Weekly Report for Week Ending January 25, 2001


 Exec. Comm. Agenda
Highlights
LSC
Administration
Hanford Observatory
Livingston Observatory
MIT
Caltech
Detector
40 Meter
TNI
LASTI
Data Analysis
LIGO II/Adv. R&D
Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  January 29, 2001 will be:

 CANCELLED DUE TO NSF REVIEW


Special Announcements:


Weekly Report Highlights

Late news from LLO, the Michelson locks!

And the LHO 2K locks better and better in full recycled configuration!

And a successful Mock Data Challenge!


LSC Issues (Weiss)



Draft minutes of EX Comm meeting:

to: LSC executive committee
from: R. Weiss January 23, 2001
concerning: Notes from the LSC Executive committee phone call 01/19/2001

A new iteration of the Data Analysis White Paper will be made by a committee
consisting of Stuart Anderson, Al Lazzarini, Tom Nash, Keith Riles, Alan
Weinstein and Alan Wiseman (chair). The White Paper needs
to articulate a long and short range scientific program and the needs of the field
for the future. One of the suggestions made at the meeting is to remove the
work lists from the body of the paper. First meeting of the group is scheduled
for Jan 23.

The proposal to hold an election for the spokesperson and various
of the LSC committee chairs was discussed. The outcome of the discussion and
comments sent around prior to the meeting is that it would be best not to hold
an election for any position other than spokesperson. The committee chairs
are determined by the spokesperson in consultation with the nominations
committee. It is also the spokesperson's job to determine if committee chairs
want to continue. I will call all committee chairs to determine their situation
before the next LSC executive meeting. As to the election for Spokesperson, if the
nominations committee agrees, we will defer this for another year. The nominations
committee should report on their deliberations at the next LSC Council meeting.

Alan Wiseman reported on the changes in the organization of the software
coordination. A software change control board consisting of Stuart
Anderson, Jolien Creighton and John Zweizig will be constituted. The old
software coordination committee will become a software advisory committee to
the Software Coordinator. The members of the advisory committee are
Sam Finn, Maria-Alessandra Papa and Tom Prince. The CCB will deal primarily
with technical issues while the advisory group will monitor the mock data
challenges, oversee the activities of the CCB and advise the Software
Coordinator.

Meetings being held by the chairs of the upper limit groups have been going on
since the GWDAW meeting last December. The meetings are designed to establish
the common software and hardware requirements of the different upper limit
groups and guide the groups in developing their analysis proposals. Alan
Wiseman in discussions with Barry and members of the executive committee is
preparing some guidelines for the upper limit groups. The principal software
to be used by the upperlimit groups is the LDAS since this will give
practice with the system designed to do the LIGO data analysis. With the
first real coincidence runs now scheduled for September 2001, the conflict
between LDAS being ready and the needs of the upper limit groups has been
somewhat alleviated. The major function of the Laboratory will be to provide
a "clean" pipeline for the data.

The major purpose of the upper limit groups is to test the software and to
write preliminary upper limit papers. The results of the upper limit analyses
should become available in January or February of 2002 when the LIGO II proposal
is presented to the NSF and colloquia are held at the NSF.

A discussion of the types of issues to be brought to the CCB followed. Such
issues as changes in the Frame format, changes in the LAL standard and the
style of Data Tables in DB2 are examples. Daniel Sigg raised the question of
CCB hearings on internal operations software such as that used in
detector diagnostics and on line detector analysis. (I believe) it was decided
that such software does not come under LSC coordination being part of the
detector operations.

Gary Sanders gave a report on his trip to VIRGO to discuss coatings which then
resulted in much broader discussions concerning the collaboration between LIGO
and VIRGO. I cannot do justice to Gary's report but summarize the main points.

1) The coating facilities in Lyon look adequate to do the coatings for LIGO II.
Although there is no demonstrated record of accomplishment of uniformity,
low absorption and low scattering for very large optics, the hope is that the coating of the
VIRGO optics in 2002 will provide the needed experience. Lyon is a viable
option for LIGO II along with several others that are still being investigated.

2) If the coatings are done at Lyon they may constitute an investment in a
broader LIGO/VIRGO collaboration.

3) VIRGO is currently going through a major reorganization. The European
Gravitational - wave Observatory (EGO) is becoming the operational leg
of the VIRGO project with power of the purse and project management. A
subgroup of the EGO is the scientific effort represented by the old VIRGO
management of Brillet and Giazotto who have been given the task to pull together
the scientific program of EGO.

4) Brillet, Giazotto and the group at CNRS including Davier, Dupont and Giacobino are eager
to make more formal couplings to the LIGO project and are talking of operating
LIGO and VIRGO as a single observatory with a uniform publications policy.

