Weekly Report for Week Ending February 1, 2001


 Exec. Comm. Agenda
Highlights
LSC
Administration
Hanford Observatory
Livingston Observatory
MIT
Caltech
Detector
40 Meter
TNI
LASTI
Data Analysis
LIGO II/Adv. R&D
Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  February 5, 2001 will be:

 (Meeting time: 10:30 am Pacific Time)

Open meeting 10:30 - 11:30

  1. Announcements
  2. LSC Issues (Weiss)
  3. Comments on Weekly Report
  4. WBS 1 LIGO I Construction (Lindquist)
  5. WBS 2 LIGO Lab Operations
  6. WBS 3 and 4  Advanced R&D and LIGO II (Sanders)
Executive Committee only 11:30 - noon   Topics:   NSF review reprise
 

Special Items:


Special Announcements:

The LIGO Newsletter for January 2001 is now posted!
Read it here:

http://www.ligo.caltech.edu/LIGO_web/0101news/0101main.html
 


Weekly Report Highlights

LLO Fabry-Perot cavity locking studies along the X-arm

A 'first look'  displacement sensitivity spectrum was taken for the LHO 2k power recycled interferometer with recycling gain of 11


LSC Issues (Weiss)


No report this week.


LIGO I Construction/LIGO Laboratory Administration (Lindquist)


NSF Review


A NSF Review Committee (Detector Research and Development Subpanel) conducted a review of the Advanced R&D program proposed for FY 2002-2006.  This review was conducted at Caltech January 29,2000 through February 1, 2000.

The review panel provided a briefing on February 1, 2000.

The review panel indicated that the proposal for research and development on an advanced LIGO detector contains a set of significant technical challenges that, if met, will provide a design for an advanced gravitational-wave detector and deemed the proposed balance between operation of initial LIGO and R&D on advanced LIGO, as described during the review, appropriate.

[GHS note:   The review was a great success! While we have been advancing in detector commissioning and in preparations for data analysis and modeling, the review recognized the third leg in the stool; a very powerful R&D program for advanced LIGO that is in place as a strong collaborative effort with the LSC and that has grown to a full 1/3 of all of the Laboratory's efforts. Everyone is to be thanked and congratulated for their efforts in this program and for the thorough preparation and expert responses to the review panel's questions.]
 

WBS 1.2 LIGO Operations--Administration


LIGO Weekly Site Telecon (Lindquist)

There was no site teleconference held on Thursday, February 1, 2001.

The next site telecon is scheduled for Thursday, February 8, 2001.  The list of current actions revised to reflect open actions assigned through January 25, 2001 may be found at ACTION LIST.


PROPERTY MANAGEMENT (Chargois)

From: Ed Chargois <chargois_e@ligo.caltech.edu>


DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner - turner@ligo.caltech.edu>

Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .

ACCOMPLISHMENTS

From: Cleveland Mak <mak_c@ligo.caltech.edu>
Packages Faxes
In 38 45
Out 9 50

Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.


COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Akutagawa, Kaufman)

From: Esther Cunningham <esther@ligo.caltech.edu>

Press here for ACCOUNTS PAYABLE HISTORY DATA.

From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

From: Florence Kaufman <fkaufman@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: irena@ligo.caltech.edu (Irena Petrac)

From: Ed Jasnow <jasnow@ligo.caltech.edu>


Support (Wood)

 
Rita Torres
  • Helped with change order No. 11 to MIT, and also with forms to accompany proposal to TAMA.  Formatted letter to NSF Re: Request for Approval of Procurement of Phase I of LDAS.  Did some printing during NSF preparations.
  • Spent lots of time this week chasing after invoices and such to address Pcard purchases needing to be reconciled, also placed more orders.   Distributed LIGO Laser Safety Plan to participants at the recent safety training.
  • Ongoing activity: Preparing labels to organize drawings and such in the BD lab.  Update site trips.
Dorothy Lloyd

Graphic provided by C. Akutagawa.

