Weekly Report for Week Ending March
29, 2001
The LIGO Executive Committee
Agenda for Monday April 2, 2001 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
-
Announcements
-
LSC Issues (Weiss)
-
Comments on Weekly Report
-
WBS 1 LIGO I Construction (Lindquist)
-
Field Change Orders/Contingency Liens/Change Requests
-
WBS 2 LIGO Lab Operations
-
Administration (Lindquist)
-
Sites (Raab, Coles, Shoemaker, Sanders)
-
Detector (Whitcomb, Coyne)
-
Campus Research Facilities (Weinstein (40 Meter), Libbrecht (TNI), Zucker(LASTI))
-
Data Analysis and Computing (Lazzarini)
-
WBS 3 and 4 Advanced R&D and LIGO II
(Sanders)
Executive Committee only 11:30 - noon
Topics:
Special Items: LHO Building
schedule options regarding commissioning/science run interference, temperature
control spec, energy reduction options at LHO
Special Announcements:
Weekly
Report Highlights
LSC Issues (Weiss)
no report
LIGO I Construction/LIGO Laboratory
Administration (Lindquist)
WBS 1.2 LIGO Operations--Administration
LIGO Weekly Site Telecon (Lindquist)
A site teleconference was held on Thursday, March
29, 2001. Discussion included the end of February costs. We also discussed
the schedule for the building in Hanford relative to the schedule for beginning
science operations. This item will be on the agenda for the Executive Committee
meeting on Monday. The power costs at Hanford are expected to increase
$100K or more as a result of the crisis on the west coast. We will also
put on the agenda for the Monday Executive Committee meeting a discussion
of possible reductions of power usage and the potential impact on science
operations.
The next site telecon is scheduled for Thursday,
April 5, 2001. The list of current actions revised to reflect open actions
assigned through March 29, 2001 may be found at ACTION
LIST.
PROPERTY
MANAGEMENT (Chargois)
From: Ed Chargois <chargois_e@ligo.caltech.edu>
-
Created a LIGO Property Loan Agreement Request with
Register to maintain accountability of all off-Campus
and off-Site Equipment being loaned to other Institutions or subcontracting
Companies.
-
Assisted J. Camp with the packing and shipping of a
Turbo Station, Sn# TSU060/8378 Mdl# C3, acquisition cost $4726.40, to Syracuse
University (S.Penn) on a long term loan agreement. Account Number LIGO.00002-7-NSFLIGO.504800.
-
Updating the Property Data Base to reflect the updating/upgrading
or equipment being provided throughout the LIGO Project by the Systems
Administrators, L. Wallace/L.Bogue.
DOCUMENT
CONTROL CENTER (Turner, Mak)
>From: Linda Turner
- turner@ligo.caltech.edu>
Web pages for the
DCC give simple how-to's for document numbering, easy access to the latest
on-line documents, and search capabilities for the DCC database. Take
a look. . .
ACCOMPLISHMENTS
-
Dealt with last few LSC presentations. Only a
few remain to process and post.
-
Worked with Ed Jasnow on formatting in changes and merges
to the latest cooperative agreement between Caltech-LIGO and the NSF.
-
For Otto Matherny, spent several days working to locate
antiquated documents regarding past ecological and environmental studies
conducted for the Hanford site prior to construction. Also searched
for permits extended to LIGO for building on the DOE land.
-
Sent out brief questionnaire to approximately half of
the LSC attendees for developing an article for the upcoming newsletter.
Response was terrific and quick!
-
Began the process for reordering LIGO polo shirts.
An email will go out by first of next week and an order will be placed
by mid-April. Hopefully, shirts will be here by the next NSF review.
-
Received and began processing for distribution 11 DCN's.
From: Cleveland
Mak <mak_c@ligo.caltech.edu>
-
Finished processing any remaining LSC documents.
-
Electronic documents continue to roll in on a steady basis.
-
Spent considerable time searching for old documents regarding Hanford Land
Use/Permits per Otto Matherny's request.
|
Packages |
Faxes |
| In |
57 |
39 |
| Out |
12 |
42 |
Press here to access
the DOCUMENT CONTROL CENTER
WEB PAGE.
COST SCHEDULE
CONTROL SYSTEMS (Cunningham, Brambila, Akutagawa, Kaufman)
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS
PAYABLE HISTORY DATA.
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
-
Finished up Ernest Orlando Lawrence Berkeley contract
renewal through FY2004 and the prepayment was mailed out. Working on Las
R Shield and General Optics.
-
Placing pcard orders and reconciling monthly charges.
-
Working on updating the master list of the LIGO subcontracts
which is due today for the DCAA auditors.
-
We will be relocating soon and the files will be reduced
at the new location; therefore, I'll be going through the old contracts
and po's which are closed and sending them off to Record Retention or DCC
as appropriate before the move. We expect that we will only keep the correct
and prior fiscal year on one time po's along with open subcontracts in
the office filing cabinets.
From: Florence Kaufman <fkaufman@ligo.caltech.edu>
-
Provided report of his grant to Greg Mendel.
-
Reviewed and made comments on 3 Fabricated Equipment Request Forms from
Dennis Coyne.
-
Started working on reports for March.
SUBCONTRACTS MANAGEMENT (Petrac,
Jasnow)
From: irena@ligo.caltech.edu (Irena Petrac)
From: Ed Jasnow <jasnow@ligo.caltech.edu>
-
Benton County PUD has announced to its major users that
there will be substantial increases in the cost of electricity beginning
October 1, 2001. This will cause a major increase in the facilities budget
for Hanford in Fiscal Year 2002, which was not addressed in our proposal
to the NSF.
