Weekly Report for Week Ending April 12, 2001


 Exec. Comm. Agenda
Highlights
LSC
Administration
Hanford Observatory
Livingston Observatory
MIT
Caltech
Detector
40 Meter
TNI
LASTI
Data Analysis
LIGO II/Adv. R&D
Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  April 16, 2001 will be:

 (Meeting time: 10:30 am Pacific Time)

Open meeting 10:30 - 11:30

  1. Announcements
  2. LSC Issues (Weiss)
  3. Comments on Weekly Report
  4. WBS 1 LIGO I Construction (Lindquist)
  5. WBS 2 LIGO Lab Operations
  6. WBS 3 and 4  Advanced R&D and LIGO II (Sanders)
Executive Committee only 11:30 - noon   Topics:
 

Special Items:


Special Announcements:  The new Newsletter is on the LIGO home page.


Weekly Report Highlights

 This week, the LLO 4K interferometer was locked in a recombined state for the first time.


LSC Issues (Weiss)


no report


LIGO I Construction/LIGO Laboratory Administration (Lindquist)



 

WBS 1.2 LIGO Operations--Administration



LIGO Weekly Site Telecon (Lindquist)

A site teleconference was held on Thursday, April 12, 2001.  Discussion included:

1) The current status of the plans for the building at Hanford, potential contingency needs, and possible sources of contingency.  Ed Jasnow has an action to check with the Office of Sponsored Research concerning the "brick wall" for spending Construction funds.  We need to get a better handle on our contingency to facilitate project level decisions.
2) The DCAA audit of our Proposal for Continuing Operations.  A meeting is scheduled Friday, April 13 at 9:00 am.
3) Some (possibly many) employees at the sites are being harassed by the Franchise Tax Board of California as a result of mistakes made at Caltech identifying them as California residents.  In some cases this harassment involves collection agencies and credit bureaus.  Ed Jasnow has accepted two actions: a) notify Anita Yanes of the problem and seek immediate relif for those affected, and b) prepare a memo to Al Horvath documenting the problem(s).  Remediation actions should include a letter sent by Caltech to the Franchise Tax Board with copies to the various credit agencies.
4) Schedule for Site Inventories: Livingston--April 29, Hanford--May 13.
5) Meetings with the Caltech Immigration and Visas folks continue.  Of interest during the most recent meeting is the information that those with certain visas should be very careful about foreign travel.  All LIGO foreign travelors in LIGO holding US Visas should check with Elizabeth Wood prior to making the trip.

The next site telecon is scheduled for Thursday, April  19, 2001.  The list of current actions revised to reflect open actions assigned through April 12, 2001 may be found at ACTION LIST.


PROPERTY MANAGEMENT (Chargois)

From: Ed Chargois <chargois_e@ligo.caltech.edu>


DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner - turner@ligo.caltech.edu>

Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .

ACCOMPLISHMENTS

From: Cleveland Mak <mak_c@ligo.caltech.edu>
Packages Faxes
In 30 31
Out 14 39

Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.


COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Akutagawa, Kaufman)

From: Esther Cunningham <esther@ligo.caltech.edu>

Press here for ACCOUNTS PAYABLE HISTORY DATA.

No report this week.

From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

From: Florence Kaufman <fkaufman@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: irena@ligo.caltech.edu (Irena Petrac)

From: Ed Jasnow <jasnow@ligo.caltech.edu>


Support (Wood)

 
Dorothy Lloyd

Out of the office this week.

