|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The LIGO Executive Committee Agenda for Monday April 16, 2001 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
Special Items:
This week, the LLO 4K interferometer was locked in a recombined state for the first time.
no report
WBS 1.2 LIGO Operations--Administration
A site teleconference was held on Thursday, April 12, 2001. Discussion included:
1) The current status of the plans for the building
at Hanford, potential contingency needs, and possible sources of contingency.
Ed Jasnow has an action to check with the Office of Sponsored Research
concerning the "brick wall" for spending Construction funds. We need
to get a better handle on our contingency to facilitate project level decisions.
2) The DCAA audit of our Proposal for Continuing
Operations. A meeting is scheduled Friday, April 13 at 9:00 am.
3) Some
(possibly many) employees at the sites are being harassed by the Franchise
Tax Board of California as a result of mistakes made at Caltech identifying
them as California residents. In some cases this harassment involves
collection agencies and credit bureaus. Ed Jasnow has accepted two
actions: a) notify Anita Yanes of the problem and seek immediate relif
for those affected, and b) prepare a memo to Al Horvath documenting the
problem(s). Remediation actions should include a letter sent by Caltech
to the Franchise Tax Board with copies to the various credit agencies.
4) Schedule for Site Inventories: Livingston--April
29, Hanford--May 13.
5) Meetings with the Caltech Immigration and
Visas folks continue.
Of interest during the most recent meeting is the information that those
with certain visas should be very careful about foreign travel. All
LIGO foreign travelors in LIGO holding US Visas should check with Elizabeth
Wood prior to making the trip.
The next site telecon is scheduled for Thursday,
April 19, 2001. The list of current actions revised to reflect
open actions assigned through April 12, 2001 may be found at
ACTION
LIST.
From: Ed Chargois <chargois_e@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .
ACCOMPLISHMENTS
| Packages | Faxes | |
| In | 30 | 31 |
| Out | 14 | 39 |
Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS PAYABLE HISTORY DATA.
No report this week.
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
From: irena@ligo.caltech.edu (Irena Petrac)
Support (Wood)
Out of the office this week.
Rita Torres
Progress Period from 04.06 to 04.12
Accomplishments:
WBS 1.4.1.2 Project Controls (LIGO Construction)
I am assembling and editing the contributions submitted for the end-of-February Quarterly Progess Report.
Also working with David Shoemaker to set up assignments for Advanced R&D Annual Report. We should be sumbitting this report (necessary to get FY 2001 funding) over the next month or so.
The following Change Requests have
been submitted:
| CR-000018 | WBS 1.1.4 | Curbing for Service Roads at Livingston | G. Stapfer |
| CR-000019 | WBS 1.2 | Additional Lab Equipment | D. Coyne |
| CR-000020 | WBS 1.1.4 | Staging Building and Renovations to Existing Building--Livigston | F. Asiri |
| CR-010001 | WBS 1.1.4 | Return of Unused Construction Budget To Contingency | F. Asiri |
We should schedule a Change Control Board soon.
Press for the latest Contingency Needs Projection.
From: Kris Duncan <kris@ligo.caltech.edu>
The financial reports on the web provide supporting
detail.
http://docuserv.ligo.caltech.edu/~fireport
http://docuserv.ligo.caltech.edu/~finance
From: Ed Jasnow <jasnow@ligo.caltech.edu>
General Items:
--------------
(F. Raab)
The focus here continues to be on getting both
interferometers on line as
soon as possible. We are continuing to experience
problems. The short story
is that the ITMy-2k mass slipped in its suspension
during alignment, causing
damage to the optic. In examining potential causes
for the slippage, we
uncovered some problems with suspension-wire
terminations that we will
address during the recovery from this incident.
Doug Cook's report (below)
provides the details.
A new (and distracting) activity here is the study of potential seismic
disturbances at LHO from the new gravel mining operation in N. Richland,
approximately 10 miles from the y arm. Digging, rock crushing and grading
activities began April 2 and will continue through April 20, or so.
The
stockpiled gravel will then be trucked out during the year as the market
demands it. The intention is to repeat this cycle annually until the
mine
site reaches a particular level, expected to take ten years or so,
depending
on market demand. Hugh Radkins, Alan Rohay and I are assessing the
potential
impacts for LIGO and Pacific Northwest National Laboratory (PNNL).
