Weekly Report for Week Ending December
14, 2000
The LIGO Executive Committee
Agenda for Monday December 18, 2000 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
-
Announcements
-
LSC Issues (Weiss)
-
Comments on Weekly Report
-
WBS 1 LIGO I Construction (Lindquist)
-
Field Change Orders/Contingency Liens/Change Requests
-
WBS 2 LIGO Lab Operations
-
Administration (Lindquist)
-
Sites (Raab, Coles, Shoemaker, Sanders)
-
Detector (Whitcomb, Coyne)
-
Campus Research Facilities (Weinstein (40 Meter), Libbrecht (TNI), Zucker(LASTI))
-
Data Analysis and Computing (Lazzarini)
-
WBS 3 and 4 Advanced R&D and LIGO II
(Sanders)
Executive Committee only 11:30 - noon
Topics:
Special Items: PAC 9 and GWDAW reprise
Special Announcements:
Weekly
Report Highlights
The TNI arm test cavity lock has been achieved!
LSC Issues (Weiss)
No report.
LIGO I Construction/LIGO Laboratory
Administration (Lindquist)
WBS 1.2 LIGO Operations--Administration
LIGO Weekly Site
Telecon (Lindquist)
No Report this week.
PROPERTY
MANAGEMENT (Chargois)
From: Ed Chargois <chargois_e@ligo.caltech.edu>
-
Assisted the Detector Group (L. Jones) with the preparation
of two Caltech Physical Plant Project Request for shipping crates . Account
Number LIGO 00008 1.6.2 NSFLIGO.000002.
-
Provided the a letter to Caltech Insurance Adjuster
(D.Artura) referencing the reimbursement for the repaired of the damaged
Ford Corsica At LLO for the sum of $3946.72 minus $200.00 deductible, these
funds will be credited to the LIGO Account.
-
Assisted the Detector Group (L.Jones) with the packing
and shipping of the following Machined Part 4 Support Beams (D000360_2A)
, 1 Bottom Plate (D000361-A) and 1 Top Plate (D000362-A) tp LLO att: R.
Riesen expected delivery date 12-14-00 via UPS account Number LIGO. 00008
1.6.2 NSFLIGO.000002.
DOCUMENT
CONTROL CENTER (Turner, Mak)
>From: Linda Turner - turner@ligo.caltech.edu>
Web pages for the
DCC give simple how-to's for document numbering, easy access to the latest
on-line documents, and search capabilities for the DCC database. Take
a look. . .
ACCOMPLISHMENTS
-
The audit process continues with the Hanford construction
drawings.
-
I finished a review of the 40-M
science bulletin board to check that all documents are numbered and
available in the DCC electronically. I began with the 40M Update
board and, so far, out of the first 14 documents, only 4 were numbered
and in the DCC. All documents currently on the board have been numbered
and entered into the database. A meeting with Alan is next to let
him know the numbers and the links that need to be updated. This
process will continue through all the bulletin boards.
-
Christmas party planning culminated in the annual LIGO
party. Approximately 130-150 LIGO-ites, friends, and family came
to the festivities and a good time was enjoyed by all (I hope. . .)!
-
Worked through another large number of electronic documents.
Over 60 electronic documents were processed and transferred into the dcc
directory and database. This represents another hectic week of processing.
-
The schedule for transitioning the DCC to Office 2000
was completed.
REMINDER to all LIGO-ites
-
Electronic documents continue to come in at a regular
pace. To help keep the process streamlined and timely for everyone:
-
File naming should be based on the root part of the
number plus the revision and without the Group ID. Additionally,
the file name should be in capitals, and the format extension in small
letters. Thus a document numbered as
-
LIGO-G990025-00-D would
have a file name of G990025-00.pdf
-
All pertinent information needs
to be on every document. This includes:
-
DCC number
-
Author's name
-
Date of document
-
Title
-
Duplicate submittals can be confusing
as well as time consuming. If you can't remember whether a document
has been submitted to the DCC, you might check the docspublic directory
to see if it resides there. Or, feel free to give us a call so we
may check for you.
From: Cleveland Mak <mak_c@ligo.caltech.edu>
-
Progress continues on auditing of Hanford Construction
drawings with no new problems to report.
-
Assisted Fred and Linda in preparation of a contract
(Livingston New Staging Bldg.) to be shipped out soon.
-
Processed numerous electronic docs
|
Packages |
Faxes |
| In |
58 |
34 |
| Out |
16 |
32 |
Press here to access the DOCUMENT
CONTROL CENTER WEB PAGE.
COST
SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Akutagawa, Kaufman)
From: Esther Cunningham
<esther@ligo.caltech.edu>
Press here for ACCOUNTS
PAYABLE HISTORY DATA.
| Date |
Incoming Invoices And Receivers |
Wires |
Large Contract Invoices |
| December
8, 2000 |
10 |
0 |
0 |
| December
11, 2000 |
12 |
0 |
0 |
| December
12, 2000 |
12 |
1 |
0 |
| December
13, 2000 |
3 |
0 |
0 |
| December
14, 2000 |
11 |
0 |
0 |
| Totals |
48 |
1 |
0 |
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
From: Florence Kaufman <fkaufman@ligo.caltech.edu>
-
Completed and posted Operations report for November.
