Weekly Report for Week Ending November
9, 2000
The LIGO Executive Committee
Agenda for Monday November 13, 2000 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
-
Announcements
-
LSC Issues (Weiss)
-
Comments on Weekly Report
-
WBS 1 LIGO I Construction (Lindquist)
-
Field Change Orders/Contingency Liens/Change Requests
-
WBS 2 LIGO Lab Operations
-
Administration (Lindquist)
-
Sites (Raab, Coles, Shoemaker, Sanders)
-
Detector (Whitcomb, Coyne)
-
Campus Research Facilities (Weinstein (40 Meter), Libbrecht (TNI), Zucker(LASTI))
-
Data Analysis and Computing (Lazzarini)
-
WBS 3 and 4 Advanced R&D and LIGO II
(Sanders)
Executive Committee only 11:30 - noon
Topics:
Special Items: Operating Costs through the end of October
Special Announcements:
Weekly
Report Highlights
LSC Issues (Weiss)
no report
LIGO I Construction/LIGO Laboratory
Administration (Lindquist)
WBS 1.2 LIGO Operations--Administration
LIGO Weekly Site Telecon (Lindquist)
A site teleconference was held on Thursday, November
9, 2000. Issues included establishing subaccounts for the site facilities.
The list of current actions revised to reflect
open actions assigned through November 9, 2000 may be found at
ACTION
LIST.
PROPERTY
MANAGEMENT (Chargois)
From: Ed Chargois <chargois_e@ligo.caltech.edu>
-
Assisted the Optic Engineer (H. Armandula) with the shipping of two (2)
End Test Mass and Folding Mirrors SN# SPETM04, valued at $61,262, and SN#
FM04, valued at $75,517, to Stanford University (S. Rowan) via Fed-X.
Account Number P158138.
-
Assisted the Systems Administrator (L. Bogue) with the packing and
shipping of a Defective 3Com Hub Part # 3C421600-US to TWG Solutions
at Windham, NH. Account Number P158166.
-
Assisted the Systems Administrator (S .Singh) with the Packing and Shipping
of a Rack Filler to the LIGO Hanford Observatory (G. Mendel) via
Fed-X . Account Number P158166.
-
Responded to a letter from General Services Administration (J. Creel),
Haraham LA, stating zero available of pick-up trucks for the LLO at this
time, and that an additional request should be sent to The General Services
Administration Headquarters (Ms. Susan Johnson) at Arlington,
VA. This request was accomplished on November 8, 2000, DCC
# L0002259-00-P.
DOCUMENT
CONTROL CENTER (Turner, Mak)
>From: Linda Turner
- turner@ligo.caltech.edu>
Web pages for the
DCC give simple how-to's for document numbering, easy access to the latest
on-line documents, and search capabilities for the DCC database. Take
a look. . .
ACCOMPLISHMENTS
-
Great progress continues on the auditing and sorting
of drawings for Livingston.
-
Christmas party posters were designed and emails sent
to cit-all and about 50 Caltech staff outside of LIGO who are associated
or working with LIGO personnel. The response has been immediate and
positive from these outside guests.
-
Worked through a tremendous number of electronic documents.
There continues to be a need for me to fix file names and imbed LIGO numbers
in several of these submitted documents.
-
Prepared several sheets of labels for past revisions
of Livingston drawings needing to be filed.
-
Work continued on the large pile of process travelers.
From: Cleveland Mak
<mak_c@ligo.caltech.edu>
Considerable progress is being made on Livingston
drawings. The pile is definitely shrinking! Many more drawings
were either tossed because of duplication or placed into files. Most
of the drawings being filed were mainly originals replacing copy versions
or filing of a particular 'size' of a revision of a drawing that we did
not already have.
Processed large number of electronic documents as
well.
|
Packages |
Faxes |
| In |
45 |
41 |
| Out |
11 |
36 |
Press here to access
the DOCUMENT CONTROL CENTER
WEB PAGE.
COST SCHEDULE
CONTROL SYSTEMS (Cunningham, Brambila, Akutagawa, Kaufman)
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS
PAYABLE HISTORY DATA.
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
-
Working on Brian Loucks, Hereaus Amersil, Corning.
Looks like Butler may be audited by DCAA. The DCAA has requested certain
information to be provided which I will be working on obtaining today.
-
There were a large number of requisitions recently submitted
for one time purchase orders. I am working with Gina in helping her get
them all processed.
-
We just received word that the expenditure type of "Equipment-Not
Capitalized" was created in Oracle specifically for equipment priced from
$500 through $4,999 which will not be capitalized beginning Oct 1, 2001.
I understand that overhead will not be charged on this expenditure type
until the beginning of the next fiscal year. We expect to begin using this
new expenditure type now that it has been specifically designated for such
equipment. I will check with Ed before we proceed with the use of this
new expenditure type.
From: Florence Kaufman <fkaufman@ligo.caltech.edu>
-
Completed and issued monthly report for Operations for
October 2000.
-
Provided information for and reviewed Annual Property
Report to NSF.
-
Completed and issued Integrated Report for MIT for October.
-
Completed and issued Integrated Report for Data Analysis
Group for October.
-
Prepared draft of Classification Guidelines for Equipment
for review by Ed Jasnow and Phil Lindquist.
SUBCONTRACTS MANAGEMENT (Petrac,
Jasnow)
From: irena@ligo.caltech.edu (Irena Petrac)
-
Univ. of Michigan: CO No. 03, adding funds for D. Gustafson's
participation on the 2K interferometer commissioning at LHO, was released
to CIT Purchasing.
-
Univ. of Florida: CO No. 10, re-allocating charges to
appropriated LIGO accounts, is being coordinated with the Univ. of Florida.
-
RFQ/Advanced LIGO/Optics Coating: Issuance of the RFQ
is pending final updates by the Detector/Optics group.
-
RFQ/Advanced LIGO/Seismic Isolation Hardware: Project
review and approval (of the RFQ package) for release is pending final updates
of technical and contractual content.
-
Crystal Systems: CO No. 2 is in re-write to incorporate
additional scope planned for FY'01.
-
TAMA: A draft contract for the purchase, by the National
Astronomical Observatory-Japan (NAO) from Caltech, of one TAMA-SAS prototype
was reviewed by the Sponsored Research and found acceptable to Caltech.
The draft text was forwarded to TAMA for finalization and processing.
