Weekly Report for Week Ending November 9, 2000


 Exec. Comm. Agenda
Highlights
LSC
Administration
Hanford Observatory
Livingston Observatory
MIT
Caltech
Detector
40 Meter
TNI
LASTI
Data Analysis
LIGO II/Adv. R&D
Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  November 13, 2000 will be:
 (Meeting time: 10:30 am Pacific Time)

Open meeting 10:30 - 11:30

  1. Announcements
  2. LSC Issues (Weiss)
  3. Comments on Weekly Report
  4. WBS 1 LIGO I Construction (Lindquist)
  5. WBS 2 LIGO Lab Operations
  6. WBS 3 and 4  Advanced R&D and LIGO II (Sanders)
Executive Committee only 11:30 - noon   Topics:
 

Special Items: Operating Costs through the end of October


Special Announcements:


Weekly Report Highlights
 


LSC Issues (Weiss)


no report


LIGO I Construction/LIGO Laboratory Administration (Lindquist)


WBS 1.2 LIGO Operations--Administration


LIGO Weekly Site Telecon (Lindquist)

A site teleconference was held on Thursday, November 9, 2000.  Issues included establishing subaccounts for the site facilities.

The list of current actions revised to reflect open actions assigned through November 9, 2000 may be found at ACTION LIST.


PROPERTY MANAGEMENT (Chargois)

From: Ed Chargois <chargois_e@ligo.caltech.edu>


DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner - turner@ligo.caltech.edu>

Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .

ACCOMPLISHMENTS

From: Cleveland Mak <mak_c@ligo.caltech.edu>

Considerable progress is being made on Livingston drawings.  The pile is definitely shrinking!  Many more drawings were either tossed because of duplication or placed into files.  Most of the drawings being filed were mainly originals replacing copy versions or filing of a particular 'size' of a revision of a drawing that we did not already have.

Processed large number of electronic documents as well.
 

Packages Faxes
In 45 41
Out 11 36

Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.


COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Akutagawa, Kaufman)

From: Esther Cunningham <esther@ligo.caltech.edu>

Press here for ACCOUNTS PAYABLE HISTORY DATA.

From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

From: Florence Kaufman <fkaufman@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: irena@ligo.caltech.edu (Irena Petrac)

From: Ed Jasnow <jasnow@ligo.caltech.edu>



Support (Wood)
 
Irene Baldon
  • Eighteen (18) new trips were started (including one trip using an old canceled ticket) and I have eight (8) trips pending final approval before tickets can be issued.  I prepared a few Advance Requests and Payment Requests using the old system due to various reasons that excluded them from the new system.
  • Worked with a few travelers who had questions or needed further clarification on using or reconciling their new P-Cards.  For the most part, those having cards seem to be doing fine and find the cards a convenience.
  • The P-Card Expense Report was revised by Michelle Thompson's group, and I made a few minor change recommendations.  My re-revised version was approved by Michelle's group and has been sent on to Beth Moore's group to be put into FileMaker Pro form.  As of this writing, I haven't heard anything from Beth or her group.
  • Worked on and completed thirty-one (31) Expense Reports.  I have twenty-five (25) Expense Reports to work on.  The new P-Card Expense Report was sent to the existing P-Card holders, and I sent out a note to all LIGO travelers clarifying some issues in regard to the report and processing.
  • Prepared the Travel/Vacation Itinerary for the Week of November 6, 2000.  Performed normal recording and filing associated with Travel and Reimbursement.  Worked on several problem issues with Travel Audit in addition to the above.  Also performed miscellaneous duties as requested by various members of the LIGO Project here at Caltech as well as from members of the staffs of each of the two (2) sites.   I continue to do MIT's travel to the sites for installation activities and also to assist them wherever possible.
Dorothy Lloyd
  • Processed the usual requisitions, invoices and receiving on-line. For more detail, see "Cost Schedule Control Systems" report by Esther Cunningham.
  • Tracked and followed up on invoice problems.
  • Reviewed and recorded payments processed by Esther for the week of October 30, on contract summary sheets and LIGO database.
  • Continue to monitor contract and blanket order funding levels and notify task managers when supplements are needed.
  • Jim continues to do data entry in the LIGO database and help out in the DCC.
Rita Torres
  • Over the last several days participated in fast and furious purchasing activity associated with the Bridge Development lab.  Activities for lab set up are ongoing.
  • Did change order No. 3 for Corning, also for Heraeus Amersil, obtained Oracle requisition numbers for both.  Also did change order No. 10 for Univ. of FL.  A few MOU documents in the works.
  • Ongoing activity: Sent out a test message to LSC email addresses.  Out of almost 390 names, 40 addresses bounced back.  I have identified the individuals' organizations, now I must check their Z documents.  Were these input errors, was the info given us in error, did the info change after they gave it to us?  So far I've found two input errors, the rest I am investigating.
  • Continue to chase various details associated with Pcard purchases.
Elizabeth K. Wood
  • With a little brainstorming on the part of Lisa, Larry, and me, and help from Stan and Garilynn, we were able to convert the proposal into .pdf format.  It only took reinserting five figures, one of which had to be reduced in computer-memory size, printing the WORD file to the color laser printer in room 18, and running the resulting postscript file through Adobe Distiller version 3.0 on Sirius (not on my PC) in order to produce a complete .pdf file.  It only took two different operating systems and a lot of patience to produce a file that might be readable to the NSF.
  • As a test to see whether the now finished .pdf file could be read by FastLane (TM, all rights reserved), I sent a 2,242KB file to the NSF.  Well, I tried.  Four times.  As of this writing, it’s not clear whether the hang-up is at the NSF side or our side.  I was told by a FastLane guru that the size of the file shouldn’t make any difference.

