Weekly Report for Week Ending March 29, 2001


 Exec. Comm. Agenda
Highlights
LSC
Administration
Hanford Observatory
Livingston Observatory
MIT
Caltech
Detector
40 Meter
TNI
LASTI
Data Analysis
LIGO II/Adv. R&D
Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  April 2, 2001 will be:

 (Meeting time: 10:30 am Pacific Time)

Open meeting 10:30 - 11:30

  1. Announcements
  2. LSC Issues (Weiss)
  3. Comments on Weekly Report
  4. WBS 1 LIGO I Construction (Lindquist)
  5. WBS 2 LIGO Lab Operations
  6. WBS 3 and 4  Advanced R&D and LIGO II (Sanders)
Executive Committee only 11:30 - noon   Topics:
 

Special Items:   LHO Building schedule options regarding commissioning/science run interference, temperature control spec, energy reduction options at LHO


Special Announcements:


Weekly Report Highlights
 


LSC Issues (Weiss)


no report


LIGO I Construction/LIGO Laboratory Administration (Lindquist)



 

WBS 1.2 LIGO Operations--Administration



LIGO Weekly Site Telecon (Lindquist)

A site teleconference was held on Thursday, March 29, 2001. Discussion included the end of February costs. We also discussed the schedule for the building in Hanford relative to the schedule for beginning science operations. This item will be on the agenda for the Executive Committee meeting on Monday.  The power costs at Hanford are expected to increase $100K or more as a result of the crisis on the west coast. We will also put on the agenda for the Monday Executive Committee meeting a discussion of possible reductions of power usage and the potential impact on science operations.

The next site telecon is scheduled for Thursday, April 5, 2001. The list of current actions revised to reflect open actions assigned through March 29, 2001 may be found at ACTION LIST.


PROPERTY MANAGEMENT (Chargois)

From: Ed Chargois <chargois_e@ligo.caltech.edu>


DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner - turner@ligo.caltech.edu>

Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .

ACCOMPLISHMENTS

From: Cleveland Mak <mak_c@ligo.caltech.edu>

Packages Faxes
In 57 39
Out 12 42

Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.


COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Akutagawa, Kaufman)

From: Esther Cunningham <esther@ligo.caltech.edu>

Press here for ACCOUNTS PAYABLE HISTORY DATA.
 
 

From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

From: Florence Kaufman <fkaufman@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: irena@ligo.caltech.edu (Irena Petrac)

From: Ed Jasnow <jasnow@ligo.caltech.edu>


Support (Wood)

Rita Torres

Dorothy Lloyd Irene Baldon Elizabeth K. Wood

Advanced LIGO (Frey, Petrac)

From: Thomas Frey <tfrey@ligo.caltech.edu>

Progress Period from 03.23 to 03.29

Accomplishments:

Schedule 03.30 to 04.05:



WBS 1.4.1.2   Project Controls (LIGO Construction)



Reports (Lindquist)

Change Control/Contingency (Lindquist)

The following Change Requests have been submitted:
 

CR-000018 WBS 1.1.4 Curbing for Service Roads at Livingston G. Stapfer
CR-000019 WBS 1.2 Additional Lab Equipment D. Coyne
CR-000020 WBS 1.1.4 Staging Building and Renovations to Existing Building--Livigston F. Asiri
CR-010001 WBS 1.1.4 Return of Unused Construction Budget To Contingency F. Asiri

Press for the latest Contingency Needs Projection.


COST SCHEDULE CONTROL SYSTEMS (Duncan, Akutagawa)

From: Kris Duncan <kris@ligo.caltech.edu>

From: Cindy Akutagawa <cindy@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: Ed Jasnow <jasnow@ligo.caltech.edu>

From: irena@ligo.caltech.edu (Irena Petrac)

Quality/Safety (Tyler)

>From: Bill Tyler <tyler@ligo.caltech.edu>


LIGO Hanford Observatory (LHO) Operations (Raab)


General Items:
--------------
(F. Raab)
 

Eucon mobilized its gravel crushing operation to North Richland at 7pm
on 3/28. We will be monitoring the effects of the mining operation to
see if it violates the ambient seismic spectrum at LIGO. The distance
is approximately 10 miles from the Y arm.
 

