Weekly Report for Week Ending February
1, 2001
The LIGO Executive Committee
Agenda for Monday February 5, 2001 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
-
Announcements
-
LSC Issues (Weiss)
-
Comments on Weekly Report
-
WBS 1 LIGO I Construction (Lindquist)
-
Field Change Orders/Contingency Liens/Change Requests
-
WBS 2 LIGO Lab Operations
-
Administration (Lindquist)
-
Sites (Raab, Coles, Shoemaker, Sanders)
-
Detector (Whitcomb, Coyne)
-
Campus Research Facilities (Weinstein (40 Meter), Libbrecht (TNI), Zucker(LASTI))
-
Data Analysis and Computing (Lazzarini)
-
WBS 3 and 4 Advanced R&D and LIGO II
(Sanders)
Executive Committee only 11:30 - noon
Topics: NSF review reprise
Special Items:
Special Announcements:
The LIGO Newsletter for January 2001 is now
posted!
Read it here:
http://www.ligo.caltech.edu/LIGO_web/0101news/0101main.html
Weekly
Report Highlights
LLO Fabry-Perot cavity locking
studies along the X-arm
A 'first look' displacement sensitivity spectrum
was taken for the LHO 2k power recycled interferometer with recycling gain
of 11
LSC Issues (Weiss)
No report this week.
LIGO I Construction/LIGO Laboratory
Administration (Lindquist)
NSF Review
A NSF Review Committee (Detector Research and Development
Subpanel) conducted a review of the Advanced R&D program proposed for
FY 2002-2006. This review was conducted at Caltech January 29,2000
through February 1, 2000.
The review panel provided a briefing on February 1, 2000.
The review panel indicated that the proposal for research
and development on an advanced LIGO detector contains a set of significant
technical challenges that, if met, will provide a design for an advanced
gravitational-wave detector and deemed the proposed balance between operation
of initial LIGO and R&D on advanced LIGO, as described during the review,
appropriate.
[GHS note: The review
was a great success! While we have been advancing in detector commissioning
and in preparations for data analysis and modeling, the review recognized
the third leg in the stool; a very powerful R&D program for advanced
LIGO that is in place as a strong collaborative effort with the LSC and
that has grown to a full 1/3 of all of the Laboratory's efforts. Everyone
is to be thanked and congratulated for their efforts in this program and
for the thorough preparation and expert responses to the review panel's
questions.]
WBS 1.2 LIGO Operations--Administration
LIGO Weekly Site Telecon (Lindquist)
There was no site teleconference held on Thursday,
February 1, 2001.
The next site telecon is scheduled for Thursday,
February 8, 2001. The list of current actions revised to reflect
open actions assigned through January 25, 2001 may be found at
ACTION
LIST.
PROPERTY
MANAGEMENT (Chargois)
From: Ed Chargois <chargois_e@ligo.caltech.edu>
-
No report (at Livingston).
DOCUMENT
CONTROL CENTER (Turner, Mak)
>From: Linda Turner
- turner@ligo.caltech.edu>
Web pages for the
DCC give simple how-to's for document numbering, easy access to the latest
on-line documents, and search capabilities for the DCC database. Take
a look. . .
ACCOMPLISHMENTS
-
During the past month a total of 91 new documents
were made available on-line. An additional 238 documents were processed
and added to the database. Packages received or sent out totalled
274, and there were 158 faxes received and another 204 sent out.
-
Met with Paul Russell and Rick Karwoski to
review documentation procedures for a drawing release. The use of
an ECO and its relationship with a DCN were discussed. They will
also be adding a revision history block to their drawing format.
-
Made several layout designs for a LIGO award/service
plaque. A final rendition was chosen by Barry and will be taken to
a vendor for framing.
-
Met with Phil and Barbara to decide the benefits
of either of them attending the AIIM conference with me in April.
Both will review the agenda of the sessions and seminars to decide on their
attendance and plan of action for making the most of the opportunity.
-
Began the process of outlining a system requirements
document for the DCC. A mission statement for the DCC and initial
questions/considerations will be garnered and passed along for additions
by Phil and Barbara. Once amended, the document will be distributed
to a few for additional comments or changes. The goal is to have
a completed version by end of March in preparation for my attendance at
the AIIM conference at the end of April.
-
Processed and distributed 1 DCN.
From: Cleveland Mak
<mak_c@ligo.caltech.edu>
-
continued auditing Hanford Construction drawings.
-
electronic document submittals were fairly light this reporting period.
|
Packages |
Faxes |
| In |
38 |
45 |
| Out |
9 |
50 |
Press here to access
the DOCUMENT CONTROL CENTER
WEB PAGE.
COST SCHEDULE
CONTROL SYSTEMS (Cunningham, Brambila, Akutagawa, Kaufman)
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS
PAYABLE HISTORY DATA.
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
-
Working on MIT, Heritiage Landscape, Sydney Meshkov, and John Desmond.
-
Working with Cindy and Dorothy to close out PO's and remove encumbrances
on various poetas.
-
BOC Gases for the LLO will not be extended beyond May 31, 2001. It
will go out for RFP. (See below.)
