"Weekly" Report for Two Weeks Ending January 2, 2001


 Exec. Comm. Agenda
Highlights
LSC
Administration
Hanford Observatory
Livingston Observatory
MIT
Caltech
Detector
40 Meter
TNI
LASTI
Data Analysis
LIGO II/Adv. R&D
Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  January 8, 2001 will be:
 (Meeting time: 10:30 am Pacific Time)

Open meeting 10:30 - 11:30

  1. Announcements
  2. LSC Issues (Weiss)
  3. Comments on Weekly Report
  4. WBS 1 LIGO I Construction (Lindquist)
  5. WBS 2 LIGO Lab Operations
  6. WBS 3 and 4  Advanced R&D and LIGO II (Sanders)
Executive Committee only 11:30 - noon   Topics:
 

Special Items:


Special Announcements:


Weekly Report Highlights

Light in the "X" and "Y" Beam Tubes at Livingston.

Light in the "X" and "Y" Beam Tubes at Livingston (more)


LSC Issues (Weiss)


no report


LIGO I Construction/LIGO Laboratory Administration (Lindquist)


WBS 1.2 LIGO Operations--Administration


LIGO Weekly Site Telecon (Lindquist)

There was a site teleconference held on Thursday, January 4, 2001.  Discussion items included:
1) the financial reports  for the end of November 2000, total booked costs were slightly more than $20.9 million.  However, a number of large open commitments are still being booked, and the total for the fiscal year is expected to reach $21.8 million,
2) the contract for the staging building and Livingston, the NSF has approved the contract. Fred Asiri has submitted a Change Request (CR-000020),
4) presentations are scheduled today at Hanford to potential bidders for the building at Hanford,
3) laser safety, because of continuing laser incidents as well as plans to operate at higher powers, Gary has requested a plan by the end of the month.

The list of current actions revised to reflect open actions assigned through January 4, 2001 may be found at ACTION LIST.


PROPERTY MANAGEMENT (Chargois)

From: Ed Chargois <chargois_e@ligo.caltech.edu>


DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner - turner@ligo.caltech.edu>

Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .

ACCOMPLISHMENTS

REMINDER FOR ALL LIGO-ites From: Cleveland Mak <mak_c@ligo.caltech.edu>
  • prepared, packaged, and shipped contract and drawings for IFB EJ-319 to Brunt Construction for signatures.
  • distributed new Caltech 2001 directories including LHO and LLO.
  • progress continues on auditing of Hanford Facility drawings.
  • Packages Faxes
    In 39 31
    Out 18 34

    Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.


    COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Akutagawa, Kaufman)

    From: Esther Cunningham <esther@ligo.caltech.edu>

    Press here for ACCOUNTS PAYABLE HISTORY DATA.

    From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

    From: Florence Kaufman <fkaufman@ligo.caltech.edu>

    SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

    From: irena@ligo.caltech.edu (Irena Petrac)

    From: Ed Jasnow <jasnow@ligo.caltech.edu>



    Support (Wood)
     