Support (Wood)
Rita Torres
-
Checking weekly for incoming LSC reports and plans. Formatted the
report from Harvard-Smithsonian. Scanned year 2000 Attachments A
and submitted to the DCC: LA State U., Brownsville-Texas, Oregon,
Dominguez Hills, Penn State, and Florida. Scanned 2001 documents
for Fermilab: MOU, and Attachments A & Z. Also sent for
LA State U files, their signed Attachment A. Prepared letters to
bidders of RFP IPGS-511 Re: Proposal Cost Estimates Update.
-
Researched some resistor part numbers that Newark forgot to ship.
Submitted a list of these to Newark, they can now complete the order.
A pair of prescription glasses arrived in my name from GPT Glendale, I
tracked down the rightful owner.
-
Reconciled 5 Pcard purchases this week, needed backup information for 4
of them. Updated site trips on the web.
Dorothy Lloyd
-
Processed the usual requisitions, invoices and receiving on-line. For more
detail, see "Cost Schedule Control Systems" report by Esther Cunningham.
-
Tracked and followed up on invoice problems.
-
Reviewed and recorded payments processed by Esther for the week of
March 19, on contract summary sheets and in the LIGO database.
-
Continue to monitor contract and blanket order encumbrance and notify task
managers when supplements are needed.
-
Jim continues with data entry in the LIGO database and also help out in
the travel and DCC areas.
Irene Baldon
-
The bulk of this week dealt with a number of problems with P-Card charges,
reconciling, expense reports, travel audit and meetings regarding P-Card
procedures. I was also ill for one (1) day.
-
Processed six (6) new trips (including Advance Checks written and hotel/car
rental authorizations filled out and FAXed to appropriate vendors in various
locations); five (5) trips have been ticketed and are awaiting completion
of necessary paper work; and eight (8) trips are pending final approval
before tickets can be issued.
-
Completed twelve (12) Expense Reports and have forty (40) Expense Reports
to work on. I'm holding two (2) reports which need a check from the
traveler before processing and an additional four(4) which need information
from the traveler. Jim Covington completed ten (10) Expense Reports
and has twelve (12) reports that he is working on. I continue to
train and supervise him on expense reports.
-
I reconciled seventy-four (74) items on my P-Card. Assisted a few
travelers with their reconciling and/or data entry.
-
Prepared the Travel/Vacation Itinerary for the Week of March 19, 2001.
Performed normal recording and filing associated with Travel and Reimbursement.
Also performed miscellaneous duties as requested by various members of
the LIGO Project here at Caltech as well as from members of the staffs
of each of the two (2) sites. I continue to do MIT's travel
to the sites for installation activities and also to assist them wherever
possible.
Elizabeth K. Wood
-
As part of the implementation of travel with the pcard, we need to re-examine
how LIGO personnel deal with their trips. EVERYONE needs to provide
Irene with a travel authorization form prior to travel. In addition,
if you have a pcard, when you turn in your travel expense report, please
turn in the updated order log to which you reconciled your travel-related
expenses. It will help you and Travel Audit in preparing and auditing
your expense report. We will be announcing and implementing more
fine tuning for pcard travel in the near future.
-
I have been working on two proposals in FastLane.
-
And doing lots of personnel stuff.
Advanced LIGO (Frey, Petrac)
From: Thomas Frey <tfrey@ligo.caltech.edu>
Progress Period from 03.23 to 03.29
Accomplishments:
-
Out of Office on Monday the 23rd.
-
Proposal plan development for Advanced LIGO MRE.
-
Updating on hold until after NSF review and when proposal strategy is announced.
-
Development of the TNI work plan and schedule has no change in status.
-
Project Plan for the 40-Meter Lab Upgrade continues.
-
Followed up on data requests for progress data as of 03.30.01 that are
due Friday the 30th.
-
Planning process for the LASTI project at MIT is in progress.
-
Followed up on data requests for progress data as of 03.30.01 that are
due Friday the 30th.
-
Received request from David to re-baseline the LASTI plan. Also received
Dennis Coyne's comments regarding same.
-
Continue to test the Cost Book Tool. (Highest Priority)
-
Continue mapping and formatting of OPS cost data for input.
-
Continue preparing data representing the most recent changes.
-
Produced weekly status report for Phil due to his work load.
-
Development of the Advanced LIGO Project Controls Guidebook continues.
-
Project Web Site for posting schedule and progress related data continues
to be updated with the latest and greatest.
Schedule 03.30 to 04.05:
-
Next weekly Advanced LIGO Project Controls meeting will be scheduled for
April 2nd.
-
Advanced LIGO MRE Proposal
-
Updating of schedule on hold until after NSF review and when proposal strategy
is announced.
-
Highest priority is the development of the Cost Estimate.
-
Will continue to pursue all other sub system schedules.
-
Will initiate the updating of the COC and AOS schedules.
-
Will Continue to develop the TNI Schedule.
-
Will begin integration into the P3 Database.
-
Will Continue to update the LASTI Schedule with progress.
-
Will update the plan with progress as of 03.30.01 and Post to site.
-
Will issue data requests for progress data as of 04.13.01 that are due
Friday the 13th.
-
Will begin to incorporate changes to the baseline plan.
-
Will continue updating the 40 meter schedule and incorporate any changes.
-
Will update the plan with progress as of 03.30.01 and Post to site.
-
Will issue data requests for progress data as of 04.13.01 that are due
Friday the 13th.
-
Continue to test the Cost Book Tool.
-
Cost Book Tool development continues. (Highest Priority Task)
-
Will Continue data changes for BK.
-
Will continue ops cost data input.
-
Will continue the development of the Advanced LIGO Project Web Site.
-
Will continue the development of the Advanced LIGO Project Controls Guide
Book.
WBS 1.4.1.2 Project Controls (LIGO Construction)
Reports (Lindquist)
-
I have received several contributions for an end-of-February
Quarterly Progress Report and the report is in progress.
