Weekly Report for Week Ending April 5, 2001


 Exec. Comm. Agenda
Highlights
LSC
Administration
Hanford Observatory
Livingston Observatory
MIT
Caltech
Detector
40 Meter
TNI
LASTI
Data Analysis
LIGO II/Adv. R&D
Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  April 9, 2001 will be:

 (Meeting time: 10:30 am Pacific Time)

Open meeting 10:30 - 11:30

  1. Announcements
  2. LSC Issues (Weiss)
  3. Comments on Weekly Report
  4. WBS 1 LIGO I Construction (Lindquist)
  5. WBS 2 LIGO Lab Operations
  6. WBS 3 and 4  Advanced R&D and LIGO II (Sanders)
Executive Committee only 11:30 - noon   Topics:
 

Special Items:


Special Announcements:


Weekly Report Highlights
 


LSC Issues (Weiss)


no report


LIGO I Construction/LIGO Laboratory Administration (Lindquist)



 

WBS 1.2 LIGO Operations--Administration



LIGO Weekly Site Telecon (Lindquist)

No report this week.

The next site telecon is scheduled for Thursday, April 12, 2001. The list of current actions revised to reflect open actions assigned through March 29, 2001 may be found at ACTION LIST.


PROPERTY MANAGEMENT (Chargois)

From: Ed Chargois <chargois_e@ligo.caltech.edu>


DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner - turner@ligo.caltech.edu>

Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .

ACCOMPLISHMENTS

From: Cleveland Mak <mak_c@ligo.caltech.edu>
Packages Faxes
In 47 32
Out 11 49

Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.


COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Akutagawa, Kaufman)

From: Esther Cunningham <esther@ligo.caltech.edu>

Press here for ACCOUNTS PAYABLE HISTORY DATA.

From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

From: Florence Kaufman <fkaufman@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: irena@ligo.caltech.edu (Irena Petrac)

From: Ed Jasnow <jasnow@ligo.caltech.edu>


Support (Wood)

Irene Baldon

Dorothy Lloyd Rita Torres Elizabeth K. Wood

Advanced LIGO (Frey, Petrac)

From: Thomas Frey <tfrey@ligo.caltech.edu>

Progress Period from 03.30 to 04.05

Accomplishments:

Schedule 04.06 to 04.12:

From: irena@ligo.caltech.edu (Irena Petrac)


WBS 1.4.1.2   Project Controls (LIGO Construction)



Reports (Lindquist)

Change Control/Contingency (Lindquist)

The following Change Requests have been submitted:
 

CR-000018 WBS 1.1.4 Curbing for Service Roads at Livingston G. Stapfer
CR-000019 WBS 1.2 Additional Lab Equipment D. Coyne
CR-000020 WBS 1.1.4 Staging Building and Renovations to Existing Building--Livingston F. Asiri
CR-010001 WBS 1.1.4 Return of Unused Construction Budget To Contingency F. Asiri

Press for the latest Contingency Needs Projection.


COST SCHEDULE CONTROL SYSTEMS (Duncan, Akutagawa)

From: Kris Duncan <kris@ligo.caltech.edu>

From: Cindy Akutagawa <cindy@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: Ed Jasnow <jasnow@ligo.caltech.edu>

From: irena@ligo.caltech.edu (Irena Petrac)

Quality/Safety (Tyler)

>From: Bill Tyler <tyler@ligo.caltech.edu>


LIGO Hanford Observatory (LHO) Operations (Raab)


Weekly for Doug Cook (submitted by D. Coyne)
All 2 km interferometer small optics suspensions (IO) have been put back
into the HAM chambers with the exception of one mode cleaner (MC) flat
mirror which required rework to the suspension tower; This rework has been
completed and the optic is expected to be re-installed soon. The 4 km
interferometer MC has been locked in air for as long as ~1/2 hr. Length
measurements are pending. Work continues on alignment of the 4 km PSL
pre-mode cleaner.
 

