Weekly Report for Week Ending January
18, 2001
The LIGO Executive Committee
Agenda for Monday January 22, 2001 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
-
Announcements
-
LSC Issues (Weiss)
-
Comments on Weekly Report
-
WBS 1 LIGO I Construction (Lindquist)
-
Field Change Orders/Contingency Liens/Change Requests
-
WBS 2 LIGO Lab Operations
-
Administration (Lindquist)
-
Sites (Raab, Coles, Shoemaker, Sanders)
-
Detector (Whitcomb, Coyne)
-
Campus Research Facilities (Weinstein (40 Meter), Libbrecht (TNI), Zucker(LASTI))
-
Data Analysis and Computing (Lazzarini)
-
WBS 3 and 4 Advanced R&D and LIGO II
(Sanders)
Executive Committee only 11:30 - noon
Topics: coating options
Special Items:
Special Announcements:
Weekly
Report Highlights
Another LHO commissioning advance - full recycling
with gain
LSC Issues (Weiss)
no report
LIGO I Construction/LIGO Laboratory
Administration (Lindquist)
WBS 1.2 LIGO Operations--Administration
LIGO Weekly Site Telecon (Lindquist)
There was a site teleconference held on Thursday,
January 18, 2001. Discussion items included the financial reports
for the end of Decvember 2000; total booked costs were slightly less than
$21.9 million. However, a number of large open commitments are still
being booked, and the total for the fiscal year is expected to reach $21.8
million. Costs for FY 2001 are just beginning to roll in and December was
a short month. Other items on the agenda were procurement of a standby
generator for Livingston, selection of an A&E contractor for the Hanford
Support Building, and preparations for the NSF Operations Review at Hanford
The next site telecon is scheduled for Thursday,
January 25, 2001. The list of current actions revised to reflect
open actions assigned through January 18, 2001 may be found at
ACTION
LIST.
PROPERTY
MANAGEMENT (Chargois)
From: Ed Chargois <chargois_e@ligo.caltech.edu>
-
Assisted the Systems Administrator (L. Wallace) with packing and shipping
of a reel of Fiber Cable (1016 ft) to the LIGO Hanford Observatory (R.
McCarthy) via UPS, scheduled arrival date: 01-19-01, account number: LIGO.00009
1.5.3 NSFLIGO.000001.
-
Assisted Livingston Observatory (R.Riesen ) with the preparation of a Caltech
Request for Purchase Order to arrange the shippment of a 15'x6'x6' section
of Beam Tube, to be transported to LIGO Hanford Observatory (O.Matherny)
via United Motor Freight. Account Number: LIGO.00007 2.2.5 NSFLIGO 000003.
-
Assisting the Seismic Isolation Group (R. DeSalvo) with preparation of
a Commercial Invoice and with Customs Clearance and transportation of the
TAMA SAS to Tokyo(Seiji Kawamura) via Nittsu. Account Number: LIGO.00002
3 NSFLIGO.504800.
DOCUMENT
CONTROL CENTER (Turner, Mak)
>From: Linda Turner
- turner@ligo.caltech.edu>
Web pages for the
DCC give simple how-to's for document numbering, easy access to the latest
on-line documents, and search capabilities for the DCC database. Take
a look. . .
ACCOMPLISHMENTS
-
Review of the ASIS web page continues.
-
Planned for meeting at the end of the week
regarding electronic document issues.
-
Processed and distributed three DCN's.
From: Cleveland Mak
<mak_c@ligo.caltech.edu>
-
packaged and shipped 10 more copies of specifications and drawings for
IFB EJ-319 to Brunt Construction as well as two more copies to Gerry Stapfer.
-
editing of titles continues on Livingston Construction drawings.
|
Packages |
Faxes |
| In |
34 |
27 |
| Out |
16 |
32 |
Press here to access
the DOCUMENT CONTROL CENTER
WEB PAGE.
COST SCHEDULE
CONTROL SYSTEMS (Cunningham, Brambila, Akutagawa, Kaufman)
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS
PAYABLE HISTORY DATA.
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
-
Working on change orders to Richard Price, Apollo, MMR, and Tyler.
-
Working with Florence, and Dorothy to transfer FY2000 funds to the new
FY2001 poetas. Working with Cindy following up on old encumbrances
and inquiring whether funds should be released and the p.o. closed, or
transferred to the new FY2001 poetas.
-
Working on getting bids for a generator for LLO.
-
Reconciling and placing pcard orders. I noticed that one large vendor
whom we deal regularly with as of yesterday was still charging the California
sales tax at the higher rate of 8.25%, and once I inquired about the incorrect
rate being charged, they inform me they will put through a credit for the
additional .25% collected.
From: Florence Kaufman <fkaufman@ligo.caltech.edu>
-
Submitted four Fabricated Equipment Request Forms for LDAS equipment to
Federal Accounting.
-
Attended Sponsored Research Forum on January 17, 2001.
-
Sent out Integrated Report for Data Group as of December 2000 to Albert
Lazzarini.