-
Working with Dot and Ruth to transfer encumbrances to
the new numbers for the ten month Fiscal Period ending September 30, 2001.
-
Worked with Federal Accounting on required Budget Alignments
for Construction accounts, so that Sponsored Research can bill the NSF.
The Oracle system does not permit billing where the budget entered in Oracle
for a project number exceeds the costs recorded for that project number.
-
Continued working with Federal Accounting to make sure
that the budgets in Oracle agree with the NSF awards for Construction,
Operations, R&D and Visitor Programs. Currently the Budgets in
Oracle for the Construction Accounts is less than the Award amount by approximately
$480,000.
-
Submitted Cost Transfer Requests for the University
of Florida contract. $126,553 previously charged to a construction
account are to be reclassified to various operations accounts.
SUBCONTRACTS MANAGEMENT (Petrac,
Jasnow)
From: irena@ligo.caltech.edu
(Irena Petrac)
-
Univ. of Florida: CO No. 10, adding FY'01 funding for
continuing commissioning and operations support at LLO is pending M. Coles'
concurrence/approval.
-
NYMA: Proposal for FY'01 rate increases and continuing
support (D. Beckett, L. Cardenas and L. Turner) was received and is in
review by the Project Controls and Detector Groups.
From: Ed Jasnow <jasnow@ligo.caltech.edu>
-
Discussions were held on Thursday, December 14, concerning
impacts on operator's procedures as a result of the Engineering Run held
at Hanford, and the laser safety incident at Livingston earlier this month.
Results of these discussions will be announced at a later date.
Support (Elizabeth
Wood) <ewood@ligo.caltech.edu>
Dorothy Lloyd
-
Began updating PO Log (9/4-12/4, 174 POs and change
orders).
-
Processed the usual requisitions, invoices and receiving
on-line. For more detail, see "Cost Schedule Control Systems" report by
Esther Cunningham.
-
Tracked and followed up on invoice problems.
-
Reviewed and recorded payments processed by Esther for
the week of December 4, on contract summary sheets and LIGO database.
-
Continue to monitor contract and blanket order funding
levels and notify task managers when supplements are needed.
-
Jim continues to do data entry in the LIGO database
and help out in the DCC.
Irene Baldon
-
Ten (10) new trips were started and I have five (5)
trips pending final approval before tickets can be issued. These
trips required Advance Checks to be written as well as hotel and car authorization
forms to be filled out and Faxed to the appropriate location.
-
Worked with a few travelers who had questions or needed
further clarification on using or reconciling their new P-Cards.
For the most part those having cards seem to be doing fine and find the
cards a convenience. Reconciled twenty (20) items on my P-Card this week.
Several items were difficult to track down since the vendor's 3rd level
information was sketchy at best.
-
Worked on and completed ten (10) Expense Reports.
I have forty-three (43) Expense Reports to work on. The new Expense
Report that I sent out a couple of weeks ago is not being used by most
of our Travelers. Everyone who is using this form seems to be adjusting
to it quite nicely. I continue to make myself available for any assistance
they may need.
-
Due to bad whether through the country this week, two
(2) days of my time were greatly taken up by travelers needing assistance
due to canceled or delayed flights. Fortunately I only had one (1)
traveler trapped overnight due to an ice storm in Dallas. Flights,
hotel and car rental reservations had to be changed or switched.
-
Prepared the Travel/Vacation Itinerary for the Week
of December 11, 2000. Performed normal recording and filing associated
with Travel and Reimbursement. Worked on several problem issues with
Travel Audit in addition to the above listed issues. Also performed
miscellaneous duties as requested by various members of the LIGO Project
here at Caltech as well as from members of the staffs of each of the two
(2) sites. I continue to do MIT's travel to the sites for installation
activities and also to assist them wherever possible.
Rita Torres
-
Was out sick for several hours this week.
-
Tallied MOU documents I have scanned, chased those not
on web page. Did change order No. 10 to University of FL. FedEx
for their signature Attachments C and D, University of FL.
-
Organizing incoming letters of recommendation for R.
DeSalvo, in communication with the attorney facilitating residency business.
-
Ongoing activity: The usual chase for details associated
with Pcard purchases in order to reconcile. Prepared for E. Chargois
a summary of purchases using credit card for the Bridge Development lab.
Activities for the lab set up are ongoing.
Elizabeth K. Wood
-
Spent most of the week sorting out immigration issues,
including visas and hiring of non-U.S. citizens. If nothing else,
it has been most interesting. Also discovered that it is indeed possible
for a terminated employee to show up on the payroll again.