After re-installation into chamber WBSC8, it was discovered that the
ITMy,2k optic was hung incorrectly in pitch; It was set to retroreflect
from the anti-reflection (AR) surface instead of the high-reflectance (HR)
surface. It has been removed from the chamber. The guide rod an wire
standoff were debonded from the optic and then reset. It will be vacuum
baked this weekend and re-installed Monday.
 

The ETMy,2k suspension assembly has been re-installed into the y-mid
station chamber and is in the process of being re-aligned using a new
procedure (E010066-A) which does not require spool removal. This procedure
is facilitated by having both the LHO and LLO IAS survey equipment (total
stations and laser autocollimators) available.
 
 

Facilities
(O. Matherny)
The new  Auditorium/Office Building will be located about 775 feet southeast
from the 4K input. The field work for the geotechnical investigation for the
building was completed 4-05-01.


LIGO Livingston Observatory (LLO) Operations (Coles)



 

PEM: Finished the control room handbook for the seismometers. The handbook is a quick reference for seismometer data including current status of the
instruments, sample printouts of 'good' seismic data, an instruction guide for using the DTT and the dataviewer to view seismic data, and an anomalies section for unexplained signals. I am hoping to begin work on the voltage monitor handbook today which I believe I can finish tomorrow or Monday. I will also introduce the handbook
to the operators and encourage them to begin using the DTT routine that I set up to check the seismometers at least three times a week, perhaps daily. (Doug Lormand)

LDAS: We have received six pallets (!) of LDAS equipment, which we are sorting out. We are also preparing the mass storage room area for installation (SUN was contracted to do installation as part of the purchase contract). We have received a Dell PC and a Sun Blade 100 for upgrades for individual users. (Shannon Roddy)

GC: We are working on security issues concerning GC and CDS.

Other operations issues: I have been working on baking and cleaning osems with Gary and Harry. They should be sent out tomorrow. I also have some parts ready to go into the oven for the 40m. I have helped Rana a small amount with some calibrations of some of the channels. I have also learned the proper termination of an oscilloscope when measuring GPS signals. (Joe Langdale)

Jonathan Kern has begun to put together a detailed schedule for activities that will be undertaken during the vent following E4.

Joe Kovalik is investigating the spectral density of the mode cleaner length variation. The transfer functions of the HAM seismic stacks are apparent in the data, along with other features that should be investigated. See http://www.ligo-la.caltech.edu/ilog/pub/ilog.cgi

Outreach: As part the of East Baton Rouge Parish Library Summer Program, we will visit each libray to speak about LIGO and conduct a hands-on presentation using
the spectrometers. There are 8 libraries and we will do one per week. The presentation will be advertised by the library as a family acitivity centering around middle school children but all ages will be invited to attend. (Bonnie Wascom)
 


Detector/Technical Support (Whitcomb, Coyne)



 

DETECTOR

 
Installation& Commissioning:
Hanford
Livingston
Other Science/EngineeringActivities:
Design/Analysis/Fab
Issues/Concerns
See also the Installation web page

1.1 LHO INSTALLATION & COMMISSIONING

2km Earthquake repairs

Doug Cook, Joe Hanson, Gary Traylor, Betsy Weaver, Dave Ottoway, Corey Gray, Mark Lubinski, Hugh Radkins, Malik Rakhmanov, Herado, John, Kyle, Dennis, etc. Mark Barton
Helped with repair of various optics, especially the ITMx2K that was mishung. Wrote a draft of a update to the balancing specification E970154 to make such an error less likely in the future.

2-k IOO repairs

David Tanner reporting
All 2k optics in HAM 7 and 8, except MC1 were reinstalled. Alignment on this system will begin as soon as the PSL is brought back on line

The 2k PSL/IOO table layout has commenced, at the time of writing the PMC was aligned but not locked.

People involved in this work Betsy, Malik, Mark G, Corey, Josh, Richard and Dave O and Dave Guagliardo.

4-k IOO installation

David Tanner reporting
HAM 1 and 2 doors have been installed.

The 4k mode cleaner was locked in air for periods exceeding 20 minutes using the 4k RF system and the 2k control card. However significant power fluctuations at 1.8 Hz were observed.