-
Have obtained one quote for the generator for LLO. We will be receiving
a maintenace quote soon along with the quote from the competing supplier.
From: Florence Kaufman <fkaufman@ligo.caltech.edu>
SUBCONTRACTS MANAGEMENT (Petrac,
Jasnow)
From: irena@ligo.caltech.edu (Irena Petrac)
-
TAMA SAS: An order for two Mirror Isolation Systems,
for SAS technology demonstration/verification on TAMA 3 Meter Interferometer,
was definitized. A grant, to receive NAOJ's cost share for SAS R&D,
is being set up.
-
LaTech: CO No.3, extending the performance period
through Nov. 30, 01, was released to CIT Purchasing.
-
MIT: CO No. 11, extending the period of performance
through Nov. 30 , 01 and re-allocating residual FY'00 funds to LIGO FY'01
accounts, was released to CIT Purchasing.
From: Ed Jasnow <jasnow@ligo.caltech.edu>
-
The contract with Heritage Landscaping is being renewed for one year to
perform landscape maintenance service at Hanford.
-
The option with BOC Gases to provide liquid nitrogen for Livingston is
not being exercised due to poor service from the company. An RFP
is being prepared to find a new vendor for this item.
Support (Wood)
Rita Torres
-
Helped with change order No. 11 to MIT, and also with forms to accompany
proposal to TAMA. Formatted letter to NSF Re: Request for Approval
of Procurement of Phase I of LDAS. Did some printing during NSF preparations.
-
Spent lots of time this week chasing after invoices and such to address
Pcard purchases needing to be reconciled, also placed more orders.
Distributed LIGO Laser Safety Plan to participants at the recent safety
training.
-
Ongoing activity: Preparing labels to organize drawings and such in the
BD lab. Update site trips.
Dorothy Lloyd
Graphic provided by C. Akutagawa.
-
Processed the usual requisitions, invoices and receiving on-line. For more
detail, see "Cost Schedule Control Systems" report by Esther Cunningham.
-
Tracked and followed up on invoice problems.
-
Reviewed and recorded payments processed by Esther for the week of January
22, on contract summary sheets and LIGO database.
-
On the "Receiving" end, continued to work with Florence and Ruth on transferring
encumbrances to new fiscal period.
-
Continue to monitor contract and blanket order funding levels and n notify
task managers when supplements are needed.
-
Began updating PO Log books for the period September 15 through January
15 (253 entries).
-
Jim continues to do data entry in the LIGO database and help out in both
the DCC and travel areas.
Irene Baldon
-
Nine (9) new trips were started and I have eight (8) trips pending final
approval before tickets can be issued. Most of these trips required
Advance Checks to be written as well as hotel and car authorization forms
to be filled out and FAXed to the appropriate locations.
-
Worked on and completed eleven (11) Expense Reports. I have seven
(7) Expense Reports to work on and I'm holding one (1) report which need
a check from the traveler before processing. Jim Covington completed
twelve (12) expense reports and has six (6) that he is working on.
I continue to train and supervise him on expense reports.
-
Reconciled sixteen (16) items on my P-Card this week and have an additional
39 items to do.
-
Traveled to Hanford with Florence Kaufman and Criselda Rodriguez-Brodeur
to work with site personnel on various P-Card, account and travel issues.
In addition to the site visit, Criselda and I are working with Jim Carroll
of CCSi in regard to enhancement of the P-Card for travel. The enhancement
is proceeding, and we should have more information after he comes down
on the 13th.
-
Prepared the Travel/Vacation Itinerary for the Week of January 26, 2001.
Performed normal recording and filing associated with Travel and Reimbursement.
Worked on several problem issues with Travel Audit in addition to the above
listed issues. Also performed miscellaneous duties as requested by
various members of the LIGO Project here at Caltech as well as from members
of the staffs of each of the two (2) sites. I continue to do
MIT's travel to the sites for installation activities and also to assist
them wherever possible.
Elizabeth K. Wood
-
Oversaw the care and feeding of the NSF Review Committee during their visit.
Thanks to Peter King for providing an industrial size power strip, Lisa
and Larry for providing computer support, and Linda for helping with mopping
up.
-
Attended a meeting with Ed Jasnow and Donna to meet the new immigration
specialist. HR is still looking for a director of immigration, but
they currently have an “acting” director in the interim. The immigration
office has moved in with HR over on Holliston Street and instead of being
in Parsons-Gates in the provost's office will now be under the umbrella
of our crack HR department.
Advanced LIGO (Frey, Petrac)
From: Thomas Frey <tfrey@ligo.caltech.edu>
Progress Period from 01.26 to 02.01
Accomplishments:
-
LIGO Project Controls meeting not held this week due to NSF review.
-
Attended NSF opening and closing meetings.
-
Prepared budget data report as requested by Phil Lindquist.
-
Proposal plan development for Advanced LIGO MRE continues.
-
Issued data requests for progress data as of 02.02.01 that are due Friday.
-
Progress as of 01.26.01 was processed and posted.
-
Review of cost and schedule data is Continuing.
-
Continue to integrate the AOS schedule into Primavera and the Cost Book
Tool.
