Weekly Report for Week Ending November 16, 2000


 Exec. Comm. Agenda
Highlights
LSC
Administration
Hanford Observatory
Livingston Observatory
MIT
Caltech
Detector
40 Meter
TNI
LASTI
Data Analysis
LIGO II/Adv. R&D
Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  November 20, 2000 will be:
 (Meeting time: 10:30 am Pacific Time)

Open meeting 10:30 - 11:30

  1. Announcements
  2. LSC Issues (Weiss)
  3. Comments on Weekly Report
  4. WBS 1 LIGO I Construction (Lindquist)
  5. WBS 2 LIGO Lab Operations
  6. WBS 3 and 4  Advanced R&D and LIGO II (Sanders)
Executive Committee only 11:30 - noon   Topics:
 

Special Items: Status of Budgets and Proposal for FY 2002-2006


Special Announcements:


Weekly Report Highlights
 


LSC Issues (Weiss)


no report


LIGO I Construction/LIGO Laboratory Administration (Lindquist)


WBS 1.2 LIGO Operations--Administration


LIGO Weekly Site Telecon (Lindquist)

There was a site teleconference held on Thursday, November 16. Discussion items included the financial reports as of the end of October 2000, the status of the budgets for the FY 2002-2006 proposal, property accounting (whether materials purchased through Caltech, but sent to MIT will be accounted for in the Caltech system), site staffing, and the status of bid requests.

The list of current actions revised to reflect open actions assigned through November 9, 2000 may be found at ACTION LIST.


PROPERTY MANAGEMENT (Chargois)

From: Ed Chargois <chargois_e@ligo.caltech.edu>


DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner - turner@ligo.caltech.edu>

Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .

ACCOMPLISHMENTS

CONCERNS From: Cleveland Mak <mak_c@ligo.caltech.edu>
  • Progress on auditing of drawings continues.  Livingston Facility/Construction drawings are just about done with a few loose ends to tie up.  Auditing of Hanford drawings have begun.  With the addition of numerous full-size drawings being filed away, there was some need for considerable reshuffling of files to accommodate for these drawings.
  • Prepared, packaged, and shipped Addendum #4 to IFB EJ-319.
  • Processed large number of electronic documents as well.
  • Packages Faxes
    In 50 41
    Out 17 49

    Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.


    COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Akutagawa, Kaufman)

    From: Esther Cunningham <esther@ligo.caltech.edu>

    Press here for ACCOUNTS PAYABLE HISTORY DATA.

    From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

  • The Washington State Auditor returned yesterday and today to continue the audit of LHO.
  • Received a request today for the DCAA auditor to provide more detailed information on the "Level of Effort" contracts for LIGO. I will be obtaining that information today to respond.
  • Working on internal modifications as requested, Hereaus-Amersil, Corning, setting up the file for Manpower, and completing University of Michigan.
  • Working on resolving the one time PO to VWR and Thor. Continue to place and reconcile pcard transactions.
  • Requested special permission from Purchasing Services to have all LIGO's POs processed as "three-way" rather than "two-way" to ascertain that on-line receiving will be completed. Should be getting a response soon.
  • The class action lawsuit against Airgas was forwarded by the main Purchasing Office to Sandy Pool. Awaiting to hear a response.
  • Have been scheduled for two 2-hr Webster/Oracle Discover training sessions later this month.

  • Electronic e-mail notifications are now being generated as notification to complete and approve POs after a certain period of time. In addition, notifications are now being sent on blanket POs when funds are more than 85% expended.
    From: Florence Kaufman <fkaufman@ligo.caltech.edu>

    SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

    From: irena@ligo.caltech.edu (Irena Petrac)

    From: Ed Jasnow <jasnow@ligo.caltech.edu>



    Support (Wood)
     