-
Also working with David Shoemaker to set up assignments
for Advanced R&D Annual Report. We should be submitting this report
(necessary to get FY 2001 funding) over the next month or so.
Change Control/Contingency (Lindquist)
The following Change Requests have
been submitted:
| CR-000018 |
WBS 1.1.4 |
Curbing for Service Roads at Livingston |
G. Stapfer |
| CR-000019 |
WBS 1.2 |
Additional Lab Equipment |
D. Coyne |
| CR-000020 |
WBS 1.1.4 |
Staging Building and Renovations to Existing Building--Livigston |
F. Asiri |
| CR-010001 |
WBS 1.1.4 |
Return of Unused Construction Budget To Contingency |
F. Asiri |
Press for the latest Contingency
Needs Projection.
COST SCHEDULE
CONTROL SYSTEMS (Duncan, Akutagawa)
From: Kris Duncan <kris@ligo.caltech.edu>
-
Completed the February 2001 LIGO Quarterly and NSF Reports.
-
Continued working on the Responsibility Assignment Matrix
for LIGO construction accounts incorporating negotiated change request's
to date.
-
Continued with construction contract/work package close-out.
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
-
I received the MIT invoice and the twonk report for the month of February.
Due to the timing of the new money being received by MIT the two did not
match up. MIT will issue a new invoice total next month, and I will
get it paid then.
-
I continue to reviewed the open encumbrances on the Construction and Advanced
R&D accounts to see if the requested removals have been made. I will
continue to review these accounts weekly until all encumbrances have been
removed (Remember, I can only get these errors corrected if the Task Managers
point them out to me).
-
The financial reports on the web provide supporting detail.
-
Reminder: An updated list of all OPEN LIGO account numbers have
been posted on the LIGO internal bulletin board. Please use these lists
when you need a LIGO account number (or make yourself a printed copy for
quick references).
-
please note that the
FY00 LIGO Operation account numbers expired on November 30, 2000, and that
the new account numbers can be found at:
SUBCONTRACTS MANAGEMENT (Petrac,
Jasnow)
From: Ed Jasnow <jasnow@ligo.caltech.edu>
-
The NSF has forwarded comments on the contract for A/E
services for the Hanford OSB East Building with NTD. These comments were
addressed, and we are awaiting approval.
-
Discussions concerning schedule have revealed that the
Hanford OSB East Building needs to have the noisiest part of its construction
completed by February 2002. Since this is substantially earlier than originally
thought, the concept of design/build for some of the major elements is
being considered. A decision will be reached after further discussions.
From: irena@ligo.caltech.edu (Irena Petrac)
Quality/Safety (Tyler)
>From: Bill Tyler <tyler@ligo.caltech.edu>
LIGO Hanford Observatory (LHO) Operations
(Raab)
General Items:
--------------
(F. Raab)
Eucon mobilized its gravel crushing operation to North Richland at 7pm
on 3/28. We will be monitoring the effects of the mining operation
to
see if it violates the ambient seismic spectrum at LIGO. The distance
is approximately 10 miles from the Y arm.
Installation & Re-Installation
------------------------------
(D. Cook)
We finally were able to wind up the 4k IO and mode cleaner alignments
and
HAMs 1,2,3 have their doors in place. We will place a metal cover over
the
cloth cover at the spool opening to reduce air currents and keep things
cleaner. The RM-4k optical lever transmitter will need to be repositioned
on the pier using an offset mounting system to allow the beam to clear
the
view ports and IO baffle. The reciever side will need to have some
modifications made as well. Hugh and Gerado have mocked up the optical
lever position and currently have the beam path worked out. The FMx-2k
safety stops and OSEMs have been replaced and the alignment will follow.
The ITMx-2k OSEMs and safety stops were changed out and alignment is
done.
The ITMy-2k is next. We will be installing the second verticle PLX
and
finishing the ITMy-2k alignment today. We will steer the ITMx-4k
optical
lever beams through the arm cavity baffle, scribe it and remove it
hopefully
today as well. Mark Barton is working with Betsy on 2k SOS optics.
We are
adding additional camera view ports to several areas to aid with
commisioning and alignment. We have a camera mounted at the APS port
ready
to steer the FMx -2k. We continue to parallel
the 2k and 4k
activities with the help of many. Thanks once
again to All.
LIGO Livingston Observatory (LLO) Operations
(Coles)
Operations: We are continuing control room operator support after normal
working hours
as needed for the commissioning effort. We are continuing the mix of
operations specialist duties as 50% control room support and 50% "other"
which consists of LOS circuit board repairs, vacuum bake support for LHO
and the 40 meter, LHO optics repair support at
LHO, shipping and receiving, particle counter repair, CDS software
upgrades
and refinements, on going work on getting a set of base values for
all OSEM
coils (L&R), continuing work on ISCT3 table alignment, ISCT4 installation
of safety hardware, and mode cleaner alignment. (Rich Riesen)
GC: Configured the Fore 2810 in the communications room. This will allow
100
mbit connectivity for several more machines. (Shannon Roddy)
LDAS: The main breaker panel and the wiring has been installed in the
Mass
Storage Room for the incoming LDAS equipment. We still need to run
the circuits
etc for the individual outlets but the main breakers are in. (Shannon
Roddy)
Facilities The construction of the new building is going ahead on schedule.
The changes for the handicapped elevator are being finalized and the
affected drawings will be issued as revision -1. (Gerry Stapfer)
Detector/Technical Support (Whitcomb,
Coyne)
1.1 LHO INSTALLATION & COMMISSIONING
2km & Vertex Re-alignment
Doug Cook (reporting for the team)
-
The 2 km re-alignment started this week. A procedure (E010057-B) has been
define to allow re-alignment from the two spool pieces already removed
for the 4 km IFO alignmen. Tooling/mounting modifications to support this
procedure have been completed.