-
Started to integrate the COC schedule into Primavera and the Cost Book
Tool.
-
Did not received any data from Dave Reitze or Peter King.
-
Initiated the development of the TNI work plan and schedule per Gary Sanders.
-
Eric Black has acquired MS Project and will install after Aspen.
-
Project Plan for the 40-Meter Lab Upgrade continues.
-
Issued data requests for progress data as of 02.02.01 that are due Friday.
-
Progress as of 01.26.01 was processed and posted.
-
Waiting for comments from Alan Weinstein regarding the changes he said
he wants to make to the WBS.
-
Planning process for the LASTI project at MIT is in progress.
-
Issued data requests for progress data as of 02.02.01 that are due Friday.
-
Progress as of 01.26.01 was processed and posted.
-
Changes are pending from David per his discussions with GEO regarding the
acceleration of prototype noise testing.
-
Continue to test the Cost Book Tool.
-
Continue mapping and formatting of OPs cost data for input.
-
Preparing data representing the most recent changes.
-
Development of the Advanced LIGO Project Controls Guidebook continues.
-
Project Web Site for posting schedule and progress related data continues
to be updated with the latest and greatest.
Schedule 02.02 to 02.08:
-
Next weekly meeting will be Monday afternoon February 12th from 1 to 2pm
regarding the planning and control of the Advanced LIGO MRE proposal development.
-
Will prepare budget presentation data as needed for NSF review at the end
of February.
-
Advanced LIGO Proposal
-
All effort on hold pending internal review.
-
Will Continue to develop the TNI Schedule.
-
Meeting scheduled with Eric Black on February 12th at 9am.
-
Will Continue to update the LASTI Schedule with progress.
-
All effort on hold pending internal review.
-
Will continue updating the 40 meter schedule and incorporate any changes.
-
All effort on hold pending internal review.
-
Continue to test the Cost Book Tool.
-
Cost Book Tool development continues.
-
All effort on hold pending internal review.
-
Will continue the development of the Advanced LIGO Project Web Site.
-
Will continue the development of the Advanced LIGO Project Controls Guide
Book.
WBS 1.4.1.2 Project Controls (LIGO Construction)
Reports (Lindquist)
Nothing to Report.
Change Control/Contingency (Lindquist)
The following Change Requests have
been submitted:
| CR-000018 |
WBS 1.1.4 |
Curbing for Service Roads at Livingston |
G. Stapfer |
| CR-000019 |
WBS 1.2 |
Additional Lab Equipment |
D. Coyne |
| CR-000020 |
WBS 1.1.4 |
Staging Building and Renovations to Existing Building--Livigston |
F. Asiri |
| CR-010001 |
WBS 1.1.4 |
Return of Unused Construction Budget To Contingency |
F. Asiri |
Press for the latest Contingency
Needs Projection.
COST SCHEDULE CONTROL SYSTEMS (Duncan,
Akutagawa)
From: Kris Duncan <kris@ligo.caltech.edu>
-
Continued with the December 2000 CSSR and related
materials.
-
Continued with construction contract/work package
close out.
-
Continued work on transferring the COBRA files into
Excel format.
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
-
I received the MIT invoice and TWONK (MIT cost allocation)
report for the month of December, and I compiled the data for payment using
the new account numbers. I am waiting for the change order to add
the money to these accounts to be completed so I can submit the invoice
for payment.
-
I continue to review the open encumbrances on the
Construction and Advanced R&D accounts to see if the requested removals
have been made. I will continue to review these accounts weekly until all
encumbrances have been removed (Remember, I can only get these errors corrected
if the Task Managers point them out to me).
The financial reports on the web provide supporting
detail.
http://docuserv.ligo.caltech.edu/~fireport
http://docuserv.ligo.caltech.edu/~finance
SUBCONTRACTS MANAGEMENT (Petrac,
Jasnow)
From: Ed Jasnow <jasnow@ligo.caltech.edu>
-
The review committee for the A/E contract for the Hanford Support Building
has completed its evaluation of the three competing companies, and is recommending
a selection. The committee's report will be presented to Barry Barish
and Gary Sanders next week. Upon their approval, the recommendation
will be forwarded to the NSF for their approval.
-
The package containing information on the procurement of Phase I of LDAS
has been sent to the NSF for their approval. A presentation to them
on this package has been tentatively set for the week of February 12.
-
The first concrete has been poured this week for the Livingston Staging
Building. The contractor continues to be slightly ahead of
schedule.
From: irena@ligo.caltech.edu (Irena Petrac)
-
No report this week; see Operations Section above.
LIGO Hanford Observatory (LHO) Operations
(Raab)
General Items:
--------------
(F. Raab)
After finishing up ETMx, installation has moved to the corner station.
The
Controls and Computing reports (prepared last week but not submitted
due to
my error) are also reprinted.
Controls
--------
(D. Barker)
Built the EPICS controls for the LSC high gain switching system for
QPD
Sum signals.
Begin the installation of the latest version of EPICS, 3.13.3.
Worked VME problem with ASC front end FM optlev pentek card.
Put together test stands for baja and pentium code dev.