Rita Torres

  • Checking weekly for incoming LSC reports and plans.  Assigned DCC number to report from Syracuse, and submitted for web posting.  Formatted Attachment A from ACIGA.  Formatted a draft MOU and Attachment A for European Gravitational Observatory (EGO).  Obtained an Oracle requisition number for Syracuse Univ., change order 2.
  • For E. Jasnow, did edits to proposed contract with NTD Architects.  FedExed copies to the NSF for further review, and approval.  Finished arranging the resistors in the BD lab, matched up with the labels I prepared last week.
  • Placed a few Pcard orders this week for LDAS work, arranged for parts to be delivered to the sites.  Investigated a delayed delivery from Synergy Microwave, also a FedEx charge for which I had no record, and corrected an error with Norland (they forgot my buy was by card, and not net 30).  Updated site trips on the web.  Finished the Caltech Justification Checklist for purchases over $5K in MS Word.  Gave to L. Wallace to test drive.  Prepared for filing with the DCC, chronological files from Project Controls and Detector groups for the years 1999 and 2000.
Irene Baldon
  • Processed three (3) new trips (including Advance Checks written and hotel/car rental authorizations filled out and FAXed to appropriate vendors in various locations); six (6) trips have been ticketed and are awaiting completion of necessary paper work; and sixteen (16) trips are pending final approval before tickets can be issued.  Once again I'm working with Ken Libbrecht on the 2001 SURF/LIGO travel.  I have received the first four (4) inquiries and awaiting contact from the remaining eighteen (18).  There is a total of twenty-two (22) students accepted for this summer, and they will be working at Caltech, Hanford, and Livingston.
  • Completed twenty-six (26) Expense Reports, have thirty (30) completed by Jim and need to be reviewed before sending to Travel Audit, Jim has twenty (20) that he is working on, and there are twenty (20) to be done.  I'm holding three (3) reports which need a check from the traveler before processing and five (5) that have problems that I need to work on.  I continue to train and supervise him on expense reports as best I can.
  • I reconciled thirty-nine (39) items on my P-Card, some of which needed additional work to contact vendor involved.  Assisted a few travelers with their reconciling and/or data entry.
  • Prepared the Travel/Vacation Itinerary for the Week of April 9, 2001.  Performed normal recording and filing associated with Travel and Reimbursement.  Also performed miscellaneous duties as requested by various members of  the LIGO Project here at Caltech as well as from members of the staffs of each of the two (2) sites.   I continue to do MIT's travel to the sites for installation activities and also to assist them wherever possible.
Elizabeth K. Wood
  • Attended a meeting with Immigration.  If you are on an H visa and need to leave the country, please check with me before initiating any travel plans.  If your visa is in the process of being extended, please remember that extensions of the H visa take time and during that time, you shouldn’t be traveling without contacting me or the Immigration people first.  You may be able to leave the country, but it’s not clear you’ll be able to come back in.
  • Began making catering and food arrangements for the NSF Review, April 30-May 2 here in room 114 EB.

Advanced LIGO (Frey, Petrac)

From: Thomas Frey <tfrey@ligo.caltech.edu>

Progress Period from 04.06 to 04.12

Accomplishments:

Schedule 04.13 to 04.19:

WBS 1.4.1.2   Project Controls (LIGO Construction)



Reports (Lindquist)

I am assembling and editing the contributions submitted for the end-of-February Quarterly Progess Report.

Also working with David Shoemaker to set up assignments for Advanced R&D Annual Report.  We should be sumbitting this report (necessary to get FY 2001 funding) over the next month or so.



Change Control/Contingency (Lindquist)

The following Change Requests have been submitted:
 

CR-000018 WBS 1.1.4 Curbing for Service Roads at Livingston G. Stapfer
CR-000019 WBS 1.2 Additional Lab Equipment D. Coyne
CR-000020 WBS 1.1.4 Staging Building and Renovations to Existing Building--Livigston F. Asiri
CR-010001 WBS 1.1.4 Return of Unused Construction Budget To Contingency F. Asiri

We should schedule a Change Control Board soon.

Press for the latest Contingency Needs Projection.


COST SCHEDULE CONTROL SYSTEMS (Duncan, Akutagawa)

From: Kris Duncan <kris@ligo.caltech.edu>

From: Cindy Akutagawa <cindy@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: Ed Jasnow <jasnow@ligo.caltech.edu>

From: irena@ligo.caltech.edu (Irena Petrac)

Quality/Safety (Tyler)

>From: Bill Tyler <tyler@ligo.caltech.edu>

LIGO Hanford Observatory (LHO) Operations (Raab)


General Items:
--------------
(F. Raab)
 

The focus here continues to be on getting both interferometers on line as
soon as possible. We are continuing to experience problems. The short story
is that the ITMy-2k mass slipped in its suspension during alignment, causing
damage to the optic. In examining potential causes for the slippage, we
uncovered some problems with suspension-wire terminations that we will
address during the recovery from this incident. Doug Cook's report (below)
provides the details.
 

A new (and distracting) activity here is the study of potential seismic
disturbances at LHO from the new gravel mining operation in N. Richland,
approximately 10 miles from the y arm. Digging, rock crushing and grading
activities began April 2 and will continue through April 20, or so. The
stockpiled gravel will then be trucked out during the year as the market
demands it. The intention is to repeat this cycle annually until the mine
site reaches a particular level, expected to take ten years or so, depending
on market demand. Hugh Radkins, Alan Rohay and I are assessing the potential
impacts for LIGO and Pacific Northwest National Laboratory (PNNL). We will be
reporting results at upcoming hearings involving the Richland City Council
for permitting of the gravel mine. The Council's Board of Adjustment is
requiring that the operation not be disruptive to the scientific missions of
LIGO or PNNL.
 

