"Weekly" Report for Two Weeks Ending
January 2, 2001
The LIGO Executive Committee
Agenda for Monday January 8, 2001 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
-
Announcements
-
LSC Issues (Weiss)
-
Comments on Weekly Report
-
WBS 1 LIGO I Construction (Lindquist)
-
Field Change Orders/Contingency Liens/Change Requests
-
WBS 2 LIGO Lab Operations
-
Administration (Lindquist)
-
Sites (Raab, Coles, Shoemaker, Sanders)
-
Detector (Whitcomb, Coyne)
-
Campus Research Facilities (Weinstein (40 Meter), Libbrecht (TNI), Zucker(LASTI))
-
Data Analysis and Computing (Lazzarini)
-
WBS 3 and 4 Advanced R&D and LIGO II
(Sanders)
Executive Committee only 11:30 - noon
Topics:
Special Items:
Special Announcements:
Weekly
Report Highlights
Light in the "X" and "Y" Beam Tubes at Livingston.
Light in the "X" and "Y" Beam Tubes at Livingston
(more)
LSC Issues (Weiss)
no report
LIGO I Construction/LIGO Laboratory
Administration (Lindquist)
WBS 1.2 LIGO Operations--Administration
LIGO Weekly Site Telecon (Lindquist)
There was a site teleconference held on Thursday,
January 4, 2001. Discussion items included:
1) the financial reports for the end of
November 2000, total booked costs were slightly more than $20.9 million.
However, a number of large open commitments are still being booked, and
the total for the fiscal year is expected to reach $21.8 million,
2) the contract for the staging building and
Livingston, the NSF has approved the contract. Fred Asiri has submitted
a Change Request (CR-000020),
4) presentations are scheduled today at Hanford
to potential bidders for the building at Hanford,
3) laser safety, because of continuing laser
incidents as well as plans to operate at higher powers, Gary has requested
a plan by the end of the month.
The list of current actions revised to reflect
open actions assigned through January 4, 2001 may be found at
ACTION
LIST.
PROPERTY
MANAGEMENT (Chargois)
From: Ed Chargois <chargois_e@ligo.caltech.edu>
-
The State of Louisiana Property Management Branch (Mr. Thomas Jordan)
will take possession of the following GSA Items: Lathe (Monach), SN18855,
$6,863.86 and Milling Machine (Heckert), SN3211/17. These items will be
removed from the LIGO Livingston Observatory on January 4, 2001 at no cost
to the project.
-
Assisted the Seismic Isolation group (R. DeSalvo) with US Customs Clearance
and delivery of TAMA-SAS 1x1x2 meter crate at the weight of 400kg from
Italy to Caltech. This equipment will remain at Caltech until approximately
January 31, after which I will arrange shipment to Japan (Seiji Kawamura),
NAO Representative.
-
Preparing a Standard Form 120 to the National Science Foundation to Surplus
more unserviceable equipment from the LIGO Livingston Observatory.
DOCUMENT
CONTROL CENTER (Turner, Mak)
>From: Linda Turner
- turner@ligo.caltech.edu>
Web pages for the
DCC give simple how-to's for document numbering, easy access to the latest
on-line documents, and search capabilities for the DCC database. Take
a look. . .
ACCOMPLISHMENTS
-
Review of the ASIS web page continues.
Due to the complexity of the ASIS web page, this continues to be a labor-intensive
effort. First level links have been reviewed, but many documents
contain links which in turn need to be considered and carried over with
any distilling of the documents.
-
Prepared, packaged and shipped the contract
and drawings for IFB EJ-319 to Brunt Construction for signatures.
-
The table below summarizes statistically the
various activities in the DCC during the year 2000. It was quite
busy but productive for the group.