-
Worked with Federal Accounting to make sure that account type has been
set up correctly for new building at Livingston so that all costs related
to construction of the building will not be subject to Indirect charge.
-
Prepared Cost Transfer Request Forms required for Sky and Telescope and
Astronomy Magazine Orders.
-
Continued working with Ruth Brambila and Dorothy Lloyd for transfer of
encumbrances to Fiscal Period 2001 Operations accounts.
SUBCONTRACTS MANAGEMENT (Petrac,
Jasnow)
From: irena@ligo.caltech.edu (Irena Petrac)
-
Nothing significant to report.
From: Ed Jasnow <jasnow@ligo.caltech.edu>
-
A policy regarding the processing of appointed visitors to the sites is
being developed. This is to assure that all of the paperwork for
these visitors is properly completed.
-
Ed Jasnow, Elizabeth Wood, and Donna Tomlinson met with the new Director
of Human Resources, Pam Robertson, to discuss the processing of visas for
faculty and staff. That process has been moved from the provost's
office to Human Resources, where a new immigration specialist, Holly Willis,
is starting January 24.
Support (Wood)
Irene Baldon
-
Twelve (12) new trips were started and I have fourteen (14) trips pending
final approval before tickets can be issued. Most of these trips
required Advance Checks to be written as well as hotel and car authorization
forms to be filled out and FAXed to the appropriate locations.
-
Reconciled fifty-six (56) items on my P-Card this week.
-
Worked on and completed twenty five (25) Expense Reports. I have
twenty-eight (28) Expense Reports to work on and I'm holding three (3)
reports which need a check from the traveler before processing.
-
Please use the new Expense Report form, particularly if you are using the
Pcard for your travels. If you do not have a copy of the new expense
report, please let me know and I’ll resend it immediately.
-
I would like to remind all travelers that if your flight is considerably
delayed or completely canceled, and Gina or I are not available to personally
assist you in rearranging your itinerary or notifying the hotels and car
rentals of your delay (i.e., after working hours here in California or
on the weekends), you as the traveler are responsible for calling either
the number listed on your Itinerary, their 800 number, or even a local
number (or airport desk) for the vendor. Please let them know that
you will either be late or a "No Show" otherwise you will be charged a
"No Show Fee" and you could lose your reservation completely.
Rita Torres
-
Converted to MS Word the Attachments B, C, and D for Stanford to update
for the next period. Edits to the Advanced SEI Mechanical Structure
RFP for G. Stapfer. Obtained DCC numbers for 25 drawings to accompany
the RFP, listed this numbers and titles in the document.
-
Arranged eye exams, and upcoming training session. Obtained information
to prepare requisition with IFR Americas. Arranged for telecon on
Friday for LIGO 2 systems. Took a nice walk to Sponsored Research
to obtain a signature.
-
Ongoing activity: Chased information associated with Pcard purchases.
No sooner do I reconcile a group in Passport when more appear to be done;
reconciled 24 this period. Completed the updates to PO log for D.
Lloyd.
Dorothy Lloyd
Image by C. Akutagawa
-
Processed the usual requisitions, invoices and receiving on-line. For more
detail, see "Cost Schedule Control Systems" report by Esther Cunningham.
-
Reviewed and recorded payments processed by Esther for the week of January
8, on contract summary sheets and LIGO database.
-
Continued to work with Florence and Ruth on transferring encumbrances to
new fiscal period.
-
Continue to monitor contract and blanket order funding levels and notify
task managers when supplements are needed.
-
Jim continues to do data entry in the LIGO database and help out in the
DCC.
Elizabeth K. Wood
-
Submitted to the NSF the final report for the Amaldi conference.
-
Continuing with preparations for the NSF Review at the end of the month.
-
Along those same lines, at some point I will begin asking the presenters
for the review to get me their transparencies so I can put them in binders
for the reviewers. Just thought I’d let you know about my nagging
in advance.
Advanced LIGO (Frey, Petrac)
From: Thomas Frey <tfrey@ligo.caltech.edu>
Progress Period from 01.12 to 01.18
Accomplishments:
-
Monday the 15th Holiday.
-
No Advanced LIGO Project Controls meeting held this week.
-
Proposal plan development for Advanced LIGO MRE continues.
-
Issued data requests for progress data as of 01.19.01 that are due Friday.
-
Progress as of 01.12.01 was processed and posted.
-
Review of cost and schedule data is Continuing.
-
Started to integrate the AOS schedule into Primavera and the Cost Book
Tool.
-
Received data from Garilyn Billingsly and review is in progress.
-
Have not received any data from Dave Reitze or Peter King.
-
Initiated the development of the TNI work plan and schedule per Gary Sanders.
-
Project Plan for the 40-Meter Lab Upgrade continues.
-
Issued data requests for progress data as of 01.19.01 that are due Friday.
-
Progress as of 01.12.01 was processed and posted.
-
Met with Alan regarding comments to experiment tasks and comments are forthcoming.