We will be
reporting results at upcoming hearings involving the Richland City
Council
for permitting of the gravel mine. The Council's Board of Adjustment
is
requiring that the operation not be disruptive to the scientific missions
of
LIGO or PNNL.
Interferometer Installation/Repair/Retrofit
-------------------------------------------
(D. Cook)
LHO suffered another hard hit in the 2k installation
updates and
earthquake recovery. After re-installing the
ITMy-2k optic I began releasing
the safety stops to complete the alignment. I
backed off the two right bottom
stops and before I could start the left side
the optic rotated and dropped,
shearing the face magnets inside the OSEMS. It
appears the wire pulled loose
from the clamps. It is not conclusive, but it
seems that through repeated uses
of the same suspension top block and clamps,
grooves form from the hard wire
being compressed into the softer block material.
These grooves measured out
to be .009" of the .012 diameter of the wire.
We do not disassemble the
clamps from the block so this problem was not
evident. If the wire was not
relocated back into the existing groove to start
with and/or we did not
have a uniform squeeze on the clamps, the
wire may have migrated to the
groove giving the clearance needed to slip. We
may not have had enough
compression left to clamp the wire tight enough.
Just prior to transporting the optic we rechecked
the wire clamps and
pulled the top winches and verified the balance
angle. Transporting and
installation went smoothly (no bumps). We made
one small structure yaw
rotation and upon clamping the structure to the
table we had an immediate
signal return to the total station showing <
200 mrads in both pitch and yaw
with the optic still clamped. If the optic had
been bounced we probably
would have lost this alignment. The wire was
still located in the wire
standoff grooves. After moving the optic back
to the optics lab we pulled
the height adaptor and when we loosened the wire
clamps there was a
distinct "snap" to most of the 8 screws. It is
not likely that the wire
stretched as we are about 3 times under the wire
yield point. We will be
changing some features on the top block to help
to improve the accuracy of
the assembly and to avoid potential losses from
poor wire clamping.
This is a significantly hard hit again. Sorry
for the let down.
The lower right magnet pulled glass from the optic
face (ITMy-2k). It is a
'D' shape of about two thirds the diameter of
the standoff footprint and
~.005-.010" deep. As this could affect the Q
of the optic we will replace it
with a spare ITM. This will cause some additional
delays as the scattering
mapping will need to be performed before it gets
shipped to LHO.
We will begin a realignment on the ETMx-4k in
the meantime. We will also
add the new safety stops etc. The ETMx-2k will
follow on shortly afterwards
to change out the OSEMs, safety stops and align.
If further delays occur we
will move onto the ETMy-4k and do a complete
installation. This is the last
of the 4K core optics.
We will be pumping the X vertex section until the 2k alignment resumes.
Detector: This week, the LLO 4K interferometer was locked in a recombined state for the first time. The final factors which led to the locking were chiefly insights by Rana Adhakari to properly adjust the signs of the LSC matrix control signals and to find a "sweet spot" for some of the relative gain values and other lock acquisition parameters. Locking is not yet very robust, and lock acquisition takes a long time, but this is still an important milestone that has been achieved. Detailed investigations to improve performance are now underway. Guido Mueller is also here this week working on improvement of the MC mode matching.
PEM: (Doug Lormand) I have finished the PEM handbook for
the voltage monitors. I have the skeleton handbooks for the magnetometers,
accelerometers, and tiltmeters. I
have also created the DTT routines for the voltage monitors and
accelerometers. I am planning to finish the DTT routines and handbooks
for
the magnetometers, accelerometers, and tiltmeters this week. I have
a longer
cable and three mounting stands for our fluxgate magnetometers on order
from
Bartington. I used my DTT seismometer routine to save a sample of the
seismic activity that is caused by our local train.
Control room operations: Operators not on Control Room duty (50%)
have been busy with cleaning and
vac baking for LHO and the 40 meter, working in the Electronics Lab,
assisting the commissioning team, preparing for the E4 run, and starting
the gathering, cleaning and staging items needed for the tear down
up-coming. There is on-going training with RGA , IFO locking, DTT,
DMT,
and other Data Tools.