  • Processed the usual requisitions, invoices and receiving on-line. For more detail, see "Cost Schedule Control Systems" report by Esther Cunningham.
  • Tracked and followed up on invoice problems.
  • Reviewed and recorded payments processed by Esther for the week of January 22, on contract summary sheets and LIGO database.
  • On the "Receiving" end, continued to work with Florence and Ruth on transferring encumbrances to new fiscal period.
  • Continue to monitor contract and blanket order funding levels and n notify task managers when supplements are needed.
  • Began updating PO Log books for the period September 15 through January 15 (253 entries).
  • Jim continues to do data entry in the LIGO database and help out in both the DCC and travel areas.
Irene Baldon
  • Nine (9) new trips were started and I have eight (8) trips pending final approval before tickets can be issued.  Most of these trips required Advance Checks to be written as well as hotel and car authorization forms to be filled out and FAXed to the appropriate locations.
  • Worked on and completed eleven (11) Expense Reports.  I have seven (7) Expense Reports to work on and I'm holding one (1) report which need a check from the traveler before processing.  Jim Covington completed twelve (12) expense reports and has six (6) that he is working on.  I continue to train and supervise him on expense reports.
  • Reconciled sixteen (16) items on my P-Card this week and have an additional 39 items to do.
  • Traveled to Hanford with Florence Kaufman and Criselda Rodriguez-Brodeur to work with site personnel on various P-Card, account and travel issues.  In addition to the site visit, Criselda and I are working with Jim Carroll of CCSi in regard to enhancement of the P-Card for travel.  The enhancement is proceeding, and we should have more information after he comes down on the 13th.
  • Prepared the Travel/Vacation Itinerary for the Week of January 26, 2001.  Performed normal recording and filing associated with Travel and Reimbursement.  Worked on several problem issues with Travel Audit in addition to the above listed issues.  Also performed miscellaneous duties as requested by various members of the LIGO Project here at Caltech as well as from members of the staffs of each of the two (2) sites.   I continue to do MIT's travel to the sites for installation activities and also to assist them wherever possible.
Elizabeth K. Wood
  • Oversaw the care and feeding of the NSF Review Committee during their visit.  Thanks to Peter King for providing an industrial size power strip, Lisa and Larry for providing computer support, and Linda for helping with mopping up.
  • Attended a meeting with Ed Jasnow and Donna to meet the new immigration specialist.  HR is still looking for a director of immigration, but they currently have an “acting” director in the interim.  The immigration office has moved in with HR over on Holliston Street and instead of being in Parsons-Gates in the provost's office will now be under the umbrella of our crack HR department.

Advanced LIGO (Frey, Petrac)

From: Thomas Frey <tfrey@ligo.caltech.edu>

Progress Period from 01.26 to 02.01

Accomplishments:

Schedule 02.02 to 02.08:

WBS 1.4.1.2   Project Controls (LIGO Construction)



Reports (Lindquist)

Nothing to Report.



Change Control/Contingency (Lindquist)

The following Change Requests have been submitted:
 

CR-000018 WBS 1.1.4 Curbing for Service Roads at Livingston G. Stapfer
CR-000019 WBS 1.2 Additional Lab Equipment D. Coyne
CR-000020 WBS 1.1.4 Staging Building and Renovations to Existing Building--Livigston F. Asiri
CR-010001 WBS 1.1.4 Return of Unused Construction Budget To Contingency F. Asiri

Press for the latest Contingency Needs Projection.


COST SCHEDULE CONTROL SYSTEMS (Duncan, Akutagawa)

From: Kris Duncan <kris@ligo.caltech.edu>

From: Cindy Akutagawa <cindy@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: Ed Jasnow <jasnow@ligo.caltech.edu>

From: irena@ligo.caltech.edu (Irena Petrac)

LIGO Hanford Observatory (LHO) Operations (Raab)


General Items:
--------------
(F. Raab)

After finishing up ETMx, installation has moved to the corner station. The
Controls and Computing reports (prepared last week but not submitted due to
my error) are also reprinted.

Controls
--------
(D. Barker)

Built the EPICS controls for the LSC high gain switching system for QPD
Sum signals.

Begin the installation of the latest version of EPICS, 3.13.3.

Worked VME problem with ASC front end FM optlev pentek card.

Put together test stands for baja and pentium code dev.

Computing
---------
(C. Patton)

A read only copy of the LHO elogs is now available at

http://apex.ligo-wa.caltech.edu/ilog/.

Everyone uses the username
"reader" and password "readonly".  Thanks to Bruce Sears for setting
this up.  The elog files are being copied from the CDS network to apex
daily.
 