Galli&Morelli: A Purchase Order for components
and associated electronics needed for construction of one TAMA-SAS prototype
is pending receipt of NAO's purchase order as indicated in the above item.
From: Ed Jasnow <jasnow@ligo.caltech.edu>
-
No report this week (See section addressing Construction below.)
Support (Wood)
Irene Baldon
-
Eighteen (18) new trips were started (including one
trip using an old canceled ticket) and I have eight (8) trips pending final
approval before tickets can be issued. I prepared a few Advance Requests
and Payment Requests using the old system due to various reasons that excluded
them from the new system.
-
Worked with a few travelers who had questions or needed
further clarification on using or reconciling their new P-Cards.
For the most part, those having cards seem to be doing fine and find the
cards a convenience.
-
The P-Card Expense Report was revised by Michelle Thompson's
group, and I made a few minor change recommendations. My re-revised
version was approved by Michelle's group and has been sent on to Beth Moore's
group to be put into FileMaker Pro form. As of this writing, I haven't
heard anything from Beth or her group.
-
Worked on and completed thirty-one (31) Expense Reports.
I have twenty-five (25) Expense Reports to work on. The new P-Card
Expense Report was sent to the existing P-Card holders, and I sent out
a note to all LIGO travelers clarifying some issues in regard to the report
and processing.
-
Prepared the Travel/Vacation Itinerary for the Week
of November 6, 2000. Performed normal recording and filing associated
with Travel and Reimbursement. Worked on several problem issues with
Travel Audit in addition to the above. Also performed miscellaneous
duties as requested by various members of the LIGO Project here at Caltech
as well as from members of the staffs of each of the two (2) sites.
I continue to do MIT's travel to the sites for installation activities
and also to assist them wherever possible.
Dorothy Lloyd
-
Processed the usual requisitions, invoices and receiving
on-line. For more detail, see "Cost Schedule Control Systems" report by
Esther Cunningham.
-
Tracked and followed up on invoice problems.
-
Reviewed and recorded payments processed by Esther for
the week of October 30, on contract summary sheets and LIGO database.
-
Continue to monitor contract and blanket order funding
levels and notify task managers when supplements are needed.
-
Jim continues to do data entry in the LIGO database
and help out in the DCC.
Rita Torres
-
Over the last several days participated in fast and
furious purchasing activity associated with the Bridge Development lab.
Activities for lab set up are ongoing.
-
Did change order No. 3 for Corning, also for Heraeus
Amersil, obtained Oracle requisition numbers for both. Also did change
order No. 10 for Univ. of FL. A few MOU documents in the works.
-
Ongoing activity: Sent out a test message to LSC email
addresses. Out of almost 390 names, 40 addresses bounced back.
I have identified the individuals' organizations, now I must check their
Z documents. Were these input errors, was the info given us in error,
did the info change after they gave it to us? So far I've found two
input errors, the rest I am investigating.
-
Continue to chase various details associated with Pcard
purchases.
Elizabeth K. Wood
-
With a little brainstorming on the part of Lisa, Larry,
and me, and help from Stan and Garilynn, we were able to convert the proposal
into .pdf format. It only took reinserting five figures, one of which
had to be reduced in computer-memory size, printing the WORD file to the
color laser printer in room 18, and running the resulting postscript file
through Adobe Distiller version 3.0 on Sirius (not on my PC) in order to
produce a complete .pdf file. It only took two different operating
systems and a lot of patience to produce a file that might be readable
to the NSF.
-
As a test to see whether the now finished .pdf file
could be read by FastLane (TM, all rights reserved), I sent a 2,242KB file
to the NSF. Well, I tried. Four times. As of this writing,
it’s not clear whether the hang-up is at the NSF side or our side.
I was told by a FastLane guru that the size of the file shouldn’t make
any difference.
Just a reminder: if you have had an article
submitted, accepted, or published since the last time I asked, please oh
please oh please let me/Linda/Barbara know.
Advanced LIGO (Frey)
From: Thomas Frey <tfrey@ligo.caltech.edu>
Progress Period from 11.03
to 11.09
Accomplishments:
-
Out of office sick on 11.7 and 11.8.
-
Advanced LIGO Project Controls meeting with Phil, Gary
and Dennis. Focus on ongoing R&D Proposal and 40-Meter planning.
-
Proposal plan development for Advanced LIGO and Operations
continues.
-
Issued data requests for progress data as of 11.10.00
that are due Friday.
-
Progress as of 11.03.00 was processed and posted.
-
Review of cost and schedule data is now ongoing.
-
Project Plan for the 40-Meter Lab Upgrade continues.
-
Issued data requests for progress data as of 11.10.00
that are due Friday.
-
Updated the plan with progress as of 11.03.00.
Posted to site.
-
Did not attend 40-Meter weekly meeting scheduled every
Wednesday at 2:30pm. (Out Sick)
-
Continuing to push for a CDS procurement schedule.
-
Met with Alan W. on Monday and received data regarding
the planning of experiments for the 40-Meter.
-
Planning process for the LASTI project at MIT is in
progress.
-
Followed up with David for any changes and to begin
updates.
-
Continue to test the Cost Book Tool. Met with
Barbara K., Elizabeth W., Rita T., and Irena P. to discuss the resource
database status.
-
Development of the Advanced LIGO Project Controls Guidebook
continues. Continuing to write section on data dictionaries.
-
Project Web Site for posting schedule and progress related
data continues to be updated with the latest and greatest.
Schedule 11.10 to 11.16:
-
Next weekly meeting will be Monday afternoon November
13 from 1 to 2pm regarding the planning and control of the Advanced LIGO
proposal development.
-
Advanced LIGO Proposal
-
Will begin the effort of contacting each system leader
to collect cost and schedule data. Hope to begin importing schedules
and cost this coming week or next.
-
Will begin to update the LASTI Schedule with progress.
-
Continue to pursue the planning and scheduling of the
staging buildings currently being bid and designed for HLO and LLO.
-
Will continue to update the Advanced LIGO / Ops Proposal
Plans and incorporate any changes.
-
Will post progress report by end of day Tuesday with
progress as of 11.10.00.
-
Will issue 18th week of status data to teams.
-
Will continue updating the 40 meter schedule and incorporate
any changes.
-
Will post progress report by end of day Tuesday with
progress as of 11.10.00.
-
Will issue 18th week of status data to teams.
-
Will finish revisions to WBS provided by Alan W.
-
Will meet with Alan to review development of 40-Meter
experiment tasks.
