Weekly Report for Week Ending February 15, 2001


 Exec. Comm. Agenda
Highlights
LSC
Administration
Hanford Observatory
Livingston Observatory
MIT
Caltech
Detector
40 Meter
TNI
LASTI
Data Analysis
LIGO II/Adv. R&D
Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  January 15, 2001 will be:

 CANCELLED DUE TO HOLIDAY
 


Special Announcements:


Weekly Report Highlights
 


LSC Issues (Weiss)


no report


LIGO I Construction/LIGO Laboratory Administration (Lindquist)



 
 

WBS 1.2 LIGO Operations--Administration


LIGO Weekly Site Telecon (Lindquist)

There was no site teleconference held on Thursday, February 15, 2001.

The next site telecon is scheduled for Thursday, February 22, 2001.  The list of current actions revised to reflect open actions assigned through February 8, 2001 may be found at ACTION LIST.


PROPERTY MANAGEMENT (Chargois)

From: Ed Chargois <chargois_e@ligo.caltech.edu>


DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner - turner@ligo.caltech.edu>

Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .

ACCOMPLISHMENTS

From: Cleveland Mak <mak_c@ligo.caltech.edu>
Packages Faxes
In 30 30
Out 6 30

Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.


COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Akutagawa, Kaufman)

From: Esther Cunningham <esther@ligo.caltech.edu>

Press here for ACCOUNTS PAYABLE HISTORY DATA.

From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

From: Florence Kaufman <fkaufman@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: irena@ligo.caltech.edu (Irena Petrac)

From: Ed Jasnow <jasnow@ligo.caltech.edu>


Support (Wood)

Dorothy Lloyd

Irene Baldon Rita Torres Elizabeth K. Wood

Advanced LIGO (Frey, Petrac)

From: Thomas Frey <tfrey@ligo.caltech.edu>

Progress Period from 02.09 to 02.15

Accomplishments:

Schedule 02.16 to 02.22:



WBS 1.4.1.2   Project Controls (LIGO Construction)



Reports (Lindquist)

Working on material for the NSF Review scheduled at the end of the month in Hanford. Copies of my materials will be distributed this week for reference as required in other talks.



Change Control/Contingency (Lindquist)

The following Change Requests have been submitted:
 

CR-000018 WBS 1.1.4 Curbing for Service Roads at Livingston G. Stapfer
CR-000019 WBS 1.2 Additional Lab Equipment D. Coyne
CR-000020 WBS 1.1.4 Staging Building and Renovations to Existing Building--Livigston F. Asiri
CR-010001 WBS 1.1.4 Return of Unused Construction Budget To Contingency F. Asiri

Press for the latest Contingency Needs Projection.


COST SCHEDULE CONTROL SYSTEMS (Duncan, Akutagawa)

From: Kris Duncan <kris@ligo.caltech.edu>

From: Cindy Akutagawa <cindy@ligo.caltech.edu>
http://docuserv.ligo.caltech.edu/~fireport
http://docuserv.ligo.caltech.edu/~finance
Reminder: An updated list of all OPEN LIGO account numbers have been posted on the LIGO internal bulletin board. Please use these lists when you need a LIGO account number (or make yourself a printed copy for quick references).

http://docuserv.ligo.caltech.edu/



SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: Ed Jasnow <jasnow@ligo.caltech.edu>

From: irena@ligo.caltech.edu (Irena Petrac)

Quality/Safety (Tyler)

>From: Bill Tyler <tyler@ligo.caltech.edu>


LIGO Hanford Observatory (LHO) Operations (Raab)



 
 

General Items:
--------------
(F. Raab)
 

The installation on the 4K interferometer continues in the corner station. Basically
we have one ITM and the BS complete.
 

We have made some security changes at LHO. A few weeks ago, one of our staff was
burglarized and an LHO master key was taken. We have now replaced the locks and
issued new keys. Jill is recalling all old keys and issuing new keys. We also are
changing some common passwords (e.g., to LHO CDS machines). Call Dave Barker if a
password is needed.
 


LIGO Livingston Observatory (LLO) Operations (Coles)



 

This week we successfully locked the X arm for several hours during the evening last Monday, Feb. 12. Improvements made to the PSL servos were evident in the locking, which was far more robust than that observed during earlier attempts. On Wednesday, Feb. 14., we also locked the Y arm of the interferometer for the first time. This went very smoothly and fell right into place. Locking appeared to be even more stable than the X arm locking observed Monday night. We attempted, for the first time at LLO, to recombine the light from both arms into a Michelson, but encountered problems with the X-arm locking using the anti-symmetric port (see the e-log for details.) Thanks to all the many LLO staff and visitors who have put in some very long days this week.