-
New OSEM and modified safety/earthquake stop kits have been prepared and
installation is well underway. The FMx-2k safety stops have been replaced
and I'll finish up the ITMx-2k OSEM and tip change out and alignment by
noon. I'll start the ITMy-2k next by installing the second PLX and finishing
the alignment today.
-
ETMy-2k has been resuspended
-
2 km Small Optics Suspensions are being re-assembled; all new OSEMs have
been received for the small optics.
-
We will steer the ITMx-4k optical lever beams through the arm cavity baffle,
scribe it and put it down (so as not to impede finding the arm cavity)
hopefully today as well.
-
Preparations have been made for setting up two COS autocollimators: a power
cable was ordered for the second 500 mW, 940 nm autocollimator (due to
arrive 3/29), the laser power supply was received from MIT, and a second
post mount was made. A camera tripod is set up for viewing the output beams
with an IR video camera through the output ports in HAM9 and HAM10.
4-k IOO Installation
Dave Tanner (reporting for the IO team)
The HAM 1 and HAM 2 doors have been replaced. A new technique for
setting the Earthquake stops using a temporary optical lever was
employed which ensures that the face stops are positioned 0.5 mm from
the optics. The optics are then swept there full bias range to check
that the stops are not interfering with the optics. In addition each
mode of the optic ie pitch and yaw are also rung up separately to ensure
that the stops are not touching anything. We tested this technique
on a
bench and found that the stops could be reproduceably positioned without
the need for a difficult marginally accurate back breaking inspection.
The viewports on HAM 1 will be returned to the
conventional centered viewports because some how nowbody told me that
we
would be deviating from the 2K in this regard, so I set the output
beams
up to come out standard centered viewports. I do not believe that this
will impinge on performance of the modecleaner and the change was
cleared by Dennis Coyne. Unfortunately I only noticed the change when
we
had already put the doors back on HAM 1.
The new layout for the 2K PSL/IOO table has been finalized. Guido did
the
new mode matching calculations and I independently verified them. Rick
and Malik are in the process of laying out this table.
We are currently staging to replace the optics in the 2K interferometer
and all the 2K optics should be re-installed by early next week if
all
things go well.
1.2LLO INSTALLATION & COMMISSIONING
Commissioning
Rai Weiss
No report.
Rich Abbott
While at LLO, I worked did some repairs on the LSC system (whitening
filter board) and went through the ASC system in order to write a short
report on its status. A list of things necessary to get two wavefront
sensors activated was prepared.
E3 Data Analysis
Peter Fritschel
Correlation of the power lines between LHO & LLO.
I have been looking at the coherence between the two sites' power line
monitors and magnetometers, at 60 Hz and harmonics. Observations to
date:
1. The broadband noise on the line monitors (between the line
frequency/harmonic peaks) is about 10x higher at LLO than at LHO. The
LHO
line monitors show a lot of structure between the line harmonics, but
any
such structure on the LLO lines is masked by the higher broadband noise.
2. At a given site, the coherence between a line monitor and a
magnetometer is essentially unity at the line frequency and harmonics.
3. Coherence between sites: The coherence between a line monitor at
LLO &
a line monitor at LHO (@60 Hz) is essentially unity over short time
scales
(t < 60 sec), but becomes small over time scales longer than a few
hundred
seconds. For example, ten coherence measurements over 1000 seconds
(each)
yielded coherence values between 0.01 - 0.1. Over 10,000 seconds, one
measurement gave a coherence of ~0.001.
2.0 OtherEngineering and Scientific Activities
2.1 Design/Analysis/Fab
Embedded Controller Board (MVME162) Upgrade
Jay Heefner
9 MVME162-P242 CPUs have been shipped back to the manufacturer and
will be
exchanged for MVME-PA262 CPUs. Rumor has it that these units will be
able to run
EPICS
ASC/LSC/SUS
Jay Heefner
- Rev B of the Universal Dewhitening Board has been sent out for fab.
and boards
are due back by 4/1. Rev B includes the ability to jumper out filter
sections
and the possiblity of "softening" the response of the filter to allow
for better
IFO locking during commissioning.
- A Satellite Amplifier adapter board has been designed and sent out
for fab.
This board will adapt the old satellite amps to the new digital suspension
PD
interface and coil driver boards.
- 5 more LOS Coil driver chassis have been completed and tested. They
will be
sent to LHO for installation on the 4K.
- ADCs procurred by LIGO have arrived at Pentek and they should be
shipping us
more modules by next week.
Optics
GariLynn Billingsley
Dave Reitze is sending IO optics and blanks to me, for rework, polishing
and coating.
I'm building a list of LIGO optics so that the general user can easily
find specification/drawing information for individual part optics.
As optics are re-polished they are not always built to the original
specification as indicated by the serial number, but may be reused for
another purpose. This list will be filed in the DCC and will provide
a means of tracking the current status of an optic. Under the title
"data package" there will be a link to the scanned in test results for
each optic. This process has been started, some Beam splitter data
packages can already be found in DCC/OUT. I will complete those links
when the documents have a permanent home in the DCC.
While it's being built the list will reside at:
http://www.ligo.caltech.edu/~gari/COCAsBuilt.htm
After it is filed in the DCC you will be able to find a link at:
http://www.ligo.caltech.edu/~gari/
LSC
Rich Abbott, Flavio Nocera, Mohana Mageswara
MC servo model has been updated with parts that are available to speed
up the circuit response. A detailed analysis of the whole servo system
model supplied by Peter F. and Nergis is underway to ensure we are within
the design limits.