CUMULATIVE 2000 STATISTICS
FOR THE DCC
|
| |
NEW DOCUMENTS
|
FAXES
|
PACKAGES
|
PHOTOS
|
|
DATABASE
|
ELECTRONIC
|
SENT
|
REC'D
|
SENT
|
REC'D
|
PRES. PKGS
|
|
JANUARY
|
357
|
92
|
136
|
101
|
56
|
109
|
7
|
|
FEBRUARY
|
218
|
100
|
185
|
130
|
53
|
122
|
10
|
|
MARCH
|
784
|
811
|
238
|
150
|
72
|
139
|
9
|
|
APRIL
|
110
|
82
|
175
|
132
|
54
|
98
|
9
|
|
MAY
|
373
|
71
|
192
|
164
|
42
|
132
|
5
|
|
JUNE
|
108
|
93
|
153
|
152
|
57
|
127
|
4
|
|
JULY
|
151
|
69
|
130
|
143
|
52
|
123
|
17
|
|
AUGUST
|
562
|
86
|
114
|
91
|
37
|
86
|
8
|
|
SEPTEMBER
|
177
|
136
|
163
|
145
|
92
|
94
|
7
|
|
OCTOBER
|
305
|
149
|
153
|
162
|
94
|
161
|
9
|
|
NOVEMBER
|
206
|
240
|
187
|
178
|
59
|
206
|
9
|
|
DECEMBER
|
149
|
94
|
119
|
129
|
90
|
161
|
7
|
|
TOTALS
|
3,500
|
2,023
|
1,945
|
1,677
|
758
|
1,558
|
101
|
REMINDER
FOR ALL LIGO-ites
-
Electronic documents continue to come in at
a regular pace. To help keep the process streamlined and timely for
everyone:
-
File naming should be based on the root part
of the number plus the revision and without the Group ID. Additionally,
the file name should be in capitals, and the format extension in small
letters. Thus a document numbered as
-
LIGO-G990025-00-D
would have a file name of G990025-00.pdf
-
All pertinent information
needs to be on every document. This includes:
-
DCC number
-
Author's name
-
Date of document
-
Title
-
Duplicate submittals
can be confusing as well as time consuming. If you can't remember
whether a document has been submitted to the DCC, you might check the docspublic
directory to see if it resides there. Or, feel free to give us a
call so we may check for you.
From: Cleveland Mak
<mak_c@ligo.caltech.edu>
prepared, packaged, and shipped contract and drawings for IFB EJ-319 to
Brunt Construction for signatures.
distributed new Caltech 2001 directories including LHO and LLO.
progress continues on auditing of Hanford Facility drawings.
|
Packages |
Faxes |
| In |
39 |
31 |
| Out |
18 |
34 |
Press here to access
the DOCUMENT CONTROL CENTER
WEB PAGE.
COST SCHEDULE
CONTROL SYSTEMS (Cunningham, Brambila, Akutagawa, Kaufman)
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS
PAYABLE HISTORY DATA.
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
-
Just got back today from vacation. Going through my emails, mail
and new requests and cleaning up loose ends.
-
Have Triad c/o's 64 & 65 to process as invoices are pending payment.
Have a new consulting agreement for Kratochwill. On Brunt,
the poeta still needs to be set up. I understand that it should be
set up soon now by Sponsored Research.
-
Received the credit of $535.00 from Xerox who had billed for items which
should have been covered under the maintenance agreement.
-
Have a several requests to remove open encumbrances, and still have other
LIGO FY2001 transfers to be made once FY2000 payments have been made.
-
Just a reminder, the California sales tax rate dropped .25 effective Jan
2001.
From: Florence Kaufman <fkaufman@ligo.caltech.edu>
-
Worked on Operations Reports for December for FY99, FY2000, and FP2001.
-
Responded to requests from Federal Accounting for additional information
related to setting up Fabrication Project for Livingston building.
-
Continued working on transferring encumbrances to new fiscal period.
SUBCONTRACTS MANAGEMENT (Petrac,
Jasnow)
From: irena@ligo.caltech.edu (Irena Petrac)
-
Univ. of Florida: A draft proposal for the collaboration of the Institute
of Applied Physics (IAP) was received and is in Project review.
-
Invoices for August, September and October are being re-submitted to reflect
the correct (off-site) burden.
-
FDC: Proposal for FY'01 rate increases was received. LIGO's counter-offer
was communicated to FDC.
-
Open LIGO Sub-contracts: All open subcontracts for LIGO support activity
will be extended through Nov. 31, 2001. Cognizant Engineers will be contacted
for concurrences.
From: Ed Jasnow <jasnow@ligo.caltech.edu>
-
The search continues for an effective security system for the safe operation
of the laser. At the same time, discussion continues regarding the
amount of research which must be performed while the laser is on.
Support (Wood)
Dorothy Lloyd
Irene Baldon
-
Please Note: This report is for three (3) days only due to my vacation
and the holidays.
-
Seven (7) new trips were started and I have four (4) trips pending final
approval before tickets can be issued with eight (8) trips finalized and
paper work pending completion. Most of these trips required Advance
Checks to be written as well as hotel and car authorization forms to be
filled out and FAXed to the appropriate location.
-
Reconciled thirty-one (31) items on my P-Card this week. Several
items were difficult to track down since the vendor's 3rd level information
was sketchy at best. This requires phone calls for clarification
from the vendor and sometimes takes a considerable amount of time.
I'm working with some of our frequent vendors to see what can be done to
include more information on their 3rd level information. Worked with
a few travelers who had questions or needed further clarification on using
or reconciling their new P-Cards. For the most part those having
cards seem to be doing fine and find the cards a convenience.
