Weekly Report for Week Ending March 23, 2000


 Exec. Comm. Agenda
Highlights
LSC
Administration
Hanford Observatory
Livingston Observatory
MIT
Caltech
Detector
40 Meter
TNI
LASTI
Data Analysis
LIGO II/Adv. R&D
Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  March 27, 2000 will be:
 (Meeting time: 10:30 am Pacific Time)

Open meeting 10:30 - 11:30

  1. Announcements
  2. LSC Issues (Weiss)
  3. Comments on Weekly Report
  4. WBS 1 LIGO I Construction (Lindquist)
  5. WBS 2 LIGO Lab Operations
  6. WBS 3 and 4  Advanced R&D and LIGO II (Sanders)
Executive Committee only 11:30 - noon
 

Special Items:


Special Announcements:


Weekly Report Highlights
 


LSC Issues (Weiss)


LSC Activities

Significant organizational issues from the LSC meeting.

The next LSC meeting is at Hanford August 15,16,17. A session on astrophysics for
LIGO II and the planning of the first papers on upper limits using the analysis of
LIGO I data is being considered for August 14. The idea would be to invite subsets
of LSC and the astrophysical community to Hanford.

The next GWDAW meeting is planned for Louisiana Dec 14,15,16.

A mechanism for providing the LSC access to LIGO engineering data is being
formulated. The concept is to have LSC groups request data by writing a letter
to the Project Director with copies to the LSC Spokesperson, LSC Detector
Characterization Committee Chair and the LDAS Scientist. The letter is to include
the intended use of the data, the demands placed on LIGO facilities, the people
who will work on the data at the LSC institution. The LSC Publications and
Presentations policy applies to results derived from these studies. A template
letter is in preparation.

The executive committee of the LSC (Lab Directorate, LSC committee chairs and Lab
liaisons, LDAS scientist, LSC Spokesperson, selected wisepersons) will meet on the
third Friday of each month by phone at 11AM Eastern Time to discuss major issues
and respond to new initiatives.

LSC is prepared to support the LDAS proposal and the NSF review of the LDAS
procurement.

Technical issues to be discussed in another weekly.


LIGO I Construction/LIGO Laboratory Administration (Lindquist)


WBS 1.2 LIGO Operations--Administration


LIGO Weekly Site Telecon (Jasnow)

A site telecon was held on Thursday, March 23, 2000.   The list of current actions revised to reflect actions assigned during the meeting may be found at ACTION LIST.

End of February 2000 reports were distributed prior to this meeting.  However, discussion was deferred until next week.  Given that costs are currently running at fifty percent of a straight-line budget, all were given the action to be prepared to discuss these cost reports next week.

The monthly report can be found on the network in .pdf format.


PROPERTY MANAGEMENT (Chargois)

From: Ed Chargois <chargois_e@ligo.caltech.edu>

Assisted the Detector Group (M. Smith) with packing and shipping of APS Telescope hardware to the LIGO Hanford Observatory (B. Weaver), delivery confirmed . Account Number P96937.

Assisted the Detector Group (L. Jones) with the disposal of recyclable Stainless Steel Coupons from the 40M Annex and the Bridge Annex Sub-basement.

Assisted the Detector Group (L. Jones) with the packing and shipping of two (2) packages of Stainless Steel Coupons to the LIGO Livingston Observatory (G. Stapfer). Account Number P96919.

Assisted the Detector Group (L.Jones) with arranging transportation for the HAM Ribbon Cable Form being shipped to the LIGO Hanford Observatory (L.Jones) via United Motor Freight. Account Number LIGO.5F500 LIGO 2.2 NSFLIGO.5F5000.

Assisted the Caltech Property Management Section with written procedures and the development of a Disposition From that will enable Projects on Campus to Surplus, Excess or Transfer Accountable Equipment and maintain an audit trail.


DOCUMENT CONTROL CENTER (Turner, Mak)

From: the DCC <dcc@ligo.caltech.edu>

Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .

ACTIVITY HIGHLIGHTS

From: Cleveland Mak <mak_c@ligo.caltech.edu> Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.


COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Akutagawa, Kaufman)

From: Esther Cunningham <esther@ligo.caltech.edu>

Press here for ACCOUNTS PAYABLE HISTORY DATA.

From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

I've been working on closing out encumbrances on poeta's as requested.  The majority of the encumbrances were for removals, while two of the transactions were for transfers to a different task.  All items on the spreadsheet have been completed with the exception of the removal of an encumbrance on Triad under task 2.1 which I need to inquire on as it appears that funds previously on 2.1 have already been moved to 2.10.  While in the process of removing encumbrances, we did find out that several open encumbrances listed as "$0" dollar continue to appear as open transactions when looking at their respective poetas.  These "zero" dollar transactions occured a while back and cannot be removed as these lines were "cancelled" while the "received" and "billed" amounts did not match.  A while back we did revise our procedures in cancelling lines by having the "received" and "billed" amounts match.