-
Planning process for the LASTI project at MIT is in progress.
-
Issued data requests for progress data as of 01.19.01 that are due Friday.
-
Progress as of 01.12.01 was processed and posted.
-
Changes are pending from David per his discussions with GEO regarding the
acceleration of prototype noise testing.
-
Continue to test the Cost Book Tool.
-
Continue mapping and formatting of OPs cost data for input.
-
Met with Barbara Kratochwill to discuss the adjustments and effort is continuing.
-
Development of the Advanced LIGO Project Controls Guidebook continues.
-
Project Web Site for posting schedule and progress related data continues
to be updated with the latest and greatest.
Schedule 01.19 to 01.25:
-
Next weekly meeting will be Monday afternoon January 22nd from 1 to 2pm
regarding the planning and control of the Advanced LIGO MRE proposal development.
-
Continue to pursue the planning and scheduling of the staging buildings
currently being bid and designed for HLO and LLO.
-
Advanced LIGO Proposal
-
Will continue the effort of contacting each system leader to collect cost
and schedule data.
-
Will continue input of AOS to the cost book and schedule.
-
Will finish review of COC and begin integration.
-
Will meet with Eric Black, Shanti Rao, and Luca Matone to begin development
of the TNI work plan and schedule on Wednesday at 9am at SSCR.
-
Will Continue to update the LASTI Schedule with progress.
-
Will post progress report by end of day Tuesday the 23rd with progress
as of 01.19.01.
-
Will issue 25th week of status data to teams by the 23rd.
-
Will continue to update the Advanced LIGO / Ops Proposal Plans and incorporate
any changes.
-
Will post progress report by end of day Tuesday the 23rd with progress
as of 01.19.01.
-
Will issue 25th week of status data to teams by the 23rd.
-
Will continue updating the 40 meter schedule and incorporate any changes.
-
Will post progress report by end of day Tuesday the 23rd with progress
as of 01.19.01.
-
Will issue 25th week of status data to teams by the 23rd.
-
Continue to test the Cost Book Tool.
-
Cost Book Tool development continues.
-
BK continues work on program adjustments to the cost book tool.
-
Input of OPs cost data will continue.
-
Will continue the development of the Advanced LIGO Project Web Site.
-
Will continue the development of the Advanced LIGO Project Controls Guide
Book.
WBS 1.4.1.2 Project Controls (LIGO Construction)
Reports (Lindquist)
Annual Report: The Annual Progress Report
for the LIGO Construction effort as of the end of November 2000 has been
sent to the NSF. An electronic version should appear shortly in the
DCC under LIGO-M0100003-00-P.
Change Control/Contingency (Lindquist)
The following Change Requests have
been submitted:
| CR-000018 |
WBS 1.1.4 |
Curbing for Service Roads at Livingston |
G. Stapfer |
| CR-000019 |
WBS 1.2 |
Additional Lab Equipment |
D. Coyne |
| CR-000020 |
WBS 1.1.4 |
Staging Building and Renovations to Existing Building--Livigston |
F. Asiri |
Press for the latest Contingency
Needs Projection.
COST SCHEDULE CONTROL SYSTEMS (Duncan,
Akutagawa)
From: Kris Duncan <kris@ligo.caltech.edu>
-
Completed and submitted the November 2000 CSSR materials
for the NSF Annual Report and LIGO Project distribution.
-
Initiated work on the December CSSR (calculation
of earned value, advancing calendars, and rebuilding indexes).
-
Continued with construction contract/work package
close out.
-
Completed the final draft of the construction RAM
for period end November 2000.
-
Continued with actual cost and commitment data reconciliation
between LIGO and CIT finance.
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
-
The monthly reports (Allocation of Actual Costs for
Construction and Advanced R&D) for periods ending December 2000 have
been put on the network. E-mail has been sent to the Task Managers noting
the location of the files.
-
I am working on gathering the details for the monthly
reports on the Construction and Advanced R&D accounts for December
2000. I will email them to the Task managers as soon as I have completed
them.
-
I received the MIT invoice for the month of December
and as soon as I receive the TWONK (MIT expense allocation report) I will
compile the data for payment.
-
I continue to review the open encumbrances on the
Construction and Advanced R&D accounts to see if the requested removals
have been made. I will continue to review these accounts weekly until all
encumbrances have been removed (Remember, I can only get these errors corrected
if the Task Managers point them out to me).
The financial reports on the web provide supporting
detail.
http://docuserv.ligo.caltech.edu/~fireport
http://docuserv.ligo.caltech.edu/~finance
Reminder: An updated list of all OPEN LIGO account
numbers has been posted on the LIGO internal bulletin board. Please use
these lists when you need a LIGO account number (or make yourself a printed
copy for quick references).
Please note that the FY00 LIGO Operation account
numbers expired on November 30, 2000, and that the new account numbers
can be found at:
SUBCONTRACTS MANAGEMENT (Petrac,
Jasnow)
From: Ed Jasnow <jasnow@ligo.caltech.edu>
A visit to the third A/E candidate for the Hanford Support Building
is scheduled for Wednesday, January 24, at the contractor's facility in
Glendora, CA. A decision on the selection is scheduled before the
end of the month.
