|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The LIGO Executive Committee Agenda for Monday January 29, 2001 will be:
CANCELLED DUE TO NSF REVIEW
Late news from LLO, the Michelson locks!
And the LHO 2K locks better and better in full recycled configuration!
And a successful Mock Data Challenge!
to: LSC executive committee
from: R. Weiss January 23, 2001
concerning: Notes from the LSC Executive committee phone call 01/19/2001
A new iteration of the Data Analysis White Paper will be made by a committee
consisting of Stuart Anderson, Al Lazzarini, Tom Nash, Keith Riles,
Alan
Weinstein and Alan Wiseman (chair). The White Paper needs
to articulate a long and short range scientific program and the needs
of the field
for the future. One of the suggestions made at the meeting is to remove
the
work lists from the body of the paper. First meeting of the group is
scheduled
for Jan 23.
The proposal to hold an election for the spokesperson and various
of the LSC committee chairs was discussed. The outcome of the discussion
and
comments sent around prior to the meeting is that it would be best
not to hold
an election for any position other than spokesperson. The committee
chairs
are determined by the spokesperson in consultation with the nominations
committee. It is also the spokesperson's job to determine if committee
chairs
want to continue. I will call all committee chairs to determine their
situation
before the next LSC executive meeting. As to the election for Spokesperson,
if the
nominations committee agrees, we will defer this for another year.
The nominations
committee should report on their deliberations at the next LSC Council
meeting.
Alan Wiseman reported on the changes in the organization of the software
coordination. A software change control board consisting of Stuart
Anderson, Jolien Creighton and John Zweizig will be constituted. The
old
software coordination committee will become a software advisory committee
to
the Software Coordinator. The members of the advisory committee are
Sam Finn, Maria-Alessandra Papa and Tom Prince. The CCB will deal primarily
with technical issues while the advisory group will monitor the mock
data
challenges, oversee the activities of the CCB and advise the Software
Coordinator.
Meetings being held by the chairs of the upper limit groups have been
going on
since the GWDAW meeting last December. The meetings are designed to
establish
the common software and hardware requirements of the different upper
limit
groups and guide the groups in developing their analysis proposals.
Alan
Wiseman in discussions with Barry and members of the executive committee
is
preparing some guidelines for the upper limit groups. The principal
software
to be used by the upperlimit groups is the LDAS since this will give
practice with the system designed to do the LIGO data analysis. With
the
first real coincidence runs now scheduled for September 2001, the conflict
between LDAS being ready and the needs of the upper limit groups has
been
somewhat alleviated. The major function of the Laboratory will be to
provide
a "clean" pipeline for the data.
The major purpose of the upper limit groups is to test the software
and to
write preliminary upper limit papers. The results of the upper limit
analyses
should become available in January or February of 2002 when the LIGO
II proposal
is presented to the NSF and colloquia are held at the NSF.
A discussion of the types of issues to be brought to the CCB followed.
Such
issues as changes in the Frame format, changes in the LAL standard
and the
style of Data Tables in DB2 are examples. Daniel Sigg raised the question
of
CCB hearings on internal operations software such as that used in
detector diagnostics and on line detector analysis. (I believe) it
was decided
that such software does not come under LSC coordination being part
of the
detector operations.
Gary Sanders gave a report on his trip to VIRGO to discuss coatings
which then
resulted in much broader discussions concerning the collaboration between
LIGO
and VIRGO. I cannot do justice to Gary's report but summarize the main
points.
1) The coating facilities in Lyon look adequate to do the coatings for
LIGO II.
Although there is no demonstrated record of accomplishment of uniformity,
low absorption and low scattering for very large optics, the hope is
that the coating of the
VIRGO optics in 2002 will provide the needed experience. Lyon is a
viable
option for LIGO II along with several others that are still being investigated.
2) If the coatings are done at Lyon they may constitute an investment
in a
broader LIGO/VIRGO collaboration.
3) VIRGO is currently going through a major reorganization. The European
Gravitational - wave Observatory (EGO) is becoming the operational
leg
of the VIRGO project with power of the purse and project management.
A
subgroup of the EGO is the scientific effort represented by the old
VIRGO
management of Brillet and Giazotto who have been given the task to
pull together
the scientific program of EGO.
4) Brillet, Giazotto and the group at CNRS including Davier, Dupont
and Giacobino are eager
to make more formal couplings to the LIGO project and are talking of
operating
LIGO and VIRGO as a single observatory with a uniform publications
policy.