I am working on gathering information on the OAG subscription(s) for LIGO.  Looks like one subscription was renewed on an American Express credit card (which appears strange as Caltech normally uses a Mastercard for credit card purchases).  I am waiting for the vendor to pull the information on the renewal and get back to me so we can make a decision on the renewal(s).

Continue to set up folders on new change orders to subcontracts which go for approvals across the street.

Gina will be working on bringing current the GE Capital lease for the copier which is in arears and just came to light a few days ago.

Automobile lease on the Chevrolet Suburban is still on hold.

From: Florence Kaufman <fkaufman@ligo.caltech.edu>

From: Cindy Akutagawa <cindy@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: irena@ligo.caltech.edu (Irena Petrac)

From: Ed Jasnow <jasnow@ligo.caltech.edu>

OPERATIONS

Efforts are underway to develop a policy and guidelines for long-term visitors to the sites.  This policy will also determine the financial impact to the sites of supporting these visitors.



Support (Wood)

Irene Baldon

No report, the hard disk on her computer died.

Rita Torres

For I. Petrac formatted Attachment Z for Stanford University. For P. Lindquist formatted memo Re: Proper assignment of LIGO property, then distributed. Also FedExed to NSF LIGO II Integrated R&D Program for 2000 & 2001, distributed in-house. Prepared books to file December and January reports.

Obtained new input from DCC for lists of SEI drawings. Working with F. Asiri and DCC to create a useable system to quickly access pertinent drawings, project ongoing. Helped D. Lloyd to capture transactions recorded under one Poeta which should have been recorded under a different Poeta. Usual P-card activities, chased some invoices, reconciled 15 this period. Did site trip updates. Spending time with I. Baldon on travel documents.

Dorothy Lloyd

Received billed amounts on-line on a number of contracts and blanket orders for Ruth, in order for her to cancel the lines out to correct account distributions or to close out the contracts.

Continue to process requisitions, invoices and receiving on-line. For more detail see "Cost Schedule Control Systems" report by Esther Cunningham.

Tracked and follow up on various invoice problems.

Reviewed payments processed by Esther during the week of March 13. Payments were entered in contract summary sheets and the LIGO database by both Jim and me.

Monitored contract and blanket order funding levels and notified task managers where supplements needed to be made.

Elizabeth K. Wood

Made further arrangements for the impending NSF site review in May.

These days, I'm working a touch more on the Kipfest. For details of Kip's 60th birthday celebration, please see http://wugrav.wustl.edu/People/CLIFF/KipFest/kipmain.html


LIGO II (Frey)

From: Thomas Frey <tfrey@ligo.caltech.edu>

Progress Period from 3.10 to 3.23

Accomplishments:

Schedule: Scope Changes:
Switch from P3e to P3 3.0.

General Comments:
I am interested in holding training session(s) for any users or other persons who will be interfacing with P3 3.0.  This will be an opportunity to demonstrate the capability of the software and how it is being implemented.



WBS 1.4.1.2   Project Controls (LIGO Construction)


Reports (Lindquist)

I still need some submittals for the Quarterly Report for the end of February 2000.

We are preparing a schedule for the support that is going to be required for proposals, work plans, and reports for the last half of FY 2000.  Clearly there is a lot of information needed, and there is a lot of overlap in the schedules that will have to be spread out given limited resources.



Change Control/Contingency (Lindquist)

The following change requests have been submitted:
 

CR-990028 WBS 1.1.3 Beam Tube Enclosure Closeout F. Asiri
CR-000001 WBS 1.1.4 Fencing Road at Livingston (Info Only) G. Stapfer
CR-000002 WBS 1.4 Project Office Close Out K. Duncan
CR-000003 WBS 1.1.4.3 Erosion Control--Livingston Observatory G. Stapfer

Press for the latest Contingency Needs Projection.


COST SCHEDULE CONTROL SYSTEMS (Duncan, Akutagawa)

From: Kris Duncan <kris@ligo.caltech.edu>

From: Cindy Akutagawa <cindy@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: Ed Jasnow <jasnow@acrux.ligo.caltech.edu>

CONSTRUCTION

The schedule for the contracting and construction of the Louisiana Staging Building has been completed and agreed to by project management. The schedule calls for issuance of the Invitation for Bids on June 23, a job walk on July 25, and bid opening on August 4.  Following this is the NSF's review, with contract award on September 19.  This provides for the building to be completed by December 20, 2001.


Quality/Safety (Tyler)

>From: Bill Tyler <tyler@ligo.caltech.edu>

No report this week.



 

From: Syd Meshkov <syd@ligo.caltech.edu>

1. Viewgraphs from the Aspen Winter Conference are now available on the
LIGO Web pages at:

http://www.ligo.caltech.edu/%7Everonica/Aspen2000/webpages/scripts/Transparencies.html

Thanks are due Veronica for her work in assembling and
arranging them, and to Barbara for her help in posting them.

2. Worked on various Visitor Program activities, including a long term
visit to LLO by David Reitze, as well as a long term visit by Benoit
Mours.

