Weekly Report for Week Ending February 10, 2000



 Project Control Meeting Agenda  Highlights  Hanford Observatory     Livingston Observatory     Detector  Project Office    System/Data Analysis    Administrative  Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  February 14, 2000 will be:
 (Meeting time: 10:30 am Pacific Time)

Open meeting 10:30 - 11:30

  1. Announcements
  2. LSC Issues (Weiss)
  3. Comments on Weekly Report
  4. WBS 1 LIGO I Construction (Lindquist)
  5. WBS 2 LIGO Lab Operations
  6. WBS 3 and 4  Advanced R&D and LIGO II (Sanders)
Executive Committee only 11:30 - noon
 

Special Items:


Special Announcements:


Weekly Report Highlights
 
 


LIGO Hanford Observatory (LHO) Operations



Announcements:
--------------
(F. Raab)

Mike Landry joined us this week from TRIUMF to begin his postdoctoral
appointment. We have received responses to our ad for entry-level operators
in the TriCity Herald. (If you know of hot young Physics or EE
baccalaureates, send them to us.

Bake Oven:
----------
(K. Ryan)

LHO vacuum bake oven load #75, consisting of elliptical baffle glass,
faraday isolator mount, forks, washers and bolts was released late last
week.

Load #76, consisting of the final three LHO BSC bellows and hundreds of
Arm Cavity Baffle fasteners, is vacuum baking.

Dennis Coyne notified us this week that some portion of LLO's scheduled
vacuum bake oven loads will be re-directed to LHO.

PreStabilized Laser:
--------------------
(M. Guenther & R. Savage)

We connected two temperature monitors this week.  Both are recorded in
EPICS channels at 1 Hz.   H2:PSL-FSS_RMTEMP monitors the air temperature
in the 2k PSL enclosure.  H2:PSL-FSS_RCTEMP monitors the temperature of
the vacuum chamber for the PSL reference cavity.  Both sensors utilize
AD590 chips and, after preamplifiers and database conversions, give
approximately one volt per deg K.

We discovered that some wires has been soldered incorrectly on the
intensity stabilization servo (ISS) card causing two of the fast data
channels to be interchanged.  This was corrected this morning by J.
Myers by soldering the wires correctly.

The gain on the Generic DAQ interface card for the H2:PSL-ISS_ISERR_F
channel was increased by a factor of 10 to make better use of the ADC
range.  PSL data channel descriptions and calibration information are
available at www.ligo-wa.caltech.edu/~rick/PSL/Channels.

Seismic Systems:
----------------------
(C. Gray & H. Radkins)

HAM1:  The chamber was closed up last week as planned--SEI installation
complete.

BSC3:  This past week had the dome off, all isolation stages installed,
balance weights & Kapton cabling installed, and the dome replaced--SEI
installation complete except for the electronics and pneumatics of the
Coarse Actuation System (CAS).

BSC2:  While access was available through BSC3, the balance weights were
installed and the lower portion of the Kapton Cabling installation was
completed--SEI installation complete except for the leak checks of the
Expansion Bellows and the CAS electronics and pneumatics.

HAM3:  The door has been removed and Isolation stage installation is
beginning today.

Computing:
----------
(C. Patton)

Helped two new Post-docs get set-up with computers and user accounts.
Put in Purchase Requests for two new Sun workstations; one for one of
the Post-docs, the other for the site license server.  Obtained computer
serial numbers for all 30 PCs on site, and some home PCs, then submitted
them to Caltech ITS to be included in the Norton Antivirus site license.

Upgraded the two site laptops to Windows 98, removed unauthorized
software which had been installed by users, upgraded the authorized
application software to current releases, fixed the network
configuration and printer setup so that they would work again.
Purchased an external floppy drive and CD-ROM drive for use with the
laptops and as spares.

Purchased additional MS Office software for two new guest PCs.  Called
for a quote on Exceed 6.2, to upgrade our 20 user site license and
increase the number of licenses to 35.

Spoke with Dr. Lee Philipp at WSU Tri-City about hiring a student to
help with the PC System Administration.  He recommended two students who
I will be interviewing next week.

Continued network security maintenance, did the usual backups, helped
users with several printer and PC problems, and kept the GC accounting
paper work up to date.
 

Controls:
---------
(D. Barker)

Installed CDS VCR in control room. Installed netscape on control room pc
(Tom Nash installed video grabber in this PC). Linked controls logger
(EPICS command channels archiver) to CDS web page.

Started redesign of DCU code. This in response to RFM problems resulting
in network collisions.

DAQ system had several problems this week, some resulting in crashes.
Restarted the systems as soon as we could, and we are investigating the
crashes. EDCU is having intermittent socket problems.

Upgraded CDS Red Book on restarting the complete DAQ and ASC systems.

Upgraded CDS DAQ and Rack drawings, submitted new versions to DCC.
 

Physics Environmental Monitoring:
---------------------------------
(M. Lubinski)

A system to find out the status of data channels and entry of calibration
data has been set up on the CDS web page under a section called "Data
Acquisition System" in a segment called "Installation Files".  When you
open this you will see a file "LHO Calib.PDF" the channels are in rack
order with the status of  the channels shown. There is a folder
labeled "calibration" and in this will be the text files of calibration
data for these channels. There are several PDF files which are the Vender
calibration data for all of the PEM  instruments (seismometers, tiltmeters,
microphones).

Installed accelerometers at both mid stations. Received 2 calibration units
for the accelerometers, one will be sent to LLO.  We are investigating some
problems with the microphone hook up and the power supplies for them.
 


