Weekly Report for Week Ending November
2, 2000
The LIGO Executive Committee
Agenda for Monday November 6, 2000 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
-
Announcements
-
LSC Issues (Weiss)
-
Comments on Weekly Report
-
WBS 1 LIGO I Construction (Lindquist)
-
Field Change Orders/Contingency Liens/Change Requests
-
WBS 2 LIGO Lab Operations
-
Administration (Lindquist)
-
Sites (Raab, Coles, Shoemaker, Sanders)
-
Detector (Whitcomb, Coyne)
-
Campus Research Facilities (Weinstein (40 Meter), Libbrecht (TNI), Zucker(LASTI))
-
Data Analysis and Computing (Lazzarini)
-
WBS 3 and 4 Advanced R&D and LIGO II
(Sanders)
Executive Committee only 11:30 - noon
Topics:
Special Items:
Special Announcements:
Weekly
Report Highlights
LSC Issues (Weiss)
no report
LIGO I Construction/LIGO Laboratory
Administration (Lindquist)
WBS 1.2 LIGO Operations--Administration
LIGO Weekly Site Telecon (Lindquist)
A site teleconference was held on Thursday, November
2, 2000. Issues included a reduced bid package for the staging and
storage facility at Livingston, the Manual being prepared for Interferometer
Operations, and discussions held with the Office of Sponsored Research
regarding the mechanism for a no cost extension for Construction funds
into LIGO FY 2002.
The next site telecon is scheduled for Thursday,
November 9, 2000.
The list of current actions revised to reflect
open actions assigned through November 2, 2000 may be found at
ACTION
LIST.
PROPERTY
MANAGEMENT (Chargois)
From: Ed Chargois <chargois_e@ligo.caltech.edu>
-
Assisted the Detector Group (H. Armandula) with the shipment of a Beamsplitter,
Serial Number BS03, valued at $108,122, to the LIGO Hanford Observatory
(D. Cook) via Federal Express 3-day delivery. Account Number P158138.
-
Assisted Equipment Fabrication (F. Asiri) with packing and shipping of
two (2) stainless steel Bellows to Allied Engineering & Production
(M. Kahn) via Federal Express. Account Number P158082.
-
Assisted the Quality Assurance Engineer (B. Tyler) with the return of a
dolly to McMaster-Carr at Santa Fe Springs, Ca, RMA #5031706-01 for
refund. Account Number LIGO 00003-1.5.3-NSFLIGO.000001. The returned item
was received and signed for by McMaster-Carr's representative, Mr. Bowman,
on 10-27-00.
DOCUMENT
CONTROL CENTER (Turner, Mak)
>From: Linda Turner
- turner@ligo.caltech.edu>
Web pages for the
DCC give simple how-to's for document numbering, easy access to the latest
on-line documents, and search capabilities for the DCC database. Take
a look. . .
ACCOMPLISHMENTS
-
During the month of October, we processed
a large volume of incoming documentation. A total of 149 new
electronic documents were made available to the project, while254 documents
were added to the database. Photo activity was hectic with 9 presentation
packages assembled for use. Package handling was also busy as 161
packages were received and 94 were sent out.
-
We made progress auditing and sorting of drawings.
We began with all the drawings associated with Livingston. The Final
Design set of drawings were not on the shelf, and the latest revisions
of the BTE drawings had not been entered into the database. During
the coming week, physical copies will be added for the Final Design and
data entry will be completed on the BTE revisions. This remains a
large project that will take several weeks as time permits. The result
will be new space and less congestion.
-
Processed between 20 and 30 .ppt formatted
presentations, readying them for availability electronically. As
soon as Barbara returns and her testing is completed, both .pdf and .ppt
formats will be available for these presentations. When a search
is done, both formats will appear where available.
-
Work continued on the large pile of process
travelers.
From: Cleveland Mak
<mak_c@ligo.caltech.edu>
Progress is being made on auditing/sorting of drawings. Physical
audit of Livingston As Builts, Construction, Final Design, Bid Set, and
BTE drawings on file were checked. As of this day (there is still
a considerable pile to sort through), all of the drawings were found on
file with the exception of the Final Design Set. A database check
was done as well on these particular drawings, with most already being
in the database with the exception of the latest revisions of the BTE drawings.
These revisions will be added to the database in the upcoming week.
Processed fairly high volume of electronic docs (mainly drawings) during
this reporting period as well.
|
Packages |
Faxes |
| In |
38 |
32 |
| Out |
9 |
31 |
Press here to access
the DOCUMENT CONTROL CENTER
WEB PAGE.
COST SCHEDULE
CONTROL SYSTEMS (Cunningham, Brambila, Akutagawa, Kaufman)
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS
PAYABLE HISTORY DATA.