3. Worked with Rita Torres to send David Blair useful information, such as
our NSF proposal for support, to help him with his organizational
activities of the next Amaldi conference in Australia.


LIGO Hanford Observatory (LHO) Operations (Raab)


Announcements:
--------------
(F. Raab)
 

Apologies for missing the weekly report last week. This week we have installation
of phase camera hardware, transfer function measurements of the fine actuator and
other ongoing commissioning work. Unfortunately it appears we will not be able to
get useful noise performance from the PSL prior to ending the one arm test (see
below). Nonetheless, we will run what we have for a 24-hour stretch on April 3 to
provide some data for checking detector characterization software. We are getting
some pledges of support for this effort from within the Lab and the
Collaboration. On the installation front, it looks like seismic will wrap in
about two weeks. Sounds like time for a party.

Bake Oven:
----------
(K. Ryan)
 

LHO vacuum bake oven load #82, consisting of 5 Pick Off Telescopes and Beam Dump
assemblies, was released Monday, 3.20.00.  This load was extended an extra three
days due to the quantity of parts (partially blocked pump port => reduced pump
speed, greater mass => longer cool down).
 

Load #83, consisting of the last LHO BSC bellow, 4K IO baffle components, misc.
Pick Off Telescope and Beam Dump parts, misc. stainless steel hardware and HAM 6,
HAM 12 and BSC purge air fittings, is underway and should be released Friday,
3.24.00.
 

PreStabilized Laser:
--------------------
(R. Savage)
 

Investigations of PSL optical mount resonances revealed that the periscopes and
RF photodetectors are the biggest sources of noise. We are modifying the mounts
for those components to reduce their motions. Hopefully the upgraded hardware
will be ready for the 2k PSL upgrade in mid-April.
 

We have been having some difficulty locking the pre-modecleaner which we think is
due to a faulty AD602 device and a mistake in how it is wired. Rich Abbott sent
a replacement AD602 and we hope to make the change later this week.
 

A high school student from Southridge High School, is now working on the PSL
documentation.  He is just getting started, but already having a positive impact
(see http://www.ligo-wa.caltech.edu/~rick/PSL)
 
 

Optics:
---------------------
(D. Cook)
 

The Y arm Folding Mirror low signal mystery has been resolved. This optic has
weathered several reprocessings and installations early on due to failed magnet
bonds.  Apparently the lower right OSEM was installed with a stowaway inside. A
loose magnet. This magnet found its way to and attached itself to the optic
magnet blocking most of the sensor light. It was not attached to the PAM magnet
however.  It will be tricky to remove it from the optic magnet. This will not be
attempted until the mid April in situ work due to present alignment criteria. The
ITMy-2k optic went through a fine realignment today by adjusting the PAM screws.
The ITMy-2k and FMy-2k wire violin frequencies will be measured as we continue
the BSC in situ tasks. Mike Landry and Betsy installed the Y-arm conical baffle
as part of the related tasks. The ITMy-2k Optical lever was calibrated using the
new system and re-zeroed as the beam had drifted off the diode. I will note the
calibration values, alignment numbers, resonances etc. in the e-log.
 

Seismic Systems:
-----------------------------------
(C. Gray, M. Guenther & H. Radkins)
 

We've managed to miss a few weeklys with Hugh and Mark at LLO for Coarse
Actuation System (CAS) training from HYTEC and Corey in Montana for a
presentation.  However we have managed to get some work done.
 

BSC2(4K BS): The Expansion Bellows were leak checked and passed first time.
This completes the SEI hardware installation in the LVEA.  We still need
to run cable and testing for the CAS though.
 

BSC10(4K ETMy):  Since the last weekly we have completed the external
hardware installation, that is up to the big blue crossbeams; and, pulled
the dome, completed all internal hardware installations and put the dome
back on!  The expansion bellows have passed the leak check.  Thanks to
Larry Jones and others.
 

BSC9(4K ETMx):  The Scissors Tables are on and three of the four X-Fine
Stages, we are waiting to install the fourth unit, see below.
 

X-Fine Stage:  This section of the actuation stack provides fine axial
positioning to accommodate IFO length changes due to Tidal forces (Moon)
and Microseism waves.  The positioning is provided by PZTs in the X-Fine
stage on each of the four piers.  The PZT controllers are driven by an
excitation engine/program during the One Arm Testing of the IFO.  This has
been done.
 

Meanwhile one of the PZT controllers goes into a resonance oscillation when
the servo loop is closed.  The unit is back at the manufacturer for
adjustment; we expect it soon.
 

BSC5(2K ETMx):  The installation of the PZTs into the X-Fine Stages was
completed here this week.  The position of the Optics is now being
maintained by the PZTs.  During the installation procedure, the PZTs were
operated at 0.450 Hz with peak amplitude of 90 microns for several minutes.
The dial indicators on the stages only showed motion of 88µ.  The
difference may be attributable to frame or component distortion.  The
optical levers were monitored and the optic appeared to return to the
before position.
 

