Weekly Report for Week Ending February 8, 2001


 Exec. Comm. Agenda
Highlights
LSC
Administration
Hanford Observatory
Livingston Observatory
MIT
Caltech
Detector
40 Meter
TNI
LASTI
Data Analysis
LIGO II/Adv. R&D
Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  February 12, 2001 will be:

 (Meeting time: 10:30 am Pacific Time)

Open meeting 10:30 - 11:30

  1. Announcements
  2. LSC Issues (Weiss)
  3. Comments on Weekly Report
  4. WBS 1 LIGO I Construction (Lindquist)
  5. WBS 2 LIGO Lab Operations
  6. WBS 3 and 4  Advanced R&D and LIGO II (Sanders)
Executive Committee only 11:30 - noon   Topics:
 

Special Items:


Special Announcements:


Weekly Report Highlights
 
 


LSC Issues (Weiss)


no report


LIGO I Construction/LIGO Laboratory Administration (Lindquist)



 

WBS 1.2 LIGO Operations--Administration


LIGO Weekly Site Telecon (Lindquist)

There was a site teleconference held on Thursday, February 8, 2001.  Subjects discussed included the selection of NTD Architects as the A/E for the Hanford Support Building and preparations for the Proposed Operations scheduled for the end of the month at Hanford.

The next site telecon is scheduled for Thursday, February 15, 2001.  The list of current actions revised to reflect open actions assigned through February 8, 2001 may be found at ACTION LIST.


PROPERTY MANAGEMENT (Chargois)

From: Ed Chargois <chargois_e@ligo.caltech.edu>


DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner - turner@ligo.caltech.edu>

Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .

ACCOMPLISHMENTS

From: Cleveland Mak <mak_c@ligo.caltech.edu>
 
Packages Faxes
In 46 30
Out 16 34

Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.


COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Akutagawa, Kaufman)

From: Esther Cunningham <esther@ligo.caltech.edu>

Press here for ACCOUNTS PAYABLE HISTORY DATA.

From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

From: Florence Kaufman <fkaufman@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: irena@ligo.caltech.edu (Irena Petrac)

From: Ed Jasnow <jasnow@ligo.caltech.edu>


Support (Wood)

 
Irene Baldon

On travel this week.

Rita Torres

Out due to illness.

Dorothy Lloyd

  • Processed the usual requisitions, invoices and receiving on-line. For more detail, see "Cost Schedule Control Systems" report by Esther Cunningham.
  • Tracked and followed up on invoice problems.
  • Reviewed and recorded payments processed by Esther for the week of January 29, on contract summary sheets and LIGO database.
  • Continued to work with Florence and Ruth on transferring encumbrances to new fiscal period and closing out old POs.
  • Continue to monitor contract and blanket order funding levels and notify task managers when supplements are needed.
  • Continue to update PO Log books.
  • Jim continues to do data entry in the LIGO database and help out in both the DCC and travel areas.
Elizabeth K. Wood
  • It’s been an interesting week with respect to Human Resources.  A paycheck was made out to a brand new employee for the wrong amount because HR’s Records department entered the hourly rate incorrectly, and another employee didn’t get a check at all because Records didn’t think updating current visa information was terribly important or urgent, therefore denying the employee a paycheck.  Those errors are only two of an on-going ballet of faux pas.  On the bright side, however, our payroll processor Cassandra leaped through flaming hoops to fix all of these inaccuracies in a timely manner.
  • I’ve had two meetings over at HR this week to discuss immigration issues past and present and problems with Records.  I also spent most of Wednesday morning in HR dealing with a variety of job classification issues and retroactive labor distributions.
  • Most of the people in HR now recognize me and say "hi."

  • Jill in Hanford and I have been working together to get the next NSF Review in shape.  Note:  The dry-run will be Tuesday, February 20 in the SCR beginning at 9:00 a.m.  I would really like to have your final copies available by the end of business Wednesday, but because the dry-run is so late, we may need to push this deadline to Thursday.

Advanced LIGO (Frey, Petrac)

From: Thomas Frey <tfrey@ligo.caltech.edu>

Progress Period from 02.02 to 02.08

Accomplishments:

Schedule 02.09 to 02.15:

WBS 1.4.1.2   Project Controls (LIGO Construction)



Reports (Lindquist)

Working on material for the NSF Review scheduled at the end of the month in Hanford.



