohana Megeswaran, Flavio Nocera

ASC/LSC/Digital Suspensions

Rolf Bork

Data Acquisition

Rolf Bork

GDS

Daniel Sigg
Thanks to Ed's effort the linux DMT machine at LLO is finally up and running (the installation was held up by a really strange networking problem related the 3810 switches.)

A new 500GB disk system came in which will be shipped to MIT to replace the equipment which was lent by ldas.

The RDS writer setup on decatur had to be reinstalled after the hacker incidence. At the same time the epics control for the rds writer had been added to msrepics and a medm screen was put on the site overview.
 

DMT

John Zweizig
This week I have been putting together a version of the dmt software for use in the E4 run. This includes installing monitors and other software submitted by LSC members, fixing up some dmt infrastructure code and setting up configuration files.

I have also been working with Szabi to recover from the reinstallation of the Delaronde operating system necessitated by the recent hacker attack.
 


40 Meter Interferometer (Weinstein)



 
  • PSL (King):
  • PSL electronics (Karwoski): Sander has repaired and tested the 80 MHz VCO board for the 40m. It has been integrated with the adjoining RF power amp and packaged. It is ready for system test and delivery. Most or all of the OTS and custom electronics is ready; a detailed inventory will be made in the next few days.
  • Vacuum envelope and hardware (Larry Jones):
  • Vacuum control system (Ugolini, Ben Abbott, Vass):
  • Optical layout (Mike Smith): A new optical layout of the 40 meter IFO with the SRM moved to its final configuration was completed. Position and angle sensing photodiodes and a Tropel frequency analyzer were added to the PSL output beam. The GW signal detection system was moved to accomodate the input optics additions. Latest composite drawing here.
  • STACIS active seismic isolation system (Ugolini, AJW, Vass): There are definitely problems with at least one of our new Wilcoxon accelerometers above 100 Hz; they are not at all intercalibrated, giving very different results when placed side by side. When we resolve this, we hope to get more meaningful measurements of the STACIS excess noise above 100 Hz, both below and on top of the chamber isolation stacks.
  • PEM system (AJW, Abbott, Ganezer, Ugolini): We received from LHO the EPROM for the IOC (Motorola cpu with RS232 ports to read digital devices into EPICS). Dennis and Ben used it to read out our MetOne dust particle monitor and display it on a simple EPICS GUI. Next: the weather station, STACIS controllers, RGA. We'll install the weather station on the roof next week; longer cables are needed to get the signals down to the lab.
  • Facility (Vass, Abbott): Ben is still trying to get changes to the 6 control room chairs that are way too small. The desks are about half assembled.
  • Optics (Billingsley): Garilynn is trying to get quotes from CSIRO to polish our mode cleaner optics.


  • Thermal Noise Interferometer (Libbrecht)


    This week we have been working on arm-cavity lock acquisition. A finesse of
    100,000 makes lock acquisition in these cavities challenging.  Because the
    resonance is so narrow, a high-bandwidth servo is needed to catch the
    system in the short amount of time it spends on resonance during a "flash."
     When we bypassed the mode cleaner, we achieved this bandwidth by acting on
    the laser's PZT at high frequencies.  Now that we have the mode cleaner in
    place, using the PZT is not so straightforward.  Even if the mode cleaner
    did not already send a control signal into the PZT, any changes in
    frequency the PZT induced in response to the arm cavity would show up in
    the mode cleaner's error signal, potentially knocking it out of lock.
     

    We have done some preliminary tests of basic servos acting on only a single
    arm-cavity mirror, with appropriate compensation, and acting on an
    arm-cavity mirror and the PZT, using a summing junction to combine the
    signals from the arm cavity and those of the mode cleaner.  We have not yet
    succeeded in acquiring lock, but as of this writing it is too early to rule
    out any of these schemes.  Although we have several models for the system,
    both analytic and simulink-based, there is a lot of parameter space to
    explore here.  We are also looking into using broad-band Pockels cells
    after the mode cleaner (which are already in place) to provide actuation
    independent of the mode cleaner at high frequencies.
     