David Ottaway is going to transfer from LIGO Hanford to LIGO MIT, with a cross-country trek starting at the end of April. He will join the team working on LASTI. While Hanford will certainly miss him, we are very much looking forward his presence and contribution at MIT, and it is great that he is staying in the 'LIGO Family'.
no report
| Installation&
Commissioning:
Livingston |
Other Science/EngineeringActivities:
Issues/Concerns |
See also the Installation web page
Rich Abbott
The analysis of the displacement noise in the single cavity operation during the E3 run has progressed showing a spectrum dominated by seismic noise (strongly correlated with the seismometers) at frequencies below 10 Hz and dependent on frequency noise above 10 Hz.
Work is on-going to establish the mode matching to and loss in the x and y arm cavities.
Plans are being made to organize the tasks to be done when we open the interferometer to the atmosphere shortly after the E4 run.
Sander Liu
In the process of help testing both 21.5 MHz and 35.5 MHz photodiode
boards.
We continued repairing our
remaining OSEM controllers this week, and now
have all of them debugged. Three are in place on the mode cleaner,
and
four are ready for the test cavities. Three of the four test
cavity
controllers had previously been debugged, diagonalized, and tested
on
suspended optics, but the forth continued to be problematic.
Despite very
similar electrical properties to the working ones (at least for the
longitudinal, pitch, and yaw modes), the last controller produced a
much
higher resonance Q. A close look at the OSEM's side control showed
that 1)
its gain was 10x less than the working ones, and 2) a few op-amp stages
were not connected as shown in the schematics. By cutting a track,
adding
a few bypasses and replacing a resistor, this OSEM controller is now
in
line with the others and can damp the resonant Q to 10-15.
We also made considerable
progress with our arm-cavity alignment scheme,
and we have observed transmission through the North arm cavity in the
TEM-00 mode with the mode cleaner locked in air. The difficulties
we
experienced last week appear to have been the result of low transmission
through the mode cleaner and the arm cavities. Careful alignment
of both
cavities, and optimization of the mode-cleaner servo for maximum
transmission, seem to have corrected the problem, and we can now reliably
observe the arm cavity flashing through resonance in the TEM-00 mode
with
the arm cavity mirrors locally damped and the mode cleaner locked.
We
intend to wait until we have the chamber pumped out before attempting
to
lock the arm cavities.
Finally, we began installation
of the vacuum-pump safety interlock
hardware. Many thanks to Steve Vass for
his continuing advice on that
project!
LASTI (MacInnis, Mason, Shoemaker, Rollins, Harry, Mittleman, Zucker)
Interferometer layout: feedback so far from the advanced LIGO SUS team
on the "packing density" of advanced suspensions is encouraging,
although the word is still not definitive that we can live within our
present 30" beam tube.
Lab infrastructure: The second HAM cleanroom has been extended in
height and fitted with new electricals to improve access and
efficiency. Bob Laliberte (tech specialist on loan from Center
for
Space Research) is assisting Myron with the steelwork. Lab
floor cleaning has been scheduled for this week. The control
room
has been reorganized to accommodate cleanroom garb as well as
EPICS control room functions.
BSC SEI installation: The roller-V-block structure for installing
the BSC support tubes has been mounted and rough-aligned. Some
small modifications were required to get around the roof support
column.
PSL: Components continue to roll in. We relocated some cabinets
to make room for work on the PSL around the designated table
area.
E2E MODELLING:
e2eLIGO package
(Hiro) The Han2k package is now underway of big changes.
[a] It will use the same latest code of the control matrix
as the one
used at the site.
[b] One set of box files will be used for Hanford 2k,
4k and
Livingston 4k IFO, for one FP, recombined and power recycled
configuration.
[c] All difference will be taken care by using revised
macro files.
[d] psd measuring tools will be installed in the standard
distribution
[e] Speed up will be done using macros more extensively.
[f] Thermal noises will be included.
[g] This one is ready for modal mode fields
[h] 3D mirror and WFS will be implemented
All except [h] will be ready in a week, and will be released
as the
next package together with a new version of modeler which
is necessary
for this e2eLIGO package.
Lock acquisition Studies
(Biplab) Generated probability densities for the lock-acquisition
time
in certain cases of misalignments.