Change Control/Contingency (Lindquist)

The following Change Requests have been submitted:
 

CR-000018 WBS 1.1.4 Curbing for Service Roads at Livingston G. Stapfer
CR-000019 WBS 1.2 Additional Lab Equipment D. Coyne
CR-000020 WBS 1.1.4 Staging Building and Renovations to Existing Building--Livigston F. Asiri
CR-010001 WBS 1.1.4 Return of Unused Construction Budget To Contingency F. Asiri

Press for the latest Contingency Needs Projection.


COST SCHEDULE CONTROL SYSTEMS (Duncan, Akutagawa)

From: Kris Duncan <kris@ligo.caltech.edu>

From: Cindy Akutagawa <cindy@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: Ed Jasnow <jasnow@ligo.caltech.edu>

From: irena@ligo.caltech.edu (Irena Petrac)

LIGO Hanford Observatory (LHO) Operations (Raab)


General Items:
--------------
(F. Raab)

4K Installation
---------------
(D. Cook)

The 4K installation is proceeding close to its schedule. A few set backs as
usual. The MMT3 optic and RM optic are in and aligned. The IOO group has
started to place their components into HAM1 and aligning the beam from the
PSL table. BSC3 elevation was set and the ITMx is ready to install. The CAS
newly installed software seems to have a couple of glitches that caused a
work around in setting the elevation. We are having to share temporary
controllers and satellite boxes as the permanent ones are not available as
yet which is not a problem until we start the COS alignment. Some COS
components have also been placed where parallel tasks have allowed. The BS
coordinates need to be reviewed as we have some conflicting numbers. LOS
and SOS suspensions are being processed with the new OSEMs and are keeping
pace with installations. Thanks to a large group of participants things are
going well.
 

4k PSL Activities (T. Mahood and M. Guenther):
-------------------------------------------------
Upon completion of the assorted leg vibration investigations, the slightly wandering
4k optical table has been coaxed back to its rightful position and leveled.
Following that, the remaining optical and electronic components have been placed on
the table and are in the process of final alignment.  "Test point" bulkhead connectors
have been installed to allow for sampling of signals from various table components
when working at the table, without disturbing the sometimes delicate positioning of
the signal sources.
 

4k Reference Cavity (M. Guenther):
---------------------------------------
A new ion pump has been installed and activated on the 4k PSL reference cavity. An
RMA # has been obtained for the failed ion pump, and it will be returned for repair,
hopefully under warranty. The heater blanket has been installed on the reference
cavity, we expect the installation of temperature sensors and insulation to be
complete 2/9.
 

4k Pre-modecleaner Losses (M. Rakhmanov and R. Savage)
----------------------------------------------------
We have analyzed the 4k PSL PMC losses based on recent measurements.  Assuming all
three mirrors have equal losses, we estimate the losses per mirror to be about
1340 parts per million. This is costing us about 1.7 W of light. The output is just
over 6 W with 9 W input and 88% modematching.
 

Controls
--------
(D. Barker)
 

Returned 50GB RAID to Cybernetics for repair.
 

Working on EPICS problems with new Motorola 162-242 CPU boards.
Installed latest EPICS 3.13.3, working with VxWorks on latest BSP and
with EPICS Tech-Talk community for possible solution to this problem
 


LIGO Livingston Observatory (LLO) Operations (Coles)



 

OPTICS : Many observers have noted the asymmetry of the video image seen at the darkport since we first observed interference in the Michelson last December. This week we set forth to ascertain where the (apparent) beam clipping was occurring. An initial attempt to yaw MMT3 while looking at the darkport video camera seemed to improve the image, whilst moving it off the field. Our sense was that the clipping was occurring in the Faraday on Ham 1. Joe Kovalik decided to yaw SM1, and we unambiguously observed the clipping to diminish. We iterated SM1, and the beam alignment on ISCT-1 and 4. We then observed a circularly symmetric image at both the bright and dark ports. It is unfortunate that this clipping was discovered this month, because in moving SM1 we ruined the alignment of the input beam launched from MMT-3. It would have been wise to double check the alignment scheme attempted last year when ISCT-1 was moved into position. In as much as we were forced to perturb the telescope's pointing, we elected to recheck the beam position on the mode-matching telescope's mirrors. A Sony camera positioned above MMT-2 in HAM-2 permitted us to center the beam on MMT-2 by iterating between pointing positions when we saw the beam striking the structure to the left and right, above and below the optic. Last fall, we were unable to perform a similar test at MMT-3 because of the insensitivity of the Sony cameras, but now we have available a Watec camera and find that it has ample sensitivity to image the ~4" diameter beam at MMT-3. Not surprisingly, we found the beam to be well above center, by an amount that appears consistent with what we observed during those times when we had the X-arm locked last week. We centered the beam on MMT-3. We have spent several days this week reestablishing the mode matching telescope, as well as mode cleaner alignment. We are close to completing this task, but a catastrophic power outage this morning has hindered our work. (Kovalik/Giaime/Traylor/Kern)

OTHER: LLO experienced a major power disruption Thursday morning. This was a general outage that affected the surrounding region as least as far away as Denham Springs, the major population center 15 miles east. All systems were recovered by mid afternoon.

