|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The LIGO Executive Committee Agenda for Monday March 19, 2001 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
Special Items: LSC meeting reprise
No report but this is the week off the LSC meeting in Louisiana.
WBS 1.2 LIGO Operations--Administration
There was no site teleconference held on Thursday, March 15, 2001.
The next site telecon is scheduled for Thursday,
March 21, 2001. The list of current actions revised to reflect open
actions assigned through February 22, 2001 may be found at
ACTION
LIST.
From: Ed Chargois <chargois_e@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .
ACCOMPLISHMENTS
| Packages | Faxes | |
| In | 46 | 33 |
| Out | 14 | 48 |
Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS PAYABLE HISTORY DATA.
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
From: irena@ligo.caltech.edu (Irena Petrac)
Support (Wood)
Progress Period from 03.09 to 03.15
Accomplishments:
WBS 1.4.1.2 Project Controls (LIGO Construction)
A reminder that I require contributions for an end-of-February Quarterly Progress Report. I am requesting contributions by Friday, March 23rd. Thanks!
The following Change Requests have
been submitted:
| CR-000018 | WBS 1.1.4 | Curbing for Service Roads at Livingston | G. Stapfer |
| CR-000019 | WBS 1.2 | Additional Lab Equipment | D. Coyne |
| CR-000020 | WBS 1.1.4 | Staging Building and Renovations to Existing Building--Livigston | F. Asiri |
| CR-010001 | WBS 1.1.4 | Return of Unused Construction Budget To Contingency | F. Asiri |
Press for the latest Contingency Needs Projection.
From: Kris Duncan <kris@ligo.caltech.edu>
The financial reports on the web provide supporting
detail.
http://docuserv.ligo.caltech.edu/~fireport
http://docuserv.ligo.caltech.edu/~finance
http://docuserv.ligo.caltech.edu/
From: Ed Jasnow <jasnow@ligo.caltech.edu>
> The 4k IFO installation continues
to make steady positive progress.The
>mode Cleaner alignment will start today. The MMT3 side PAM screw was
>removed and the 50% OSEM voltage was reset on the MMT3. The MMT3 position
>coordinates were double checked with the COS laser autocollimator
beam. The
>beam was retro-reflected off the RM and then onto a target placed
on the
>MMT3 structure. The beam path was next aligned to a target placed
on the
>MMT2 by steering MMT3. We will now begin to align the PSL beam through
the
>IOO optics on HAM1 and into the MC. The ITMx and ITMy and BS optics
>alignment was re-adjusted one more time using the COS laser autocollimator.
>The COS beam dumps in BSC2 were also installed and aligned. Optical
lever
>build up continues. The ETMy-4k core optic is waiting its installation
>schedule and the ETMx-4k may require revisiting as their appears to
be a
>drift problem(earth quake or optical lever related??).
>
> The 2k earth quake recover and
retro fit is also making steady progress.
>The RM, MMT3, MC1,SM2 MMT2 and MC1(4k) go into the vacuum bake oven
today.
>The FMy and ITMy come out and will be re suspended and ready for
>installation on Friday morning. The installation tooling has been
placed
>into BSC8 and the normal staging is completed. The MMT3 will be removed
>from HAM 1 today. We had processed the spare MMT3 to expedite the
schedule,
>but it turned out that the spare structure side OSEM mounting brackets
were
>welded in the wrong location and will need to be replaced so this
structure
>is needed. BSC 6 was staged and the ETMy was extracted, tooling was
then
>transported and setup for BSC8. The ETMy was missing a side magnet.
It has
>been stripped, is being cleaned and will begin to be reprocessed.
MMT1 and
>SM1 have been repaired.
>
> Modifications to both the small
and large suspension safety stops are on
>going both here and at LLO.
>
> RM off axis beam dumps are being
machined and readied for cleaning, baking
>and installation.
>
> The PLX mounting modifications
are in the works. This is being done to
>allow us to use them in a vertical position which is needed for a
modified
>2k alignment procedure .