5) Major questions raised are whether it is in the best interest of
the field
to make bilateral agreement between LIGO/VIRGO. How to involve the
LSC in the
collaboration. How the new initiatives intersect with the goals and
activities
of GWIC.
6) The general response of the LSC executive committee was positive
to the
VIRGO overtures and urged that the details be explored. It was
suggested that the forthcoming LIGO/VIRGO network analysis meeting
on Feb 11
actually try to incorporate the VIRGO project in the Engineering runs
as a way
of developing confidence and generating useful techniques. Correlation
of
PEM signals was considered an interesting and easy initial step. It
should be
possible to make special arangements for VIRGO scientists to become
involved in
the engineering data analysis by bringing their participation to the
executive committee as we have done for non-LSC people.
The next LSC executive committee meeting will be at 11 AM EDT Friday
February 16, 2001
WBS 1.2 LIGO Operations--Administration
The next site telecon is scheduled for Thursday,
February 1, 2001. The list of current actions revised to reflect
open actions assigned through January 25, 2001 may be found at
ACTION
LIST.
From: Ed Chargois <chargois_e@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .
ACCOMPLISHMENTS
| Packages | Faxes | |
| In | 47 | 26 |
| Out | 23 | 45 |
Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS PAYABLE HISTORY DATA.
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
From: irena@ligo.caltech.edu (Irena Petrac)
Activities
Support (Wood)
Progress Period from 01.19 to 01.25
Accomplishments:
WBS 1.4.1.2 Project Controls (LIGO Construction)
Nothing to Report.
The following Change Requests have
been submitted:
| CR-000018 | WBS 1.1.4 | Curbing for Service Roads at Livingston | G. Stapfer |
| CR-000019 | WBS 1.2 | Additional Lab Equipment | D. Coyne |
| CR-000020 | WBS 1.1.4 | Staging Building and Renovations to Existing Building--Livigston | F. Asiri |
| CR-010001 | WBS 1.1.4 | Return of Unused Construction Budget To Contingency | F. Asiri |
Change Request CR-010001 will return approximately $240,000 to Contingency for budget unused in Civil Construction (WBS 1.1.4). The remaining budget includes $200,000 in account 5D522 to cover A&E costs at Hanford (per approved Change Request CR-000017) plus $2,000,000 in account 5D532 to cover the Storage and Staging building in Livingston (per CR-000020) and the remaining A&E work. The analysis is based on Actual Costs through the end of December 2000. The amount returned to Contingency is somewhat below previously advertised amounts because costs in excess of $200,000 were booked during December for the paving of the roads along the Beam Tube in Hanford, and these outstanding commitments had not been properly factored into our thinking.
Florence has inquired of Finance as to whether there are any Construction amounts still hanging around in the Retention accounts. They have not yet responded. While we do not expect there to be any significant retention amounts (other than for currently active subcontracts), it is possible that there might be additional favorable adjustments to these accounts.
Press for the latest Contingency Needs Projection.
From: Kris Duncan <kris@ligo.caltech.edu>
The financial reports on the web provide supporting
detail.
http://docuserv.ligo.caltech.edu/~fireport
http://docuserv.ligo.caltech.edu/~finance
From: Ed Jasnow <jasnow@ligo.caltech.edu>
NO REPORT RECEIVED THIS WEEK.
Late news: We have successfully locked the vertex Michelson using the LSC controls. On Thursday, we opened the gate valve on the X-arm and are now working on the lock of a 4 km long arm as a Fabry-Perot cavity. We see nice fringes, but have lots of work to do to understand the situation and tune appropriately.
LLO high-power lab work: Set up of the high-power lab at the X-end station at LLO progressed this week. (Previous work there was stopped due to the ceiling leak, which is now fixed.)The optical table was moved from the receiving area to the enclosed area inside the room. Currently the table is sitting on the custom-made carts. Its original legs are slightly damaged and are being prepared for shipment to the manufacturer.The 10W laser was set up on the table. At the moment it is not operating. Standard actions have been taken to meet the LIGO laser safety requirements necessary for operation of this laser (warning light was installed, a laser curtain is in place, SOP is submitted, etc.) Optical components from Thorlabs, New Focus, and CVI have been received and made ready for installation in the high-power lab. (Sany Yoshida)
General Computing, LDAS, and CDS computing: Almost ready to transfer
web services to our new server. This will require changing dns entries.