  • Just a reminder:  if you have had an article submitted, accepted, or published since the last time I asked, please oh please oh please let me/Linda/Barbara know.

Advanced LIGO (Frey)

From: Thomas Frey <tfrey@ligo.caltech.edu>
 
Progress Period from 11.03 to 11.09

Accomplishments:

Schedule 11.10 to 11.16:
Anticipated Challenges:
Corrective Action:
None to report at this time.



WBS 1.4.1.2   Project Controls (LIGO Construction)



Reports (Lindquist)

Annual Report:  There will be an Annual Report due as of the end of November.  I will be requesting inputs from the usual bunch mid-December after the dust from the proposal has a chance to settle a bit.  I propose to keep this report moderate in size, about the size and complexity of a Quarterly Report, to minimize the burden.



Change Control/Contingency (Lindquist)

The following Change Requests have been submitted:
 

CR-000018 WBS 1.1.4 Curbing for Service Roads at Livingston G. Stapfer
CR-000019 WBS 1.2 Additional Lab Equipment D. Coyne

Press for the latest Contingency Needs Projection.


COST SCHEDULE CONTROL SYSTEMS (Duncan, Akutagawa)

From: Kris Duncan <kris@ligo.caltech.edu>

From: Cindy Akutagawa <cindy@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: Ed Jasnow <jasnow@ligo.caltech.edu>

From: irena@ligo.caltech.edu (Irena Petrac)

Quality/Safety (Tyler)

>From: Bill Tyler <tyler@ligo.caltech.edu>

No report.


LIGO Hanford Observatory (LHO) Operations (Raab).


General Items (F. Raab)

E2 is underway.

PreStabilized Lasers

2k/4k PSL (R. Savage, M. Guenther and T. Mahood)

The new Al block optical table legs have arrived and are out for final machining.  They will be initally tested on the 4k table, then possibly moved to the 2k table if they prove to reduce table resonances.

The new rigid mirror mounts and PBS cube holders are out for fabrication, and should be received in a few days.  A new semi-rigid periscope for the 4k reference cavity has been designed and is under construction.  This periscope is based upon the Livingston design (and uses on of those mirror holders), but the top periscope mirror is held by a steerable Newport U100A mirror mount.

A problem has been discovered with the existing Livingston rigid mounts, in that a transmitted beam is interferred with by the spring that holds the mirror in place.  In most cases it's simply an issue of improperly dumping the transmitted beam, but we'll need a clean transmitted beam to feed the frequency shifter and reference cavity in the 4k build-up.  A simple add-in fix has been designed and is being constructed to allow use of these mounts.


LIGO Livingston Observatory (LLO) Operations (Coles).


OPTICS/COC/SEI INSTALLATION (Jonathan Kern)

Allen discovered that the bellows we replaced at the X-end last week is still leaking; now it seems that the leak was at the support tube copper gasket. We've just completed replacement of the 2nd bellows and are pumping down again. Opt-lev showed a 0.25v (32u-rad) misalignment after replacing the bellows. We've staged everything at the Y-end, and resurveyed all of the IAM monuments. We're waiting on the completion of leak checking before we vent for realignment and installation of the Arm Cavity Baffle. In the meantime, we're working with the commissioners to damp the core optics in the vertex and align the Michelson.