LIGO Livingston Observatory (LLO) Operations



 

Beam tube bakeout: Bake of y1 is on going at 168C. We have had minor problems with cool spots on the gate valves. The mid point valve is the worst offender because the blankets were designed for 44" valves and we had to make them fit the 48" mid point valve. We are working through this. (Allen Sibley)

Input-Output Optics: We realigned the PSL beam which was misaligned when the PZT driven mount at the top of the periscope moved by power shut down last week. The realignment was done by adjusting the periscope mirrors keeping the folding mirrors on HAMs intact. The beam now goes through the centering fixtures of MC1, MC3 and MC2, comes back to MC1, and goes through MC3's centering fixture towards MC2 again. (The centering fixture has the entrance and exit holes and attached to each suspended mirror to fix the angle of incidence.) At this point we started to aligned the steering mirror. The beam now hits the centering fixture of MMT1. The beam reflected by MMT1 hits an edge of MMT2 optic.

We assembled the Faraday isolator on its base in the optics lab using a 700 mW NPRO YAG laser. The polarizers and the half wave plates have been adjusted. The single pass isolation ratio is better than 38 dB. We helped the large optics group damp the ETM at the y end station. We also
helped them measure frequency spectrum when they hung another large optic. (Sany Yoshida)

General Computers:We have received a duplex unit to allow our printer to print double-sided pages.
Bake Oven: We have finished baking an ETM mirror with magnets. We are cleaning and preparing to bake a load of 2" COS mirrors.
(Tom Evans)

PSL: The new pre Mode Cleaner arrived from Caltech. It will be installed with another high voltage power supply during the week of Feb. 21-25 when both Peter King and Rich Abbot will be here. (Joe Kovalik)

CDS: I successfully got DCU cards working at west end station; complete test of system awaits finding GPS antenna and completion of anti-alias box. Anti-alias box stuffed with 850Hz filters for x,y,z of Seismometer and a couple for use with Wilcoxan accelerometer. Obtained power cord from Rusyl and power cord pinout from Paul Russel. We are awaiting power supplies for the anti-alias boxes. Rolf to send two more anti-alias boxes with Lemo's on front with 6-8 more filter modules.
PEM:Matt Smith, Peter S., Rich Reason and I decided on the placement of the seismometer and the tiltmeter at the south end station. I asked Ed Daw to redo his drawing of the Guralp /anti-aliasing filter wiring to use 2 pair TWSP wire and Lemos and I recieved the revised drawing from him today.
Weather Stations: Obtained parts for mounting two new weather towers...pad pouring to begin on Wedn. Feb. 9. Repair and cleaning of rain gauge
completed. Test of Web page update modification on going...
Course for summer Administative work continues into possiblity of me teaching a summer course in general relativity at LLO.
End to End modeling of LSC Work continues to add more detail to block diagrams--investigation into addition of whitening and de-whitening.
Siesmic Analysis with GRASP Horentsia and I put more of the LSU bewoulf computers on line at LSU and mounted GRASP on them.
Angular Momentum My paper demonstrating the generality of the new definition of angular mometum in general relativity, (the first definition that allows for the exchange of angular momentum in general relativity) submitted to PRD.
(Anthony Rizzi)

CDS:
1.) Installed (4) - RG-58 from the Mass Storage Room to the roof (PEM antenna and spares)
2.) Completed hook-up and testing PEM particle counters in the vacuum and optics lab.
3.) Completed termination of PEM accelerometer cables.
4.) Ordered (3) - UPS's for RGA computers.
5.) Installed ETMX suspension controls at the west end station.
6.) Installed PEM microphone cables in the LVEA.
(Rus Wooley)

Dust monitor installation in lab area is complete.
Few testings and modifications of its EPICS programs are done. People who are interested in dust data can check them out from CDS MEDM screen. Did some general electronics part inventory check for EE lab.
Ordered parts and patch cables in great demand for EE lab.
(Juilien Svoboda)

Seismic actuators:
BSC#5 West end station:
Rotated all 4 Air Bearing bases for Z-Pivot installation, installed all Z-Pivot hardware and torqued per spec.
BSC#4 South end station:
Installed View Port per D. Coyne's drawings, torqued same to spec.
Staged all equipment from S. end station to W. end station for Optics installation and alignment.
Fabricating "Stay Clear Zone" enclosures.
Assisting PEM personnel in the installation of RGAs on BSC#4.
(Rich Riesen)
 


WBS 1.2, 1.3    Detector Group


----------------------------------------------
Interferometer Sensing and Control -- Peter Fritschel for M Zucker
(WBS 1.2.1.1.6, 1.2.1.1.7)
----------------------------------------------
2km Arm cavity testing (Rai W, Daniel S, Haisheng R, Ed D, David O,
Robert S, Fred R, Josh M, Nergis M)
We had some successful arm cavity locking this week. We introduced
a notch filter in the servo to attenuate a 5.75 kHz resonance in
ITMx, thanks to a very speedy assembly and testing by Dale O.
This gave us stable locking for several hours with very periodic
~3 minute lock streteches. The control signal drifted by ~3 um in
those three minutes and lock was reacquired almost instantaneously.
Since we were operating at low gain we were not able to realize the
full range of the controller (> 40 um). During a single lock stretch
where we ran with increased DC gain we were able to lock for longer
(~5 minutes). The origin of the drift is not yet known. We have added
temperature sensors in the psl and mode cleaner channels to the DAQ
system to log laser frequency drifts. Earth tides is another candidate.
A second lock attempt two days later was also successful in that we
were able to lock for ~few minute stretches. This time we were unable
to increase the DC gain to lock for longer and had an increased level
of line noise in the arm cavity signals. We are now hunting this down.
We have also observed loss of coherence between the arm cavity error
and control signals at low frequencies when we run at higher gain.
The error signal also develops a large DC offset in the presence of
the feed back signal. These are also under investigation.
Many victims of the transmission monitor will be pleased to know
that the X transmission has been tamed and we know have a transmitted
light signal in the control room.
ISC Design
----------
Peter F. has been working with Matt Evans (visiting from Caltech) on
lock acquisition modeling using e2e; Matt is taking this on as a
thesis project.