Augering and excavation for the staging building addition is now underway, creating a noisy seismic environment during the day which often makes it difficult to carry out commissioning work. We have begun to staff the control room on a regular basis on Saturdays to take advantage of the "quiet time" when there is no construction work on site.

Outreach: Students from two Livingston Parish Jr. High Schools (Plaquemine High School and Frost High School) spent a day at LIGO in the Job Shadow Program working with Bonnie and others in the Control Room and in the Front Office. Job Shadow is a program in the public school system in Louisiana to help students gain knowledge and
awareness about the working world and various careers.
 


Detector/Technical Support (Whitcomb, Coyne)



 

DETECTOR

 
Installation& Commissioning:
Hanford
Livingston
Other Science/EngineeringActivities:
Design/Analysis/Fab
Issues/Concerns
Seealso the Installation web page

1.1 LHO INSTALLATION & COMMISSIONING

2km Commissioning

Nergis Mavalavala, Peter Fritschel, Richard McCarthy, Josh Myers, Rich Abbott, Dave Barker, Stan Whitcomb
Most of this week was spent implementing the new mode cleaner servo. The new servo is now working and some limited characterization has been done. The loop now has a unity gain frequency of 75 kHz with phase margin of ~40 degrees. An elliptic filter in the MC length path at 150 Hz (temporarily higher than design cutoff at 35 Hz) is being used to allow for a higher crossover (~30 Hz) frequency. We are able to engage this elliptic filter to suppress frequency noise above 150 Hz. We tested this with a single arm cavity locked, but were unable to see the improvement since the frequency noise does not dominate the arm cavity signal above ~100 Hz. Since then we have had short periods of full interferometer locking and are now working on bringing the ifo up again.

Before starting the work on the modecleaner servo, we were able to take a calibrated noise spectrum with the whitening filters engaged on the antisymmetric port photodiode.  The calibrated error signal and control signal for the arm length difference is shown in a  spectrum in the elog. Because of the servo, the correct estimator of the noise is to lake the higher of the green and blue curves at any given frequecy.  The dark noise in the photodetector/electronics is shown in the red curve.  The bect sensitivity (2 x 10e-16 m/rtHz) is a significant improvement over what we had in the E2 run last November.  The dominant noise below about 400 Hz is frequency noise (though as far as we can tell there is something else lurking just below the frequency noise), and should be helped by the servo change to the modecleaner described above.

Core Optics

Doug Cook, Mark Lubinski, Hugh Radkins,  Betsy Weaver, Rick Graff, Gerardo Moreno, Ken Mason, David Ottaway, Corey Gray, .....
The vertex installation of the 4 km interferometer is in full swing.  MMT3 and the recycling mirror have been installed and aligned.  The setup for installing ITMX is underway. The irises for aligning the COS autocollimator have been installed and aligned.

The safety shutter for the PSL to vaccum chamber connection had fit problems and is being reworked.  Small optic suspension have been prepared for installation and the first one may be going in at this very moment.

So far we are almost exactly on schedule.

COS

Mike Smith, Ken Mailand
Preparation is being made for installation of the 4K COS vertex equipment starting the week of 2/19.

E2 Investigations

Szabi Marka
I have been working on the final document of the E2 timing investigation.
 

1.2LLO INSTALLATION & COMMISSIONING

Commissioning

Rai Weiss, et al.
Commissioning activity at Livingston was dedicated to improving the ability to lock the x arm and to understand the source of the power fluctuations while the x arm is locked.

The most time consuming effort (still on going) is the realignment of the mode matching telescope and the mode cleaner to avoid the clipping of the beam at the symmetric and antisymmetric ports while still maintaining the alignment of the arm cavities.

To increase the dynamic range of the lock using the ITMX, the coil driver has been modified as it was at Hanford.

The optical lever damping servo for ETMX is currently being set up and an attempt is being made to install and use the Matt Evans acquisition code for the x arm locking.

The vibrations associated with construction of the new building at the site prohibit cavity locking during the day and most of the locking and diagnostic work is taking place at night.