Computing
---------
(C. Patton)
A read only copy of the LHO elogs is now available
at
http://apex.ligo-wa.caltech.edu/ilog/.
Everyone uses the username
"reader" and password "readonly". Thanks
to Bruce Sears for setting
this up. The elog files are being copied
from the CDS network to apex
daily.
Last week I attended an Advanced PC Maintenance course. I learned
a few
good things about BIOS settings, using the Windows registry, optimizing
memory and CPU, and security features in Windows 98.
Input Optics (4 K installation)
--------------------------------
(Betsy Weaver, Corey Gray and David Ottaway)
The new OSEMs have been fitted to the MC2 and
SM1. It was noticed that
these OSEMs change the balance angle by up to
3 mRad. The direction
change is always front face (HR Surface) tilts
downwards. This effect
has been traced to the face magnets attracting
towards the ferromagnetic
components in the new OSEMS. In consultation
with Stan W and Peter F it
has been decided to proceed with the installation
as is and correct for
this problem using higher range current drivers.
Core Optics (4 K installation)
------------------------------
(D. Cook)
The LHO 4K installation has moved to the corner station. The MMT3 is
on
the optics table, but the final position has not been finished as we
need
to reverify the location dimensions. The HAM 1,2,3 and BSC2&34
tables have
had their elevations set and leveled. SUS temporary controllers and
the new
satellite boxes installed and tested. The optical levers are getting
close
to their final setups. The RM is being fitted with its new OSEMS and
will
be next in line for installation the first part of next week. We have
a ton
of COS hardware stage and ready to follow on after the IAS finishes
up.
Even with a couple a minor setbacks we are holding to our original
schedule
thanks to a big team
effort. (SKI,Gerardo,Hugh,Corey,Dave,Betsy,Rick,Richard,
Josh, The PSL group
and others, Did I mention MOM in there?)
LIGO Livingston Observatory (LLO) Operations
(Coles)
This week we began Fabry-Perot
cavity locking studies along the X-arm. We have been able to achieve locked
sections that are as long as several minutes and in one case nearly ten
minutes long. We have been able to make spectral measurements and are now
busy discovering problems with the installed system and are fixing them
incrementally. For example, there is an obvious pitch motion of ITM-x that
we are now trying to understand. The residual water content in the vacuum
in the corner station is very low, so wetting the beam tube has not been
a major concern. Only about 1 torr-liter of water load has been added to
the beam tube during each of the roughly 12 hour periods the X-arm gate
valve has been open for locking studies. A general concern is that the
seismic environment here is higher at low frequencies (around 1-3 Hz) than
that encountered at Hanford, and construction of the staging building modification
is now underway, generating additional noise - so our attempts at locking
have been at night.
General Computing: Exabyte tape library has been removed from
decatur and will be installed on aubry (future email server). AIT2 tape
library has been installed on decatur. It has been tested and is up and
functional. We have been investigating different models of Cisco PIX Firewalls.
LDAS:The AIT2 tape library has been installed and configured
on Beowulf. Gregg Mendell is running some scripts on it to run it through
its paces.
CDS :We have installed ghostscript on one of the CDS machines
and will install it on the server shortly. (Shannon Roddy)
Other: We are in the process of working on several loads for
the 40M in Pasadena. However, we are currently having a problem with either
a leak or vacuum instrumentation, or with both, and are trying to resolve
that before heating the oven. (Tom Evans)
Rough grading for the annex to the staging building began this week.
Excavation of the footings for the interior supports is nearly complete.
Augering for the vertical steel columns will be done next week.
Detector/Technical Support (Whitcomb,
Coyne)
1.1 LHO INSTALLATION & COMMISSIONING
2km Commissioning
Dennis Coyne
A 'first look' displacement
sensitivity spectrum was taken for the power recycled interferometer
with recycling gain of 11. There is some significant uncertainties about
the calibration (see the log entry for details), but it is interesting
nonetheless. Most of the past few days have been taken up with aligning
the 2 km interferometer, trying to get back to a good locking state so
that WFS can be tested and brought on-line. By examining the beam spot
locations on the ITMs and ETMs, we conclude that the beam is low in the
recycling cavity, though still roughly parallel to the plane of the interferometer;
The beam will be walked up through the MMT this weekend.
The AS whitening filters were engaged successfully (REF Q whitening
filter only because REF I whitening kills lock.) and appear to improve
the noise performance.
Mode Cleaner Servo
Rich Abbott
Shipped the new modecleaner servo board, PD interface card and an appropriately
tuned I&Q demodulator board. A new database and screens are to
be sent up within the next day. A second eliptic filter daughter
card is being built at 150 Hz to provide the ability to have higher frequency
crossovers in the MC/PSL crossover.
4km Interferometer Installation
Dennis Coyne
The vertex section of the vacuum system was vented and in-chamber installation
has begun. The MMT3 will be the first supended optic to be installed and
aligned this week. The entire in-chamber vertex installation is expected
to be completed in late March. (Note: This instalation is with the new
OSEMs.) Preparation is being made for installation of the IO components
next week and the 4K COS vertex equipment starting the week of 2/19.