-
Worked on and completed six (6) Expense Reports. Liz worked on twenty-five
(25) reports while I was gone and I will do a final check before sending
them on to Travel Audit for payment. Worked with Jim from Dorothy's
area to familiarize him with the Expense Report and he has two (2) reports
at the present that he is working on. I have thirty (30) Expense
Reports to work on and I'm holding one (1) report which needs a check from
the traveler before processing. The new Expense
Report that I sent out a couple of weeks ago is not being used by most
of our Travelers. I ask that everyone please use this new form.
If you have any questions on its use please contact me. Everyone
who is using this form seems to be adjusting to it quite nicely.
I continue to make myself available for any assistance they may need.
-
I would like to remind all travelers that if your flight is considerably
delayed or completely canceled, and Gina or I are not available to personally
assist you in rearranging your itinerary or notifying the hotels and car
rentals of your delay (i.e., after working hours here in California), that
you as the traveler are responsible for calling either the number listed
on your Itinerary, their 800 number, or even a local number (or airport
desk) for the vendor. Please let them know that you will either be
late or a No Show otherwise you will be charged a No Show Fee.
-
Prepared the Travel/Vacation Itinerary for the Week of January 2, 2001.
Performed normal recording and filing associated with Travel and Reimbursement.
Worked on several problem issues with Travel Audit in addition to the above
listed issues. Also performed miscellaneous duties as requested by
various members of the LIGO Project here at Caltech as well as from
members of the staffs of each of the two (2) sites. I continue
to do MIT's travel to the sites for installation activities and also to
assist them wherever possible.
Rita Torres
-
Prepared letters and FedEx packages for: V. Cook at NSF, and Attachment
Z for U. of FL. Scanned for the web page: Attachment Z & C to
IAP, Attachment Z to Wisconsin-Milwaukee, Attachment B to Iowa State, and
Attachment 2 to Virgo. Continue to do requisitions in D. Lloyd's
absence.
-
During the quiet time in the office, I was able to update safety records,
and street addresses (for FedEx deliveries) for LSC entities, organize
Pcard and subcontract records, and generally organize my work area.
Was also able to start a schedule for 2001 site trips, and to restock needed
office supplies.
-
Spent time obtaining from Grainger keys that should have come with a cabinet.
Organized correspondence for R. DeSalvo. Ongoing activity: The usual
quest for pertinent information associated with Pcard purchases.
Elizabeth K. Wood
-
Continuing with logistical details concerning the NSF Proposal review at
the end of this month and next month.
-
Dealt what seems like an increasing number of personnel issues.
-
Did some travel reimbursements for Irene during the Christmas break.
Advanced LIGO (Frey, Petrac)
From:
Thomas Frey <tfrey@ligo.caltech.edu>
Progress Period from 12.22 to 01.04
Accomplishments:
-
Out of Office on 12.22, 12.25, 12.29, and 01.01.
-
No Advanced LIGO Project Controls meetings held during this period due
to holidays and short work week.
-
Proposal plan development for Advanced LIGO MRE continues.
-
Review of cost and schedule data is Continuing.
-
Completed latest changes to AOS schedule per meeting with Mike Smith and
data developed by Dennis Coyne for R&D.
-
Followed up with Garilynn B. regarding schedule and cost data for COC.
-
Followed up with Peter K. regarding schedule and cost data for PSL.
Meeting scheduled with Dennis Coyne on Monday the 8th at 1pm at SSCR.
-
Project Plan for the 40-Meter Lab Upgrade continues.
-
Waiting for comments from Alan and Mike regarding their requested changes
that have been input.
-
Planning process for the LASTI project at MIT is in progress.
-
Changes are pending from David per his discussions with GEO regarding the
acceleration of prototype noise testing.
-
Continue to test the Cost Book Tool.
-
Began mapping and formatting of OPs cost data for input. Ran test
data and found issues with cost book calculations.
-
Met with Barbara Kratochwill to discuss the adjustments and effort is proceeding.
-
Began preparation of changes to data required for BK to program changes.
-
Development of the Advanced LIGO Project Controls Guidebook continues.
-
Project Web Site for posting schedule and progress related data continues
to be updated with the latest and greatest.
Schedule 01.05 to 01.11:
-
Next weekly meeting will be Tuesday afternoon January 16th from 1 to 2pm
regarding the planning and control of the Advanced LIGO MRE proposal development.
-
Continue to pursue the planning and scheduling of the staging buildings
currently being bid and designed for HLO and LLO.
-
Advanced LIGO Proposal
-
Will continue the effort of contacting each system leader to collect cost
and schedule data. Hope to begin importing schedules and cost ASAP.
-
AOS and IO hope to be ready for presentation during NSF review in January.