-------------------------------------------
Lasers and Optics -- J. Camp
(1.2.1.1.2, 1.2.1.1.3, 1.2.1.1.4,1.2.1.1.5)
--------------------------------------------
Prestabilized Laser -- Peter King
--------------------------------------------
- Two 80 MHz VCO units are currently undergoing testing. Measurements of
their phase noise are currently being performed.
- A modified intensity stabilization servo has been kludged together from
an intensity stabilization servo based on the old AC current adjust
actuator. Initial testing of the servo revealed something wrong with the
circuit. Further testing has been placed on hold until after the
director's review.
- A high voltage PZT pre-modecleaner was shipped to LLO. Installation of
the pre-modecleaner will take place the first week in March.
Input/Output Optics -- Dave Reitze, UF
-----------------------------------------
LHO 2K (Haisheng Rong)
IO WFS - The IO WFS alignment control has been fixed. We tracked down a
misbehaving channel (WFS2/2). After we replaced the demod board and
realigned the beam, the alignment servo showed satisfactory performance.
IO DAQ Channels - More IO DAQ channels has been added to CDS DAQ system:
MC error signal; MC length control; PSL VCO broad band input; and 2 beam
position sensor channels.
MC output beam stability - We installed a quad PD on IOT7 table ~6m away
from the MC waist to measure the MC output beam position stability. On a
short time scale, the fluctuations at ~ 1-1.5 Hz (suspension and stack
resonance) have p-p amplitude of 4 microns vertical and 7 horizontal,
and the largest long term fluctuation observed is about 27 p-p microns
vertical and 14 horizontal over 12 h period.
Also, MC related resonance peaks appeared in X-arm error signal
spectrum. So far we can clearly identify the SOS bounce mode peaks at
14.75 Hz and 15.6 Hz in the power spectrum of the arm cavity error
signal, and they are among the major rms contributors. Another peak at
17.8 Hz seems to be from the MC, as it appears also in the spectrum of
the position sensor signals mentioned above. Origin of this frequency
has not been identified.
LLO 4k (Sany Yoshida, Malik Rakhmanov, David Tanner)
The Faraday isolator components have been assembled on their breadboards
and aligned. This was done in the LLO optics lab. The remaining 5 DLC
mounts for fixed in-vacuum mirror mounts have been assembled (mirrors
installed and posts attached). The Faraday and DLC mounts will be
installed in the vacuum today.
We realigned the PSL beam which was misaligned when the PZT driven mount at
the top of the periscope moved by power shut down last week. The
realignment was done by adjusting the periscope mirrors keeping the folding
mirrors on HAMs intact.

Core Optics Procurement and Metrology -- GariLynn Billingsley
-------------------------------------------------------------
We're attempting a three flat test in the metrology lab. The chilled water
pressure has been changing quite a lot lately. So we've been unable to
stabilize the room. I'm meeting with Alan Rice and hopefully someone from
Physical plant next week to discuss pressure regulation options.

Core Optics Support -- Michael Smith
------------------------------------

ETM TELESCOPE
Ken M. and Mike S. assembled and bench-aligned the ETMy telescope at LLO,
and installed and aligned it in BSC 5 at the end station. The LLO ETMx
telescope parts will be sent from LLO to LHO for cleaning and baking. The
LLO ETMx beam dump parts will be sent from CIT to LHO on 2/10, for cleaning
and baking. Preparations are being made for installation of the LLO ETMx
telescope the week of 2/28.
ETM MIRROR
Mike S. assisted the ISC group, by using the COS IR autocollimator to align
the ETMy mirror in BSC5 at LLO.
PO MIRROR MOUNT
The reworked parts for the 4K PO mirror mounts for LHO and LLO have been
received and will be sent to Allied for cleaning.
ARM CAVITY BAFFLE
Paul K. has completed detailing the glass drawings and is working on the
assembly and installation drawings. The glass cutter will begin fabricating
the arm cavity glass on 2/11/00.
SPARE IR ALIGNMENT LASER
The spare alignment lasers were received, but the SMA fiber optic
termination is still incorrect, and the lasers will be sent back to the
vendor for rework.
INSTALLATION PLAN, LHO
item completion install
4K IO Baffle, HAM2 done ?
Elliptical baffle 4KITMx, BSC3 done ?
Elliptical baffle 4KITMy, BSC1 done ?
Elliptical baffle 4KRM, HAM3 done ?
PO mirror, 4KITMy, BSC2 done ?
PO mirror, 4KITMx, BSC2 done ?
PO mirror, 4KBS-1, BSC1 done ?
PO mirror, 4KBS-2, BSC1 done ?
PO telescope, 2KITMx done 4/00
PO telescope, 2KITMy done 4/00
PO telescope, 2KBS done 4/00
Beam dumps 2K done 4/00
Beam dump 4KETMy vac window done ?
Beam dump 4KETMx vac window done ?
Arm Cavity Baffle, X-vertex done 4/00
Arm Cavity Baffle, Y-vertex done 4/00
Arm Cavity Baffle, X-end done ?
Arm Cavity Baffle, Y-end done ?
INSTALLATION PLAN, LLO
item completion install
4K IO Baffle, HAM2 done ?
Elliptical baffle 4KITMx, BSC3 done ?
Elliptical baffle 4KITMy, BSC1 done ?
Elliptical baffle 4KRM, HAM3 done ?
PO mirror, 4KITMy, BSC2 done ?
PO mirror, 4KITMx, BSC2 done ?
PO mirror, 4KBS-1, BSC1 done ?
PO mirror, 4KBS-2, BSC1 done ?
PO telescope, 4KAPS done ?
PO telescope, 4KITMx done ?
PO telescope, 4KITMy done ?
PO telescope, 4KBS done ?
Beam dump ETMx vac window done 2/28
Arm Cavity Baffle, X-vertex done ?
Arm Cavity Baffle, Y-vertex done ?
Arm Cavity Baffle, X-end done ?
Arm Cavity Baffle, Y-end done ?
ETMx Telescope done 2/28
 

--------------------------
Isolation Group -- M. Fine
--------------------------
Seismic Design (Mike Fine)
--------------------------------------------------------------------------
1 Counter Weights:
Allied has arranged a truck to pick up the counter weights tomorrow.
Weather permitting, the arrival of the shipment at Hanford is expected
to be next Tuesday.
2 Spare CAS:
Hand Precision expects to ship the actuator set to Hanford next Tuesday.
The arrival is possibly next Friday.
 