2.0 OtherEngineering and Scientific Activities

2.1 Design/Analysis/Fab

Optical Metrology

Helena Armandula, GariLynnBillingsley
2ITM03 data set is complete. Averages from the various data sets indicates that the radius of curvature is within specs.

Optics Modelling

Erika d'Ambrosio
The flat topped modes studies are going on since they bring an improvement for the thermoelastic noise of a factor ~3. The problem now arises on stability and with a view to better understanding what are the experimental issues, there was a meeting with Nergis Mavalvala who also gave me some materials that helped me to prepare the input files for the FFT-code simulation runs. The interferometer seems to react in a different way to a disalignment of the mirrors if they are:
- spherical or
- reshaped in order to excite the flat topped mode.
 

Light is bounced back toward the recycling cavity because of the mismatch in the former case (so that more power exits from the asymmetric port or outside the recycling mirror) while the losses are so high in the latter case that inside all cavities (since they are coupled) the energy storage performance is corrupted though there is a sort of addition of these two effects so that in the recycling cavity the gain is less reduced than in the long arm cavity.

In order to link such results to a mathematical prediction I wrote a small Fortran code that evaluates the scalar product of the field maps inside the cavity after normalizing them. As it could be expected the squared value roughly coincides with how much gain survives if one mirror is tilted.
 

Example for reshaped mirrors:
|<u_tilt|u_notilt>|^2=1-0.00315           Gain_tilt/Gain_notilt=1-0.00345
Example for spherical mirrors:
|<psi_tilt|psi_notilt>|^2=1-1e-5           Gain_tilt/Gain_notilt=1-5.5e-6

ASC

Jay Heefner
A daughter card has been developed to add an output buffer to the universal dewhitening module. We are in the process of adding the RevA1 mods to the boards we have in house. They should be complete by 2/10. They will then be shipped to the sites to be swapped with the RevA modules in the field. LLO's modules should be swapped next week.

Rolf Bork
Request from Rai and also LHO to add optical lever servos for end station test masses.  It is requested to be installed at LLO by this weekend, so this is my focus for the next day or two.

Report out of LHO that they are seeing 16Hz components on the ASC DAC outputs.  I still need to get more info on this before starting to track it down.

LSC

Rich Abbott,  Flavio Nocero
Shipped additional 150 Hz eliptic filter board to LHO for use with new MC servo.  We have been supporting the effort to commission the new board up at LHO and simultaneously updating the design for the release of a new board.

We are now building 16 new RFPD's for use at various frequencies.

Mode Cleaner Servo

Mohana Mageswara, Rich Abbott, Nergis Mavalvala, Peter Fritschel
The Mode Cleaner System(Rev A) is running up in Hanford. Mohana made the epics screen for the Mode Cleaner servo, andalso sent a tested Elliptic Filter with the cutoff frequency 150 Hz to the Hanford site. She have finished the design of  the next revision Servo with some changes on it, and will be finishing up the CAD by end of this week.

PSL

Peter King
The output power from SN #110 decayed to the point where its output power was no longer greater than 10 W, despite a careful alignment by Lee. Following the lessons learned from the recent LHO 2k laser maintenance call, the cooling hoses were shortened to 15 ft.  After a tweak to the alignment the output power of the laser is now back over 10 W.  The output beam from the laser is currently being characterized.

Rick Karwoski, Paul Russell,Ben Abbott
Custom Card Situation:

  • A second set of PMC cards (LASTI/40m) has been completely bench tested
  • These boards will be system tested at Lauritsen at our earliest opportunity
  • A full set of updated schematics has been generated on all PSL custom boards and sent to Hanford

  • 40m/LASTI Cross-connect and General PSL assembly
  • We are working with the crew at Hanford to update the current cross-connect documentation.
  • We are rounding up components, cabling, etc. in preparation for the upcoming cross connect assembly.
  • The flawed photodiode has gone through a second round of troubleshooting, and is now ready for another test at Peter King's Lab.

  • Intensity Stabilization
  • Evaluation of the photodiode circuit requirements is underway
  • Matlab simulation of proposed servo control strategies is in process.
  • The simulation model is based on frequency response and noise data taken on the laser/detector setup in Lauritsen
  • New OSEM Heads

    Janeen Romie

    Digital Suspensions

    Rolf Bork
    Software for LVEA controller is about 80-90% complete. Key items yet to be added are excitation and test point interfaces to GDS.  Since we are experiencing a delay in receiving more Pentek ADC/DAC modules necessary to populate the LVEA system, I'm going to shift my efforts to getting the end station software together.  This will allow us to do a "first article test" on the LHO ETM with the parts we do have, hopefully the week of Feb. 26. It will require a certain amount of "throw away" code, since the LVEA subsystem will not be complete (LVEA components provide DAQ and operator interfaces for LVEA and end stations).