Will be ordering the GC AIT2 tape library Thursday so it can be here for
the engineering run. We will move the GC EX-220 tape library off of decatur
to another machine so that the GC backups can be performed on a different
machine. Testing 802.11b networking is in progress here in three laptops.
This will be usefull for conferences etc. Installed replacement ram into
linuxbox1. Will install RH 6.2. Shannon installed the tape library hardware
over the previous weekend. He will install the software this week or this
weekend. Diagnosing a possible memory leak on London (cds to gc gateway).
After a few weeks of uptime London runs out of swap space. (Shannon
Roddy -
Tom Evans)
Other: We have two new employees at LLO,
Ken Watts and Joe Langdale. Both began work as Operations Specialists within
the last two weeks. Cheithan Paramesawaya has also returned to work following
the renewal of his practical training certificate. Students from
three fifth grade classes at Episcopal School of Baton Rouge journeyed
to LIGO on Tuesday, Wednesday, and Thursday for science lessons on the
properties of light. Special thanks to Peter King for being Mr. Wizard
for one of the classes!
| Installation&
Commissioning:
Livingston |
Other Science/EngineeringActivities:
Issues/Concerns |
Seealso the Installationweb page
We have begun work on commissioning a wavefront sensor at the reflectionport and are now working with Rolf on upgrades/fixes to the LSC and ASC digital control systems to remedy some bugs that were observed during the lock acquisition activities above.
Rolf Bork
Working on tracking down cause of NSPOB signal jump when LSC test pointsare
selected. They had reported other TP problems in both LSC and ASC,but
those disappeared on reset of the test point manager. I've addeddiagnostic
code to the LSC front end such that it reports all Excitation/Testpoints
that it thinks are selected and reports these back to an operatordisplay.
Continue to have problems with lscMonitor task (which provides LSC readouts to operator displays) randomly crashing on floating point exceptions (FPE). Barker and I are working to add FPE handlers to determine cause and prevent code from locking up.
2) Preparations have been completed (Thursday noon) to open the x arm gate valves and attempt to lock the 4km cavity.
A 3 x 10^-4 torr liter/sec leak opened up on the y arm beam tube in the mid building gate valve annulus pumping system. The leak was opened during the time workmen were removing scaffolding in the mid building. The leak wasopened for about a day and deposited about 3/4 of a torr liter of water inthe 4 km tube, an insignificant amount relative to the 400 torr liters allowed. The leak was discovered in the pressure record. The next day it was found and repaired.
David Shoemaker
Worked on diagonalization of the core optics suspension controllers
at LLO. Mostly was useful to get the setup in place and to help Warren
and Szabidig into the question; I think it takes a few iterations and some
more alignment of optical levers to get a useful number, but they have
been working on it.
The alignment of the frequency shifting acousto-optic modulator was tweaked, along with the alignment into the reference cavity in order to improve things a little. This was done to increase the light onto the RF photodetector in order to get more gain the frequency stabilization servo as the laserpower is decaying.
Joe Kovalik and I made measurements of the in-the-loop and out-of-loop PSL frequency noise. The measurements are on entered on the ilog for 01/22/01.
We are preparing a test to further improve the RF susceptibility issues associated with the RFPD and to find ways to reduce any remaining leakage from the frequency distribution system.
Rick Karwoski, Paul Russell,Ben Abbott
Jay Heefner
This week we have continued characterizing our system. We have
calibrated
the fast input on one of the OSEM controllers, as connected to a test
mass,
studied the PZT response of the laser, and repaired the fast input
on a
second OSEM controller. We have also instituted more clean-room
practices
in preparation for opening the chamber, once the characterization is
complete.
Congratulations to Shanti for passing his candidacy exam!
No progress this week. All on travel.
* In order to reproduce large power fluctuations in Han2k locked
states (as was shown by Bill Kells in his Monday talk), I tried
two simulation runs (i) 3.4e-7 rad-rms ang. fluctuations in
end
mirrors keeping ang. fluctuations in central hall mirrors at
a
low level (of the order of 1e8 rad-rms) (ii) Just the reverse:
large ang. fluctuations in central hall mirrors and low level
of ang. fluctuations in end mirrors.
Both cases achieve locked states of short durations with large
power-fluctuations.