    Dorothy Lloyd
    • Dorothy is on vacation.
    Irene Baldon
    • Please Note:  This report is for three (3) days only due to my vacation and the holidays.
    • Seven (7) new trips were started and I have four (4) trips pending final approval before tickets can be issued with eight (8) trips finalized and paper work pending completion.  Most of these trips required Advance Checks to be written as well as hotel and car authorization forms to be filled out and FAXed to the appropriate location.
    • Reconciled thirty-one (31) items on my P-Card this week.  Several items were difficult to track down since the vendor's 3rd level information was sketchy at best.  This requires phone calls for clarification from the vendor and sometimes takes a considerable amount of time.  I'm working with some of our frequent vendors to see what can be done to include more information on their 3rd level information.  Worked with a few travelers who had questions or needed further clarification on using or reconciling their new P-Cards.  For the most part those having cards seem to be doing fine and find the cards a convenience.
    • Worked on and completed six (6) Expense Reports.  Liz worked on twenty-five (25) reports while I was gone and I will do a final check before sending them on to Travel Audit for payment.  Worked with Jim from Dorothy's area to familiarize him with the Expense Report and he has two (2) reports at the present that he is working on.  I have thirty (30) Expense Reports to work on and I'm holding one (1) report which needs a check from the traveler before processing.  The new Expense Report that I sent out a couple of weeks ago is not being used by most of our Travelers.  I ask that everyone please use this new form.  If you have any questions on its use please contact me.  Everyone who is using this form seems to be adjusting to it quite nicely.  I continue to make myself available for any assistance they may need.
    • I would like to remind all travelers that if your flight is considerably delayed or completely canceled, and Gina or I are not available to personally assist you in rearranging your itinerary or notifying the hotels and car rentals of your delay (i.e., after working hours here in California), that you as the traveler are responsible for calling either the number listed on your Itinerary, their 800 number, or even a local number (or airport desk) for the vendor.  Please let them know that you will either be late or a No Show otherwise you will be charged a No Show Fee.
    • Prepared the Travel/Vacation Itinerary for the Week of January 2, 2001.  Performed normal recording and filing associated with Travel and Reimbursement.  Worked on several problem issues with Travel Audit in addition to the above listed issues.  Also performed miscellaneous duties as requested by various members of  the LIGO Project here at Caltech as well as from members of the staffs of each of the two (2) sites.   I continue to do MIT's travel to the sites for installation activities and also to assist them wherever possible.
    Rita Torres
    • Prepared letters and FedEx packages for: V. Cook at NSF, and Attachment Z for U. of FL.  Scanned for the web page: Attachment Z & C to IAP, Attachment Z to Wisconsin-Milwaukee, Attachment B to Iowa State, and Attachment 2 to Virgo.  Continue to do requisitions in D. Lloyd's absence.
    • During the quiet time in the office, I was able to update safety records, and street addresses (for FedEx deliveries) for LSC entities, organize Pcard and subcontract records, and generally organize my work area.  Was also able to start a schedule for 2001 site trips, and to restock needed office supplies.
    • Spent time obtaining from Grainger keys that should have come with a cabinet.  Organized correspondence for R. DeSalvo.  Ongoing activity: The usual quest for pertinent information associated with Pcard purchases.
    Elizabeth K. Wood
    • Continuing with logistical details concerning the NSF Proposal review at the end of this month and next month.
    • Dealt what seems like an increasing number of personnel issues.
    • Did some travel reimbursements for Irene during the Christmas break.

    Advanced LIGO (Frey, Petrac)

    From: Thomas Frey <tfrey@ligo.caltech.edu>
    Progress Period from 12.22 to 01.04

    Accomplishments:

    • Out of Office on 12.22, 12.25, 12.29, and 01.01.
    • No Advanced LIGO Project Controls meetings held during this period due to holidays and short work week.
    • Proposal plan development for Advanced LIGO MRE continues.
      • Review of cost and schedule data is Continuing.
      • Completed latest changes to AOS schedule per meeting with Mike Smith and data developed by Dennis Coyne for R&D.
      • Followed up with Garilynn B. regarding schedule and cost data for COC.
      • Followed up with Peter K. regarding schedule and cost data for PSL.  Meeting scheduled with Dennis Coyne on Monday the 8th at 1pm at SSCR.
    • Project Plan for the 40-Meter Lab Upgrade continues.
      • Waiting for comments from Alan and Mike regarding their requested changes that have been input.
    • Planning process for the LASTI project at MIT is in progress.
      • Changes are pending from David per his discussions with GEO regarding the acceleration of prototype noise testing.
    • Continue to test the Cost Book Tool.
      • Began mapping and formatting of OPs cost data for input.  Ran test data and found issues with cost book calculations.
      • Met with Barbara Kratochwill to discuss the adjustments and effort is proceeding.
      • Began preparation of changes to data required for BK to program changes.
    • Development of the Advanced LIGO Project Controls Guidebook continues.
    • Project Web Site for posting schedule and progress related data continues to be updated with the latest and greatest.
    Schedule 01.05 to 01.11:
    • Next weekly meeting will be Tuesday afternoon January 16th from 1 to 2pm regarding the planning and control of the Advanced LIGO MRE proposal development.
    • Continue to pursue the planning and scheduling of the staging buildings currently being bid and designed for HLO and LLO.
    • Advanced LIGO Proposal
      • Will continue the effort of contacting each system leader to collect cost and schedule data.  Hope to begin importing schedules and cost ASAP.
      • AOS and IO hope to be ready for presentation during NSF review in January.
      • Will continue input of AOS and IO to the cost book and schedule.  Hope to have data from David Reitze for IO by the 8th.  AOS is pending review by Mike Smith, Mike Zucker, and Dennis Coyne.
      • Meeting scheduled with Dennis Coyne on Monday the 8th at 1pm at SSCR to discuss PSL schedule and cost status.
      • Hope to have data for COC by 16th.
    • Will Continue to update the LASTI Schedule with progress.
      • Will post progress report by end of day Tuesday the 9th with progress as of 01.05.01.
      • Will issue 23rd week of status data to teams by the 9th.
    • Will continue to update the Advanced LIGO / Ops Proposal Plans and incorporate any changes.
      • Will post progress report by end of day Tuesday the 9th with progress as of 01.05.01.
      • Will issue 23rd week of status data to teams by the 9th.
    • Will continue updating the 40 meter schedule and incorporate any changes.
      • Will post progress report by end of day Tuesday the 9th with progress as of 01.05.01.
      • Will issue 23rd week of status data to teams by the 9th.
      • Will meet with Alan to review development of 40-Meter experiment tasks.
    • Continue to test the Cost Book Tool.
    • Cost Book Tool development continues.
      • Will provide BK with the data she needs to program adjustments to the cost book tool.
      • Input of OPs cost data will continue.
    • Will continue the development of the Advanced LIGO Project Web Site.
    • Will continue the development of the Advanced LIGO Project Controls Guide Book.
    Anticipated Challenges:
    None to report at this time.
    Corrective Action:
    None to report at this time.
    WBS 1.4.1.2   Project Controls (LIGO Construction)


    Reports (Lindquist)

    Annual Report: Currently working the Annual Report.



    Change Control/Contingency (Lindquist)

    The following Change Requests have been submitted:
     

    CR-000018 WBS 1.1.4 Curbing for Service Roads at Livingston G. Stapfer
    CR-000019 WBS 1.2 Additional Lab Equipment D. Coyne
    CR-000020 WBS 1.1.4 Livingston Storage and Staging Building Contract and Associated Costs F. Asiri

    Press for the latest Contingency Needs Projection.


    COST SCHEDULE CONTROL SYSTEMS (Duncan, Akutagawa)

    From: Kris Duncan <kris@ligo.caltech.edu>

    From: Cindy Akutagawa <cindy@ligo.caltech.edu>

    SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

    From: Ed Jasnow <jasnow@ligo.caltech.edu>

    From: irena@ligo.caltech.edu (Irena Petrac)

    Quality/Safety (Tyler)

    >From: Bill Tyler <tyler@ligo.caltech.edu>

    No report.


    LIGO Hanford Observatory (LHO) Operations (Raab).


    General Items (F. Raab)

    The last two weeks have had no commissioning activities, allowing us to address some items that have needed attention. Examples are updates to the general computing and CDS environments, rationalization of cable layouts in the control room, and modifications to the 2K PSL to increase output power. We believe all will be back in operating order by Monday, Jan. 8. We also expect to be ready for installation into chambers by Jan 15.
     

    Computing (C. Patton)

    The file and email servers were successfully upgraded last week.  Over the next few weeks I will be moving user accounts around to provide more disk space for everyone.  I will also be setting up the anonymous ftp and upgrading the web server.


    LIGO Livingston Observatory (LLO) Operations (Coles).


    Two very important milestones were attained at LLO this week. On January 3, we opened the X-arm beamtube for the first time, and found the projected laser beam striking the ETMx LOS just above the optic. The return beam at ITMx wasn't found quite so easily, but we did finally locate it and almost immediately noted resonance flashes recorded by the ETM transmission monitor. See the Jan 3 LLO i-log (http://www.ligo-la.caltech.edu/ilog/pub/ilog.cgi) for detailed notes and images of the beams striking the towers. Furthermore, on January 4 the gate valves on the Y-end station were opened and once again, without any adjustments to the optic biases, the beam was seen on the ETM-y AND the return beam spot could clearly be seen on ITM-y. These are two very significant milestones for LLO! Thanks to all of the LLO staff and visitors for their sustained efforts to make these achievements possible.