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
-
Met with Bill Copper on Monday. Spent the begining of the week coordinating
the Washington tax issue with Ed Jasnow. The deadline was met and the check
was cut.
-
Finished up the change orders to CSIRO, MMR, and Richard Price. I
am working on Tradewinds, Brian Loucks, Steve Bell and I still need to
make the internal modifications of expenditure type.
-
Have been placing pcard orders and reconciling transactions.
From: Florence Kaufman <fkaufman@ligo.caltech.edu>
-
Attended meeting with Property Accounting Department regarding preparation
of the property report for NSF and other ssues regarding property.
-
Responded to request from Federal Accounting for budget realignment for
Visitor Program, moving funds within the Award from non-participant support
costs to participant support costs.
-
Began working on the monthly Operations report for October.
SUBCONTRACTS MANAGEMENT (Petrac,
Jasnow)
From: irena@ligo.caltech.edu (Irena Petrac)
-
HYTEC: Estimates for additional support prior to
the contract close out were solicited.
-
Galli&Morelli: Draft PO for TAMA-SAS mechanical
components and associated electronics is in Project Controls Group review.
[We reviewed our approach with the Office of Sponsored Research.
We will be required to establish a separate account for TAMA funds from
which G&M will be paid (See next bullet.)--pel]
-
TAMA: Draft PO (from TAMA to Caltech) for one Mirror
Isolation System (TAMA-SAS prototype) is in Project Controls Group review.
-
Corning: CO No. 03, ordering additional fused silica
material for 40M optics, was released to CIT Purchasing. Advanced copies
were faxed to the contractor to expedite delivery.
-
Heraeus Amersil: CO No. 03, ordering additional fused
silica material for 40M optics, was released to CIT Purchasing. Advanced
copies were faxed to the contractor to expedite delivery.
-
Crystal Systems: CO No. 02 for polishing of LIGO
sapphire crystal samples is in Detector Group review.
-
Advanced LIGO/Optics Coating/RFQ: All inputs have
been received and are being finalized.
LSC/Advanced LIGO: Material for proposal section
on LSC's contributions in support of Advanced LIGO effort is being finalized.
From: Ed Jasnow <jasnow@ligo.caltech.edu>
-
No report this week (See section addressing Construction below.)
Support (Wood)
Dorothy Lloyd
-
Provided total amounts paid on all LIGO contract and blanket orders for
fiscal year 1999-2000 to Acquisitions (Ruth) for DCAA auditors.
-
Continued to work on updating PO logbooks and general filing for Ed Jasnow.
-
Processed the usual requisitions, invoices and receiving on-line. For more
detail, see "Cost Schedule Control Systems" report by Esther Cunningham.
-
Tracked and followed up on invoice problems.
-
Reviewed and recorded payments processed by Esther for the weeks of October
16 and 23, on contract summary sheets and LIGO database.
-
Continue to monitor contract and blanket order funding levels and notify
task managers when supplements are needed.
-
Jim continues to do data entry in the LIGO database and help out in the
DCC.
Irene Baldon
-
Twenty-two (22) new trips were started (including one trip using an old
canceled ticket) and I have thirteen (13) trips pending final approval
before tickets can be issued. I prepared a few Advance Requests and
Payment Requests using the old system due to various reasons that excluded
them from the new system.
-
Worked with a few travelers who had questions or needed further clarification
on using or reconciling their new P-Cards. For the most part those
having cards seem to be doing fine and fine the cards a convenience.
-
The P-Card Expense Report was revised by Michelle Thompson's group, and
I made a few minor change recommendations. My re-revised version
was sent to Michelle for final approval but as of this writing I haven't
heard if it has been accepted. Once this new form is approved it
will go over to Beth Moore's group to be put into FileMaker Pro form.
-
I worked with World Travel Group to clear some outstanding canceled trips
that had tickets that either needed to be transferred to a new traveler
or a credit due from the airlines. These are special cases and since
LIGO is a big ticket user with the airlines involved the airlines are giving
us a case-by-case special credit or exchange. We were able to get
credit on two (2) trips (1 has been received and 1 is still coming) and
the final two (2) trips were turned down. I put through Expense Reports
on these and closed them out.
-
Worked on and completed thirty-four (34) Expense Reports. I have
twenty-nine (29) Expense Reports to work on.
-
Prepared the Travel/Vacation Itinerary for the Week of October 30, 2000.
Performed normal recording and filing associated with Travel and Reimbursement.
Worked on several problem issues with Travel Audit in addition to the above
listed. Also performed miscellaneous duties as requested by various
members of the LIGO Project here at Caltech as well as from members of
the staffs of each of the two (2) sites. I continue to do MIT's
travel to the sites for installation activities and also to assist them
wherever possible.
