|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The LIGO Executive Committee Agenda for Monday February 12, 2001 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
Special Items:
no report
WBS 1.2 LIGO Operations--Administration
The next site telecon is scheduled for Thursday,
February 15, 2001. The list of current actions revised to reflect
open actions assigned through February 8, 2001 may be found at
ACTION
LIST.
From: Ed Chargois <chargois_e@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .
ACCOMPLISHMENTS
| Packages | Faxes | |
| In | 46 | 30 |
| Out | 16 | 34 |
Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS PAYABLE HISTORY DATA.
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
From: irena@ligo.caltech.edu (Irena Petrac)
Support (Wood)
On travel this week.
Rita Torres
Out due to illness.
Dorothy Lloyd
Progress Period from 02.02 to 02.08
Accomplishments:
WBS 1.4.1.2 Project Controls (LIGO Construction)
Working on material for the NSF Review scheduled at the end of the month in Hanford.
The following Change Requests have
been submitted:
| CR-000018 | WBS 1.1.4 | Curbing for Service Roads at Livingston | G. Stapfer |
| CR-000019 | WBS 1.2 | Additional Lab Equipment | D. Coyne |
| CR-000020 | WBS 1.1.4 | Staging Building and Renovations to Existing Building--Livigston | F. Asiri |
| CR-010001 | WBS 1.1.4 | Return of Unused Construction Budget To Contingency | F. Asiri |
Press for the latest Contingency Needs Projection.
From: Kris Duncan <kris@ligo.caltech.edu>
The financial reports on the web provide supporting
detail.
http://docuserv.ligo.caltech.edu/~fireport
http://docuserv.ligo.caltech.edu/~finance
From: Ed Jasnow <jasnow@ligo.caltech.edu>
General Items:
--------------
(F. Raab)
4K Installation
---------------
(D. Cook)
The 4K installation is proceeding close to its schedule. A few set backs
as
usual. The MMT3 optic and RM optic are in and aligned. The IOO group
has
started to place their components into HAM1 and aligning the beam from
the
PSL table. BSC3 elevation was set and the ITMx is ready to install.
The CAS
newly installed software seems to have a couple of glitches that caused
a
work around in setting the elevation. We are having to share temporary
controllers and satellite boxes as the permanent ones are not available
as
yet which is not a problem until we start the COS alignment. Some COS
components have also been placed where parallel tasks have allowed.
The BS
coordinates need to be reviewed as we have some conflicting numbers.
LOS
and SOS suspensions are being processed with the new OSEMs and are
keeping
pace with installations. Thanks to a large group
of participants things are
going well.
4k PSL Activities (T. Mahood and M. Guenther):
-------------------------------------------------
Upon completion of the assorted leg vibration investigations, the slightly
wandering
4k optical table has been coaxed back to its rightful position and
leveled.
Following that, the remaining optical and electronic components have
been placed on
the table and are in the process of final alignment. "Test point"
bulkhead connectors
have been installed to allow for sampling of signals from various table
components
when working at the table, without disturbing the sometimes delicate
positioning of
the signal sources.
4k Reference Cavity (M. Guenther):
---------------------------------------
A new ion pump has been installed and activated on the 4k PSL reference
cavity. An
RMA # has been obtained for the failed ion pump, and it will be returned
for repair,
hopefully under warranty. The heater blanket has been installed on
the reference
cavity, we expect the installation of temperature sensors and insulation
to be
complete 2/9.
4k Pre-modecleaner Losses (M. Rakhmanov and R. Savage)
----------------------------------------------------
We have analyzed the 4k PSL PMC losses based on recent measurements.
Assuming all
three mirrors have equal losses, we estimate the losses per mirror
to be about
1340 parts per million. This is costing us about 1.7 W of light. The
output is just
over 6 W with 9 W input and 88% modematching.
Controls
--------
(D. Barker)
Returned 50GB RAID to Cybernetics for repair.
Working on EPICS problems with new Motorola 162-242 CPU boards.