The letter to the NSF requesting approval for Phase I of the LDAS procurement
has been completed in its first draft. This is being reviewed and
edited. It will be submitted when the vendors have been selected
for all of the different components comprising Phase I.
From: irena@ligo.caltech.edu (Irena Petrac)
-
No report this week; see Operations Section above.
LIGO Hanford Observatory (LHO) Operations
(Raab)
General Items:
--------------
(F. Raab)
Our valiant commissars have made a major breakthrough
in extending locking times
for the full 2-km configuration to one minute!
(Undoubtedly there will be more
crowing about this elsewhere in this report,
so I will say no more.) On another
front, we began installation of optics for the X End into the vacuum
chamber.
Alignment was proceeding as of the afternoon of 18 Jan. A number of
changes
have been made to controls and there are moves afoot to improve the
acoustic
isoaltion of the PSL.
Controls
--------
(D. Barker)
Upgraded CDS main server hanford1. Replaced internal disk drives and
upgraded operating system to solaris 2.7.
Recabled CDS/GC ethernet and ATM networks in the control room and mass
storage room. Updated all cable labels and brought drawings up to
date.
Reorganised Sun workstations in the control room.
Worked on web server blue, trying to get apache to serve elog to all
hosts while keeping access control to other CGIs restricted to LIGO/LSC.
Fixed DAQ fibre optics problem with the 4k Y End station. EY ADCU now
keeps in sync with other 4k units. The failure of the 4k automatic
bypass
board means that the 4k system is currently running on manual bypasses
only.
Worked with Hugh to setup an EPICS test stand for the PSL tidal
correction software.
Set up the 4k PSL EPICS system on an mv162.
Tested GEO's ADCU timing cards.
Bringing all CDS Rack, DAQ and networking drawings up to date.
Autoburt new feature programmed. PVs can be marked to be backed up,
but
not restored to IOC.
Put FMCS controls pc onto CDS network, allows backup of fmcs data onto
hanford1 for archiving.
LIGO Livingston Observatory (LLO) Operations
(Coles)
Commissioning (Joe Kovalik) LSC and ASC now work both in the LVEA and
end
stations. The GDS excitation engine works in the end stations. Work
is going
on in diagonalizing the actuators for the large optics.
Both ISCT1 (symmetric) and ISCT4 (anti-symmetric) are aligned. The
photodiodes are installed and the demodulated outputs are now operational.
LSC (Ed Daw and Szabi Marka)We added D.C. offsets at various points
in the
LSC servo block diagram to do rudimentary tests of individual servo
components. We found every control we tested was working.
We measured the transfer functions of parts of the LSC digital servo
and
associated analog pre and post digital signal conditioning. See LIGO
Livingston e-log entries, 17th Jan 2001.
We measured the dynamic range of the Lm LSC servo as a function of
frequency. We observed glitches in the output of the servo when saturating
below frequency of ~100Hz. See e-log entries, 18th Jan 2001.
Facilities (Gerry Stapfer) The Contractor (Brunt Construction Inc.)
has
started work on the renovation of the Staging Building.
Detector/Technical Support (Whitcomb,
Coyne)
1.1 LHO
INSTALLATION & COMMISSIONING
2km Commissioning
Matt Evans, Nergis Mavalavala,
Bill Kells, Richard McCarthy, Dave Barker, Stan Whitcomb
We
continued with our attempts to lock the 2 km ilnterferometer this week.
The eary part of the week was spent trying to understand and remove
the apparent offset that had been observed in locking the sidebands to
the power recycled Michelson. We made a number of tests, did a major
realignment in the corner station and were unable to significantly change
the offset. In the end, a series of FFT rune by Bill Kells convinced
us that the apparent offset is a real effect from the (slightly) unstable
recycling cavity, and thus it is a good thing not to be able to eliminate
it.
With that under our belts we tackled
locking. We measured the lock acquisition parameters for Matt Evans
code, getting similar numbers to what we had gotten in the past.
The rf phase for the reflected port ended up about 7 degrees different
(and in my opinion, better), but most other numbers did not seem to be
changed by much.
The interferometer locked robustly
in all of the subconfigurations (including a new one: one arm and a half-Michelson).
The we tried the full interferometer. Initially the results were
similar to what had been achieved in the past: buildups in the arms indicative
of "recycling gains of 7-10, but durations typically 0.1 second.
One striking feature of these brief locks was the similarity of the signals
from attempt to attempt; one frequently had to really examine traces in
detail to see that two printouts of the timetraces were from different
events. This lead us to believe that the action was dominated by
what we were doing to the optics via the servos and not by random forces
or initial conditions.