    Irene Baldon
    • Eleven (11) new trips were started and I have fourteen (14) trips pending final approval before tickets can be issued.  These trips required Advance Checks to be written as well as hotel and car authorization forms to be filled out and Faxed to the appropriate location.
    • Worked with a few travelers who had questions or needed further clarification on using or reconciling their new P-Cards.  For the most part those having cards seem to be doing fine and find the cards a convenience. Reconciled forty-four (44) items on my P-Card this week.  As of today I have had one hundred-forty items come through for this month.
    • Worked on and completed thirty-six (36) Expense Reports.  I have ten (10) Expense Reports to work on and I'm holding one (1) that requires a check from the Traveler before sending to Travel Audit.  I sent out the latest P-Card Expense Report to all LIGO personnel and have made myself available to anyone having questions or needing further help in filling it out.  As of this writing I haven't heard anything from Beth or her group regarding the FileMaker Pro version.  I'll make this available to everyone as soon as I received it.
    • Prepared the Travel/Vacation Itinerary for the Week of November 13, 2000.  Performed normal recording and filing associated with Travel and Reimbursement.  Worked on several problem issues with Travel Audit in addition to the above listed issues.  Also performed miscellaneous duties as requested by various members of the LIGO Project here at Caltech as well as from members of the staffs of each of the two (2) sites.   I continue to do MIT's travel to the sites for installation activities and also to assist them wherever possible.
    Dorothy Lloyd
    • Processed the usual requisitions, invoices and receiving on-line. For more detail, see "Cost Schedule Control Systems" report by Esther Cunningham.
    • Tracked and followed up on invoice problems.
    • Reviewed and recorded payments processed by Esther for the week of November 6, on contract summary sheets and LIGO database.
    • Continue to monitor contract and blanket order funding levels and notify task managers when supplements are needed.
    • Jim continues to do data entry in the LIGO database and help out in the DCC.
    Rita Torres
    • Did change order No. 3 to University of Michigan, obtained Oracle requisition number.  Distributed copies of RFQ for Advanced LIGO Coating Development.  Did a few letters to NSF re: Advance Notification Regarding Joint Program with Foreign Entities.
    • Edits to draft RFP IPGS-511 (G. Stapfer) for LIGO Advanced SEI mechanical Structure.  Verified names and addresses for the 8 proposers, typed the list.  Prepared for internal review, a rather large pdf version to distribute.
    • Did Addendum No. 4 to IFB EJ-319 (re bid) for LIGO Staging Building & Renovations to Existing Buildings at LLO.
    • Ongoing activity: Continue to investigate the 40 LSC email addresses that bounced back.  Discovered 4 input errors, and many changes to addresses and personnel.  This investigation is taking many hours to do (verifying Z documents, phone calls & faxes), still need to send out more test messages.  With any luck, we should have up-to-date information for everyone by early next week.
    • Activities for lab set up are ongoing.  Continue to chase various details associated with Pcard purchases, must have accurate info to reconcile.
    Elizabeth K. Wood
    • Continuing attempts to transfer a test version of the proposal through FastLane (TM, all rights reserved) failed until today.  Earlier this week, I talked to the NSF and relayed to them the error messages I had been receiving, most having to do with a network timeout.  Turns out the network timeout was somewhere in Arizona.  I tried to send the .pdf file today and miracle of miracles, it actually went through.  I was even able to look at it.  So, as of 1:12 p.m. on Thursday, November 16, 2000, it IS possible to get a large proposal to the NSF visa FastLane (TM, all rights reserved).  Whether it will be possible in two weeks is anyone’s guess.
    • Barbara and I have pulled together what we hope is the most recent version of LIGO’s publication list.  I can’t remind LIGOites often enough how important it is to let Linda/me/Barbara of the status of your articles—in preparation, submitted, in press, or published.

    Advanced LIGO (Frey, Petrac)

    From: Thomas Frey <tfrey@ligo.caltech.edu>


    Progress Period from 11.10 to 11.16

    Accomplishments:

    Schedule 11.17 to 11.23:
    Anticipated Challenges:
    Will not be able to produce a complete / accurate baseline schedule for the 40-Meter lab due to the lack of planning regarding the CDS.  Per 40-Meter meetings, I cannot expect to receive this data anytime soon if at all.
    Due to the availability challenges for Jay and Rolf related to the Advanced LIGO program plan, it is unlikely that a complete estimate and schedule will be available for the NSF review in January.
    Corrective Action:

    None to report at this time.

    From: irena@ligo.caltech.edu (Irena Petrac)


    WBS 1.4.1.2   Project Controls (LIGO Construction)



    Reports (Lindquist)

    Annual Report:  There will be an Annual Report due as of the end of November.  I will be requesting inputs from the usual bunch mid-December after the dust from the proposal has a chance to settle a bit.  I propose to keep this report moderate in size, about the size and complexity of a Quarterly Report, to minimize the burden.