Installed latest EPICS 3.13.3, working with VxWorks on latest BSP and
with EPICS Tech-Talk community for possible solution to this problem
OPTICS : Many observers have noted the asymmetry of the video image seen at the darkport since we first observed interference in the Michelson last December. This week we set forth to ascertain where the (apparent) beam clipping was occurring. An initial attempt to yaw MMT3 while looking at the darkport video camera seemed to improve the image, whilst moving it off the field. Our sense was that the clipping was occurring in the Faraday on Ham 1. Joe Kovalik decided to yaw SM1, and we unambiguously observed the clipping to diminish. We iterated SM1, and the beam alignment on ISCT-1 and 4. We then observed a circularly symmetric image at both the bright and dark ports. It is unfortunate that this clipping was discovered this month, because in moving SM1 we ruined the alignment of the input beam launched from MMT-3. It would have been wise to double check the alignment scheme attempted last year when ISCT-1 was moved into position. In as much as we were forced to perturb the telescope's pointing, we elected to recheck the beam position on the mode-matching telescope's mirrors. A Sony camera positioned above MMT-2 in HAM-2 permitted us to center the beam on MMT-2 by iterating between pointing positions when we saw the beam striking the structure to the left and right, above and below the optic. Last fall, we were unable to perform a similar test at MMT-3 because of the insensitivity of the Sony cameras, but now we have available a Watec camera and find that it has ample sensitivity to image the ~4" diameter beam at MMT-3. Not surprisingly, we found the beam to be well above center, by an amount that appears consistent with what we observed during those times when we had the X-arm locked last week. We centered the beam on MMT-3. We have spent several days this week reestablishing the mode matching telescope, as well as mode cleaner alignment. We are close to completing this task, but a catastrophic power outage this morning has hindered our work. (Kovalik/Giaime/Traylor/Kern)
OTHER: LLO experienced a major power disruption Thursday morning. This was a general outage that affected the surrounding region as least as far away as Denham Springs, the major population center 15 miles east. All systems were recovered by mid afternoon.
Augering and excavation for the staging building addition is now underway, creating a noisy seismic environment during the day which often makes it difficult to carry out commissioning work. We have begun to staff the control room on a regular basis on Saturdays to take advantage of the "quiet time" when there is no construction work on site.
Outreach: Students from two Livingston Parish Jr. High Schools
(Plaquemine High School and Frost High School) spent a day at LIGO in the
Job Shadow Program working with Bonnie and others in the Control Room and
in the Front Office. Job Shadow is a program in the public school system
in Louisiana to help students gain knowledge and
awareness about the working world and various careers.
| Installation&
Commissioning:
Livingston |
Other Science/EngineeringActivities:
Issues/Concerns |
Seealso the Installation web page
Before starting the work on the modecleaner servo, we were able to take a calibrated noise spectrum with the whitening filters engaged on the antisymmetric port photodiode. The calibrated error signal and control signal for the arm length difference is shown in a spectrum in the elog. Because of the servo, the correct estimator of the noise is to lake the higher of the green and blue curves at any given frequecy. The dark noise in the photodetector/electronics is shown in the red curve. The bect sensitivity (2 x 10e-16 m/rtHz) is a significant improvement over what we had in the E2 run last November. The dominant noise below about 400 Hz is frequency noise (though as far as we can tell there is something else lurking just below the frequency noise), and should be helped by the servo change to the modecleaner described above.
The safety shutter for the PSL to vaccum chamber connection had fit problems and is being reworked. Small optic suspension have been prepared for installation and the first one may be going in at this very moment.
So far we are almost exactly on schedule.
The most time consuming effort (still on going) is the realignment of the mode matching telescope and the mode cleaner to avoid the clipping of the beam at the symmetric and antisymmetric ports while still maintaining the alignment of the arm cavities.
To increase the dynamic range of the lock using the ITMX, the coil driver has been modified as it was at Hanford.
The optical lever damping servo for ETMX is currently being set up and an attempt is being made to install and use the Matt Evans acquisition code for the x arm locking.
The vibrations associated with construction of the new building at the site prohibit cavity locking during the day and most of the locking and diagnostic work is taking place at night.