Code Development
(Hiro) Random number generator: Random number generator
is taking non
negligible amount of time. Tavio (he left LIGO at the
end of March)
looked around for fast generator and identified one based
on Mersenne
Twister algorithm. This sped up flat randum number generator
by factor
of 3. The normal random number generator is updated to
avoid using
sinusoidal functions and two numbers are generated together.
This
sped up normal distribution by factor of 2.
Macro enhancements: In order to make it easy to create
and maintain
complex configuration, implementation of macro has been
enhanced to
include paths. Now a macro can be defined like
LIGO.IFO.name = val
Also expression like
LIGO.IFO.ITM.T = 0.03
can be used to specify directly settings of primitives.
The treatment
of primitive settings can be dramatically changed, but
for now, to
save time, the code structure will not be changed.
Code Maintenance & Validation
(Hiro) Some functions were too complicated and had trouble
when
compiling. Code was cleaned up by changing the data strcuture
and
by other ways. Now the object code side is reduce by
1/3, and
compilation is much smoother.
Cavity summation bug identified: Some bugs of Fabry-Perot
cavity
summation code were found and fixed. Coupled cavity configuration
was
used to test the code by comparing the summation cavity
calculation
and the simulation using primitive optics. For scalar
case, those two
matched nicely, but they showed discrepancy for modal
fields.
(Biplab) working on comparison of results in a coupled
cavity using
either primitives or Fabry-Perot summation cavity.
E2E at CACR
(Ed) Finished modifications to compile on CACR V2500 class
computer.
Stated work on jobber (a program to submit jobs remotely
to the V2500
systems).
(Hiro) C++ compiler on skinner computer: The simulation
code could not
reproduce proper answers. After debugging, a bug of g++
running on
HP-UX was idenfied. complex /= double generates NaN if
double < 1.
Two versions of HP compiler, CC and aCC, were tested
as a substitute
to g++ to compile the simulation engine, but both were
not quite C++
standard compliant. CACR programmer is trying to find
if there is a
newer version of g++ for HP without this bug.
Alfi
(Bruce) Completed work on showing box/primitive comments
correctly
in the parameters dialog. Working on input port settings
in the
parameters dialog.
LIGO Data Analysis System
Software Systems (Blackburn)
The LDAS release 0.0.17 was finalized on Monday of
this week. The
time between code freeze and actual release was reduced
down to a
record 4 days. This version of LDAS has been pushed to
all the LDAS
system (including the sites) as of Monday afternoon.
We were not able to get the full support for multiple
frames and
arbitrary time intervals in each frame into the frameAPI
for this
release of LDAS. However, the C++ components are all
in place and
the remaining TCL components are expected to be finished
by weeks
end.
The problem with the cpu usage in the eventMonitorAPI
was determined
to be from a TCL "after" statement. This has now been
resolved so
that the eventMonitorAPI doesn't use a tremendous amount
of CPU even
when idle. However, there may be a remaining timing problem
which is
causing requests to the metaDataAPI to drop jobs. It
is being further
investigated.
The need for linear algebra support within the dataConditionAPI
has
been a source of tremendous debate and frustration for
LDAS and LSC
team members. The problem has been with the none thread-safe
nature
of all stable libraries in the public domain. This week
at a brain-
storming session, an idea was proposed by Ed, Alex and
Kent which
turned out to work and allows us to use community standard
libraries
such as LAPACK and its variants. Alex has demonstrated
the workability
of this approach and C++ classes to wrap linear algebra
into the
dataConditionAPI are being designed and implemented.
The MPI MDC datasets and the wrapperAPI have been changed
to use
the Frame Specification standards for GPS time. This
will also
require a change to LAL which has already been made to
the LAL
CVS repository. Now UINT4 will be used instead of UINT8.
The
wrapperAPI also had its history format enhanced to use
an ILWD
container. The new LALwrapper was also installed on the
LDAS
software server this week.
The new release of LAM-6.5.1 was tested at UWM and here
at CIT
this week. The developers of LAM are highly dependent
on KAI's
C++ compiler and as a result have taken out support for
shared
object libraries. This is being evaluated to determine
if a
quick fix can be made to the LAM code and shared with
the LAM
development team to make this release of LAM more useful
to
groups that use GCC compilers and shared object libraries
in
their projects (like us).