Installation & Re-Installation
------------------------------
(D. Cook)
 

We finally were able to wind up the 4k IO and mode cleaner alignments and
HAMs 1,2,3 have their doors in place. We will place a metal cover over the
cloth cover at the spool opening to reduce air currents and keep things
cleaner. The RM-4k optical lever transmitter will need to be repositioned
on the pier using an offset mounting system to allow the beam to clear the
view ports and IO baffle. The reciever side will need to have some
modifications made as well. Hugh and Gerado have mocked up the optical
lever position and currently have the beam path worked out. The FMx-2k
safety stops and OSEMs have been replaced and the alignment will follow.
The ITMx-2k OSEMs and safety stops were changed out and alignment is done.
The ITMy-2k is next. We will be installing the second verticle PLX and
finishing the  ITMy-2k alignment today. We will steer the ITMx-4k optical
lever beams through the arm cavity baffle, scribe it and remove it hopefully
today as well. Mark Barton is working with Betsy on 2k SOS optics. We are
adding additional camera view ports to several areas to aid with
commisioning and alignment. We have a camera mounted at the APS port ready
to steer the FMx -2k. We continue to parallel the 2k and 4k
activities with the help of many. Thanks once again to All.
 


LIGO Livingston Observatory (LLO) Operations (Coles)


Operations: We are continuing control room operator support after normal working hours
as needed for the commissioning effort. We are continuing the mix of operations specialist duties as 50% control room support and 50% "other" which consists of LOS circuit board repairs, vacuum bake support for LHO and the 40 meter, LHO optics repair support at
LHO, shipping and receiving, particle counter repair, CDS software upgrades
and refinements, on going work on getting a set of base values for all OSEM
coils (L&R), continuing work on ISCT3 table alignment, ISCT4 installation
of safety hardware, and mode cleaner alignment. (Rich Riesen)

GC: Configured the Fore 2810 in the communications room. This will allow 100
mbit connectivity for several more machines. (Shannon Roddy)

LDAS: The main breaker panel and the wiring has been installed in the Mass
Storage Room for the incoming LDAS equipment. We still need to run the circuits
etc for the individual outlets but the main breakers are in. (Shannon Roddy)

Facilities The construction of the new building is going ahead on schedule.
The changes for the handicapped elevator are being finalized and the
affected drawings will be issued as revision -1. (Gerry Stapfer)
 
 


Detector/Technical Support (Whitcomb, Coyne)


 
Installation& Commissioning:
Hanford
Livingston
Other Science/EngineeringActivities:
Design/Analysis/Fab
Issues/Concerns

1.1 LHO INSTALLATION & COMMISSIONING

2km & Vertex Re-alignment

Doug Cook (reporting for the team)

4-k IOO Installation

Dave Tanner (reporting for the IO team)
The HAM 1 and HAM 2 doors have been replaced. A new technique for
setting the Earthquake stops using a temporary optical lever was
employed which ensures that the face stops are positioned 0.5 mm from
the optics. The optics are then swept there full bias range to check
that the stops are not interfering with the optics. In addition each
mode of the optic ie pitch and yaw are also rung up separately to ensure
that the stops are not touching anything. We tested this technique on a
bench and found that the stops could be reproduceably positioned without
the need for a difficult marginally accurate back breaking inspection.

The viewports on HAM 1 will be returned to the
conventional centered viewports because some how nowbody told me that we
would be deviating from the 2K in this regard, so I set the output beams
up to come out standard centered viewports. I do not believe that this
will impinge on performance of the modecleaner and the change was
cleared by Dennis Coyne. Unfortunately I only noticed the change when we
had already put the doors back on HAM 1.

The new layout for the 2K PSL/IOO table has been finalized. Guido did the
new mode matching calculations and I independently verified them. Rick
and Malik are in the process of laying out this table.
We are currently staging to replace the optics in the 2K interferometer
and all the 2K optics should be re-installed by early next week if all
things go well.
 

1.2LLO INSTALLATION & COMMISSIONING

Commissioning

Rai Weiss
No report.

Rich Abbott
While at LLO, I worked did some repairs on the LSC system (whitening filter board) and went through the ASC system in order to write a short report on its status.  A list of things necessary to get two wavefront sensors activated was prepared.

