|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The LIGO Executive Committee Agenda for Monday January 15, 2001 will be:
CANCELLED DUE TO HOLIDAY
no report
The next site telecon is scheduled
for Thursday, February 22, 2001. The list of current actions revised
to reflect open actions assigned through February 8, 2001 may be found
at
ACTION
LIST.
From: Ed Chargois <chargois_e@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .
ACCOMPLISHMENTS
| Packages | Faxes | |
| In | 30 | 30 |
| Out | 6 | 30 |
Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS PAYABLE HISTORY DATA.
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
From: irena@ligo.caltech.edu (Irena Petrac)
Support (Wood)
Dorothy Lloyd
Progress Period from 02.09 to 02.15
Accomplishments:
WBS 1.4.1.2 Project Controls (LIGO
Construction)
Working on material for the NSF Review scheduled at the end of the month in Hanford. Copies of my materials will be distributed this week for reference as required in other talks.
The following Change Requests
have been submitted:
| CR-000018 | WBS 1.1.4 | Curbing for Service Roads at Livingston | G. Stapfer |
| CR-000019 | WBS 1.2 | Additional Lab Equipment | D. Coyne |
| CR-000020 | WBS 1.1.4 | Staging Building and Renovations to Existing Building--Livigston | F. Asiri |
| CR-010001 | WBS 1.1.4 | Return of Unused Construction Budget To Contingency | F. Asiri |
Press for the latest Contingency
Needs Projection.
From: Kris Duncan <kris@ligo.caltech.edu>
Reminder: An updated list of all OPEN LIGO account numbers have been posted on the LIGO internal bulletin board. Please use these lists when you need a LIGO account number (or make yourself a printed copy for quick references).
http://docuserv.ligo.caltech.edu/
From: Ed Jasnow <jasnow@ligo.caltech.edu>
General Items:
--------------
(F. Raab)
The installation on the 4K interferometer continues in the corner station.
Basically
we have one ITM and the BS complete.
We have made some security changes at LHO. A few weeks ago, one of our
staff was
burglarized and an LHO master key was taken. We have now replaced the
locks and
issued new keys. Jill is recalling all old keys and issuing new keys.
We also are
changing some common passwords (e.g., to LHO CDS machines). Call Dave
Barker if a
password is needed.
This week we successfully locked the X arm for several hours during the evening last Monday, Feb. 12. Improvements made to the PSL servos were evident in the locking, which was far more robust than that observed during earlier attempts. On Wednesday, Feb. 14., we also locked the Y arm of the interferometer for the first time. This went very smoothly and fell right into place. Locking appeared to be even more stable than the X arm locking observed Monday night. We attempted, for the first time at LLO, to recombine the light from both arms into a Michelson, but encountered problems with the X-arm locking using the anti-symmetric port (see the e-log for details.) Thanks to all the many LLO staff and visitors who have put in some very long days this week.
OPTICS: The small spikes in the frequency control loop of the
laser were eliminated by a increase in the pump diode operating
current. Peter King remembered a similar problem at LHO and pointed
us in the right direction. We rotated the mode cleaner about
its long axis over last weekend. Rotation of the mode cleaner eliminates
the beam clipping we observed at the darkport, but it
appeared to couple the mode cleaner with the stack and it was unreliable
in lock. We returned it to the old orientation. We've been
operating the arm locks with what appears to be clipping somewhere
in HAM4, presumably at the Faraday Isolator. We reconfigured
(temporarily) ISCT1 to enable a Watec camera and the LSC photodiode
at the brightport, and have aligned the QPDs at both ends, as
well as the video cameras at the end transmission monitors. (Kovalik/Giaime/Traylor/Kern)
Operations: Shipped out the last of the equipment necessary for the BSC build-up in LASTI at MIT this coming spring. Initiated an operator training guide allowing all operators and others to cross train off each others specialities. This has been working quite well. We are expanding our e-log capability with a maintenance log area. Returned from the WAO2001 with some interesting notes. They will be in the DCC tomorrow (T010013-00-L).