[A value of 3.4e-7 rad-rms is consistent with what Daniel reported
in Director's review Mar'00.]
* Putting large ang. fluctuations (3.4e-7 rad-rms) in ALL mirrors
does not allow the system to go to stage 4.
If one considers that angular fluctuations are at same level
in all
mirrors, the upper limit for achieving stage 4 is about 4e-8
rad-rms.
By reducing ang. fluc. in recycling mirror to a lower level,
thus
reducing fluctuations in resonant sideband power in stage 2,
one can
raise this limit by a factor of about 2.
Once in stage 4, not much of power-fluctuations (< 5%) are
observed
in all these cases.
* So, it seems either the central hall mirrors or the end mirrors
(but NOT both) are having too much of fluctuations.
Considering the fact that the control of only end mirrors using
only one WFS at dark port [Ref: detector elog by Matt, Nergis
1/22]
could reduce power fluc. and elongate the locked states, it
seems
the current state of Han2k is more like situation (i) described
above.
* I considered modes up to order 1 only. I also ran with modes upto
order 3 but that did not change the above results and guesses.
>> Mechanics model for advanced LIGO
(Virginio)
* The quad-pendulum model using MSE has been debug further.
* Including of the violin motion of the wires suspending the bottom
mass is going on now.
* Future work plan will be discussed when Peter visits Caltech next week.
>> Parallelization of the simulation engine
(Tavio, Matt, Hiro)
* A final answer from SUN engineer came to confirm our observation that
the delay of the order of 50 microseconds when switching to
other
threads is a harware/OS limitation and there is no way to reduce
it.
* Various different methods to speed up the switching of tasks between
thread have been tested, but we could not find any way to reduce
the
overhead.
* A systematic study of the overhead due to the thread and queuing
mechanisms have been done for a various different inputs under
different
use of threads.
* The overhead due to the threading and queuing mechanism is, roughly
speaking, constant overhead of 50-100 microseconds + 2.5 microseconds
per node which will be pushed into and poped out of the queue.
* The testbed is close to be completed, and the develepment of the algorithm
will follow.
>> ALFI
(Ed, Bruce)
* A new utility "boxjoiner" has been written to create one single box
file
out of a multiple box inputs. This is to make it easy to use
server
computers.
* Parameter windows is being updated and improved, including the support
of included files.
* Automation of a new release of alfi is being pursued.
* Transition to the latest release of xwWindow is in progress. This
is
necessary to resolve a conflict of the latest SUN OS and the
previous
version of xwWindow.
Software Systems (Blackburn)
The MPI MDC officially ended on Friday with a resounding successful
completion mark from the leads (Patrick Brady of UWM and Kent Blackburn
of Caltech). A few minor tests which did not impact any later tests and
check pointed such as documentation and ilwd file read/write errors
need more work but all of the big tests involving the search for signals
in simulated data using an inspiral search engine and an excess power
search engine cast into wrapperAPI compatible dynamically loaded shared
objects were a total success. In fact, the code was left running all
weekend, applying 1000 templates per node on each of more than 1000
data segments with only two terminated jobs due to what we suspect is
a filesystem caching problem in combination with the wrong choice of
ssh shell options (which has now been corrected and tested). It was
a wonderful feeling seeing LDAS drive search codes on the development
Beowulf cluster so successfully. Everyone in the LDAS development team
should feel very proud! See: http://www.ligo.caltech.edu/~lazz/MPIMDCPhotos/
See also the iLog log we have set up for the
MDCs: http://blue.ligo-wa.caltech.edu/ilog/index.htmlAfter the MDC, LDAS turned to formulating a new release of the software
which captures all the necessary changes that were identified during
the week and a half of MDC tests. This new release should be out in
about two weeks. New versions of the LAL and LALwrapper software will
also be released to include all the changes brought about by the MDC
as well as their regular compliment of code development.LDAS will be working to incorporate a much more fully developed version
of the frameAPI and the frameCPP library in this next release which has
support for a none trivial set of features of the frame specification
which have not been exercised by the framebuilder or LDAS to date. This
includes support for complex data and strings, as well as processed data
and simulated data in frames.The controlMonitorAPI continues to mature. Several issues of security
in the client component were identified and corrected this week. The
client is also now able to run outside the LDAS martian network. A
request has been made to enhance the temporary tapescript control
feature of the controlMonitorAPI in anticipation of the next engineering
run. There is also support now for monitoring the state of the LDAS
beowulf cluster.The conversion to Unified Data Type classes continues in the
dataConditionAPI
this week. The window, psd and firLP classes are being focused on. Also the
ingestion of LDAS native ilwd data into UDT data has nearly been completed.