-
Will continue input of AOS and IO to the cost book and schedule.
Hope to have data from David Reitze for IO by the 8th. AOS is pending
review by Mike Smith, Mike Zucker, and Dennis Coyne.
-
Meeting scheduled with Dennis Coyne on Monday the 8th at 1pm at SSCR to
discuss PSL schedule and cost status.
-
Hope to have data for COC by 16th.
-
Will Continue to update the LASTI Schedule with progress.
-
Will post progress report by end of day Tuesday the 9th with progress as
of 01.05.01.
-
Will issue 23rd week of status data to teams by the 9th.
-
Will continue to update the Advanced LIGO / Ops Proposal Plans and incorporate
any changes.
-
Will post progress report by end of day Tuesday the 9th with progress as
of 01.05.01.
-
Will issue 23rd week of status data to teams by the 9th.
-
Will continue updating the 40 meter schedule and incorporate any changes.
-
Will post progress report by end of day Tuesday the 9th with progress as
of 01.05.01.
-
Will issue 23rd week of status data to teams by the 9th.
-
Will meet with Alan to review development of 40-Meter experiment tasks.
-
Continue to test the Cost Book Tool.
-
Cost Book Tool development continues.
-
Will provide BK with the data she needs to program adjustments to the cost
book tool.
-
Input of OPs cost data will continue.
-
Will continue the development of the Advanced LIGO Project Web Site.
-
Will continue the development of the Advanced LIGO Project Controls Guide
Book.
Anticipated Challenges:
None to
report at this time.
Corrective
Action:
None to
report at this time.
WBS 1.4.1.2 Project Controls (LIGO Construction)
Reports (Lindquist)
Annual Report: Currently working the Annual Report.
Change Control/Contingency (Lindquist)
The following Change Requests have
been submitted:
| CR-000018 |
WBS 1.1.4 |
Curbing for Service Roads at Livingston |
G. Stapfer |
| CR-000019 |
WBS 1.2 |
Additional Lab Equipment |
D. Coyne |
| CR-000020 |
WBS 1.1.4 |
Livingston Storage and Staging Building Contract and Associated Costs |
F. Asiri |
Press for the latest Contingency
Needs Projection.
COST SCHEDULE CONTROL SYSTEMS (Duncan,
Akutagawa)
From: Kris Duncan <kris@ligo.caltech.edu>
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
-
No report this week (vacation).
SUBCONTRACTS MANAGEMENT (Petrac,
Jasnow)
From: Ed Jasnow <jasnow@ligo.caltech.edu>
-
On December 27, the NSF approved the award of the contract for the new
Livingston Staging Building to the Brunt Construction Company in the amount
of $1,947,000. The contract will be executed early next week, with
the kickoff meeting scheduled for January 9 in Livingston.
-
Presentations for the new Hanford Support Building were made by two architect/engineering
firms on January 4. They were Nils Finney Architects of Seattle,
and SCM Consultants of Kennewick. Both firms presented their qualifications
to the review committee at Hanford, which felt that both firms were qualified.
One more firm will present its qualifications in California on January
24, following which a decision will be made.
From: irena@ligo.caltech.edu (Irena Petrac)
-
No report (see Operations Section above).
Quality/Safety (Tyler)
>From: Bill Tyler <tyler@ligo.caltech.edu>
No report.
LIGO Hanford Observatory (LHO) Operations
(Raab).
General Items (F. Raab)
The last two weeks have had no commissioning activities, allowing us
to address some items that have needed attention. Examples are updates
to the general computing and CDS environments, rationalization of cable
layouts in the control room, and modifications to the 2K PSL to increase
output power. We believe all will be back in operating order by Monday,
Jan. 8. We also expect to be ready for installation into chambers by Jan
15.
Computing (C. Patton)
The file and email servers were successfully upgraded last week.
Over the next few weeks I will be moving user accounts around to provide
more disk space for everyone. I will also be setting up the anonymous
ftp and upgrading the web server.
LIGO Livingston Observatory (LLO) Operations
(Coles).
Two very important milestones were attained
at LLO this week. On January 3, we opened the X-arm beamtube for the first
time, and found the projected laser beam striking the ETMx LOS just above
the optic. The return beam at ITMx wasn't found quite so easily, but we
did finally locate it and almost immediately noted resonance flashes recorded
by the ETM transmission monitor. See the Jan 3 LLO i-log (http://www.ligo-la.caltech.edu/ilog/pub/ilog.cgi)
for detailed notes and images of the beams striking the towers. Furthermore,
on January 4 the gate valves on the Y-end station were opened and once
again, without any adjustments to the optic biases, the beam was seen on
the ETM-y AND the return beam spot could clearly be seen on ITM-y. These
are two very significant milestones for LLO! Thanks to all of the LLO staff
and visitors for their sustained efforts to make these achievements possible.