Coarse Actuation System:  The CAS operations manual is under
construction--E000140-00-D.  This will incorporate the HYTEC operations
manual to cover initial system testing, adjustment, maintenance, and
operation.
 

Controls:
---------
(D. Barker)
 

Arbitrary Waveform Generator is working in MX. It was used this week to
activate the fine actuators on BSC5. Some bugs still remain which are
being worked offline.
 

CDS software is being reorganized in preparation for putting it under
configuration control using LDAS CVS.


LIGO Livingston Observatory (LLO) Operations (Coles)



 

Mode Cleaner Commissioning: The mode cleaner now stays reliably locked for hours! We reduced the modulation depth to 0.002. We now are in the process of re-measuring the mode cleaner transfer function.

Visitors last week measured the UGF of the MC transfer function at 40 kHz (BP on) with lots of phase margin. We can evidently push to 75 kHz or so as is; sharp phase rolloff at ~ 60 kHz appears consistent with acousto propagation delay, which should be measured independently.

Some initial measurements of the mode cleaner characteristics are:


Problems:

GDS: The GDS is on and up at LLO. Thanks to John and Daniel for their assistance. The Diagnostic Test Tool with the Excitation Engine is available from the control room. The LLO Data Monitoring Tool is ready to use. We received the replacement for the FDR12 chasis but are still waiting for the 6 outlet module.

Optical levers: We looked into the placement of the optical levers in the LVEA at the ends of the manifolds. There are some dimensional interferences with some of the VE conduit which will have to be reworked. We are scoping out what will be involved and developing a plan for how best to proceed.

Community relations: The University of Texas at Arlington SPS chapter visited this week and added to our collection of murals on the beam tube enclosures. About 45 members of the Instrumenation Society of America visited Tuesday evening for a tour. About 75 members of the Am Soc. of Chem. Engineers toured the LIGO site on Thursday evening.

Other: We had an auto accident this week at LLO involving a visiting scientist and a "normally open" gate on the access road. Visitors to LLO are reminded to review the procedures at http://www.ligo-la.caltech.edu/visitor_page/FirstTimeVis.htm and to inform the security guard of comings and goings after hours. Harry Overmayer began work at LLO this week as an operations specialist.
 


MIT (Shoemaker)


no report


Caltech (Sanders)


no report


Detector/Technical Support (Whitcomb, Coyne)



Installation:
Hanford
Livingston
Commisioning:
Hanford
Livingston
Other Science/Engineering
Activities

1.0 INSTALLATION (including fabrication and subsystem test)

see also the Installation web page

1.1 LHO

2 km ASC/LSC

Dale Ouimette, Rolf Bork, Rich Abbott, Mohana Mageswaran
The first of the two Common Mode Servo boards is due back from PCB fab Thursday March 23rd. All parts have been ordered and should be here ready for stuffing. The second board layout is not done as of Wednesday PM. It will be completed Thursday and sent out for 2 day fab. The plan is still to show up at Hanford April 3 with both boards tested. Paul is milling front panels in our shop for both boards. Phoenix will be stuffing the boards.
In process of constructing full up ASC/LSC digital system at Caltech for testing and development; should be complete by Friday.
Rich finished testing of the first box in the LSC/ASC Frequency Distribution system.  It performs according to spec. Sent the second of the three boxes for the LSC/ASC Frequency Distribution system to the board house to be manufactured and began the design of the last box.  I anticipate finishing the design by the end of the week with the board at the board house by early next week.
Mohana is working on the schematic for the whitening filter board design and ordered some parts for this board.

Seismic Isolation

Larry Jones
The bellows seals of WBSC 10 (Y end) were leak tested and shown to be acceptable.
The PZT controller with the signal oscillation problem was returned to the vendor; return of a repaired/replacement unit is expected shortly. Three of the fine stages for WBSC 9 (X end) have been assembled and installed; the fourth is awaiting the return of the PZT controller to complete bench calibration with the specific PZT prior to installation.

GDS

Daniel Sigg
Installed the most recent version of the diagnostics test tool at LHO.

COS 2 km interferometer Assemblies

Mike Smith
PO Telescopes and PO optical train: The input baffle parts and the black glass for the 2K APS telescope have been received by LHO. Alignment tools were shipped to LHO on 3/22. A modification to Jonathan's wire frame HAM door viewport proxy fixture is being designed, to determine the location of the reflected ghost beams from the COS viewports in the HAM chambers.
Viewport beam dumps for HAM9 and HAM10: The viewport beam dump glass has been received by LHO. A purchase order for the mechanical parts will be let on 3/23, and the parts are expected to be fabricated by 3/30.
Arm Cavity Baffle: The arm cavity baffle glass in being fabricated and is expected to arrive at LHO during the week of 3/27.
Faraday Isolator: One magnet assembly is being baked at CIT and will come out of the oven 3/24. 3 cleaned half-wave have been received and will be baked following the magnet assembly.
COS Alignment Proceedure: The IR diode lasers, which were sent back to the manufacturer for correcting the fiber output coupler, are scheduled to be shipped to LHO on 3/23