PSL
Peter King
Two problems were reported with the EPICS records database for the
4k PSL. One was the signal relating to the voltage applied to the
SLOW actuator on the NPRO master oscillator. In the rack electronics
drawings, this signal is indicated as being connected to the first 4116
module, whereas it is connected to the second. The second problem
related to the signal for monitoring the laser power. The 2k PSL
EPICS records database reflects the cross-connect installed in 2X7 and
not that fabricated for 1X3. Since the 4k PSL EPICS records were
copied from the 2k database, the signal PSL-126MOPA_AMPMON needed to be
changed to reflect the hardware connection to the 3123A.
1.2LLO INSTALLATION & COMMISSIONING
Commissioning
Rai Weiss
The major event was the first lock of the x arm
4km cavity. The locked stretches lasted for up to 10 minutes but showed
large power fluctuations (50% and larger) in the transmitted beam. The
lock seemed to be associated with pitch fluctuations which generally terminated
the locked sections. The feedback used the digital servo system. A second
attempt to lock the cavity was made several days later in which locked
sections were achieved by controlling both the input and end test masses.
The diagnostic phase has begun with data mining to search for correlations
between experiment variables and especially to determine the source of
the pitch instability.
The digital system at Livingston, both the LSC and DAQ, has been improved
so that typically only one rebooting is required per day. The reduced data
archiving system was installed so that selected channels can be archived
with full bandwidth for permanent storage.
GRB
Szabi Marka
We received a real GRB warning this week. (Supernova early warning
project)
PEM
Szabi Marka
I worked on the setup/repair of seismic equipment for the LLO array.
Our collaborators from LouisianaTech are already taking measurements and
we would like them to use all the available DAQ units.
GDS
Szabi Marka
The Reduced DataSet writer and tape robot setup is finished on DECATUR
(fortress equivalent computer at LLO). The new version of DTT is also installed
and tested. Delaronde was also upgraded to be able to handle the new frame
format. Decatur and Delaronde received a memory upgrade to a total of 2Gb
each. Thanks is due to Ed (Daw), Daniel (Sigg) and John (Zweizig)! I released
the new DMT monitor observer web-page writer script. It provides more info
for operators and greatly improved fault detection. Further enhancements
are coming...
2.0 OtherEngineering and Scientific Activities
2.1 R&D/Design/Analysis/Fab
Advanced R&D Review
An advanced R&D review was held, by an NSF appointed committee, at
Caltech for the LIGO Lab proposed research plan for advanced LIGO.
Optics Modelling
Erika d'Ambrosio
The parallel version of the Dual Recycling Model FFT Code has been
compiled. It works well but looking at the output data regarding the GW
sidebands I suspect they are not sensible. Since Ken Ganezer, George Jennings
and others have separately accomplished the same goal I will not go further
in investigating inside the core. I am entering inside the core of
the Power Recycling Model FFT Code in order to extract more information
on the beam.
LSC
Rich Abbott, Mohana Mageswara, Flavio Nocero
We are now building any outstanding PCB's for use in the 4K LSC installation
at LHO. This will continue in the weeks to come.
PSL
Peter King, Lee Cardenas
-
The redesigned goniometer mounting scheme mentioned last week was modified
by Lee. The end result I think is much nicer in terms of mechanical
stability. The prototype is currently being installed in the laser
but seems to have all the features we desire for adjustments. Later
this week I hope to finalize the AutoCAD drawings for it. (holds the EOM,
the goniometer and the New Focus mount all together in place).
-
Working on the MOPA S/N 110 laser alignment.
-
I have increased the current on the NPRO from 2.064 amps to 2.107 amps.
I encounter a situation on the process, the potentiometer is not responding
as a turn it up. So, the most is 2.107 amps. I wanted
to increase the NPRO power from 453 mw to 500 mw but the most i got is
485mw. I will contact Lightwave.
-
I have put together a Ref. cavity contacting mount, consisting of breadboard,
XYZ-Translation stages, rail and carriages.
Rick Karwoski, Ben Abbott, Paul Russell
-
A 2nd set of PMC servo boards is currently in test
-
Schematic updates and refinements for the PSL are on-going.
-
Preparations for Bridge Lab-constructed cross connects for 40m and LASTI
have begun
-
Progress is being made on the intensity servo.
New OSEM Heads
Janeen Romie
Rapid Prototyping ran two batches of ZrN coating on acid etched heads.They
use an ion infusion process. The first batch of 60 along with the second
batch of 7 have turned out faulty. With both batches, when the heads were
ultrasonically cleaned in Liquinox, coating material came off. John Petersen
from Rapid Prototyping is trying to determine the cause of the problem.
The second batch had different parameters than the first - more heat, more
bias boltage and more nitrogen - but did not prove superior in durability.
We have submitted an RFQ to Macro Metalics for TiCr coating heads.
The quote is due here tomorrow. It will include a polishing operation.
We have submitted an RFQ to Macro Metalics and to Astro Pak for stripping
ZrN parts. Astro Pak will receive two heads tomorrow as samples.
Twenty acid etched heads have gone to Surmet for ZrN sputtering. They
are trying to complete this by the end of this week. Progressive Technology
is shipping most of the next osem head shipment today and the balance tomorrow.