-
Meeting scheduled for Wednesday November 15 at 2:30pm
at LSCR.
-
Continue to test the Cost Book Tool. Have a meeting
with Barbara K. to discuss the Cost Book and the Resource DB.
-
Cost Book Tool development continues. Will be
importing data for Installation so that Dennis Coyne can proceed with estimating.
-
Will continue the development of the Advanced LIGO Project
Web Site.
-
Will continue the development of the Advanced LIGO Project
Controls Guide Book. Finish section on data dictionaries and start
on update process.
Anticipated Challenges:
Will not be able to produce
a complete / accurate baseline schedule for the 40-Meter lab due to the
lack of planning regarding the CDS. Per 40-Meter meetings, I cannot
expect to receive this data anytime soon if at all.
Due to the availability challenges
for Jay and Rolf related to the Advanced LIGO program plan, it is unlikely
that a complete estimate and schedule will be available for the NSF review
in January.
Corrective
Action:
None
to report at this time.
WBS 1.4.1.2 Project Controls (LIGO Construction)
Reports (Lindquist)
Annual Report: There
will be an Annual Report due as of the end of November. I will be
requesting inputs from the usual bunch mid-December after the dust from
the proposal has a chance to settle a bit. I propose to keep this
report moderate in size, about the size and complexity of a Quarterly Report,
to minimize the burden.
Change Control/Contingency (Lindquist)
The following Change Requests have
been submitted:
| CR-000018 |
WBS 1.1.4 |
Curbing for Service Roads at Livingston |
G. Stapfer |
| CR-000019 |
WBS 1.2 |
Additional Lab Equipment |
D. Coyne |
Press for the latest Contingency
Needs Projection.
COST SCHEDULE CONTROL SYSTEMS (Duncan,
Akutagawa)
From: Kris Duncan <kris@ligo.caltech.edu>
-
Continued with the October 2000
monthly CSSR. Continued to calculate earned value from input from task
managers.
-
Received the actual cost to date
and commitment data for October 2000 and began a reconciliation between
LIGO and CIT financial data.
-
Continued with construction contract/work
package close out.
-
Began preparations for a comprehensive
Estimate at Completion for the Annual NSF Report (November 2000).
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
-
The monthly reports (Allocation of Actual Costs for
Construction and Advanced R&D) for period ending October 2000 has been
put on the network. E-mail has been sent to the Task Managers noting the
location of the files.
-
I am working on gathering the details for the monthly
actuals and the open encumbrances for the above accounts. I will email
them to the Task managers as soon as I have completed them.
-
Continue to review the open encumbrances on the Construction
and Advanced R&D accounts to see if the requested removals have been
made. I will continue to review these accounts weekly until all encumbrances
have been removed.
SUBCONTRACTS MANAGEMENT (Petrac,
Jasnow)
From: Ed Jasnow <jasnow@ligo.caltech.edu>
-
Work is ongoing to revise the specifications and drawings
for the Livingston Staging Building. The schedule calls for the revised
package to be in the hands of the original four bidders by Wednesday, November
15, with the resultant bids due on Thursday, November 30.
-
We have received credentials and expressions of interest
from two architectural firms concerning performing the design of the new
Hanford Staging Building. We have sent out requests for interest to seven
firms.
From: irena@ligo.caltech.edu (Irena Petrac)
-
No report this week; see Operations Section above.
Quality/Safety (Tyler)
>From: Bill Tyler <tyler@ligo.caltech.edu>
No report.
LIGO Hanford Observatory (LHO) Operations
(Raab).
General Items (F. Raab)
E2 is underway.
PreStabilized Lasers
2k/4k PSL (R. Savage, M. Guenther and T. Mahood)
The new Al block optical table legs have arrived and are out for final
machining. They will be initally tested on the 4k table, then possibly
moved to the 2k table if they prove to reduce table resonances.
The new rigid mirror mounts and PBS cube holders are out for fabrication,
and should be received in a few days. A new semi-rigid periscope
for the 4k reference cavity has been designed and is under construction.
This periscope is based upon the Livingston design (and uses on of those
mirror holders), but the top periscope mirror is held by a steerable Newport
U100A mirror mount.
A problem has been discovered with the existing Livingston rigid mounts,
in that a transmitted beam is interferred with by the spring that holds
the mirror in place. In most cases it's simply an issue of improperly
dumping the transmitted beam, but we'll need a clean transmitted beam to
feed the frequency shifter and reference cavity in the 4k build-up.
A simple add-in fix has been designed and is being constructed to allow
use of these mounts.
LIGO Livingston Observatory (LLO) Operations
(Coles).
OPTICS/COC/SEI INSTALLATION (Jonathan Kern)
Allen discovered that the bellows we replaced at the X-end last week
is still leaking; now it seems that the leak was at the support tube copper
gasket. We've just completed replacement of the 2nd bellows and are pumping
down again. Opt-lev showed a 0.25v (32u-rad) misalignment after replacing
the bellows. We've staged everything at the Y-end, and resurveyed all of
the IAM monuments. We're waiting on the completion of leak checking before
we vent for realignment and installation of the Arm Cavity Baffle. In the
meantime, we're working with the commissioners to damp the core optics
in the vertex and align the Michelson.
ISC (Anthony Rizzi)
Sany and I have aligned Steering and Mode Matching mirrors such that
the beam coming out of the Faraday port into ISCT1 is within 20% of it's
expected power. We have also seen the first (though briefest of) flashing
at the dark port. However, the dark port beams are swinging due to problem
with beam-splitter suspension control. The numbers are as follows.
-
PSL output power: 94mW
-
MC transmitted power: 2.8mW
-
power out of Faraday (reflection off of RM) port: 47.5mW
-
approx. power in each of the two beams at Dark port 130-150uW
We are currently working to get Faraday port power up and suspension
control problems with beam-splitter fixed. ISCT1 has been permanently
placed and marked in its correct position such that periscope is aligned
with beam Faraday beam. We plan to re-check beam path on ISCT1
Detector/Technical Support (Whitcomb,
Coyne).
1.1 LHO
INSTALLATION & COMMISSIONING
2km Commissioning
The E2
run began on Wednesday. (cast
of thousands)
Daniel
Sigg
Since
Wednesday Nov. 8 the second engineering run (E2) is in progress. Non-invasive
operations started at around 16:00 in the recombined Michelson configuration.