CDS: X-end station cabling installed for QPD-x, using DAQ channel for
accel X to view sum of QPD-X. At the Y-end station, the calbling for QPD-y
was installed and the quad cell was found to be bad, and was replaced with
a working one by Jonathan Kern. Also, the clock driver in the crate was
replaced. (Wooley, Fyffe)
Detector/Technical Support (Whitcomb,
Coyne).
1.1 LHO
INSTALLATION & COMMISSIONING
2km Commissioning
Bill Kells, Erica d'Ambrosio
Mostly cranking the FFT
code up to full productivity on "Mulder" one of the HP V2500 CACR machines.
Suprisingly many bugs with their operations, etc. so this was not insignificant.
It is now at a usefull level roughly equivalent to former days on TREX.
Used above to study behaviour of PRM at LHO. Usefull results to appear
this week (will sent e-mail and post in e-log).
COS
Mike Smith, Ken Mailand, Betsy
Weaver
Updated installation drawings
for the LHO end station installation of the COS ETM telescope, beam dump
and arm cavity baffle are being prepared. An retroreflecting mirror assembly
for aiding in the alignment of the ETM telescope beam dump was fabricated.
COS autocollimators were shipped to LHO.
PSL
Peter King
Adapter plates for the new
mounting scheme for the phase-correcting electro-optic modulator (EOM)
have arrived. The new mounting scheme involves mounting the EOM to
a low-height goniometer instead of a four-axis tilt stage. The goniometers
will be shipped to LHO as soon as they arrive from the manufacturer.
1.2
LLO INSTALLATION & COMMISSIONING
Commissioning
Rai Weiss, Mike Zucker and everyone
at LLO
A plan for the commissioning
activities during January has been circulated. The plan involves first
opening the arms to determine the alignment. During the middle two weeks
of January extensive work will be done to align the detection tables and
bring the RF and digital servo electronics into operation. At the end of
the month attempts will be made to lock the single arm cavities and the
Fabry-Perot/Michelson without recycling.
Jan 3 we opened the x arm
and found the beam within 30 microradians of the aligned position. The
cavity was aligned and produced flashes. The beam size was measured crudely
and it was determined and found not to be well mode matched. There is an
indication that the ITMX reflecting surface has more scattering than the
mirrors at Hanford.
In the next few days we expect
to open the y arm and determine its alignment.
#SEW# This is a tremendous
achivement that should be savored by all who contributed. And in
late breaking news, I have just heard that the Y arm has been checked and
was almost as close as the x-arm! Congratulations to all!
ISC
Mike Zucker
Completed tuning and characterization
of LLO length sensing photodetectors and shipped to LLO.
2.0 Other
Engineering and Scientific Activities
2.1 Design/Analysis/Fab
Optical Metrology
Helena Armandula, GariLynn Billingsley
Because the temperature
has been very unstable in the lab., still taking data on 2ITM02. Expect
to be finished on Monday.
PSL
Peter King
Performance characterization
of the new pre-modecleaner (PMC) are still on-going. Initially the
PMC was left where it was located on a previous occassion. Since
that time the 10-W laser has been removed from the optical table, re-installed
and re-aligned. The output of the laser was aligned into the PMC
without re-measuring the beam waist location and the PMC throughput was
approximately 75%. The output of the laser has been re-measured and
the mode-matching lenses re-positioned. This should improve the throughput
since things have been checked. The previous exercise was more a
curiosity study to see what we could get away with.
I have been trying to simulate
the performance of a high-power photodiode with PSpice, without much luck
so far. The problem being that I haven't figured out how to incorporate
the Spice model provided by the manufacturer of the op-amp used into the
PSpice model. When a "generic" op-amp is substituted the circuit
seems to have the right characteristics that I intended.
The table for the LASTI PSL
is being tracked down, since I was expecting it to be delivered just before
Christmas to MIT.
For reasons not entirely
obvious to me, the computer down in the PSL Lab no longer allows local
console logins. This problem seems to have originated since Christmas.
Lisa did fix the problem once before, why it has returned is not clear
to me. In addition there was a problem with the /etc/hosts file on
luna because the IP address for scipe25 was incorrect, resulting in the
input/output controller not being able to boot from luna.
Rick Karwoski, Paul Russell,
Ben Abbott
The following is the status
on the PSL Frequency Reference suite of boards:
Photo detector module -- Bench
test complete, assembled
Frequency Reference -- Bench
test complete
80 MHz VCO -- Bench test
complete
Servo -- 80% tested
These boards are due at
Hanford by January 15. We will take the additional time to burn them in
and run them as a group at the Lauritsen Laser lab.