At that point we turned off the
angular suspension damping from the OSEMs; it had been turned way down
when the optical lever damping was implemented, but typically left on at
a low level for those occasional times when the optlev goes out of range
(typically during the alignment process). Lock duration immediately
leaped to 0.3 seconds. After a good night's rest, the interferometer was
ready to go for 2.5 seconds and encouraged by the occasional passerby,
these locked stretches gradually extended to more than one minute.
Slight improvements to the alignment have brought the recycling factor
up to about 15. We had to reduce power on a couple of photodiodes
to eliminate saturation.
The figure below shows key images
from four locations in the interferometer: on top the two transmitted beams
through the two arms, below, the "dark port" and a pickoff inside the recycling
cavity. These are more or less the same ones as in background of
the first lock photo of Rai on the webpage, but note that the saturated
nature of the images indicates the increase in power in the interferometer
(of order 500 for the transmitted beams).
Core Optics
Doug Cook, Mark Lubinski, Hugh Radkins, Betsy Weaver, Rick Graff, John
Worden, Kyle Ryan, Gerardo Moreno
Installation of the 4 km ETMX started. The vacuum volume was
vented. The door and spool piece were removed. The tooling was installed
and the alignment equipment inserted into the chamber. The ETM telescope
was installed and rough aligned. The assembly of the arm cavity baffle
was started. The ETM has been installed and aligned. So far
it looks like we have a pretty good chance to finish this week, but may
not get the end station pumped down until the beginning of next week.
COS
Mike Smith, Ken Mailand
, Doug Cook, Dennis Coyne
The ETMx telescope was installed and aligned roughly
in preparation for final alignment with the COS autocollimator.
The arm cavity baffle is in process of being assembled.
IOO
Jay Heefner
Drawings and cross connect lists for the "new" mode cleaner
length controls are complete. R. McCarthy is building the cross connects
for both the 2K and 4K. We still need to change the database and the operator
screens prior to running the system.
1.2LLO
INSTALLATION & COMMISSIONING
Commissioning
Rai Weiss, Mike Zucker and everyoneat
LLO
The short term goal of the commissioning at Livingston
is to individually lock the 4 km arm cavities. In order to achieve this,
the commissioning effort in the past two weeks has concentrated:
-
to bring the LSC and ASC digital control into operation at
the end stations
-
to test and measure the properties of the LSC digital servo
program
-
to optically align the antisymmetric and symmetric port detection
tables
-
to tune and test the LSC RF electronics (preamplifiers, mixers)
at the symmetric and antisymmetric ports
-
to diagonalize the ITM and ETM translational coil drive matrices
Visitors to the site have been Rolf Bork, Jay Heefner, Rich Abbott and
David
Shoemaker.
ISC
Rich Abbott
Helped with the troubleshooting of the ETMY LOS suspension
controller that had two coil driver channels inoperative.
Performed functional checks of all I&Q demodulator
boards due to poor detection linearity. Problem was found to be an
improperly set LO drive level. Fixed the problem and now all channels
have I relative to Q phase of 90 +/- 0.5 degrees, and I relative to Q magnitude
balance of better than 0.5 %
Changed all elements of the frequency distribution system
to incorporate the RF decoupling capacitors. This should improve
RF leakage from the cabling. A measurement is to be performed today
to check the field strength against the numbers obtained by Rai.
Rolf Bork
Finished up at LLO Friday. The intermittent problem
withthe ASC/LSC front ends turned out to be a bad Pentium CPU in the ASC
crate. This was the problem that I had been looking for since the
first installationand appeared to be a problem with the X end station,
as system would crashdue to non-numeric data (0xffff everywhere) randomly
showing up in the Xend reflected memory. This would cause one or more of
the three CPUs on thisnet to crash. Finally found the problem Thursday
night while monitoringall three CPU on my laptop from the hotel.
With no software running, suddenly0xffff ate thru the memory of the ASC
processor reflected memory board. Replaced that CPU on Friday, and
problem has not reappeared.
Jay Heefner
A new set of schematics showing the LSC wiring and cross
connects has been generated. The previous version had many mistakes, was
hard to follow and did not incorporate changes needed for lock acquisition.
Once the drawings are checked the new version will be released.
All modules, wiring and software for the ASC and LSC systems
are installed and operational. This does not include any additions that
may come from the lock acquisition studies at LHO.
2.0 OtherEngineering
and Scientific Activities
2.1 Design/Analysis/Fab
Optical Metrology
Helena Armandula, GariLynn Billingsley
Given the marked temperature fluctuations testing of
2ITM03 is "on hold"
Optics Modelling
EriKa d'Ambrosio
Testing how stable is a cavity supporting a flattopped
beam as an eigenstate
I created the maps for the hypothetical mirrors by making
thebeam propagate and catching the constant phase surfaces as border conditionsfor
reflection. Those were put inside the FFT-code and after relaxation isreached
the field grid of the resonating beam was picked up for post-checkthat
the eigenmode is the one we want. Comparisons were made by using "perfectspherical
mirrors" and the curve of power gain versus tilt for the "reshapedmirrors"
decreases with a slope that is ~thirty times larger.