Lock stretches of typically 40-60 minutes are observed; most likely limited
by tidal effects which exceed the suspension controller ranges. The instrument
is running smoothly up to now.
The
E2 web page is at: http://blue.ligo-wa.caltech.edu/engrun/
Nergis Mavavala, Rai Weiss,
Matt Evans, Gaby Gonzalez
The end of last week was
spent writing up and testing operating instructions for locking and running
the interferometer configurations to be used in the E2 run. This ended
with a little training session for interested persons.
We then turned our attention
back to WFS1 and now with DAQ/GDS/ASC in better health, we were able to
confirm our earlier observation that all four quadrants of WFS1 saw mostly
common-mode signals, even when we drove the mirror angles on both the ETMs
and/or the ITMs. We tried some simple things (though we wouldn't expect
those to make a big difference) such as focussing the beam more on the
WFS, but saw no change in this puzzling behavior. More on this after the
E2.
Bill Kells
running e2e for understanding
of the full ifo locking.
Prep for E2 (eg understanding
DMT tools, etc.)
Szabi Marka, Akiteru Takamori,
Daniel Sigg
We had our first run for
the E2E timing measurement yesterday. We injected sine wawes at various
frequencies to I/ETMX/Y and recorded the relevant channels. The GPS timing
monitor is running on STONE for the duration of the E2 run.
DAQ
Rolf Bork, Dave Barker
Rolf flew to LHO on
Friday to help fix some problems with the DAQ system prior to the E2 run:
1) Random noise was noticed
on all DAQ channels: Several Data Collection Units (DCU) diagnostics were
reported network data errors. This was tracked down to several loose
fiber optic connections (fibers inserted into connections, but twist locks
not cammed over). One of the DCU's was then passing on corrupted data.
The Y end station DCU is still reporting problems, but this looks to be
a long haul fiber problem. As it is not passing corrupted data and
not critical to the E2 run, it was opted to track this down later and concentrate
on item 2.
2) Request had been made
to increase the EPICS data collection rate from 1Hz to 16Hz and number
of channels increased from 785 to ~2800. Several problems now exist in
doing this:
Every DAQ channel requires 96bytes
of descriptor info per channel to be sent to the EDCU and FrameBuilder
when they start up. Since the controller is already running and passing
thru data, it didn't have enough time to pass this info on request and
still keep up with the data thruput and would fall out of sync. Therefore,
for now, the number of EPICS channels has been reduced to ~1100 channels.
For a long term fix, the controller code will be modified to send this
data info on request using Direct Memory Access (DMA) block transfers.
This will move the data faster and the CPU is not involved in this transfer,
thus it should not be distracted from its primary job of moving data to
the FrameBuilder.
The EDCU processor locks up
periodically, requiring reboot of the system. The system typically runs
10+ hours before this occurs. This problem is still be tracked offline
on the test system at Caltech.
3) ASC system test points
were not functioning properly. Turned out code was compiled against
an incorrect header file.
RF Distribution
Rich Abbott
Finished construction and
analysis of the radiation problems associated with the RF distribution
system. A test was conducted to measure the change in phase of the
various outputs of the system in response to physical contact and grounding
variations. The observed phase changes in the distribution system
are less than 0.01 degrees as measured with the network analyzer.
Todd Etzel will post the results on his web site.
PSL
Peter King
One of the LHO spare lasers,
SN #107, is being shipped back to LHO from Caltech, now that SN #110 has
been returned after servicing from Lightwave. Included in the shipment
is a reference cavity for the 4k PSL and laser power supply #108.
The power supply was returned to Lightwave because it kept tripping out
an unusually large number of times. Lightwave tested the electro-static
discharge (ESD) sensitivity of the power supply and could find no faults.
It appears the only action taken by Lightwave was to partially remove the
anodizing behind the front panel in order to improve the ground connection
to the instrument rack.
Lee Cardenas is still working
on the block for mounting the pre-modecleaner. Some details concerning
mounting holes and position stops are being figured out.
Input Optics
David Ottaway, Betsy Weaver
After the MC mirrors came
out of the bake oven, pitch balance angle shifts were found, sometimes
up to 2 mrad. Spares will be processed with available magnets, dumbbel
standoffs, wire standoffs and guide rods at LHO. LLO is shipping
all of their spares, and UF is producing enough for 10 more small optics.
Suspensions
Janeen Romie
Working with Doug Cook to
understand why there is difficulty with the 4k LHO LOS gluing fixtures.
Reviewing Betsy Weaver and David Ottaway's updated SOS Balancing Spec.
4K Initial Alignment
K.Mason
Completed the initial alignment
theodolite positions and angular orientations for the 4k corner station
alignment in Hanford. PLX retroreflector positions were sent to Doug Cook
so that he could set up and clean parts in preparation for the alignment.
LIGO-TriNet
Szabi Marka, Akiteru Takamori,
Mark Lubinski, Virginio Sannibale
We set up the seismometer,
strong motion sensor, power and datalogger in its temporary position at
the LHO Y endstation. It is up and accessible through the net. We still
have to place the thermal insulation and safty barriers around the instrument.
1.2
LLO INSTALLATION & COMMISSIONING
Commissioning
Peter Saulson
Locking of the mode cleaner
is now robust: typically it stays in lock for periods approaching 1 day.
This has allowed us to accomplish several perfomance tests.
The MC cavity pole was measured
to be 4.08 kHz, equivalent to finesse of 1500, as expected.
Fundamental internal modes of
MC mirrors (28.2 kHz) each have Q of about 500,000, as hoped.
Frequency noise of PSL was
measured during Peter King's visit, using the MC as an analyzer cavity.
Above 1 kHz, the noise is white at a level about a factor of 2 above the
spec. Also, there are several surprising spectral lines in the frequency
spectrum above 13 kHz. The reasons for these are not yet known.
We are still following up
Mark Barton's discovery that quality factors of some of the rigid body
modes of SOS mirrors are surprisingly small. Pitch modes in particular
show Q values as low as 300 to 500. Equally troubling is evidence for non-linear
behavior in some ringdowns, and in especially small Q values that one infers
from how the mirrors ring up after damping is disabled.
Ed Daw's band-limited rms
monitor has revealed that times when we typically lose lock on the mode
cleaner (around 1:30 a.m. and around 6 a.m.) are times of large seismic
noise in the 1 to 3 Hz band. These times are when trains pass through Livingston.