The reverse process taking UDT into ilwd is also being sorted out.The LDAS database mock data challenge is still on hold pending Peter
Shawhan's
return from jury duty. It is expected to resume in earnest next week.Over forty new problem reports were generated during last weeks MDC. Almost
all of these have now been analyzed or closed out. We have seen a tremendous
increase in the flux of problems through the problem tracking system with
the recent LDAS release and the MDC. It has been extremely valuable as a
tool for tracing software issues during such a dynamic phase in our code
development.
Hardware Systems (Anderson)
Continuing discussions with vendors for the first large LDAS hardware
procurement, which includes ~30TB of disk and the first beowulf clusters
at LHO and LLO.Solaris UFS logging enabled on the main LDAS NFS/CVS/HTTP server and
the entire ldas-dev system.Upgrade of the general computing network on the 6th floor of Millikan
to allow additional network connections in the large conference room.Single mode fibre sent to LHO in anticipation of LDAS moving the bulk
of the servers from the mass storage room to the staging building.Identification of additional floor space for LDAS at LLO that will
allow LDAS to expand beyond the currently allocated space in the
mass storage room.Finished commissioning of the ldas-test system which is now generally
available for use as an LDAS system with: dataserver, metaserver, beowulf,
and 8 dual processor compute cluster nodes.(Shannon/LLO)
Installed replacement ram into linuxbox1. Will install RH 6.2
this evening or in the morning.
Installed the tape library hardware over the weekend. I
still have to install the software this week or this weekend.(Larry/CIT)
Updated DNS and NIS+ tables for new LDAS name.
Spent a number of hours on the phone (mostly on hold) getting
quotes and configurations for the PC purchases.
Shawhan:Data Analysis Activities
LIGOtools now includes version 0.6 of LAL (the LIGO/LSC Algorithm
Library), as well as the FFTW package. In addition, a bug was
fixed which had affected viewing of off-line data.
A.Vicere', 18-25 January 2001
- Meeting with A.Giazotto and G.Cella to work on the schedule for the
next network analysis meeting
- Contacts with F.Ricci, responsible in VIRGO for the Grid project,
to start
common work on the definition of a "use case" for the
LIGO-VIRGO
participation to the USGrid-EUGrid collaboration.
- Contacts with F.Barone, responsible in VIRGO for the environmental
monitoring, to understand which channels can be included
in the
reduced data set to be exchanged
Charlton:
Wrote up the derivation of the general FCT expression and error estimate.
Lingchin has taken over control of the code from Rick and next I'll
switch over to that code for my heirarchical search prototype and add
more
tests to Rick's code to check numerical accuracy.
Livingston:
(Shannon)
- Almost ready to transfer web services to our new server. This
will require changing dns entries.
- Will be ordering the GC AIT2 tape library this evening so it can
be here for the engineering run.
- We will move the GC EX-220 tape library off of decatur to another
machine so that the GC backups can be performed on a different machine.
- Testing 802.11b net networking here in three laptops. This
will
be useful for conferences etc.
Hanford:
(Christine)
- A read only copy of the LHO elogs is now available at
http://apex.ligo-wa.caltech.edu/ilog/.
Everyone uses the username
"reader" and password "read-only". Thanks to Bruce Sears for
setting
this up. The elog files are being copied from the CDS network
to apex
daily.
- Last week I attended an Advanced PC Maintenance course. I learned
a few
good things about BIOS settings, using the Windows registry, optimizing
memory and CPU, and security features in Windows 98.
[Bruce Sears]
* (BS) Hanford Ilog Mirror:
- LHO ilog mirror setup
has been completed. Actual updating
of log files
to this server is now up to the LHO systems people.
CIT:
(Lisa)
- Rebuilt 3 Ultra10's and 2 ultra1's with solaris 8.
- Recovered files off Bill Kells' laptop
- Am wrapping up the switch over to the new modem pool. I would
like to do that
on Monday.
- Went to Laser safety training.
- Worked with Larry on getting the tape robot tested for general backups.
- Ordered new software pkg. for backups.