Interferometer Installation/Repair/Retrofit
-------------------------------------------
(D. Cook)
 

LHO suffered another hard hit in the 2k installation updates and
earthquake recovery. After re-installing the ITMy-2k optic I began releasing
the safety stops to complete the alignment. I backed off the two right bottom
stops and before I could start the left side the optic rotated and dropped,
shearing the face magnets inside the OSEMS. It appears the wire pulled loose
from the clamps. It is not conclusive, but it seems that through repeated uses
of the same suspension top block and clamps, grooves form from the hard wire
being compressed into the softer block material. These grooves measured out
to be .009" of the .012 diameter of the wire.  We do not disassemble the
clamps from the block so this problem was not evident. If the wire was not
relocated back into the existing groove to start with and/or we did not
have a  uniform squeeze on the clamps, the wire may have migrated to the
groove giving the clearance needed to slip. We may not have had enough
compression left to clamp the wire tight enough.
 

Just prior to transporting the optic we rechecked the wire clamps and
pulled the top winches and verified the balance angle. Transporting and
installation went smoothly (no bumps). We made one small structure yaw
rotation and upon clamping the structure to the table we had an immediate
signal return to the total station showing < 200 mrads in both pitch and yaw
with the optic still clamped. If the optic had been bounced we probably
would have lost this alignment. The wire was still located in the wire
standoff grooves. After moving the optic back to the optics lab we pulled
the height adaptor and when we loosened the wire clamps there was a
distinct "snap" to most of the 8 screws. It is not likely that the wire
stretched as we are about 3 times under the wire yield point. We will be
changing some features on the top block to help to improve the accuracy of
the assembly and to avoid potential losses from poor wire clamping.
This is a significantly hard hit again. Sorry for the let down.
 

The lower right magnet pulled glass from the optic face (ITMy-2k). It is a
'D' shape of about two thirds the diameter of the standoff footprint and
~.005-.010" deep. As this could affect the Q of the optic we will replace it
with a spare ITM. This will cause some additional delays as the scattering
mapping will need to be performed before it gets shipped to LHO.
 

We will begin a realignment on the ETMx-4k in the meantime. We will also
add the new safety stops etc. The ETMx-2k will follow on shortly afterwards
to change out the OSEMs, safety stops and align. If further delays occur we
will move onto the ETMy-4k and do a complete installation. This is the last
of the 4K core optics.
 

We will be pumping the X vertex section until the 2k alignment resumes.
 
 


LIGO Livingston Observatory (LLO) Operations (Coles)



 

Detector: This week, the LLO 4K interferometer was locked in a recombined state for the first time. The final factors which led to the locking were chiefly insights by Rana Adhakari to properly adjust the signs of the LSC matrix control signals and to find a "sweet spot" for some of the relative gain values and other lock acquisition parameters. Locking is not yet very robust, and lock acquisition takes a long time, but this is still an important milestone that has been achieved. Detailed investigations to improve performance are now underway. Guido Mueller is also here this week working on improvement of the MC mode matching.

PEM: (Doug Lormand) I have finished the PEM handbook for the voltage monitors. I have the skeleton handbooks for the magnetometers, accelerometers, and tiltmeters. I
have also created the DTT routines for the voltage monitors and
accelerometers. I am planning to finish the DTT routines and handbooks for
the magnetometers, accelerometers, and tiltmeters this week. I have a longer
cable and three mounting stands for our fluxgate magnetometers on order from
Bartington. I used my DTT seismometer routine to save a sample of the
seismic activity that is caused by our local train.

Control room operations: Operators not on Control Room duty (50%) have been busy with cleaning and
vac baking for LHO and the 40 meter, working in the Electronics Lab,
assisting the commissioning team, preparing for the E4 run, and starting
the gathering, cleaning and staging items needed for the tear down
up-coming. There is on-going training with RGA , IFO locking, DTT, DMT,
and other Data Tools.
 


MIT (Shoemaker)


David Ottaway is going to transfer from LIGO Hanford to LIGO MIT, with a cross-country trek starting at the end of April. He will join the team working on LASTI. While Hanford will certainly miss him, we are very much looking forward his presence and contribution at MIT, and it is great that he is staying in the 'LIGO Family'.