E3 Data Analysis

Peter Fritschel
Correlation of the power lines between LHO & LLO.
I have been looking at the coherence between the two sites' power line
monitors and magnetometers, at 60 Hz and harmonics. Observations to date:

1. The broadband noise on the line monitors (between the line
frequency/harmonic peaks) is about 10x higher at LLO than at LHO. The LHO
line monitors show a lot of structure between the line harmonics, but any
such structure on the LLO lines is masked by the higher broadband noise.

2. At a given site, the coherence between a line monitor and a
magnetometer is essentially unity at the line frequency and harmonics.

3. Coherence between sites: The coherence between a line monitor at LLO &
a line monitor at LHO (@60 Hz) is essentially unity over short time scales
(t < 60 sec), but becomes small over time scales longer than a few hundred
seconds. For example, ten coherence measurements over 1000 seconds (each)
yielded coherence values between 0.01 - 0.1. Over 10,000 seconds, one
measurement gave a coherence of ~0.001.

2.0 OtherEngineering and Scientific Activities

2.1 Design/Analysis/Fab

Embedded Controller Board (MVME162) Upgrade

Jay Heefner
9 MVME162-P242 CPUs have been shipped back to the manufacturer and will be
exchanged for MVME-PA262 CPUs. Rumor has it that these units will be able to run
EPICS

ASC/LSC/SUS

Jay Heefner
- Rev B of the Universal Dewhitening Board has been sent out for fab. and boards
are due back by 4/1. Rev B includes the ability to jumper out filter sections
and the possiblity of "softening" the response of the filter to allow for better
IFO locking during commissioning.
- A Satellite Amplifier adapter board has been designed and sent out for fab.
This board will adapt the old satellite amps to the new digital suspension PD
interface and coil driver boards.
- 5 more LOS Coil driver chassis have been completed and tested. They will be
sent to LHO for installation on the 4K.
- ADCs procurred by LIGO have arrived at Pentek and they should be shipping us
more modules by next week.

Optics

GariLynn Billingsley
Dave Reitze is sending IO optics and blanks to me, for rework, polishing and coating.

I'm building a list of LIGO optics so that the general user can easily find specification/drawing information for individual part optics.

As optics are re-polished they are not always built to the original specification as indicated by the serial number, but may be reused for another purpose.  This list will be filed in the DCC and will provide a means of tracking the current status of an optic.  Under the title "data package" there will be a link to the scanned in test results for each optic.  This process has been started, some Beam splitter data packages can already be found in DCC/OUT.  I will complete those links when the documents have a permanent home in the DCC.
While it's being built the list will reside at:
http://www.ligo.caltech.edu/~gari/COCAsBuilt.htm

After it is filed in the DCC you will be able to find a link at:
http://www.ligo.caltech.edu/~gari/

LSC

Rich Abbott, Flavio Nocera, Mohana Mageswara
MC servo model has been updated with parts that are available to speed up the circuit response. A detailed analysis of the whole servo system model supplied by Peter F. and Nergis is underway to ensure we are within the design limits.

Sent out the MC Servo PCB to the board house for fabrication. Now doing the new design DC readout module simulations and also fixing some of the PCB errors which are on the LSC Whitening Anti Aliasing Boards which are needed for the 4K arm. All other aspects of the 4k modecleaner electronics seem to be in line for delivery.  Have arranged with Peter King to use the laser in the basement of Lauritson lab to do a high power test of the RFPD in an effort to sort out the saturation problem and match results with the simulations.

PSL

Peter King
In an exercise to see if we could optically contact optics
together, two sets of precision flats were optically contacted together.
For one set the LIGO optics cleaning procedure was followed, for the other
set cleaning with only acetone was done.  Both sets have not been separated
yet, despite numerous tries - including soaking in a Liquinox solution and
agitating for 10 minutes.  The results gives us some confidence that we
should be able to fabricate our own reference cavities and the next
generation of pre-modecleaner.

The intensity noise before and after the high finesse pre-modecleaner was
measured.  The cavity bandwidth of the pre-modecleaner is consistent with
the expected value and should provide sufficient filtering of the intensity
noise at around 25 MHz.