    Jay Heefner

    Data Acaquisition

    Rolf Bork, Hongyu Ding
    After meeting with LDAS, Stan and Sigg, looks like we want to acquire EPICS channels at both 1Hz and 16Hz and increase frame sizes from 1 second to 32 seconds.  First change requires primarily code changes in the DAQ controller software (my code).  Second change requires framebuilder code revision by Alex Ivanov.  Target is to have code updates by time of E3.  I still need to check with Lazzerini on whether the 32 second frame length is in fact agreed to and if Alex will have time to make his necessary changes. If we are go to proceed, we want to test on the Wilson House development system week of Feb. 19 and install at LHO week of Feb. 26. I'll be at LLO March 5 thru the E3 run, and would install and test new software there early that week.

    Hongyu is modifying dataviewer to create data groups by signal names, rather than using the group IDs given in the DAQ master configuration table.

    GDS

    Daniel Sigg
    Made the channel selection easier from the DTT. This was necessary because a large number of slow channels have been added which in turn were "hiding" the fast ones. The new channel selection combobox separates slow and fast channels and allows manual editing of channel names including copy-paste.

    Last week was spent ugrading the DTT at LLO and installing the reduced data set writer on decatur.

    DMT

    John Zweizig
    Last week, about 3000 Epics channels were added to the LHO online (broadcast) frames when these channels were added to the standard frame configuration file. The resulting frames are not readable by the FrameCPP library in less than 1 second on the DMT nodes. As a result, those monitors that need to read many contiguous frames started to fail.

    To provide a temporary remedy for this problem, I have written and debugged a new data accesser (Dacc) class. The new Dacc classe uses the DaqReader and DaqFrame classes in FrameCPP which read a single frame as a template and then quickly updates specified fields from subsequent files. With this new readout class the CPU usage of a typical monitor drops from >90% to about 15%!

    This temporary solution has several properties that make it undesirable as a final solution (a) these classes do not support multi-frame files, (b) there is no way to verify that a given channel was actually updated, and (c) the classes will not work with compressed data.

    Because of these faults, the faster access class can not be used offline. I have therefore added a new library directory which will be linked to by online programs only. The online library is now being used by most monitors and I am recompiling others as the sources become available. Clearly, this solution will have to be replaced in the near future with one that is appropriate for both online and offline purposes.

    Data Acquisition

    Sander Liu
    Ordered a heavy duty shipping crate from carpenter's shop and shipped the +/- 5V @25A power supply to MIT.
    In the process of building a test stand to facilitate testing the PSL boards for Rick Karwoski.
    The new version of our de facto EDA - Protel 98 software, the Protel 99SE version,  contains a very nice spice circuit simulation engine that can be used to simulate both analog and digital circuits. It can provide insights into our circuit design philosophy and check circuit performance before boards are built. Anyone interested in getting this porton of the program going, I will be more than happy to help you get started.


    40 Meter Interferometer (Weinstein)


    no report received


    Thermal Noise Interferometer (Libbrecht)



     
     

    We have re-locked one suspended arm cavity, and are testing various servo
    configurations.  We are measuring transfer functions for the components and
    are building a detailed Simulink model of the servo.  Part of this effort
    is aimed at eliminating a strong resonance at 21.5 Hz, which we suspect is
    caused by a poor crossover.
     

    The seismic isolation system appears to have a slow drift (over several
    weeks), but fortunately the suspension controllers have enough dynamic
    range to compensate for the misalignment this causes.  We have improved the
    cavity throughput over our last lock by fine-tuning the alignment and the
    servo parameters.
     

    We have also begun construction of isolation transformers for reducing
    ground-line noise.
     


    LASTI (Zucker)


    no report received


    Data Analysis and Computing (Lazzarini)


    LIGO DATA ANALYSIS (LDAS)
     

    LDAS SOFTWARE SYSTEM
     

    (Kent Blackburn)
    - The focus this week has been to generate a new release of LDAS which
      has full support for the MPI MDC as well as a working version of the
      dataConditionAPI with close to the full set of functions that were in
      place during the dataConditionAPI MDC. All of this is to be a precursor
      to another release of LDAS at the end of the month in support of the
      next engineering run (E3). New in the release will be a fully functional
      controlMonitorAPI and a greatly expanded frameAPI and frameCPP which are
      will now be used to generate LIGO frames with "Table of Contents" which
      can be used to in analysis software to improve data I/O speeds.
     