Caltech (Sanders)


no report


Detector/Technical Support (Whitcomb, Coyne)


 
Installation& Commissioning:
Hanford
Livingston
Other Science/EngineeringActivities:
Design/Analysis/Fab
Issues/Concerns
See also the Installation web page

1.1 LHO INSTALLATION & COMMISSIONING

2km Earthquake repairs

Doug Cook, Joe Hanson, Gary Traylor, Betsy Weaver, Dave Ottoway, Corey Gray, Mark Lubinski, Hugh Radkins, Malik Rakhmanov, Gerado, John, Kyle, etc.

2-k IOO repairs

David Tanner reporting
All suspended 2K small optics have been reinstalled. Progress on the re-alignment of the 2K IO has be held up as we wait for the completion of the main PSL beamline. The PMC was locked late on Tuesday and the installation of IO components on PSL/IOO table will be finished by Wednesday. We hope to start the final alignment of the 2K IO early on Thursday.

4-k IOO installation

David Tanner reporting
This week we measured the length of the 4K mode cleaner by locking it in air and tuning the resonant sideband to minimize RFAM. The resonant sideband frequency needed to minimize the RFAM was 24.889 MHz +/- 3 kHz. The design frequency in air is 24.887 MHz. A shift of 2 kHz corresponds to 1 mm in mode cleaner half length. Because the doors are on, we plan to remeasure after pumping down. The path length can be adusted when necessary by repositioning the HAM tables using the external mechanism.

Rich Abbott

LHO-TriNet seismic station (LTH)

Szabi Marka, Shourov Chatterji, Richard McCarthy
We finished the infrastructure and installation of the seismic amd magnetometric equipment in the Hanford vault. The vault has good and tested network access via optical fibers and quiet +/-12VDC power with battery backup. The seismic equipment is protected and well insulated thermally. We built a very stiff and stable support structure for the magnetometer coils from composite plastic members and glue joints. This way ce could minimize the metal content of the vault and ensure the structure's insensitivity to temperature and moisture variations while keeping the cost down. The equipment is operational and we are in the testing phase.
 

1.2LLO INSTALLATION & COMMISSIONING

Commissioning

Rai Weiss, et al.
After several iterations of the parameters used in the lock acquisition program and a reduction in the 60Hz amplitude in the control signal, the 4km interferometer was locked in an unrecycled Fabry-Perot/Michelson configuration for ten's of seconds. Work is in progress to improve the acquisition range and to make the lock more robust. The prior difficulties in achieving a lock can be attributed to the large dynamic range required in the control signal and to unoptimized parameters in the acquistion program.

The analysis of the displacement noise in the single cavity operation during the E3 run has progressed showing a spectrum dominated by seismic noise (strongly correlated with the seismometers) at frequencies below 10 Hz and dependent on frequency noise above 10 Hz.

Work is on-going to establish the mode matching to and loss in the x and y arm cavities.

Plans are being made to organize the tasks to be done when we open the interferometer to the atmosphere shortly after the E4 run.

DMT

Tom Evans, Szabi Marka
Due to a hacker attack we had to reinstall the operating system and some of the software on the Livingston DMT (delaronde) machine. The machine is up and running again.

Input Optics

David Tanner reporting
Work is underway on the diagnostic of the mode matching between MC and core optics. The mode matching is presently poor both for the MC to core optics and for the laser to MC. The reason for this has not yet been determined.

PSL

Peter King
Rus and I went off looking for 60 Hz related stuff.  A number of connections Rus already knew about.  These were disabled and the 60 Hz buzzer we were using indicated that a significant change was made. Although no significant change was registered in the signals that we were monitoring with a signal analyzer (PSL Out Mon, PSL-ISS_ERR and PMC_PZT). Each ground connection was pulled in the circuit breaker panel and no effect was observed.  Ditto when all the LVEA air handlers were disabled.

2.0 OtherEngineering and Scientific Activities

2.1 Design/Analysis/Fab

Input Optics Spares

GariLynn Billingsley
We have all of the Mode cleaner blanks and mirrors on hand which are to be repolished by Wave Precision (General Optics.)  I visited WP on Tuesday and obtained a copy of the quote for this work.  We are ready to go ahead and modify the PO and get this work going.

PSL

Lee Cardenas Rick Karwoski, Paul Russell Ben Abbott
The intensity servo DC photodiode board is set to return from the board house tomorrow.