NPRO #170 will be returned to Lightwave for repair.  This is the second
time in my project memory that this has happened to this particular NPRO.

Rich Abbott, Peter ing, Ben Abbott
Rich, Ben and I measured the characteristics of the current shunt actuator from 1 kHz to 10 MHz at various points in the system.  Both the transfer function from current shunt drive to light out and current shunt drive to current out were measured. As an aside to the above measurement, the modified PDA-55 response was flat
to 10 MHz, as measured using the test laser at the Wilson house.  The photodetector exhibited some gain peaking at 26 MHz, wherethe peak was approximately 7 dB higher. The data (once analyzed) will yield the response of the electronics and the laser process independently and should help form a basis for the further development of the intensity servo by Rick Karwoski.

Ben Abbott
The intensity servo DC photodiode preliminary design is complete.  The design document is available on my website here (www.ligo.caltech.edu/~babbott).  If  anyone would care to review the design and give me feedback, the input would be most welcome.

Rick Karwoski, Paul Russell

LIGO Tri-Net Stations

Szabi Marka
I created a script+web interface (CSAI) to display the seismic activity
at both
LHO (http://blue.ligo-wa.caltech.edu/gds/TriNet/) and
LLO (http://london.ligo-la.caltech.edu/gds/TriNet/).
Each web page contains plots of the triaxial ground velocity history of both
observatories for the last three hours. It is automatically refreshed to
include recent data. Presently it provides easy access to calibrated
data (mm/s), simplified detection of potentially disturbing seismic
activity and effortless comparison of seismic activity at the sites. It
is a work in progress; I welcome your comments, ideas and suggestions.
Help me make it better!
Our recently released document
(http://www.ligo.caltech.edu/docs/T/T000131-00.pdf) is available from
the DCC or linked to the CSAI web page. It describes how to download
data directly from the LIGO-TriNet dataloggers via their web interface.

PEM Tiltmeters

Szabi Marka
I received an interesting document from GeoTech Inc. the maker of our
seismometer. The paper describes in detail the sources of tiltmeter
temperature drift and provides hints on how to deal with it. The scanned
doc is available from the DCC
(http://www.ligo.caltech.edu/docs/E/E010059-00.pdf).

New OSEMs

Janeen Romie
Micro Hybrid Dimensions reports that they'll deliver the new
circuit boards on 4/30. Myron reports that Laser Services has done a
great job with laser marking the coated heads. He also reports that
Surmet shall finish coating the heads by 3/30. He will clean and inspect
the heads and send them to Laser Services next week.
Doug Cook has ordered more PAM brackets and screws.
Oliver delivered 60 pigtails (52 long and 8 shorts) to LLO. Rich  has
sent the pigtails along with the cleaned and baked heads (48 long and 53
short) to LHO for processing.

GDS

Daniel Sigg
Started preparations for porting DTT to other platforms. The first step
is to make DTT and its auxiliary packages compile under solaris/gcc.
The makefiles must be completely rewritten to support multi platform
configuration and setup. The first step has been completed for the
algorithm, calibration and gui extension packages. Took the opportunity
to upgrade to ROOT version 3 which required some small updates in
the GUI package. Looked into the possibility of porting to Windows.
This may be doable if we get a UNIX/POSIX emulation software. Drop
me an e-mail if you are interested (assuming you have read this far).
 

A new DMT machine has been shipped to LLO (dual 1GHz Intel, Linux,
1GB RAM, gigabit ethernet).

DMT

John Zweizig
This week I spent mostly fixing bug in the DMT software. Most importantly,
with the help of Alex Ivanov I was able to locate the memory leak in
FrameCPP that has been adversely affecting the stability of DMT monitors
for the last few weeks. I have also chased down and fixed code that is not
faulty as it stands, but will cause problems if ported to linux because of
the byte ordering. I have also been updai\ting the documentation of
moitors I have written.

2.1 Issues

no new issues


40 Meter Interferometer (Weinstein)




Thermal Noise Interferometer (Libbrecht)


This week we aligned the TNI suspended mode cleaner and locked it in air.
We also continued checking and repairing our OSEM controllers, and we have
constructed and tested one power-line isolation transformer to be used for
eliminating ground loops.  We installed one of our new, four-pin BNC
feedthroughs on the vacuum chamber, and next we expect to begin aligning
our arm cavities.