Sent out the MC Servo PCB to the board house for fabrication. Now doing
the new design DC readout module simulations and also fixing some of the
PCB errors which are on the LSC Whitening Anti Aliasing Boards which are
needed for the 4K arm. All other aspects of the 4k modecleaner electronics
seem to be in line for delivery. Have arranged with Peter King to
use the laser in the basement of Lauritson lab to do a high power test
of the RFPD in an effort to sort out the saturation problem and match results
with the simulations.
PSL
Peter King
In an exercise to see if we could optically contact optics
together, two sets of precision flats were optically contacted together.
For one set the LIGO optics cleaning procedure was followed, for the
other
set cleaning with only acetone was done. Both sets have not been
separated
yet, despite numerous tries - including soaking in a Liquinox solution
and
agitating for 10 minutes. The results gives us some confidence
that we
should be able to fabricate our own reference cavities and the next
generation of pre-modecleaner.
The intensity noise before and after the high finesse pre-modecleaner
was
measured. The cavity bandwidth of the pre-modecleaner is consistent
with
the expected value and should provide sufficient filtering of the intensity
noise at around 25 MHz.
NPRO #170 will be returned to Lightwave for repair. This is the
second
time in my project memory that this has happened to this particular
NPRO.
Rich Abbott, Peter ing, Ben Abbott
Rich, Ben and I measured the characteristics of the current shunt actuator
from 1 kHz to 10 MHz at various points in the system. Both the transfer
function from current shunt drive to light out and current shunt drive
to current out were measured. As an aside to the above measurement, the
modified PDA-55 response was flat
to 10 MHz, as measured using the test laser at the Wilson house.
The photodetector exhibited some gain peaking at 26 MHz, wherethe peak
was approximately 7 dB higher. The data (once analyzed) will yield the
response of the electronics and the laser process independently and should
help form a basis for the further development of the intensity servo by
Rick Karwoski.
Ben Abbott
The intensity servo DC photodiode preliminary design is complete.
The design document is available on my website here (www.ligo.caltech.edu/~babbott).
If anyone would care to review the design and give me feedback, the
input would be most welcome.
Rick Karwoski, Paul Russell
-
PSL custom boards -- We have been waiting for components for the final
two 80 MHz VCO boards. The boards have been completed, they are in the
Lab now and are ready for test. We now have the required quantity of Frequency
Stabilization boards for LASTI and 40m. Testing continues on the
Frequency stabilization boards.
-
Cross-connect panels -- A single PSL cross-connect panel exists. There
has been no progress on a second; PR's attention remains focused on Intensity
Stabilization support.
-
Intensity stabilization. -- An informal design review was conducted
on Tuesday. As reported last week, photo-detector front-end electronics
has been completed; it is in test and will be integrated with the
Lauritsen equipment.
LIGO Tri-Net Stations
Szabi Marka
I created a script+web interface (CSAI) to display the seismic activity
at both
LHO (http://blue.ligo-wa.caltech.edu/gds/TriNet/)
and
LLO (http://london.ligo-la.caltech.edu/gds/TriNet/).
Each web page contains plots of the triaxial ground velocity history
of both
observatories for the last three hours. It is automatically refreshed
to
include recent data. Presently it provides easy access to calibrated
data (mm/s), simplified detection of potentially disturbing seismic
activity and effortless comparison of seismic activity at the sites.
It
is a work in progress; I welcome your comments, ideas and suggestions.
Help me make it better!
Our recently released document
(http://www.ligo.caltech.edu/docs/T/T000131-00.pdf)
is available from
the DCC or linked to the CSAI web page. It describes how to download
data directly from the LIGO-TriNet dataloggers via their web interface.
PEM Tiltmeters
Szabi Marka
I received an interesting document from GeoTech Inc. the maker of our
seismometer. The paper describes in detail the sources of tiltmeter
temperature drift and provides hints on how to deal with it. The scanned
doc is available from the DCC
(http://www.ligo.caltech.edu/docs/E/E010059-00.pdf).
New OSEMs
Janeen Romie
Micro Hybrid Dimensions reports that they'll deliver the new
circuit boards on 4/30. Myron reports that Laser Services has done
a
great job with laser marking the coated heads. He also reports that
Surmet shall finish coating the heads by 3/30. He will clean and inspect
the heads and send them to Laser Services next week.
Doug Cook has ordered more PAM brackets and screws.
Oliver delivered 60 pigtails (52 long and 8 shorts) to LLO. Rich
has
sent the pigtails along with the cleaned and baked heads (48 long and
53
short) to LHO for processing.
GDS
Daniel Sigg
Started preparations for porting DTT to other platforms. The first
step
is to make DTT and its auxiliary packages compile under solaris/gcc.
The makefiles must be completely rewritten to support multi platform
configuration and setup. The first step has been completed for the
algorithm, calibration and gui extension packages. Took the opportunity
to upgrade to ROOT version 3 which required some small updates in
the GUI package. Looked into the possibility of porting to Windows.
This may be doable if we get a UNIX/POSIX emulation software.
Drop
me an e-mail if you are interested (assuming
you have read this far).
A new DMT machine has been shipped to LLO (dual 1GHz Intel, Linux,
1GB RAM, gigabit ethernet).
DMT
John Zweizig
This week I spent mostly fixing bug in the DMT software. Most importantly,
with the help of Alex Ivanov I was able to locate the memory leak in
FrameCPP that has been adversely affecting the stability of DMT monitors
for the last few weeks. I have also chased down and fixed code that
is not
faulty as it stands, but will cause problems if ported to linux because
of
the byte ordering. I have also been updai\ting the documentation of
moitors I have written.
2.1 Issues
no new issues
40 Meter Interferometer (Weinstein)
-
Ben Abbott has installed all major parts in the Data Aquisition Rack at
the 40m. The list of installed components includes: a reflective memory
disconnect module, two anti-alias filter boards, an empty VME split backplane
crate, a SUN Ultra 60 (frame building and data logging), a disk array,
and a +/- 5V power supply. This system will be sufficient to log 64 analog
channels to frames (we'll start with PEM seismic equipment), as well as
EPICS info from the vacuum and PEM (STACIS monitoring, dust, weather, etc)
systems.