-
Gathered together some information for the PMA division
office regarding the furnishing of room 254 WB.
-
Don’t forget that Friday December 22, Monday December
25, Tuesday December 26, and Monday January 1 are all institute holidays.
Advanced LIGO (Frey, Petrac)
From:
Thomas Frey <tfrey@ligo.caltech.edu>
Progress Period from 12.8 to 12.14
Accomplishments:
-
Out sick Monday the 11th.
-
Advanced LIGO Project Controls meeting - Not held this week due to PAC
meetings at Livingston.
-
Proposal plan development for Advanced LIGO and Operations continues.
-
Issued data requests for progress data as of 12.15.00 that are due Friday.
-
Progress as of 12.08.00 was processed and posted.
-
Review of cost and schedule data is now ongoing.
-
Data input into the cost book and schedule for AOS continues.
-
Received data from David Reitze for IO and review in progress
-
Project Plan for the 40-Meter Lab Upgrade continues.
-
Issued data requests for progress data as of 12.15.00 that are due Friday.
-
Updated the plan with progress as of 12.08.00. Posted to site.
-
Continuing to push for a CDS procurement schedule.
-
Finished input of data for experiments and changes to AOS per Mike Smith..
-
Planning process for the LASTI project at MIT is in progress.
-
Issued data requests for progress data as of 12.15.00 that are due Friday.
-
Progress as of 12.08.00 was processed and posted.
-
Changes are pending from David per his discussions with GEO.
-
Continue to test the Cost Book Tool.
-
Development of the Advanced LIGO Project Controls Guidebook continues.
Continuing to write section on data dictionaries.
-
Project Web Site for posting schedule and progress related data continues
to be updated with the latest and greatest.
Schedule 12.15 to 12.21:
-
Next weekly meeting will be Monday afternoon December 18 from 1 to 2pm
regarding the planning and control of the Advanced LIGO proposal development.
-
Continue to pursue the planning and scheduling of the staging buildings
currently being bid and designed for HLO and LLO.
-
Advanced LIGO Proposal
-
Will begin the effort of contacting each system leader to collect cost
and schedule data. Hope to begin importing schedules and cost ASAP.
(AOS and IO ready for NSF review in January.)
-
Will continue input of AOS and IO to the cost book and schedule.
-
Will Continue to update the LASTI Schedule with progress.
-
Will post progress report by end of day Tuesday with progress as of 12.15.00.
-
Will issue 22nd week of status data to teams.
-
Will continue to update the Advanced LIGO / Ops Proposal Plans and incorporate
any changes.
-
Will post progress report by end of day Tuesday with progress as of 12.15.00.
-
Will issue 22nd week of status data to teams.
-
Will continue updating the 40 meter schedule and incorporate any changes.
-
Will post progress report by end of day Tuesday with progress as of 12.15.00.
-
Will issue 22nd week of status data to teams.
-
Will meet with Alan to review development of 40-Meter experiment tasks.
-
Meeting scheduled for Wednesday December 20 at 2:00pm at LSCR.
-
Continue to test the Cost Book Tool. Have a meeting with Barbara
K. to discuss the Cost Book and the Resource DB.
-
Cost Book Tool development continues. Will be importing data for
Installation so that Dennis Coyne can proceed with estimating.
-
Will continue the development of the Advanced LIGO Project Web Site.
-
Will continue the development of the Advanced LIGO Project Controls Guide
Book. Finish section on data dictionaries and start on update process.
From:
irena@ligo.caltech.edu (Irena Petrac)
-
Advanced LIGO/Core Optics Coating: The bid due date
of Dec. 8 was extended through Dec. 22, 2000.
WBS 1.4.1.2 Project
Controls (LIGO Construction)
Reports (Lindquist)
Annual Report: There
will be an Annual Report due as of the end of November. I will be
requesting inputs from the usual bunch mid-December after the dust from
the proposal has a chance to settle a bit. I propose to keep this
report moderate in size, about the size and complexity of a Quarterly Report,
to minimize the burden.
Change Control/Contingency (Lindquist)
The following Change Requests have
been submitted:
| CR-000018 |
WBS 1.1.4 |
Curbing for Service Roads at Livingston |
G. Stapfer |
| CR-000019 |
WBS 1.2 |
Additional Lab Equipment |
D. Coyne |
Press for the latest Contingency
Needs Projection.
COST
SCHEDULE CONTROL SYSTEMS (Duncan, Akutagawa)
From: Kris Duncan <kris@ligo.caltech.edu>
-
Continued work on the November 2000 CSSR and annual
NSF report.
-
Continued with the reconciliation of the LIGO actual
cost and commitment data to the CIT financial reports.
-
Continued with construction contract close out.
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
SUBCONTRACTS MANAGEMENT (Petrac,
Jasnow)
From: Ed Jasnow <jasnow@ligo.caltech.edu>
-
Gerry Stapfer, Fred Asiri, and Ed Jasnow will be presenting
the contract for the Livingston Staging Building to the NSF in Arlington,
Virginia, on Tuesday, December 19. It is essential that this contract be
awarded in early January so that the heavy construction effort does not
interfere with the commissioning of the detector.