Sander Liu
In the process of help testing both 21.5 MHz and 35.5 MHz photodiode boards.

New OSEM Heads

Janeen Romie
Working on Test box spec and updating the new osem assy spec.

AC OSEMs

Jay Heefner
A new prototype of the stabilized oscillator circuit that uses lower noise mixers has been built and tested at CIT. The circuit uses mini-circuits RAY-6U mixers that are good down to 10KHz. The circuit is indeed less noisy than previous version and initial testing is very promising. There is only one potential problem with the circuit. The mixers are level 23 and require substantial drive and therefore the circuit requires somehat greater input current, but it is still in the manageable range. If further testing is successful, a five channel prototype will be built for test on an IFO optic or optics.

ASC/LSC/Digital Suspensions

Jay Heefner Rolf Bork
LVEA code for SOS/LOS control about 90% complete (need to add oplevs). Installation for LHO 4k scheduled for week of April 23. Still waiting on Pentek ADC modules, which will hopefully be here in the next day or two.

Data Acquisition

Rolf Bork
Installed 40m Framebuilder and Lisa installed Solaris 8 on it so we could verify if the VMIC refected memory drivers would work on the new Solaris before we switch over the LHO system (desired, as Solaris 8 is reported to be faster at NFS, which will be needed when we write to the new LDAS disk drives instead of the framebuilder local drives).  Alex was able to get the drivers compiled and attached to the Sun, so that's a start.  In next day or two, will move over the VME hardware and beginning testing, particularly that reflected memory interrupts work properly on Solaris 8.

GDS

Daniel Sigg

40 Meter Interferometer (Weinstein)



 



Thermal Noise Interferometer (Libbrecht)


        We continued repairing our remaining OSEM controllers this week, and now
have all of them debugged.  Three are in place on the mode cleaner, and
four are ready for the test cavities.  Three of the four test cavity
controllers had previously been debugged, diagonalized, and tested on
suspended optics, but the forth continued to be problematic.  Despite very
similar electrical properties to the working ones (at least for the
longitudinal, pitch, and yaw modes), the last controller produced a much
higher resonance Q.  A close look at the OSEM's side control showed that 1)
its gain was 10x less than the working ones, and 2) a few op-amp stages
were not connected as shown in the schematics.  By cutting a track, adding
a few bypasses and replacing a resistor, this OSEM controller is now in
line with the others and can damp the resonant Q to 10-15.
 

        We also made considerable progress with our arm-cavity alignment scheme,
and we have observed transmission through the North arm cavity in the
TEM-00 mode with the mode cleaner locked in air.  The difficulties we
experienced last week appear to have been the result of low transmission
through the mode cleaner and the arm cavities.  Careful alignment of both
cavities, and optimization of the mode-cleaner servo for maximum
transmission, seem to have corrected the problem, and we can now reliably
observe the arm cavity flashing through resonance in the TEM-00 mode with
the arm cavity mirrors locally damped and the mode cleaner locked.  We
intend to wait until we have the chamber pumped out before attempting to
lock the arm cavities.
 

        Finally, we began installation of the vacuum-pump safety interlock
hardware.  Many thanks to Steve Vass for his continuing advice on that
project!
 


LASTI (Zucker)


LASTI (MacInnis, Mason, Shoemaker, Rollins, Harry, Mittleman, Zucker)
 

Interferometer layout: feedback so far from the advanced LIGO SUS team
on the "packing density" of advanced suspensions is encouraging,
although the word is still not definitive that we can live within our
present 30" beam tube.
 

Lab infrastructure: The second HAM cleanroom has been extended in
height and fitted with new electricals to improve access and
efficiency.  Bob Laliberte (tech specialist on loan from Center for
Space Research) is assisting Myron with the steelwork.  Lab
floor cleaning has been scheduled for this week.  The control room
has been reorganized to accommodate cleanroom garb as well as
EPICS control room functions.
 

BSC SEI installation: The roller-V-block structure for installing
the BSC support tubes has been mounted and rough-aligned.  Some
small modifications were required to get around the roof support
column.
 

PSL: Components continue to roll in.  We relocated some cabinets
to make room for work on the PSL around the designated table
area.