UF will ship this week 2 Coherent optical spectrum analyzers (and 1 controller) for use on the 4-k PSL and IOT tables.

Rich Abbott
LHO received the boards for the modecleaner servo.

LHO-TriNet seismic station (LTH)

Szabi Marka
We tested the network access in the vault with the new fiber media converters (Transition Networks; J/E-C/F-01). The connection was established very quickly, so it seems these inexpensive boxes are a good solution. The fiber connection to the Coil-magnetometer electronics was also tested and works fine. We plan to populate the vault (seismic equipment and magnetometer) by the end of this week.

1.2LLO INSTALLATION & COMMISSIONING

Commissioning

Rai Weiss, et al.
We are still attempting to lock the recombined Fabry-Perot Michelson without recycling. Significant work can only take place at night and on weekends due to the seismic disturbances from the building construction.

Much of the last two weeks has been dedicated to chasing several electronics problems. The most difficult to diagnose has been poor synchronization of the interferometer control computers at the LVEA and the y end station. The problem was ultimately traced to a faulty GPS timing distribution board at the y end station.

The lock acquisition has progressed to the ability to lock either arm cavity and the Michelson interferometer together. The process to lock the entire system works up to the point where a cavity and the Michelson are locked and the second cavity is brought into resonance. Then the transition to the final lock acquistion is made in the locking code but the system fails to make the final acquisition. There is a good chance that we will resolve the problem in the coming week.

Concurrently work is on going to make an authoritive measurement of the frequency noise of the laser/mode cleaner and to derive a calibrated displacement spectrum of the single arm cavity from the E3 data.

Input Optics

David Tanner
1/4-20 screws for use as the viton-tipped safety screws were shipped to LLO.

2.0 OtherEngineering and Scientific Activities

2.1 Design/Analysis/Fab

Optics Modelling

Bill Kells
This week I have been almost exclusively working on FFT code simulations to come to some final conclusions about how the SB fields behave. The immediate goal is to compare to what MELODY yields. The two use apparently (an subtlely) different algorithms. Are they equivalent? are both "wrong". One intreguing issue is under what circumstances are the +/- SB field amplitudes imbalanced. Many instances of such occur in simulation, and we've seen some evidence of it at LHO. Trying to sort out the real from that due to approximations, etc. in many ways this is an extension of the modeling of SBs pompted by what we had observed in the RC of the full LHO 2k ifo.

Modelling Flattened Modes for Advanced LIGO

Erika D'Ambrosio
I went back on looking at the runs I made by tilting one ITM mirror. Those gave the results Kip showed at the LSC Meeting about the contrast. I had some doubts on the locking procedure since the definition of the phase is strictly related to the chosen basis of modes that generally is the Hermite-Gaussian one.

I also found that the two branches of the recycling cavity are adjusted by a quantity larger than lambda so I tuned by myself the lengths around the value chosen by the code to check whether it has stopped on the top of the resonance curve and it effectively has.

I took another step back since the overall power inside the interferometer is far smaller than what expected both from evaluations and the previous tests with only one cavity in resonance; I put the spherical recycling mirror back instead of the "reshaped" one but the power built up was still small.

Then I started to look at the field maps and I found an asymmetric deformation of the wavefront inside the recycling cavity and I will discover the source. To do that I sneaked a pipe inside the algorithm and added many lines to the code with a view to have informations on the field in more points than the ones the program has been providing.

I am currently debugging such updated version of the code on the CACR machines.

LSC

Mike Zucker
Obtaining quotes from vendors for last bits of ISC fab (photon calibrators and misc. updates to video and sensing table systems) to enable closeout of construction.

Rich Abbott, Flavio Nocera, Mohana Mageswara
LHO MC Servo: Mohana has sent three PCB's to the board house.  We should have the new revision of the MC servo within a day or so.  It will be stuffed and tested immediately

LSC at Livingston: While I was there a week ago, it was brought to my attention that the reset circuits on the whitening filter boards had malfunctioned.  The new revision of the whitening filter uses a commercial reset circuit.

Flavio has been developing test procedures for timing boards and has tested several to date for use in the LHO 4k LSC.