PSL
Peter King
An attempt to re-measure
the PSL frequency noise with the modecleaner was only partially successful
because of the modecleaner partially going out of alignment every few seconds
- which played havoc with the signal analyzer averaging. This occurred
when the damping gains were close to minimum in last weeks effort to get
the modecleaner locking more robustly.
Input Optics
Dave Reitze, Sanny Yoshida,
Warren Johnson, etc
Sany and Warren Johnson
measured Q of small optic suspensions using excitation and ringdown.
Warren wrote a nice digital lock-in program for analyzing the ringdown
data. So far:
MMT1: Pos Q=8000, Pit
Q=1280, Yaw Q=8750
MMT2: Pos Q=9980, Pit
Q=503, Yaw Q=8450
MC2: Pos Q=4265,
Pit Q=484, Yaw Q=3700
The low Qs for pitch are
puzzling and under investigation.
Continued aligning optics
after Mode cleaner. Observed a beam coming out of Faraday isolator to ISCT1
table. The beam height looked right (i.e., going to ICST1 periscope top
mirror). The power is lower than expected - under investigation.
LSC and ASC
Jay Heefner
Jay and Rolf will be in La.
next week to complete the installation and test of the LSC system.
2 61 MHz WFS PD were calibrated
and sent to LLO for installation.
16 Optical lever PD amps
were tested and sent to MIT for installation in boxes. These PDs should
complete the remaining optical lever installations and provide each site
with a few spares.
2.0 Other
Engineering and Scientific Activities
2.1 Design/Analysis/Fab
Optical Metrology
GariLynn Billingsley
Come to think of it.. I
haven't done a darn thing for the detector this week. The Lab has
been investigating Sapphire homogeneity...
PSL
Peter King
Currently in the midst of
preparing a presentation for next week's meeting at LZH, concerning the
LIGO II PSL.
The
paper on intensity stabilization using a current shunt, submitted to Review
of Scientific Instruments was accepted for publication. Currently
the paper is scheduled to appear in the February 2001 edition.
Rick Karwoski, Paul Russell
Working on getting the essential
elements of the Hanford 4 km PSL ready to ship to the site.
We have begun testing the pre-mode
cleaner circuit boards.
A test fixture for the VME-based
boards has been built and is in use on the Frequency Reference Card.
The test fixture for the Photo-diode
Boards will be operational tomorrow
The Reference card has undergone
a full end-to-end functional test.
Testing of internal signal paths
has started. We will document readings for Acceptance Test Procedure documentation
which will follow.
Preliminary testing of the photo-diode
boards
will start tomorrow.
ISC
Rich Abbott, Flavio Nocera,
Mohana Mageswaran
Mode cleaner servo is being
stuffed. Pentek clock fanout boards have been re-ordered and are back in
house after fixing an existing cad error on the current rev. These
boards will be sent to LLO next week to be installed in the LSC by Jay
and Rolf. A full bill of materials is being prepared for the LSC
system by Flavio.
Modulated OSEM Design
Jay Heefner
It has been verified that
we can run the current PDs used in the suspension in photovoltaic mode.
This will allow us to use a differential amplifier configuration on the
input of the satellite amplifer, thus making the system more immune to
induced emi. This mode of operation does not degrade the sensitivity nor
does it appear to have any effect on the upconversion of scattered light
to the LED modulation
New OSEM Heads
Janeen Romie
Dennis and I will meet with
Progressive Technology's subcontracted plating company, Macro Metalics,
on friday to examine their prototypes and to test the surface finish of
the production parts from Progressive Technology. Buying parts for production
assembly.
Peter Fritschel
OSEM head plating: we have
decided to do a test plating run of a handful of the new alumina heads
with Rapid Prototyping Corp, in Longmont, CO. The plating material will
be zirconium nitride, which offers good wear, sliding coefficient of friction,
emissivity (~0.3) and resistivity (>200 ohms/square) characteristics. This
test run should take place early next week.
Digital Suspensions
Jay Heefner
Universal dewhitening boards
for the 4K have been tested and are ready for installation. Anti-Image
boards are also complete.
LOS coil driver and LOS Bias
modules are being stuffed.
Data Monitoring Tool
John Zweizig
This week I have been preparing
for and participating in the E2 Run. There was an enormous amount of setup
work for the data monitoring. I have also produced a bunch of documentation
on how the monitors are used by shift workers and on shift procedures.
Data Acquisitions System
Sander Liu
1. In the process of ordering parts for 12 new chassis.
2. In the process of obtaining quotes for circuit board assembly from Accu-Sembly.
3. In the process of obtaining quote for cable fabrication from PalPilot.
Global Diagnostics
Sander Liu
1. Released schematic drawings D000203 to Document Control.
2. Shipped eight (8) signal processors to LHO.
3. Shipped four (4) signal processors to LLO.
2.2 Issues
Concerns
nothing
new
40 Meter Interferometer (Weinstein).
-
STACIS active seismic isolators: We expected the remaining 3 of four STACIS
isolator systems last week; they still haven't arrived, and we are talking
with the manufacturers.
-
Larry Jones has received the grouting plates and cradles that transfer
the load of the stacks to the STACIS isolators; preparation for grouting
has already started, and should be done by sometime next week.
-
Steve Vass and Larry Jones are assembling everything they need to manufacture
the pieces of the 12 m mode cleaner that were not built way back in 1995.
Larry is waiting on quotes from Hyspan for adjustable bellows. CES is making
some of the parts. Steve will order Vacuum T joints, etc, and will clean
and bake everything.
-
Steve Vass measured the height of the mode cleaner seismic stack built
in 1995. On it's table, it totals 36", which is exaclty how high it should
be; BUT, Steve and Larry feel it should be a bit lower, to allow for some
adjustment when all the parts are in place. So Steve will cut off some
of the table leg length.
-
The newly manufactured output optic chamber seismic stack and associated
in-vacuum hardware has been sent to Allied for cleaning and baking. Allied
noticed damage to two of the vacuum bellows. Fortunately, we have spares.
-
Dennis Ugolini is at Hanford this week. He finished up most of the EPICS
code for the vacuum control system, including interlocks, before he left.
-
Ben Abbott: The wiring for the vacuum valve control boxes is completed,
but not tested as yet. Cables from these boxes to the valves, and to the
control crate, should be coming in tomorrow and the wiring can be begun
soon.