PSL
Peter King
Ben, PR and I have been testing out the newly fabricated
frequency stabilization servo, 80 MHz VCO and 21.5 MHz RF photodiode down
in the PSL Lab. Both the VCO and the photodiode passed without modification.
After the addition of an external capacitor, the frequency servo functioned
as usual.
A prototype board for the high power photodiode was fabricated
and stuffed. After some bemusement about the circuit's behavior,
the cutting of a few traces ... the photodiode was placed in the laser
beam. The output of the photodiode was consistent with there being
about 115 mA of photocurrent. Unfortunately the photodiode bandwidth was
not as high as hoped for. The measured bandwidth was only 70 kHz,
compared to the hoped for 70 MHz. Measurements of the feedback resistor
and capacitor confirmed that they were the proper values, so I don't quite
understand where all the bandwidth went.
Lee Cardenas
Work on the Laser. Complete re-alignment and Beam scan
for both lasers, the npro as well as the amplifier is on going. Since
we are replacing the mount for the EOM with a goniometer.
Preparing an station to mount the reference cavity so
we can be able to do optical contacting on the new reference cavities.
General lab task ( placing orders, paper work, drawings
etc...)
Rick Karwoski, Paul Russell,
Ben Abbott
All four boards composing the Frequency stabilization
sub-system have been bench tested, system-tested at Lauritsen, and shipped
to Hanford for installation.
Modulated OSEM DesignJay
Heefne r
Five stabilized oscillator satellite amps are operational
and in final test. The boxes for the boards are late from the vendor. We
can ship the boards and test them with no boxes if the LHO commissioning
team needs them. Richard McCarthy is checking with Stan.
New OSEM Heads
Peter Fritschel, Myron McInnis,
Fred Miller
We're continuing production of new osems for the LHO
4k installation. We have had more problems of poor bonding of the device
boards to the cylindrical forms. We have thus moved to a different ceramabond
adhesive. This one is based on alumina (rather than magnesium oxide) which
is a better match to the alumina parts; it is also much easier to work
with as it is less viscous than the previous adhesive. Early results indicate
that it is giving better bonds. We expect to finish all LHO 4k osems in
a couple of days.
Janeen Romie
Helena and I cleaned the 120 acid etched heads from Orbit
Technology. Rapid Prototyping will receive them tomorrow morning for metallization.
The assembly specification is being updated.
Digital Suspensions
Rolf Bork
This week, returned to code development for the digital
suspension system. Some early testing indicates we might be able
to run all suspensions with two CPU in the LVEA, one performing all servo
calcs and SOS coil drives and the other performing final LOS calculations
(add in ASC/LSC inputs) and LOS coil drives. I'm in the process of adding
in the sensor input / coil output filters now (for a total of up to 39
user definable digital filters per suspension) and hope to get performance
numbers by Friday. We need this info to complete the system layout
and begin the system wiring diagrams.
Jay Heefner
-
System layout and wiring diagrams will be started this week
and should be ready for review by 1/26.
GDS
Daniel Sigg
Started with the new client interface for the DTT which
should be able to read frame files and which can get data directly from
the archive with the help of the data flow manager.
Helped tracking down two problems with mini-nds and the
rds writer. The reduced data set writer can now be started and stopped
from the control room. It has an internal buffer to store frames for several
seconds. This made it possible to implement a snap shot feature which saves
frame files to disk around the time someone presses the rds snapshot button.
For example, if the operator sees an interesting feature with the data
viewer, the event can be saved to fortress by taking a snap shot.
DMT
John Zweizig
This week I am attending the GEO data analysis conference.
They aregetting all sorts of good(?) advice on how to run their experiment.
Data Acquisition
Sander Liu
SoCal ValueAdded delivered the first 16 channel data
cable they built for us for testing. Continuity check was ok and it looks
good. They were authorized to proceed building the rest of the cables for
us per our purchase order.
In the process of testing a +/- 5V, 25 Amp power supply
for the 40 meter.
2.2 IssuesConcerns
nothing
new
40 Meter Interferometer (Weinstein)
Mike Smith continues to add detail to the optical layout of the 40m IFO.
Six of the 9 output beams now go to tables to the south of the PSL table,
close to 7 electronics racks. Jay Heefner, Mike, Ben, and Steve have gone
over the layout of the tables and electronics racks, and think there's
(barely) enough room for the required equipment. Some rework of our brand
new electrical wiring may be required. The integrated layout of the 40
meter interferometer, which combines the building layout, electrical layout,
and opto-mechanical layout, is being revised to incorporate the planned
locations of the electronic racks, and the as-build configuration of the
cable trays.
PSL, from Peter King: following last week's report stating that the vibration
isolation stacks arrived, some parts were discovered to be missing. Nor-Cal
have been contacted and the parts should arrive sometime in the next two
weeks. Somehow fabrication of the parts was overlooked.
PSL, from Rick Karwoski: Plan to begin moving pieces of the 40m PSL to
the 40m lab in February is still on track.