     

    CDS: X-end station cabling installed for QPD-x, using DAQ channel for accel X to view sum of QPD-X. At the Y-end station, the calbling for QPD-y was installed and the quad cell was found to be bad, and was replaced with a working one by Jonathan Kern. Also, the clock driver in the crate was replaced. (Wooley, Fyffe)


    Detector/Technical Support (Whitcomb, Coyne).


     
    Installation & Commissioning:
    Hanford
    Livingston
    Other Science/Engineering Activities:
    Design/Analysis/Fab
    Issues/Concerns
    See also the Installation web page

    1.1 LHO INSTALLATION & COMMISSIONING

    2km Commissioning

    Bill Kells, Erica d'Ambrosio
    Mostly cranking the FFT code up to full productivity on "Mulder" one of the HP V2500 CACR machines. Suprisingly many bugs with their operations, etc. so this was not insignificant. It is now at a usefull level roughly equivalent to former days on TREX. Used above to study behaviour of PRM at LHO. Usefull results to appear this week (will sent e-mail and post in e-log).

    COS

    Mike Smith, Ken Mailand, Betsy Weaver
    Updated installation drawings for the LHO end station installation of the COS ETM telescope, beam dump and arm cavity baffle are being prepared. An retroreflecting mirror assembly for aiding in the alignment of the ETM telescope beam dump was fabricated. COS autocollimators were shipped to LHO.

    PSL

    Peter King
    Adapter plates for the new mounting scheme for the phase-correcting electro-optic modulator (EOM) have arrived.  The new mounting scheme involves mounting the EOM to a low-height goniometer instead of a four-axis tilt stage.  The goniometers will be shipped to LHO as soon as they arrive from the manufacturer.

    1.2 LLO INSTALLATION & COMMISSIONING

    Commissioning

    Rai Weiss, Mike Zucker and everyone at LLO
    A plan for the commissioning activities during January has been circulated. The plan involves first opening the arms to determine the alignment. During the middle two weeks of January extensive work will be done to align the detection tables and bring the RF and digital servo electronics into operation. At the end of the month attempts will be made to lock the single arm cavities and the Fabry-Perot/Michelson without recycling.

    Jan 3 we opened the x arm and found the beam within 30 microradians of the aligned position. The cavity was aligned and produced flashes. The beam size was measured crudely and it was determined and found not to be well mode matched. There is an indication that the ITMX reflecting surface has more scattering than the mirrors at Hanford.

    In the next few days we expect to open the y arm and determine its alignment.

    #SEW# This is a tremendous achivement that should be savored by all who contributed.  And in late breaking news, I have just heard that the Y arm has been checked and was almost as close as the x-arm!  Congratulations to all!

    ISC

    Mike Zucker
  • Completed tuning and characterization of LLO length sensing photodetectors and shipped to LLO.
  • 2.0 Other Engineering and Scientific Activities

    2.1 Design/Analysis/Fab

    Optical Metrology

    Helena Armandula, GariLynn Billingsley
    Because the temperature has been very unstable in the lab., still taking data on 2ITM02. Expect to be finished on Monday.

    PSL

    Peter King
    Performance characterization of the new pre-modecleaner (PMC) are still on-going.  Initially the PMC was left where it was located on a previous occassion.  Since that time the 10-W laser has been removed from the optical table, re-installed and re-aligned.  The output of the laser was aligned into the PMC without re-measuring the beam waist location and the PMC throughput was approximately 75%.  The output of the laser has been re-measured and the mode-matching lenses re-positioned.  This should improve the throughput since things have been checked.  The previous exercise was more a curiosity study to see what we could get away with.

    I have been trying to simulate the performance of a high-power photodiode with PSpice, without much luck so far.  The problem being that I haven't figured out how to incorporate the Spice model provided by the manufacturer of the op-amp used into the PSpice model.  When a "generic" op-amp is substituted the circuit seems to have the right characteristics that I intended.