1.2 LLO

Pre-Stabilized Laser (PSL)

Peter King & Rich Abbott
New MEDM PSL operator screens are being trialed.  So far most of the new features seem to work seamlessly except when BURT is called up.
The generic data acquisition interface has been installed and cabled into the PSL rack (1X3).  Signals from the servo cards have been wired across to interface card.  TB6 was removed from the rack to allow room for the data acquisition FLKM-64 block.  The wiring completion has allowed the side and the door of the PSL rack to be re-installed.
The current shunt in the laser is broken.  Examination of the circuit revealed two burnt resistors.  The maximum current through these resistors is around 20 A, resulting in a maximum power of 20 W.  For reasons not understood (by me at least), these two resistors were installed as 1/4-W components.  This has been brought to Lightwave's attention, who's response was something along the lines of "oops".  The current shunt's malfunction may have been the cause of the laser power supply failure that occurred two weeks ago.
The diode current of the 10-W laser was reduced from 24.50 A to 24.00 A and the temperature of the laser was scanned.  It was found that the laser delivered the same power at a different operating temperature, thereby allowing the diode current to be lowered.  This would have some implications about extending the lifetime of the laser.  Whether this result is valid for other lasers is yet to be determined.
The PSL's EPICS records database has been updated.  Now the LLO and LHO PSL's database are nearly the same --- the differences being due to some field wire changes.

Anti-aliasing Filters

Sander Liu
Received partial shipment of 5V power supplies from Kepco. Six were used to build three +/- 5 volt rack mount units for LLO Antialiasing Filter Chassis. One was shipped to LLO yesterday (3/21/00). The other two will follow in a day or two.
Frequency Devices will FedEx 100 Antialiasing Filter modules to us tomorrow (03/23/00). They should arrive on Friday (03/24/00).

COS Assemblies

Mike Smith
PO Telescopes and PO optical train: The input baffle glass for the 2K APS telescope have been received by LHO.
Viewport beam dumps for HAM9 and HAM10: The viewport beam dump glass has been received by LLO. A purchase order for  the mechanical parts will be let on 3/23, and the parts are expected to be fabricated by 3/30.
Arm Cavity Baffle: The arm cavity baffle parts, cleaned by Allied, and  the arm cavity baffle glass from Hydratech are expected to arrive at LLO during the week of 4/3.

2.0 COMMISSIONING (incl. diagnostics and characterization)

2.1 LHO

Cavity Length and Seismometer Correlation

Peter Fritschel
I have been looking at a stretch of data of the LHO 2km X arm cavity lock of 3 Mar 00, to see how the 6-8 second period microseism changes the length of the 2km cavity. The idea is to compare the actual cavity length fluctuations, as indicated by the length control signal of the cavity servo, to the fluctuations measured by the seismometers. The longer term goal is to be able to use the seismometer signal to feedforward to the cavity length, via the stack fine actuators, and thus to reduce the length fluctuations at the microseism. To date the comparison has used only the minimal seismic information: the  X-axis channel of the LVEA and MX seismometers. The comparison looks  very encouraging; the coherence between the cavity length control  signal and the difference of the two seismometers is good at the  frequencies of interest (~.92 at the peak). The following figures (made using 4000 sec of continuous lock data) tell the story:

 
power spectra of the length control signal, the two seismometers, and the seismometer difference (seismometer data converted to displacement); the dashed line is the integrated rms of the control signal
phase difference and the coherence between the two seismometer channels; the phase shows that they are close to being in-phase, so that the length fluctuations should be smaller than either of the two seismometers (as the length control signal power spectrum indicates).
phase difference and the coherence between the length control signal and the seismometer difference (converted to displacement). The thing to note here is that the coherence around the microseism is high, and the phase is very close to zero degrees!
200 sec time series stretch of the length control signal, the seismometer difference signal, and the residual of (difference between) the two. The amplitudes match up well using only the specified calibration of the seismometers, and the measured calibration of the length control signal. This data has been sent through a 0.1-0.4 Hz bandpass filter.

In order to get the phase between the length control and seismometer signals to match up, it was necessary to compensate the seismometer channels for the frequency response of these instruments, which is given in the Guralp manual as being two zeros at DC and a complex pole pair at 33mHz. This has the side-effect of increasing the very low frequency drift component of the seismometer signals; this drift will have to be dealt with in implementing the feedforward system.

Length Control

Nergis Mavalvala, Bill Kells, Stan Whitcomb, Peter Saulson, Rana Adhikari and Daniel Sigg
We measured the loop gain in the length locking servo and found it to be somewhat lower than expected with a unity gain frequency of about 70 Hz. In attempting to measure the transfer function of the coil driver stages of the ITMx LOS controller we managed to cripple it. Our attempted diagnostics and repairs did not completely cure it and the controller had to be replaced. It has been sent to Caltech for diagnostics.