>
>Again this work is being accomplished by a BIG
LIGO TEAM effort supported
>by local staff members who normally would not
be involved in the
>installation and alignment work, by visiting
staff that would normally be
>here, but have had to extend stays and working
hours and to others who have
>expertise in critical areas that have come up
from CIT and LLO and MIT to
>help out and will continue to help us out.
>Thanks for rallying!!!
This was a very busy week at LLO, with preparation and execution of the E3 run on Friday-Monday, overlapping with preparation for the LSC meeting and planning for a major educational outreach event involving approximately several hundred students in Lafayette, LA.
Thanks to all of the LLO staff for their efforts to prepare for the run and then to support it during round the clock operation! This the first time LLO has staffed for round-the-clock operation and it went very well. We assigned two experienced Operations Specialists to each 8 hour shift, along with scientific visitors. Szabi Marka, as run coordinator, was present the entire time except when sleeping, and many other LLO staff were present large fractions of the total time. The X-arm remained locked about 86% of the scheduled "up time". The major contributor to the down time was an error with the tape writing system that occurred at the beginning of the run and which was quickly fixed. Data was recorded for approximately 1 additional day following the official end of the run, and during that time the X-arm remained locked for around 95% of the time.
Operation of the seismic array located along the Y-arm will conclude this week and will hopefully resume in late summer. We have been operating 8 Guralp 40G seismometers in a two dimensional array and have been collecting data in various configurations since the beginning of the year. The seismometers and Reftek data loggers are on loan from the IRIS Passcal consortium at New Mexico Tech University and must be returned to them after this week. We have requested 40 seismometers (or geophones) plus data loggers for a follow-on study this summer. We have also requested an extension on the loan to allow two seismometers to be shipped to Caltech for a one week study in the 40 meter led by Alan Weinstein and are awaiting consent from IRIS to do this.
Rai Weiss will be the featured scientist at a special two-day science event in Lafayette, Louisiana next Monday and Tuesday which will involve about 500 fifth grade public school students. Approximately 200 students, plus teachers and parents toured LLO this week in preparation for next week's event. Bonnie Wascom is coordinating LIGO involvement in this event.
No report due to LSC meeting.
No report due to LSC meeting
This week we finalized our plan for obtaining data on sapphire mirrors
before the LIGO II COC material downselect date, June 4, 2002, and with
the help of Thomas Frey we have begun integrating our group's activities
with the other advanced R&D efforts. We are now finishing the
second week of this new schedule and are holding to it nicely so far.
Seiji Kawamura visited briefly on Monday and had a lot of useful input
on our design. He pointed out that our current plan of locking the
arm cavities with the help of broadband Pockels cells might prove difficult
to implement, and we discussed alternate schemes. Other lock-acquisition
strategies might include feeding around the mode cleaner to act on the
PZT, even when the mode cleaner is locked, or replacing the test masses
in our arm cavities with lower-reflectivity mirrors to reduce the arm-cavity
finesse. Our arm cavities currently have a finesse on the order of
100,000. We chose this number some time ago to achieve a shot-noise
limited sensitivity of approximately 2.5x10^-21 meters/rtHz, which we believed
was necessary to observe thermal noise in sapphire. More recent estimates
of the thermal noise in sapphire indicate that we could tolerate a larger
shot noise limit by a factor of ten (or more). Changing the arm-cavity
finesse to 10,000 would likely make lock acquisition significantly easier,
and we have the necessary fused silica mirror blanks. It remains
to be seen whether or not we can have them polished and coated in time
to be of use.
Last week we reglued side magnets onto two of our suspended optics:
the South arm-cavity input mass, and the back mode-cleaner mass. This week
we began reinstalling these two optics. As of this writing the South
input mass has been installed, and we are in the process of installing
the back model-cleaner mass. No rebalancing was necessary for the
South input mass, since we glued the wire standoffs in place after it was
balanced the first time. Since no rebalancing was necessary, we were
able to install the local-damping sensor/actuator heads the same day and
optimize their postitions to produce a mean-zero shadow sensor signal.