Ben Abbott will update his plan for the control room layout, including
furniture, computer locations, PSL cooling location, etc, and will begin
the process of ordering the furniture.
Larry Jones reports a series of mishaps where parts for the 40m mode cleaner
vacuum chamber were not ordered when they were supposed to be, things weren't
shipped to LLO for cleaning when they were supposed to, other parts are
on back order, etc. Nonetheless, we can still hope to begin assembly of
the mode cleaner vacuum enveloped in February.
As you can tell from the above, February and March will be a very busy
time at the lab: installation of the output optic chamber and it's new
seismic isolation stacks; installation of the 12 meter mode cleaner; begin
installation of the PSL; installation of 9 electronics racks and the beginnings
of populating them with VME crates, DAQ electronics, etc; setting up of
the control room (furniture, computers, networking); regeneration and re-installation
of the ion pumps; commissioning of the new vacuum control system; finish
up items on the building rehab punch list; etc. Wow! A very preliminary
but detailed schedule is here.
AJW met very briefly with Tom Frey to go over the Primevera-based WBS for
the 40m program. Unfortunately, AJW is battling the flu, but promises to
give Tom detailed comments when he returns to sentience.
Similarly, AJW was too zonked to prepare for or attend the dry run for
the NSF review on Friday, but promises transparencies ASAP.
Thermal Noise Interferometer (Libbrecht)
We are currently in the process of characterizing and experimenting
with
our successfully locked test cavity, and we are debugging and repairing
the
fast inputs on two of our OSEM controllers. Shanti is also working
on
materials for his candidacy exam next week.
LASTI (Zucker)
no report
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Yamamoto)
* physics analysis :
Biplab kept working on the systematic study of the effect
of angular fluctuation on the lock acquisition process.
Lock acquisition with misalignments: studying tolerance
of various stages of the lock-acquisition procedure towards
levels of angular fluctuations in mirrors.
Studying power fluctuations at desired states of various stages.
Although it may sound obvious, it has been observed from
simulation runs that the statistical quantity
"average lock-acquisition time" increases with the level
of angular fluctuations.
Hiro worked in the noise modeling. In order to simplify
the PSD analysis, primitives calculating psd and some
low pass filters will be provided.
* LIGO II mechanics modeling
Virginio has reassembled and completed the first version of the
quad suspension model for LIGO II, based on the work done by
Akiteru and himself using MSE by G.Cella. The top blade is not
implemented yet, and he will discuss with Peter Fritschel and
Giancarlo Cella to find out the most effective way of implementing
the blade. Hiro is working to complete the interface between MSE
and e2e.
* parallelization effort
Having the thread-safe queue and a looping algorithm completed,
Tavio and Hiro designed the testbed which has an interface identical
to the real simulation program as to the module arrangement and
execution. Future effort will be concentrated to the algorithm
development to arrange the module execution using optimal number
of thread in this testbed.
Tavio and Hiro tried semaphore synch mechanism under the assumption
that it's being simple and (probably) having a kernel implementation
would make it faster that mutexes & cond variables.
Unfortunately,
same long delay (~50 micro seconds) was observed as was the case
using mutextes & cond variables.
* alfi / GUI :
A new released has been installed at CIT and LHO, and a tarball is
made available from the webpage. Copy&Paste and new setting front
end is coming.
In order to simplify using remote computers (like CACR) as computation
engine, a program will be written to merge all box files keeping only
minimal information in it.
LIGO Data Analysis System
Software Systems (Blackburn)
LDAS released version 0.0.13 late on Friday of last week. The release
was
tagged in the CVS repository, extracted and a distribution built and
added
to the LDAS webpage. It was also re-built and compiled from the distribution
over the weekend in preparation for the begin of the MPI Mock Data
Challenge.
The remainder of the week has been dominated with activities in support
of
the MPI MDC. Several of the staff worked on the MPI MDC Plan documentation
and prepared TCL test scripts to exercise each aspect of required functionality
being evaluated during the MDC. So far we have tested the mpiAPI, wrapperAPI,
LAL, LALwrapper, and mpi-wrapper interface. Testing of the details
of the
individual search libraries is actively underway. It looks like there
is a
very good chance that the week will end with a very successful completion
of
this MDC.
Other areas that have been worked on this week include closing out a
large
number of lingering open problem reports. The documentation has also
been
greatly improved in areas of the frameAPI, controlMonitorAPI and the
dataConditionAPI.
Very good progress is being made towards recasting the dataConditionAPI
classes to use the new UDT with significant support from UTB, PSU,
and ANU.
The completion of data ingestion has been given a very high priority
this
week in hopes that we might be able to do a couple of tests during
the MDC
of the mpiAPI, wrapperAPI "and the dataConditionAPI" before everyone
packs
up and heads back to their home institutions.
Hardware Systems (Anderson)
Work in support of the LDAS
MPI MDC, including the installation
of a 16 processor Beowulf cluster in the ldas-test system (AltaCluster).