    LASTI (Zucker)


    LASTI (MacInnis, LaLiberte, Miller, Mason, Rollins, Harry,
    Mittleman, Ottaway, Shoemaker, Zucker)
    -------------------------------------------
    Cleanrooms: The custom BSC cleanroom/work platform and
    "cartridge installation" craneable cleanroom arrived from the vendor
    and were installed by our rigging subcontractor.
    Fit is excellent and the dome flange-level work platform feels
    solid.  Curtains have been installed and the blowers and lights are being wired
    up for testing.  Bob L. and Fred. M. are modifying the
    safety rails slightly to facilitate temporary opening of gates for passage
    of crane loads.
     

    Electronics: We received more cross-connect components, power supplies and
    two more powered Eurocard crates from Caltech.
     

    PSL: Dave Ottaway joined us this week and will begin organizing
    the assembly and test of the PSL. The reference cavity vacuum chamber
    sent by Lee Cardenas arrived seriously abused by UPS; we are evaluating
    if they did any irreversable damage (our UPS driver actually tried to sneak away
    after leaving the severely beaten box in our back stairwell!).
     

    Lab space: the "Stiff" LIGO II active seismic isolator prototype was crated and
    will be loaded on a truck bound for Stanford today.


    Data Analysis and Computing (Lazzarini)


    Simulation and Modeling (Bhawal)

    Pre Stabilised Laser
    --------------------
    (Biplab) Rick and I are studying the effects of transverse motion of RF
    photodetectors on frequency sensor.
     

    Dual Recycling summation cavity
    -------------------------------
    Malik has simplified his formulas for dual recycling summation cavity.
    His Matlab code runs faster using these.
     
    Code development
    ----------------
    (Andrea) I am just starting to set up the interface for writing frame
    formatted output data. It should not take long however.
     

    Code maintenance
    ----------------
    (Ed Maros) Fixed configure.in to support pthreads under SunOS.
     

    Alfi
    ----
    (Bruce) Created multiple choice dialog.
    Continuing work on implementation of connection junctions.
    (Ed Maros) Implemented most of fix to prevent fully qualified path names
    from appearing in box files.
     

    Andrea:
    * Starting to set up the interface for writing frame formatted data.
     

    LIGO Data Analysis System
     

    Software Systems (Blackburn)
     

    The main thrust of effort has been in preparation of the LDAS release
    to support the next MDC. Members of the LSC will be arriving on Monday
    of next week and there will be a joint LDAS/MDC meeting at 8:30AM to
    organize the releases of LAL and LDAS. We decided to remain with the
    previous release of LDAS installed at the sites for this E4 engineering
    run due to the late date anticipated for the release of LDAS. The previous
    version is one release later than the version of LDAS used in the last
    engineering run.
     

    At present we are still struggling with a handful of problems with the
    dataPipeline command which will be used to control the LDAS system and
    data flow all the way from the frames through the parallel search codes
    and on to the database. This has yet to be tested successfully. There a
    are a couple of problems with reading in data from frames which only
    showed up mid week. We are also making changed to handle a problem with
    data identification in the wrapperAPI when data is sent to it from the
    dataConditionAPI.
     

    There has been a significant amount of testing this week. All the base-
    line tests show the system to be working fine. But the more integrated
    tests have been showing issues related to rapid changes to functionality
    to handle more general data structures.
     

    A new framebuilder code has been developed to support multi-second and
    multi-frame frame files. This code is being tested now but will not be
    used in the engineering run.
     

    The installation documentation for LDAS was corrected and upgraded in
    preparation for the new release. Several LSC sites reported problems in
    the build of the last release. All inconsistencies in the documentation
    have been fixed for this release.
     

    Peter Shawhan developed a client program called SeqInsert to serialize
    the insertion of LIGO metadata from the DMT into the LDAS database.
    This will prevent job failures due to metadata being inserted "out of
    order" by the multithreaded metadataAPI.  It may also serve as a model
    for other "smart" LDAS job sequencing clients.
     

    At the end of the day (after the report was submitted), Kent reported:


    "At approximately 1:30PM today Phil was successful at running
    |the first LDAS dataPipeline command using LIGO frames for
    |input data from the Hanford Observatory's E2 run. The data
    |consisted of a locked section of the LSC-AS_Q channel and
    |one other ancillary channel. The data was resampled and a
    |power spectrum generated in the dataConditionAPI. The IFO
    |response function was read in and appended to the data sent
    |to the wrapperAPI. The wrapperAPI ran the latest inspiral
    |search code to look for waveforms from 1.4/1.4 and 1.4/1.8
    |solar mass pairs. No events were detected so no entry was
    |made in the database. This marks the very  first search for
    |binary inspiral waveforms in LIGO data using LDAS. My
    |congratulations to all of you for working to make this little
    |step in LDAS happen!
    |
    |Undoubtedly there are still a lot of things to be worked out
    |and tested with the dataPipeline, but to me this is tremendous
    |news."