ISC
Mohana Mageswaran
I have finished testing
the MC Servo board, and I am doing the documentation for the tested board.
Modulated OSEM Design
Jay Heefner
5 stabilized oscillator satellite
amps are stuffed and being tested. They should be complete by 1/10/01.
New OSEM Heads
Peter Fritschel, Myron McInnis,
Fred Miller
Busy assembling and testing
the new osems for the LHO 4k interferometer. We are approximately 40% complete
on this first set, and the production rate has increased as problems are
worked out. The biggest problem has been that the screws used to hold the
pin-plate and connector onto the rear of the body would not thread into
the tapped holes in the alumina. The solution has been to etch down the
OD of the screw threads by about 5-mils, followed by a re-passivation of
the ss screws. We are shipping 15 long heads to LHO today. The rest of
the heads should be completed by the end of next week.
Janeen Romie,
Betsy is preparing to do
a second bake on a number of heads tomorrow or Friday at Hanford. I'm working
on travelers and the process spec.
Progressive Technology is
still trying to remove the metalization from some of the heads so they
may be recoated. They are having mixed success. I am researching other
methods. Progressive Technology reports that the second batch of alumina
heads should be complete at the end of this month.
Digital Suspensions
Jay Heefner
8 additional PD whitening/Interface
boards have been tested. We now have enough to complete the 4K IFO.
SOS dewhitening amps are due
back this week.
LOS Bias modules are stuffed
and ready for test.
SOS coil driver board layout
will be complete by 1/5/01. This is the last board needed for initial installation
and test of the SOS controls.
DMT
John Zweizig
I have been collecting numerous
changes made on the fly to the various DMT components and merging them
into the cvs source repository. I will release this version soon. Several
changes were made in the CDS configuration over the holidays and some manual
intervention was necessary to make the DMT run after these changes. Apart
from these minor tweaks, the DMT seems to have been running smoothly.
2.2 Issues
Concerns
Nothing new.
40 Meter Interferometer (Weinstein).
-
Steve Vass has suggested a major change to the layout of the 40m vacuum
envelope. Previously, we planned to install the second side chamber (the
"Output Optic Chamber OOC") on the north side of the beamsplitter chamber
(the dark port side) to house the signal mirror. This was problematical,
because it leaves no room between the OOC and the north wall of the building
to pass through - we'd need to build a bridge to get by. Now, we plan to
put the signal mirror in the beamsplitter chamber, and the dark port beam
can be folded in any direction. Mike Smith will see if he can send the
beam back in the direction of the PSL. Then, and we can put the OOC to
the west of the input optic chamber (IOC), which houses two of the three
input mode cleaner (IMC) mirrors, and put the output mode cleaner OMC (and
associated optics) in the OOC. He will see if he can get ALL output beams
out in that direction, so that they ALL go out to one huge table to the
south of these chambers, next to all the electronics. (All output beams:
bright port, dark port, three PRC pickoff beams, IMC transmitted, IMC reflected,
OMC transmitted (DCGW signal), OMC reflected; for a total of NINE beams).
Confused? Maybe a diagram
will help. And here's a more detailed engineering
drawing from Larry Jones.
-
Mike Smith is working on the Autocad layout of the entire IFO, including
optics, beams, vacuum envelope, building walls, etc. He's finished the
layout of the new input mode cleaner. He will merge in Autocad drawings
of the building walls, electrical panels, CDS racks, etc. He will see if
he can rearrange the beams to accomadate the layout proposed above.
-
Nine CDS racks have been delivered to the 40m lab. The floor (new tiles)
will be cleaned and polished, and the racks put into place. They won't
be bolted down until we have a "final" layout (see above).
-
STACIS: the stacis active seismic isolation system has been on and in continuous
operation for 3 weeks. There are two problems:
-
As we noticed immediately after installation (and even before), transfer
function spectra taken with geophones and natural ground motion show no
evidence for passive isolation (which there should be). The folks at TMC
finally admit that it doesn't look right. We will continue to investigate
this.
-
We have 12 isolators, each with 3 axes of control. Of these 36 loops, two
appear to be malfunctioning. One (the first isolator we installed) is particularly
bad: it rattles, the servo indicator oscillates, and the fault light is
on. We will get TMC to diagnose and fix. TMC suggested that we might have
too much horizontal load, and horizontal load drift, on the isolators.
Larry Jones doesn't think so, but to make sure, he has unloaded and reloaded
ALL isolators, taking care to minimize any horizontal load. That first
isolator still looks sick.
-
Details: web
page, postscript,
pdf.