-
Rolf Bork gave us an overview of the (eventual, full) reflective memory
loops for the ISC, the suspension controls, and the DAQ. We'll need Frame
Broadcast service and Network Data Serving Repeaters in order to run DMT,
dataviewer, and GDS tools.
-
Jay Heefner resports that the modifications to the digital suspension controllers
for the test mass optics (5" diameter, 2" thick) will be straightforward.
-
Ben Abbott reports that the intolerably noisy power conditioner for the
PSL will be swapped with a replacement by the manufacturer; if that doesn't
reduce the noise to acceptable levels, we will have to purchase a different
(probably more expensive and bigger) device.
-
Dennis Ugolini reports that all vacuum control hardware is ready for a
full system test, to begin this Friday. The EPICS state code and databases
have been updated, we can now use EPICS GUIs to control almost all the
hardware. This will all be tested thoroughly before we attempt to pump
down in the next 2 weeks or so.
-
Seismic testing and monitoring: We have completed two rounds of measurements
of the STACIS seismic isolators, using a pair of 3-axis Barry Controls
geophones on loan from MIT. This past week, Szabi Marka brought over a
pair of 3-axis Guralp CMG-40T seismometers, and took data all week. The
results confirm the geophone measurements, with higher precision: The floor
to top of STACIS transfer function has a broad peak of +3 dB in the 0.5
Hz range, then it falls to -25 dB (vertical) or -20 dB (horizontal) in
the 1 - 20 Hz range. (See stacis.pdf
for a complete description). Neither instrument has much measuring power
above 20 Hz. We have purchased 6 Wilcoxon 731A accelerometers and will
use them to probe the 10 - 200 Hz region, where we hope to see evidence
of the passive isolation. We plan on purchasing low-cost low-frequency
geophones (Kinemetrics EpiSensors?) to replace the on-loan devices for
long-term monitoring (along with the accelerometers).
-
Rick Karwoski reports that one PSL electronics cross-connect is complete;
two are needed for the 40m and LASTI. The PMC and FSS boards are complete
for both PSLs.
-
Steve Vass is declaring the construction work at
the 40m complete(!). Over the next 2 weeks, we will clean up and convert
to clean-room conditions, in preparation for PSL installation.
-
Steve Vass, Larry Jones, and Mike Smith are compiling a complete list of
electrical feedthroughs into the vacuum system, and optical ports. It will
not be possible to establish the form of the feedthroughs and the in-vacuum
cabling from the optical table down the stack to the feedthroughs, until
the question of what cabling is required for the modulated OSEMs (twisted
pair or ribbon). This is a high priority!
-
Larry Jones reports that the last big piece of vacuum hardware, the 29.5"
adjustable bellows, will be shipped on April 23, directly to Allied for
cleaning / baking / testing. Steve Vass will package and ship to Allied
the remaining big pieces (already in hand).
-
Larry is reviewing the design of the mechanical supports for the cameras
that view the suspended optics, and the tables that support the optical
levers.
-
AJW has released an updated "Conceptual Design of the 40 meter Laboratory
Upgrade for prototyping a Advanced LIGO Interferometer",
40m_cdr.pdf.
This document is still a very rough draft, but comments are much appreciated!
-
While working on tolerances for mirror radii of curvature
(ROC) it occured to me that we may want to re-evaluate this.
-
The plan has been to make 40m arm cavities with flat
ITMs (so that we can view the beam waist at the ITM), and an optimally-stable
g-factor of 1/3, yielding an ETM ROC of 57 meters, and spot sizes of 3.03
mm at the ITM and 5.25 mm at the ETM.
-
LIGO I arms have g-factor = 0.3; ETM ROC = 7400,
ITM ROC = 14540 m; and spot sizes of 36.3 mm at the ITM and 45.6 mm at
the ETM.
-
Ken Strain & Peter Fritschel propose blowing
up the beam for Advanced LIGO, to reduce thermoelastic noise; for sapphire,
this could be, eg, g-factor = 0.86; ETM ROC = 54,000, ITM ROC = 54,000
m; and spot sizes of 60.0 mm at the ITM and 60.0 mm at the ETM.
Is there any good reason for considering doing something
similar at the 40m, given our stated desire to be as high-fidelity to the
optical configuration and control of Advanced LIGO as possible?
-
no matter what we'll do, we'll never get beams as
big as AdvLIGO;
-
we'll have fused silica mirrors, negligible thermoelastic
noise;
-
plenty of brownian noise, however;
-
we'll operate with a LIGO I laser, probably at <=
1 watt; so small (I think??) thermal lensing effects;
-
perhaps the different problems associated with higher-g-factor
cavities (eg, very different Guoy phase shifts) is worth prototyping at
the 40m?
Comments, opinions, suggestions on this are appreciated;
we'd like to settle on the ROC as soon as possible.
Thermal Noise Interferometer (Libbrecht)
This week we aligned the TNI suspended mode cleaner and locked it in
air.
We also continued checking and repairing our OSEM controllers, and
we have
constructed and tested one power-line isolation transformer to be used
for
eliminating ground loops. We installed one of our new, four-pin
BNC
feedthroughs on the vacuum chamber, and next we expect to begin aligning
our arm cavities.
LASTI (Zucker)
no report
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Bhawal)
Telephone conference with LHO
LHO : Rick, Michael
CIT : Biplab, Matt, Andrea, Hiro
(0) Lock acquisition issues, if/what ever it shows up, will be taken
care
by Matt, with whatever necessary assistance by others.