PSL

Peter King
Rich, Ben and I measured the characteristics of a high power photodetector circuit that I have been working on (and off) for the past two months.  The good news is that it exhibits the bandwidth necessary for the intensity stabilization but the output noise will most likely be higher than the photodetector that Ben worked out.  For the record, the photodetector has a 3-dB bandwidth of 110 MHz with 1 dB of gain peaking at 70 MHz.

Lee is currently re-installing the phase-correcting Pockels cell in the laser, after a successful trial of the prototype alignment housing.  The Pockels cell will be installed with the final housing.

Rick Karwoski, Paul Russell

Ben Abbott
The intensity servo DC photodiode preliminary design has been improved thanks to valuable email input from Peter Fritschel, David Shoemaker and Mike Zucker.  The layout is complete, and it will be sent out for fab tomorrow.

Sander Liu
Two each of the 21.5 MHz and 35.5 MHz Frequency Reference cards are now fully functional and ready for system test.

New OSEM Heads

Janeen Romie
Surmet has delivered their final heads. New England Techni-Coil still has about 300 head to wind.

AC OSEMs

Jay Heefner
Another, lower noise prototype stabilized oscillator circuit will be tested at CIT next week. This circuit is similar to the circuit at LLO, but uses lower noise mixers.

ASC/LSC/Digital Suspensions

Jay Heefner
  • 10 Pentek boards will be shipped on 4/6. We should have them early next week.
  • Two Rev B1 QPD whitening boards will be shipped to LLO next week. These boards have the connections needed for the lock acquistion code.
  • 4 LOS Coil Driver chassis have been completed and shipped to LHO. This is the full complement needed for the LHO 4K.

  •  

     

    Rolf Bork, Lori
    Lori has been working on the code for the LVEA LOS coil drivers. This code should be ready end of next week.  In the process, we determined that a single CPU can not handle more than three optics, due to the many filter sections required to provide for the frequency dependent output matrix.  This will then necessitate a harware change, which Jay is incorporating in his drawings.

    Data Acquisition

    Rolf Bork
    Past two weeks have been concentrating on modifications to the DAQ software to accomodate the addition of the Digital Suspension Controller (DSC).  This includes the following changes:

    a) Hardware:


    b) ADCU Software:

    c) DAQ controller:

    GDS

    Daniel Sigg
    Continued with porting DTT to other platforms. Updated all auxiliary packages and DTT itself to use the new configuration scripts and to compile under gcc/solaris.

    Wrote a program to test if it is possible to use the 2D histograms of ROOT as a real-time display for time-frequency plots. This required the implementation of a custom update method which scrolls the plot horizontally---rather than redrawing the whole plot every time a new frequency column is added. This seems to work just fine: A 200 bin x 200 bin color-coded histogram could be scrolled as fast as 50 bins/sec
     
     


    40 Meter Interferometer (Weinstein)



     



    Thermal Noise Interferometer (Libbrecht)


    This week we have been developing an alignment scheme for our arm cavities,
    using the beam transmitted through the mode cleaner.  Finding the cavity
    axis in such a short cavity (1cm) is somewhat subtle because we do not have
    access to the space between the test masses.  We developed a fairly
    reliable alignment scheme last December, when we were sending the beam
    around the mode cleaner and directly into the test cavity, using an
    auxiliary He-Ne to find the
    cavity axis.  Alignment is somewhat more difficult with the mode cleaner
    locked, largely because all of the cavities are on the same
    seismic-isolation stack.  Any manual adjustments made to the steering
    mirrors to bring the beam into the arm cavity disturb the mode cleaner.  We
    are still working on this.
     

    The pneumatic gate valve and 0.015 liter-per-second needle valve for the
    vacuum-pump safety interlock system have arrived, and we expect to begin
    installation of that system soon.
     

    We have also continued to repair the remaining OSEM controllers and expect
    to have all seven working according to spec by this Friday.