Last week I attended an Advanced PC Maintenance course.  I learned a few
good things about BIOS settings, using the Windows registry, optimizing
memory and CPU, and security features in Windows 98.

Input Optics (4 K installation)
--------------------------------
(Betsy Weaver, Corey Gray and David Ottaway)

The new OSEMs have been fitted to the MC2 and SM1. It was noticed that
these OSEMs change the balance angle by up to 3 mRad. The direction
change is always front face (HR Surface) tilts downwards. This effect
has been traced to the face magnets attracting towards the ferromagnetic
components in the new OSEMS. In consultation with Stan W and Peter F it
has been decided to proceed with the installation as is and correct for
this problem using higher range current drivers.
 

Core Optics (4 K installation)
------------------------------
(D. Cook)

The LHO 4K installation has moved to the corner station. The MMT3 is on
the optics table, but the final position has not been finished as we need
to reverify the location dimensions. The HAM 1,2,3 and BSC2&34 tables have
had their elevations set and leveled. SUS temporary controllers and the new
satellite boxes installed and tested. The optical levers are getting close
to their final setups. The RM is being fitted with its new OSEMS and will
be next in line for installation the first part of next week. We have a ton
of COS hardware stage and ready to follow on after the IAS finishes up.
Even with a couple a minor setbacks we are holding to our original schedule
thanks to a big team
effort.   (SKI,Gerardo,Hugh,Corey,Dave,Betsy,Rick,Richard, Josh, The PSL group
and others, Did I mention MOM in there?)


LIGO Livingston Observatory (LLO) Operations (Coles)



 

This week we began Fabry-Perot cavity locking studies along the X-arm. We have been able to achieve locked sections that are as long as several minutes and in one case nearly ten minutes long. We have been able to make spectral measurements and are now busy discovering problems with the installed system and are fixing them incrementally. For example, there is an obvious pitch motion of ITM-x that we are now trying to understand. The residual water content in the vacuum in the corner station is very low, so wetting the beam tube has not been a major concern. Only about 1 torr-liter of water load has been added to the beam tube during each of the roughly 12 hour periods the X-arm gate valve has been open for locking studies. A general concern is that the seismic environment here is higher at low frequencies (around 1-3 Hz) than that encountered at Hanford, and construction of the staging building modification is now underway, generating additional noise - so our attempts at locking have been at night.

General Computing: Exabyte tape library has been removed from decatur and will be installed on aubry (future email server). AIT2 tape library has been installed on decatur. It has been tested and is up and functional. We have been investigating different models of Cisco PIX Firewalls.
LDAS:The AIT2 tape library has been installed and configured on Beowulf. Gregg Mendell is running some scripts on it to run it through its paces.
CDS :We have installed ghostscript on one of the CDS machines and will install it on the server shortly. (Shannon Roddy)

Other: We are in the process of working on several loads for the 40M in Pasadena. However, we are currently having a problem with either a leak or vacuum instrumentation, or with both, and are trying to resolve that before heating the oven. (Tom Evans)

Rough grading for the annex to the staging building began this week. Excavation of the footings for the interior supports is nearly complete. Augering for the vertical steel columns will be done next week.


Detector/Technical Support (Whitcomb, Coyne)



 

Installation& Commissioning:
Hanford
Livingston
Other Science/EngineeringActivities:
Design/Analysis/Fab
Issues/Concerns
Seealso the Installationweb page

1.1 LHO INSTALLATION & COMMISSIONING

2km Commissioning

Dennis Coyne
A 'first look'  displacement sensitivity spectrum was taken for the power recycled interferometer with recycling gain of 11. There is some significant uncertainties about the calibration (see the log entry for details), but it is interesting nonetheless. Most of the past few days have been taken up with aligning the 2 km interferometer, trying to get back to a good locking state so that WFS can be tested and brought on-line. By examining the beam spot locations on the ITMs and ETMs, we conclude that the beam is low in the recycling cavity, though still roughly parallel to the plane of the interferometer; The beam will be walked up through the MMT this weekend.
The AS whitening filters were engaged successfully (REF Q whitening filter only because REF I whitening kills lock.) and appear to improve the noise performance.

Mode Cleaner Servo

Rich Abbott
Shipped the new modecleaner servo board, PD interface card and an appropriately tuned I&Q demodulator board.  A new database and screens are to be sent up within the next day.  A second eliptic filter daughter card is being built at 150 Hz to provide the ability to have higher frequency crossovers in the MC/PSL crossover.