    Change Control/Contingency (Lindquist)

    The following Change Requests have been submitted:
     

    CR-000018 WBS 1.1.4 Curbing for Service Roads at Livingston G. Stapfer
    CR-000019 WBS 1.2 Additional Lab Equipment D. Coyne

    Press for the latest Contingency Needs Projection.


    COST SCHEDULE CONTROL SYSTEMS (Duncan, Akutagawa)

    From: Kris Duncan <kris@ligo.caltech.edu>

    From: Cindy Akutagawa <cindy@ligo.caltech.edu>

    SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

    From: Ed Jasnow <jasnow@ligo.caltech.edu>

    From: irena@ligo.caltech.edu (Irena Petrac)

    Quality/Safety (Tyler)

    >From: Bill Tyler <tyler@ligo.caltech.edu>

    No report.


    LIGO Hanford Observatory (LHO) Operations (Raab).


    General Items (F. Raab)

    E2 has been completed as scheduled and tasks that were on hold to allow unmolested running are getting attention. A great job was done by all. The overall run looked successful, but will be reported more thoroughly elsewhere. My major observation is that an idea we adopted early on in planning the facilities - that users would be able to conveniently access data from the computer users room and elsewhere on site - is not yet reality. Consequently, it is a hardship to get at diagnostics without being at a control-room computer, so it is difficult to control control-room traffic when we have many visitors. This is not urgently an issue, but it will need attention before runs become "routine."


    LIGO Livingston Observatory (LLO) Operations (Coles).


    OPTICS/COC/SEI INSTALLATION: Realignment of ETM-y is in progress. Arm cavity baffle has been installed, and will be aligned today. We measured a 1 cm error in the +Y position of the ETM (which also is reflected in the PSI monuments on the slab) referencing BT-VE5. We'll move the LOS to correct this before final alignment. We plan on completing the in-vacuum work and pumping down early next week. (Jonathan Kern)

    Computing: Shannon is working on the control room checklist, and is adding functionality to it. (Data entry is working, but data retrieval
    forms are still being written.)We have ordered extra SCSI drivers and a disk to allow us to move the web and mail services to separate machines, and to provide some redundancy for them. We are expecting an evaluation copy of "Quick Restore" to help automate backups on our new tape robot.We are configuring a workstation to be a standalone Solaris 7 machine for running the E2E software, which seems to be having problems with Solaris 8.

    ISC: Sany and I continued ISC prep. by fine aligning Faraday port beam into ISCT1; the beam now looks fairly gaussian in both x and y axis: appears to be no clipping now. ITMX, ITMY, and BS seem to have suspension control issues; we are troubleshooting these. (Anthony Rizzi)


    Detector/Technical Support (Whitcomb, Coyne).


     
    Installation & Commissioning:
    Hanford
    Livingston
    Other Science/Engineering Activities:
    Design/Analysis/Fab
    Issues/Concerns
    See also the Installation web page

    1.1 LHO INSTALLATION & COMMISSIONING

    2km Commissioning
    The week long engineering run (E2) ended on Wednesday (cast of thousands).  The E2 web page is at: http://blue.ligo-wa.caltech.edu/engrun/

    Daniel Sigg, John Zweizig, Stan Whitcomb and a cast of thousands....

    The second Engineering Run at Hanford (dubbed E2) was concluded this week.  The  2 km interferometer was operated around the clock for 7 days.  Approximately 40 scientists from the Lab and the LSC participated, so the control room was a "happenin' place" all the time.
    The interferometer was operated in the recombined Michelson mode with both arm cavities for the first 6 days--4 days of quiet running, followed by two days of parametric studies in which a number of operating parameters were varied to assess their effect on performance.  The last day was devoted to single arm operation.

    The system performed pretty well.  Typical lock durations were  30-60 minuted in the recombined configuration,  2-6 hours in the single arm configuration.  Reacquisition of lock typically took less than 1 minute. There were no major hardware failures.  The data acquisition system complained about the heavy load, but hung in for the duration.  We collected 2 terrabytes bytes of data, performed some on-line analysis, and educated a number of LSC scientists.

    E2 run (Daniel Sigg)

    The second engineering run was a great success. Data taking started on Wed., 11/8, at 12:00am and ended a week later on 11/15, 12:00am.  Without making an exact analysis the estimated up-time was at least 80%---probably around 90%. The first 5.5 days were run in the recombined Michelson configuration with typical lock stretches between 30 and 60 minutes; with the longest one approximately 3 hours. The remaining 1.5 days were dedicated to single arm operations, equally split the y and the x arm configuration.