5) Major questions raised are whether it is in the best interest of the field
to make bilateral agreement between LIGO/VIRGO. How to involve the LSC in the
collaboration. How the new initiatives intersect with the goals and activities
of GWIC.

6) The general response of the LSC executive committee was positive to the
VIRGO overtures and urged that the details be explored. It was
suggested that the forthcoming LIGO/VIRGO network analysis meeting on Feb 11
actually try to incorporate the VIRGO project in the Engineering runs as a way
of developing confidence and generating useful techniques. Correlation of
PEM signals was considered an interesting and easy initial step. It should be
possible to make special arangements for VIRGO scientists to become involved in
the engineering data analysis by bringing their participation to the
executive committee as we have done for non-LSC people.
 

The next LSC executive committee meeting will be at 11 AM EDT Friday
February 16, 2001
 
 


LIGO I Construction/LIGO Laboratory Administration (Lindquist)


WBS 1.2 LIGO Operations--Administration


LIGO Weekly Site Telecon (Lindquist)

There was a site teleconference held on Thursday, January 25, 2001.  Discussion items included:
1) the financial reports  for the end of Decvember 2000, total booked costs were slightly less than $21.9 million.  Livingston came in within 0.02 percent of budget to capture the "nailed dismount" award.
2) Action Item 86 is closed because it is no longer an issue.  However, copies of the TJLab Administration Policies governing Intellectual Property and visiting researchers have been provided to Ed Jasnow and to the DCC for future reference.
3) Action Item 87 -- Ed Jasnow has provided copies of the Caltech Acquisition Manual to each site.  However, the action remains open pending determination as to whether or not the requested information resides therein.

The next site telecon is scheduled for Thursday, February 1, 2001.  The list of current actions revised to reflect open actions assigned through January 25, 2001 may be found at ACTION LIST.


PROPERTY MANAGEMENT (Chargois)

From: Ed Chargois <chargois_e@ligo.caltech.edu>


DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner - turner@ligo.caltech.edu>

Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .

ACCOMPLISHMENTS

From: Cleveland Mak <mak_c@ligo.caltech.edu>
Packages Faxes
In 47 26
Out 23 45

Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.


COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Akutagawa, Kaufman)

From: Esther Cunningham <esther@ligo.caltech.edu>

Press here for ACCOUNTS PAYABLE HISTORY DATA.

From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

From: Florence Kaufman <fkaufman@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: irena@ligo.caltech.edu (Irena Petrac)

From: Ed Jasnow <jasnow@ligo.caltech.edu>



LIGO NEWSLETTER (Beckett)

>From: Dave Beckett  <beckett@ligo.caltech.edu>

A January LIGO Web Newsletter is in production and should be ready for posting by the middle of next week.  A meeting Monday between Gary, Phil and myself identified and addressed previous obstacles to a regular publishing schedule. A powerful resolve to uphold and sustain the newsletter was borne from this meeting, any my thanks go to Gary and Phil both for their assistance.

Activities


Support (Wood)

 
Dorothy Lloyd
  • Processed the usual requisitions, invoices and receiving on-line. For more detail, see "Cost Schedule Control Systems" report by Esther Cunningham.
  • Tracked and followed up on invoice problems.
  • Reviewed and recorded payments processed by Esther for the week of January 15, on contract summary sheets and LIGO database.
  • Continued to work with Florence and Ruth on transferring encumbrances to new fiscal period.
  • Continue to monitor contract and blanket order funding levels and notify task managers when supplements are needed.
  • Jim continues to do data entry in the LIGO database and help out in both the DCC and travel areas.
Rita Torres
  • Spent lots of time this week on the SEI Mechanical Structure RFP for LLO.  The RFP file I inherited took forever to open (and save) because of an embedded graphic.  Coordinated with the DCC on drawings, did letters to proposers, prepared pdf versions for LLO.  Did change order No. 16 to Butler International.
  • FedExed the Annual Report to the NSF, did internal distribution.  Coordinated info for R. DeSalvo and the attorney.
  • Arranged an eye exam, also arranged laser safety training.
  • Ongoing activity: Pcard purchases.  I attempt to reconcile each transaction as soon as I receive notice from the Pcard staff.  Update site trips.
Irene Baldon
  • Eleven (11) new trips were started and I have nine (9) trips pending final approval before tickets can be issued.  Most of these trips required Advance Checks to be written as well as hotel and car authorization forms to be filled out and FAXed to the appropriate locations.
  • Worked on and completed eighteen (18) Expense Reports.  I have twenty (20) Expense Reports to work on and I'm holding two (2) reports that need a check from the traveler before processing.
  • The new Expense Report that I sent out a couple of weeks ago is not being used by most of our Travelers.  I ask that everyone please use this new form.  If you have any questions on its use please contact me.  If you did not save my previously sent note enclosing the New Expense Report please let me know and I'll resend it immediately.  I will be at both sites during the next two (2) weeks (Hanford Jan. 29th/30th and Livingston Feb. 8th/9th) and will be happy to work with you on either a one-to-one basis or by group.
  • Reconciled fifty-six (13) items on my P-Card this week.
  • We experienced a breach of security to one (1) of our P-Cards this past week.  The illegal use of this card was discovered almost immediately and appropriate steps were taken to correction the situation.  I caution you to be alert when using your card, especially when using it on the net.  This can occur with all cards, not just those being used for travel.
  • Prepared the Travel/Vacation Itinerary for the Week of January 22, 2001.  Performed normal recording and filing associated with Travel and Reimbursement.  Worked on several problem issues with Travel Audit in addition to the above listed issues.  Also performed miscellaneous duties as requested by various members of  the LIGO Project here at Caltech as well as from members of the staffs of each of the two (2) sites.   I continue to do MIT's travel to the sites for installation activities and also to assist them wherever possible.
Elizabeth K. Wood
  • Continued with catering preparations and other details for the NSF Review next week.
  • I continue to deal with HR.  You don’t know how lucky you are not to have to deal with HR.
  • Dealt with personnel and visa issues.