GC: evaluating Quick Restore software on the Exabyte 220 tape
library for use in GC backups. Installed the AIT2 tape library on decatur.
(Daniel Sigg installed and configured it while at LLO) The 802.11b network
seems to be working very well. I also have drivers for linux for the Lucent
(and some other) pcmcia cards. Windows seems to work ok with it also, with
the exception of one laptop which I have not been able to troubleshoot
yet.
CDS: I am making one of the CDS computers into an applications
server (temporary until we have a dedicated apps server) for some of the
gnu software packages that have been requested. This will include ghostscript,
gcc, gnu ld, make, autoconf, etc. If there are any requests for any other
packages, please let me know. (Shannon Roddy, Tom Evans)
Outreach: We have lots of educational outreach activities planned
over the next few months in which we are reaching schools and children
from all across the
southern portion of Louisiana. Today we were visited by a group of
home schoolers from Ascension Parish. Next week we have a group of middle
school students from the New Orleans area (Pine View Middle) coming out
to tour and do our hands on spectrometry project. In March, we have 2 visits
planned from schools in the Lafayette area. We are invited to participate
in the St. Bernhard Schools science symposium in which Rai Weiss will be
the guest speaker during opening activities and two representatives from
our site will conduct polarization of light and spectrometer hands on activities
with the 3rd, 4th, and 5th graders. Also in March is the State Science
Fair and Junior Science Symposium at LSU in which we will supply judges
for physics related projects. Lastly, in May, we will do a presentation
on LIGO at the BREC Observatory during one of their fireside evenings chats
and host a teacher's workshop (Project Plato). (Bonnie Wascom)
| Installation&
Commissioning:
Livingston |
Other Science/EngineeringActivities:
Issues/Concerns |
See also the Installation web page
Spent a considerable amount of time re-aligning the interferomter to move the beam up ~5 cm in the recycling cavity so that it is centered on the core optcs. The translation was accomplished with MMT1 and MMT3 (see elog entry 1 and elog entry 2 for method; user: reader, password: readonly). Alignment was hampered by noisy 4 km interferometer core installation work and frame builder failures. The beam is now approximately centered on the ITMs vertically (+/- 0.5 cm) and the optical gain boost is > 450 and locks are > 10 minutes without a WFS. The beams are still not centered horizontally on the ITMs as yet.
With the full 2k interferometer realigned and locking well we proceeded with studies of the noise spectrum (ASQ and LSC-Darm). The biggest single improvement found has been with invoking the new MC elliptic filter. A factor of as much as 10 lower (than ASQ spectrum of 02/2 e-log) noise is achieved in the vicinity of 80Hz.
The BS was placed into the WBSC1 chamber and is in the process of being aligned. So far we are almost exactly on schedule.
All 4 SOS towers (MC1, MC3, SM1, and MMT1 were placed into Ham-1. The preference was to begin with the two SOS which are near the middle of the Ham table and therefore are hardest to reach. The suspensions were placed using micrometer pushers with settings calculated from the IO CAD drawings. In addition, we installed 5 out of 7 DLC mirrors. All the suspended optics were connected to the suspension controllers. The Faraday assembly is next to be installed.
- without OSEMs:
- yaw = 0.8657 Hz
- position = 1.0063 Hz
- with OSEMs:
- yaw = 0.8491 Hz
- position = 1.0054 Hz
An unexpected problem occured when trying to install the safety tube
and the view-port cover onto the main beam view-port of Ham-1. (This is
the assembly that connects Ham-1 with PSL enclosure.) The cup which is
holding the tube was cut with wrong angle. Unlike 2k Ifo, the viewport
on 4k ifo is a small (less than half
of the size of the flange) and is shifted off the center of the flange.
It was installed to the Ham chamber offset in vertical direction. The safety
cover (built at UF) was made for this orientation.