The LDAS staff met on Wednesday to discuss plans for the
next LDAS
release (0.0.17) which will support the May 15th Inspiral
Mock-Data-
Challenge. A rework of the dataPipeline was the focus
of the meeting.
It looks like better than 95% of the infrastructure for
this next
release and the dataPipeline are already in place and
the effort
will be on cleaning up primitives used by the user command
and adding
tuning parameters.
Ran the datasocket and frame tests at Hanford and Livingston.
The
frame-to-ilwd test passed within reasonable limits (<5%)
at both
sites. All the datasocket tests completed at both sites.
This is
somewhat news since we have had difficulty completing
all the tests
in one shot in the past (specifically concerning controlmon
and
linuxbox1). The overall comparison with previous test
results passed.
Although, some of the individual tests had significant
different
times/rates, specifically those involving controlmon
and linuxbox1.
The DC-MDC API tests were also rerun at ldas-dev. This
time the
intermediates show up in the ILWDs. The results matched
with a set
of results I collected previously. For the psd and stat
tests there
were some extra data in the ILWDs than in the previous
results but
it is most likely due to the default output which may
now be in
'wrapper' format.
There was also worked on LDAS test documentation. It will
be placed in
CVS and then installed with every build. We haven't
yet finalized on
a permanent place in CVS. Ed and Isaac are working the
remaining issues.
The wrapperAPI, and dataConditionAPI are now using a new
library called
dbaccess which properly formats ILWD data for insertion
into the LDAS
database. With this release of LDAS, the table information
is hard-
coded into the C++ classes. Work began on making this
dynamic, using
the SQL source that generates the tables.
This week Peter modified guild to be able to abort LDAS
jobs that it
submits, using the "abortJob" user command. [Aside:
it turns out that
abortJob does not actually interrupt any given API's
processing, it
just takes effect at the transitions between APIs.
So if you
accidentally start a job that is going to spend 3 minutes
in the first
API, and then you immediately send an abortJob, it will
still take 3
minutes for the abort to take effect.]
Peter also spent some time trying to track down the "late
packet"
problem which has been causing LDAS jobs to fail on the
test system.
Stuart identified some tcp parameters to tweak, but that
didn't help.
It seems likely that we will need to modify LDAS to be
smarter about
waiting until it has the complete input message, rather
than assuming
that it all arrives within a given amount of time.
The framebuilder code is bing upgraded at the request
of Rolf and
Benoit. The next release of the framebuilder will use
the same frameCPP
source code to be distributed in LDAS release 0.0.17
in May.
Hardware Systems (Anderson)
LDAS activity at LHO:
1) The move of LDAS hardware from the mass storage room
to the staging
building was completed on Mar 29 & 30. The
network connection has been
tested and working since then.
2) 72 boxes of equipment for the 15.5 TB Sun T3 disk farm
have arrived.
A separate order of hubs, and fiber channel switches
and cards also
arrived. The boxes have been moved to the mezzanine
of the staging
building in preparation for installation. A few
more items need to
arrive before the installation can occur.
3) A Sun Blade 100 computer for administration of the
disk farm arrived,
and was installed onto the ldas network.
Comparable Sun equipment has arrived at Caltech, LLO,
and MIT, and is
awaiting installation by Sun at all 4 sites. It is anticipated
that
installation order will be: LHO, CIT, LLO, and MIT starting
April 18th
at LHO. The goal being to not have more than 1 LDAS system
down at any
given time.
The 6000-slot tape library for the central LIGO data archive
has
been successfully assembled to the point that the robot
arm moves
and the LED's turn on. A more complete integration and
acceptance
testing schedule is being developed with the vendor.
New model Sun computers come with USB only keyboard and
mouse
connectors. A successful search for a cheap converter
has been
completed (Belkin USB to PS/2 adapter) that has allowed
these
computers (e.g., Blade100) to be connected to existing
KVM switches.
An initial configuration of tripwire has been developed
to monitor
LDAS computers against un-authorized modifications.
Other Data Analysis Activities
(Charlton) Worked on bringing the FCT code up to specification.
Several
bug fixes were made to the code. Also worked on FCT documentation.
General Computing (Wallace)
MIT:
- Wrapped printer ports
- Interfaced with MIT networking for LDAS IP addresses
- Investigated tripwire ASE and AIDE GNU tools
- Installed AIDE (tripwire like) GNU tool on several
machines
- Migrated some email users to secure APOP
- NFS server disk space issues
Livingston:
See Livingston Report.