-
AJW, Ben, Rick, Jay, and Rolf have begun to lay out the computer network
and 40m control room layout. Configurations for consoles and monitors are
being fleshed out. Ben will draw these up in Protel.
-
Ben and Rolf are also working on the DAQ rack layout.
-
Jay Heefner, with Ben and Rick, are ordering racks, crates, and VME boards,
representing some significant fraction (maybe 15%) of CDS for the 40m.
-
Rick Karwoski has been working on the PSL. He and Peter will hopefully
firm up a plan for installing a PSL at the 40m lab in stages during winter
2001.
-
Rick and friends will keep an eye on what the contract electricians are
actually installing at the 40m, and then determine what remains to be done
to ensure clean and isolated power to the CDS racks, free of ground loops,
EMF, and other electronic noise sources.
-
AJW continues to work on the budget for FY01, FY02 for the 40m, with help
from Phil Lindquist and Florence Kaufman.
-
AJW has been asking all people who have made purchaes against the 40 meter
accounts to please inform him of which items on the list of all expenditures
originated from them. Florence has been helping with this.
Thermal Noise Interferometer (Libbrecht).
Electronics for locking the test cavities is mostly complete, with only
minor finishing touches to be made. There are still lots of cables
to be made and installed.
We balanced and aligned the second test cavity, and spot glued the wire
standoffs to preserve this alignment. Sensor/actuator heads are installed,
but not plugged in.
LASTI (Zucker).
LASTI (MacInnis, Mason, Smith, Kruzel, Shoemaker, Zucker)
Seismic installation: Installation of seismic supports in HAM20 (left
end) is now physically complete and bellows have all passed leak check
(after re-torquing; we discovered a broken torque wrench with our leak
detector!). Backfilled and removed door for final leveling/shimming
tomorrow (Thursday) morning. Some parts for the cleanroom on the
last HAM, HAM21 (right end) are still stuck at the manufacturer so we are
going to finish installing the BSC support piers before finishing off the
last of the HAM's.
Vacuum equipment: We now have a second QDP80 roughing pump courtesy
of Allen Sibley at LLO; this is being installed to allow us to rough to
turbopump range within a single shift. We tweaked up our interlock setpoints
and tested the gate valve closure system, so the system is now qualified
to run unattended. Letting it go for approximately 100 hours we reached
2e-6 torr. A rate-of-rise test indicates the outgas rate (presumed
mostly water) is not unreasonable for this time under vacuum, of order
2e-10 tl/s/cm^2 (note there is a stack in one HAM), but taken with the
above base pressure this indicates a mysteriously low turbopump speed (~100
l/s vs. nominal 1000 l/s expected). No impact on the program, but
a head scratcher.
Instrumentation: Rolf and Jay released PO's for major parts of the DAQ
and GDS systems (Racks, VME processors, reflective memory modules and VME
crates have been ordered for the initial DAQ systems for LASTI. --Jay)
Cleanrooms: started brainstorming in earnest on the BSC cleanroom concept
for LASTI. Our latest idea is to tie into our accursed roof support columns
to hold up the cleanroom fan/roof assembly without any legs to the floor.
This allows the roof to support higher loads without deep trusses (e.g.,
to accommodate the "doghouse" suggested for the cartridge SEI installation
technique) and removes all floor-level obstructions except for curtains.
LASTI (Janeen Romie)
Updated the SOS drawings to the LIGO I as-built configuration.
Submitted the drawings for the machined mechanical parts to CES for LASTI's
two SOSs. Continuing procurement of osems for suspensions.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling
(Week of Nov 9)
<2e2>
This week, Hiro worked at Hanford, participating in E2 run shifts. First
night, he studied the correlation of the darkport DC output and the break
of locks.
With the help of Matt, Hiro has set up three directories each of which
simulates one of the 3 configurations of LHO 2K IFO, one for one arm, one
for recombined and the last the full power recycling configuration. This
needs a newer version of modeler/modeler_freq so that the simulation code
uses the latest LSC servo code. Hiro built one including the latest code
changes done by Tavio for speed improvements.
Hiro also worked with Rick about the issue of the PSL table motion and
doppler effect size estimation. The vertical motion was mistakenly used
to estimate the effect, and the prediction came out 10 times larger. Details
will be covered by Rick.
<Adlib>
Hiro (hopefully) fixed the problem of the primitive mirror with curvature
mismatch. There still is discrepancy between the simulation with primitive
optics and summation cavities. Biplab is working on this. He modified and
cleaned some parts of the code.
In order to generate proper noise curves from Han2k model, Biplab is
testing matlab codes for calculation of power spectral density and the
time-series data generated by E2E's digital filters especially when those
deal with very steep transfer functions (e.g. seismic noise).
Tavio worked with Matt to define the strategy to implement threads in
the e2e simulation code. Matt is writing a code of modeler to make it easy
for Tavio to implement threads in e2e. Tavio is cleaning and finalizing
the idea before he start the coding.
<Alfi>
Ed Maros focussed on closing several problem reports for alfi. Bruce
Sears is working on moving some infrastructure code from Alfi to ALParser
in order to make it more generally available. This is necessary for the
solution of the cyclic include problem. This will increase the utility
of the transferred methods in general as well.
(Week of Nov 2)
LHO
Biplab stayed last week at LHO and worked with Rick on PSL noise study.
I investigated, with Rick Savage, the effect of Doppler shift of laser
due to table motion wrt the suspended mode cleaner and reference cavity.
We tried to counter the effect by reversing the entry of light into the
reference cavity of Han2k. It could not improve the frequency noise (especially
the peak at 50Hz which has a strong coherence with the table motion) much.
Rick and others also added metal plates to the table legs, which helped
in eliminating the 50Hz peak at the cost of a broad 80Hz peak. [Details:
see LHO part of weekly]. More investigation going on.
Matt Evans is working this week for the improved lock acquisition.
Simulation code
in-lock state noise
Biplab is trying to generate Han2k In-lock state noise curve. He is
facing some problem in FFT calculation when the amplitude of noise varies
much over frequency range (e.g., seismic noise) and is expected to generate
a steep spectral density.
3D mirror
Hiro discussed with Mark Barton discussing about the modeling of suspended
mirrors. Based on this discussion, 3d mirror will be implemented following
the design document by Jay (T980043). This will be integrated into a modified
version of Han2k simulation code. The calibration process will be skipped,
but in stead for now, expected variation of inbalances of the sensor and
actuator after calibration will be artificially included in the simulation
model parameter.