-
Report on building rehab, from Fred Asiri:
-
The roofers are done, but they need for the roof to settle for 2 weeks
before they come back for final inspection and patching, and replacing
the ceiling tiles in the North Annex.
-
Only a few items remain for the contractor: a little paint touch-up, some
plumbing patching, door and pipe sealing, safety windows installed on several
doors, smoke sensors installed, laser kill switch wiring.
-
The second of two power conditioners is due to be shipped to us this week.
-
After a year of work, the building rehab is just-about done!
-
Many thanks to Fred Asiri, and we wish him all the best in his new job!
-
Larry Jones reports that parts for the side chamber seismic stack, and
for input mode cleaner vacuum envelope, are being cleaned, tested, and
baked, at Allied and at Livingston (Rich Riesen and company). He expects
all these pieces to be back at Caltech by the end of January.
-
Larry has ordered a new 29" door with 10" port for the side chamber to
accomadate the input mode cleaner. Should take 4-6 weeks. Steve has ordered
all the other vacuum envelope hardware for the MC, and everything should
be cleaned and baked, and ready for installation, by the end of February.
Steve Vass will assemble the MC vacuum envelope and pump down and RGA test,
before connecting it to the main IFO vacuum envelope.
-
Vacuum controls (Ben Abbott and Dennis Ugolini): all wiring and other hardware
for the vacuum control system is done. The full system can't be tested
until (a) nitrogen lines for the pneumatic valve controls, removed for
STACIS installation, are re-installed; (b) chamber annulus plumbing, dismantled
for STACIS installation, is re-plumbed; (c) five ion pumps are regenerated
and reinstalled with new gate valves. This should all happen in the next
2 months. Otherwise, the system is ready to go. Steve Vass will have Varian
regenerate and refurbish the five (Varian-made) ion pumps.
-
PSL (Rick Karwoski, Ben Abbott): all the boards for the H4K PSL are complete,
they will now prepare updated documentation and begin to assemble pieces
for the 40m and LASTI PSLs.
(Jay Heefner)
-
9 racks were delivered to the lab.
Thermal Noise Interferometer (Libbrecht).
No report this week.
LASTI (Zucker).
LASTI (Jay Heefner)
-
Two VME crates for the DAQ system were received and forwarded to MIT.
-
5 racks have been shipped from the vendor and should arrive at MIT by next
week.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling (Yamamoto)
> physics simulaion (B.Bhawal, H.Yamamoto)
The seismic noise study continued. High pass filters are used to whiten
the seismic noise and we confirmed the correct spectrum below 100 Hz was
generated within a short simulation time (100 sec), We compared this to
the case with no high pass filter which took va ery long (5000 sec) to
calculate correct psd at high frequency.
To pinpoint the effect of the numerical accuracy limit ( double precision
has an accuracy of 15 digits, but the simulation involves many number manipulations,
it looks like 10 to 11 digits is the effective dynamic range covered ),
Hiro wrote a program with a digital filter
and psd to be compiled with double precision and quadruple preciosion
accuracy.
Biplab will focus on the study of the effect of the optics misalignment
on the lock acquisition.
> simulation engine parallelization (T.Dangelis)
algorithm/implementation to produce a one-execNode 'tick list' was written
and incorporated into the program after partitioning.
algorithm/implementation for finding the 'ideal-arrival-time', a topology
metric, was written, along with a not-yet-working version of a 'node-to-node
distance' metric.
> GUI (E.Maros, B.Sears)
Improving alfi, the GUI frontend of e2e. Ed is implementing copy and
paste. A new release is expected next monday, which will be based on a
new version of xwWindow. Bruce is implementing a new inferace for setting
parameter.
LIGO Data Analysis System
Software Systems (Blackburn)
LDAS is busy preparing a new release of the software in support of the
MDC activities expected to cover the bulk of January and February. The
MPI Group from UWM will begin arriving the middle of next week as we setup
and prepare for the MPI Mock Data Challenge to begin the following Monday
morning. Activities associated with the Database Mock Data Challenge will
also begin to ramp up during the next couple of weeks.
The mpiAPI and the wrapperAPI are presently considered to be in very
good shape for this MDC. An LDAS user command is also available for starting
jobs on the BEOWULF. This command has been lightly tested and looks to
have all the necessary functionality needed for the MDC. One issue that
has come up is the inability to completely control the host(node) assignment
list used in MPI jobs using LAM. These hasn't been looked at in great details
so there may be a simple configuration option to manage this at compile
time or run time. The good news however is that we have finally run a parallel
LDAS wrapperAPI job on all 16(17) nodes of our new LDAS
development Beowulf system to completion.