LASTI (Zucker)


no report


Data Analysis and Computing (Lazzarini)



 
 

Simulation and Modeling (Bhawal)


Telephone conference with LHO
LHO : Rick, Michael
CIT : Biplab, Matt, Andrea, Hiro

(0) Lock acquisition issues, if/what ever it shows up, will be taken care
by Matt, with whatever necessary assistance by others.

(1) In the next 6 months, the main focus is to make the e2e simulation
more realistic to simulate the inlock state LIGO performance by
incroprorating site specific parameters, like seismic motion, stack
transfer functions, etc. After that, the focus is to identify problems
to which simulation can be used to improve the LIGO performance.

(2) Once per month, there will be a telephone conference to confirm the
progress and discuss the next plan.

(3) 1 week per month, Hiro or Biplab or someone will travel to LHO and
incorporate the measurements done by Rick or Michael into the model, and
discuss the future plan.

(4) Hiro will summarize the action items to be done in the coming 6
months.

(5) 4k IFO simulation needs update of a database file, e2eDB.mcr. This
will be tested at CIT, and will be passed around to LHO and LLO.

(6) The noise curve generation will be setup so that people can
easily generate noise curves by various sources.

Code Development
----------------
(Andrea) Implemented a module for linear prediction based on the Burg
algorithm. The purpose is to propose a replacement for the "delay" module
at least in those cases where one-step in the simulation can be accurately
modeled with an IIR filter.

Alfi
----
(Bruce) Finished cleaning code for ports.  Should finish Problem Report
202 (Same port name problem) and be able to start on implementing
connection junctions.

LIGO Data Analysis System

  • Software Systems (Blackburn)

  •  

     

    Several changes to the frameAPI software began this week. The performance
    for
    concatenating data from sequential frames has been enhanced through a rework
    of the code by about a factor of 30. Also a memory leak in the frameCPP I/O
    library was identified and fixed. The effort began to support reading of
    frame
    files having multisecond frames.

    Enough of the eventMonitorAPI code materialized this week to include it in
    the
    nightly build of LDAS for the development system. It is now up and running
    on
    the LDAS-DEV system and able to receive and parse data from wrapperAPIs. It
    is
    also able to separate the database, state, and multidim data from the
    wrapper's
    output sending the multidim to users and state to file. More work is needed
    to
    fully support the database.

    Guild was updated this week to support the metadataAPI's ability to work
    with
    multible database table simultaneously.

    More test code was developed this week to improve the performance of our
    code
    test suite. New tests exercise additional components of the lightWeightAPI
    and
    the frameAPI.

    The dataConditionAPI group worked mostly on documentation this week. Some
    effort has been put into tracking down a segmentation fault which occurs
    sometimes when multiple ffts are performed concurrently.

    The big news for this week was the first LDAS user command based on the new
    dataPipeline command was stitched together to send data almost fully end-to-
    end. Data was read in from frame files using the frameAPI. This data was
    then
    translated into the ILWD format and sent to the dataCondtionAPI where it was
    pushed into a call-chain and a power-spectrum was calculated. The original
    time series data along with the calculated power-spectrum were then bundled
    together and sent to a wrapperAPI job which was started by the mpiAPI as
    part of the analysis pipeline flow control. The wrapperAPI called a
    "trivial"
    shared object provided by the LSC and the results from this wrapperAPI
    search
    were shipped off to the eventMonitorAPI where the three sub-components of
    data were recognized and parsed out and then sent to their respective
    destinations (file, lightWeightAPI, metaDataAPI). Each step along the way
    was managed by the managerAPI. No verification of the results have been made
    but are on the action list for next thing to do.

  • Hardware Systems (Anderson)

  •  

     

    The first components of the LDAS Phase I procurement (large disk farm and
    tape silo) have arrived, and the remainder is either in transit or
    scheduled to ship on Fri Mar 30.

    The purchase requisitions for the first component of the LDAS Engineering run
    Beowulf systems have been submitted.

    An integrated system backup, security monitor, and SNMP configuration server
    has been specified for each of the LDAS installations and will be ordered
    shortly.