I brought a number of heads to JPL for measurement of surface finish.
DAQ
Rolf Bork
Made necessary changes to DAQ controller software to handle up to 5900
DAQ channels. This was required to accept the additional 2000+ EPICS
channels at LHO.
Digital Suspensions & Controls
Rolf Bork
Continued work on digital suspension software; looks like it should
be ready to go in about 2 weeks.
(D. Coyne: First install and test will be at the X-end station in
Hanford.)
Received new vxWorks board support package (Tornado 2) software for
our latest models of VME Pentium processors. This was required as the latest
chipsets are Intel GX series processors, not supported under Tornado I.
Seems like Intel chip sets change rapidly, as CPUs we had purchased just
3 months prior had rev
"BX" chip sets. Anyway, spent about a day making our specific
kernel changes and testing the new CPU boards.
Jay Heefner
-
Rack and wiring diagrams for all 4K suspension systems are complete. Cross
connect lists, etc. will be sent to Richard by 2/2 for assembly.
-
LOS Bias boards are complete and tested.
-
SOS Coil driver boards and are being stuffed. This is the last board needed
for the 4K installation.
-
Capacitors for the LOS coil driver have been received. Chassis should be
assembled and tested by 2/9.
-
The option of optical lever damping of each optic has been added to the
4K system. Lori has completed the design of a module that will interface
the optical lever PDs to the spare penteks in the system. Boards should
be available by the end of Feb.
Data Acquisition
Sander Liu
Picked up the twelve antialiasing filter boards Accu-Sembly was building
for us. One complete LEMO chassis was built and tested. The unit was delivered
to CDS for system integration test. The remaining units will be built and
tested within the next few weeks.
Fabrication of the 16 channels data cables is now complete. They were
scheduled for delivery to us from So-Cal Value Added within the next few
days.
2.2 IssuesConcerns
Magnetic material in the new OSEM
Dennis Coyne
The filter seal for the photodiode and the LED for the new OSEMs were
found to be magnetic. The interaction with the magnets on the optic causes
a DC pitch alignment shift of about 1.5 mrad for the small optics. A solution
for the mode cleaner optics is being pursued.
40 Meter Interferometer (Weinstein)
-
AJW gave a talk
to the NSF Advanced LIGO review panel, to explain the purpose of the 40m
program and why Glasgow isn't doing it all (in my zeal, I probably insulted
the Glasgow effort, for which I apologize!).
-
From Mike Smith: The ACAD opto-mechanical layout of the 40 meter interferometer
has been revised to incorporate the PSL and IO optics. The mode-matching
optics for the input mode cleaner are being designed. Design requirements
documents for the auxiliary optics subsystem (AOS) are in process.
-
Larry Jones is assiduously following the progress of all the mode cleaner
and output optic chamber hardware as it makes its way from manufacturer
to Allied and or LLO for cleaning, baking, and testing. There have been
a variety of delays and snafus, but we can expect all parts to be back
at Caltech for installation in February.
-
Larry is designing the last remaining element of the vacuum envelope, an
29.5" diameter, 18" long adjustable bellows to connect the existing side
optic chamber with the new output optic chamber. He is also learning AutoCad
(in his semi-retirement) and updating the building drawing portion of Mike
Smith's layout.
-
The 1m linear mode cleaner that served the 40m well in its last years was
removed, and is stored away. The PSL table at the 40m was moved into the
position that we currently believe is final, and an enclosure (like the
ones at the sites) was built around it on Thursday. Peter King and Lee
Cardenas were on hand to assist and approve it.
-
It looks like the PSL for the 40m will be assembled at the same time as
the PSL for LASTI, which has an impact on the 40m schedule. Visitng grad
student Guillaume Michel will assist in the building and commissioning
of the PSL.
-
Garilynn is pursuing the polishing and coating (at MLD) of the three input
mode cleaner suspended optics.
-
Steve Vass removed the last of the 40m recycling experiment test masses
and transferred it to Ron Drever. Ron now has all the test masses from
the recombination and recycling experiments.
-
Ben Abbott and Dennis Ugolini visited IAC Industries furniture showroom,
and selected their LAN Station product line for use in the 40m control
room. We will order the tables, chairs, shelving, etc soon.
-
The Sun Ultra 60 which will be used for 40m DAQ arrived on Wednesday. It
is still in boxes. It will be set up by Rolf with the reflective memory
card, etc.
-
Guillaume and Dennis Ugolini are making progress in understanding E2E and
the 40m/DR E2E model.
-
Dennis Ugolini is working on the final report for the E2 seismic study.
Thermal Noise Interferometer (Libbrecht)
no report
LASTI (Zucker)
no report
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Bhawal)
_____________
In wednesday's weekly meeting, We discussed about pros and cons of
developing a client-server framework to get ready to use CACR multi-CPU
computers to handle multiple long e2e jobs simultaneously.