  • Criselda helped me undo a series of incorrect charges on Gary's pcard.   Each time B of A undid and then redid a transaction, LIGO was charged the usual 2.5% transaction fee even though the changes were made through their errors, not ours.

Advanced LIGO (Frey, Petrac)

From: Thomas Frey <tfrey@ligo.caltech.edu>

Progress Period from 01.19 to 01.25

Accomplishments:

Schedule 01.26 to 02.01:

WBS 1.4.1.2   Project Controls (LIGO Construction)



Reports (Lindquist)

Nothing to Report.



Change Control/Contingency (Lindquist)

The following Change Requests have been submitted:
 

CR-000018 WBS 1.1.4 Curbing for Service Roads at Livingston G. Stapfer
CR-000019 WBS 1.2 Additional Lab Equipment D. Coyne
CR-000020 WBS 1.1.4 Staging Building and Renovations to Existing Building--Livigston F. Asiri
CR-010001 WBS 1.1.4 Return of Unused Construction Budget To Contingency F. Asiri

Change Request CR-010001 will return approximately $240,000 to Contingency for budget unused in Civil Construction (WBS 1.1.4).  The remaining budget includes $200,000 in account 5D522 to cover A&E costs at Hanford (per approved Change Request CR-000017) plus $2,000,000 in account 5D532 to cover the Storage and Staging building in Livingston (per CR-000020) and the  remaining A&E work.  The analysis is based on Actual Costs through the end of December 2000.  The amount returned to Contingency is somewhat below previously advertised amounts because costs in excess of $200,000 were booked during December for the paving of the roads along the Beam Tube in Hanford, and these outstanding commitments had not been properly factored into our thinking.

Florence has inquired of Finance as to whether there are any Construction amounts still hanging around in the Retention accounts.  They have not yet responded.  While we do not expect there to be any significant retention amounts (other than for currently active subcontracts), it is possible that there might be additional favorable adjustments to these accounts.

Press for the latest Contingency Needs Projection.


COST SCHEDULE CONTROL SYSTEMS (Duncan, Akutagawa)

From: Kris Duncan <kris@ligo.caltech.edu>

From: Cindy Akutagawa <cindy@ligo.caltech.edu> Reminder: An updated list of all OPEN LIGO account numbers has been posted on the LIGO internal bulletin board. Please use these lists when you need a LIGO account number (or make yourself a printed copy for quick references). Please note that the FY00 LIGO Operation account numbers expired on November 30, 2000, and that the new account numbers can be found at:

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: Ed Jasnow <jasnow@ligo.caltech.edu>

From: irena@ligo.caltech.edu (Irena Petrac)

Quality/Safety (Tyler)

>From: Bill Tyler <tyler@ligo.caltech.edu>

LIGO Hanford Observatory (LHO) Operations (Raab)


NO REPORT RECEIVED THIS WEEK.


LIGO Livingston Observatory (LLO) Operations (Coles)



 

Late news: We have successfully locked the vertex Michelson using the LSC controls. On Thursday, we opened the gate valve on the X-arm and are now working on the lock of a 4 km long arm as a Fabry-Perot cavity. We see nice fringes, but have lots of work to do to understand the situation and tune appropriately.