-
The review committee for selection of the architect/engineering
firm for the Hanford Support Building convened on Wednesday, December 13.
The committee discussed the six proposals submitted, and reduced the list
down to three firms. They are Nils Finne Architects, Seattle, WA NTD Architects
,Glendora, CA, and SCM Consultants, Kennewick, WA. These three firms will
be invited to make presentations to the committee around the middle of
January.
From: irena@ligo.caltech.edu
(Irena Petrac)
-
No report this week. See
subcontracts above.
LIGO Hanford Observatory (LHO) Operations
(Raab)
General Items:
--------------
(F. Raab)
Work is continuing on a number of fronts, most of which are either unremarkable
or reported elsewhere. We had a meeting with Peter Fritschel, Rolf
Bork, Dave
Barker, Dennis Coyne, Hugh Radkins and Fred Raab to discuss implementation
of
tidal feedforward compensation and how it might interact with plans
for possible
tidal feedback and for compensation of microseism. We agreed the tidal
actuator
on the PSL did not interact with the microseism. An interesting question
will be
whether feedforward alone might suffice for this actuator. Tidal and
microseism
signals potentially interact at the SEI fine actuators. We resolved
to separate
these two problems, because of great differences in signal sizes and
signal time-
scales, using separate DACs to feed an analog summing point. Rolf and
Dave favored
using an EPICs sandbox sequencer to provide the tidal signals for both
PSL and
SEI. An analog lo-pass filter before the summing junction for the SEI
fine actuator
should provide additional equipment safety on equipment reboots and
will help with
noise suppression. Rick Savage and Hugh are working the PSL side of
the problem,
Dave is working on the EPICs implementation, and Fred is continuing
to work the
issues on the predictor code.
LIGO Livingston Observatory (LLO) Operations
(Coles)
Hosted the PAC meeting, December 12-13, 2000. Members of the PAC
attended
programmatic sessions and presented status and proposal summaries.
OPTICS/COC/SEI INSTALLATION: Calibration of optical levers, and installation
of cameras and illuminators has consumed the bulk of our time this
week. We
found an open OSEM driver coil on the BS, which
explains the damping
difficulties we experienced last week. We've
prepared a lab at the X-end for
the U of F hi-power laser, and have been helping set things up there.
The
last 2 BSC bellows for LASTI have passed RGA, and Joe Hanson will be
crating
and shipping them soon. Continuing to move the machine shop as opportunities
present themselves. (Jonathan Kern)
Operations/Control Room: We have developed a protocol for tracking
and
controlling commissioning activities. This includes informing the lead
operator of any changes to Epic settings or configurations. This
enables
coordinated work efforts with all parties being informed on other parallel
activities. An LLO Operations I-log site has be established that
will
include all pertinent control room activities. Control room staffing
has
increased to accommodate extended work hours for
the LLO staff and visitors. (Rich Riesen)
Administrative: We have been working with our vendors which currently
do
not accept Master Card. So far, we have added seven vendors to accept
the
card. Results probably will not become apparent until January-February
because we need to allow time for them to receive the equipment and
installed it.
To ensure better phone coverage for the 3100 extension, we have
re-programmed our telephone system to allow calls to roll over to the
control room if the front office does not answer. If the control room
is
either busy or does not answer, then the calls will be forwarded to
the main
voice-mail box. We have also set up our phone with a holiday greeting
during
this season.
Have provided administrative assistance to PAC attendees as needed
and made
sure everyone had plenty of good food to eat during the last couple
of days.
(Bonnie Wascom)
Detector/Technical Support (Whitcomb,
Coyne)
1.1 LHO
INSTALLATION & COMMISSIONING
2km Commissioning
Peter Fritschel, Matt
Evans, Rolf Bork, Nergis Mavalvala, Dick Gustafson, Stan Whitcomb
Work
on locking the full interferometer continues with moderate progress. We
implemented optical lever based damping of the beamsplitter and the two
fold mirrors, as had been done previously with the input test masses. This
helped dramatically to stabilize the fluctuations in power buildup in the
power recycling cavity, which in turn has allowed us to make better measurements
on the system. We also moved the feedback for the power recycled michelson
(PRM) from acting on the four test masses (moving the cavities as a whole)
to acting on the fold mirrors, which also resulted in a more stable PRM
lock.
We
continue to have brief lock stretches of the full interferometer, with
longer lock stretches for lower power buildup cases (we continue to exercise
some control over the latter by clipping the beams with the gate valves).
The largest buildup seen corresponds to a recycling gain of about 10, but
lasting only ~1/10 second.
Bill Kells
Brought back a raft of lock
stretches from last week at LHO. Am trying to come to some insight
as to their characteristic nature (with eye on improving the situation).