Transmission Monitor Centering

Nergis Mavavala, Daniel Sigg, Rolf Bork
After bench testing the QPD in the transmission monitor was remounted and we have now centered a spot on the QPD which is also quite well centered on the ETM. Peter S confirmed spot centering on the ETM using a frame grabber and getting a better image by subtracting out a background (no ifo spot) frame. Successfully measured the transfer function of the input beam direction to the quadrant photdetector in the X mid station. We also attempted to close the auto-centering loop with the QPD and the beam splitter, but uncovered some software bugs that are being fixed. Further investigation are under way.

LHO one arm data transient analysis

Julien Sylvestre
Worked on the implementation of a transients identification pipeline for the one arm LHO data. Various scripts for improved automatization were written and tested.

Phase Camera

Rana Adhikari & Peter Saulson
Set up Rana's phase camera on ISCT10 and made a few long integration measurements.  One of the difficulties has been the movement of the spot at the suspension eignefrequencies. Interpreting results, learning how to capture video frames for later analysis (MATLAB will probably end up being a better environment than the image processing software originally planned).

Fine Actuator Measurements

Virginio Sannibale
Measured the fine actuator transfer function using the cavity control signal from .1Hz to 15Hz and the strain gauge output using a sweep sine method. Checked the resonances found in the transfer function with the stack resonances provided by Hytec. They matched well. The measured transfer function seems to be reasonably behaved, as expected. Normalized the fine act transfer function by the mirror pendulum transfer function using nominal values to obtain the transfer function of mirror displacement over strain gauge displacement.
Measured the ETMX ring down using the shadow sensor monitors with the damping on. Using the entire stream data of the ring down I got 755mHz and Q~8. Using the last part of the data I got 735mHz and Q=4.4

2.2 LLO

Pre-Stabilized Laser (PSL)

Peter King
Some new EPICS sequences have been written.  The software loop that adjusts the SLOW actuator voltage to keep the FAST actuator voltage small can be engaged or disabled with a button.  In addition a new software routine detects if the frequency servo Pockels cell output is railed; the software then lowers the common gain until the oscillation stops and then increases the gain to the previous value.  The routine has a built-in time delay of 1 s, to allow things to settle down before restoring the gain.  In testing so far, the routine seems to work well, with oscillations lasting no longer than 1 or 2 s.
It was found with that there is a DC voltage (approx. 1.3 V) on the cable from the modecleaner servo amp to the PSL's VCO.  This voltage is present even if light to the modecleaner is blocked and appears to cause some transient problems if the VCO's wideband input is enabled.

Mode Cleaner (MC)

Haisheng Rong
Some preliminary data of LLO mode cleaner:
MC cavity pole: 4.43 kHz (calculated value: 3.92 kHz using specified mirror reflectivity)
MC length: 12.23698 m (design length 12.240m)
Cavity Finesse: 1383
Visibility in reflection: 75% (1-min/max)
Q's of mirror internal modes
           f (kHz)         Q (10^6)
MC2     28.237          0.70
MC3     28.240          0.85
MC1     (noisy ringdown trace due to beat of double resonances at 28.176 and 28.240 kHz)

Some problems:

Global Diagnostics System (GDS)

Szabolcs Marka, John Zweizig, Daniel Sigg
The GDS is on and up at LLO. The Diagnostic Test Tool with the Excitation Engine is available from the control room. LLO Data Monitoring Tool is ready to use. We received the replacement for the FDR12 chasis but still waiting for the 6 outlet module.

Suspension Controller Tuning

Mark Barton
Last week at LLO, worked on suspension controller tuning. I moved the Matlab software across from LHO, and customised it for LLO. Gabriela Gonzales and I started work on a version of the software for SOS (as opposed to LOS). Many of the LLO DAQ channels were not yet working but took some data on MC1 using a PC with LabView and adjusted the format to suit the existing Matlab routines. At least according to the data we took, the sensors on MC1 were very uneven, and the software was suggesting (unimplementable) negative gains. We are still looking into the reasons. However I completed writing up the parts of the procedure finalized so far (tuning of LOS sensor matrix and position componnents of the actuation matrix) as document T000003-00 (see the electronic DCC)..

3.0 Other Engineering and Scientific Activities

3.1 Design/Analysis

Core Optics Metrology

GariLynn Billingsley
I have found significant astigmatism error in our calibration of "C".  This  appears when rotating the 90 degree clocked measurements back to zero and  subtracting the 0 degree clocked measurement.  The error is on the order of 10 nm peak to valley.  This problem doesn't show up in the 180 degree  rotations.  After accounting for the way the terms subtract this indicates  an astigmatism error of ~ 5 nm in the calibration of "C" along a 45 degree  clocked diagonal.
Resolved design and contract issues with Bryan Loucks.  I've reviewed his first drawing concept for both 45 degree incidence fixtures.

2K APS Telescope focus and Guoy phase accumulation

Mike Smith
A Gaussian beam propagation analysis, to model the focus parameters of the 2K APS telescope as determined by the COS focussing procedure, has been completed, and the Guoy phase accumulation through the APS telescope optical train has been calculated. The results will be discussed with Nergis and compared with the as-built Guoy phase measurements made on ISCT10.