Speed improvement
Tavio Dangelis has started to work on the implementation of thread
in the simulation engine. He wrote a simple program to understand the implementation
of thread on SUN. After that research is over, he will look into
the details of the simulation code and design the implementation of thread.
alfi
Ed and Bruce are working to improve the stability of alfi. Almost all
the major issues are addressed, except for the timing issue (proper updating
of drawing and saving files). Code cleaning is also going which will also
improve the stability.
LIGO Data Analysis System
Software Systems (Blackburn)
Week of Nov 9: In middle of E2 run; will be provided next week.
Week of Nov 2:
This week focused on testing of the LDAS software to be used in the
engineering run. The testing identified two classes of bugs, those that
had to be fixed for the E2 run and those that could be left for after the
CVS tagging. It required roughly two days of testing after necessary bug
fixes were implemented to be sure that the fixes didn't introduce new bugs.
The remaining open bugs are in the problem tracking system and a text version
of these will be made part of the LDAS distribution.
The documentation for the wrapperAPI and mpiAPI were enhanced this week
to include information needed to support the event- MonitorAPI's functional
requirement to correctly insert event data into the LDAS database. In addition
the code modules for the wrapperAPI needed to handle the process and processparam
tables was started.
A couple of master-slave flow control problems were identified in the
current version of the wrapperAPI. Masha and Kent worked on a solution
to this problem which results from the current model of the slave running
with individual decoupled while loops. The work around was discussed in
the weekly mpiGroup meeting and will be implemented and tested in the next
week. Work on a DSO that is compatible with the new wrapperAPI continues
at UWM a problem with the dataConditon() interface was identified by Masha
and reported to UWM. They will have a new version with a fix soon.
The new Unified Data Type class for the dataConditionAPI has been integrated
into a yet to be released version of the dcAPI. New test code based on
this UDT was also started this week.
In an effort to better understand the test failures associated with
the dataConditionAPI, swap space was added to the dcAPI and the full test
suite issued. This resulted in all but 3 out of roughly 550 tests passing.
The remaining three failures are a bit of a mystery, associated with out
of memory errors that were not seen just a week earlier in resample() actions.
It is hoped that a better understanding will develop when the group gets
together next Monday.
An effort was made to produce a user command that would take data from
frames, pass the data through the dataConditionAPI where some algorithmic
processing would occur and then send the results to the database. This
command could only perform two of the three steps in time for the software
release. This sub-command is part of the release and may be useful to the
E2 run but the completed command was not possible in the time available.
Test code was developed to verify a statement found on the net that
GCC was not thread safe in its throwing of exceptions. The code was developed
and tested by Alex. It required running of code for long periods of time
on SMP linux boxes to reproduce the stated bug. Until GCC and Linux come
up with a fix to this problem we run a slim risk of having threaded exceptions
kill an API (primarily the dataConditionAPI).
Finished implementation of tape control gui as per discussion with Greg
last Wed. Tested with Greg at Hanford regarding start up and stop monitoring
of his tape controller scripts. Made gui changes per his request. All working
as of Wednesday afternoon.
Peter Shawhan
My LDAS activities this week have been to do some testing of the system,
and to re-commission the mechanism by which the DMT sends data to the database
(by anonymous ftp). The test data I used to check out this pathway
happened to also reveal the bug regarding the handling of lstrings, though
they are not actually used by the DMT at present, so this is not a critical
issue for the E2 run.
I also researched the "HSI" interface to the hpss system at CACR. In
the near term, access to E2 data will make use of a simple server based
on this interface.
Hardware Systems (Anderson)
(Week of Nov 9)
The electrical work for the LDAS Development system has been completed
at Caltech and now allows for twice the power consumption.
A direct connection from the LDAS networks at LHO and LLO has been reestablished
to the GDS DMT machines over Fast Ethernet now that the LDAS ATM networks
has been replaced with 100/1000Mbit/s Ethernet.
The ATM OC-12 (622 Mbit/s) link between the Caltech LIGO and CACR networks
has been reestablished.
The single LDAS Alpha based computer (sadan) has been upgraded to RedHat
6.2.
The first price quotes for LHO and LLO few-hundred-slot tape libraries
have been obtained.
General Computing
(Week of Nov 9)
MIT
Setting things up for an ILOG system to be installed.
Livingston
Setting up tape backup unit.
Hanford
Setup a few new accounts. Working issues related to the E2 run.
Albert and Larry met with PNNL concerning the increase in bandwidth
for the Hanford site. Presently, the investigation will go in the direction
of getting onto PNNL's OC3 network. It appears to be the most cost affective
solution but there are a number of logistical items that need to be checked
out first.
CIT
(Lisa)
-
Started to set up the new modem pool. We are using 3com Superstack
II RAS 1500 equipment. The base unit needed to be returned because
the vendor shipped us a model that was out of date. It seems that
this is a very popular item and it might take us a while to get a new one
in.
-
I've been working on the Sunpci setup. I'm currently trying to resolve
problems with the networking aspect of it. I am hoping that once
I get past this, I will be able to get p-card running on it.
-
Backed up and installed algol with solaris 8.
-
Fixed Irene's e-mail
-
Installed a CDR for Linda
-
updated some of the applications in pcapps on sirius.
-
got a price quote for Quick Restore. I still need to get them the
device information for our tape robot so that they can write a driver for
it.
-
Ed Chargois got our latest round of surplus equipment taken away.
I have started creating a new sun workstation staging area in its wake.
(Barbara)
I have been catching up with web site changes since being away last
week. Most of the time has been spent on the REU pages and the conference
page.
(Sam)
The ethernet card from Dell arrived. Answered various users questions.
Continued the quest to remain a student.
(Suresh)
-
-Worked with Stuart to create a Permanent Virtual Circuit (PVC) in ATM
switch between two OC-12 (622 Mb/s) ports. This PVC enabled his workstation
(jelly) to have dedicated channel with CACR.
-
-Transferred all the data from one of the external hard drive (4 GB) from
Janeen's workstation (minkar) to RAID5 at sargas after noticing that the
drive was completely filled up. It will be replaced with a new one that
is on order.
-
-Fixed Duncan Brown's account access problem by renewing it for one more
year. Also set up a new user account for a new grad student.
-
-Increased the total Idle time out value of sshd1 config file in acrux.
(Larry)
-
-Resolved a number of PC issues. Worked with Lisa on getting one of the
DCC scanners back on-line. It is no longer supported by HP so it will have
to be replaced.