Data Analysis and Computing (Lazzarini)



Simulation and Modeling (Bhawal)

E2E MODELLING:

e2eLIGO package

(Hiro) The Han2k package is now underway of big changes.
[a] It will use the same latest code of the control matrix as the one
used at the site.
[b] One set of box files will be used for Hanford 2k, 4k and
Livingston 4k IFO, for one FP, recombined and power recycled
configuration.
[c] All difference will be taken care by using revised macro files.
[d] psd measuring tools will be installed in the standard distribution
[e] Speed up will be done using macros more extensively.
[f] Thermal noises will be included.
[g] This one is ready for modal mode fields
[h] 3D mirror and WFS will be implemented

All except [h] will be ready in a week, and will be released as the
next package together with a new version of modeler which is necessary
for this e2eLIGO package.

Lock acquisition Studies

(Biplab) Generated probability densities for the lock-acquisition time
in certain cases of misalignments.

Code Development

(Hiro) Random number generator: Random number generator is taking non
negligible amount of time. Tavio (he left LIGO at the end of March)
looked around for fast generator and identified one based on Mersenne
Twister algorithm. This sped up flat randum number generator by factor
of 3. The normal random number generator is updated to avoid using
sinusoidal functions and two numbers are generated together. This
sped up normal distribution by factor of 2.

Macro enhancements: In order to make it easy to create and maintain
complex configuration, implementation of macro has been enhanced to
include paths. Now a macro can be defined like
LIGO.IFO.name = val
Also expression like
LIGO.IFO.ITM.T = 0.03
can be used to specify directly settings of primitives. The treatment
of primitive settings can be dramatically changed, but for now, to
save time, the code structure will not be changed.

Code Maintenance & Validation

(Hiro) Some functions were too complicated and had trouble when
compiling. Code was cleaned up by changing the data strcuture and
by other ways. Now the object code side is reduce by 1/3, and
compilation is much smoother.

Cavity summation bug identified: Some bugs of Fabry-Perot cavity
summation code were found and fixed. Coupled cavity configuration was
used to test the code by comparing the summation cavity calculation
and the simulation using primitive optics. For scalar case, those two
matched nicely, but they showed discrepancy for modal fields.

(Biplab) working on comparison of results in a coupled cavity using
either primitives or Fabry-Perot summation cavity.

E2E at CACR

(Ed) Finished modifications to compile on CACR V2500 class computer.
Stated work on jobber (a program to submit jobs remotely to the V2500
systems).

(Hiro) C++ compiler on skinner computer: The simulation code could not
reproduce proper answers. After debugging, a bug of g++ running on
HP-UX was idenfied. complex /= double generates NaN if double < 1.
Two versions of HP compiler, CC and aCC, were tested as a substitute
to g++ to compile the simulation engine, but both were not quite C++
standard compliant. CACR programmer is trying to find if there is a
newer version of g++ for HP without this bug.

Alfi

(Bruce) Completed work on showing box/primitive comments correctly
in the parameters dialog. Working on input port settings in the
parameters dialog.

LIGO Data Analysis System

Software Systems (Blackburn)

The LDAS release 0.0.17 was finalized on Monday of this week. The
time between code freeze and actual release was reduced down to a
record 4 days. This version of LDAS has been pushed to all the LDAS
system (including the sites) as of Monday afternoon.

We were not able to get the full support for multiple frames and
arbitrary time intervals in each frame into the frameAPI for this
release of LDAS. However, the C++ components are all in place and
the remaining TCL components are expected to be finished by weeks
end.

The problem with the cpu usage in the eventMonitorAPI was determined
to be from a TCL "after" statement. This has now been resolved so
that the eventMonitorAPI doesn't use a tremendous amount of CPU even
when idle. However, there may be a remaining timing problem which is
causing requests to the metaDataAPI to drop jobs. It is being further
investigated.

The need for linear algebra support within the dataConditionAPI has
been a source of tremendous debate and frustration for LDAS and LSC
team members. The problem has been with the none thread-safe nature
of all stable libraries in the public domain. This week at a brain-
storming session, an idea was proposed by Ed, Alex and Kent which
turned out to work and allows us to use community standard libraries
such as LAPACK and its variants. Alex has demonstrated the workability
of this approach and C++ classes to wrap linear algebra into the
dataConditionAPI are being designed and implemented.

The MPI MDC datasets and the wrapperAPI have been changed to use
the Frame Specification standards for GPS time. This will also
require a change to LAL which has already been made to the LAL
CVS repository. Now UINT4 will be used instead of UINT8. The
wrapperAPI also had its history format enhanced to use an ILWD
container. The new LALwrapper was also installed on the LDAS
software server this week.