    - The baseline requirements for the eventMonitorAPI have now been formally
      documented and included in the LIGO DCC. The LDAS software team will
      begin development of this API with a target delivery of the first half
      of March.
     

    - The dataConditionAPI has really been on a roller-coaster ride for the
      past week with our development team working around the world (and around
      the clock) to recapture the original functionality based on the new
      Universal Data Type (UDT). The only remaining actions are linear
      filtering and resampling and these should be ready in one more of these
      "follow the setting Sun" work days. One other area of intense activity
      associated with the dataConditionAPI has be a set of enhancements and
      modifications to the MDC test scripts to support running of the tests
      on systems other than the LDAS-Development system. In addition some of
      the additional ingestion processing associated with the new UDT have
      added a set of new dataset naming conventions which had to be touched
      up to successfully run these scripts. These have been completed now and
      all that remains is to run the test scripts once the dataConditionAPI
      is conpleted.
     

    - New instructions are being added to the LDAS webpages specific to the
      building and installation of the frameCPP library and the
    controlMonitorAPI
      client. Separate tarballs will also be generated for these allowing for
      users of these sub-packages of LDAS to limit their downloads.
     

    - There have been several problems identified with LDAS user command,
      especially with the returnprotocol options. These are being fixed in
      time for the new release. But the fixes will require some modifications
      to GUILD (the Graphical User Interface to the LIGO Database), which
      will also be added and tested for this next release.
     

    - Only minor changes have been made in the wrapperAPI this week. Mostly
      to support the full description of event data to be generated by the
      underlying search algorithms prior to distribution to the soon to be
      developed eventMonitorAPI.
     

    - Several C++ issues associated with dynamic memory allocation were
      identified in the ILWD code and code that is based or used the ILWD.
      The ILWD issues have now been fixed and all codes using this new code
      in each API have been brought in line with the correct usage.
     
     
     
     

    LDAS HARDWARE SYSTEM
     

    (Stuart Anderson)
    - Linux (RedHat 7.1beta) has been successfully installed on the new LDAS
    Beowulf
      test nodes (Intel P4 and AMD K7).
     

    - The last 30x4GB of old disk drives reclaimed from the old CACR Paragon
      parallel computer by LDAS have now been decomissioned by LDAS to be
      further recycled to hold radio pulsar data.
     

    - The LDAS Cybernetics AIT-2 robot at LHO has been shipped back to the
    vendor to
      work on an intermittent problem before the upcoming E3 run.
     

    - Solaris UFS logging has been enabled on all of the LDAS Sun computers at
    LLO,
      which completes this upgrade for all LDAS Sun computers.
     

    - Sun has identified the solution for an intermittent E450 reboot problem.
      A different graphics driver (TSIpgx) is being installed on all the
    effected
      machines which where running a less reliable driver (TSIgfx). This is
    fully
      expected to fix the problem and allow for reliable rebooting of these
    machines.
     

    - Solaris 8 maintenance update 3 is being applied to all LDAS Sun computers
      to allow investigation of the new "snapshot" functionality in the UFS
      filesystem, i.e., this should finally make it reliable to backup active
    Solaris
      UFS filesystems. Furthermore, if it works as well as the canonical Network
      Appliance filesystem this may also allow the backing up of active LDAS
    database
      systems and thereby increase the availability of LDAS.
     

    - Larry Wallace will be managing the LDAS system at LLO during the E3 run.
     

    - The large HP plotter (hpcolor0) is now working on the 6th floor of
    Millikan
      at Caltech.
     
     

    FAST CHIRP TRANSFORM (FCT)
     

    (Philip Charlton)
    - worked on code to test the numerical accuracy of Rick Jenet's FCT
      implementation (which uses approximations) compared to the slow, exact
      discrete chirp transform. The issues here are:
     

      - to verify that the approximate FCT implementation is accurate to
        within the analytically determined error bounds. A failure here
        may indicate a bug in the code. With a generic numerical accuracy
        test, it will be easier to spot errors (if any) in the code. For
        example, it may be the case that the FCT fails only for certain
        phase functions or numbers of dimensions - it's easier to check
        a large number of cases with this type of test.
     

      - to provide a means of checking changes to the FCT code over time.
        To verify changes, we need to check the results of FCT vs. DCT as
        above, but also have a set of results which we expect the FCT
        code to reproduce exactly. If a bug is introduced between code
        revisions it's likely to be picked up here.
     