    No major hardware or software problem was encountered during the run: the SUS, LSC and ASC systems worked reliably over days. The PSL and IOO showed excellent performance---not a single lock was lost due to laser or mode cleaner. The data acquisition system was handling the load and all data was saved to disk and broadcasted to the data monitoring tools. A couple of glitches which have to fixed in the next few weeks showed up: reliability was not 100% and the system (or part of it) had to be rebooted occasionally, the number of EPICS channels could not be scaled up to the full set, there were occasional timing glitches and the lack of anti-aliasing

    in certain circumstances gave rise to confusion.
    There were a couple of tape backup problems in the LDAS system but no data was lost because of it. The total data volume was of order 1TB which was all written to tape during the run and sent to CIT for archiving. The control room and the diagnostics tools received a lot of exercise.  Most of the control room machines were in use most of the time---running data viewer and diagnostics test tool. The data monitoring tool had its first test with a heavy load of monitor tasks which used up most of the CPU time on sand and stone. Both machines handled it quite well. Some of the monitors---in particular the ones generating triggers---became ready only during the end of the run and have to be rerun off-line. The RDS writer on fortress was writing a reduced data set on the new 1TB raid system. Unfortunately, we had to restrict the access to this machine during the run since it was interfering with the RDS writer which was loosing frame files when not running exclusively.

    The organization of the shifts and check list tasks worked out fine. Even so, we had do a lot of self-education at the beginning, the excellent motivation of people on shift made it work. Clearly, a couple of  improvements need to be implemented for the next go around: in particular the e-log and the check lists need more attention and fine tuning,

    The scientific shift group also undertook a set of investigation tasks looking at the cause of lock, various stationary and non-stationary noise sources, transient, angular fluctuations, and data integrity. We also performed extensive calibrations of both amplitude, phase and absolute timing and frequency noise propagation. First preliminary results are already available for cause of lock (length-angle coupling twisting the optics), tidal trends (both differential and common mode over a total of 130 hours), calibration of the sensitivity (a few times 10^-18 m/m/rtHz at 1kHz) and the stability of  lines in the spectra (including calibration lines).

    More as it becomes available on the E2 web site

    Luca Matone, Micheal Landry

    Worked on the Calibration task for E2. We have made a few measurements, in particular we have sent sinusoid sweeps to the masses to get transfer functions of the response of the system and we have injected calibration lines to the ETMs to obtain their calibrations when only one arm was locked).

    Input Optics (Dave Reitze )

    Preparation of the small optics continues.  A mishap with one of the MC flat mirrors occurred; it looks like it will have to be repolished and recoated.  Fortunately, spares were available and have been sent to LHO for gluing. In addition, sufficient magnet standoffs and wire standoffs for 10 additional mirror glue cycles have been manufactured and will be

    sent to LHO by the end of the week.

    1.2 LLO INSTALLATION & COMMISSIONING

    Commissioning (Peter Saulson )

    (The team this week included Nergis Mavalvala and David Shoemaker.)

    We have done careful measurements of the mode cleaner's loop gain, confirming that a unity gain frequency of about 20 kHz can be achieved with good behavior, but that turning the gain up leads to oscillation around 70 kHz. A new calibration was also made of the MC length error signal. In addition, the MC length/frequency crossover was mapped as a function of MCA gain.

    Warren Johnson continues to help us learn about the anomalous damping of  the small optics. In addition to low Q's of many pitch modes, there are other modes that show Q that gets dramatically worse at the low amplitudes characteristic of operating conditions, even though they show reasonable Q when driven to large amplitudes.

    Nergis is updating our CDS software. Anthony and Sany are making good progress on the alignment of ISCT1. We also successfully completed the renaming of the IOO controls channels. New IOO DAQ channels have been hooked up and Rolf has added them to the master configuration.

    We reinstalled some IOO WFS software and got the mode cleaner WFS working again. Since installation of the RF distribution system, the RF phases have changed, so the optimal WFS matrix will have to be remeasured, but the loops work even with the old matrix.

    Input Optics (Dave Reitze)

    2.0 Other Engineering and Scientific Activities

    2.1 Design/Analysis/Fab

    Optical Metrology

    GariLynn Billingsley
    A summary of LIGO spares status was generated per request.
    We have yet to measure:
         Uncoated RMs (3),
         One recently repolished SPETM,
         2K ITMs(2),
         FMs(2),
         ETMs(2)

    FM04 and  SPETM04 (uncoated) were sent to S. Rowan at Stanford to investigate the effect of coating on Q.