4km Interferometer Installation

Dennis Coyne
The vertex section of the vacuum system was vented and in-chamber installation has begun. The MMT3 will be the first supended optic to be installed and aligned this week. The entire in-chamber vertex installation is expected to be completed in late March. (Note: This instalation is with the new OSEMs.) Preparation is being made for installation of the IO components next week and the 4K COS vertex equipment starting the week of 2/19.

PSL

Peter King
Two problems were reported with the EPICS records database for the 4k PSL.  One was the signal relating to the voltage applied to the SLOW actuator on the NPRO master oscillator.  In the rack electronics drawings, this signal is indicated as being connected to the first 4116 module, whereas it is connected to the second.  The second problem related to the signal for monitoring the laser power.  The 2k PSL EPICS records database reflects the cross-connect installed in 2X7 and not that fabricated for 1X3.  Since the 4k PSL EPICS records were copied from the 2k database, the signal PSL-126MOPA_AMPMON needed to be changed to reflect the hardware connection to the 3123A.
 

1.2LLO INSTALLATION & COMMISSIONING

Commissioning

Rai Weiss
The major event was the first lock of the x arm 4km cavity. The locked stretches lasted for up to 10 minutes but showed large power fluctuations (50% and larger) in the transmitted beam. The lock seemed to be associated with pitch fluctuations which generally terminated the locked sections. The feedback used the digital servo system. A second attempt to lock the cavity was made several days later in which locked sections were achieved by controlling both the input and end test masses. The diagnostic phase has begun with data mining to search for correlations between experiment variables and especially to determine the source of the pitch instability.

The digital system at Livingston, both the LSC and DAQ, has been improved so that typically only one rebooting is required per day. The reduced data archiving system was installed so that selected channels can be archived with full bandwidth for permanent storage.

GRB

Szabi Marka
We received a real GRB warning this week. (Supernova early warning project)

PEM

Szabi Marka
I worked on the setup/repair of seismic equipment for the LLO array. Our collaborators from LouisianaTech are already taking measurements and we would like them to use all the available DAQ units.

GDS

Szabi Marka
The Reduced DataSet writer and tape robot setup is finished on DECATUR (fortress equivalent computer at LLO). The new version of DTT is also installed and tested. Delaronde was also upgraded to be able to handle the new frame format. Decatur and Delaronde received a memory upgrade to a total of 2Gb each. Thanks is due to Ed (Daw), Daniel (Sigg) and John (Zweizig)! I released the new DMT monitor observer web-page writer script. It provides more info for operators and greatly improved fault detection. Further enhancements are coming...

2.0 OtherEngineering and Scientific Activities

2.1 R&D/Design/Analysis/Fab

Advanced R&D Review

An advanced R&D review was held, by an NSF appointed committee, at Caltech for the LIGO Lab proposed research plan for advanced LIGO.

Optics Modelling

Erika d'Ambrosio
The parallel version of the Dual Recycling Model FFT Code has been compiled. It works well but looking at the output data regarding the GW sidebands I suspect they are not sensible. Since Ken Ganezer, George Jennings and others have separately accomplished the same goal I will not go further in investigating inside the core.  I am entering inside the core of the Power Recycling Model FFT Code in order to extract more information on the beam.

LSC

Rich Abbott, Mohana Mageswara, Flavio Nocero
We are now building any outstanding PCB's for use in the 4K LSC installation at LHO.  This will continue in the weeks to come.

PSL

Peter King, Lee Cardenas Rick Karwoski, Ben Abbott, Paul Russell

New OSEM Heads

Janeen Romie
Rapid Prototyping ran two batches of ZrN coating on acid etched heads.They use an ion infusion process. The first batch of 60 along with the second batch of 7 have turned out faulty. With both batches, when the heads were ultrasonically cleaned in Liquinox, coating material came off. John Petersen from Rapid Prototyping is trying to determine the cause of the problem. The second batch had different parameters than the first - more heat, more bias boltage and more nitrogen - but did not prove superior in durability.
We have submitted an RFQ to Macro Metalics for TiCr coating heads. The quote is due here tomorrow. It will include a polishing operation. We have submitted an RFQ to Macro Metalics and to Astro Pak for stripping ZrN parts. Astro Pak will receive two heads tomorrow as samples.
Twenty acid etched heads have gone to Surmet for ZrN sputtering. They are trying to complete this by the end of this week. Progressive Technology is shipping most of the next osem head shipment today and the balance tomorrow. I brought a number of heads to JPL for measurement of surface finish.