(Sam)
-Fixed laptop
-Help dave beckett with a cd problem
-Helped Gina with a few PC issues.
-Looked at lori's computer
-Looked at florence's computer
looked at other stuff
didn't sleep
did homework
went to lab
did research
played basketball
(Barbara)
1. Worked on further changes to the CostBook
- reworked web forms, queries, calcs etc to look up the Location in
the WBS
table rather than entering it on each of the forms.
- fixed the calculation for the G1-G4 items.
- reworked the Risk Override field so it can be 0% or a negative percent.
- added Location to the WBS add/edit forms.
- reworked the procedure for calculating the item amount to accommodate
all
of the above changes.
I still have to develop forms for C and I as MIT resources and to
incorporate G6 somewhere. And the cost code lookup has to be
updated since
there will be only one cost code per WBS.
2. Worked on the web page for Data & Computing Groups contacts.
Had
problems figuring out how to capture the mail aliases file onto the
LDAS
servers but Stuart came to my rescue.
3. Made web site changes for SURF, the data analysis white paper, meetings.
4. Attended DCC planning meeting.
5. Help Ed Chargois with some file maintenance.
(Suresh)
-Installed Autocad 2000i in two PCs of west bridge.
-Did some cabling work in Millikan 6th floor conference room.
-Installed some windows applications in a new PC to be used by Mike
Smith.
-Created some e-mail aliases for LDAS group.
(Larry)
- Worked a number of PC issues. Most have been resolved and those that
have
not have been turned over to other people.
Just as a note at this point we do not purchase
CD players, speakers or any
other equipment for entertainment purposes. Many
times those items are part
of the pkg. of the item being ordered so the
people receiving that equipment
get lucky. Please, do not ask for support are
special ordering of equipment
so you can play music on a computer.
When using someone else's computer please do
not change the settings on the unit
and try to contact the main user before using
their workstation.
Update your virus files. There are some new viruses
out that really cause
problems. This includes those that are using
Mac units.
- Placed a number of orders for equipment and now trying to track items
down
that should have arrived. Hopefully, the UPS replacements will arrive
before
the end of the month so we can swap the network UPS out the first of
next month.
- Worked a few DCC issues with Linda.
- Assisted in taking care of a few Autocad problems.
- Installed tape robot and working on backup tests with Lisa.
From Helena:
Advanced LIGO Coatings
A visit to evaluate MLD's coating facilities in Oregon has been scheduled
for tomorrow, Thursday 25th.
From: GariLynn Billingsley <Billingsley_G@ligo.caltech.edu>
Subject: Weekly Report - Billingsley
A draft polishing specification for a 25 cm sapphire substrate has been
completed and circulated for comment.
From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>
Alessandro
Linear electronics, all parts now in, will be ready and shipped end
of
the week.
Edwin, Tatsuo
Measured 11 mini-GAS springs for selection for the top mass of the
multiple pendulum.
Can tune at 1 Hz easily, the load spread is narrow enough, it will
be
easy to chose matched quartets for each mass.
Virginio, Akiteru
Preparing top mass assembly, need masses for pre-tensioning the four
mini-GAS springs and keep them vertical. Preparing wire clamps.
Akiteru
LVDT controls achieved on TAMA SAS, small low frequency oscillation
at
10 mHz, need to optimize gain to avoid this instability which happens
at
the switchover between the DC and the AC controls. As soon as
solved
will start the Accelerometer diagonalization.
Kenji
IP counterweight curves look good, can move notch at will but,
found a
pitfall. The wire suspended shaker, replacing the oil bearing, introduce
a frequency shift difficult to quantize. Look for a way to renormalize
the measurement to optimize the counterweight. Will try to measure
and
subtract the wire suspension induced tilt, it should work.
Filter 0 tuned to bistability in order to introduce the control spring.
The filter returns to stability with the control spring added
K. The
spring is magnetic and not compatible with the vertical voice
coil
magnet but received already SS replacement, will install next.
Now can safely trim the other F0 blades.
Digital Electronics (IDED)
Digital cards assembled, under test, missing DAC chips now promised
by
Analogue Devices by mid February
DME crates ready to ship
NIM crates due beginning February
Ric
Shipping crates in construction, will be ready during the week.
Blades
and coils either will be delivered by Fed Ex today or Monday.
Shipment
clamps to be shipped tomorrow.
For additional information about this report, contact sanders@ligo.caltech.edu