The optic is now suspended and locally damped. We anticipate having
the back mode-cleaner mass suspended and damped by this Friday.
Last week we replaced our laser and measured the frequency noise of
the new unit. We analyzed the results of that measurement early this
week and find it to be 60Hz/rtHz at 100Hz, falling off to 10Hz/rtHz at
1kHz, well withing spec and a nice change from the previous laser. There
is some indication of a pole in the PZT response at 80kHz, which was not
present in the other unit. A preliminary measurement of our electronic
noise gives a level equivaltent to about 2x10^-17meters/rtHz, flat between
20Hz and 3kHz with a few small peaks.
We have also been designing an upgrade to our vacuum-pumping system. The current system uses a roughing pump and catalyzer trap connected directly to the chamber, and we believe we are getting some backstreaming into the chamber at low roughing pressures. We plan to insert a needle valve in the roughing line to limit the pressure and hence the backstreaming during rough out. Many thanks to Steve Vass for suggesting this approach! The current system also uses a manual gate valve, and we would like to replace this with a pneumatically operated valve with a safety interlock that would close in case of power failure during pumpout. We have finished the design calculations for the flow rate of the needle valve and have now placed orders for all of the necessary components. We also ordered a spare turbo pump.
No report due to LSC meeting
No report due to LSC meeting
Riccardo, Gianni
Updating drawings of TAMA-SAS as built.
Notations for improvements in further units.
Riccardo, Carlo
Building cable feed-through flanges.
Akiteru
Reorganizing Hongo lab.
Building Vacuum vessel 15 cm extension for accelerometers.
Next week presenting SAS expected performance at Kamioka.
Sending vacuum vessel drawings to Gianni for update and production
of
new suspension wires.
Alessandro,
Finished and delivered Thesis.
Accelerometer mechanics ready end of next week, electronics OK.
Going to install in Hongo on April 2nd.
Discussions with Faimond to build Ultra Sound cutting machine.
Riccardo
Discussions with Wayne at Sonic-Bell to build Ultra Sound cutting
machine.
Result of discussions,
Sonic’s existing rotary Ultra Sound milling machine is unsuitable for
our uses because it is a contacting machine with a diamond tool, it
would destroy any flex joint. Sonic’s non-contacting heads are
not
adapted to NC milling.
Sonic is unwilling to build/develop a single non-contacting machine
just for us, they would provide us with Ultra Sound head (30K$) but
we
would have to adapt it ourselves to an existing Milling machine (60K$)
and make its operational software also ourselves.
Faimond would develop for and with us a complete Ultra Sound milling
machine, similar but more advanced than the ONERA one, with software
included for about 100K$ in about 6 months. They already have
both the
head and the NC milling chassis for it.
It seems certain now that, as declared by the ONERA people, there is
presently no machine as theirs anywhere in the world.
Frederic
Will go to ONERA to learn the details of the operation of their home
made Ultra Sound Milling machine to be applied to the Faimond machine.
Started simulation of mirror suspension flex joints including the non
linear thermal conductivity of Sapphire at 0-50 Kelvin.
Edwin
Getting DAQ program running on creep facility.
Reconstructed PC cannibalized to run TAMA-SAS tests.
Designing harder clamps and wedges to check out hysteresis problem
in
MGASFs
Roberto Taddei
Did not receive the DAC chips from provider, despite repeated promises
Virginio, Roberto
Tracked some DAC chips from a broker in Florida.
Ordered chips for immediate delivery through FedEx to CIT.
Riccardo, Virginio
Next week to LSC meeting in Baton Rouge.
Riccardo presenting the Cryo-LIGO outlook and the Hongo installation.
Probably no meeting next week because of the LSC and Kamioka meetings.
For additional information about this report, contact sanders@ligo.caltech.edu