---------------------------------------------------------
Detector Systems Engineering -- D. Shoemaker/D Coyne
(WBS 1.2.1.1.9)
---------------------------------------------------------
Global Diagnostics System
(Daniel Sigg, John Zweizig)

This week I created an update to the last version of the DMT
software with a few bug fixes. I added a online documentation
on downloading the DMT software modified the code so that
it was more easily compilable on platforms (notably linux alphas)
other than my usual solaris development platform. I have also
been writing a frame directory utility that determines the
contents of all files in a directory containing a large number of
multi-frame files and can be used to summarize this information
for a user or to find a specific frame within the directory.
Started writing code for storing/restoring the plot settings of the
diagnostics test tool.
The diagnostics test tool software was downloaded to LLO.
Compilation of VxWorks/VME code was going smoothly and
the test point manager code could be installed. Compilation
for Solaris revealed several problems with corrupt and out-dated
system libraries. We think these problem can be fixed by
installing the most recent Solaris patches.

Physics Environmental Monitor (Matt Smith)
-----------------------------------------------------------------------
This week in Livingston I installed an RGA tree in the LVEA on the Y
arm, near the 80K pump. I am also in the process now of installing the
RGA tree in the Y end station. These sections need to be leak checked
and baked.
I also intstalled the PEM interface plates onto BSC 3 and 4.
Meet with Rich Riesen on locating the PEM stay clear zones for the
seismometers and tiltmeters. We had some discussions on setting up the
seismometers and tiltmeters with Anthony rizzi and Peter Saulson.
Walked thru the LVEA with Russ Wooley marking the locations for the
microphone power supplies.
 

-----------------------------------------
Control and Data System -- R. Bork
(WBS 1.2.2)
-------------------------------------------
IO Controls (Jay)
====================================
- Design and layout completed for the four channel 14.75Hz, Q=100 notch module
required for LHO. Boards should be fab'd by 2/21.
Suspension (Jay)
===================================
- Thesecond LOS controller that failed on LHO FMY has been repaired. All of
the
output stages had failed. This chassis did not have any vaporized traces like
the first chassis that failed. The cause of the failures is still under
investigation.
- Jay is putting together some modification kits to upgrade all LOS
controllers.
These upgrades will require that the chassis be removed from the system. The
upgrade should take less than 1 hour per chassis.
- Strawman and conceptual designs for the all digital suspension system are
being developed. Rolf and Jay will be testing in order to answer some of the
outstanding questions such as can the ICS110B ADCs be used? Should we use
Pentek
DACs?....
- Jay has designed a few circuits to test the feasibily of building a
universal
dewhitening filter that would be required for a "full up" digital suspension,
LSC and ASC system. So far there appear to be no show stoppers.
- Coherent detection satellite amps are being fab'd and should be ready for
bench test by 2/14. They will then be installed at LHO and tested in the
system.
LSC CDS (Dale):
=============================
Have been working on the LSC Common Mode Servo design. To solve some
noise issues I designed a 16 Step Variable Gain Amplifier with a range
of 0 to 45 dB in 3 dB steps. It has 3nV/rtHz input referred noise and a
voltage swing of +/- 13.5 volts. It is gain controlled by a linear
differential voltage to eliminate the possibility of ground loops from
digital ground connections. And it costs a few dollars per channel in
small quantities. This may prove to be very useful in other control
circuits. There is still much work to be done on the CM Servo design.
Helped Mohana with noise modeling of the LSC Whitening /AA filter
circuit. This circuit will be split into two boards because of board and
front panel space.
GPS Timing System (Dale):
=============================
The 7 Clock Driver boards are just waiting for me to get to them for the
final testing and then we will ship them to the sites. We are in the
process of getting the Y2K upgrade EPROMS from JXI2 and installed them
at the sites.
Data Acq.
=========
- (H. Ding) A Java interface has been written for the control of the tape
robot
system; now working on interface to user applications to write data to /
retrieve data from tape automatically.
- (R.Bork) Working on designs for upgrades to present system, including single
configuration tables used by all applications and increasing EPICS channel
data
acquisition beyond the present 1Hz rate.
Suspensions (Rolf)
==================
- Began working on software designs for digital suspension controller. Had
hoped to run some benchmarks to refine an initial timing diagram, but the last
batch of Pentium III processors we received did not come with the vxWorks
microkernel, as ordered. These have been shipped back and will take a week or
two to return.
PSL (Rich)
***********
1. Preparing for the Directors Review next Tuesday
2. Lowered the noise of the PSL VCO to about 6 mHz/rtHz flat from 100 Hz
to 10 kHz
3. Testing of two more VCO's is just about complete and will allow a quick
change out of the VCO's at LHO and LLO
4. Participated in the development of the LIGO2 laser spec.
LSC/ASC Frequency Distribution (Rich)
***********
1. Finished all final reviews of the first part of the system (AM
stabilizer) and sent boards out to the board house.
2. Receiving parts for the above system.
 


WBS 1.4    Project Office


 WBS 1.4.1.2   Project Controls



Reports (Lindquist) Change Control/Contingency (Lindquist)

The following change requests have been submitted:
 

CR-990028 WBS 1.1.3 Beam Tube Enclosure Closeout F. Asiri
CR-990029 WBS 1.1.4 Fencing Road at Livingston (Info Only) G. Stapfer

Press for the latest Contingency Needs Projection


LIGO Weekly Site Telecon (Jasnow)

A site telecon was held on on Thursday, February 10, 2000.  The list of current actions assigned may be found at ACTION LIST.