    END-TO-END SIMULATION (E2E)
     

    PHYSICS STUDIES
    (Hiro)
    - worked on the in-lock state noise study. A software doing
      whitening and unwhitening has been completed and will be added to e2e
      as a primitive. This primitive generates a psd distribution of a given
      channel. The numerical accuracy issue was revisited. For LIGO I with
      the estimated thermal noise level, the artificial trick to be applied
      is to remove the low frequency seismic noise (flatten the noise spectrum
      below 1 Hz at 10^-9 m/sqrt(Hz)). This needs to be verified, but it is
      most likely that the in-lock state noise in the frequency range of
      interest is not affected by this artificial trick. If we need to
      simulate seismic noise further up, the pendulum and stack resonance at
      around 1 Hz will need to be artificially suppressed.
     

    - Various thermal noises are so far generated using digital filters. For
      each mirror with a set of quantities, like mass, a matlab code needs to
      be used to calculate zeros and poles. These calculations will be put
      into a new primitive so that the intermediate step can be skipped.
     

    (Biplab)
    - Running lock-acquisition codes for various levels of misalignments
      (results are statistics-dependent and so several long runs are needed).
      Working out some math to understand meaning of the limits obtained
      from results of runs.
     

    - Preparing a draft for our work (Brad Zamft, Rick Savage, ...) on
      effects of higher order modes on the frequency sensor noise.
     

    CLIENT-SERVER FRAMEWORK
    (Tavio D'Angelis)
    - I had been working for the most part of last week up until Monday writing
      a client and server program to automatically upload data files, submit a
      job, and then automatically download the files back to an Adlib user
      running a server on a remote location from CACR. This idea is now on hold
      given the present security needs discussed during a visit with a CACR
      representative. At present, either I can (i) Convert my server to work
      with SSL (secure sockets layer), (ii) Explore the automation via script
      files.
    - Ed Maros and I will meet with Bevan Bennet early next week to come up
      with a plan that is acceptable to CACR.
     

    ALFI:
    (Ed Maros)
     - Patched Caltech version of modeler
     - Discussed issues with running modeler at CACR
     

    (Bruce Sears)
     - Finished implementation of primitive parameter file editing via the
       parameter edit dialog.
     - Working on problem where derived nodes may already have connections
       to sink ports which are subsequently connected to in a later base
       node edit session. This needs to be disallowed.
     

    LIGO General Computing

    MIT:
    Nothing to report.

    Livingston:
    - Ordered and received an additional laptop for general
      use at conferences.
    - Working on preparations for the engineering run and
      the LSC meeting here next month.
    - Recovering from a power outage.
     

    Hanford:
    (See Hanford site report)
     

    CIT:
    (Sam)
    - BILL KELL's laptop.  What a pain it is. Some funky netscape error I have
      never seen, would not uninstall, would not install properly. Mail boxes
      would not work. Was a horrible pain.  Hopefully fixed now
    - Dave Beckett's machine was not recognizing its CD ROM. I believe that I
      fixed that problem.
    - Phil Williems off to Scotland. Hopefully with a fully functioning
      laptop. Also with one that be easily recoverable.
    - I did some other stuff, but I am too tired to remember.
     

    (Lisa)
    - Successfully got the ISDN portion of the new modem pool on-line. We now
      have 2 phone lines on ISDN. My initial tests are showing connections
    speeds
      of over 46,000bps. Larry and I still need to test the 800 number on the
      new modem pool before the switch takes place.
    - Troubleshooting display issues with one of our laptops.
    - Working on updating our IP records for the 115 subnet. I'll be finished
      with that today.
    - The usual round of PC issues.
     

    (Barbara)
    - Made changes to the DCC system to support document folders.  A folder
      will be named with the document stem, e.g. G000183-00.  It will contain
      the pdf version of the document as well as any source files such as a
      PowerPoint file and any linked images or videos.  I need to coordinate
      with Linda on installation since some existing files have to be grouped
      into folders and some web pages have to be changed.
    - Began to install the DCC report for Dave Shoemaker.
    - Set up an account on pherkab for Irena Petrac and mapped a drive on her
      PC so she can see the LSC documents database and the Roster.
    - Made some changes to the acknowledgment on the LDAS home page.
    - Got a version of WebBase that runs on Windows ME.
     