DAQ

Rolf Bork
Made necessary changes to DAQ controller software to handle up to 5900 DAQ channels.  This was required to accept the additional 2000+ EPICS channels at LHO.

Digital Suspensions & Controls

Rolf Bork
Continued work on digital suspension software; looks like it should be ready to go in about 2 weeks.
(D. Coyne: First install and test will be at the X-end station in Hanford.)

Received new vxWorks board support package (Tornado 2) software for our latest models of VME Pentium processors. This was required as the latest chipsets are Intel GX series processors, not supported under Tornado I.  Seems like Intel chip sets change rapidly, as CPUs we had purchased just 3 months prior had rev
"BX" chip sets.  Anyway, spent about a day making our specific kernel changes and testing the new CPU boards.

Jay Heefner

Data Acquisition

Sander Liu
Picked up the twelve antialiasing filter boards Accu-Sembly was building for us. One complete LEMO chassis was built and tested. The unit was delivered to CDS for system integration test. The remaining units will be built and tested within the next few weeks.
Fabrication of the 16 channels data cables is now complete. They were scheduled for delivery to us from So-Cal Value Added within the next few days.

2.2 IssuesConcerns

Magnetic material in the new OSEM

Dennis Coyne
The filter seal for the photodiode and the LED for the new OSEMs were found to be magnetic. The interaction with the magnets on the optic causes a DC pitch alignment shift of about 1.5 mrad for the small optics. A solution for the mode cleaner optics is being pursued.



40 Meter Interferometer (Weinstein)




Thermal Noise Interferometer (Libbrecht)


no report


LASTI (Zucker)


no report


Data Analysis and Computing (Lazzarini)


Simulation and Modeling (Bhawal)

_____________

In wednesday's weekly meeting, We discussed about pros and cons of
developing a client-server framework to get ready to use CACR multi-CPU
computers to handle multiple long e2e jobs simultaneously.

* Client-server framework (Tavio D'Angelis)
-------------------------------------------
  The client-server framework for the end-to-end modeling application is
  being constructed as stand-alone client and server processes until the
  framework is robust enough to handle the modeling application as a
  co-process. The first essentials of the program for the request-reply
  structure of the client and server application are the duplication of
  files over the socket connection and the e-mail notification to the
  client user.  Both of these have been demonstrated via test cases.

  I am creating the framework for the client-server model  as follows: the
  client program will submit a dummy request to a simple application which
  is invoked by a server.  The server will run this application
  and via the coprocess mechanism will store the output of the app.
  The essential features are : generating a unique request number,
  creating a subdirectory to run the application in, copying the files,
  running the application, and storing the resulting output from the
  application. Once the application aborts due to errors or successful
  completion, its output is transmitted via e-mail to the requestor.

* Parallelization of code (Matt & Hiro)
--------------------------------
  Matt has completed the simulation testbed with a revised enqueuing and
  dequeuing class. He is starting to implement logics to utilize threads
  most efficiently.
  Hiro did some basic programming work for e2e.

* Mechanical simulation (Virginio)
----------------------------------
  Virginio has built the first version of the pendulum model for the
  advanced LIGO using Cella's MSE. He had a meeting with Peter F and
  Hiro to discuss the future plan. In a week, he will provide a version
  which Peter can start using with pendulum motion of wires suspending
  the test mass.

* Lock-acquisition Studies (Biplab)
-----------------------------------
  Continuing studies of lock-acquisition in presence of angular
  fluctuations of mirrors. It seems during the acquisition process, the
  power fluctuations at early states may not always hinder the system to
  get into next state and then get fully locked. As an example, a level of
  7e-8 rad-rms ang. fluctuation causes power fluctions of the order of 13%
  (i.e, rms/mean) in state 2 or state 3. In most of the cases (if state 2 or
  3 are long), such a situation is not good enough for the IFO to get fully
  locked but, if it so happens (due to probability-dependent state of the
  length-changes) that state 2 or 3 are short-lived and the system gets
  locked, the power fluctuation in the full-locked state is only 5%.
  From a number of runs, it seems, power fluctuations in fully locked
  state are mainly dependent on ang. fluctuations in end mirrors.
  Working on mathematical explanation of results.