OPTICS: The small spikes in the frequency control loop of the laser were eliminated by a increase in the pump diode operating
current. Peter King remembered a similar problem at LHO and pointed us in the right direction. We rotated the mode cleaner about
its long axis over last weekend. Rotation of the mode cleaner eliminates the beam clipping we observed at the darkport, but it
appeared to couple the mode cleaner with the stack and it was unreliable in lock. We returned it to the old orientation. We've been
operating the arm locks with what appears to be clipping somewhere in HAM4, presumably at the Faraday Isolator. We reconfigured
(temporarily) ISCT1 to enable a Watec camera and the LSC photodiode at the brightport, and have aligned the QPDs at both ends, as
well as the video cameras at the end transmission monitors. (Kovalik/Giaime/Traylor/Kern)

Operations: Shipped out the last of the equipment necessary for the BSC build-up in LASTI at MIT this coming spring. Initiated an operator training guide allowing all operators and others to cross train off each others specialities. This has been working quite well. We are expanding our e-log capability with a maintenance log area. Returned from the WAO2001 with some interesting notes. They will be in the DCC tomorrow (T010013-00-L).

GC: evaluating Quick Restore software on the Exabyte 220 tape library for use in GC backups. Installed the AIT2 tape library on decatur. (Daniel Sigg installed and configured it while at LLO) The 802.11b network seems to be working very well. I also have drivers for linux for the Lucent (and some other) pcmcia cards. Windows seems to work ok with it also, with the exception of one laptop which I have not been able to troubleshoot yet.
CDS: I am making one of the CDS computers into an applications server (temporary until we have a dedicated apps server) for some of the gnu software packages that have been requested. This will include ghostscript, gcc, gnu ld, make, autoconf, etc. If there are any requests for any other packages, please let me know. (Shannon Roddy, Tom Evans)

Outreach: We have lots of educational outreach activities planned over the next few months in which we are reaching schools and children from all across the
southern portion of Louisiana. Today we were visited by a group of home schoolers from Ascension Parish. Next week we have a group of middle school students from the New Orleans area (Pine View Middle) coming out to tour and do our hands on spectrometry project. In March, we have 2 visits planned from schools in the Lafayette area. We are invited to participate in the St. Bernhard Schools science symposium in which Rai Weiss will be the guest speaker during opening activities and two representatives from our site will conduct polarization of light and spectrometer hands on activities with the 3rd, 4th, and 5th graders. Also in March is the State Science Fair and Junior Science Symposium at LSU in which we will supply judges for physics related projects. Lastly, in May, we will do a presentation on LIGO at the BREC Observatory during one of their fireside evenings chats and host a teacher's workshop (Project Plato). (Bonnie Wascom)


Detector/Technical Support (Whitcomb, Coyne)



 


 

Installation& Commissioning:
Hanford
Livingston
Other Science/EngineeringActivities:
Design/Analysis/Fab
Issues/Concerns
See also the Installation web page

1.1 LHO INSTALLATION & COMMISSIONING

2km Commissioning

Bill Kells, Dick Gustafson, Mike Landry, ... (reported by Dennis Coyne)
Found that the lock robustness, and in fact the preferred lock state, is sensitive to the WFS1 demodulation phase. After adjustment, we now can leave the WFS1 engaged always, and get more frequent locks (> 10 minutes).

Spent a considerable amount of time re-aligning the interferomter to move the beam up ~5 cm in the recycling cavity so that it is centered on the core optcs. The translation was accomplished with MMT1 and MMT3 (see elog entry 1 and elog entry 2 for method; user: reader, password: readonly). Alignment was hampered by noisy 4 km interferometer core installation work and frame builder failures. The beam is now approximately centered on the ITMs vertically (+/- 0.5 cm) and the optical gain boost is > 450 and locks are > 10 minutes without a WFS. The beams are still not centered horizontally on the ITMs as yet.

With the full 2k interferometer realigned and locking well we proceeded with studies of the noise spectrum (ASQ and LSC-Darm). The biggest single improvement found has been with invoking the new MC elliptic filter. A factor of as much as 10 lower (than ASQ spectrum of 02/2 e-log) noise is achieved in the vicinity of 80Hz.