3.2 Issues Concerns

Optical Lever Lasers & Calibration

Mike Zucker
Continued discussions/negotiations with engineers from Point Source Inc. about projected MTTF of their iFLEX fibercoupled diode lasers. They are still working on a quote for replacement of some/all of our lasers but are skittish about my request of 25k hours MTTF.  Meanwhile Ken and Myron have done some more forensics on failed units; in one case a visibly overheated voltage regulator was found inside the case, but nothing like that on the others. We still can't say for certain that we've isolated the problem adequately to guarantee replacements will be immune.
Per commissioning directors' request, began draft revision to Optical Lever Calibration document T990026.  Revision covers inversion of S-shaped sensitivity curve to linearize readout over full range of motion (or, alternatively, back-correction of a calibration performed away from null).

Contingency

Mike Zucker
Worked up revised estimate for return to contingency of unspent salaries ascribed to understaffing in design/fabrication phase (to be reviewed against Caltech PAN data).

In-Vacuum Cabling Creep?

Larry Jones
There is a possibility that the kevlar ribbon cables installed with the seismic isolation system may be sagging with time, adding the risk of touching structures or other cables with resultant mechanical noise. We're setting up a test to measure the long term magnitudes of sagging in the most harmful cable runs.

3.3 Site Support

Software Configuration Control

Rolf Bork
Working with Barker to get CVS set up for CDS source code control.


40 Meter Interferometer (Weinstein)




Thermal Noise Interferometer (Libbrecht)


no report


LASTI (Zucker)


The review of the preliminary experimental plan for LASTI at last
week's LSC meeting was thorough and illuminating.  The committee
(chaired by Peter Saulson) highlighted several logistical issues
(manpower, critical skills, etc.) which, in large part, reflect shared
concerns across the LIGO II enterprise.  In this connection, the
committee endorsed our invitation for a strong LSC commitment to LASTI
from outside the Laboratory.

The most important scientific/strategic question was to what degree
we should emphasize achievement of low displacement noise, given the
scaling factors (especially beam diameter) which work against the
short cavity length.  We've been tasked with quantifying the potential
impacts of designing for low displacment noise on the agreed primary
mission (functional tests of the seismic isolation and suspension
system first articles with their controls).

In the laboratory, the vacuum system control/interlock panel has been
revised, reinstalled and tested, and assembly of the remaining
annulus pumping and RGA hardware is continuing.


Data Analysis and Computing (Lazzarini)



 
 

Simulation and Modeling

STAIC

Biplab attended the STAIC meeting at LSU on 20 and 21, and gave a presentation and demonstration of e2e, including the introduction of MSE. The application of e2e to LHO 2K FP data was accepted well, but the criticism came that it is available only on SUN machine, and some people specifically requested to make it available on linux. We intend to support linux, but now, we cannot build alfi functioning even on SUN. Our first priority is to make it work on SUN. Another objection was that documents and e2e website are not well maintained. We need to address it, but for now, too many to do with too little available resources.

Lock Acquisition

Matt remodeled the simulation setup to resemble more closely to the real hardware implementation. Studied more closely the various transient processes, like the velocity dependence of the transition from one state to another, and is improving the locking strategy. Matt summarizes his work in http://www.ligo.caltech.edu/~mevans/log.pdf.

Future plans

We had a meeting to discuss about e2e engine development. The main focuses are:

(1) implementation of the thermal lensing in e2e (Luca will lead this effort)
(2) thermal noise implementation based on S.Finn's matlab model (Biplab will lead this effort)
(3) switching to the new field implemention (this has been formulation by Matt, and HIro will implement it in adlib engine by replacing the existing optics modules by new modules)

We also discussed the physics modeling activities using e2e. Luca has been working to implement the LSC hardware in e2e framework and will complete it with WFS controller and 3D mirror (to be delivered very soon by Hiro). Once completed, a realistic cavity with LSC and ASC can be simulated. Biplab, Hiro and Rick are interested in working to analyze various PSL noises. They are going to have a telephone conference tomorrow to discuss the direction.

Adlib

Biplab is working to implement a new module to displace the beam. This is necessary to study the effect of the PSL RFDP motion on the frequency noise. It is also necessary to study the effect of the miscentering of the beam on ITM of the 2K FP cavity.

Alfi

Based on the feedbacks to the last release of the preliminary version of alfi, various bugs are fixed and functions are implemented. Next release is expected the end of March, which will have the minimum of alfi3 functionality with multi directory support. The final stable version release is expected to be the end of April.

LIGO Data Analysis System

LDAS Software:

Work focuse on getting out a version 0.0.10 release of LDAS
this week. This release is primarily meant to incorporate all
the major new features, enhancements, and bug fixes into a
stable release. It is also meant to establish a stable version
of LDAS that will hopefully be used in the upcoming data run at
Hanford during the first week of April.