LLO high-power lab work: Set up of the high-power lab at the X-end station at LLO progressed this week. (Previous work there was stopped due to the ceiling leak, which is now fixed.)The optical table was moved from the receiving area to the enclosed area inside the room. Currently the table is sitting on the custom-made carts. Its original legs are slightly damaged and are being prepared for shipment to the manufacturer.The 10W laser was set up on the table. At the moment it is not operating. Standard actions have been taken to meet the LIGO laser safety requirements necessary for operation of this laser (warning light was installed, a laser curtain is in place, SOP is submitted, etc.) Optical components from Thorlabs, New Focus, and CVI have been received and made ready for installation in the high-power lab. (Sany Yoshida)

General Computing, LDAS, and CDS computing: Almost ready to transfer web services to our new server. This will require changing dns entries. Will be ordering the GC AIT2 tape library Thursday so it can be here for the engineering run. We will move the GC EX-220 tape library off of decatur to another machine so that the GC backups can be performed on a different machine. Testing 802.11b networking is in progress here in three laptops. This will be usefull for conferences etc. Installed replacement ram into linuxbox1. Will install RH 6.2. Shannon installed the tape library hardware over the previous weekend. He will install the software this week or this weekend. Diagnosing a possible memory leak on London (cds to gc gateway). After a few weeks of uptime London runs out of swap space. (Shannon Roddy -
Tom Evans)

Other: We have two new employees at LLO, Ken Watts and Joe Langdale. Both began work as Operations Specialists within the last two weeks. Cheithan Paramesawaya has also returned to work following the renewal of his practical training certificate. Students from three fifth grade classes at Episcopal School of Baton Rouge journeyed to LIGO on Tuesday, Wednesday, and Thursday for science lessons on the properties of light. Special thanks to Peter King for being Mr. Wizard for one of the classes!
 



 

Detector/Technical Support (Whitcomb, Coyne)



 

Installation& Commissioning:
Hanford
Livingston
Other Science/EngineeringActivities:
Design/Analysis/Fab
Issues/Concerns
Seealso the Installationweb page

1.1 LHO INSTALLATION & COMMISSIONING

2km Commissioning

Matt Evans, Nergis Mavalavala,Richard McCarthy, Dave Barker
The main thrust of commissioning effort this week was to continue with interferometer locking. Last week we reported lock stretches of order seconds, where the main breakthroughs were fine tuning of the sensor gains and  lock acquisition parameters and disabling of all angular feed back to the ifo optics (except ETMs) from the OSEM sensors. We then addressed two different problems:
(i) Increasing the frequency of acquiring lock
We noticed that the ~ seconds lock stretches were acquired not more thana few times an hour. The reason for this was believed to be that our armcavity transmitted power photodetectors are very noisy before the power builds.To circumvent this noisiness we were smoothing the signals to the point ofhaving nearly intolerable delay. To get around this dynamic range issue,we split the transmission QPD signal into a high gain path (for low arm cavitypower) and a 10x lower gain path (for full power build up, which is about500 times the single arm power on the QPDs). This led to about a ten-foldincrease in the frequency of lock events.
(ii) With more lock events to work with we next turned out attention to extending the duration of the lock streteches. The observed fluctuations of the antisymmetric port (and correspondingly the arm cavity powers) were very large. To mitigate these we got the wavefront sensor at the antisymmetric port working. This reduced the antisymmetric port power fluctuations by a factor of  4to 5 and the interferometer lock durations are now as long as 40+ minutes.

We have begun work on commissioning a wavefront sensor at the reflectionport and are now working with Rolf on upgrades/fixes to the LSC and ASC digital control systems to remedy some bugs that were observed during the lock acquisition activities above.

Rolf Bork
Working on tracking down cause of NSPOB signal jump when LSC test pointsare selected.  They had reported other TP problems in both LSC and ASC,but those disappeared on reset of the test point manager.  I've addeddiagnostic code to the LSC front end such that it reports all Excitation/Testpoints that it thinks are selected and reports these back to an operatordisplay.

Continue to have problems with lscMonitor task (which provides LSC readouts to operator displays) randomly crashing on floating point exceptions (FPE).  Barker and I are working to add FPE handlers to determine cause and prevent code from locking up.

Core Optics

Doug Cook, Mark Lubinski, Hugh Radkins, Dennis Coyne, Rick Graff,John Worden, Kyle Ryan, Gerardo Moreno
The installation and alignment of ETMX for the 4 km interfrometer was completed, and the vacuum system closed up and pumping started. Staging for the LVEA installation next week has started.

COS

Mike Smith, Ken Mailand, Ken Mason, Hugh Radkins, Doug Cook, Dennis Coyne
The ETMx telescope and beam dump were installed and aligned with the COSautocollimator. The transmitted beam was sent out through the chamber windowto the ETM transmission monitor. The arm cavity baffle was installed andaligned. It was necessary to move the arm cavity baffle outer support framecloser to the optical lever port than the designed position, in order forthe support frame hole to clear the optical lever beam; the reason for thisis being investigated.