ISC (Anthony Rizzi)

Sany and I have aligned Steering and Mode Matching mirrors such that the beam coming out of the Faraday port into ISCT1 is within 20% of it's expected power. We have also seen the first (though briefest of) flashing at the dark port. However, the dark port beams are swinging due to problem with beam-splitter suspension control.  The numbers are as follows.

We are currently working to get Faraday port power up and  suspension control problems with beam-splitter fixed.  ISCT1 has been permanently placed and marked in its correct position such that periscope is aligned with beam Faraday beam.  We plan to re-check beam path on ISCT1


Detector/Technical Support (Whitcomb, Coyne).


 
Installation & Commissioning:
Hanford
Livingston
Other Science/Engineering Activities:
Design/Analysis/Fab
Issues/Concerns
See also the Installation web page

1.1 LHO INSTALLATION & COMMISSIONING

2km Commissioning

The E2 run began on Wednesday. (cast of thousands)

Daniel Sigg
Since Wednesday Nov. 8 the second engineering run (E2) is in progress. Non-invasive operations started at around 16:00 in the recombined Michelson configuration. Lock stretches of typically 40-60 minutes are observed; most likely limited by tidal effects which exceed the suspension controller ranges. The instrument is running smoothly up to now.

The E2 web page is at: http://blue.ligo-wa.caltech.edu/engrun/

Nergis Mavavala, Rai Weiss, Matt Evans, Gaby Gonzalez
The end of last week was spent writing up and testing operating instructions for locking and running the interferometer configurations to be used in the E2 run. This ended with a little training session for interested persons.

We then turned our attention back to WFS1 and now with DAQ/GDS/ASC in better health, we were able to confirm our earlier observation that all four quadrants of WFS1 saw mostly common-mode signals, even when we drove the mirror angles on both the ETMs and/or the ITMs. We tried some simple things (though we wouldn't expect those to make a big difference) such as focussing the beam more on the WFS, but saw no change in this puzzling behavior. More on this after the E2.

Bill Kells
running e2e for understanding of the full ifo locking.
Prep for E2 (eg understanding DMT tools, etc.)

Szabi Marka, Akiteru Takamori, Daniel Sigg
We had our first run for the E2E timing measurement yesterday. We injected sine wawes at various frequencies to I/ETMX/Y and recorded the relevant channels. The GPS timing monitor is running on STONE for the duration of the E2 run.

DAQ

Rolf Bork, Dave Barker
Rolf  flew to LHO on Friday to help fix some problems with the DAQ system prior to the E2 run:
1) Random noise was noticed on all DAQ channels: Several Data Collection Units (DCU) diagnostics were reported network data errors.  This was tracked down to several loose fiber optic connections (fibers inserted into connections, but twist locks not cammed over). One of the DCU's was then passing on corrupted data.  The Y end station DCU is still reporting problems, but this looks to be a long haul fiber problem.  As it is not passing corrupted data and not critical to the E2 run, it was opted to track this down later and concentrate on item 2.
2) Request had been made to increase the EPICS data collection rate from 1Hz to 16Hz and number of channels increased from 785 to ~2800. Several problems now exist in doing this:
  • Every DAQ channel requires 96bytes of descriptor info per channel to be sent to the EDCU and FrameBuilder when they start up. Since the controller is already running and passing thru data, it didn't have enough time to pass this info on request and still keep up with the data thruput and would fall out of sync.  Therefore, for now, the number of EPICS channels has been reduced to ~1100 channels. For a long term fix, the controller code will be modified to send this data info on request using Direct Memory Access (DMA) block transfers. This will move the data faster and the CPU is not involved in this transfer, thus it should not be distracted from its primary job of moving data to the FrameBuilder.
  • The EDCU processor locks up periodically, requiring reboot of the system. The system typically runs 10+ hours before this occurs. This problem is still be tracked offline on the test system at Caltech.

  • 3) ASC system test points were not functioning properly.  Turned out code was compiled against an incorrect header file.

    RF Distribution

    Rich Abbott
    Finished construction and analysis of the radiation problems associated with the RF distribution system.  A test was conducted to measure the change in phase of the various outputs of the system in response to physical contact and grounding variations.  The observed phase changes in the distribution system are less than 0.01 degrees as measured with the network analyzer.  Todd Etzel will post the results on his web site.