PROPERTY MANAGEMENT (Chargois)

From: Ed Chargois <chargois_e@ligo.caltech.edu>

Assisted the Project Control Office (P. Lindquist) with packing, shipping, and Customs Certification for posters to Australian National University (Dr. D. McClelland).  Account Number P47783.

Assisted the Detector Group (P. Kabot) with packing and shipping of Arm Cavity Baffle Outer Frame Hardware to the LLO (J. Kern), delivery confirmation received.  Account Number P96037.

Assisted the Detector Group (S. Whitcomb) with packaging and shipping of 12 cartons of books to the LHO (F. Raab).  Account Number P158180.

Assisted the System Administrator (L. Wallace) with packing and shipping of a Gateway Computer SN# 3091930 to LLO (T.Evans), delivery confirmation received.  Account Number P 97273.

Assisted the Caltech Safety Office with the Inventory of  all Laser 3B and above.  Also a courtesy inspection was performed.  Several on the spot corrections were made.

Liasion Vist to China Lake USN Weapons Station and Edwards AFB in search of surplus  government equipment for the project.

Rick Savage requested that I become the Point Of Contact for a possible damage claim for a Laser and Chiller that was damaged by DSI during shipment.  All necessary Claim forms will be filed along with  photographs to DSI (I. Baker)


DOCUMENT CONTROL CENTER (Turner)

From: the DCC <dcc@ligo.caltech.edu>

Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .

ACTIVITY HIGHLIGHTS

From: Cleveland Mak <mak_c@ligo.caltech.edu> Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.


COST SCHEDULE CONTROL SYSTEMS (Duncan, Moore, Akutagawa, Kaufman)

From: Esther Cunningham <esther@ligo.caltech.edu>

Press here for ACCOUNTS PAYABLE HISTORY DATA.

From: Ruth Brambila

I've started the spreadsheet into Excel to keep track of the LIGO contracts.  I really don't like to start a shadow system, but it may be helpful to keep track of the standard po's and the subcontract number initially.  The list helps Esther when she sees old "PC.." numbers on invoices and needs to find the Oracle corresponding number.  Initially, it'll be on a shared drive where Esther can see it also.  Right now it is in it's rough draft stage.  Later if we find that we don't need it, it can be discarded.

On Tuesday, I talked to Dorothy about receiving everything on po's.  Previously, only goods were being received in Oracle.   We now understand that everything (dollars on amount-based po's and subcontracts) also need to be received.  Dorothy will being receiving everything beginning Monday, February 14th.  The receiving function is necessary to effect transfers of funds on poetas and to process change orders to subcontracts.

Today, I sent out a response to a collection agency regarding Barry Barish's phone line which Caltech tried on numerous occasions to cancel, but GTE would not cancel the service.

I am going back to LIGO orders placed since Oracle came live and writing up "price analyses" (justifications).  The majority of the justification forms submitted with the req's only address source selection, but do not address price reasonableness.  There are 54 orders that do not address "price reasonableness".  I've taken care of 16 so far.  I have 38 justifications to do.

I received four (4) spreadsheets from Cindy Akutagawa to cancel encumbrances on various subcontracts and one-time po's.  Some encumbrances have been released on the one-time po's, however, I am waiting to hear back from Jose how I should handle reductions of subcontracts.  There are various issues involved here.  My making the change would revise the p.o., so it probably needs to be a change order.  If it is not a change order, then it would throw off the balances off and change order sequence when an actual change order is submitted by Irena, etc.  Also, as it is a reduction, the contractor needs to be made aware of the reduction.

We have two po's (Burns PX295760 and High Performance 1005937) which have active encumbrances on cancelled lines, which are in a permanent state.  Kathy Meade is working with Oracle to see how these funds can be released as there are other cases of this.  This was created by cancelling a line that had not been received, but had been paid.  We've since realized that everything needs to be received, and nothing can be cancelled until the billed amounts have been received.

From: Kris Duncan <kris@ligo.caltech.edu>

From: Florence Kaufman <fkaufman@ligo.caltech.edu> From: Cindy Akutagawa <cindy@ligo.caltech.edu> SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: irena@ligo.caltech.edu (Irena Petrac)

From: Ed Jasnow <jasnow@acrux.ligo.caltech.edu>

At a meeting held on Tuesday, February 8, it was agreed that the Caltech Acquisition Group will begin processing contract change orders in accordance with agreements reached with the LIGO Project several months ago.  This method essentially consists of the use of standard purchase orders to modify basic subcontracts in lieu of change orders.  The links to the basic subcontract are contained both in the system and in the text of the purchase order.  The first use of this method will be through Change Orders 6 and 7 to the MIT subcontract.

The architect/engineer for the Staging Building in Livingston, John Desmond Associates, has submitted his conceptual drawings for the building on schedule.  These drawings were discussed in a review held on Thursday, February 10, and further direction will be given to the contractor.

A request for candidates to perform scheduling on Primavera for LIGO II was sent to the four labor-hour contractors currently providing staff to LIGO.  These four are Triad, NYMA, Butler, and Support Services.  This position is scheduled for six months to one year.


WBS 1.4.3    Systems Engineering / Data Analysis and Computing



 
 

Systems Engineering

No report

Simulation and Modeling


* Matt visits MIT this week to talk with Peter Fritschel to learn about
the current LSC/ASC design. Before and during this trip, Hiro generated
using twiddle various transfer functions and powers build-up under
various resonant conditions. This is used by Matt and Peter to discuss
about the lock acquisition strategy. Next Tuesday, there will be a
meeting at CIT to discuss about the Lock Acquisition work based on this trip.