    PSL
    Note: Gary Sanders, Peter King, Rich Abbott, Rick Savage and Joe Kovalik are visiting the Univ. of Hanover to discuss collaboration on advanced LIGO laser development.

    Rick Karwski

    We continue to test the pre-mode cleaner circuit boards.
    The test fixture for the Photo-diode boards has been built, tested and is in use.
    We have completed an on-the-bench functional test of one of the photo-diode boards.
    We have discovered circuit discrepancies on the PD and we are in the process of resolving issues with the LHO crew.
    We have begun testing the pre-mode cleaner servo card.

    Lee Cardenas

    New OSEM Heads

    Peter Fritschel, Myron McInnis

    Janeen Romie, Dennis Coyne

    Visited a potential OSEM head coater (Macro Metalics) and examined their TiCr eletrostatic discharge coating. It looks promising, but another set of samples need to be fired to get the correct resistance. Also met a representative of one of the alumina head manufacturers (Progressive Technologies): they reported a delay of a few days in completion of the production lot of 300 heads.

    2.2 Issues Concerns

    Nothing new.



    40 Meter Interferometer (Weinstein).


    STACIS active seismic isolators:

    Mode cleaner vacuum envelope and output optic chamber stack:

    Thermal Noise Interferometer (Libbrecht).


    This week we finished and installed cables and electronics for one of the test cavities.  Active damping appears to work nicely on both mirrors.


    LASTI (Zucker).


    LASTI (MacInnis, Mason, Smith, Kruzel, Shoemaker, Zucker)

    SEI installation: Still waiting on some cleanroom parts for HAM21, so we are drilling for the BSC pier anchor bolts and roughing up concrete before finishing HAM21 SEI installation.

    Cleanrooms: KM and MZ are working on a BSC custom cleanroom solution compatible with Larry Jones' Cartridge SEI/SUS installation scenario; headroom is tight but with proper attention to low headroom in designing lift fixtures etc. it should be feasible.  We are now looking at having the roof of the main cleanroom double as a work platform for installation by making its section deeper, adding reinforcements for man-rating, and mounting the fan units on edge as side-blowers. There isn't enough clearance for a standard bolt-on  work platform.

    Vacuum system: ELK is completing wiring and chilled water installation in preparation for test of the new roughing pump today or tomorrow.

    LASTI (Janeen Romie)
     
     


    Data Analysis and Computing (Lazzarini)


    Simulation and Modeling (Yamamoto)

    LHO E2 run

    Physics simulation Simulation code improvement ALFI

    Ed and Bruce fixed more bugs in the bug list. alfi is quite stable now. alfi is also capable of opening box files which were editted without using alfi. The code change strategy is to make the whole system more robust in the future modification. The program report is reorganized so that it is easier to make a strategy to completely wipe out the bugs in the list.

    LIGO Data Analysis System

    Software Systems (Blackburn)

    During the second engineering run at Hanford, LDAS was able to ingest over 700,000 trigger events into its database from the DMT. This averages out to a 1 Hz trigger rate. However, there were epochs during which the DMT was generating and we were logging triggers at 100 Hz(!) and LDAS was able to handle this extreme load.

    A couple of days prior to the run it was determined that bad frames were being written with duplicate channel names. This caused a segmentation fault in the frameCPP which caused the frameAPI to go into a cyclic restart-fail loop. The frames were fixed and a patch to the start-up macro for the frameAPI was installed. This fixed all the problems seen with the frames and the frameAPI.

    The writing of the frame data to tapes proved to be much more problematic, although no data was lost and we expect the final set of tapes to arrive here at CIT tomorrow. There were tremendous problems with the tape robot and the drivers used to communicate with it. The manufacturer of the unit was contacted several times and in one instance spent several hours on the phone with us trying to sort out the problems. For reasons still unknown to us, the writting of data to tape would occasionally result in scsi resets and other problems such as lose of communications with the unit. The server for the tape robot had to be rebooted on several occasions to test out a new configuration or different hardware component. During these reboots the LDAS software had to be shutdown and later restarted. During these down periods, DMT triggers were not ingested into the database. The lesson that was learn from this was to separate the server for the tape robot from the rest of LDAS so that LDAS could continue to run when tape problems occurred.