MC Servo

Rich Abbott, Mohana Mageswaran
While working with Peter F.  and Nergis, we have become aware of the need to speed up the electronics in the new MC servo design.  We have been spending time back at the spice simulation level putting in faster parts to improve the servo phase margin. Planned a trip in February to take data on the new MC  servo.  Shipped a differential driver/receiver chassis plus additional  small parts. Finished the Elliptic Filter PCB board layout, and prepared a part list for the rest of the MC Servo Boards. Parts ill be ordered by end of this week.

Digital Suspensions

Jay Heefner
Preparations are being made for the 2/26 test of the digital suspension system at LHO, x-end station.

LSC

Jay Heefner
System drawings for the LSC have been started and should be complete by the end of next week.

Core Optics 4km interferometer Installation

Doug Cook, Mark Lubinski, Hugh Radkins, Betsy Weaver, Rick Graff, Gerardo Moreno, Ken Mason, Corey Gray, Dennis Coyne .....
The ITMx installationand alignment was completed. During the bench assembly and alignment of the new OSEMs on the BS, it was discovered that side OSEM PAMs had been inadvertently added to all optics. The effect on BS alignment was ~30 microrad pitch and ~70 microrad yaw. This significant and unwanted interaction might complicate the diagonalization of the optics, so it was decided to vent and remove the side PAM from all installed LOSs, including ETMx (which was installed the week of 1/15). Using a laser autocolimator, the change in alignment of the ETMx and the ITMx was observed to be < 5 microrad. Side PAMs have yet to be removed from the RM and the MMT3.

The BS was placed into the WBSC1 chamber and is in the process of being aligned. So far we are almost exactly on schedule.

IO 4km interferometer Installation

Dave Ottaway, Malik Rakhmanov, Betsy Weaver, Coreyt Gray (reported by Dave Tanner)
Most of Feb 5-9 was spent installing parts on HAM-1 New OSEMs were installed in MC1 and MMT1. These were the last optics readied to go into the chamber. Prior to the installation we took  PSD of the  optical lever outputs to carefully measure the resonance frequencies of the suspended mirrors as a rigid body. The concern is that the resonances can be affected by the OSEMs. The new OSEMS attract magnets on the mirrors. The covar seals around the LED and PD lens are magnetic. The extra force is much bigger than that of the electro-static effect and is now a major concern for the balancing the optics. The extra force on the mirror due to the ceramic bond  modifies the pendulum potential well. As a result the resonance frequencies of the mirror oscillations become different. The difference is small but reproducible (pitch was not excited):
All 4 SOS towers (MC1, MC3, SM1, and MMT1 were placed into Ham-1. The preference was to begin with the two SOS which are near the middle of the Ham table and therefore are hardest to reach. The suspensions were placed using  micrometer pushers with settings calculated from the IO CAD drawings. In addition, we installed 5 out of 7 DLC mirrors. All the suspended optics were connected to the suspension controllers. The Faraday assembly is next to be installed.

An unexpected problem occured when trying to install the safety tube and the view-port cover onto the main beam view-port of Ham-1. (This is the assembly that connects Ham-1 with PSL enclosure.) The cup which is holding the tube was cut with wrong angle. Unlike 2k Ifo, the viewport on 4k ifo is a small (less than half
of the size of the flange) and is shifted off the center of the flange. It was installed to the Ham chamber offset in vertical direction. The safety cover (built at UF) was made for this orientation.

An inspection of the initial beam pointing inside the Ham chamber showed that the flange needs to be rotated so that the viewport is offset in the horizontal direction. Then the safety cover no longer fits. The solution is to re-machine the cylindrical cup (which holds the tube) to the new angle. This was done on site.

Rick and Malik worked on calculations of the average losses in the 4km pre-modecleaner based on the measurements of its finesse.

1.2 LLO INSTALLATION & COMMISSIONING

Commissioning

Rai Weiss, et al.
Both X and Y arm cavities have been locked separately this past week. The locked stretches are respectably long (20 - 30 minutes) so that one can do diagnostics and vary parameters.

The power fluctuations in the Y arm are smaller by about a factor of between 2 to 3 than in the X arm. The reason for the power fluctuations is still a major research topic and could be caused by incomplete diagonalization of the driven masses, instability of the masses due laser light scattering into the OSEM dampers and/or directly the ground noise excitation. The noise measured in the cavity length control signals is, otherwise, dominated by frequency fluctuations of the light. Direct
improvements could result from simple optimization of the frequency control servos.