An inspection of the initial beam pointing inside the Ham chamber showed that the flange needs to be rotated so that the viewport is offset in the horizontal direction. Then the safety cover no longer fits. The solution is to re-machine the cylindrical cup (which holds the tube) to the new angle. This was done on site.
Rick and Malik worked on calculations of the average losses in the 4km pre-modecleaner based on the measurements of its finesse.
The power fluctuations in the Y arm are smaller
by about a factor of between 2 to 3 than in the X arm. The reason for the
power fluctuations is still a major research topic and could be caused
by incomplete diagonalization of the driven masses, instability of the
masses due laser light scattering into the OSEM dampers and/or directly
the ground noise excitation. The noise measured in the cavity length control
signals is, otherwise, dominated by frequency fluctuations of the light.
Direct
improvements could result from simple optimization
of the frequency control servos.
The research in the coming week will be dedicated to understanding and improving the performance of the cavities and to prepare the system for recombination of the beams from the two cavities.
I suggested to Rai that he might try turning down the pump diode current for the NPRO. For some reason it would appear that the trim pot direction for each NPRO is different. The diode current was increased, resulting in an increase in the laser power and the removal of the glitches.
Ben and Peter tested out a little high power photodiode circuit. We measured the 3-dB bandwidth of the transimpedance circuit to be 86 MHz. The circuit was being tested with an output of 100 mA, when the filter capacitors on the negative Vcc decided to give up. The reasons for which are not understood.
Rick Karwoski, Paul Russell,Ben Abbott, Sander Liu
We have a quote for stripping ZrN coated heads from Astro Pak. After I receive all bad parts from RPC, I will forward them to Astro Pak.
So. California Braiding quoted for pigtail assembly work. Another company did not respond. So. California Braiding's bid was a bit high (compared to expectations) and long -- about 8 weeks. We will likely build the 2 km parts in house to be timely and send the balance of the production to So. California Braiding; Our in-house electronics fab is overloaded currently.
Our objective during this period was to fully characterize and understand
our suspended test cavity and the laser.
To achieve this goal, we first locked the laser to our reference cavity
by
acting on the laser's pzt driver. This allowed us to pinpoint the driver's
efficiency to 0.7 MHz/V, a factor of 6 lower than expected. Furthermore,
inspection of the control signal (the signal sent to the driver to
maintain
the light resonating in the reference
cavity) showed 'spikes' irregularly spaced in time, of amplitude ~1.5V
and
~100ms of duration. An estimate of the laser frequency noise is
2000 Hz/rHz @ 100 Hz
30 Hz/rHz @ 1 kHz
2 Hz/rHz @ 10 kHz
compared to the expected values of
200 Hz/rHz @ 100 Hz
20 Hz/rHz @ 1 kHz
2 Hz/rHz @ 10 kHz
The laser frequency noise is found to be in excess by a factor of 10
at 100
Hz.
Having characterized the laser, we moved on to the study of the suspended
cavity. The cavity lock, robust with brief lock acquisition times,
is
achieved by actuating on both the mirror and the laser pzt driver.
In the
frequency window between 40 Hz and 100 kHz, our matlab model agrees
well
with the data and we have a good understanding of the topology of the
system. Below 40 Hz, however, there is a clear disagreement between
the
data and the model that needs to be understood.
Different topologies were also tried to displace the crossover point
(ranging from 40 Hz to ~800 Hz) between the two control paths in order
to
improve the gain of the system. We also tried different unity gain
frequencies (ranging from 1 kHz to 20 kHz) but have not settled yet
on an
optimum configuration.
END-TO-END MODELING (E2E)
(Biplab Bhawal)
* Physics Studies
------------------
(Biplab)
A pattern for the lock-acquisition criteria with misalignments
is
emerging out of several runs made in last few weeks (although
interrupted a number of times by power cut-off etc). Based on
the
understandings derived from all these complicated runs, I'm
performing
some simpler situation runs to find out causes behind successes
and
failures of the system in going from stage 2 or 3 to stage 4.