    LASTI (Zucker)


    LASTI (Mason, Shoemaker, Harry, Mittleman, MacInnis, Rollins, Zucker)
    ---------------------------------------------------------------------
    Ken Mason is working on the optical layout for the recently proposed
    dual-cavity configuration.  This plan, supported enthusiastically by
    our review board at the recent LSC meeting, will permit tests to more
    closely approach the advanced LIGO displacement noise target by
    increasing the feasible cavity beam size-- if it fits, that is. The
    sticky part is the need to get four beams (two 'arm-cavity' beams and
    the two beams of a 15-meter triangular mode cleaner) to fit through our
    30" beam tube.  So far it looks feasible in AutoCad, but only with
    tight constraints on the footprints of advanced LIGO LOS and SOS
    suspension structures. We're conferring with the suspension folks to
    understand the impact. The alternative (procuring larger beam tubes) is
    something we'd like to avoid.
     

    The custom cleanroom for the BSC is in the final stages of fabrication
    (only a week after releasing the PO!) and is not expected to
    delay the BSC support structure installation scheduled for early May.
     

    We have discussed moving the Stiff Rapid Seismic Prototype experiment
    with the AdLIGO SEI folks and have made a tentative plan to
    decommission it this month to make room near the BSC.
     

    PSL components and SEI installation fixtures continue to pour in; today
    is yet another Big Moving Day with all hands to the pallet jacks to
    reshuffle equipment and make room.


    Data Analysis and Computing (Lazzarini)



     
     

    Simulation and Modeling (Bhawal)

    E2E's near future (~1.5 year) action items are summarized and placed in e2e
    home page (http://www.ligo.caltech.edu/~e2e), "Action Items" under "Core
    Documents".

    Physics Studies
    ---------------
    Biplab and Matt are working on analytical derivation for lock acquisition
    times - first in simple cases.

    Suspension System
    -----------------
    (Virginio) quadruple pendulum suspension simulation:
    - Low frequency behavior of the single and the double chain of quadruple
      pendulum has been implemented.
    - Time domain simulation code is still buggy.
    - The internal modes of the main structures like blades and wire are still
      under debugging.
      Several patches to try to fix this issue have been test
      but each one has some problems.
    - Writing down a short internal document describing the simulation and the
      results obtained
    - Cross coupling effects on the t.f. among the DoF's under study.

    Code Development
    ----------------
    (Hiro) A senario to support the completely frequency domain simulation has
    been discussed. The same box files can be used to generate time series data
    or frequency characteristics directly. This feature is useful for
    (i) serving as nominal noise source generator and for (ii) validating box
    file settings.

    Code Maintenance
    ----------------
    Hiro and Biplab cleaned up few parts of the code.

    E2E at CACR
    -----------
    Ed and Hiro worked to port the simulation code to CACR. The code could
    finally be compiled, but some incompatibility is observed and that issue
    is being pursued.

    Alfi
    ----
    (Bruce) Working on showing box/primitive comments correctly in the
    parameters dialog.

    LIGO Data Analysis System

  • Software Systems (Blackburn)

  •  

     

    The primary focus this week was to stablize LDAS software development
    enough to have a code freeze to allow a complete testing of software
    functionality. Our goal was to maintain compatibility with previous
    LDAS functionality while also having in place all the API pieces to
    allow work on the dataPipeline functionality needed for the inspiral
    MDC to be the driving effort in the next development cycle. The code
    freeze was begun at 6PM on Wednesday and is expected to be in place
    until Monday while the tests are performed. Roughly 20 problem reports
    were closed this week in response to the need to stablize software.

    Only one API functionality was not completed in this release; The
    ability to handle multiple frames in a single frame file and the
    ability to handle frames of arbitrary duration were not completed in
    time. These missing frameAPI functions will be added immediately after
    the release to the development system.

    The eventMonitorAPI is now stable and demonstrates the baseline set
    of functionality needed to support the next MDC. It will however need
    extended support for database tables. In addition, the inspiral upper
    limits group is planning to present a new table design by April 15
    for the inspiral MDC which will have to be captured in the C++ code
    of the eventMonitorAPI.

    The documentation for the dataConditionAPI is very nearly at the 100%
    of the scheduled level for implemented functionality.