Light is bounced back toward the recycling cavity because of the mismatch in the former case (so that more power exits from the asymmetric port or outside the recycling mirror) while the losses are so high in the latter case that inside all cavities (since they are coupled) the energy storage performance is corrupted though there is a sort of addition of these two effects so that in the recycling cavity the gain is less reduced than in the long arm cavity.
In order to link such results to a mathematical prediction I wrote a
small Fortran code that evaluates the scalar product of the field maps
inside the cavity after normalizing them. As it could be expected the squared
value roughly coincides with how much gain survives if one mirror is tilted.
Example for reshaped mirrors:
|<u_tilt|u_notilt>|^2=1-0.00315
Gain_tilt/Gain_notilt=1-0.00345
Example for spherical mirrors:
|<psi_tilt|psi_notilt>|^2=1-1e-5
Gain_tilt/Gain_notilt=1-5.5e-6
Rolf Bork
Request from Rai and also LHO to add optical lever servos for end station
test masses. It is requested to be installed at LLO by this weekend,
so this is my focus for the next day or two.
Report out of LHO that they are seeing 16Hz components on the ASC DAC outputs. I still need to get more info on this before starting to track it down.
We are now building 16 new RFPD's for use at various frequencies.
Rick Karwoski, Paul Russell,Ben Abbott
Custom Card Situation:
Jay Heefner
Hongyu is modifying dataviewer to create data groups by signal names, rather than using the group IDs given in the DAQ master configuration table.
Last week was spent ugrading the DTT at LLO and installing the reduced data set writer on decatur.
To provide a temporary remedy for this problem, I have written and debugged a new data accesser (Dacc) class. The new Dacc classe uses the DaqReader and DaqFrame classes in FrameCPP which read a single frame as a template and then quickly updates specified fields from subsequent files. With this new readout class the CPU usage of a typical monitor drops from >90% to about 15%!
This temporary solution has several properties that make it undesirable as a final solution (a) these classes do not support multi-frame files, (b) there is no way to verify that a given channel was actually updated, and (c) the classes will not work with compressed data.
Because of these faults, the faster access class can not be used offline. I have therefore added a new library directory which will be linked to by online programs only. The online library is now being used by most monitors and I am recompiling others as the sources become available. Clearly, this solution will have to be replaced in the near future with one that is appropriate for both online and offline purposes.
no report received
We have re-locked one suspended arm cavity, and are testing various
servo
configurations. We are measuring transfer functions for the components
and
are building a detailed Simulink model of the servo. Part of
this effort
is aimed at eliminating a strong resonance at 21.5 Hz, which we suspect
is
caused by a poor crossover.
The seismic isolation system appears to have a slow drift (over several
weeks), but fortunately the suspension controllers have enough dynamic
range to compensate for the misalignment this causes. We have
improved the
cavity throughput over our last lock by fine-tuning the alignment and
the
servo parameters.
We have also begun construction of isolation transformers for reducing
ground-line noise.
no report received
LIGO DATA ANALYSIS (LDAS)
LDAS SOFTWARE SYSTEM
(Kent Blackburn)
- The focus this week has been to generate a new release of LDAS which
has full support for the MPI MDC as well as a working version
of the
dataConditionAPI with close to the full set of functions that
were in
place during the dataConditionAPI MDC. All of this is to be
a precursor
to another release of LDAS at the end of the month in support
of the
next engineering run (E3). New in the release will be a fully
functional
controlMonitorAPI and a greatly expanded frameAPI and frameCPP
which are
will now be used to generate LIGO frames with "Table of Contents"
which
can be used to in analysis software to improve data I/O speeds.
- The baseline requirements for the eventMonitorAPI have now been formally
documented and included in the LIGO DCC. The LDAS software team
will
begin development of this API with a target delivery of the
first half
of March.