    PSL

    Peter King
    One of the LHO spare lasers, SN #107, is being shipped back to LHO from Caltech, now that SN #110 has been returned after servicing from Lightwave. Included in the shipment is a reference cavity for the 4k PSL and laser power supply #108.  The power supply was returned to Lightwave because it kept tripping out an unusually large number of times.  Lightwave tested the electro-static discharge (ESD) sensitivity of the power supply and could find no faults.  It appears the only action taken by Lightwave was to partially remove the anodizing behind the front panel in order to improve the ground connection to the instrument rack.

    Lee Cardenas is still working on the block for mounting the pre-modecleaner.  Some details concerning mounting holes and position stops are being figured out.

    Input Optics

    David Ottaway, Betsy Weaver
    After the MC mirrors came out of the bake oven, pitch balance angle shifts were found, sometimes up to 2 mrad.  Spares will be processed with available magnets, dumbbel standoffs, wire standoffs and guide rods at LHO.  LLO is shipping all of their spares, and UF is producing enough for 10 more small optics.

    Suspensions

    Janeen Romie
    Working with Doug Cook to understand why there is difficulty with the 4k LHO LOS gluing fixtures. Reviewing Betsy Weaver and David Ottaway's updated SOS Balancing Spec.

    4K Initial Alignment

    K.Mason
    Completed the initial alignment theodolite positions and angular orientations for the 4k corner station alignment in Hanford. PLX retroreflector positions were sent to Doug Cook so that he could set up and clean parts in preparation for the alignment.

    LIGO-TriNet

    Szabi Marka, Akiteru Takamori, Mark Lubinski, Virginio Sannibale
    We set up the seismometer, strong motion sensor, power and datalogger in its temporary position at the LHO Y endstation. It is up and accessible through the net. We still have to place the thermal insulation and safty barriers around the instrument.

    1.2 LLO INSTALLATION & COMMISSIONING

    Commissioning

    Peter Saulson
    Locking of the mode cleaner is now robust: typically it stays in lock for periods approaching 1 day. This has allowed us to accomplish several perfomance tests.
  • The MC cavity pole was measured to be 4.08 kHz, equivalent to finesse of 1500, as expected.
  • Fundamental internal modes of MC mirrors (28.2 kHz) each have Q of about 500,000, as hoped.

  •  

     
     
     
     
     

    Frequency noise of PSL was measured during Peter King's visit, using the MC as an analyzer cavity. Above 1 kHz, the noise is white at a level about a factor of 2 above the spec. Also, there are several surprising spectral lines in the frequency spectrum above 13 kHz. The reasons for these are not yet known.

    We are still following up Mark Barton's discovery that quality factors of some of the rigid body modes of SOS mirrors are surprisingly small. Pitch modes in particular show Q values as low as 300 to 500. Equally troubling is evidence for non-linear behavior in some ringdowns, and in especially small Q values that one infers from how the mirrors ring up after damping is disabled.

    Ed Daw's band-limited rms monitor has revealed that times when we typically lose lock on the mode cleaner (around 1:30 a.m. and around 6 a.m.) are times of large seismic noise in the 1 to 3 Hz band. These times are when trains pass through Livingston.

    PSL

    Peter King
    An attempt to re-measure the PSL frequency noise with the modecleaner was only partially successful because of the modecleaner partially going out of alignment every few seconds - which played havoc with the signal analyzer averaging.  This occurred when the damping gains were close to minimum in last weeks effort to get the modecleaner locking more robustly.

    Input Optics

    Dave Reitze, Sanny Yoshida, Warren Johnson, etc
    Sany and Warren Johnson measured Q of small optic suspensions using excitation and ringdown.  Warren wrote a nice digital lock-in program for analyzing the ringdown data. So far:
  • MMT1: Pos Q=8000,  Pit Q=1280, Yaw Q=8750
  • MMT2: Pos Q=9980,  Pit Q=503, Yaw Q=8450
  • MC2:  Pos Q=4265,  Pit Q=484, Yaw Q=3700

  • The low Qs for pitch are puzzling and under investigation.

    Continued aligning optics after Mode cleaner. Observed a beam coming out of Faraday isolator to ISCT1 table. The beam height looked right (i.e., going to ICST1 periscope top mirror). The power is lower than expected - under investigation.