* Biplab kept working to improve the optics implementation, especially
the time dependence of the fields in the summation cavity is implemented
and validated.

* Hiro modified the simulation engine framework to speed up the code and
to make the output always friendly to matlab. adlib can now generate
binary format output. The fully STL compliant implementation speeds up
the simulation, and the simulation code is now being fixed for it.
The strategy is considered and discussed to save an intermediate
state and to load it later.

GUI

* Alfi4 release is imminent. Ed and Bruce worked hard to fix bugs and to
improve the code to make it possible to build a working version of new alfi. The
new version will have features to support more complex configurations.

Code release and maintenance

* e2e binary codes will be available in two places. One is a final
release version,
which uses staw facility. This is stable and reliable. Another is a test
version,
which can be updated daily. This version will have new features, bug
fixes, speed
improvements etc.

* A bug reporting interface using gnats is implemented in the e2e home
page.

LIGO Data Analysis System

[LazzarinI]

*    I spoke with John McCoy of PNNL regarding long term strategic plans for
high BW OC3/OC12 connections at Hanford. LIGO will be included in planning discussions
they will have in the future with local service providers. At present the market in the Tri-Cities is
not favorable to consumers. The commercial OC3 rate costs $480k/yr, whichis what PNNL will be paying.
There is hope (only hope) that as additional providers decide to move into the market in Eastern Washington (due
to the ballooning population), prices may plummet in several years...

*    I met with Stan and Rolf and our group to discuss the timing and planning for release of
the next frame format software. Consensus is to do it as soon as code is validated and available.

*    Kent and I are collaborating with S. Scott/D.McClelland at ANU to help them develop a 3-yr grant proposal to ARC.
 

[Kent Blackburn]

* (JKB) The new LDAS system administrator started this week (Omar Rashad). His
        efforts have already impacted in a positive manner, the
        efforts of the software development team towards LDAS
        goals, especially with regard to tasks Ed is associated
        with, since Ed is now somewhat more available to work LDAS
        projects.

* (JKB) Progress continues to be made on the socket class library. Ed
        reported this week that he has identified the necessary changes in
        the code to get the local loop-back socket communications working
        on the Sun boxes. Should be a simple step forward to make this
        work for Linux boxes also. However, there is still no progress
        on the linux <-> solaris socket communications issue.

* (JKB) The MPICH version 1.2.0 MPI library proved to be problematic this
        week. The bulk of the trouble we have been having is related to
        the libraries bizarre mixing of C++ exception handling between
        C and C++ code blocks. MPICH claims that GNU's compiler is not
        fully supportive of exceptions, but they reference a version of
        the compiler 2 or 3 years old. It looks to me like the MPI code is
        playing tricks with C pointers which breaks C++ exceptions and
        that the compiler is not the problem. We will have to write a
        minimal amount of extra error and exception handling to deal with
        the deficiencies of the current release. As an aside, much work
        went into the requirements for the wrapperAPI this week (which
        will be using the MPICH 1.2.0 MPI library.

* (JKB) A search was made this week to identify pentium quad processor
        hardware to support the multi-threaded dataConditioningAPI. We
        have identified 3 vendors with price structures roughly have of
        the cost Sun is offering for a similar 4CPU 450 servers. There
        is however quit a range in 4-way pentium hardware these days. I
        will start the process for acquiring one unit this week.

* (JKB) Paperwork for the Australian ARC proposal support was submitted
        to the ANU group this week. At this time it looks like all the
        needed materials are now delivered for the review process down
        under.

* (JKB) Continued weekly meetings with ANU, PSU, and UTB on the development
        of the dataConditionAPI functionality.

* (JKB) Held a meeting with BK, AL, EM and myself to discuss and detail
        the first phase of a redesign of the LDAS webpages. The changes
        will involve combining LDAS related materials located in two
        distinct areas on two distinct file servers into a common area
        and providing more user friendly interfaces for getting at the
        information that "matters".

* (JKB) The problem tracking system continues to be utilized by LDAS a
        roughly the same level as last week. The clear advantage that
        the system is showing know is its ability to prevent issues that
        came up several weeks ago in the last LDAS release build from
        falling through the cracks and not getting attention. This will
        have the effect of resolving many problems that traditionally only
        get looked at during a build cycle in between the builds, which
        in turn should simplify the chaos during LDAS builds.

[Masha Barnes]

* (MB) LightweightAPI bug fixes:
       - added support for 'char' elements of ilwd Table column without
         space delimiters.

* (MB) MPI:
       - found the bug in MPICH configuration which was preventing from
         enabling exception throwing in MPI code.
       - Traced the exception throwing bug to be a function pointer problem
         instead of gcc exception throwing problem as it was claimed by
         implementors of MPICH C++ bindings.

[ Phil Ehrens ]

*(PSE) Worked with Alex to extend the functions of the frame API
       to include extraction of arbitrary frame elements and
       package them in ilwd containers.

*(PSE) Wrote new user command getFrameElement to make use of new
       frame API functions to support extraction of arbitrary
       frame data elements.

*(PSE) Modified the "hotgrep" utility to handle "deleted" files.
       If you delete a file that is being polled by hotgrep,
       and then recreate it, hotgrep will handle it transparently.

*(PSE) Supported Mary Lei and Peter Shawhan's work on the
       metadata API user commands.

[Alex Ivanov]

* (AI) FrameCPP "make dist" tested and bug report given to Ed

* (AI) fixed a problem with updating Vector class' data in FrameCPP::DaqFrame

* (AI) byte swapping implemented for DaqReader, DaqFrame classes in FrameCPP

* (AI) FrameCPP Vector class data byte swapping problem fixed

* (AI) make FrameAPI changes requested by Phil

[Barbara Kratochwill]

* (BK) Attended meeting to plan changes to LDAS web site.