The research in the coming week will be dedicated to understanding and improving the performance of the cavities and to prepare the system for recombination of the beams from the two cavities.

LSC

Jay Heefner

PSL

Peter King
Late last Friday Doug Lormand rang and said that they had problems with locking the laser to the reference cavity.  After remotely locking the LLO laser to the reference cavity from the PSL Lab, I noticed that the FAST actuator and Pockels cell output monitors suggested that the loop was oscillating.  Rai and Jonathan told me that they saw some fast glitches on the modecleaner control signal and that the laser had problems.  Those glitches were subsequently noticed on the FAST actuator output.  This was noticed some time ago at LHO and is the third case I know of of this behavior.

I suggested to Rai that he might try turning down the pump diode current for the NPRO.  For some reason it would appear that the trim pot direction for each NPRO is different.  The diode current was increased, resulting in an increase in the laser power and the removal of the glitches.

2.0 OtherEngineering and Scientific Activities

2.1 Design/Analysis/Fab

Optics Modelling

Erika d'Ambrosio

LSC

Rich Abbott
In addition to RFPD's, we are now building differential  driver/receiver boards for use at the sites. Shipped a differential driver/receiver chassis plus additional
small parts to LLO and to LHO.

PSL

Peter King, Ben Abbott, Lee Cardenas
SN #110a delivered 10.8 W last week prior to being turned off over the weekend.  Turning the laser back on Monday, the laser only delivered 10.4 W.  We are fairly confident that the loss in power is not due to a mis-alignment of the laser optics.  The change in output could be due to the chiller not establishing the correct operating temperature.  We will look into this further, later on this week.

Ben and Peter tested out a little high power photodiode circuit.  We measured the 3-dB bandwidth of the transimpedance circuit to be 86 MHz.  The circuit was being tested with an output of 100 mA, when the filter capacitors on the negative Vcc decided to give up.  The reasons for which are not understood.

Rick Karwoski, Paul Russell,Ben Abbott, Sander Liu

New OSEM Heads

Janeen Romie, Myron McInnis
By 2/15, Surmet will have coated their first run of 20 heads of a production run of 200 heads. Myron will pick them up tonight and test them tomorrow morning. If they are satisfactory, he will call Surmet to turn them on for production and drop the parts off to New England Techni-coil tomorrow night. (The production run at RPC in Boulder will be terminated.)

We have a quote for stripping ZrN coated heads from Astro Pak. After I receive all bad parts from RPC, I will forward them to Astro Pak.

So. California Braiding quoted for pigtail assembly work. Another company did not respond. So. California Braiding's bid was a bit high (compared to expectations) and long -- about 8 weeks. We will likely build the 2 km parts in house to be timely and send the balance of the production to So. California Braiding; Our in-house electronics fab is overloaded currently.

DMT

John Zweizig
This week I have been trying to speed up reading in frames for the DMT by profiling frameCPP in an attempt to find inefficient pieces of the code that might be optimized, and by writing an alternative reader class for FrameCPP that could read partial frames.

Data Acquisition

Sander Liu
Four LEMO version Antialiasing Filter Chassis are now ready for delivery to the 40 Meter.


40 Meter Interferometer (Weinstein)



 

February 16, 2001

February 9, 2001



Thermal Noise Interferometer (Libbrecht)


Our objective during this period was to fully characterize and understand
our suspended test cavity and the laser.
 

To achieve this goal, we first locked the laser to our reference cavity by
acting on the laser's pzt driver. This allowed us to pinpoint the driver's
efficiency to 0.7 MHz/V, a factor of 6 lower than expected. Furthermore,
inspection of the control signal (the signal sent to the driver to maintain
the light resonating in the reference
cavity) showed 'spikes' irregularly spaced in time, of amplitude ~1.5V and
~100ms of duration. An estimate of the laser frequency noise is
 

                     2000 Hz/rHz @ 100 Hz
                        30 Hz/rHz @  1 kHz
                        2  Hz/rHz @ 10 kHz
 

compared to the expected values of
 

                        200 Hz/rHz @ 100 Hz
                         20 Hz/rHz @  1 kHz
                          2 Hz/rHz @ 10 kHz
 

The laser frequency noise is found to be in excess by a factor of 10 at 100
Hz.
 