First draft of a possible paper on our work on frequency sensor
noise
is almost ready.
* Code improvement
-------------------
(Hiro and Tavio)
Hiro worked on Adlib code improvement and some of the issues
on
noise generation.
Tavio is studying the Portable Expression Template Engine
(PETE),
a mechanism for loop unrolling and optimization of Array-based
expressions which hopefully will be used to further speed up
the end-to-end simulation.
He will test the speed of matrix inversion and multiplication
using
LAPACK on HP computer, which showed good speed improvements
compared
to the e2e version of matrix class. When modeler is successfully
ported to CACR, this will be tested.
* Client-Server Framework
--------------------------
(Tavio and Ed maros)
After last Wednesday's meeting, the idea to create a monolithic
client-server system was dropped since it would not meet CACR's
security
or administrative requirements.
On Monday, Ed Maros and Tavio met with a group of CACR people
including
Beven Bennet and discussed a plan for a client-side scripting
mechanism
to submit and review jobs where each user would have his own
account on
the system. This idea was accepted by all of the CACR
staff. As a result,
Ed is writing a TCK script (`Jobber') that allows submission
and query of
jobs at CACR and Tavio is providing the details of job control
on the
CACR side.
* Alfi
-------
(Bruce Sears)
- Worked on connection and port problems, particularly checks
against
sink ports being connected to multiple times via
derived nodes.
- Reorganizing some of the core ALParser code to make sure methods
are
not being made redundant or are unused if they are
not easily found.
LDAS SOFTWARE
(Kent Blackburn)
We are still busily preparing and fixing software issues in preparation
for
the release of LDAS. A couple of problems in the metaDataAPI which
impacted
the ability to get data out of the database were identified and have
now
been fixed. Similar problems showed up in the lightWeightAPI and also
have
now been fixed. The half dozen or so problems with the dataConditionAPI
test
have now been reduce to a single known problem which we think we know
the
fix
for. This problem involves linear filtering code for complex data sequences.
It will require a new set of test scripts to exercise this last remaining
bug.
The documentation for the LDAS release is now ready for the two new
tarballs
of distribution code for the controlMonitorAPI client and frameCPP
library.
New links were added to the LDAS software block diagram for the
eventMonitorAPI. Several meetings were held this week to outline the
development and implementation for the eventMonitorAPI now that the
baseline
requirements are available.
A load balancing test plan was drafted and sent the MPI team for the
wrapperAPI and mpiAPI. This test will be performed on the version of
these
APIs available with the next release.
We were hoping to be in a position to push a pre-release of LDAS to
the
sites today but due to security issues at Hanford, we are now having
to
change
all LDAS system account passwords which will prevent development and
debugging
on the systems for several hours and mostlikely delay our plans for
a
software
push to the site until tomorrow. We will need to carry out our test
procedure
one last time once we have the code at the sites before officially
tagging
the repository and preparing a new software release distribution.
A subcommittee of GWIC meet over the weekend to discuss network data
analysis. The outcome of the meeting is a plan to be in a position
to share
a handful of PEM channels by June 1 of this year between LIGO, GEO
and VIRGO
for the purpose of performing coincidence studies.
This week also involve a significant amount of interaction with the
Upper
Limits groups, including a chairs meeting on Tuesday. Proposals are
now
available from three of the groups with the fourth group planning to
hold
its
first meeting on Friday of this week.
LDAS HARDWARE
(Stuart Anderson)
The last 2 years of LHO minute trend frames have been successfully retrieved
from the LDAS archive for re-transmission back to LHO after a recent
disk
failure on the CDS frame builder.
ldas-dev survived a diesel generator power test at Caltech.
The main LDAS software server has been upgraded to 4GB of memory in
preparation
for transferring it for use as the ldas-dev database server.
Ordered additional memory for laptop and quad-xeon datacon box at ldas-dev.