-
-Working a number of procurement issues.
-
-Tested out a number of scripts for printing out calendar information.
-
-Assisting Christine P. during the E2 run.
-
-Dealing with a couple of budget planning issues. Mainly just getting information
communicated to a number of people.
-
-Setup a new disk partition for LIGO written applications it is /ligoapps
on sirius. It has been propagated to the others servers and should be put
on the client boxes in the near future.
(Week of Nov 2)
MIT
Replacing a broken disk drive to prepare a machine to serve as web server
and ilog home.
Hanford
Larry has contacted PNNL to start communications again on getting more
bandwidth to the Observatory. Lazzarini and Wallace met with PNNL IT staff
to discuss near term and long term solutions. In immediate near term we
will move off T1 and connect the GC ATM switch directly tothe PNNL switch.
We will be limited to 10% of the ATM bandwidth, which is 10x more than
we presently have off the site. Annual cost will be ~$50k, comparable to
the presently negotiated price for the 4xT1 bandwidth. This excursion from
the previous baseline is possible becuase PNNL has installed an OC3 link
to Seattle from Richland.
Livingston
Nothing to report
CIT
(Lisa)
-
Upgraded muscida to Solaris 8.
-
Did monthly backups on all the servers and a few workstations.
-
Installed a PC card in my workstation.
-
Rebuilt jabbah with solaris 8.
-
Put together a list of equipment that needs to be surplused and gave that
to Ed Chargois. That equipment should be picked up on Friday.
Once that equipment is out of the way, I am going to build a staging area
for the Unix workstations in the area outside the server room.
-
I found a sbus ethernet card to use in Luna, but I haven't got it installed
yet.
-
Installed Quick Restore so that I could start my evaluation of it.
-
Spent some hours working with Larry to try and get the HP Scanner in the
DCC to work. The SCSI card it ran off of is bad.
-
I am testing out the CDRW software package that shipped with the 10/00
media of Solaris 8. It seems straight forward but is all command
line driven.
(Sam)
Worked on midterms, homework and became a year older.
(Suresh)
-
-Configured Sun StorEdge D1000 disk array that is attached to system sargas
as RAID5 storage system. Out of 8 disk drives, 7 are used for the RAID5
and 1 for the hot spare pool in case of emergency replacement.
-
-Made an attempt to upgrade firmware for the FORE workgroup switches on
the second and third floors in west bridge. However, due to the old switch
hardware the newer firmware was not supported and had to restore the old
firmware. Larry did replace the processor board of third floor switch with
upgraded firmware.
-
-Installed Windows 98 in Irena's PC. Fixed network connection problem of
her PC.
-
-Set up a new user account for Donald Aram Webber in CDS.
-
-Working with Rita about new version of lsc-all mailing list. She is now
testing from her PC by creating this list.
(Barbara)
On Travel
(Larry)
-
Worked with Jordan C. getting some of his data converted from an old HP
format to a regular ASCII file. Jordan found a conversion program for a
PC (written in basic) and after some hacking around we were able to get
the data transferred and converted.
-
Worked a number of procurement issues. The new plotter should be on order
as well as one of the new SUN workstations. The plan is to let different
users try out the new workstation for a few weeks before we put it in production
replacing one of the old servers.
-
Worked with DCC on a variety of problems. Presently, plan to order another
printer for them and finish the upgrades of one of their PC's. We will
have to order another HP SCSI interface card since the old one no longer
functions.
-
Spent a great deal of time with Suresh getting the 2nd and 3rd floor networks
back on-line. Still waiting for replacement parts for our test unit that
we removed parts from to get things going again.
-
General computer builds and fixes.
LIGO II/Advanced R&D (Sanders)
(Janeen Romie)
LIGO II - Working on updating the schedule and the fabrication portion
of the costs.
(Bill Kells)
-
Melody/FFT comparison work (with Ray B. and Erika A.)
-
Considering the effect of Sapphire OPD distortion on LIGO II performance:
will be commenting on this shortly !
(Helena Armandula)
LIGO Coatings
The Advanced LIGO Coating Development and Preliminary Production Specifications
are finalized. Dennis, Jordan and Gari actively participated with
their inputs. The document has a DCC number and has been placed in
DCC OUT. With this document Irena is completing the RFQ package.
Silicate Bonding
We are in the process of developing a stress test for the silicate bonds
that would allow observing and measuring stress under load. Sheila Rowan
visited last Thursday; we formulated some of the research plans and collaborations
to take place in the future. We (Phil, Sheila and I) are going to
meet with Mr. Ken Bower from Stanford to discuss the low tensile strength
in our hydroxy-catalysis bonds. Glasgow encountered similar problems.
Seismic Attenuation (Riccardo DeSalvo) (10-30 and 11-4)
(Frederick)
Ansys fully operational, starting long simulation program that will
include mirror suspensions and electrostatic actuators. Cabling DAQ for
creep oven, restarted thermostabilization of big oven, ordered 32 channel
differential DAQ card, the old one with 16 single
ended was not adequate. Designing test cuts for Sapphire including
Q measurement diving boards. Measured mini GAS blades, despite
better thickness uniformity of the blades there is still about 10% scatter
of the load carried. We will still need to make many more blades
than necessary and pick the ones that satisfy the load. We should
measure the individual blade's hardness to see if the lift power scatter
correlate with the hardness. Also the better uniformity in thickness
yielded a higher than expected lift power.
Send to Kenji the blades selected if suitable otherwise make a set of
thinner blades.
(ChenYang)
Calculated e.s. actuator electrode, Design sent to Alex for carving.
Designing setup for mirror suspensions.
(Akiteru)
Finished TAMA IP transfer function measurements, reached 80 dB
with and without hanging chain. Disassembled tower to reassemble
in active inertial damping location. Cooked small blades for Kenji.
Testing for shipment. 40 MHz DSP chips arrived from Texas.
And for free!!! 60 MHz version not available but 40 is OK.
Made paperwork for TAMA order.
(Szabi)
Measuring frequency vs. load dependence of TAMA IP. Souping up
oil bearings.
(Virginio)
Finalizing GASF paper for editorial board next week. Started data
analysis of LIGO IP control runs. Assemblying TAMA prototype actuators.
Made order for Tama electronics et al. 4 DSP, ADC,
DAC, 2 VME crates.
For additional information about this report, contact sanders@ligo.caltech.edu