    [GHS note: Congratulations for the first "search" with LDAS !!]
     

    Andrea Vicere' :
     

    He has dealt with the issue of providing data in frame format starting from ILWD data. The library is based on the Virgo FrameL library and provides a way to simulate a simple framebuilder. Some data have been converted to help the test and debugging of the LDAS pipeline. Some more work shall be needed however to fully support ILWD data conversion.
     

    Hardware Systems (Anderson)
     

    Stuart is traveling the latter half of this week for work at Green bank, WVa (radio pulsar side of his life).
    All T3 RAID systems at LLO have been successfully installed and have been brought on line.
     

    Data Analysis Activities
     

    Andrea Vicere' :
     

    Started to work with Sanjeev Dhurandhar on the issue of the coherent analysis for coalescing binaries: the main point is to understand the practical problems raised by the coherent analysis, and to look at what can be done to reduce the amount of data to be exchanged and the computations to be done, using selection criteria on the single channels.
     

    Held a 1 hour teleconference with the Virgo group
    working on coalescing binaries: I am still participating in the development of the analysis library, which can be useful to keep up to date my understanding of the Virgo analysis pipeline and be able to know what shall be available for the network analysis.
     

    General Computing (Wallace)
     

    MIT:
    (Keith)
    -Purchased single/dual/quad machines for ldas
    -Investigated 2for1 research grant deal from Sun (not great)
    -Distributed non-demo version of SSHWinSecureShell24.exe to pc users
    -Updated accounts for visitors
    -Currently installing firewall for printer (prone to attacks)
     

    Livingston:
    -Preparing for the E4 run.
    -Resolving a number of computer issues including security updates.
    -Working on password updates.
     

    Hanford:
    (Christine)
    - Setup a new laptop.
    - Modified Solaris OS files to comply with new gateway security policy.
    - Started preparing a report of hardware purchases for the year for Fred
    Raab.
    - Dealt with problems of not being able to upgrade Solaris on some Sun
    Ultra10's because users have installed software on their local disks and
    have filled the disks.
    - Provided help to several users for various problems.
     

    CIT:
    (Barbara)
    - Worked on costbook items -- changes to reports and web forms, a problem
    pasting text into the WBS definition field, and a problem with access via a
    wireless network card.  Started working on reports sorted by resource and
    NSF codes.
    - Continued efforts on LDAS hardware diagrams.
    - Installed new build of WebBase on my pc and pherkab.  Have to do antares
    yet.
    - Looked into site map creators for LDAS.
    - Reworked the LSC site to point to Jennifer's LSC newsletter.
    - Made various web site updates.
     

    (Lisa)
    - I spent a day and a half updating virus software on the PCs.  I still need to
    cover wilson house and the 40m.
    - working on building an Ultra 60 for Rolf.  This is the CDS framebuilder that
    will be sent to MIT.  I've already contacted Keith and told him that I will
    e-mail him the configuration so that he knows what shape the box is in when it
    arrives.  I installed the OS, gcc compilers and the second internal hard disk.
    I still have left to do the disk array, VXworks, and epics.
    - Working on updating the Sun Visual Workshop/Forte compilers on sirius.
    - It was a heavy PC week.
     

    (Sam)
    -Worked a few PC issues. Trying to contact a user to get their machine
    completed.
     

    (Larry)
    -Resolved a few PC related issues. As we have been going through a number of the
    PC's to fix different things we have discovered a number of them need to be
    completely rebuilt or have a number of applications reloaded from scratch. Some
    of the machines were configured incorrectly and others have become corrupted
    through use.
    -Worked a few security and policy issues. There is still much work to be done on
    that front. However, Gary agrees that the gateway machines and servers should be
    secure hardened according to the groups technical needs. The people responsible
    for those machines are working on making them more secure.
    -Attended the Networld Interop exhibit. I should have attended the conference
    and taken a few of the courses. Things are changing fast. The largest number of
    items being shown were wireless LAN's, GIGE networks, security and B2B services.
    -Bill Tyler has taken over a number of the procurement issues which has been a
    big help. Bill is also working on the installation of the projectors for the
    conference rooms.
    -Working a few network issues to make sure we can activate all of the ports on
    the 6th floor of Millikan.
    -A number of people have been receiving infected files in their e-mail. So far
    it appears that no-one has opened the files and followed the correct procedure
    in removing them.
    -Fixed a few e-mail addresses.
    -Repaired a bad file system on the LIGO web server.
    -Still getting quotes and tracking down procurement problems. Just not as many
    with Bill helping out.
     