    Work has begun on testing the applicability of LAPACK as a baseline
    linear algebra library for the dataConditionAPI. Issues of binding
    this fortran library to our C++ dataConditionAPI and thread safety
    will be first on our lists of activities to verify this candidate.

    Several changes to the wrapperAPI headers were identified and
    coordinated with the MPI group. These changes are needed to support
    BLOBS in the database and to standardize the integer types used for
    GPS timestamps to the type used on the Frame Specification.

  • Hardware Systems (Anderson)

  •  

     

            A highly successful test of the Sun HPSS port at Sun's benchmark center in Beaverton, OR was performed
    with software engineering support from Sun and IBM. This has validated the
    viability of a Sun server based HPSS solution for the central LIGO data
    archive.

            The move of LDAS from the mass storage room to the staging building
    mezzanine area at LHO has been successfully completed, see,
    http://apex.ligo-wa.caltech.edu/~gmendell/ldas_pics.

            The full 1.7TB of data from the E3 run at LHO and LLO have been
    successfully ingested into the archive at Caltech, see,
    http://www.srl.caltech.edu/personnel/sba/ligo/hpss.

            All 28TB of the LDAS disk cache have been delivered and installation
    will be scheduled throughout April and possibly the first half of May.

            The 6000-slot tape library for the central LIGO data archive has
    arrived at Caltech and is being assembled this week in Powell-Booth, see,
    http://www.cacr.caltech.edu/~sarah/pics/robot0401.

            A security, backup, and SNMP management server has been identified
    and ordered for each LDAS system.

            Numerous memory, network switches, cables, 19" equipment racks, and
    UPS's have been ordered to support an initial installation of LDAS at
    MIT, and to effectively integrate the large LDAS disk cache systems at
    each site.

            A Gigabit Ethernet and video card have arrived for installation
    in the new main LDAS software server at Caltech.

            A dual-processor data-conditioning server is now available in
    the ldas-test system at Caltech.

  • Data Analysis Activities
  • Charlton:
    * Continued to work on LAL/FCT interface, particularly the provision of a
    user definable replacement for malloc/free to keep LAL happy

    Shawhan:

    This week, besides working on the database MDC, I spent a significant
    amount of time helping LSC institutions get LIGOtools working properly
    on their computer systems and access LIGO data from the archive.  This
    has led to a number of robustness improvements in the build process.
    The trickiest problem had to do with data access from behind a firewall,
    which prevented the server from notifying the client when the job was
    done.  For this, I had to change the client-server communication
    protocol.

    General Computing (Wallace)


    MIT:
    -Moved/upgraded mailserver to 2.8 machine
    -Removed Sun buggy snmp daemon(s) from all nodes
    -Installed wrappers on some machines
    -Searched for (and browsed) MIT computer policies
    -Compiled list of used/unused ip addresses for our subnet

    Livingston:
    (Shannon and Tom)
    -We have received six pallets of LDAS equipment, which we are
    sorting out.
    -We have received a Dell PC and a Sun Blade 100 for upgrades
    for individual users.
    -We are working on security issues concerning GC and CDS.

    Hanford:
    See Hanford Report.

    CIT:
    (Barbara)
    - Began setting up the reports page for LDAS Equipment.  Added features to
    track user name for adds and edits.  Reworked the authentication a bit.
    - Rebooted pherkab and antares and got the backups working again.  Broke
    the DCC's weekly compact/repair process into smaller pieces and it worked!
    - Installed the new LDAS home page into the cgi/perl script.  Tested today
    and will activate tomorrow.  Updated and installed the cgi/perl script for
    LDCG contacts.
    - Made numerous other changes to the LDAS site -- new software block
    diagram, updates to many software diagram detail pages.
    - Made a number of other web site changes -- LSC transparencies, travel
    links and forms, pending LSC talks, accounts, ...
    - Helped Ed C. import a spreadsheet into Access.
    - Got my router at home working!