* Alfi (Ed maros)
-----------------
  - Finished first pass of copy/paste, a feature being introduced in Alfi.
  - Upgraded wxWindows to 2.2.4.

LIGO Data Analysis System

  • Software Systems (Blackburn)

  •  

     

    Kent was out this week. Work has been progressing on adding functionality to the client controlMonitor API to enable viewing API status and controling LDAS jobs from remote "thin clients" with Tcl/TK. The frameAPI is having additional functionality added to it in order to support end-to-end pipeline processing, from frame data on disk to events into the database. This is preparatory for the upcoming use of LDAS for the UL analyses. A bug in the API which formats data for internal use within LDAS (ilwd format) was being tracked this week.

    [ Phil Ehrens ]

     *(PSE) Continued reimplementing frame.tcl functions to use
            dictionary and specialised accessors from frameAPI.so.

     *(PSE) System tested new ilwd and frame code on ldas-dev and
            on marfik daily to keep uncommitted changes to frame
            API in synch with other new LDAS code.

     *(PSE) Added secure method for user list in manager to be
           updated on-the-fly without affecting running jobs.

     *(PSE) Worked with Ed to develop test scripts for dc API
            development.

  • Hardware Systems (Anderson)

  •  

     

    Finished LDAS Request For Quotes (RFQ) for ~30TB of disk storage,
    a 6000 slot tape silo, and initial 16 node beowulf clusters for LHO and LLO.

    Finished renovation work on 215 Synchrotron which currently holds the ldas-test
    system and will eventually hold the main ldas-archive system. The raised floor
    supports have been fixed and missing tiles have been replaced.

    Continued planning for a probably move of LDAS to the staging building at LHO.

    Received one Intel P4 and one AMD K7 for advanced LDAS configuration and
    performance testing at Caltech with an immediate goal of selecting engineering
    run beowulf clusters for LHO and LLO, approximately 16 nodes each.

    Installation and initial testing of a 2 drive/30 slot AIT-2 robot at LLO
    in preparation for the E3 run in March.

    Initial contact with Cybernetics regarding a possibly broken AIT-2 drive
    in the robot at LHO.

    Finished upgrade of all LDAS Sun computers to Solaris version 8, including
    all desktop machines for E2E and LDAS staff on the 6th floor of Millikan.

    Solaris UFS logging enabled on all the LDAS Sun computers at LHO.

    Lazzarini met with the CACR directorship in order to bring the newly-returned Paul Messina up to date on the LIGO/CACR MOU and current plans for deploying the archive at Caltech.

  • Data Analysis Activities
  • Andrea Vicere' reports from Pisa:

    - Working with the PEM group in Virgo for collecting material in view of the
       11th February meeting.
     

    General Computing (Wallace)

    MIT:
    Nothing to report.

    Livingston:
    Tom and Shannon are looking at security options to handle the existing network
    and the future OC3 network.
     

    Hanford:
    Christine setup a meeting to go over the OC3 fiber installation. From the
    meeting Larry is going to check on a number of possible configurations for
    the installation. Fred or a representative will work on getting a contact
    to install the jumper for the fiber connection between the Observatory and
    PNL.
     

    CIT:
    (Lisa)
    - upgraded 2 more computers on 6th Millikan to Solaris 8.  Stuart swears this is
    really the last of them.
    - built a laptop and a desktop PC to support the NSF review.
    - Helped out Liz with projectors and such for the NSF review.
    - Rebuilt the OS of the server that has the new cybernetics tape robot on it.
    - Worked with Larry on getting the cybernetics drivers and software installed.
    - Did monthly backups.  I used the cybernetics robot for the data disks.  Root
    partitions will continue to go to 8mm using ufsdump.
    - The ISDN line for the new modem pool got installed but I need to call 3com
    about the configuration.
    - I identified a block of IP numbers on the 125 subnet to reserve for DHCP on
    the new modem pool.
    - Replaced Helena's pc with a better one.
    - Worked on recovering files and running diagnostics on Bill Kells laptop.  This
    was a joint project with Sam who did most of the basic rebuild.
    - Created a list of the patches that should be run on all of the Win98 boxes.