Having characterized the laser, we moved on to the study of the suspended
cavity. The cavity lock, robust with brief lock acquisition times, is
achieved by actuating on both the mirror and the laser pzt driver. In the
frequency window between 40 Hz and 100 kHz, our matlab model agrees well
with the data and we have a good understanding of the topology of the
system.  Below 40 Hz, however, there is a clear disagreement between the
data and the model that needs to be understood.
 

Different topologies were also tried to displace the crossover point
(ranging from 40 Hz to ~800 Hz) between the two control paths in order to
improve the gain of the system. We also tried different unity gain
frequencies (ranging from 1 kHz to 20 kHz) but have not settled yet on an
optimum configuration.
 


LASTI (Zucker)



 
 


Data Analysis and Computing (Lazzarini)



 
 

END-TO-END MODELING (E2E)
(Biplab Bhawal)
 

* Physics Studies
------------------
  (Biplab)
  A pattern for the lock-acquisition criteria with misalignments is
  emerging out of several runs made in last few weeks (although
  interrupted a number of times by power cut-off etc). Based on the
  understandings derived from all these complicated runs, I'm performing
  some simpler situation runs to find out causes behind successes and
  failures of the system in going from stage 2 or 3 to stage 4.
 

  First draft of a possible paper on our work on frequency sensor noise
  is almost ready.
 

* Code improvement
-------------------
  (Hiro and Tavio)
  Hiro worked on Adlib code improvement and some of the issues on
  noise generation.
  Tavio is  studying the Portable Expression Template Engine (PETE),
  a mechanism for loop unrolling and optimization of Array-based
  expressions which hopefully will be used to further speed up
  the end-to-end simulation.
  He will test the speed of matrix inversion and multiplication using
  LAPACK on HP computer, which showed good speed improvements compared
  to the e2e version of matrix class. When modeler is successfully
  ported to CACR, this will be tested.
 

* Client-Server Framework
--------------------------
  (Tavio and Ed maros)
  After last Wednesday's meeting, the idea to create a monolithic
  client-server system was dropped since it would not meet CACR's security
  or administrative requirements.
  On Monday, Ed Maros and Tavio met with a group of CACR people including
  Beven Bennet and discussed a plan for a client-side scripting mechanism
  to submit and review jobs where each user would have his own account on
  the system.  This idea was accepted by all of the CACR staff. As a result,
  Ed is writing a TCK script (`Jobber') that allows submission and query of
  jobs at CACR and Tavio is providing the details of job control on the
  CACR side.
 

* Alfi
-------
  (Bruce Sears)
  - Worked on connection and port problems, particularly checks against
    sink ports being connected to multiple times via derived nodes.
  - Reorganizing some of the core ALParser code to make sure methods are
    not being made redundant or are unused if they are not easily found.
 
 
 

LDAS SOFTWARE
(Kent Blackburn)
 

We are still busily preparing and fixing software issues in preparation for
the release of LDAS. A couple of problems in the metaDataAPI which impacted
the ability to get data out of the database were identified and have now
been fixed. Similar problems showed up in the lightWeightAPI and also have
now been fixed. The half dozen or so problems with the dataConditionAPI test
have now been reduce to a single known problem which we think we know the
fix
for. This problem involves linear filtering code for complex data sequences.
It will require a new set of test scripts to exercise this last remaining
bug.
 

The documentation for the LDAS release is now ready for the two new tarballs
of distribution code for the controlMonitorAPI client and frameCPP library.
 

New links were added to the LDAS software block diagram for the
eventMonitorAPI. Several meetings were held this week to outline the
development and implementation for the eventMonitorAPI now that the baseline
requirements are available.
 

A load balancing test plan was drafted and sent the MPI team for the
wrapperAPI and mpiAPI. This test will be performed on the version of these
APIs available with the next release.
 

We were hoping to be in a position to push a pre-release of LDAS to the
sites today but due to security issues at Hanford, we are now having to
change
all LDAS system account passwords which will prevent development and
debugging
on the systems for several hours and mostlikely delay our plans for a
software
push to the site until tomorrow. We will need to carry out our test
procedure
one last time once we have the code at the sites before officially tagging
the repository and preparing a new software release distribution.
 

A subcommittee of GWIC meet over the weekend to discuss network data
analysis. The outcome of the meeting is a plan to be in a position to share
a handful of PEM channels by June 1 of this year between LIGO, GEO and VIRGO
for the purpose of performing coincidence studies.
 