    The table for the LASTI PSL is being tracked down, since I was expecting it to be delivered just before Christmas to MIT.

    For reasons not entirely obvious to me, the computer down in the PSL Lab no longer allows local console logins.  This problem seems to have originated since Christmas.  Lisa did fix the problem once before, why it has returned is not clear to me.  In addition there was a problem with the /etc/hosts file on luna because the IP address for scipe25 was incorrect, resulting in the input/output controller not being able to boot from luna.

    Rick Karwoski, Paul Russell, Ben Abbott
    The following is the status on the PSL Frequency Reference suite of boards:

  • Photo detector module -- Bench test complete, assembled
  • Frequency Reference -- Bench test complete
  •  80 MHz VCO -- Bench test complete
  • Servo -- 80% tested

  • These boards are due at Hanford by January 15. We will take the additional time to burn them in and run them as a group at the Lauritsen Laser lab.

    ISC

    Mohana Mageswaran
    I have finished testing the MC Servo board, and I am doing the documentation for the tested board.

    Modulated OSEM Design

    Jay Heefner
  • 5 stabilized oscillator satellite amps are stuffed and being tested. They should be complete by 1/10/01.
  • New OSEM Heads

    Peter Fritschel, Myron McInnis, Fred Miller
    Busy assembling and testing the new osems for the LHO 4k interferometer. We are approximately 40% complete on this first set, and the production rate has increased as problems are worked out. The biggest problem has been that the screws used to hold the pin-plate and connector onto the rear of the body would not thread into the tapped holes in the alumina. The solution has been to etch down the OD of the screw threads by about 5-mils, followed by a re-passivation of the ss screws. We are shipping 15 long heads to LHO today. The rest of the heads should be completed by the end of next week.

    Janeen Romie,
    Betsy is preparing to do a second bake on a number of heads tomorrow or Friday at Hanford. I'm working on travelers and the process spec.
    Progressive Technology is still trying to remove the metalization from some of the heads so they may be recoated. They are having mixed success. I am researching other methods. Progressive Technology reports that the second batch of alumina heads should be complete at the end of this month.

    Digital Suspensions

    Jay Heefner
  • 8 additional PD whitening/Interface boards have been tested. We now have enough to complete the 4K IFO.
  • SOS dewhitening amps are due back this week.
  • LOS Bias modules are stuffed and ready for test.
  • SOS coil driver board layout will be complete by 1/5/01. This is the last board needed for initial installation and test of the SOS controls.
  • DMT

    John Zweizig
    I have been collecting numerous changes made on the fly to the various DMT components and merging them into the cvs source repository. I will release this version soon. Several changes were made in the CDS configuration over the holidays and some manual intervention was necessary to make the DMT run after these changes. Apart from these minor tweaks, the DMT seems to have been running smoothly.

    2.2 Issues Concerns

    Nothing new.



    40 Meter Interferometer (Weinstein).


    (Jay Heefner)

    Thermal Noise Interferometer (Libbrecht).


    No report this week.


    LASTI (Zucker).


    LASTI (Jay Heefner)


    Data Analysis and Computing (Lazzarini)


    Simulation and Modeling (Yamamoto)

    > physics simulaion (B.Bhawal, H.Yamamoto)

    The seismic noise study continued. High pass filters are used to whiten the seismic noise and we confirmed the correct spectrum below 100 Hz was generated within a short simulation time (100 sec), We compared this to the case with no high pass filter which took va ery long (5000 sec) to calculate correct psd at high frequency.

    To pinpoint the effect of the numerical accuracy limit ( double precision has an accuracy of 15 digits, but the simulation involves many number manipulations, it looks like 10 to 11 digits is the effective dynamic range covered ), Hiro wrote a program with a digital filter
    and psd to be compiled with double precision and quadruple preciosion accuracy.

    Biplab will focus on the study of the effect of the optics misalignment on the lock acquisition.

    > simulation engine parallelization (T.Dangelis)

    algorithm/implementation to produce a one-execNode 'tick list' was written and incorporated into the program after partitioning.

    algorithm/implementation for finding the 'ideal-arrival-time', a topology metric, was  written, along with a not-yet-working version of a 'node-to-node distance' metric.