    (Suresh)
    - After noticing that machines connected to ports of a Fore 2810 switch in
      third floor west bridge unable to communicate through ATM uplink, it is
      replaced by a backup 3810 switch. The firmware in ATM uplink has been
      upgraded to latest version and kept it for the backup purpose.
    - Worked with Omar and Larry to troubleshoot the ATM switch technical
      glitches and restored back to operation after rebooting it.
    - Restored old files for Hiro from archive and mail Inbox files for Bill
      Kells.
    - Put HP Designjet 650C plotter with the name hpcolor0 on the 115 subnet
      in the Millikan 6th floor conference room.
    - Helped users fixing some account problems.
     

    (Larry)
    - Worked and working a number of procurement issues. Laptops, projectors,
      mounting hardware and a few other items. The UPS battery replacement
      finally arrived. We should make the swap sometime this month.
    - Worked with Linda and others on some of the logistics for the LSC meeting.
    - Fixed and had repaired a couple of the printers. One just had worn out
      parts and the other had some damage done to it from a paper jam. One
      problem was a small piece of paper blocking a sensor, which took a few
      days to discover.
    - Cleaned up a few more accounts and working on getting more home accounts
      moved to a larger disk drive.
    - Assisted a number of people on getting their modem connections going.
    - Helped a few people on getting ssh working along with their outside
      connections. Mostly, getting the users educated on how to connect over
      the network.


    LIGO II/Advanced R&D (Sanders)


    From Peter King:
     

    3.2 Advanced LIGO PSL
    The schedule has been re-worked to largely conform to the structure
    of the WBS. Currently the WBS Dictionary is undergoing a revision.
    The VME backplane for the Eurocard cage being fabricated as part of the
    LZH/University of Hannover collaboration has been ordered.
     

    3.4 LASTI
    CCD cameras have been ordered along with the VME printed circuit
    backplanes.
     

    From Rolf Bork:

    40m and LASTI DAQ:
    Sun stations, reflected memory, ADC modules and VME CPUs have arrived; still
    waiting on disk drives and GPS receiver modules.

    From: Helena Armandula <ahelena@ligo.caltech.edu>
    Silicate Bonding

    Six silicate bonded substrates were tension tested.
    The results, better than the ones obtained before, are being analyzed.

    From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>

    We had no weekly meeting for two weeks, anycase everybody has been in
    the synchrotron.
    The two IP have been tuned, fixing the mechanical snafu of the
    counterweights and the measurement problem by constraining the shaker on
    one degree of freedom. The four filters have been tuned at nominal
    frequencies and attached in the towers, and the top mass of the double
    pendulum have been provided with its MGAS springs and attached to the
    chain.  LVDTs magnetic actuators and motorized screws have been
    installed as well.
    The double pendulum and the control coils will be assembled in Japan.
    After tuning the complete chain, the IP and filters have been hooked to
    their transport latches and one tower has been bolted inside its
    shipping crate and the crate assembled around it.  The second will be
    bolted down on Monday and the shipment will be collected on Wednesday
    morning and fly to Japan on Thursday.
    The linear electronics and cablings are in house, are being tested and
    will be shipped in the same crates.  The digital electronics is expected
    in shortly but will travel separately.
    The test IP continued to work with all LVDTs in loop and all
    accelerometers now working properly after fixing some gain problems.
    Akiteru expects to wrap it up by next week and fly in Japan to receive
    and open the crates.
     

    We found a problem of probably little importance for the present but
    quite important in the future for the noise generation front.  Operating
    the MGASF springs at very low frequencies and small excitation
    amplitudes we observed some histeresis, obviously growing with the
    square of the inverse of the frequency.
    This is not expected to affect the performance of the attenuation but it
    will produce some noise and will not be acceptable in a full scale
    interferometer.
    At higher frequency the effect was not visible and when it was observed
    in an earlier prototype  with bolted blades the effect was attributed to
    the bolting (the effect was strongly dependent on who bolted it down).
    In the final filters with wedged clamps it was not observed for a stupid
    technical reason and was a surprise to find it in the final one.  The
    problem was rapidly traced to the softness of the stainless steel
    clamps.  In future models we should use Maraging  (Or high hardness
    inserts in the clamps) and possibly brazing.  Although not visible at
    frequencies above an hertz, the effect is clamp related and likely
    present in the GEO and Virgo blade clamps, probably even worse because
    in there, there is clamping even at the tip of the blade downstream of
    the attenuation factor.
     

    The test IP continued to work with all LVDTs in loop and all
    accelerometers now working properly after fixing some small range of the
    position sensors problems.
     


    For additional information about this report, contact sanders@ligo.caltech.edu