As part of our normal procedures for getting a software release out
the door, we have begun daily and nightly builds of LDAS and associated
tests of the various components. This pre-release is showing better data
socket communication rates of ILWD data objects between hosts, but has
identified a 50% slow down in the performance of our database. There is
a possibility that this 50% slowdown is due to a misunderstanding of the
exact date that we changed the database hardware on the development system
from a Sun 450 to a Sun Ultra10. A follow-up test is being performed today
on a different LDAS system with a Sun 450 for the dataserver to verify
if a problem actually exists.
The new UDT data class in the dataConditionAPI has brought with it the
expected increase in open problem reports. However, this week we were able
to make some headway into resolving several bugs and closing out a significant
number of reports. The group also decided to take inventory of the software
components that are being moved over to the new UDT model and use this
as a baseline to track progress towards a complete transformation of the
data-ConditionAPI over to the UDT model.
The LDAS development, test and Livingston databases are now using the
updated IBM DB2 7.1 server. This server has shown about a 10% increase
in performance over the DB2 6.2 server we were previously using on our
Sun servers. To support this new version of DB2, new tables were generated
on the three systems.
The documentation of LDAS is also being overhauled in preparation for
this new release. Several APIs were not able to generate web-based documentation
using our new PERCEPS document generator. These have for the most part
been fixed. However, in one particularly difficult case, we have introduced
an ingnore command to avoid segments of C++ code that corrupt documentation
files.
Hardware Systems (Anderson)
-
The upgrade of DB2 is going smoothly (only LHO remains).
-
Competitive quotes for the LDAS tape silo have been obtained.
-
The LDAS AIT-2 robot has been delivered to LLO.
General Computing
MIT:
-
New systems administrator/programmer hired, Keith Bayer, to start 12 February.
Livingston:
-
(Tom E.) We are continuing to work on upgrading our web and e-mail server.
Both functions are currently performed by the same machine, and we are
putting them on separate machines to improve both performance and reliability.
-
(Larry) Albert has received confirmation from the Abilene group that Livingston
will be a sponsored site going through the existing LAnet.
Hanford:
-
(Christine P.) The file and e-mail servers were successfully upgraded last
week. Over the next few weeks I will be moving user accounts around
to provide more disk space for everyone. I will also be setting up the
anonymous ftp and upgrading the web server.
-
(Larry) Albert has received confirmation from the Abilene group that Hanford
will be a sponsored site going through the existing ESnet.
CIT:
-
(Sam) Swapped in the replacement scanner. Answered various user questions.
Worked on this years inventory. Started back to school.
-
(Lisa) Working on the new modem pool. The replacement equipment has finally
arrived.
-
(Barbara) Worked a few costbook and web issues. Presently, trying to resolve
some data mirroring issues.
-
(Suresh) Completed monthly full backups of LIGO servers. After observing
some of the servers had network connection problem, I did recabling of
servers in computer room in holidays. Installed and mounted a FORE 2810
ethernet switch in network closet in computer room. At least one server
is connected there.
-
(Larry)
-Worked on monthly backups.
-Ordered a few more computers and delivered a new laptop. Presently,
the only laptops we are supporting are the Dell and IBM with configurations
that LINUX supports.
-Worked with Suresh on installing a paper sorter for DCC's new printer.
-Modified a few scripts to work on other servers.
-Working on getting the SDRC license updated for the rest of the year.
LIGO II/Advanced R&D (Sanders)
LIGO II Coatings (Helena Armandula)
Received a reply to a coating inquiry that was sent to Laser Zentrum
Hannover about the company's interest and ability to provide LIGO II coatings.
They expressed interest to work with LIGO. At this time they do not
have the techniques required to meet our specs. However, they said
that with development work, they'll meet our requirements and schedule.
They quoted the LIGO work based on available facilities ? ? and the quote
is very reasonable. Some further investigation will be required to
assess their capabilities.
Optics (Garilynn Billingsley)
We now have a homogeneity phase map of the first 25 x 10 cm sapphire
substrate measured at Caltech. The measurement shows the central
150 mm of the first 250 mm sample. Peak to valley inhomogeneity is in the
400 nm range, rms is on the order of 50 nm. Uncertainty is ~5nm due
to turbulence. More
Detail
LIGO II PSL (Peter King)
Apparently the quote given to me for the pump laser diodes was not the
"best" deal that Coherent could do. Just how good a deal they would be
prepared to do was not indicated to me but I was told there was room to
negotiate on the quotation that they provided.
(Bill Kells)
Got R. Beausoleil to revise MELODY [again] to fix nominal inconsistancies.
Performed Rayleigh scatter measurements on Sapphire substrates.
Seismic Attenuation (Riccardo DeSalvo)
No report.
For additional information about this report, contact sanders@ligo.caltech.edu