E2 Run
John Zweizig
This
week I set up for and ran the E2 two-arm data through a finalized set of
monitors. The idea behind this run was to get a consistent set of triggers,
trends and other data products for use in the E2 analysis. It also provided
a means to run monitors that had not been completed at the time of the
E2 run. The data rerun proceeded with only minor snags over last weekend.
Since then Mary Lei and I verified that all the triggers generated during
the run were in fact inserted into the metaDatabase. We found that 103
of the 211477 triggers were not inserted because of two independent errors.
These errors will be prevented in the future by adding handshaking and
error recovery to the script used to submit data insertion jobs to the
ldas manager. The files containing the 103 missing triggers were resubmitted
to ldas by hand so now ALL generated triggers are in the database.
The remaining E2 data (one-arm
running) will be run through the same set of monitors soon.
COS
Mike Smith, Ken Mailand, Lee
Cardenas, Betsy Weaver
APS Telescope are awaiting
pre-alignment. ETM telescopes need a slight rework of a mounting bracket.
Two telescopes were focussed. The COS autocollimators will be evaluated
for focus alignment at CIT prior to being sent to Davidson for repair.
RF Distribution
Rich Abbott
The RF Distribution system
has been shipped to LHO, and we are awaiting the swap to retrofit the old
units for the 4K
PSL
Lee Cardenas
I have suspended the 4K
Ref. Cavity which it is awaiting inside the chamber to be closed up as
soon as Robert and Mark finished the vibration test for the optic table.
We (Mark G. & I) started
the RGA unit on the pump station destined to pump the 4K Ref. Cavity chamber.
So far, the sum of the elements (amu 16, 18, 40, 41,43, 53, 55, and 57
) are below 1E-9 torrs.
I have completely flushed
and cleaned the Neslab chiller for the 4k Laser. tomorrow will fill the
chiller with new and fresh cooling (mixture of 20% Ethylene Glycol, and
80 % of Distilled water. (1 gram/gal of water ) of Chloramine-T as
an Algae inhibitor.
Input Optics
David Ottaway, Betsy Weaver,
Corey Gray
Corey and Dave are laying
out the IO components on the PSL table.
1.2
LLO INSTALLATION & COMMISSIONING
Commissioning
David Shoemaker, Rai Weiss,
Joe Kovalik, Dave Reitze, Szabi Marka, Jay Heefner, Jonathon Kern, Russ
Wooley, Peter Saulson, Stan Whitcomb, ++++
The big push has bee to
get ready to check the initial pointing of the laser beam down the Xarm.
We have gotten all the suspensions working (we think!), though the residual
motion on some of them seems a little larger than it should be. The
most problematic was the beamsplitter, which tirns out to have an open
coil. The sensing and actuation matrices were adjusted to compensate
and it seems to be damping pretty well.
The optical levers seem to
be in good shape, though the power may be low on one or two of them.
The ASC biases are working in the corner station. All illuminaters
are functioning and the camera feed are available in the control room.
We need to re-verify the initial alignment relative to the ITMs, but we
are not far from opening the gate valves.
#SEW#
This is Peter Saulson's last week of sabbatical at LLO. We should
all give him a big thanks for his leadership in the LLO commissioning.
His successor will have big shoes to fill.
Fortunately,
Rai Weiss has agreed to serve as commissioing director at LLO, starting
immediately. Rai will concentrate his travel on LLO and will be on
site more than half time. I hope that everyone will give all possible help
to Rai in this new role.
Jay Heefner
Various problems have been
fixed in recent days The summary is as follows:
ETMX suspension controls database
had apparently been changed from the original version that was installed
and tested several months ago. The channel mapping was incorrect so there
were no control or monitoring capablities or the suspension. This has been
fixed and the controller is fully operational.
There are continuing problems
with the restore functions killing the sequencers in the suspension IOC.
We are not sure of the fix.
#SEW#
Replacing the processor on the three LOS's in the LVEA seems to have helped
(solved?) the problem, but we are continuing to monitor it
The DAQ system has been reconfigured
to add the PEM microphone channels in the LVEA.
The ETMX optical lever is now
functional.
The ASC bias adjust controls
for the suspensions are operational with the exception of MMT3 and ETMX.
It should be operational by the end of the week.
Input Optics
Dave Reitze, Sanny Yoshida,
Warren Johnson, etc
Mode
cleaner work:
we noticed
that the MC was misbehaving over the past two weeks (fragile lock, frequent
loss of lock). We investigated how the local damping gains affect
the lock stability by looking at the MC_F and MC_L signals vs gain.
Both L and F were dominated by stack motion at 1.5 Hz. Initially, all gains
(P/Y/Pos/S) were set to 9. Reducing the gain of MC1 to 2 significantly
improved the robustness of the lock; the MC_L amplitude reduced by 3X.
The lock stability was insensitive to gain changes in MC2,3
power
dependence of the lock was also looked at in anticipation of the long arm
beam hunt by looking at the MC_F control signal vs. power in the MC.