1.2LLO INSTALLATION & COMMISSIONING

Commissioning

Rai Weiss,  Mike Zucker, andeveryone at LLO
1) With the detection tables functioning and the RF system in operation,the unrecycled Michelson interferometer was locked using the digital lengthsensing and control. The lock was made by using the error signal derivedfrom the antisymmetric port and controlling the antisymmetric motion of thetwo input test masses. Preliminary measurements of the loop gains and displacementspectrum were made.

2) Preparations have been completed (Thursday noon) to open the x arm gate valves and attempt to lock the 4km cavity.

A 3 x 10^-4 torr liter/sec leak opened up on the y arm beam tube in the mid building gate valve annulus pumping system. The leak was opened during the time workmen were removing scaffolding in the mid building. The leak wasopened for about a day and deposited about 3/4 of a torr liter of water inthe 4 km tube, an insignificant amount relative to the 400 torr liters allowed. The leak was discovered in the pressure record. The next day it was found and repaired.

David Shoemaker
Worked on diagonalization of the core optics suspension controllers at LLO. Mostly was useful to get the setup in place and to help Warren and Szabidig into the question; I think it takes a few iterations and some more alignment of optical levers to get a useful number, but they have been working on it.

PSL

Peter King
I had helped Rich fix some minor problems with the RF distribution system and perform RF field strength measurements inside the PSL enclosure.

The alignment of the frequency shifting acousto-optic modulator was tweaked, along with the alignment into the reference cavity in order to improve things a little.  This was done to increase the light onto the RF photodetector in order to get more gain the frequency stabilization servo as the laserpower is decaying.

Joe Kovalik and I made measurements of the in-the-loop and out-of-loop PSL frequency noise.  The measurements are on entered on the ilog for 01/22/01.

2.0 OtherEngineering and Scientific Activities

2.1 Design/Analysis/Fab

Optical Metrology

Helena Armandula, GariLynnBillingsley
Measurement of LIGO 1 spares continues

Optics Modelling

Erika d'Ambrosio
Started the conversion of the "dual-recycling model simulation FFT-code"(written for the Paragon machine) to the MPI standards. Though the same jobhas been done for the "power recycling model" by Dr. Rick Jenet difficultiesarise from the new files dealing with the GW sidebands. There are detailshard to catch concerning the way variables are allocated and even how sometags are initialized for the messages to be distributed.

LSC

Rich Abbott, Mohana Mageswara, Flavio Nocero
Prepared short term (2 month) plan for LSC related tasks.  Continuing to receive boards from board house to clean up old problems.

We are preparing a test to further improve the RF susceptibility issues associated with the RFPD and to find ways to reduce any remaining leakage from the frequency distribution system.

PSL

Peter King
The new scheme for mounting the phase-correcting Pockels cell, using a goniometer, turned out to be much harder than I had anticipated. Part of the problemis because the beam height of the components inside the laser is only 2.35in. so I was hoping that any height adjustments could be made with shim material.  This became impractical.  As a result I have redesigned the whole mounting scheme to include a four-axis tilt stage and the goniometer.  The phase-correcting Pockels cell will now be held upside down inside the laser.  Testing of this scheme will hopefully take place next week after some plates arefabricated.

Rick Karwoski, Paul Russell,Ben Abbott

New OSEM Heads

Janeen Romie

Digital Suspensions

Rolf Bork
Completed servo code to point of being able to test performance to determine system hardware requirements.  It looks like one PentiumIII CPU canhandle the servo calcalutions and associated I/O and data acquisition forall the optics in an IFO at 2048Hz in 50% of the allotted time.

Jay Heefner

GDS

Daniel Sigg
Continued with the new client data interface for the DTT (mainly GUI stuff so far).

DMT

John Zweizig
This week I worked on making the DMT state available for Szabis web pageand documenting the meaning and actions to be taken for error messages produced by the data pusher. I also made the error messages a bit more intelligent to simplify the interpretation of the messages.

Data Acquisition

Sander Liu
Received couple of 5 volt, 25 amp linear power supplies form Kepco. The components were assembled into a single +/- 5 volt unit and tested. It will be shipped to MIT as soon as we can find a suitable container.

2.2 IssuesConcerns

nothingnew

40 Meter Interferometer (Weinstein)




Thermal Noise Interferometer (Libbrecht)


This week we have continued characterizing our system.  We have calibrated
the fast input on one of the OSEM controllers, as connected to a test mass,
studied the PZT response of the laser, and repaired the fast input on a
second OSEM controller.  We have also instituted more clean-room practices
in preparation for opening the chamber, once the characterization is
complete.
 

Congratulations to Shanti for passing his candidacy exam!


LASTI (Zucker)


No progress this week. All on travel.