Peter Shawhan is working with LDAS and GDS to develop a set of
steps that the DMT can use to send trigger data to the LDAS system
for ingestion into the LIGO database. This involves providing an
application programmer's interface (library) which will produce
LIGO_LW tables of triggers for the DMT manager to write out and
then ftp to the LDAS anonymous FTP area. The DMT manager will then
connect to the command socket on the LDAS managerAPI and request
that this LIGO_LW data be ingested through the underlying LDAS APIs.

The LDAS system is expected to be in pretty good shape for this
Hanford run. We will be working feverishly up until the last moment
to perform all the system tests needed to tag a new release and
then install the system here and at the sites.

Work on the new FrameCPP and MPI based LDAS API is continuing but
at a slower pace as we are busy preparing the release. UWM will be
looking at the wrapperAPI with an eye towards its flexibility to
support hierarchical searches. Kent reworked some of the wrapperAPI
to more easily support distributed algorithms needed for large data
set FFT and such. This will also facilitate integrating less main-
stream gravitational wave search strategies.

Data Analysis:

Lazzarini: We have recevied a very nice note from TAMA confirming that they wish to work together
to analyze the coincident datasets from Sept 1999.
We will be putting together a plan on how to proceed.

From previous week: 40m/TAMA coincidence data analysis (Zucker)
-------------------------------------------
Found the biggest time sink in the "classical" matched
filtering routine was the canned peak finding algorithm.  If
only the largest 1 or 2 peaks per second are
reported, a bank of 5 filters runs at ~ real time
(16 kS/s) on a 333 MHz PowerBook G3 (all
in interpreted Matlab).

Ed Daw is building us a more efficient peak sorter.

LHO one arm data transient analysis (Julien Sylvestre)
----------------------------------------------------------------------------
JS implemented a transients identification pipeline for the one arm LHO data
(spectrogram, bursts id, coincidence between channels, time series extraction).
Explicit coincidences were exhibited for bursts in the control signal and the
seismometers. Various scripts for improved automatization were written and
tested.

General Computing

MIT:
Received the projector and cart. David had to return the projector because of a
bulb problem. The process to do the return includes having to give Epson a
credit card number as a security deposite. They immediatly shipped a new unit
but people should be aware of the need for the credit card.

Livingston:
Worked on the LSC conference. From the experience we are working on some new
procedures that may facilitate computer connectivity for visitors in the future.
A number of people did mention they liked the use of the projector with their
computers for presentations.

Hanford:
Nothing to report.

CIT:
Barbara did a number of WEB changes and helped with some of the DCC issues. The
responces to the WEB video stream of the Inauguration have been positive.
Barbara is investigating other uses of this capability.

Suresh installed GNU compilers (gcc, g++, g77) version 2.95.2 in sirius.
Made a compressed tar ball of one of the surf student's home directory and is
sub-directories after retreiving from backup tape.
Did more tests with PGP evaluation version 6.5.2. both on unix and windows
platforms. This is something very useful tool to send documents securely across
the Internet by encrypting and signing it.
Worked with Larry to put one color printer in second floor bridge.
Setup one new user account, removed one modified some. Helped users with PC,
email, printing and file access problems.

Larry is continuing his work with purchasing issues. So far going through
Caltech Wired has not been a smooth process. They have promised to remedy a
number of the problems.
Installed/repaired and configured a number of PC's.
Worked on the hardware installation for the Primavera software.
Helped a number of users with their computer problems via telephone. Most of the
users were on travel.
Made some minor modifications on the mail server to expand its capacity. Updated
a few addresses on the DNS server.
Working with DCC concerning PDF issues. The PDFPlanet web site has been a great
source of information. It appears to help in a number of areas the Adobe web
site doesn't cover. It has a number of free utilities. Those that do a lot of
publishing should check it out.
Working on the new room to be used for the PC servers.

LDAS@CIT:

Adding LIGO Science Collaboration users to kitalpha.

Located fore mib files for proper snmp monitoring of our networking hardware.
Additionally, I've been able to locate the information we would be interested in
monitoring.

Writing a script to generate from snmp a table of mappings of network switch
ports to hosts which will make future reconfigurations easier.

Installed new network drives and tried other changes which did increase network
performance to about 60Mb/s for a 3c905C card, which while a dramatic
improvement, is still below what we should be getting.

Creating standardized software image to installed on all the redhat linux
machines.

Testing UPS software.
 


LIGO II/Advanced R&D (Sanders)


From: Sam Richman <srichman@ligo.mit.edu>
Stiff isolation system (Richman, Rollins, Chatterji)

Transfer function measurements were made to identify the various resonances
associated with the body modes of the two-stage system.  Geophone signals
were blended with position sensor signals at around 0.3 Hz in the upper
stage vertical loops.  The aluminum targets used for the (inductive)
relative position sensors were found to reduce the range of the sensor to
below 1 mm, compared to the manufacturer's spec for steel targets of 2
mm.  Though this likely poses no difficulty to the operation of the system,
we are making up a set of steel targets to evaluate.
 
 
 


For additional information about this report, contact sanders@ligo.caltech.edu