* Client-server framework (Tavio D'Angelis)
-------------------------------------------
The client-server framework for the end-to-end modeling application
is
being constructed as stand-alone client and server processes
until the
framework is robust enough to handle the modeling application
as a
co-process. The first essentials of the program for the request-reply
structure of the client and server application are the duplication
of
files over the socket connection and the e-mail notification
to the
client user. Both of these have been demonstrated via
test cases.
I am creating the framework for the client-server model
as follows: the
client program will submit a dummy request to a simple application
which
is invoked by a server. The server will run this application
and via the coprocess mechanism will store the output of the
app.
The essential features are : generating a unique request number,
creating a subdirectory to run the application in, copying the
files,
running the application, and storing the resulting output from
the
application. Once the application aborts due to errors or successful
completion, its output is transmitted via e-mail to the requestor.
* Parallelization of code (Matt & Hiro)
--------------------------------
Matt has completed the simulation testbed with a revised enqueuing
and
dequeuing class. He is starting to implement logics to utilize
threads
most efficiently.
Hiro did some basic programming work for e2e.
* Mechanical simulation (Virginio)
----------------------------------
Virginio has built the first version of the pendulum model for
the
advanced LIGO using Cella's MSE. He had a meeting with Peter
F and
Hiro to discuss the future plan. In a week, he will provide
a version
which Peter can start using with pendulum motion of wires suspending
the test mass.
* Lock-acquisition Studies (Biplab)
-----------------------------------
Continuing studies of lock-acquisition in presence of angular
fluctuations of mirrors. It seems during the acquisition process,
the
power fluctuations at early states may not always hinder the
system to
get into next state and then get fully locked. As an example,
a level of
7e-8 rad-rms ang. fluctuation causes power fluctions of the
order of 13%
(i.e, rms/mean) in state 2 or state 3. In most of the cases
(if state 2 or
3 are long), such a situation is not good enough for the IFO
to get fully
locked but, if it so happens (due to probability-dependent state
of the
length-changes) that state 2 or 3 are short-lived and the system
gets
locked, the power fluctuation in the full-locked state is only
5%.
From a number of runs, it seems, power fluctuations in fully
locked
state are mainly dependent on ang. fluctuations in end mirrors.
Working on mathematical explanation of results.
* Alfi (Ed maros)
-----------------
- Finished first pass of copy/paste, a feature being introduced
in Alfi.
- Upgraded wxWindows to 2.2.4.
LIGO Data Analysis System
Software Systems (Blackburn)
Kent was out this week. Work has been progressing on adding functionality
to the client controlMonitor API to enable viewing API status and controling
LDAS jobs from remote "thin clients" with Tcl/TK. The frameAPI is having
additional functionality added to it in order to support end-to-end pipeline
processing, from frame data on disk to events into the database. This is
preparatory for the upcoming use of LDAS for the UL analyses. A bug in
the API which formats data for internal use within LDAS (ilwd format) was
being tracked this week.
[ Phil Ehrens ]
*(PSE) Continued reimplementing frame.tcl functions to use
dictionary and specialised
accessors from frameAPI.so.
*(PSE) System tested new ilwd and frame code on ldas-dev and
on marfik daily to keep
uncommitted changes to frame
API in synch with other
new LDAS code.
*(PSE) Added secure method for user list in manager to be
updated on-the-fly without affecting
running jobs.
*(PSE) Worked with Ed to develop test scripts for dc API
development.
Hardware Systems (Anderson)
Finished LDAS Request For Quotes (RFQ) for ~30TB of disk storage,
a 6000 slot tape silo, and initial 16 node beowulf clusters for LHO
and LLO.
Finished renovation work on 215 Synchrotron which currently holds the
ldas-test
system and will eventually hold the main ldas-archive system. The raised
floor
supports have been fixed and missing tiles have been replaced.
Continued planning for a probably move of LDAS to the staging building
at LHO.
Received one Intel P4 and one AMD K7 for advanced LDAS configuration
and
performance testing at Caltech with an immediate goal of selecting
engineering
run beowulf clusters for LHO and LLO, approximately 16 nodes each.
Installation and initial testing of a 2 drive/30 slot AIT-2 robot at
LLO
in preparation for the E3 run in March.
Initial contact with Cybernetics regarding a possibly broken AIT-2 drive
in the robot at LHO.
Finished upgrade of all LDAS Sun computers to Solaris version 8, including
all desktop machines for E2E and LDAS staff on the 6th floor of Millikan.
Solaris UFS logging enabled on all the LDAS Sun computers at LHO.
Lazzarini met with the CACR directorship in order to bring the newly-returned
Paul Messina up to date on the LIGO/CACR MOU and current plans for deploying
the archive at Caltech.
Data Analysis Activities
Andrea Vicere' reports from Pisa:
- Working with the PEM group in Virgo for collecting material in view
of the
11th February meeting.
General Computing (Wallace)
MIT:
Nothing to report.
Livingston:
Tom and Shannon are looking at security options to handle the existing
network
and the future OC3 network.
Hanford:
Christine setup a meeting to go over the OC3 fiber installation. From
the
meeting Larry is going to check on a number of possible configurations
for
the installation. Fred or a representative will work on getting a contact
to install the jumper for the fiber connection between the Observatory
and
PNL.