The LDAS 30-slot AIT-2 robot has been returned to LHO from Cybernetics.
However, it is unclear what if anything was fixed/replaced.
The AIT-2 unit at LLO is undergoing continuing tests in preparation
for the
E3 run attached to an U10 to avoid problems encountered during E2 run
with
the drives attached to the main LDAS server.
Initial testing of the new AMD K7 and Intel P4 LDAS test machines running
a beta version of RedHat7.1 is proceeding well.
The LHO network diagram has been updated using Visio2000 to indicate
the
move of LDAS from ATM to Gigabit Ethernet.
All LDAS Unix passwords have been changed.
GENERAL COMPUTING
(Larry Wallace)
MIT:
-Keith Bayer has joined us and is learning about and looking over the
system. Larry Wallace will visit next week to give the larger
picture and
strategize.
Livingston:
(Shannon)
-Evaluating Quick Restore software on the
Exabyte 220 tape library for use in GC backups.
-Installed the AIT2 tape library on
decatur. (Daniel Sigg installed and configured it
while at LLO)
-The 802.11b (wireless) network seems to be working
very well. I also have drivers for linux for the
Lucent (and some other) pcmcia cards.
Windows seems to work ok with it also, with the
exception of one laptop which I have not been able
to troubleshoot yet.
Hanford: (NO REPORT)
CIT:
(Lisa)
-Took the laser safety eye-exam.
-Wrote scripts to put the daily & weekly backups onto the cybernetics
robot.
I'm still working out the kinks on those but am very close to
getting the
daily/weeklys off of poor, old, decrepit rastaban.
-Installed SunPCI cards for 2 computers on 6Millikan so that people
can do
their pcard stuff on their sun boxes.
-Larry and I finally figured out why rsh to hamal wasn't working.
It was
the
path specified for tcpd.
-Worked with Ed Chargois to get a laptop shipped back to Dell for repair.
(Sam)
-Worked on a number of PC issues.
-Assisted in a office redecoration.
(Barbara)
-Finished installing the stand-alone DCC report. There is a link
on the
Internal Bulletin Board under Documents and Publications that
will allow
you to download a text version of the DCC database. The
text version can
then be imported into a spreadsheet.
-Fixed a problem with the style sheet for the LIGO web site that occurred
only in Netscape.
-Made a change to the weekly job that compacts the DCC database that
may
prevent future failures. Also DCC will remember to shut
down the database
on Tuesday evenings.
-Helped a fellow from the astronomy department install TimeTarget (I
am
the keeper of the Caltech site license).
-Made numerous web site changes to LDAS and LIGO sites.
(Suresh)
-Begun restoring old data since 1994 from tape archives to 235 GB RAID
system
in sargas. After restoring about 90 GB of data, this will be
archived in
high
capacity SONY tapes in compressed mode in Cybernetics robot backup
system.
This will free up substantial space in tape cabinet.
-Received 2810 ATM uplink module from Marconi Inc. Installed in 2810
of
computer room and subsequently upgraded ATM firmware. Returned
old unit to
Marconi.
-Replaced Irena Petrac's PC with working one after observing erratic
system
crashes. Now I am working on the unit by replacing hard disk
with a new
one.
-Installed a Network Interface Card (NIC) on system RANA to make a
gateway
machine to 115 and 113 subnets in 40-Meter.
-Updated HP Web Jetadmin Server to reflect new printers/plotters and
their
descriptions.
(Larry)
-Spent a great deal of time working on orders and pushing things through
the
system to get items in for the next NSF review and LSC meeting.
So far it
looks
like we will have the computers and projectors we need for the
meetings.
-Resolved another procurement issue with SUN.
-Reworking a number of financial items. Fortunately I had a backup
of my
work
and only lost a small portion when my disk crashed.
-Resolved a couple of virus problems. There have been a number of machines
that
had viruses mailed to them but only a couple which some repair
work had to
be
done.