The new release of LAM-6.5.1 was tested at UWM and here at CIT
this week. The developers of LAM are highly dependent on KAI's
C++ compiler and as a result have taken out support for shared
object libraries. This is being evaluated to determine if a
quick fix can be made to the LAM code and shared with the LAM
development team to make this release of LAM more useful to
groups that use GCC compilers and shared object libraries in
their projects (like us).

The LDAS staff met on Wednesday to discuss plans for the next LDAS
release (0.0.17) which will support the May 15th Inspiral Mock-Data-
Challenge. A rework of the dataPipeline was the focus of the meeting.
It looks like better than 95% of the infrastructure for this next
release and the dataPipeline are already in place and the effort
will be on cleaning up primitives used by the user command and adding
tuning parameters.

Ran the datasocket and frame tests at Hanford and Livingston. The
frame-to-ilwd test passed within reasonable limits (<5%) at both
sites. All the datasocket tests completed at both sites. This is
somewhat news since we have had difficulty completing all the tests
in one shot in the past (specifically concerning controlmon and
linuxbox1). The overall comparison with previous test results passed.
Although, some of the individual tests had significant different
times/rates, specifically those involving controlmon and linuxbox1.

The DC-MDC API tests were also rerun at ldas-dev. This time the
intermediates show up in the ILWDs. The results matched with a set
of results I collected previously. For the psd and stat tests there
were some extra data in the ILWDs than in the previous results but
it is most likely due to the default output which may now be in
'wrapper' format.

There was also worked on LDAS test documentation. It will be placed in
CVS and then installed with every build.  We haven't yet finalized on
a permanent place in CVS. Ed and Isaac are working the remaining issues.

The wrapperAPI, and dataConditionAPI are now using a new library called
dbaccess which properly formats ILWD data for insertion into the LDAS
database. With this release of LDAS, the table information is hard-
coded into the C++ classes. Work began on making this dynamic, using
the SQL source that generates the tables.

This week Peter modified guild to be able to abort LDAS jobs that it
submits, using the "abortJob" user command.  [Aside: it turns out that
abortJob does not actually interrupt any given API's processing, it
just takes effect at the transitions between APIs.  So if you
accidentally start a job that is going to spend 3 minutes in the first
API, and then you immediately send an abortJob, it will still take 3
minutes for the abort to take effect.]

Peter also spent some time trying to track down the "late packet"
problem which has been causing LDAS jobs to fail on the test system.
Stuart identified some tcp parameters to tweak, but that didn't help.
It seems likely that we will need to modify LDAS to be smarter about
waiting until it has the complete input message, rather than assuming
that it all arrives within a given amount of time.

The framebuilder code is bing upgraded at the request of Rolf and
Benoit. The next release of the framebuilder will use the same frameCPP
source code to be distributed in LDAS release 0.0.17 in May.

Hardware Systems (Anderson)

LDAS activity at LHO:

1) The move of LDAS hardware from the mass storage room to the staging
building was completed on Mar 29 & 30.  The network connection has been
tested and working since then.

2) 72 boxes of equipment for the 15.5 TB Sun T3 disk farm have arrived.
A separate order of hubs,  and fiber channel switches and cards also
arrived.  The boxes have been moved to the mezzanine of the staging
building in preparation for installation.  A few more items need to
arrive before the installation can occur.

3) A Sun Blade 100 computer for administration of the disk farm arrived,
and was installed onto the ldas network.

Comparable Sun equipment has arrived at Caltech, LLO, and MIT, and is
awaiting installation by Sun at all 4 sites. It is anticipated that
installation order will be: LHO, CIT, LLO, and MIT starting April 18th
at LHO. The goal being to not have more than 1 LDAS system down at any
given time.

The 6000-slot tape library for the central LIGO data archive has
been successfully assembled to the point that the robot arm moves
and the LED's turn on. A more complete integration and acceptance
testing schedule is being developed with the vendor.

New model Sun computers come with USB only keyboard and mouse
connectors. A successful search for a cheap converter has been
completed (Belkin USB to PS/2 adapter) that has allowed these
computers (e.g., Blade100) to be connected to existing KVM switches.

An initial configuration of tripwire has been developed to monitor
LDAS computers against un-authorized modifications.

Other Data Analysis Activities

(Charlton) Worked on bringing the FCT code up to specification. Several
bug fixes were made to the code. Also worked on FCT documentation.