    (Lisa)
    -Did monthly backups.
    -Began disabling SNMP services because of the security vulnerability.
    -Installed Sol 8 on an Ultra2 and configured it as a DHCP server on the 125
    subnet. This conflicted with the DHCP on the modem pool, so I reconfigured the
    modem pool to use IP Pools to dole out numbers instead of DHCP.  The modem pool
    can use an external DHCP server, but I think using the IP Pools will be more
    fault tolerant.
    -Installed a wireless access point in the basement.
    -Tested win2k samba over wireless. This requires that the "Allow NetBIOS over
    TCP/IP" be enabled under advanced TCP/IP settings.  Also, instructions for
    enabling plaintext passwords for win2k are in the sys admin FAQ.
    - I am looking for an old printer that supports HP-IB or GP-IB interface for
    wilson house.  Models include the HP2225A thinkjet, 3630A paintjet and 2227
    quietjet plus.  If anyone knows where one of these can be acquired, please let
    me know.
    -Worked with Ed Chargois to get another pile of surplus equipment out of here.
    -Helped Jay with setting up a new win2k laptop for him. It is still having
    p-card issues.
    -I know there was more but I can't remember what.

    (Suresh)
    -Finally made new ES-2810 switch working. It was done by resetting it to
    factory defaults and setting it up in stand-alone. I am still testing it. So far
    the performance looks fine. The old 2810 has been shipped back to Marconi.
    -Tracked down the network problem in Bridge Development Lab in second floor
    bridge. It was a faulty hub sitting on the ceiling tiles.
    -Modified the symbolic link so that the Matlab Release 12 is run when either
    matlab is typed in command line or clicked on dropped down desktop menu.
    -Installed ssh in system nunki, a 502 MHz Sun Blade 100 unit.

    (Larry)
    -Worked a few network issues. Also, worked with Gary and Lisa with the
    wireless setup in the building. Gary has been having too much fun with
    this one.
    -Placing and tracking orders for just about every group here at CIT. Includes
    computers, networking equipment, video equipment and software.
    -Working a number of documentation issues with the rest of the system admin.
    group working on LIGO.
    -Equipment issues have been addressed this past week. There will be some changes
    in the near future for checking out computer equipment. Removed a number of old
    items. Working with SUN to get some old equipment traded in.
    -Continued working on the performance tests of the new SUNBlade units.
    The SUNBlade 100 is a cheap replacement for the Ultra 10 if any amount of cache
    memory is not needed. Its performance is better until cache is needed and then
    the Ultra 10 performs much better.
    The SUNBlade 1000 so far has performed as expected but will not be a replacement
    for the Ultra450 until the 4CPU unit comes out. It is a good dual CPU unit. All
    of the SUNBlade units will only run under the latest version of Solaris 8. They
    are suppose to be able to run under LINUX but we have not had the time to test
    that out(not a high priority at this time).

    (Bruce Sears)
    - Ilog maintenance, additions, and development: (0.25 days)
            - Small amount of general maintenance.

    (Sam)
    Nothing to report but has returned from her travels.


    LIGO II/Advanced R&D (Sanders)


    From Bill Kells:
     

    Also some considerations of the fabrication challenges of Sapphire.
    This is shaping up to develope into the specifications for LIGO II.
     

    From Peter King:
     

    40m & LASTI PSL
    The reference cavity vacuum chamber and parts for the vibration
    isolation stack are currently being baked down in the PSL Lab, using the
    vacuum chamber as the oven.
     

    The Motorola MV162-242 IOCs ordered will hopefully be allowed to be
    returned to Motorola to swap them for the MV162-PA242 IOC. Initially the
    vendor said that the IOCs were too old and that they would not take them
    back. CDS hitman Jay, was called in. Negotiations are apparently in
    progress for their return.
     

    From Peter King:
     

    LASTI
    ===============================
    - Additional power supplies for the suspensions have been ordered and should be
    delivered to MIT by 4/15.
    - The system drawings, rack layout and cross connect lists for the initial two
    suspensions have been completed. Rus Wooley will build the cross connect harness
    and ship to MIT. It should be complete by 4/15.
     
     
     

    The custom VME backplanes have arrived.
     


    For additional information about this report, contact sanders@ligo.caltech.edu