[Mary Lei]

* (ML)  Reloaded cit_1 database with new tables that have comment
        instead of remark. Tested putMetaData user command for ilwd format.
        Reported a problem with ligolw conversion of xml to ilwd.
        Reported some macro problems.

* (ML)  Closed problem reports related to metadata macros.
        cvs changes and test file changes.

* (ML)  Updated db2 document page with cit insertion rates and
        new multi-table ilwd.

* (ML)  Improved metadataAPI handling of exceptions and return
        of exceptions to manager since the user seems not to be
        getting the exceptions and the next step gets executed
        in getMetaData.
 

[ Edward Maros ]

* (EFM) Create CVS accounts for several users

* (EFM) Continued work on Linux to Sun communication

* (EFM) Started looking at loopback issue for Solaris
 

[Peter Shawhan]

* (PSS) Finished working on a program to log Epics
        control settings at the sites, and a web interface
        to retrieve information in a few useful ways.
        (Actually, this is not currently connected with LDAS,
        but eventually this information will be stored in
        the LDAS database.)

* (PSS) Updated the graphical user interface to the LIGO
        database ('guild') to access the database through
        the LDAS APIs.

[Wallace for LDAS]

Received and getting a number of quotes for budget purposes on the beouwolf
system.

Stuart Anderson:
        Started a technical discussion with Sun on the possible use of
their resell of the VERITAS Storage Migrator as a candidate for the
LIGO on-site mass storage system.

        Working with the Software Coordination Committee to put
together a top-down software development schedule for integrating LSC
software into LDAS, including externally visible milestones in the form
of pre-planned mock data challenges.

        Figured out how to get Linux running on the new Dell laptops,
which requires the latest beta version from RedHat, i.e., RH6.2Beta.

[Omar Rahsad-LDAS SysAdmin]

Applied Redhat 6.1 upgrade and updates to computer from WA.  The system has
passed initial burn-in phase and pending some further testing should be ready to
be shipped back.

Setup new user workstation m71.  Some configuration issues arose which are then
in turn issues with the cfengine automation system.

Performed monthly backup.  We are about to break the limit of four tapes.
Alternate methods of backup need to be considered as there is question as to
whether backups are being captured properly (see below quote from ufsdump
manpage) and practically.  (Depending on our growth rate, a full backup might
eventually not be possible to perform in the course of a normal business day).

     "When running ufsdump , the file
     system must be inactive; otherwise, the  output  of  ufsdump
     may  be  inconsistent  and  restoring files correctly may be
     impossible."

Resolved problem of access to the CD burner on kitalpha by making the necessary
devices.  Tested successful by burning iso of Redhat 6.2beta release needed for
configuration of Stuart's new laptop.
Use device /dev/cdr or /dev/cdrw.

Partial setup of new user workstations m81 and m82.  Final assimilation is
delayed pending resolution of cfengine issues.

Resolved two issues of how mail was being sent from spica.  Mail will now appear
to come from @ligo.caltech.edu and mail will now be delivered to remote
addresses.  This has however revealed a third issue, which is being looked into
as gnats still won't send mail to remote addresses.

This almost completes everything that was on my immediate to-do list.

Walid Majid:

Held another telecon with the LSC team interested in doing a coincidence
analysis of the 40m and TAMA data. Discussed the elements of a pipeline to
carry out a match filter analysis and figures of merits to quantify how
good a job we have done in terms of cleaning up the data set.

Continuing to look at the stationarity issue for the GW channel in the 40m
data set, using time-frequency techniques.  I am basically taking short
stretches of lock data, and calculating a power spectral density for even
shorter segments. I then look at how the normalized mean and variance for
each frequency bin evolves as we move along the time axis.

General Computing


MIT:
Working on installing new disk drives.

Livingston:
We have received a duplex unit to allow our printer to print
double-sided pages.

Hanford:
Helped two new Post-docs get set-up with computers and user accounts.
Put in Purchase Requests for two new Sun workstations; one for one of
the Post-docs, the other for the site license server.  Obtained computer
serial numbers for all 30 PCs on site, and some home PCs, then submitted
them to Caltech ITS to be included in the Norton Antivirus site license.

Upgraded the two site laptops to Windows 98, removed unauthorized
software which had been installed by users, upgraded the authorized
application software to current releases, fixed the network
configuration and printer setup so that they would work again.
Purchased an external floppy drive and CD-ROM drive for use with the
laptops and as spares.

Purchased additional MS Office software for two new guest PCs.  Called
for a quote on Exceed 6.2, to upgrade our 20 user site license and
increase the number of licenses to 35.

Spoke with Dr. Lee Philipp at WSU Tri-City about hiring a student to
help with the PC System Administration.  He recommended two students who
I will be interviewing next week.

Continued network security maintenance, did the usual backups, helped
users with several printer and PC problems, and kept the GC accounting
paper work up to date.

CIT:
Sam updated the ip list and helped Florence on some e-mail issues.

Barbara installed the latest version of TimeTarget, the NT scheduler, on
antares server.  The latest version allows you to schedule several
processes in sequence and name files that must exist before a process
begins (among other new features).  TimeTarget is used overnight to backup
the DCC database, update the database links to electronic files, and run
reports.
Began work on DCC changes to check-out a document revision number.
Added a field to the LSC Roster tables, forms, and reports for
professional designation.
Sent a copy of costbook database to Bill Althouse along with some
documentation.  Answered some emails about how it works.
The DCC Search tool and the Get-a-Document-Number tool now point
directly to the DCC database.  Any changes to the database are reflected
immediately. Links to electronic documents appear the next working day.
Picked up the editted Nov 11 tapes from Alta Video.  We reviewed a few
cuts at the studio and they looked good.  The re-editted Colwell
presentation has been encoded at 80 and 34 kbps.  Reviewed various versions
of high-speed variable bit-rate encoding of the Nov 12 segments.  The
Digital Media Center is using our videos to hone their variable bit
encoding techniques.   We decided on some settings that look best.