General Computing (Wallace)

MIT:
- Wrapped printer ports
- Interfaced with MIT networking for LDAS IP addresses
- Investigated tripwire ASE and AIDE GNU tools
- Installed AIDE (tripwire like) GNU tool on several machines
- Migrated some email users to secure APOP
- NFS server disk space issues

Livingston:
  See Livingston Report.

Hanford:
  See Hanford Report.

CIT:
(Sam)
- Worked on rebuilding a computer
- Worked on a laptop
- Trying to finish last term

(Lisa)
- Installed Sol 8 on fb40m, an ultra60 in the 40m.  The ultra60's have
  a bug when booting from an external cd drive. This and the work
  around are now documented in the FAQ. This box also had a problem
  attaching the driver for a non-Sun fiber ethernet card. Alex Ivanov
  recompiled for both a 32 and a 64 bit driver and it is now working.
  This testing was important because some of the servers at the sites
  can now upgrade to sol8.  Also, there is a new flash prom update for
  the ultra workstations that changes the timing on the network
  communications and quite a few other things.  Workstations with
  heavy network traffic should probably get flashed.
- Worked out the kinks with installing p-card under win2k.  This is
  also documented in the FAQ.
- I'm still having the odd few people who are having trouble with the
  new modem pool. Most of this has been problems in the client
  configurations.
- Got a demo version of Forte (new name for Sun Visual Workshop) 6 up
  and running. This is for the benefit of the 40m/CDS.
- Continued the installation of wireless access points. I also switched
  all of the access points to static IP's. We have three types:
  Addtron, SMC and Linksys. So far, I like the linksys best.  Addtron
  and SMC have web interfaces but the web interface doesn't always work
  well. The Linksys requires a serial connection, but the configuration
  is very straight forward.
- Had a meeting with the 40m to discuss what the present plan is for
  their network.  Dennis Ugolini has some security concerns that we
  have not been fully addressed.
- Put up a new DHCP server on the 114 subnet.  There has only been one
  problem with it so far -- the linux laptops need to have local hosts
  entries.
- Larry went out of town and for the first time the servers didn't pine
  for him. This was a relief.

(Barbara)
- Installed web form to search for reserved but unused document
  numbers. The url is
  http://antares.ligo.caltech.edu/dcc/logdefault.htf and a link
  is on the Internal Bulletin Board.  Remember to assign a discreet
  title if you are reserving a number for a confidential document.
- Installed revised web forms for reserving a document number. The
  author pull-down has been removed because it took so long to load
  and wasn't usable on unix boxes.
- Installed updated web forms for document search that meet standards.
- Continued to work on LDAS equipment web reports.
- Installed March newsletter.  Located and posted transparencies from
  February NSF review.
- I am working with Sam Finn to replicate the LDAS home page at PSU.
- The weekly DCC compact/repair job failed again this week.  I think
  it is because the .ldb file is not released after the web server is
  shut down and then the database can't be renamed and compacted. I am
  pondering yet another fix.
- Researched a problem with the PowerPoint templates on the internal
  bulletin board. You have to use IE to download them; they get
  clobbered if you use Netscape.
- Made updates to theses, publications, MOU, and LSC pages.  Posted
  the new travel authorization request form.
- Loaded secure-shell at home.

(Suresh)
- Disabled snmpXdmid processes to a list of Sun systems because of
  potential security vulnerabilities. Also, enabled sudo (superuser)
  privileges in some of the remaining machines.
- Did some printers maintenance in 6th floor Millikan.
- Resolved Larry Jones's printing problem.
- Worked with Omar to set up two new Sun Blade 100 systems.
- Doing some necessary preparation for transition to HEP.

(Larry)
- The highlight of the week other than taking some vacation time was
  helping Lisa with the SUN boxes in the 40M and fixing a few PC and
  network issues.
- Placed a number of SUN orders for both LDAS and the 40M.

----------------------------------------------------------------------
 


LIGO II/Advanced R&D (Sanders)



 
 

from Peter King:
 

40m & LASTI PSL
        The reference cavity vacuum chamber for the LASTI PSL and the
vibration isolation stack plates for the LASTI PSL and 40m Lab PSL have
been baked by Lee.  Said items have been packed in preparation for
shipping.
 

From Jay Heefner:
 

LASTI
==========================
- Cross connect wiring and cable harnesses for the suspension rack should be
shipped to MIT next week. Rus will travel to MIT the week of May 13 to install
the suspension racks and any other control or DAQ equipment that is ready by
then.
 
 


For additional information about this report, contact sanders@ligo.caltech.edu