    LDAS activity at LHO:

    1) The move of the LDAS hardware from the mass storage room to the
    staging building mezzanine has begun. Thus the ldas system at LHO will
    be down Thu Mar 29 and Fri Mar 30. The plan is to complete the move by
    Friday evening.

    2) A 3Com 8-port 10/100 ethernet switch was installed and tested on the
    ldas network. This will provide temporary network support between the
    computer user and control rooms and the new ldas location.

    3) Plans for backups of the ldas system were investigated and
    discussed.  A script was written that can do basic backups, though some
    minor fine tuning is needed. More work is needed to develop the best
    strategy for backing up the meta database.

    4) I've begun installing on my computer lal, lalwrapper, wrapperAPI, and
    the supporting packages needed to write search code.

    LDAS activity at LLO:
    (Roddy)
    The main breaker panel and the wiring has been installed in the Mass
    Storage Room for the incoming LDAS equipment.  We still need to run the circuits
    etc for the individual outlets but the main breakers are in.

  • Data Analysis Activities
  • * Data analysis: studying the framecpp and the framebuilder code with
    the purpose of setting up a interface for frame generation to be used both in the
    E2E and in digesting external formats, to prepare for ingestion in (and
    testing of) the frameAPI.
    * Network analysis: contacted Cella about the common use of Grid (better, of Globus) for data exchange.
    Planning to meet on this subject with him during my stay in Italy.

    General Computing (Wallace)

    MIT:
    (Keith)
    -Rebuilt several SUN machines with Solaris 2.8
    -Created print queue for ledger sized prints
    -Investigated freeware CORBA orb (omniORB)
    -Verified backup mail server working with MX
    record entries
    -Preparing to start work on the SUN 450 system for LDAS.
    Larry has ordered a number of boards that will need to
    be installed.

    Livingstson:
    (Shannon & Tom)
    -Returned the equipment used at the LSC conference.
    -Working on setting up a more permanent network monitoring system.
    -Received the SUN Blade100
    -Configure the FORE 2810 and have connected a few machines to it.

    Hanford:
    (Christine)
    See Hanford weekly report.

    CIT:
    (Lisa)
    -Wrote a web page on how to configure printers in staroffice (solaris)
    -Installed samba version 2.0.7 on luna.  This will give us a good test
    environment before installing it on sirius.
    -Got scp working on cdssol6 and rana in the 40meter.
    -Currently trying to recover files off a virus infected pc.
    -Worked on some p-card problems
    -Started looking into putting up a new DHCP server.
    -This week had a worse round of pc problems than usual.

    (Barbara)
    - Finished touchups to DCC log search tool and updated number reservation
    tool.  I plan to install these next week.
    - Posted another iteration of LDAS home page and received comments.  I'm
    installing the new page into the cgi script.
    - Added a new LSC web page with abstracts for upcoming presentations.
    Continued to post LSC transparencies.  Added missing talks to web page as
    gray links.  Made other quick web site changes -- bulletin boards, mou's,
    talks, etc.
    - Ran the pherkab backup by hand because it hasn't been running.  I will
    reenter the schedule in TimeTarget to see if that fixes the problem.  Also
    restarted the DCC job that compacts and repairs the database.  It still
    hangs occasionally so next I'm going to try and break it into several
    smaller jobs.
    - Continued efforts to get my router working.  According to one web site,
    there is a unique situation with my ISP so I'm going to call the router
    vendor tomorrow.

    (Suresh)
    -Installed a PC card in Peter King's Sun workstation and also swapped the two
    hard drives from earlier system.
    -Worked with Larry to do some cabling in the computer room of the bridge. This
    was done to replace Cat 5 cable connected to web/DNS server "ligo" with a new
    one.
    -Performed thorough testing of ES 2810 switch. Contacted technical support at
    Marconi for its replacement which is expected today (March 29).
    -Made a backup copy of approximately 53 Giga Byte of old data from sargas to a
    AIT tape.
    -Resolved the ideas running problem by making appropriate entree in NIS+
    table.
    -Worked on e-mail aliases.

    (Sam)
    -Out interviewing.