We were able to keep the MC locked (albeit barely) with 2 W going in.
The maximum stable operating power was ~1 W, above that we saw increased
pointing fluctuations and degradation of the MC_F signal.
MC transmission
(power transmitted through the MC/power into the HAM) was measured to be
~ 90.5%. This was done without the WFS operating and with no attempt
to improve the mode matching (the character of the reflected spot indicates
that the mode matching could be improved).
Initial measurements of dynamic
RFAM were made; we demodulated the output of the New Focus 1811 PD (2 mW
power) at the resonant side band frequency and looked for low frequency
noise above shot noise in the 0-1 KHz range. These measurements are
ongoing, but preliminary data shows some resonances in the spectrum (34
Hz), but no significant noise above shot noise.
PSL
Peter King
Well after the 9500 hours
indicated on the laser power supply, the master oscillator for the 10-W
laser (SN #103a) is only producing about 25% of the delivered output power.
The spare PSL NPRO (SN #238) from LHO has been requested, ready to be installed
at an opportune moment when the PSL output power delivered to IO becomes
an issue.
It was noticed that the pre-modecleaner
(PMC) regularly dropped out of lock overnight. Re-acquiring lock
was not as easy as previously recalled. A check of the PMC servo
mixer output indicated that not enough RF was being applied. The
RF level was increased and this appears to have solved the problem of the
PMC dropping out of lock.
The PSL generic DAQ card
was modified to permit monitoring of the AC component of the PMC PZT voltage
(above 0.1 Hz) after some consulting with RichA.
I spent some time trying
to figure out the connections for the modecleaner generic DAQ card since
it was mentioned that two of the channels were either noisy or saturated.
As it turned out, these channels were not connected. A few wire wraps
later, things were (hopefully) sorted out. The signals now appear
on the dataviewer okay.
2.0 Other
Engineering and Scientific Activities
2.1 Design/Analysis/Fab
Optical Metrology
GariLynn Billingsley
Veeco representative Sen
Han visited this week to inspect the WYKO 6000 interferometer in the metrology
lab. He was able to witness one of the various quirks that the instrument
sometimes exhibits, a feature which appears to be related to the ground
glass screen. While the behavior itself doesn't appear to take the
instrument "out of spec" it is at least a symptom of something strange
going on. Many of the instruments strange symptoms come and go at
various times. Some of these, we believe, are attributable to the
ground glass screen. We would love to see the motor replaced at minimum.
It will be interesting to see if Veeco grabs onto on the "not out of spec"
point.
PSL
Peter King
Rick Karwoski, Paul Russell
All three boards for the PMC
servo have been tested in our lab and delivered to LHO
Schematics for all three boards
have been updated and delivered to LHO
The RFPD for the Frequency stabilization
subsystem has been tested at our lab and is ready for shipment to LHO
The schematic for this board
has been updated
We are currently testing the
Frequency Ref card for the FreqStab subsystem
We are wrestling with parts
shortages on the Frequency Servo board which is mostly stuffed. We anticipate
resolution shortly and start of test by early next week.
We are awaiting the approval
of two additional work benches and cabinets for our lab. They will
be needed in short order for stuffing and testing of LASTI and 40m. electronics.
ISC
Mike Zucker
Working with Rana, Rich
Abbott and Rick Karwoski on photodetector problems found in LLO 4k length
sensing detectors. We found three (apparently unrelated) problems;
1) detectors can be destroyed by improper power supply hookup, 2) due to
an oversight in a late design change, DC readout amplifiers are vulnerable
to saturation, allowing overpowering of the detector without an external
indication, and 3) the PD bias circuit seems to oscillate at 500 kHz in
the dark (not an issue under normal operating circumstances, but potentially
confusing for calibration and dark tests). Working on fixes/workarounds
for all three; also checking to find out if problems 2 and 3 afflict installed
LHO diodes.
Rich Abbott, Flavio Nocera,
Mohana Mageswaran
All daughter boards for
the new modecleaner servo have been ordered. We are working through
the board trying to get the noise performance within specification.
All transfer functions are verified to be correct. We are building
additional timing boards and I&Q demodulator boards. We have
also been working towards understanding the recent issues with the RFPD's.
Modulated OSEM Design
Jay Heefner
Stabilized oscillator satellite
amp boards are due this week and should
be available for test in
a few weeks.
Suppressed carrier satellite
amps are being held in reserve.
New OSEM Heads
Janeen Romie, Peter Fritschel,
Myron McInnis
All
of the new osem heads have now been plated/metallized and received at MIT.
Quality is inconsistent: many are of good quality, and are now in the coil
winding stage; but many have poor quality coatings and will need to be
reworked (in progress). We do have enough good quality units for the LHO
4k ifo though, so we are still on the schedule of completing new osems
for this first installation in the first two weeks of January.