    > GUI (E.Maros, B.Sears)

    Improving alfi, the GUI frontend of e2e. Ed is implementing copy and paste. A new release is expected next monday, which will be based on a new version of xwWindow. Bruce is implementing a new inferace for setting parameter.

    LIGO Data Analysis System

    Software Systems (Blackburn)

    LDAS is busy preparing a new release of the software in support of the MDC activities expected to cover the bulk of January and February. The MPI Group from UWM will begin arriving the middle of next week as we setup and prepare for the MPI Mock Data Challenge to begin the following Monday morning. Activities associated with the Database Mock Data Challenge will also begin to ramp up during the next couple of weeks.

    The mpiAPI and the wrapperAPI are presently considered to be in very good shape for this MDC. An LDAS user command is also available for starting jobs on the BEOWULF. This command has been lightly tested and looks to have all the necessary functionality needed for the MDC. One issue that has come up is the inability to completely control the host(node) assignment list used in MPI jobs using LAM. These hasn't been looked at in great details so there may be a simple configuration option to manage this at compile time or run time. The good news however is that we have finally run a parallel LDAS wrapperAPI job on all 16(17) nodes of our new LDAS
    development Beowulf system to completion.

    As part of our normal procedures for getting a software release out the door, we have begun daily and nightly builds of LDAS and associated tests of the various components. This pre-release is showing better data socket communication rates of ILWD data objects between hosts, but has identified a 50% slow down in the performance of our database. There is a possibility that this 50% slowdown is due to a misunderstanding of the exact date that we changed the database hardware on the development system from a Sun 450 to a Sun Ultra10. A follow-up test is being performed today on a different LDAS system with a Sun 450 for the dataserver to verify if a problem actually exists.

    The new UDT data class in the dataConditionAPI has brought with it the expected increase in open problem reports. However, this week we were able to make some headway into resolving several bugs and closing out a significant number of reports. The group also decided to take inventory of the software components that are being moved over to the new UDT model and use this as a baseline to track progress towards a complete transformation of the data-ConditionAPI over to the UDT model.

    The LDAS development, test and Livingston databases are now using the updated IBM DB2 7.1 server. This server has shown about a 10% increase in performance over the DB2 6.2 server we were previously using on our Sun servers. To support this new version of DB2, new tables were generated on the three systems.

    The documentation of LDAS is also being overhauled in preparation for this new release. Several APIs were not able to generate web-based documentation using our new PERCEPS document generator. These have for the most part been fixed. However, in one particularly difficult case, we have introduced an ingnore command to avoid segments of C++ code that corrupt documentation
    files.

    Hardware Systems (Anderson)

    General Computing

    MIT:

    Livingston: Hanford: CIT:

    LIGO II/Advanced R&D (Sanders)


    LIGO II Coatings (Helena Armandula)

    Received a reply to a coating inquiry that was sent to Laser Zentrum Hannover about the company's interest and ability to provide LIGO II coatings.  They expressed interest to work with LIGO.  At this time they do not have the techniques required to meet our specs.  However, they said that with development work, they'll meet our requirements and schedule.  They quoted the LIGO work based on available facilities ? ? and the quote is very reasonable.  Some further investigation will be required to assess their capabilities.

    Optics (Garilynn Billingsley)

    We now have a homogeneity phase map of the first 25 x 10 cm sapphire substrate measured at Caltech.  The measurement shows the central 150 mm of the first 250 mm sample. Peak to valley inhomogeneity is in the 400 nm range, rms is on the order of 50 nm.  Uncertainty is ~5nm due to turbulence. More Detail

    LIGO II PSL (Peter King)

    Apparently the quote given to me for the pump laser diodes was not the "best" deal that Coherent could do. Just how good a deal they would be prepared to do was not indicated to me but I was told there was room to negotiate on the quotation that they provided.

    (Bill Kells)

    Got R. Beausoleil to revise MELODY [again] to fix nominal inconsistancies.

    Performed Rayleigh scatter measurements on Sapphire substrates.

    Seismic Attenuation (Riccardo DeSalvo)

    No report.


    For additional information about this report, contact sanders@ligo.caltech.edu