Continuing negotiations with
several vendors in preparation for the
major LDAS Phase I purchase.
Data Analysis Activities
General Computing (Wallace)
MIT:
Nothing to report.
Livingston:
-Working on a number of system maintenance items. Discussed reconfiguring
the
Big Brother program to accommodate a few other tasks.
-Larry has sent another message to Bellsouth to try and get the information
that
they promised to deliver by the first of the year.
Hanford:
-Getting elog mirrored to the Observatories main web server.
-Larry is working on the procurement for the FORE cards to connect
the
Observatory with PNL using an ATM link.
This is part of the project to get the OC3 connection going at the
Observatory.
CIT:
(Larry)
-Working on getting things started with the DCC in preparation for
the upcoming
LSC meeting. Mainly working on equipment and software purchases they
will be
needing.
-Cleaned out a number of defunct aliases on the e-mail server.
-A number of hours spent with procurement related issues. Includes
resolving
problems with existing procurements as well as placing more orders.
-Working on a number of LDAS related issues.
-Just as a note to remind everyone to be careful on any programs they
download
or install on their computers. Be sure they are virus free. Please,
download
only what is necessary and if you find it is a junk program be sure
to remove
it.
(Lisa)
- Created users in the new modem pool. I am only a day or two
away from
switching to the new pool. I still need to get a free block of
IP numbers on
the 125 subnet and chase down a couple of more people who need accounts
created.
- Updated an ultra1 on the 6th floor of Milliken to solaris 8
- Rebuilt Paul Russell's pc with a new hard disk.
- Swapped in a new ultra 10 for Hongyu in Wilson House.
- Have been dealing with lots of little laptop issues that have cropped
up as a
byproduct of the modem pool upgrade.
(Barbara)
- Completed and installed changes to CostBook system for equipment
line
items, contingency override, and subcontract overhead calculations.
- Updated LDAS database links and the green-map images.
- Tried several possibilities for a DCC report for David Shoemaker.
- Worked with Lisa on executing jobs when TimeTarget is installed as
a
service.
- Attended roster meeting with Liz and Gary.
- Made a number of web site changes to Publications and Talks pages.
(Suresh)
-Resolved the network connection in one of the cubicles in third floor
west
bridge.
-Fixed Erika's mailserver connection problem from her workstation.
Helped Paul
Russel with some applications.
-Worked on some printer maintenance.
-Working on new PC set up for Ken Mainland.
(Sam)
-Talked with Phil about his computer difficulties.
-Did some ip stuff
-Answered a few random questions
LIGO II/Advanced R&D (Sanders)
From Peter King:
LIGO II PSL
I am still working on a new costing for the PSL. Mostly incorporating
updates for the cost of fabrication of the 200-W laser.
From: Peter Fritschel <pf@ligo.mit.edu>
Completed the design requirements document for
the seismic isolation
system, and sent it out to the committee which
will be reviewing it next
week (Wednesday, 24 Jan).
From: Helena Armandula <ahelena@ligo.caltech.edu>
Silicate bonding
We may have an answer for the "ferns" seen in most of the bonds.
There is a well studied model for pattern formation, "diffusion-limited
aggregation", that explains this phenomena.
The "fern" patterns, called "fjords" in the literature, form when colloidal
particles undergoing Brownian motion adhere on contact with one another.
If the density of the particles is quite low, the aggregation process
occurs one particle at the time, and explains why we do not see these formations
right away but maybe hours after the bonding took place.
In our case, we observed that the cleaner the substrate is before bonding,
the more faint is the pattern seen.
Now, the bonding solution, which is a mild etchant, may dislodge some
loosely attached fused silica particles coming from the top "superpolished"
layer of the substrate. This may explain the changing bonding behavior
on different substrates.
Surface tension also plays an important role in this pattern formation.
From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>
Fred is sick, will be out for several weeks. Best wishes from
everybody.
Digital Electronics (IDED)
Digital cards coming along
DME crates available
NIM crates still late
Alessandro
Accelerometers I n construction, 6 for the 2 IP, 2 for Szabi and 2
spares.
Coils shipped
Linear electronics waiting for NIM boxes
Virginio, Akiteru
Testing Alessandro’s new accelerometers on old IP (3 for controls and
1
for monitor).
Testing introducing asymmetry with parasitic springs.
Kenji, Akiteru
Counterweight validation started on 3 meter units.
Galli&Morelli
The weak IP joints remade within 8 hours, they are cooking since Friday
together with the filters new blades. End of cooking and shipping on
Wednesday the 17th.
Hexawire half shells shipped.
Kenji.
Tuning F0, bystable with original blades, stabilized by shortening
blades and adding tuning parasitic springs.
Edwin
measuring mini-GASF blades to select them and install in top mass of
multiple pendulum.
Virginio
GASF paper approved by Dennis with few comments, send out next week.
Ric
Preparing shipping crates.
For additional information about this report, contact sanders@ligo.caltech.edu