- The dataConditionAPI has really been on a roller-coaster ride for
the
past week with our development team working around the world
(and around
the clock) to recapture the original functionality based on
the new
Universal Data Type (UDT). The only remaining actions are linear
filtering and resampling and these should be ready in one more
of these
"follow the setting Sun" work days. One other area of intense
activity
associated with the dataConditionAPI has be a set of enhancements
and
modifications to the MDC test scripts to support running of
the tests
on systems other than the LDAS-Development system. In addition
some of
the additional ingestion processing associated with the new
UDT have
added a set of new dataset naming conventions which had to be
touched
up to successfully run these scripts. These have been completed
now and
all that remains is to run the test scripts once the dataConditionAPI
is conpleted.
- New instructions are being added to the LDAS webpages specific to
the
building and installation of the frameCPP library and the
controlMonitorAPI
client. Separate tarballs will also be generated for these allowing
for
users of these sub-packages of LDAS to limit their downloads.
- There have been several problems identified with LDAS user command,
especially with the returnprotocol options. These are being
fixed in
time for the new release. But the fixes will require some modifications
to GUILD (the Graphical User Interface to the LIGO Database),
which
will also be added and tested for this next release.
- Only minor changes have been made in the wrapperAPI this week. Mostly
to support the full description of event data to be generated
by the
underlying search algorithms prior to distribution to the soon
to be
developed eventMonitorAPI.
- Several C++ issues associated with dynamic memory allocation were
identified in the ILWD code and code that is based or used the
ILWD.
The ILWD issues have now been fixed and all codes using this
new code
in each API have been brought in line with the correct usage.
LDAS HARDWARE SYSTEM
(Stuart Anderson)
- Linux (RedHat 7.1beta) has been successfully installed on the new
LDAS
Beowulf
test nodes (Intel P4 and AMD K7).
- The last 30x4GB of old disk drives reclaimed from the old CACR Paragon
parallel computer by LDAS have now been decomissioned by LDAS
to be
further recycled to hold radio pulsar data.
- The LDAS Cybernetics AIT-2 robot at LHO has been shipped back to the
vendor to
work on an intermittent problem before the upcoming E3 run.
- Solaris UFS logging has been enabled on all of the LDAS Sun computers
at
LLO,
which completes this upgrade for all LDAS Sun computers.
- Sun has identified the solution for an intermittent E450 reboot problem.
A different graphics driver (TSIpgx) is being installed on all
the
effected
machines which where running a less reliable driver (TSIgfx).
This is
fully
expected to fix the problem and allow for reliable rebooting
of these
machines.
- Solaris 8 maintenance update 3 is being applied to all LDAS Sun computers
to allow investigation of the new "snapshot" functionality in
the UFS
filesystem, i.e., this should finally make it reliable to backup
active
Solaris
UFS filesystems. Furthermore, if it works as well as the canonical
Network
Appliance filesystem this may also allow the backing up of active
LDAS
database
systems and thereby increase the availability of LDAS.
- Larry Wallace will be managing the LDAS system at LLO during the E3
run.
- The large HP plotter (hpcolor0) is now working on the 6th floor of
Millikan
at Caltech.
FAST CHIRP TRANSFORM (FCT)
(Philip Charlton)
- worked on code to test the numerical accuracy of Rick Jenet's FCT
implementation (which uses approximations) compared to the slow,
exact
discrete chirp transform. The issues here are:
- to verify that the approximate FCT implementation is accurate
to
within the analytically determined error bounds.
A failure here
may indicate a bug in the code. With a generic numerical
accuracy
test, it will be easier to spot errors (if any)
in the code. For
example, it may be the case that the FCT fails only
for certain
phase functions or numbers of dimensions - it's
easier to check
a large number of cases with this type of test.
- to provide a means of checking changes to the FCT code over
time.
To verify changes, we need to check the results
of FCT vs. DCT as
above, but also have a set of results which we expect
the FCT
code to reproduce exactly. If a bug is introduced
between code
revisions it's likely to be picked up here.