Mark Barton
This week I set up an experiment
to check the thermal performance of the OSEMs in vacuum. I've been practicing
on one of the old OSEMs, trying to replicate the results of Miyoki as a
sanity check. I'm checking the heating effect of both the LED and the coil.
I'll be ready to test the new design as soon as I get the ZnN coated prototype
from Peter.
Digital Suspensions
Jay Heefner
SOS Dewhitening board layout
on hold until next week. (Jay is at LLO this week)
SOS coil driver design needs
to be started
GDS
Daniel Sigg
The problems encountered
on raid2 of fortress (data loss & SCSI error) finally have been fixed
by a new set of SCSI cables.
A backup of the E2 data was
done with the data stored on fortress. The backup was checked with a separate
verify cycle. A set of tapes was assembled for MIT, another tape was sent
to LSU. Greg's tape control software proved to be very useful.
More memory (+1GB) was orderer
for all DMT machines.
Fantom (frame multiplexer
software) can now access tar archives. This makes it possible to read backups
from AIT-2 tapes without transferring the data to disk first. The next
feature will be to interface the DMT shared memory partitions. All together,
this will allow to run DMT monitor programs directly from tapes.
A couple of dtt bugs reported
during the E2 run have been tracked down and fixed.
Data acquisition
Sander Liu
In the process of purchasing
components to build couple of +/- 5Vdc power supplies. Still waiting
for long lead time components to arrive before we can proceed to build
more antialiasing filter chassis.
40 Meter Interferometer (Weinstein)
-
Report on building rehab, from Fred Asiri:
-
The contractor is replacing tiles and flooring in the main (newly expanded)
IFO hall (picture),
the new entrance hall, and the South Annex. Steve Vass erected a wall of
plastic sheeting around their work to protect the IFO equipment from dust.
Should be done by the end of the week.
-
Painter(s) will come on Friday, to paint and seal the concrete wall between
the IFO hall and the CES machine shop.
-
Electricians are still laying cable trays (picture).
Should be done SOON!
-
Lighted exit signs, laser warning signs, doorbells, etc, should be installed
by the end of this week.
-
The power conditioning transformers were received by the distributor, and
we should get ours within 30 days.
-
The roofers are ready to re-roof the 40m building and Annexes. They say
that the work will take only 5 days, and are waiting for a 5 day period
without rain (hay! how about right now!). Steve has covered everything
in plastic.
-
Larry Jones and Steve Vass have completed the installation
of STACIS on all 4 test mass chambers, and they have re-measured
the elevations and positions of all the support beams in the bellows, and
have applied shims to all support beam slopes level to 0.5 mrad. The tilts
of the chambers are ok, and any non-levelness of the optical tables can
be taken out using counter weights. Steve Vass has plenty of those in the
lab.
-
Steve Vass has protected the connecters of all the STACIS pedestals against
accidental kicks.
-
Larry Jones is coordinating the cleaning and baking of 12 m mode cleaner
hardware at Allied and LLO.
-
The 12 m mode cleaner beam tube is 8" OD. This is barely enough room to
fit the base of the triangular beam path, given how close one can position
the two flat-mirror suspensions in the Input Optic Chamber (IOC). Mike
Smith suggested that we make the beam tube 10" OD near the IOC. This means
that 8" OD parts that have not yet been ordered will be specified
as 10"OD. The only existing piece of hardware that requires modification
is the 8" port on the IOC door. Larry and Steve will arrange for CES to
re-machine that door port (or even better, order a whole new door, so we'll
have a spare); Steve will clean and bake it in atmosphere. This is a major
change, and it really relieves our worry about the MC beam clearance in
the pipe.
-
Optics and chambers layout, from Mike Smith:
-
Mike is laying out the 12 m mode cleaner in Autocad, using detailed numbers
from Steve.
-
He has a new layout of the beam in the IFO, using the latest cavity lengths
(with the signal recycling mirror in the same chamber as the beamsplitter
and power recycling mirror). He's relocating the oplev beam paths to see
every mirror.
-
He is laying out a small, monolithic, non-suspended output mode cleaner
(OMC) in the new output optic chamber, which requires a mode matching telescope
and steering into the OMC, and then out to the ISC table. We need to know
whether the OMC envisioned for Advanced LIGO for DC GW detection needs
to be suspended (somehow).
-
He has a design for a mode matching telescope (from input mode cleaner
to IFO) using two reflecting mirrors (rather than transmissive lenses,
to reduce scattered light in the beam). The two mirrors each turn the beam
by (180-4.5) degrees. Using spherical mirrors introduces astigmatism, limiting
mode matching in the horizontal plane to no better than 97%. Using off-axis
paraboloids, he can completely eliminate this astigmatism; that's the way
to go!
-
Mike is working full time on the 40m optical layout; much more work to
be done., including relocation of BSC3 output table, position of end chambers,
size and location of end optical tables, detail of mode cleaner vacuum
tube, relocation of IO table.