Rita Torres
-
I was in a Word class for two mornings. When time permits, I will
apply what I learned there to create a LIGO template for letters and memos.
-
FedExed for signature Attachment Z to Dominguez Hills, and Attachments
B, C, D & Z to GEO. Did Change Order No. 3 to Brian Loucks, obtained
an Oracle number for it, distributed the signed requisition. Did
change order No. 3 to Corning Inc. and change order No. 3 to University
of Michigan, also formatted their report from email.
-
Chased various details associated with Pcard purchases. Ongoing activity:
preparing a list to test the LSC email alias, hope to complete by next
week.
Elizabeth K. Wood
-
Spent some time attempting to convert the proposal into a .pdf file.
The error messages we are getting aren’t exactly useful---they tell us
we have an error. So far all we know is that we have one error;
there may be more we can’t get to. Lisa and Larry have been helping
out. It seems that there may be a compatibility problem with Microsoft
Office 2000 and Acrobat.
Advanced LIGO (Frey, Petrac)
From: Thomas Frey <tfrey@ligo.caltech.edu>
Progress Period from 10.27 to 11.02
Accomplishments:
-
Advanced LIGO Project Controls meeting with Gary and Dennis. Focus
on the completion of the Cost Book and Program Plan.
-
Weekly status meeting for Advanced LIGO Proposal Tuesday at 9:30am at SCR.
(Last Meeting)
-
Proposal plan development for Advanced LIGO and Operations continues.
-
Issued data requests for progress data as of 11.03.00 that are due Friday.
-
Progress as of 10.27.00 was processed and posted.
-
Review of cost and schedule data is now ongoing.
-
Prepared plan by system for delivery dates of cost and schedule data to
insure preparedness for NSF review in late January 2001.
-
Project Plan for the 40-Meter Lab Upgrade continues.
-
Issued data requests for progress data as of 11.03.00 that are due Friday.
-
Updated the plan with progress as of 10.27.00. Posted to site.
-
Attended 40-Meter weekly meeting scheduled every Wednesday at 2:30pm.
-
Continuing to push for a CDS procurement schedule.
-
Completed changes per Mike Smith.
-
Planning process for the LASTI project at MIT is in progress.
-
Integration into the program database completed.
-
Followed up with David for any changes and to begin updates.
-
Continue to test the Cost Book Tool.
-
Development of the Advanced LIGO Project Controls Guidebook continues.
Continuing to write section on data dictionaries.
-
Project Web Site for posting schedule and progress related data continues
to be updated with the latest and greatest.
Schedule 11.03 to 11.09:
-
Next weekly meeting will be Monday afternoon November 6 from 1 to 2pm regarding
the planning and control of the Advanced LIGO proposal development.
-
Advanced LIGO Proposal
-
Will begin the effort of contacting each system leader to collect cost
and schedule data. Hope to begin importing schedules and cost this
coming week or next.
-
Will begin to update the LASTI Schedule with progress.
-
Plan to pursue the planning and scheduling of the staging buildings currently
being bid and designed for HLO and LLO.
-
Will continue to update the Advanced LIGO / Ops Proposal Plans and incorporate
any changes.
-
Will post progress report by end of day Tuesday with progress as of 11.03.00.
-
Will issue 17th week of status data to teams.
-
Will continue updating the 40 meter schedule and incorporate any changes.
-
Will post progress report by end of day Tuesday with progress as of 11.03.00.
-
Will issue 17th week of status data to teams.
-
Will finish revisions to WBS provided by Mike Smith.
-
Will meet with Alan on Monday to begin development of 40-Meter experiment
tasks.
-
Meeting scheduled for Wednesday November 8 at 2:30pm at LSCR.
-
Continue to test the Cost Book Tool. Have a meeting with Barbara
K. to discuss the Cost Book and the Resource DB.
-
Cost Book Tool development continues. Will be importing data for
Installation so that Dennis Coyne can proceed with estimating.
-
Will continue the development of the Advanced LIGO Project Web Site.
-
Will continue the development of the Advanced LIGO Project Controls Guide
Book. Finish section on data dictionaries and start on update process.
Anticipated Challenges:
Will not be able to produce a complete / accurate
baseline schedule for the 40-Meter lab due to the lack of planning regarding
the CDS. Per 40-Meter meetings, I cannot expect to receive this data
anytime soon if at all.
Corrective Action:
None to report at this time.
WBS 1.4.1.2 Project Controls (LIGO Construction)
Reports (Lindquist)
Annual Report: There will be an Annual Report
due as of the end of November. I will be requesting inputs from the
usual bunch mid-December after the dust from the proposal has a chance
to settle a bit. I propose to keep this report moderate in size,
about the size and complexity of a Quarterly Report, to minimize the burden.