END-TO-END SIMULATION (E2E)
PHYSICS STUDIES
(Hiro)
- worked on the in-lock state noise study. A software doing
whitening and unwhitening has been completed and will be added
to e2e
as a primitive. This primitive generates a psd distribution
of a given
channel. The numerical accuracy issue was revisited. For LIGO
I with
the estimated thermal noise level, the artificial trick to be
applied
is to remove the low frequency seismic noise (flatten the noise
spectrum
below 1 Hz at 10^-9 m/sqrt(Hz)). This needs to be verified,
but it is
most likely that the in-lock state noise in the frequency range
of
interest is not affected by this artificial trick. If we need
to
simulate seismic noise further up, the pendulum and stack resonance
at
around 1 Hz will need to be artificially suppressed.
- Various thermal noises are so far generated using digital filters.
For
each mirror with a set of quantities, like mass, a matlab code
needs to
be used to calculate zeros and poles. These calculations will
be put
into a new primitive so that the intermediate step can be skipped.
(Biplab)
- Running lock-acquisition codes for various levels of misalignments
(results are statistics-dependent and so several long runs are
needed).
Working out some math to understand meaning of the limits obtained
from results of runs.
- Preparing a draft for our work (Brad Zamft, Rick Savage, ...) on
effects of higher order modes on the frequency sensor noise.
CLIENT-SERVER FRAMEWORK
(Tavio D'Angelis)
- I had been working for the most part of last week up until Monday
writing
a client and server program to automatically upload data files,
submit a
job, and then automatically download the files back to an Adlib
user
running a server on a remote location from CACR. This idea is
now on hold
given the present security needs discussed during a visit with
a CACR
representative. At present, either I can (i) Convert my server
to work
with SSL (secure sockets layer), (ii) Explore the automation
via script
files.
- Ed Maros and I will meet with Bevan Bennet early next week to come
up
with a plan that is acceptable to CACR.
ALFI:
(Ed Maros)
- Patched Caltech version of modeler
- Discussed issues with running modeler at CACR
(Bruce Sears)
- Finished implementation of primitive parameter file editing
via the
parameter edit dialog.
- Working on problem where derived nodes may already have connections
to sink ports which are subsequently connected to in a
later base
node edit session. This needs to be disallowed.
LIGO General Computing
MIT:
Nothing to report.
Livingston:
- Ordered and received an additional laptop for general
use at conferences.
- Working on preparations for the engineering run and
the LSC meeting here next month.
- Recovering from a power outage.
Hanford:
(See Hanford site report)
CIT:
(Sam)
- BILL KELL's laptop. What a pain it is. Some funky netscape
error I have
never seen, would not uninstall, would not install properly.
Mail boxes
would not work. Was a horrible pain. Hopefully fixed now
- Dave Beckett's machine was not recognizing its CD ROM. I believe
that I
fixed that problem.
- Phil Williems off to Scotland. Hopefully with a fully functioning
laptop. Also with one that be easily recoverable.
- I did some other stuff, but I am too tired to remember.
(Lisa)
- Successfully got the ISDN portion of the new modem pool on-line.
We now
have 2 phone lines on ISDN. My initial tests are showing connections
speeds
of over 46,000bps. Larry and I still need to test the 800 number
on the
new modem pool before the switch takes place.
- Troubleshooting display issues with one of our laptops.
- Working on updating our IP records for the 115 subnet. I'll be finished
with that today.
- The usual round of PC issues.
(Barbara)
- Made changes to the DCC system to support document folders.
A folder
will be named with the document stem, e.g. G000183-00.
It will contain
the pdf version of the document as well as any source files
such as a
PowerPoint file and any linked images or videos. I need
to coordinate
with Linda on installation since some existing files have to
be grouped
into folders and some web pages have to be changed.
- Began to install the DCC report for Dave Shoemaker.
- Set up an account on pherkab for Irena Petrac and mapped a drive
on her
PC so she can see the LSC documents database and the Roster.
- Made some changes to the acknowledgment on the LDAS home page.
- Got a version of WebBase that runs on Windows ME.
(Suresh)
- After noticing that machines connected to ports of a Fore 2810 switch
in
third floor west bridge unable to communicate through ATM uplink,
it is
replaced by a backup 3810 switch. The firmware in ATM uplink
has been
upgraded to latest version and kept it for the backup purpose.