     


    LIGO II/Advanced R&D (Sanders)


    From Janeen Romie:

    New osems for 40m, LASTI, PNI etc.: Pigtail fabrication has been held up
    one more time. Pal Pilot needs to rework all pigtails a second time. A
    new delivery date has not been confirmed. They were due here 4/18.
    LEDs and photodiodes have been delivered early. LEDs were not due until
    mid July so this is good news. Todd Etzel and company will be taking
    over fabrication duties. Boards were delivered at the end of April.

    Advanced LIGO: Holding a telecon tomorrow morning with Norna Robertson
    about advanced suspensions documentation. Helena and I are working on
    costing in preparation for the review June 18th.

    From Peter King:

    2.2 40m Lab & LASTI
    I met with Alan and Mike Smith to thrash out some details on the
    opto-mechanical layout for the 40m Lab PSL table. Also I've been chasing
    some hardware prices for extra bits Alan requested.

    With the wiring of the PSL enclosure apparently finished. Lee will begin
    assembling the reference cavity under the PSL enclosure hopefully by week's
    end, after running the HEPA filter for a day or so.

    Lee is getting the parts for the reference cavity vibration isolation stack
    packed, ready for shipping along with an ion pump and its controller.

    I had a brief discussion with Ben Abbott and Dennis Ugolini about the 40m
    Lab PSL. Giving a semi-guided tour of the table components and the
    instrument rack.

    Dave Barker sent down the 40m Lab PSL IOC VxWorks EPROM.

    From Lee Cardenas:

    ·       New Ref. Cavity chamber already baked was sent out to MIT-LASTI.
    ·       The rest of the components to hung the ref. cavity are in preparation to be sent to MIT-LASTI.
    ·       Another new ref. cavity chamber is ready to be taken to 40m. lab and hung the ref. cavity in place.

    From Rich Abbott:

    I have been working with vendors to get a rough size for the capacitive position sensors used on the LIGO II seismic isolation platform

    From Mike Smith:

    40 METER

    A new optical layout of the 40 meter IFO with the SRM moved to its final
    configuration was completed. Position and angle sensing photodiodes and a
    Tropel frequency analyzer were added to the PSL output beam. The GW signal
    detection system was moved to accomodate the input optics additions.

    From: Helena Armandula <ahelena@ligo.caltech.edu>

    Silicate Bonding

    I was unable to make good sapphire/sapphire silicate bonds because the 1/2" substrate's surface was not flat to specs.
    Made some sapphire/sapphire bonds while at Stanford to verify that the process used was correct.
    The results from the bonds made at Stanford were similar to the bonds made at Caltech.
    The 1/2" sapphire substrates were sent for rework.
    (The 1" substrates are flat within specs.)
     

    While at Stanford, we took the LIGO coated optic from the chamber (where Q measurements were taken), cleaned the optic and shipped it to Caltech.
     

    From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>

    Japan operation: vacation week,  no notable results
     

    Creep facility
    Edwin, Run into trouble with the data, compounded by heavy and
    intermittent noise; Virginio and Riccardo identified fundamental ground
    loop problems. Riccardo and Edwin looking into completely cleaning up
    system and treating the ground problems.  Physical plant will bring new
    power line separated from the heating line.
     

    Szabi
    Started design for IP actuators replacing the present motorised sled and
    parasitic springs with memory metal springs.  Great simplifications may
    follow.  Restarting analysis of old data with Hareem
     

    Alessandro
    Back in Italy, will supervise Faimond for test ultrasound cutting of
    Sapphire, get some spare LVDT coils made (all spares used), advance with
    the vertical accelerometer design.
     

    Riccardo
    Working on a bid with Sonic mill for sapphire machining.  They ask 4000
    to 6000 $ only for tooling (the machining will be negligible) for he
    same job being done by Faimond for 1200 $.
    Hopefully  will converge before going to Japan (next week).


    For additional information about this report, contact sanders@ligo.caltech.edu