Data Analysis and Computing (Lazzarini)



 

Simulation and Modeling (Yamamoto)

>> Effect of mirror angular fluctuation on the lock acquisition
(Biplab)

* In order to reproduce large power fluctuations in Han2k locked
  states (as was shown by Bill Kells in his Monday talk), I tried
  two simulation runs (i) 3.4e-7 rad-rms ang. fluctuations in end
  mirrors keeping ang. fluctuations in central hall mirrors at a
  low level (of the order of 1e8 rad-rms) (ii) Just the reverse:
  large ang. fluctuations in central hall mirrors and low level
  of ang. fluctuations in end mirrors.
  Both cases achieve locked states of short durations with large
  power-fluctuations.
  [A value of 3.4e-7 rad-rms is consistent with what Daniel reported
  in Director's review Mar'00.]

* Putting large ang. fluctuations (3.4e-7 rad-rms) in ALL mirrors
  does not allow the system to go to stage 4.
  If one considers that angular fluctuations are at same level in all
  mirrors, the upper limit for achieving stage 4 is about 4e-8 rad-rms.
  By reducing ang. fluc. in recycling mirror to a lower level, thus
  reducing fluctuations in resonant sideband power in stage 2, one can
  raise this limit by a factor of about 2.
  Once in stage 4, not much of power-fluctuations (< 5%) are observed
  in all these cases.

* So, it seems either the central hall mirrors or the end mirrors
  (but NOT both) are having too much of fluctuations.
  Considering the fact that the control of only end mirrors using
  only one WFS at dark port [Ref: detector elog by Matt, Nergis 1/22]
  could reduce power fluc. and elongate the locked states, it seems
  the current state of Han2k is more like situation (i) described above.

* I considered modes up to order 1 only. I also ran with modes upto
  order 3 but that did not change the above results and guesses.

>> Mechanics model for advanced LIGO
(Virginio)

* The quad-pendulum model using MSE has been debug further.

* Including of the violin motion of the wires suspending the bottom
  mass is going on now.

* Future work plan will be discussed when Peter visits Caltech next week.

>> Parallelization of the simulation engine
(Tavio, Matt, Hiro)

* A final answer from SUN engineer came to confirm our observation that
  the delay of the order of 50 microseconds when switching to other
  threads is a harware/OS limitation and there is no way to reduce it.

* Various different methods to speed up the switching of tasks between
  thread have been tested, but we could not find any way to reduce the
  overhead.

* A systematic study of the overhead due to the thread and queuing
  mechanisms have been done for a various different inputs under different
  use of threads.

* The overhead due to the threading and queuing mechanism is, roughly
  speaking, constant overhead of 50-100 microseconds + 2.5 microseconds
  per node which will be pushed into and poped out of the queue.

* The testbed is close to be completed, and the develepment of the algorithm
  will follow.

>> ALFI
(Ed, Bruce)

* A new utility "boxjoiner" has been written to create one single box file
  out of a multiple box inputs. This is to make it easy to use server
  computers.

* Parameter windows is being updated and improved, including the support
  of included files.

* Automation of a new release of alfi is being pursued.

* Transition to the latest release of xwWindow is in progress. This is
  necessary to resolve a conflict of the latest SUN OS and the previous
  version of xwWindow.

LIGO Data Analysis System

  • Software Systems (Blackburn)

  • The MPI MDC officially ended on Friday with a resounding successful
    completion mark from the leads (Patrick Brady of UWM and Kent Blackburn
    of Caltech). A few minor tests which did not impact any later tests and
    check pointed such as documentation and ilwd file read/write errors
    need more work but all of the big tests involving the search for signals
    in simulated data using an inspiral search engine and an excess power
    search engine cast into wrapperAPI compatible dynamically loaded shared
    objects were a total success. In fact, the code was left running all
    weekend, applying 1000 templates per node on each of more than 1000
    data segments with only two terminated jobs due to what we suspect is
    a filesystem caching problem in combination with the wrong choice of
    ssh shell options (which has now been corrected and tested). It was
    a wonderful feeling seeing LDAS drive search codes on the development
    Beowulf cluster so successfully. Everyone in the LDAS development team
    should feel very proud! See: http://www.ligo.caltech.edu/~lazz/MPIMDCPhotos/
    See also the iLog log we have set up for the
    MDCs: http://blue.ligo-wa.caltech.edu/ilog/index.html

    After the MDC, LDAS turned to formulating a new release of the software
    which captures all the necessary changes that were identified during
    the week and a half of MDC tests. This new release should be out in
    about two weeks. New versions of the LAL and LALwrapper software will
    also be released to include all the changes brought about by the MDC
    as well as their regular compliment of code development.

    LDAS will be working to incorporate a much more fully developed version
    of the frameAPI and the frameCPP library in this next release which has
    support for a none trivial set of features of the frame specification
    which have not been exercised by the framebuilder or LDAS to date. This
    includes support for complex data and strings, as well as processed data
    and simulated data in frames.