- Worked with Omar and Larry to troubleshoot the ATM switch technical
glitches and restored back to operation after rebooting it.
- Restored old files for Hiro from archive and mail Inbox files for
Bill
Kells.
- Put HP Designjet 650C plotter with the name hpcolor0 on the 115 subnet
in the Millikan 6th floor conference room.
- Helped users fixing some account problems.
(Larry)
- Worked and working a number of procurement issues. Laptops, projectors,
mounting hardware and a few other items. The UPS battery replacement
finally arrived. We should make the swap sometime this month.
- Worked with Linda and others on some of the logistics for the LSC
meeting.
- Fixed and had repaired a couple of the printers. One just had worn
out
parts and the other had some damage done to it from a paper
jam. One
problem was a small piece of paper blocking a sensor, which
took a few
days to discover.
- Cleaned up a few more accounts and working on getting more home accounts
moved to a larger disk drive.
- Assisted a number of people on getting their modem connections going.
- Helped a few people on getting ssh working along with their outside
connections. Mostly, getting the users educated on how to connect
over
the network.
From Peter King:
3.2 Advanced LIGO PSL
The schedule has been re-worked to largely conform to the structure
of the WBS. Currently the WBS Dictionary is undergoing a revision.
The VME backplane for the Eurocard cage being fabricated as part of
the
LZH/University of Hannover collaboration has been ordered.
3.4 LASTI
CCD cameras have been ordered along with the VME printed circuit
backplanes.
From Rolf Bork:
40m and LASTI DAQ:
Sun stations, reflected memory, ADC modules and VME CPUs have arrived;
still
waiting on disk drives and GPS receiver modules.
From: Helena Armandula <ahelena@ligo.caltech.edu>
Silicate Bonding
Six silicate bonded substrates were tension tested.
The results, better than the ones obtained before, are being analyzed.
From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>
We had no weekly meeting for two weeks, anycase everybody has been in
the synchrotron.
The two IP have been tuned, fixing the mechanical snafu of the
counterweights and the measurement problem by constraining the shaker
on
one degree of freedom. The four filters have been tuned at nominal
frequencies and attached in the towers, and the top mass of the double
pendulum have been provided with its MGAS springs and attached to the
chain. LVDTs magnetic actuators and motorized screws have been
installed as well.
The double pendulum and the control coils will be assembled in Japan.
After tuning the complete chain, the IP and filters have been hooked
to
their transport latches and one tower has been bolted inside its
shipping crate and the crate assembled around it. The second
will be
bolted down on Monday and the shipment will be collected on Wednesday
morning and fly to Japan on Thursday.
The linear electronics and cablings are in house, are being tested
and
will be shipped in the same crates. The digital electronics is
expected
in shortly but will travel separately.
The test IP continued to work with all LVDTs in loop and all
accelerometers now working properly after fixing some gain problems.
Akiteru expects to wrap it up by next week and fly in Japan to receive
and open the crates.
We found a problem of probably little importance for the present but
quite important in the future for the noise generation front.
Operating
the MGASF springs at very low frequencies and small excitation
amplitudes we observed some histeresis, obviously growing with the
square of the inverse of the frequency.
This is not expected to affect the performance of the attenuation but
it
will produce some noise and will not be acceptable in a full scale
interferometer.
At higher frequency the effect was not visible and when it was observed
in an earlier prototype with bolted blades the effect was attributed
to
the bolting (the effect was strongly dependent on who bolted it down).
In the final filters with wedged clamps it was not observed for a stupid
technical reason and was a surprise to find it in the final one.
The
problem was rapidly traced to the softness of the stainless steel
clamps. In future models we should use Maraging (Or high
hardness
inserts in the clamps) and possibly brazing. Although not visible
at
frequencies above an hertz, the effect is clamp related and likely
present in the GEO and Virgo blade clamps, probably even worse because
in there, there is clamping even at the tip of the blade downstream
of
the attenuation factor.
The test IP continued to work with all LVDTs in loop and all
accelerometers now working properly after fixing some small range of
the
position sensors problems.
For additional information about this report, contact sanders@ligo.caltech.edu