    (Suresh)
    -Installed and doing some tests on Concurrent Version System (CVS) on my
    workstation.
    -Helped Helena replacing her old PC with Gateway 400 PC. Transferred some
    files and installed additional applications.
    -Did some tests on ATM switch to find the problem with ES2810 ATM uplink
    connection in computer room.
    -Diagnosed Mike Smith's new PC's floppy drive reading problem and replaced
    with new one. Did some printer maintenance.

    (Sam)
    Wow, have I been busy
    -Rebuilt two laptops, lots and lots of time involved.
    -Worked on gina's computer
    -Answered a bunch of pc questions
    -Burned some CD's
    -Working on fixing some stuff for Dave B.

    (Barbara)
    -Created a program that makes a "flat" version of the DCC database for David
    Shoemaker.  The first use will be to make T, M, P, and G documents
    available in an Excel spreadsheet.  Next I have to set up the process to
    run it regularly and set up links to it on the internal bulletin board.
    -Worked on the LDAS web page for contacts -- a perl script.  It has been
    simultaneously an educational, frustrating, and rewarding experience trying
    to read and use data in the mail aliases file.
    -Updated LIGO home page with graphics from latest edition of newsletter.
    Created and installed web page for PAC transparencies.  Installed January
    newsletter.  Added links to LHO logs and Amaldi.
    -Investigated a new US map for the LDAS web site.  Sized photos from the MDC.
    -Fixed several incidents with the DCC batch job that compacts the database.
    The process hangs with the step that renames the main document database.
    This job has been working for almost a year now so this new wrinkle is a
    mystery.
    -Update public document search tool.
    -Met with Phil and Linda about the AIIM meeting and discussed the procedure
    for posting the March LSC transparencies with Linda.

    (Larry)
    -Worked a number of DCC issues. Presently, working with Linda to get things
    ready for the LSC conference.
    -Modified/updated DNS tables and host files to accommodate naming changes and
    LDAS testing.
    -Worked through a number of purchases. Hopefully, the projectors will arrive in
    the next few weeks, Epson has them on back order. The UPS replacement still has
    not arrived but APC assures me that it has shipped. A number of the PC's have
    arrived. Will be ordering a couple more laptops.
    The travel laptops and projectors worked out well for the NSF review.
    -Resolving some issues with the anonymous ftp services running at this time.
    The LDAS group has made changes to the LDAS server in order to increase
    security. The GC server will still be open because of the number of
    locations it needs to support. However, if we have too many problems we may need
    to make it more secure which will change the way some people are exchanging
    files.
    -Resolved a number of PC issues. Most were just setups that needed to be
    reworked. Bill Kells laptop and a few others have been taking up some time.
    Mostly, working with the vendor to get things diagnosed.
    -Worked a number of SDRC issues. Installed a new license but waiting for the
    word on when it will actually expire before that issue is closed.
     


    LIGO II/Advanced R&D (Sanders)


    Peter King
    3.1 Advanced LIGO PSL
            Benno Willke and I have worked through a revised schedule that
    adopts the major elements of the WBS.  To initiate the transition to
    EPICS
    controls, we will be shipping them some items of VME hardware, RF
    photodiodes, VCO and frequency servo for testing and implementation on
    the
    current GEO injection-locked laser.  Later this week I hope to revise
    the
    WBS Dictionary, the schedule and the costing.
     

    3.2 40m Lab PSL
            I have completed the 2-dimensional layout of the 40m Lab PSL.
    The
    drawing was passed to Mike Smith to allow him to complete the optical
    layout of the 40m Lab.
     

    The PSL table enclosure is scheduled to arrive tomorrow (Thursday) after
    being held in storage for some number of months.
     

    3.3 LASTI PSL
            I had a quick meeting with David Shoemaker about what exactly he
    was expecting by ways of a PSL, as I had wondered if I'd have to do a
    complete installation or supply a box of parts.  Consequently many boxes
    will be arriving in the near future.
     

    Helena Armandula
    Silicate bonding
    Fabricated a new test apparatus to be able to test tension on bonded
    substrates.
    Researching epoxies to be able to affix the silicate bonded substrate to
    the testing holders without introducing stress to the glass.
     

    LIGO-II SEI
    Szabi Marka
    I was working on the design and modeling of the new version of the UHV
    compatible STS-2 lock mechanism.<x-html>
     


    For additional information about this report, contact sanders@ligo.caltech.edu