Suresh worked with Larry on migration to new sirius over the weekend. All
Sun workstations are initialized as NIS+ clients. Transferred users home
directories and some applications to new sirius. The process of tunning up
sirius is continuing that might last few weeks.
Making full backups of filesystems in new sirius. But yet to work on tape
robot for daily backups.
Setup couple of users accounts for new Handford post-docs.
Helping users to update their accounts/machines as a consequence of the
migration.

Larry worked on the move to the new sirius server. This process will take about
another week to get all of the kinks worked out. The initial move took quite a
bit of time because of the need to setup new NIS+ tables and the data transfers
took longer than they should have.
The upgrade included a number of application upgrades which have had some minor
problems but generally went OK.
Working on getting new s/w for the backup juke box system to be installed on the
sirius upgrade.
Worked a number of procurement and licensing issues.
Worked with Cindy to clear out a number of old financial issues.
Works in progress, along with the sirius upgrade is the installation of a new
docuserv unit which should happen at the end of the month and a new ftp server.
We have done some testing on a internal to ligo and external anonymous ftp
server and found a configuration that should allow people to transfer files
without too many problems.
Installed/setup a couple of pc's and laptops.
The work on video connections between computers has been put on hold. We will
get back to that project after the server system upgrades have been finished.
Used the projector system for a real conference meeting and it worked out quite
well.
 


WBS 1.4.4.1    Administrative Group


Dorothy Lloyd

After being away for 2 weeks, returned to a very heavy load of invoices to be processed. Needless to say, spent the majority of this week processing invoices. Processed receiving and requisitions both on- and off-line at a minimum.

Irene Baldon

This report covers only 4 days since I was out 1 day on sick leave. My time was taken with an unusually high number of problem issues thus reducing my stats.

Worked on preparing the paper work for 22 new trips taken recently or upcoming (22 Payment Requests and 18 Advance Requests). There are approximately an additional 10 new trips in various stages pending completion of travel arrangements before the paper work can be completed. Also worked on an extremely high number of problem issues which required a good portion of my time.

Completed 10 Expense Reports, some of which were extensive, involving 2-3 or more pages each. Some of these reports were still not taped or completed by the Traveler, and required additional time for completion. Worked additionally on a number of problem issues associated with these which required a good portion of my time. There are 28 Expense Reports still to be done. I'm holding 4 completed Expense Reports which require a check from the Traveler before sending to Travel Audit to clear. Rita/Liz have 6 Expense Reports to work on.

I have not seen any significant change in the time lag for receiving checks. They still continue to hold checks in Disbursement Audit for up to an additional week after the check has been issued. This additional lag adds significantly to the lag that already occurs in Travel Audit/Accounting. I have started receiving T numbers intermittently. We'll have to see how long this lasts this time.

Performed normal recording and filing associated with Travel and Reimbursement.

Prepared the Travel/Vacation Itinerary for the Week of February 8, 2000.

Performed miscellaneous duties as requested by various members of the LIGO Project here at Caltech, as well as from members of the staffs of each of the two (2) sites. I continue to do MIT's travel to the sites for installation activities and also to assist them wherever possible.

Rita Torres

I lost my network connections Monday through Wednesday, and I could not print. At Thursday morning everything appears to be working. Many thanks to Suresh Singh who worked tirelessly to resolve these problems, and to Fred Asiri who printed for me the things I relayed via email.

For I. Petrac did edits to accounts sheet for change order No. 7 to MIT, obtained an Oracle requisition number. Per R. Brambila request, re-input information for Lightwave Electronics in order to obtain a new Oracle requisition number. Copied for internal distribution the package going for NSF approval of modification to the Galli & Morelli contract. Chased some LSC reports, submitted these for posting on the web.

For E. Jasnow, did letter to Siemens Building Technologies, Inc. to transmit the executed contract. Prepared then FedExed 4 letters Re: Scheduler Requirement. For P. Lindquist obtained copies of Annual Work Plan for Operations & Commissioning, FedExed to the NSF.

Spent a bit more time for input of subsystem drawings dates and titles. Project ongoing. Over several days, I took a stab at helping out with travel expense reports.

Set up on the 3rd floor name labels for Kenji Numata. Ongoing P-card purchases, reconciling, and chasing after details. Slightly more update to PO log for D. Lloyd. Doing as time permits.

Elizabeth K. Wood

Began putting together Guide to LIGO: An Employee’s Best Friend. It includes LIGO’s policies, among them the publication policy, safety procedures, computer information, and travel policies.

Worked on LIGO’s office space situation.

REMINDER: PLEASE let me know when you are expecting visitors/guests who will be here for an extended visit and will need office space. I just hate surprises.

After payroll had been delivered last week, one of our employees pointed out to me that he hadn't gotten a paycheck. Not only had he not received a paycheck receipt, but nothing had been deposited in his account. I called payroll to find out what had happened. It appears that not only had one LIGO employee been shortchanged; two had. Fortunately, the good people in payroll rectified the situation within a couple of hours and issued checks immediately.

ORACLE continues to amaze me with its deft manipulation of data. For several months now I have been trying to restore some lost vacation time to an employee after ORACLE subtracted vacation hours the employee never took. Those hours MAY be restored in the coming weeks; I’ll believe it when I see it. It’s only been two and a half months since we first discovered the problem.  These things take time.

Along those same lines, I adjusted another employee’s vacation time several months ago; it has yet to show up as corrected on the employee’s vacation total.

My utter confidence in the DEBACLE system remains unshaken.

Nota Bene to Caltech employees: Your personal holiday converts to vacation time if you don’t use it during the year. This becomes important if you are nearing the vacation accrual limit of 320 hours. To avoid possible errors regarding the accrual of vacation time, please consider taking your personal holiday before the last two weeks of December.


For additional information about this report, contact sanders@ligo.caltech.edu