Hanford:
See Hanford Report.
CIT:
(Sam)
- Worked on rebuilding a computer
- Worked on a laptop
- Trying to finish last term
(Lisa)
- Installed Sol 8 on fb40m, an ultra60 in the 40m.
The ultra60's have
a bug when booting from an external cd drive.
This and the work
around are now documented in the FAQ. This box
also had a problem
attaching the driver for a non-Sun fiber ethernet
card. Alex Ivanov
recompiled for both a 32 and a 64 bit driver and
it is now working.
This testing was important because some of the
servers at the sites
can now upgrade to sol8. Also, there is
a new flash prom update for
the ultra workstations that changes the timing
on the network
communications and quite a few other things.
Workstations with
heavy network traffic should probably get flashed.
- Worked out the kinks with installing p-card under win2k.
This is
also documented in the FAQ.
- I'm still having the odd few people who are having
trouble with the
new modem pool. Most of this has been problems
in the client
configurations.
- Got a demo version of Forte (new name for Sun Visual
Workshop) 6 up
and running. This is for the benefit of the 40m/CDS.
- Continued the installation of wireless access points.
I also switched
all of the access points to static IP's. We have
three types:
Addtron, SMC and Linksys. So far, I like the linksys
best. Addtron
and SMC have web interfaces but the web interface
doesn't always work
well. The Linksys requires a serial connection,
but the configuration
is very straight forward.
- Had a meeting with the 40m to discuss what the present
plan is for
their network. Dennis Ugolini has some security
concerns that we
have not been fully addressed.
- Put up a new DHCP server on the 114 subnet. There
has only been one
problem with it so far -- the linux laptops need
to have local hosts
entries.
- Larry went out of town and for the first time the servers
didn't pine
for him. This was a relief.
(Barbara)
- Installed web form to search for reserved but unused
document
numbers. The url is
http://antares.ligo.caltech.edu/dcc/logdefault.htf
and a link
is on the Internal Bulletin Board. Remember
to assign a discreet
title if you are reserving a number for a confidential
document.
- Installed revised web forms for reserving a document
number. The
author pull-down has been removed because it took
so long to load
and wasn't usable on unix boxes.
- Installed updated web forms for document search that
meet standards.
- Continued to work on LDAS equipment web reports.
- Installed March newsletter. Located and posted
transparencies from
February NSF review.
- I am working with Sam Finn to replicate the LDAS home
page at PSU.
- The weekly DCC compact/repair job failed again this
week. I think
it is because the .ldb file is not released after
the web server is
shut down and then the database can't be renamed
and compacted. I am
pondering yet another fix.
- Researched a problem with the PowerPoint templates
on the internal
bulletin board. You have to use IE to download
them; they get
clobbered if you use Netscape.
- Made updates to theses, publications, MOU, and LSC
pages. Posted
the new travel authorization request form.
- Loaded secure-shell at home.
(Suresh)
- Disabled snmpXdmid processes to a list of Sun systems
because of
potential security vulnerabilities. Also, enabled
sudo (superuser)
privileges in some of the remaining machines.
- Did some printers maintenance in 6th floor Millikan.
- Resolved Larry Jones's printing problem.
- Worked with Omar to set up two new Sun Blade 100 systems.
- Doing some necessary preparation for transition to
HEP.
(Larry)
- The highlight of the week other than taking some vacation
time was
helping Lisa with the SUN boxes in the 40M and
fixing a few PC and
network issues.
- Placed a number of SUN orders for both LDAS and the
40M.
----------------------------------------------------------------------
from Peter King:
40m & LASTI PSL
The reference cavity vacuum
chamber for the LASTI PSL and the
vibration isolation stack plates for the LASTI PSL and 40m Lab PSL
have
been baked by Lee. Said items have been packed in preparation
for
shipping.
From Jay Heefner:
LASTI
==========================
- Cross connect wiring and cable harnesses for the suspension rack
should be
shipped to MIT next week. Rus will travel to MIT the week of May 13
to install
the suspension racks and any other control or DAQ equipment that is
ready by
then.
For additional information about this report, contact sanders@ligo.caltech.edu