-Just a reminder on the PC's using Eudora there is an attachment directory
that
the files need to be cleaned out of. Just deleting the e-mail
doesn't take
care
of everything.
-Working a few more logistical issues with DCC and the LSC conference.
-Worked with Suresh to resolve a couple of network issues. Hopefully,
we
will be
able to do some testing with the 2810's under different configurations
this
next
month.
Advanced LIGO PSL
Peter King
I had a few discussions
with Benno Willke about the timing of
things. Especially about when a good time for the electronics
engineer
from GEO to visit might be.
3.2 40m Lab
Quotations have been gathered
for the optics in order to comply
with the multiple bid requirement. Some pieces of the optical
mounting
hardware are beginning to trickle in.
After speaking with Mike Smith, I will design an on-table mechanical
beam
block to stop the PSL beam going into the modecleaner. This will
be in
addition to any shutter located between the PSL enclosure and the vacuum
chamber.
From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>
Informal and out of time meeting.
The two crates containing the TAMA SAS towers
and related linear
electronics have been shipped to Tokyo, have
arrived, have been
redressed and are already in the optics laboratory.
The crates will be opened shortly and the pre-tuned
tower will be ready
to be lowered in their respective vacuum chambers.
Then the tuning
testing and installation of the suspensions will
begin over there.
People interested in photos, please look into:
http://www.ligo.caltech.edu/~takamori/images/tamasas/
The digital electronics is scheduled to fly to
Japan on February 20th.
Akiteru is flying over on the 15th and Riccardo
on the 17th.
Next meetings will be move don Thursdays in order not to have it on
Saturdays in Japan (simple isn’t it?).
The exact date is Thursday the 22nd at 5 p.m. California time, which
makes it on Friday the 23rd at 10 a.m. in Japan. The place in
California is still the small engineering room. T.b.d. in Tokyo.
Virginio, Akiteru
Continuing control development on the test TAMA SAS tower.
LVDT controls work very well, Inertial damping with the accelerometer
is
OK in the yaw mode but there is a problem in signal to noise
in
diagonalization of the two translational direction. Given the
quality
of the LVDT controls, Virginio’s idea is to excite the chain on the
LVDT
translation eigenmodes and align the virtual accelerometers on the
same
reference system. Virginio will try it since Akiteru will be
gone and
the active controls will not be operational in Japan for a while.
IP, solved the problem of the attenuation plateau. It was an artifact
of the tuning springs (Not connected to the shaken part) generating
an
offset in the counterweight calibration transfer functions.
Now that the problem is understood we can calculate and cut the last
small correction counterweights.
Alessandro, Carlo
Machining the accelerometers from 8 CuBe blocks from a new company
and
from two replacement (radiographed) blocks from the old German
provider. The 8 new blocks are workable easily, just great, the
2
blocks from the old company keep breaking tools like last time and
are
almost unmachineable. Interviewed the metallurgist of the new
company,
he explained that CERTAINLY the other CuBe contain Nickel within the
CuBe specs but in concentrations that make it unmachineable.
Everybody
know in the market that the official CuBe specifications are
unsatisfactory and unscrupolous vendors give away the bad kind to
unknowledgeable clients. Good show!!! The company to be
avoided is
DURO METALL, Metall&Schweisstechnic GMBH I Dusserdolf.
I do not have yet the name of the better company which is in Milano.
Edwin, Riccardo
Continuing studies on hysteresis in blade clamping. Studying
the
possibilities of using harder clamps and wedges and to make the blades
thicker at the clamped area.
We will also make new holders for the mini-MGASF blades.
Edwin
Restarting the creep work.
Frederic
Taken service again in Lyon, he will organise a small team of wannabe
French engineers from there. He is getting tooled: "Note that
we just
bought a vacuum chamber and a special device (sensor) in the lab to
measure Sapphire quality factor for the DGA (army)." So
thanks to the
French Army Surplus Cryo seems to be in business already.
For additional information about this report, contact sanders@ligo.caltech.edu