-
Mike will add little motorized "flags" to top the beam, in front of the
ITMs and the ETMs. This is very useful for alignment and commissioning.
It does the job that they use 48" gate valves to do at H2K.
-
After Mike is finished with a preliminary layout, we will assemble a list
of in-vacuum parts for design or purchase, including all optics, controls,
motors, cables, feedthroughs, etc.
-
Rick Karwoski and Ben Abbott continues to build and test boards for the
H4K PSL, with extras for 40m and LASTI. Still plan on beginning installation
of basic light source in 40m lab in January. The PSL enclosure will be
built around the PSL table as soon as we can revert to cleanroom conditions,
hopefully in January.
-
Ben Abbott is almost finished with all the wiring and cabling for all the
vecuum control boxes.
-
Ben and Dennis Ugolini expect that as soon as the vacuum envelope is ready,
they can modify the EPICS database and begin testing the new vacuum control
system with the real hardware. This is still a ways away, because (a) a
couple of ion pumps have been removed to allow for the installation of
stacis. Steve Vass is ordering hardware for repositioning these pumps.
(b) The ion pumps have to be regenerated; Steve will get to that after
all the building rehab work is done. (c) Ion pump gate valves must be installed.
(d) The annulus vacuum lines have been partially disassembled to make room
for stacis installation; they will have to be put back together. (e) Probably
lots more stuff. Steve will develop a schedule.
-
Steve Vass and Dennis Ugolini removed the recycling mirror (and suspension)
from the 40m vacuum chamber on Thursday morning (picture
and closeup).
They will ship the mirror (magnets attached!) to Gregg Harry in Syracuse
to tests of thermal noise from the coating.
-
Dennis Ugolini is working on E2 seismic studies.
-
Tom Frey has input the WBS for the 40m "experiment" into Primavera; see
his web page.
Thermal Noise Interferometer (Libbrecht)
TNI Weekly Report
(Eric Black, Luca Matone, Shanti Rao, Kevin Schulz, Ken Libbrecht,
with
help from Seiji Kawamura)
TNI test cavity locked!
We spent a considerable amount
of time this week trying to get our
mode-cleaner to lock well, but without a great deal of success.
After
solving a few assembly problems (a wire brushing against one of the
mirrors, a bad electrical contact), we still could not achieve an
acceptable lock. The symptoms included some unusual high-frequency
oscillations, and we suspect that the laser PZT is not functioning
properly. We observed additional odd behavior when locking the
laser to
our fixed-length reference cavity, which seems to support our hypothesis
that the laser is at fault. The easiest way to check this is
to swap in
another laser, and this will be done shortly.
We also found a low-frequency
oscillation in the mode cleaner lock that
goes away when the laser power is reduced, suggesting
that scattered light
from the cavity may be getting into our OSEM
sensors. We need to nail down
our lock much better before we can investigate this problem further.
Rather than swapping lasers
right away, and having to realign the works,
we decided to first route around the mode cleaner cavity and try locking
a
test cavity. We expected lock acquisition might not be straightforward,
since the test cavity finesse is high (the mirrors were coated for
F=100000, and a quick measurement gave F>55000). We first locked
the laser
to a reference cavity, and tried locking the test cavity to the laser
using
a broad-band Pockels cell to increase the servo bandwidth. This didn't
work
for some rather uninteresting reasons. First the electronic gain
required
for the PC path was too high. Also, we were using one power supply
for the
laser PZT driver and the PC driver, and saturation of the PC driver
tended
to push the reference cavity out of lock.
Finally we tried to lock
the test cavity and laser by actuating on the
laser PZT and the test mass, without a reference cavity and without
the
Pockels cell. This worked well. The
lock was robust and stable for at
least 10s of minutes at a time. The system
is still far from its final
configuration, but we are now fairly confident
that lock acquisition for
the test cavities will not be a serious problem.
LASTI (Zucker)
No report received.
Data Analysis and Computing (Lazzarini)
No report received. Must be the GWDAW meeting ?
LIGO II/Advanced R&D (Sanders)
From Bill Kells:
2. Going over some loose ends with Jordan on the work we have
done on Sapphire mirror birefringence. In particular it seems
that we have observed very much lower Rayleigh scatter in the
sapphire mirror we used than has previously been thought.
3. More work on getting the FFT code running revved up. Have executed
my first run on the new CACR supercomputer!
From Peter King
3.2 LASTI
The reference cavities for the LASTI PSL have arrived on campus.
3.3 40m Lab
The reference cavities for the 40m Lab PSL have arrived on campus.
The
vacuum chambers should arrive some time next week.
From: GariLynn Billingsley <Billingsley_G@ligo.caltech.edu>
The Core Optics Development plan has been circulated. Until it
finds a permanent home in the DCC, you can obtain a copy of LIGO- T000098-00-D
at DCC\OUT\ or at http://ligo.caltech.edu/~gari/LIGOII/index.htm
For additional information about this report, contact sanders@ligo.caltech.edu