    There have been a couple of issues associated with the migration of the wrapperAPI over to LAM. These are still being worked out. However, we did learn that "collective" calls can be very dangerous to use and have hence replaced all these with point-to-point communications.

    Work on the mpiAPI has begun again using the LAM implementation of MPI as the standard. There is still a significant amount of code development needed to integrate the mpiAPI with the wrapperAPI.

    Several bugs in the dataConditionAPI call chain were identified and fixed this week. The focus of work on the dataConditionAPI is now on formalizing the implementation of the new unified data type (UDT). A substantial portion of the dataConditionAPI has been reworked to use this new UDT. This new code will be appended to the cvs repository later this week.

    A new user interface was developed to exercise user commands which condition frame data using the dataConditionAPI. This interface is graphical and is called "chex" for CHannel EXerciser. It is in the LDAS repository and has been made available to the development team for the dataConditionAPI for evaluation and feedback. In addition chex was used during the engineering run to perform statistical analysis of various frame channels in 60 second segments.

    The new controlMonitorAPI which appeard in the 0.0.12 release of LDAS used during the engineering run was successfully used to monitor the state of LDAS and the tape controller software. It also was used to easily start and stop the LDAS system when hardware maintenance was performed.

    All problems identified with the frameCPP i/o library during the engineering run have been fixed and added to the repository, as well as to the framebuilder.

    In closing I would like to say that the performance of the LDAS software during the second engineering run was outstanding. The software was very stable and able to endure stresses outside of those used in routine validation test. The software team did an excellent job of preparation getting ready for this run.

    Hardware Systems (Anderson)

    The memory problems with the new 16-node LDAS beowulf computer have been fully characterized and the system is close to being released for software development.

    Problems with the AIT-2 tape drives during the 2nd LHO Engineering run have been diagnosed and a candidate fix will be tested now that the run is over.

    The first price quotes for a 6000 slot LDAS tape robot has been obtained.

    An investigation into an alternative tape storage system to HPSS is commencing.

    ----- Forwarded message from Greg Mendell -----

    1) LDAS successfully archived all of the raw frame data from the LHO E2 run onto tape. Seventeen tapes have already arrived at Caltech.  Another eight tapes are in transit and three more are waiting to be shipped today. All tapes should be at Caltech by Friday Nov. 17, 2000.  A backup copy of each of these tapes is at LHO.

    2) SCSI reset problems with the tape drives were documented in the elogs at LHO.  These types of resets did not occur during testing on the ldas system prior to the run.  The resets were overcome by restarting the tape control script as needed, and by enhancing the script to handle resets. They did not cause the loss of any files from the entire E2 run. Reconfiguration of the drivers for the tape drives should fix the problem in the future.  Test of this are now underway.  Also, it should be noted that the actual enterprise level tape library system to be used at LHO has not yet been purchased.  The system used for the E2 run was based on the hardware currently on hand.

    3) The tapes contain tar balls with 200 one-second frame files per tar ball. The frame size during the E2 run was 3.183092 MB, thus each tar ball is just over 636.6 MB.  Each tar ball will have a name beginning with the first frame file in the tar ball, followed by .n, followed by the number of frame files in the tar ball, followed by .tar, e.g.: H-657305418.F.n200.tar

    3) The tapes are currently being ingested in HPSS at Caltech.

    Data Analysis Activities (Charlton)

    Worked on Matlab code for collating and testing statistics of the FCT.  Tom would like to see how the values of the SNR are distributed from a large number of trials of a (fixed) chirp + noise (where new noise is generated for each trial). We anticipate that the distribution should be Ricean (that is, non-central chi2) when a chirp is present and chi2 degree 2 when no chirp is present. I'm writing Matlab routines for generating chi2 prob. distribution function and cumulative distribution function. To test the goodness-of-fit I'm writing code for a chi2 test and the Kolmogorov-Smirnoff test.

    General Computing

    MIT:

    Livingston: Hanford: CIT:

    (Lisa)

    (Sam)

    Worked a few PC issues. Basically, busy with school.

    (Suresh)

    (Barbara) (Larry)

    LIGO II/Advanced R&D (Sanders)


    (Helena Armandula)

    Phil Willems is in Glasgow this week.  Nothing significant to report.  Working on the SUS schedule.

    Seismic Attenuation (Riccardo DeSalvo)

    No report.


    For additional information about this report, contact sanders@ligo.caltech.edu