    The controlMonitorAPI continues to mature. Several issues of security
    in the client component were identified and corrected this week. The
    client is also now able to run outside the LDAS martian network. A
    request has been made to enhance the temporary tapescript control
    feature of the controlMonitorAPI in anticipation of the next engineering
    run. There is also support now for monitoring the state of the LDAS
    beowulf cluster.

    The conversion to Unified Data Type classes continues in the
    dataConditionAPI
    this week. The window, psd and firLP classes are being focused on. Also the
    ingestion of LDAS native ilwd data into UDT data has nearly been completed.
    The reverse process taking UDT into ilwd is also being sorted out.

    The LDAS database mock data challenge is still on hold pending Peter
    Shawhan's
    return from jury duty. It is expected to resume in earnest next week.

    Over forty new problem reports were generated during last weeks MDC. Almost
    all of these have now been analyzed or closed out. We have seen a tremendous
    increase in the flux of problems through the problem tracking system with
    the recent LDAS release and the MDC. It has been extremely valuable as a
    tool for tracing software issues during such a dynamic phase in our code
    development.

  • Hardware Systems (Anderson)

  • Continuing discussions with vendors for the first large LDAS hardware
    procurement, which includes ~30TB of disk and the first beowulf clusters
    at LHO and LLO.

    Solaris UFS logging enabled on the main LDAS NFS/CVS/HTTP server and
    the entire ldas-dev system.

    Upgrade of the general computing network on the 6th floor of Millikan
    to allow additional network connections in the large conference room.

    Single mode fibre sent to LHO in anticipation of LDAS moving the bulk
    of the servers from the mass storage room to the staging building.

    Identification of additional floor space for LDAS at LLO that will
    allow LDAS to expand beyond the currently allocated space in the
    mass storage room.

    Finished commissioning of the ldas-test system which is now generally
    available for use as an LDAS system with: dataserver, metaserver, beowulf,
    and 8 dual processor compute cluster nodes.

    (Shannon/LLO)
    Installed replacement ram into linuxbox1.  Will install RH 6.2
    this evening or in the morning.
     Installed the tape library hardware over the weekend.  I
    still have to install the software this week or this weekend.

    (Larry/CIT)
    Updated DNS and NIS+ tables for new LDAS name.
    Spent a number of hours on the phone (mostly on hold) getting
    quotes and configurations for the PC purchases.

  • Data Analysis Activities
  • Shawhan:

    LIGOtools now includes version 0.6 of LAL (the LIGO/LSC Algorithm
    Library), as well as the FFTW package.  In addition, a bug was
    fixed which had affected viewing of off-line data.

    A.Vicere', 18-25 January 2001
    - Meeting with A.Giazotto and G.Cella to work on the schedule for the
       next network analysis meeting
    - Contacts with F.Ricci, responsible in VIRGO for the Grid project, to start
       common work on the definition of a "use case" for the LIGO-VIRGO
       participation to the USGrid-EUGrid collaboration.
    - Contacts with F.Barone, responsible in VIRGO for the environmental
       monitoring, to understand which channels can be included in the
       reduced data set to be exchanged

    Charlton:

    Wrote up the derivation of the general FCT expression and error estimate.
    Lingchin has taken over control of the code from Rick and next I'll
    switch over to that code for my heirarchical search prototype and add more
    tests to Rick's code to check numerical accuracy.

    General Computing (Wallace)

    MIT:
    Nothing to report.

    Livingston:
    (Shannon)
    - Almost ready to transfer web services to our new server. This
    will require changing dns entries.
    - Will be ordering the GC AIT2 tape library this evening so it can
    be here for the engineering run.
    - We will move the GC EX-220 tape library off of decatur to another
    machine so that the GC backups can be performed on a different machine.
    - Testing 802.11b net networking here in three laptops.  This will
    be useful for conferences etc.

    Hanford:
    (Christine)
    - A read only copy of the LHO elogs is now available at
    http://apex.ligo-wa.caltech.edu/ilog/.  Everyone uses the username
    "reader" and password "read-only".  Thanks to Bruce Sears for setting
    this up.  The elog files are being copied from the CDS network to apex
    daily.
    - Last week I attended an Advanced PC Maintenance course.  I learned a few
    good things about BIOS settings, using the Windows registry, optimizing
    memory and CPU, and security features in Windows 98.
     

    [Bruce Sears]
    * (BS) Hanford Ilog Mirror:
            - LHO ilog mirror setup has been completed.  Actual updating
              of log files to this server is now up to the LHO systems people.

    CIT:
    (Lisa)
    - Rebuilt 3 Ultra10's and 2 ultra1's with solaris 8.
    - Recovered files off Bill Kells' laptop
    - Am wrapping up the switch over to the new modem pool.  I would like to do that
    on Monday.
    - Went to Laser safety training.
    - Worked with Larry on getting the tape robot tested for general backups.
    - Ordered new software pkg. for backups.