    LSC and ASC

    Jay Heefner
  • Jay and Rolf will be in La. next week to complete the installation and test of the LSC system.
  • 2 61 MHz WFS PD were calibrated and sent to LLO for installation.

  • 16 Optical lever PD amps were tested and sent to MIT for installation in boxes. These PDs should complete the remaining optical lever installations and provide each site with a few spares.

    2.0 Other Engineering and Scientific Activities

    2.1 Design/Analysis/Fab

    Optical Metrology

    GariLynn Billingsley
    Come to think of it.. I haven't done a darn thing for the detector this week.  The Lab has been investigating Sapphire homogeneity...

    PSL

    Peter King
    Currently in the midst of preparing a presentation for next week's meeting at LZH, concerning the LIGO II PSL.

    The paper on intensity stabilization using a current shunt, submitted to Review of Scientific Instruments was accepted for publication.  Currently the paper is scheduled to appear in the February 2001 edition.

    Rick Karwoski, Paul Russell
    Working on getting the essential elements of the Hanford 4 km PSL ready to ship to the site.

  • We have begun testing the pre-mode cleaner circuit boards.
  • A test fixture for the VME-based boards has been built and is in use on the Frequency Reference Card.
  • The test fixture for the Photo-diode Boards will be operational tomorrow
  • The Reference card has undergone a full end-to-end functional test.
  • Testing of internal signal paths has started. We will document readings for Acceptance Test Procedure documentation which will follow.
  • Preliminary testing of the photo-diode boards will start tomorrow.
  • ISC

    Rich Abbott, Flavio Nocera, Mohana Mageswaran
    Mode cleaner servo is being stuffed. Pentek clock fanout boards have been re-ordered and are back in house after fixing an existing cad error on the current rev.  These boards will be sent to LLO next week to be installed in the LSC by Jay and Rolf.  A full bill of materials is being prepared for the LSC system by Flavio.

    Modulated OSEM Design

    Jay Heefner
    It has been verified that we can run the current PDs used in the suspension in photovoltaic mode. This will allow us to use a differential amplifier configuration on the input of the satellite amplifer, thus making the system more immune to induced emi. This mode of operation does not degrade the sensitivity nor does it appear to have any effect on the upconversion of scattered light to the LED modulation

    New OSEM Heads

    Janeen Romie
    Dennis and I will meet with Progressive Technology's subcontracted plating company, Macro Metalics, on friday to examine their prototypes and to test the surface finish of the production parts from Progressive Technology. Buying parts for production assembly.

    Peter Fritschel
    OSEM head plating: we have decided to do a test plating run of a handful of the new alumina heads with Rapid Prototyping Corp, in Longmont, CO. The plating material will be zirconium nitride, which offers good wear, sliding coefficient of friction, emissivity (~0.3) and resistivity (>200 ohms/square) characteristics. This test run should take place early next week.

    Digital Suspensions

    Jay Heefner
  • Universal dewhitening boards for the 4K have been tested and are ready for installation. Anti-Image boards are also complete.
  • LOS coil driver and LOS Bias modules are being stuffed.
  • Data Monitoring Tool

    John Zweizig
    This week I have been preparing for and participating in the E2 Run. There was an enormous amount of setup work for the data monitoring. I have also produced a bunch of documentation on how the monitors are used by shift workers and on shift procedures.

    Data Acquisitions System

    Sander Liu
            1. In the process of ordering parts for 12 new chassis.
            2. In the process of obtaining quotes for circuit board assembly from Accu-Sembly.
            3. In the process of obtaining quote for cable fabrication from PalPilot.

    Global Diagnostics

    Sander Liu
            1. Released schematic drawings D000203 to Document Control.
            2. Shipped eight (8) signal processors to LHO.
            3. Shipped four (4) signal processors to LLO.

    2.2 Issues Concerns

    nothing new



    40 Meter Interferometer (Weinstein).



    Thermal Noise Interferometer (Libbrecht).


    Electronics for locking the test cavities is mostly complete, with only minor finishing touches to be made.  There are still lots of cables to be made and installed.

    We balanced and aligned the second test cavity, and spot glued the wire standoffs to preserve this alignment.  Sensor/actuator heads are installed, but not plugged in.


    LASTI (Zucker).