(1) In the next 6 months, the main focus is to make the e2e simulation
more realistic to simulate the inlock state LIGO performance by
incroprorating site specific parameters, like seismic motion, stack
transfer functions, etc. After that, the focus is to identify problems
to which simulation can be used to improve the LIGO performance.
(2) Once per month, there will be a telephone conference to confirm
the
progress and discuss the next plan.
(3) 1 week per month, Hiro or Biplab or someone will travel to LHO and
incorporate the measurements done by Rick or Michael into the model,
and
discuss the future plan.
(4) Hiro will summarize the action items to be done in the coming 6
months.
(5) 4k IFO simulation needs update of a database file, e2eDB.mcr. This
will be tested at CIT, and will be passed around to LHO and LLO.
(6) The noise curve generation will be setup so that people can
easily generate noise curves by various sources.
Code Development
----------------
(Andrea) Implemented a module for linear prediction based on the Burg
algorithm. The purpose is to propose a replacement for the "delay"
module
at least in those cases where one-step in the simulation can be accurately
modeled with an IIR filter.
Alfi
----
(Bruce) Finished cleaning code for ports. Should finish Problem
Report
202 (Same port name problem) and be able to start on implementing
connection junctions.
LIGO Data Analysis System
Software Systems (Blackburn)
Several changes to the frameAPI software began this week. The performance
for
concatenating data from sequential frames has been enhanced through
a rework
of the code by about a factor of 30. Also a memory leak in the frameCPP
I/O
library was identified and fixed. The effort began to support reading
of
frame
files having multisecond frames.
Enough of the eventMonitorAPI code materialized this week to include
it in
the
nightly build of LDAS for the development system. It is now up and
running
on
the LDAS-DEV system and able to receive and parse data from wrapperAPIs.
It
is
also able to separate the database, state, and multidim data from the
wrapper's
output sending the multidim to users and state to file. More work is
needed
to
fully support the database.
Guild was updated this week to support the metadataAPI's ability to
work
with
multible database table simultaneously.
More test code was developed this week to improve the performance of
our
code
test suite. New tests exercise additional components of the lightWeightAPI
and
the frameAPI.
The dataConditionAPI group worked mostly on documentation this week.
Some
effort has been put into tracking down a segmentation fault which occurs
sometimes when multiple ffts are performed concurrently.
The big news for this week was the first LDAS
user command based on the new
dataPipeline command was stitched together
to send data almost fully end-to-
end. Data was read in from frame files using
the frameAPI. This data was
then
translated into the ILWD format and sent to
the dataCondtionAPI where it was
pushed into a call-chain and a power-spectrum
was calculated. The original
time series data along with the calculated
power-spectrum were then bundled
together and sent to a wrapperAPI job which
was started by the mpiAPI as
part of the analysis pipeline flow control.
The wrapperAPI called a
"trivial"
shared object provided by the LSC and the
results from this wrapperAPI
search
were shipped off to the eventMonitorAPI where
the three sub-components of
data were recognized and parsed out and then
sent to their respective
destinations (file, lightWeightAPI, metaDataAPI).
Each step along the way
was managed by the managerAPI. No verification
of the results have been made
but are on the action list for next thing
to do.
Hardware Systems (Anderson)
The first components of the LDAS Phase I procurement
(large disk farm and
tape silo) have arrived, and the remainder
is either in transit or
scheduled to ship on Fri Mar 30.
The purchase requisitions for the first component of the LDAS Engineering
run
Beowulf systems have been submitted.
An integrated system backup, security monitor, and SNMP configuration
server
has been specified for each of the LDAS installations and will be ordered
shortly.
LDAS activity at LHO:
1) The move of the LDAS hardware from the mass
storage room to the
staging building mezzanine has begun. Thus
the ldas system at LHO will
be down Thu Mar 29 and Fri Mar 30. The plan
is to complete the move by
Friday evening.
2) A 3Com 8-port 10/100 ethernet switch was installed and tested on
the
ldas network. This will provide temporary network support between the
computer user and control rooms and the new ldas location.
3) Plans for backups of the ldas system were investigated and
discussed. A script was written that can do basic backups, though
some
minor fine tuning is needed. More work is needed to develop the best
strategy for backing up the meta database.
4) I've begun installing on my computer lal, lalwrapper, wrapperAPI,
and
the supporting packages needed to write search code.
LDAS activity at LLO:
(Roddy)
The main breaker panel and the wiring has been installed in the Mass
Storage Room for the incoming LDAS equipment. We still need to
run the circuits
etc for the individual outlets but the main breakers are in.
Data Analysis Activities
* Data analysis: studying the framecpp and the framebuilder code with
the purpose of setting up a interface for frame generation to be used
both in the
E2E and in digesting external formats, to prepare for ingestion in
(and
testing of) the frameAPI.
* Network analysis: contacted Cella about
the common use of Grid (better, of Globus) for data exchange.
Planning to meet on this subject with him
during my stay in Italy.
General Computing (Wallace)
MIT:
(Keith)
-Rebuilt several SUN machines with Solaris 2.8
-Created print queue for ledger sized prints
-Investigated freeware CORBA orb (omniORB)
-Verified backup mail server working with MX
record entries
-Preparing to start work on the SUN 450 system for LDAS.
Larry has ordered a number of boards that will need to
be installed.
Livingstson:
(Shannon & Tom)
-Returned the equipment used at the LSC conference.
-Working on setting up a more permanent network monitoring system.
-Received the SUN Blade100
-Configure the FORE 2810 and have connected a few machines to it.
Hanford:
(Christine)
See Hanford weekly report.
CIT:
(Lisa)
-Wrote a web page on how to configure printers in staroffice (solaris)
-Installed samba version 2.0.7 on luna. This will give us a good
test
environment before installing it on sirius.
-Got scp working on cdssol6 and rana in the 40meter.