CIT:
(Lisa)
- upgraded 2 more computers on 6th Millikan to Solaris 8. Stuart
swears this is
really the last of them.
- built a laptop and a desktop PC to support the NSF review.
- Helped out Liz with projectors and such for the NSF review.
- Rebuilt the OS of the server that has the new cybernetics tape robot
on it.
- Worked with Larry on getting the cybernetics drivers and software
installed.
- Did monthly backups. I used the cybernetics robot for the data
disks. Root
partitions will continue to go to 8mm using ufsdump.
- The ISDN line for the new modem pool got installed but I need to
call 3com
about the configuration.
- I identified a block of IP numbers on the 125 subnet to reserve for
DHCP on
the new modem pool.
- Replaced Helena's pc with a better one.
- Worked on recovering files and running diagnostics on Bill Kells
laptop. This
was a joint project with Sam who did most of the basic rebuild.
- Created a list of the patches that should be run on all of the Win98
boxes.
(Suresh)
-Installed and doing some tests on Concurrent Version System (CVS)
on my
workstation.
-Helped Helena replacing her old PC with Gateway 400 PC. Transferred
some
files and installed additional applications.
-Did some tests on ATM switch to find the problem with ES2810 ATM uplink
connection in computer room.
-Diagnosed Mike Smith's new PC's floppy drive reading problem and replaced
with new one. Did some printer maintenance.
(Sam)
Wow, have I been busy
-Rebuilt two laptops, lots and lots of time involved.
-Worked on gina's computer
-Answered a bunch of pc questions
-Burned some CD's
-Working on fixing some stuff for Dave B.
(Barbara)
-Created a program that makes a "flat" version of the DCC database
for David
Shoemaker. The first use will be to make T, M, P, and G documents
available in an Excel spreadsheet. Next I have to set up the
process to
run it regularly and set up links to it on the internal bulletin board.
-Worked on the LDAS web page for contacts -- a perl script. It
has been
simultaneously an educational, frustrating, and rewarding experience
trying
to read and use data in the mail aliases file.
-Updated LIGO home page with graphics from latest edition of newsletter.
Created and installed web page for PAC transparencies. Installed
January
newsletter. Added links to LHO logs and Amaldi.
-Investigated a new US map for the LDAS web site. Sized photos
from the MDC.
-Fixed several incidents with the DCC batch job that compacts the database.
The process hangs with the step that renames the main document database.
This job has been working for almost a year now so this new wrinkle
is a
mystery.
-Update public document search tool.
-Met with Phil and Linda about the AIIM meeting and discussed the procedure
for posting the March LSC transparencies with Linda.
(Larry)
-Worked a number of DCC issues. Presently, working with Linda to get
things
ready for the LSC conference.
-Modified/updated DNS tables and host files to accommodate naming changes
and
LDAS testing.
-Worked through a number of purchases. Hopefully, the projectors will
arrive in
the next few weeks, Epson has them on back order. The UPS replacement
still has
not arrived but APC assures me that it has shipped. A number of the
PC's have
arrived. Will be ordering a couple more laptops.
The travel laptops and projectors worked out well for the NSF review.
-Resolving some issues with the anonymous ftp services running at this
time.
The LDAS group has made changes to the LDAS server in order to increase
security. The GC server will still be open because of the number of
locations it needs to support. However, if we have too many problems
we may need
to make it more secure which will change the way some people are exchanging
files.
-Resolved a number of PC issues. Most were just setups that needed
to be
reworked. Bill Kells laptop and a few others have been taking up some
time.
Mostly, working with the vendor to get things diagnosed.
-Worked a number of SDRC issues. Installed a new license but waiting
for the
word on when it will actually expire before that issue is closed.
LIGO II/Advanced R&D (Sanders)
Peter King
3.1 Advanced LIGO PSL
Benno Willke and I have
worked through a revised schedule that
adopts the major elements of the WBS. To initiate the transition
to
EPICS
controls, we will be shipping them some items of VME hardware, RF
photodiodes, VCO and frequency servo for testing and implementation
on
the
current GEO injection-locked laser. Later this week I hope to
revise
the
WBS Dictionary, the schedule and the costing.
3.2 40m Lab PSL
I have completed the 2-dimensional
layout of the 40m Lab PSL.
The
drawing was passed to Mike Smith to allow him to complete the optical
layout of the 40m Lab.
The PSL table enclosure is scheduled to arrive tomorrow (Thursday) after
being held in storage for some number of months.
3.3 LASTI PSL
I had a quick meeting with
David Shoemaker about what exactly he
was expecting by ways of a PSL, as I had wondered if I'd have to do
a
complete installation or supply a box of parts. Consequently
many boxes
will be arriving in the near future.
Helena Armandula
Silicate bonding
Fabricated a new test apparatus to be able to test tension on bonded
substrates.
Researching epoxies to be able to affix the silicate bonded substrate
to
the testing holders without introducing stress to the glass.
LIGO-II SEI
Szabi Marka
I was working on the design and modeling of the new version of the
UHV
compatible STS-2 lock mechanism.<x-html>
For additional information about this report, contact sanders@ligo.caltech.edu