    LASTI (MacInnis, Mason, Smith, Kruzel, Shoemaker, Zucker)

    Seismic installation: Installation of seismic supports in HAM20 (left end) is now physically complete and bellows have all passed leak check (after re-torquing; we discovered a broken torque wrench with our leak detector!).  Backfilled and removed door for final leveling/shimming tomorrow (Thursday) morning.  Some parts for the cleanroom on the last HAM, HAM21 (right end) are still stuck at the manufacturer so we are going to finish installing the BSC support piers before finishing off the last of the HAM's.

    Vacuum equipment: We now have a second QDP80 roughing pump courtesy of Allen Sibley at LLO; this is being installed to allow us to rough to turbopump range within a single shift. We tweaked up our interlock setpoints and tested the gate valve closure system, so the system is now qualified to run unattended.  Letting it go for approximately 100 hours we reached 2e-6 torr.  A rate-of-rise test indicates the outgas rate (presumed mostly water) is not unreasonable for this time under vacuum, of order 2e-10 tl/s/cm^2 (note there is a stack in one HAM), but taken with the above base pressure this indicates a mysteriously low turbopump speed (~100 l/s vs. nominal 1000 l/s expected).  No impact on the program, but a head scratcher.

    Instrumentation: Rolf and Jay released PO's for major parts of the DAQ and GDS systems (Racks, VME processors, reflective memory modules and VME crates have been ordered for the initial DAQ systems for LASTI. --Jay)

    Cleanrooms: started brainstorming in earnest on the BSC cleanroom concept for LASTI. Our latest idea is to tie into our accursed roof support columns to hold up the cleanroom fan/roof assembly without any legs to the floor. This allows the roof to support higher loads without deep trusses (e.g., to accommodate the "doghouse" suggested for the cartridge SEI installation technique) and removes all floor-level obstructions except for curtains.

    LASTI (Janeen Romie)

    Updated the SOS drawings to the LIGO I as-built configuration.  Submitted the drawings for the machined mechanical parts to CES for LASTI's two SOSs. Continuing procurement of osems for suspensions.


    Data Analysis and Computing (Lazzarini)


    Simulation and Modeling

    (Week of Nov 9)

    <2e2>

    This week, Hiro worked at Hanford, participating in E2 run shifts. First night, he studied the correlation of the darkport DC output and the break of locks.

    With the help of Matt, Hiro has set up three directories each of which simulates one of the 3 configurations of LHO 2K IFO, one for one arm, one for recombined and the last the full power recycling configuration. This needs a newer version of modeler/modeler_freq so that the simulation code uses the latest LSC servo code. Hiro built one including the latest code changes done by Tavio for speed improvements.

    Hiro also worked with Rick about the issue of the PSL table motion and doppler effect size estimation. The vertical motion was mistakenly used to estimate the effect, and the prediction came out 10 times larger. Details will be covered by Rick.

    <Adlib>

    Hiro (hopefully) fixed the problem of the primitive mirror with curvature mismatch. There still is discrepancy between the simulation with primitive optics and summation cavities. Biplab is working on this. He modified and cleaned some parts of the code.

    In order to generate proper noise curves from Han2k model, Biplab is testing matlab codes for calculation of power spectral density and the time-series data generated by E2E's digital filters especially when those deal with very steep transfer functions (e.g. seismic noise).

    Tavio worked with Matt to define the strategy to implement threads in the e2e simulation code. Matt is writing a code of modeler to make it easy for Tavio to implement threads in e2e. Tavio is cleaning and finalizing the idea before he start the coding.

    <Alfi>

    Ed Maros focussed on closing several problem reports for alfi. Bruce Sears is working on moving some infrastructure code from Alfi to ALParser in order to make it more generally available. This is necessary for the solution of the cyclic include problem. This will increase the utility of the transferred methods in general as well.

    (Week of Nov 2)

    LHO

    Biplab stayed last week at LHO and worked with Rick on PSL noise study. I investigated, with Rick Savage, the effect of Doppler shift of laser due to table motion wrt the suspended mode cleaner and reference cavity. We tried to counter the effect by reversing the entry of light into the reference cavity of Han2k. It could not improve the frequency noise (especially the peak at 50Hz which has a strong coherence with the table motion) much. Rick and others also added metal plates to the table legs, which helped in eliminating the 50Hz peak at the cost of a broad 80Hz peak. [Details: see LHO part of weekly].  More investigation going on.

    Matt Evans is working this week for the improved lock acquisition.

    Simulation code

    in-lock state noise
    Biplab is trying to generate Han2k In-lock state noise curve. He is facing some problem in FFT calculation when the amplitude of noise varies much over frequency range (e.g., seismic noise) and is expected to generate a steep spectral density.