    (Sam)
    -Fixed laptop
    -Help dave beckett with a cd problem
    -Helped Gina with a few PC issues.
    -Looked at lori's computer
    -Looked at florence's computer
    looked at other stuff
    didn't sleep
    did homework
    went to lab
    did research
    played basketball

    (Barbara)
    1. Worked on further changes to the CostBook
    - reworked web forms, queries, calcs etc to look up the Location in the WBS
    table rather than entering it on each of the forms.
    - fixed the calculation for the G1-G4 items.
    - reworked the Risk Override field so it can be 0% or a negative percent.
    - added Location to the WBS add/edit forms.
    - reworked the procedure for calculating the item amount to accommodate all
    of the above changes.
    I still have to develop forms for C and I as MIT resources and to
    incorporate G6 somewhere.  And the cost code lookup has to be updated since
    there will be only one cost code per WBS.

    2. Worked on the web page for Data & Computing Groups contacts.  Had
    problems figuring out how to capture the mail aliases file onto the LDAS
    servers but Stuart came to my rescue.

    3. Made web site changes for SURF, the data analysis white paper, meetings.

    4. Attended DCC planning meeting.

    5. Help Ed Chargois with some file maintenance.

    (Suresh)
    -Installed Autocad 2000i in two PCs of west bridge.
    -Did some cabling work in Millikan 6th floor conference room.
    -Installed some windows applications in a new PC to be used by Mike Smith.
    -Created some e-mail aliases for LDAS group.

    (Larry)
    - Worked a number of PC issues. Most have been resolved and those that have
    not have been turned over to other people.
    Just as a note at this point we do not purchase CD players, speakers or any
    other equipment for entertainment purposes. Many times those items are part
    of the pkg. of the item being ordered so the people receiving that equipment
    get lucky. Please, do not ask for support are special ordering of equipment
    so you can play music on a computer.
    When using someone else's computer please do not change the settings on the unit
    and try to contact the main user before using their workstation.
    Update your virus files. There are some new viruses out that really cause
    problems. This includes those that are using Mac units.
    - Placed a number of orders for equipment and now trying to track items down
    that should have arrived. Hopefully, the UPS replacements will arrive before
    the end of the month so we can swap the network UPS out the first of next month.
    - Worked a few DCC issues with Linda.
    - Assisted in taking care of a few Autocad problems.
    - Installed tape robot and working on backup tests with Lisa.
     


    LIGO II/Advanced R&D (Sanders)


    From Helena:
     

    Advanced LIGO Coatings
    A visit to evaluate MLD's coating facilities in Oregon has been scheduled for tomorrow, Thursday 25th.

    From: GariLynn Billingsley <Billingsley_G@ligo.caltech.edu>
    Subject: Weekly Report - Billingsley
     

    A draft polishing specification for a 25 cm sapphire substrate has been completed and circulated for comment.
     

    From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>

    Alessandro
    Linear electronics, all parts now in, will be ready and shipped end of
    the week.
     

    Edwin, Tatsuo
    Measured 11 mini-GAS springs for selection for the top mass of the
    multiple pendulum.
    Can tune at 1 Hz easily, the load spread is narrow enough, it will be
    easy to chose matched quartets for each mass.
     

    Virginio, Akiteru
    Preparing top mass assembly, need masses for pre-tensioning the four
    mini-GAS springs and keep them vertical.  Preparing wire clamps.
     

    Akiteru
    LVDT controls achieved on TAMA SAS, small low frequency oscillation at
    10 mHz, need to optimize gain to avoid this instability which happens at
    the switchover between the DC and the AC controls.  As soon as solved
    will start the Accelerometer diagonalization.
     

    Kenji
    IP counterweight curves look good,  can move notch at will but, found a
    pitfall. The wire suspended shaker, replacing the oil bearing, introduce
    a frequency shift difficult to quantize.  Look for a way to renormalize
    the measurement to optimize the counterweight.  Will try to measure and
    subtract the wire suspension induced tilt, it should work.
    Filter 0 tuned to bistability in order to introduce the control spring.
    The filter  returns to stability with the control spring added K.  The
    spring is magnetic and not compatible with the vertical  voice coil
    magnet but received already SS replacement,  will install next.
    Now can safely trim the other F0 blades.
     

    Digital Electronics (IDED)
    Digital cards assembled, under test, missing DAC chips now promised by
    Analogue Devices by mid February
    DME crates ready to ship
    NIM crates due beginning February
     

    Ric
    Shipping crates in construction, will be ready during the week.  Blades
    and coils either will be delivered  by Fed Ex today or Monday.  Shipment
    clamps to be shipped tomorrow.
     


    For additional information about this report, contact sanders@ligo.caltech.edu