    (Larry)
    -Some good news. We finally received the SUN Blade1000 unit that we had ordered
    in Oct. of last year. Preliminary tests show it to be faster than a dual SPARC60
    in all cases. In Biplap's Modeler test it is run 1.6 X's faster than the SUN450
    per CPU (clock speed ratio is ~1.8:1)
    The SUN Blade100 unit is still being setup for testing but for the money appears
    to be a good box.
    -Finalized the FORE maintenance contract and it is now going through the system.
    -Repaired a couple of computers. Working on a new configuration for the SUN
    Ultra 10's and Solaris 8.
    -Made a number of purchases for memory, disk upgrades and related equipment.
    -Was able to get the P-card s/w working on a PC that was having problems
    with the application.
    -Worked a few minor network problems and resolved a couple of application
    issues.
     

    [Bruce Sears]
    * (BS) Ilog maintenance, additions, and development:
            - Small amount of general maintenance.
    --


    LIGO II/Advanced R&D (Sanders)


    Sander Liu
    Data Acquisition System - Delivered one LEMO and one BNC chassis to the 40M
     

    Peter King
    40m & LASTI PSL
    Lee is presently gearing up to check out the reference cavity
    vacuum chambers. Also during the week he checked the levelness of the PSL
    table.
    All the commercially sourced PDA-55 photodetectors have been modified for
    a lower transimpedance gain (2.5V/mA).
     

    LIGO II
    -----------
    This week I spoke with the local Coherent Laser rep. about their
    pump laser diodes. I had mentioned that I received information from their
    rep. in Santa Clara. Apparently Coherent is interested in supplying the
    pump laser diodes at a price significantly less than their original quote
    and is ready to give us some numbers.
    At the end of April, or beginning of May, an electrical engineer from GEO
    will be visiting for a month as part of the PSL development. During his
    stay, Andreas will hopefully pick up on how CDS packages electronics, does
    the EPICS interfacing ... all sorts of things that will be needed for a
    smooth integration of the Advanced LIGO PSL into the facilities.
     

    Janeen Romie
    Ordering parts for 4 additional SOSs for LASTI
     

    Szabi Marka
    40m TRF measurements (I guess Alan will mention this in his report)
    We transferred 2 full PASSCAL data acquisition systems from LLO
    (complete with datalogger and triaxial seismometers) to aid in the
    transfer function measurements of the STACIS units of the 40m lab. We
    collected long streches of good data between Thursday and Monday and preliminary checks indicated successful measurements.
     

    From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>

    We had no meeting again this week, I was home sick.
     

    Unfortunately Frederick has been hired out by a private company and will
    leave us next month.  Good luck to him, we will miss him.
     

    Finally the DAC chips are in our hands.  Taddei is assemblying them into
    the DAC boards and testing.  They should leave for Hongo next Monday
     

    Edwin, Riccardo
    Made several cable potting tests,  ready for the flanges.  Feed through
    flanges, water cutting was blowing up the plexyglass, we had to start
    again and made them in Stainless, we will pot the flat cable within next
    week.  Should be ready to go to Hongo by the end of the week.
     

    Alessandro
    Assemblying and testing accelerometers.  Will be shipped to Hongo by the
    end of the next week.  Alessandro will fly in to assemble them the same
    week end (7th April)
     

    Gianni, Carlo
    Introduced design of new vacuum tank and redesigned suspension wires.
    Started the production of the two double nail head wire, should be made
    by middle of the week, then they will undergo the 5 day precipitation
    process.  Also redesigning coil for F0 actuator.  Cannot be made until
    feed back from Akiteru’s measurements is received.
     

    This will complete all parts still to be sent to Hongo.
     

    New hard clamp and wedges for hysteresis tests in Pasadena have been
    built.  Delivery delayed to wait for Maraging hardening bake and send
    together with Penn State MGAS blades that are cooked together with the
    double nail head wires.
     

    Akiteru
    Testing transfer function of the suspensions, preparing cabling hooks,
    preparing for Japanese Physics Society which is at the end of this
    Month.
     

    Szabi
    Provided Francesco with Olympia earthquake and train transit
    accelerometer time series.
    Franesco and Giancarlo will combine it with Akiteru’s simulations MSE
    (validated by the oil bearing IP characterisation measurements) and
    hopefully confirm that TAMA SAS would have survived totally unscathed.
     
     


    For additional information about this report, contact sanders@ligo.caltech.edu