This week also involve a significant amount of interaction with the Upper
Limits groups, including a chairs meeting on Tuesday. Proposals are now
available from three of the groups with the fourth group planning to hold
its
first meeting on Friday of this week.
 
 
 

LDAS HARDWARE
(Stuart Anderson)
 

The last 2 years of LHO minute trend frames have been successfully retrieved
from the LDAS archive for re-transmission back to LHO after a recent disk
failure on the CDS frame builder.
 

ldas-dev survived a diesel generator power test at Caltech.
 

The main LDAS software server has been upgraded to 4GB of memory in
preparation
for transferring it for use as the ldas-dev database server.
 

Ordered additional memory for laptop and quad-xeon datacon box at ldas-dev.
 

The LDAS 30-slot AIT-2 robot has been returned to LHO from Cybernetics.
However, it is unclear what if anything was fixed/replaced.
 

The AIT-2 unit at LLO is undergoing continuing tests in preparation for the
E3 run attached to an U10 to avoid problems encountered during E2 run with
the drives attached to the main LDAS server.
 

Initial testing of the new AMD K7 and Intel P4 LDAS test machines running
a beta version of RedHat7.1 is proceeding well.
 

The LHO network diagram has been updated using Visio2000 to indicate the
move of LDAS from ATM to Gigabit Ethernet.
 

All LDAS Unix passwords have been changed.
 
 
 

GENERAL COMPUTING
(Larry Wallace)
 

MIT:
-Keith Bayer has joined us and is learning about and looking over the
 system. Larry Wallace will visit next week to give the larger picture and
 strategize.
 

Livingston:
(Shannon)
-Evaluating Quick Restore software on the
 Exabyte 220 tape library for use in GC backups.
-Installed the AIT2 tape library on
 decatur. (Daniel Sigg installed and configured it
 while at LLO)
-The 802.11b (wireless) network seems to be working
 very well.  I also have drivers for linux for the
 Lucent (and some other) pcmcia cards.
 Windows seems to work ok with it also, with the
 exception of one laptop which I have not been able
to troubleshoot yet.
 

Hanford: (NO REPORT)
 

CIT:
(Lisa)
-Took the laser safety eye-exam.
-Wrote scripts to put the daily & weekly backups onto the cybernetics robot.
 I'm still working out the kinks on those but am very close to getting the
 daily/weeklys off of poor, old, decrepit rastaban.
-Installed SunPCI cards for 2 computers on 6Millikan so that people can do
their pcard stuff on their sun boxes.
-Larry and I finally figured out why rsh to hamal wasn't working.  It was
the
 path specified for tcpd.
-Worked with Ed Chargois to get a laptop shipped back to Dell for repair.
 

(Sam)
-Worked on a number of PC issues.
-Assisted in a office redecoration.
 

(Barbara)
-Finished installing the stand-alone DCC report.  There is a link on the
 Internal Bulletin Board under Documents and Publications that will allow
 you to download a text version of the DCC database.  The text version can
 then be imported into a spreadsheet.
-Fixed a problem with the style sheet for the LIGO web site that occurred
 only in Netscape.
-Made a change to the weekly job that compacts the DCC database that may
 prevent future failures.  Also DCC will remember to shut down the database
 on Tuesday evenings.
-Helped a fellow from the astronomy department install TimeTarget (I am
 the keeper of the Caltech site license).
-Made numerous web site changes to LDAS and LIGO sites.
 

(Suresh)
-Begun restoring old data since 1994 from tape archives to 235 GB RAID
system
 in sargas. After restoring about 90 GB of data, this will be archived in
high
 capacity SONY tapes in compressed mode in Cybernetics robot backup system.
 This will free up substantial space in tape cabinet.
-Received 2810 ATM uplink module from Marconi Inc. Installed in 2810 of
 computer room and subsequently upgraded ATM firmware. Returned old unit to
 Marconi.
-Replaced Irena Petrac's PC with working one after observing erratic system
 crashes. Now I am working on the unit by replacing hard disk with a new
one.
-Installed a Network Interface Card (NIC) on system RANA to make a gateway
 machine to 115 and 113 subnets in 40-Meter.
-Updated HP Web Jetadmin Server to reflect new printers/plotters and their
 descriptions.
 