    3D mirror
    Hiro discussed with Mark Barton discussing about the modeling of suspended mirrors. Based on this discussion, 3d mirror will be implemented following the design document by Jay (T980043). This will be integrated into a modified version of Han2k simulation code. The calibration process will be skipped, but in stead for now, expected variation of inbalances of the sensor and actuator after calibration will be artificially included in the simulation model parameter.

    Speed improvement
    Tavio Dangelis has started to work on the implementation of thread in the simulation engine. He wrote a simple program to understand the implementation of thread on SUN.  After that research is over, he will look into the details of the simulation code and design the implementation of thread.

    alfi

    Ed and Bruce are working to improve the stability of alfi. Almost all the major issues are addressed, except for the timing issue (proper updating of drawing and saving files). Code cleaning is also going which will also improve the stability.

    LIGO Data Analysis System

    Software Systems (Blackburn)

    Week of Nov 9: In middle of E2 run; will be provided next week.

    Week of Nov 2:

    This week focused on testing of the LDAS software to be used in the engineering run. The testing identified two classes of bugs, those that had to be fixed for the E2 run and those that could be left for after the CVS tagging. It required roughly two days of testing after necessary bug fixes were implemented to be sure that the fixes didn't introduce new bugs. The remaining open bugs are in the problem tracking system and a text version of these will be made part of the LDAS distribution.

    The documentation for the wrapperAPI and mpiAPI were enhanced this week to include information needed to support the event- MonitorAPI's functional requirement to correctly insert event data into the LDAS database. In addition the code modules for the wrapperAPI needed to handle the process and processparam tables was started.

    A couple of master-slave flow control problems were identified in the current version of the wrapperAPI. Masha and Kent worked on a solution to this problem which results from the current model of the slave running with individual decoupled while loops. The work around was discussed in the weekly mpiGroup meeting and will be implemented and tested in the next week. Work on a DSO that is compatible with the new wrapperAPI continues at UWM a problem with the dataConditon() interface was identified by Masha and reported to UWM. They will have a new version with a fix soon.

    The new Unified Data Type class for the dataConditionAPI has been integrated into a yet to be released version of the dcAPI. New test code based on this UDT was also started this week.

    In an effort to better understand the test failures associated with the dataConditionAPI, swap space was added to the dcAPI and the full test suite issued. This resulted in all but 3 out of roughly 550 tests passing. The remaining three failures are a bit of a mystery, associated with out of memory errors that were not seen just a week earlier in resample() actions. It is hoped that a better understanding will develop when the group gets together next Monday.

    An effort was made to produce a user command that would take data from frames, pass the data through the dataConditionAPI where some algorithmic processing would occur and then send the results to the database. This command could only perform two of the three steps in time for the software release. This sub-command is part of the release and may be useful to the E2 run but the completed command was not possible in the time available.

    Test code was developed to verify a statement found on the net that GCC was not thread safe in its throwing of exceptions. The code was developed and tested by Alex. It required running of code for long periods of time on SMP linux boxes to reproduce the stated bug. Until GCC and Linux come up with a fix to this problem we run a slim risk of having threaded exceptions kill an API (primarily the dataConditionAPI).

    Finished implementation of tape control gui as per discussion with Greg last Wed. Tested with Greg at Hanford regarding start up and stop monitoring of his tape controller scripts. Made gui changes per his request. All working as of Wednesday afternoon.

    Peter Shawhan

    My LDAS activities this week have been to do some testing of the system, and to re-commission the mechanism by which the DMT sends data to the database (by anonymous ftp).  The test data I used to check out this pathway happened to also reveal the bug regarding the handling of lstrings, though they are not actually used by the DMT at present, so this is not a critical issue for the E2 run.

    I also researched the "HSI" interface to the hpss system at CACR. In the near term, access to E2 data will make use of a simple server based on this interface.

    Hardware Systems (Anderson)

    (Week of Nov 9)

    The electrical work for the LDAS Development system has been completed at Caltech and now allows for twice the power consumption.

    A direct connection from the LDAS networks at LHO and LLO has been reestablished to the GDS DMT machines over Fast Ethernet now that the LDAS ATM networks has been replaced with 100/1000Mbit/s Ethernet.

    The ATM OC-12 (622 Mbit/s) link between the Caltech LIGO and CACR networks has been reestablished.

    The single LDAS Alpha based computer (sadan) has been upgraded to RedHat 6.2.