-Currently trying to recover files off a virus infected pc.
-Worked on some p-card problems
-Started looking into putting up a new DHCP server.
-This week had a worse round of pc problems than usual.
(Barbara)
- Finished touchups to DCC log search tool and updated number reservation
tool. I plan to install these next week.
- Posted another iteration of LDAS home page and received comments.
I'm
installing the new page into the cgi script.
- Added a new LSC web page with abstracts for upcoming presentations.
Continued to post LSC transparencies. Added missing talks to
web page as
gray links. Made other quick web site changes -- bulletin boards,
mou's,
talks, etc.
- Ran the pherkab backup by hand because it hasn't been running.
I will
reenter the schedule in TimeTarget to see if that fixes the problem.
Also
restarted the DCC job that compacts and repairs the database.
It still
hangs occasionally so next I'm going to try and break it into several
smaller jobs.
- Continued efforts to get my router working. According to one
web site,
there is a unique situation with my ISP so I'm going to call the router
vendor tomorrow.
(Suresh)
-Installed a PC card in Peter King's Sun workstation and also swapped
the two
hard drives from earlier system.
-Worked with Larry to do some cabling in the computer room of the bridge.
This
was done to replace Cat 5 cable connected to web/DNS server "ligo"
with a new
one.
-Performed thorough testing of ES 2810 switch. Contacted technical
support at
Marconi for its replacement which is expected today (March 29).
-Made a backup copy of approximately 53 Giga Byte of old data from
sargas to a
AIT tape.
-Resolved the ideas running problem by making appropriate entree in
NIS+
table.
-Worked on e-mail aliases.
(Sam)
-Out interviewing.
(Larry)
-Some good news. We finally received the SUN Blade1000 unit that we
had ordered
in Oct. of last year. Preliminary tests show it to be faster than a
dual SPARC60
in all cases. In Biplap's Modeler test it is run 1.6 X's faster than
the SUN450
per CPU (clock speed ratio is ~1.8:1)
The SUN Blade100 unit is still being setup for testing but for the
money appears
to be a good box.
-Finalized the FORE maintenance contract and it is now going through
the system.
-Repaired a couple of computers. Working on a new configuration for
the SUN
Ultra 10's and Solaris 8.
-Made a number of purchases for memory, disk upgrades and related equipment.
-Was able to get the P-card s/w working on a PC that was having problems
with the application.
-Worked a few minor network problems and resolved a couple of application
issues.
[Bruce Sears]
* (BS) Ilog maintenance, additions, and development:
- Small amount of general
maintenance.
--
LIGO II/Advanced R&D (Sanders)
Sander Liu
Data Acquisition System - Delivered one LEMO and one BNC chassis to
the 40M
Peter King
40m & LASTI PSL
Lee is presently gearing up to check out the reference cavity
vacuum chambers. Also during the week he checked the levelness of the
PSL
table.
All the commercially sourced PDA-55 photodetectors have been modified
for
a lower transimpedance gain (2.5V/mA).
LIGO II
-----------
This week I spoke with the local Coherent Laser rep. about their
pump laser diodes. I had mentioned that I received information from
their
rep. in Santa Clara. Apparently Coherent is interested in supplying
the
pump laser diodes at a price significantly less than their original
quote
and is ready to give us some numbers.
At the end of April, or beginning of May, an electrical engineer from
GEO
will be visiting for a month as part of the PSL development. During
his
stay, Andreas will hopefully pick up on how CDS packages electronics,
does
the EPICS interfacing ... all sorts of things that will be needed for
a
smooth integration of the Advanced LIGO PSL into the facilities.
Janeen Romie
Ordering parts for 4 additional SOSs for LASTI
Szabi Marka
40m TRF measurements (I guess Alan will mention this in his report)
We transferred 2 full PASSCAL data acquisition systems from LLO
(complete with datalogger and triaxial seismometers) to aid in the
transfer function measurements of the STACIS units of the 40m lab.
We
collected long streches of good data between Thursday and Monday and
preliminary checks indicated successful measurements.
From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>
We had no meeting again this week, I was home sick.
Unfortunately Frederick has been hired out by a private company and
will
leave us next month. Good luck to him, we will miss him.
Finally the DAC chips are in our hands. Taddei is assemblying
them into
the DAC boards and testing. They should leave for Hongo next
Monday
Edwin, Riccardo
Made several cable potting tests, ready for the flanges.
Feed through
flanges, water cutting was blowing up the plexyglass, we had to start
again and made them in Stainless, we will pot the flat cable within
next
week. Should be ready to go to Hongo by the end of the week.
Alessandro
Assemblying and testing accelerometers. Will be shipped to Hongo
by the
end of the next week. Alessandro will fly in to assemble them
the same
week end (7th April)
Gianni, Carlo
Introduced design of new vacuum tank and redesigned suspension wires.
Started the production of the two double nail head wire, should be
made
by middle of the week, then they will undergo the 5 day precipitation
process. Also redesigning coil for F0 actuator. Cannot
be made until
feed back from Akiteru’s measurements is received.
This will complete all parts still to be sent to Hongo.
New hard clamp and wedges for hysteresis tests in Pasadena have been
built. Delivery delayed to wait for Maraging hardening bake and
send
together with Penn State MGAS blades that are cooked together with
the
double nail head wires.
Akiteru
Testing transfer function of the suspensions, preparing cabling hooks,
preparing for Japanese Physics Society which is at the end of this
Month.
Szabi
Provided Francesco with Olympia earthquake and train transit
accelerometer time series.
Franesco and Giancarlo will combine it with Akiteru’s simulations MSE
(validated by the oil bearing IP characterisation measurements) and
hopefully confirm that TAMA SAS would have survived totally unscathed.
For additional information about this report, contact sanders@ligo.caltech.edu