(Larry)
-Spent a great deal of time working on orders and pushing things through the
 system to get items in for the next NSF review and LSC meeting. So far it
looks
 like we will have the computers and projectors we need for the meetings.
-Resolved another procurement issue with SUN.
-Reworking a number of financial items. Fortunately I had a backup of my
work
 and only lost a small portion when my disk crashed.
-Resolved a couple of virus problems. There have been a number of machines
that
 had viruses mailed to them but only a couple which some repair work had to
be
 done.
-Just a reminder on the PC's using Eudora there is an attachment directory
that
 the files need to be cleaned out of. Just deleting the e-mail doesn't take
care
 of everything.
-Working a few more logistical issues with DCC and the LSC conference.
-Worked with Suresh to resolve a couple of network issues. Hopefully, we
will be
 able to do some testing with the 2810's under different configurations this
next
 month.
 
 


LIGO II/Advanced R&D (Sanders)


Advanced LIGO PSL
Peter King
        I had a few discussions with Benno Willke about the timing of
things.  Especially about when a good time for the electronics engineer
from GEO to visit might be.
 

3.2 40m Lab
        Quotations have been gathered for the optics in order to comply
with the multiple bid requirement.  Some pieces of the optical mounting
hardware are beginning to trickle in.
 

After speaking with Mike Smith, I will design an on-table mechanical
beam
block to stop the PSL beam going into the modecleaner.  This will be in
addition to any shutter located between the PSL enclosure and the vacuum
chamber.

From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>

Informal and out of time meeting.
The two crates containing the TAMA SAS towers and related linear
electronics have been shipped to Tokyo, have arrived, have been
redressed and are already in the optics laboratory.
The crates will be opened shortly and the pre-tuned tower will be ready
to be lowered in their respective vacuum chambers.  Then the tuning
testing and installation of the suspensions will begin over there.
People interested in photos, please look into:
http://www.ligo.caltech.edu/~takamori/images/tamasas/
The digital electronics is scheduled to fly to Japan on February 20th.
Akiteru is flying over on the 15th and Riccardo on the 17th.
 

Next meetings will be move don Thursdays in order not to have it on
Saturdays in Japan (simple isn’t it?).
The exact date is Thursday the 22nd at 5 p.m. California time, which
makes it on Friday the 23rd at 10 a.m. in Japan.  The place in
California is still the small engineering room.  T.b.d. in Tokyo.
 
 

Virginio, Akiteru
Continuing control development on the test TAMA SAS tower.
LVDT controls work very well, Inertial damping with the accelerometer is
OK in the yaw mode  but there is a problem in signal to noise in
diagonalization of the two translational direction.  Given the quality
of the LVDT controls, Virginio’s idea is to excite the chain on the LVDT
translation eigenmodes and align the virtual accelerometers on the same
reference system.  Virginio will try it since Akiteru will be gone and
the active controls will not be operational in Japan for a while.
 

IP, solved the problem of the attenuation plateau.  It was an artifact
of the tuning springs (Not connected to the shaken part) generating an
offset in the counterweight calibration transfer functions.
Now that the problem is understood we can calculate and cut the last
small correction counterweights.
 

Alessandro, Carlo
Machining the accelerometers from 8 CuBe blocks from a new company and
from two replacement (radiographed) blocks from the old German
provider.  The 8 new blocks are workable easily, just great, the 2
blocks from the old company keep breaking tools like last time and are
almost unmachineable.  Interviewed the metallurgist of the new company,
he explained that CERTAINLY the other CuBe contain Nickel within the
CuBe specs but in concentrations that make it unmachineable.  Everybody
know in the market that the official CuBe specifications are
unsatisfactory and unscrupolous vendors give away the bad kind to
unknowledgeable clients.  Good show!!!  The company to be avoided is
DURO METALL, Metall&Schweisstechnic GMBH I Dusserdolf.
I do not have yet the name of the better company which is in Milano.
 

Edwin, Riccardo
Continuing studies on hysteresis in blade clamping.  Studying the
possibilities of using harder clamps and wedges and to make the blades
thicker at the clamped area.
We will also make new holders for the mini-MGASF blades.
 

Edwin
Restarting the creep work.
 

Frederic
Taken service again in Lyon, he will organise a small team of wannabe
French engineers from there.  He is getting tooled: "Note that we just
bought a vacuum chamber and a special device (sensor) in the lab to
measure Sapphire quality factor for the DGA (army)."   So thanks to the
French Army Surplus Cryo seems to be in business already.


For additional information about this report, contact sanders@ligo.caltech.edu