    The first price quotes for LHO and LLO few-hundred-slot tape libraries have been obtained.

    General Computing

    (Week of Nov 9)

    MIT

    Setting things up for an ILOG system to be installed.

    Livingston

    Setting up tape backup unit.

    Hanford

    Setup a few new accounts. Working issues related to the E2 run.

    Albert and Larry met with PNNL concerning the increase in bandwidth for the Hanford site. Presently, the investigation will go in the direction of getting onto PNNL's OC3 network. It appears to be the most cost affective solution but there are a number of logistical items that need to be checked out first.

    CIT

    (Lisa)

    (Barbara)

    I have been catching up with web site changes since being away last week. Most of the time has been spent on the REU pages and the conference page.

    (Sam)

    The ethernet card from Dell arrived. Answered various users questions. Continued the quest to remain a student.

    (Suresh)

    (Larry) (Week of Nov 2)

    MIT

    Replacing a broken disk drive to prepare a machine to serve as web server and ilog home.

    Hanford

    Larry has contacted PNNL to start communications again on getting more bandwidth to the Observatory. Lazzarini and Wallace met with PNNL IT staff to discuss near term and long term solutions. In immediate near term we will move off T1 and connect the GC ATM switch directly tothe PNNL switch. We will be limited to 10% of the ATM bandwidth, which is 10x more than we presently have off the site. Annual cost will be ~$50k, comparable to the presently negotiated price for the 4xT1 bandwidth. This excursion from the previous baseline is possible becuase PNNL has installed an OC3 link to Seattle from Richland.

    Livingston

    Nothing to report

    CIT

    (Lisa)

    (Sam)

    Worked on midterms, homework and became a year older.

    (Suresh)

    (Barbara)

    On Travel

    (Larry)


    LIGO II/Advanced R&D (Sanders)


    (Janeen Romie)

    LIGO II - Working on updating the schedule and the fabrication portion of the costs.

    (Bill Kells)

    (Helena Armandula)

    LIGO Coatings

    The Advanced LIGO Coating Development and Preliminary Production Specifications are finalized.  Dennis, Jordan and Gari actively participated with their inputs.  The document has a DCC number and has been placed in DCC OUT.  With this document Irena is completing the RFQ package.

    Silicate Bonding

    We are in the process of developing a stress test for the silicate bonds that would allow observing and measuring stress under load. Sheila Rowan visited last Thursday; we formulated some of the research plans and collaborations to take place in the future.  We (Phil, Sheila and I) are going to meet with Mr. Ken Bower from Stanford to discuss the low tensile strength in our hydroxy-catalysis bonds. Glasgow encountered similar problems.

    Seismic Attenuation (Riccardo DeSalvo) (10-30 and 11-4)

    (Frederick)

    Ansys fully operational, starting long simulation program that will include mirror suspensions and electrostatic actuators. Cabling DAQ for creep oven, restarted thermostabilization of big oven, ordered 32 channel differential DAQ card, the old one with 16 single
    ended was not adequate.  Designing test cuts for Sapphire including Q measurement diving boards.  Measured mini GAS blades,  despite better thickness uniformity of the blades there is still about 10% scatter of the load carried.  We will still need to make many more blades than necessary and pick the ones that satisfy the load.  We should measure the individual blade's hardness to see if the lift power scatter correlate with the hardness.  Also the better uniformity in thickness yielded a higher than expected lift power.

    Send to Kenji the blades selected if suitable otherwise make a set of thinner blades.

    (ChenYang)

    Calculated e.s. actuator electrode,  Design sent to Alex for carving.  Designing setup for mirror suspensions.

    (Akiteru)

    Finished TAMA IP transfer function measurements,  reached 80 dB with and without hanging chain.  Disassembled tower to reassemble in active inertial damping location.  Cooked small blades for Kenji.  Testing for shipment.  40 MHz DSP chips arrived from Texas.    And for free!!!   60 MHz version not available but 40 is OK.  Made paperwork for TAMA order.

    (Szabi)

    Measuring frequency vs. load dependence of TAMA IP.  Souping up oil bearings.

    (Virginio)

    Finalizing GASF paper for editorial board next week.  Started data analysis of LIGO IP control runs.  Assemblying TAMA prototype actuators.   Made order  for Tama electronics et al.  4 DSP,  ADC,  DAC, 2 VME crates.


    For additional information about this report, contact sanders@ligo.caltech.edu