Change Control/Contingency (Lindquist)
The following Change Requests have
been submitted:
| CR-000018 |
WBS 1.1.4 |
Curbing for Service Roads at Livingston |
G. Stapfer |
| CR-000019 |
WBS 1.2 |
Additional Lab Equipment |
D. Coyne |
Press for the latest Contingency
Needs Projection.
COST SCHEDULE CONTROL SYSTEMS (Duncan,
Akutagawa)
From: Kris Duncan <kris@ligo.caltech.edu>
-
Completed the September 2000 CSSR, rebuilt indexes
and advanced calenders in COBRA (in hopes that it will be up and running
again).
-
Incorporated CR-000017 ($200K) into the Performance
Measurement Baseline (PMB) for the A&E work to modify the staging building
at Hanford.
-
Began calculation of earned value for month end October
2000.
-
Continued transferring data from the COBRA format
into Excel spreadsheets.
-
Continued with construction contract/work package
close out.
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
-
I am working on gathering the details for the monthly
reports on the Construction and Advanced R&D accounts for October 2000.
I will email them to the Task managers as soon as I have completed them.
-
Continue to reviewed the open encumbrances on the
Construction and Advanced R&D accounts to see if the requested removals
have been made. I will continue to review these accounts weekly until all
encumbrances have been removed.
The financial reports on the web provide supporting
detail.
http://docuserv.ligo.caltech.edu/~fireport
http://docuserv.ligo.caltech.edu/~finance
SUBCONTRACTS MANAGEMENT (Petrac,
Jasnow)
From: Ed Jasnow <jasnow@ligo.caltech.edu>
As a result of the high bids received on October 19 for the Livingston
Staging Building, it has been decided to scrub the design and specifications
for errors, and re-examine the scope to see if some items can be deferred
to a later time. Since all four of the bids received were very close
to each other, we will be issuing a revised solicitation package to all
four bidders on November 15, and open their revised bids on November 30.
On October 25, Ruth Brambila and Ed Jasnow met with auditors from the
Washington State Department of Revenue to discuss LIGO's obligations for
use tax. The supervising auditor, Ms. Rhonda McKnight, stated that
she feels that under the special legislation passed for LIGO, all materials
and supplies purchased for the laboratory related to scientific or engineering
work are exempt from sales and use tax. This is a far more liberal
interpretation of the law than we have ever received. Under this
interpretation, LIGO will receive a substantial credit for sales tax previously
paid. Using this guidance, and with the hard work of Ruth Brambila,
Esther Cunningham, and Michelle Thompson, we were able to file our quarterly
tax return to the State of Washington on time. LIGO owed $1,551.24
in use tax for the third quarter. Additionally, there is over $2,000
in sales tax that we can recover from various vendors.
From: irena@ligo.caltech.edu (Irena Petrac)
-
No report this week; see Operations Section above.
Quality/Safety (Tyler)
>From: Bill Tyler <tyler@ligo.caltech.edu>
-
Supported discussions with Gary Sanders regarding questions/concerns about
LIGO safety activities. A major topic of discussion centered on the recent
forest fire incident at Livingston, LA. It was agreed at this meeting
that Cas Scislowicz would discuss this incident and the local emergency
system response with the risk management personnel for recommendations
regarding the site emergency response plans.
-
Supported weekly telecon and discussions for 24/7 operator plans and safety
issues.
LIGO Hanford Observatory (LHO) Operations
(Raab).
General Items:
--------------
(F. Raab)
Getting ready for E2.
PreStabilized Lasers:
--------------------
(M. Guenther, T. Mahood, R. Savage)
-Mirror mount resonances:
M. Landry and B. Butler have completed optical mount resonance
measurements. In a nutshell, they recommend that we avoid using
the New
Focus hold-down forks and screw directly to the table with
several screws per mount. They also recommend using the Newport
U100
mounts as a first choice and the Klinger mounts as a second choice.
Based upon their findings, we've designed new monolithic, bolt-down
aluminum mounts to support both Newport U100 and Newport SL25.4 (AKA
"Klinger mounts") mirror mounts. We've continued the concept and
designed similar mounts to support our polarizing
beam splitter cubes. These new mounts are presently out for
fabrication.
-Optical table legs:
R. Schofield identified the optical table legs as the source of a broad
peak in the PSL frequency noise spectrum centered around 50 Hz.
We plan
to replace the six legs now being used with three fixed-height legs
after the E2 engineering run (see below). In the meantime, we
are
attempting to reduce the noised induced by the present legs.
We
fabricated 3/4" thick steel disks with slots that allow them to be
bolted to the bottom of the legs using the existing lock nuts.
After
bolting the disks to the legs, the broad 50 Hz peak shifted to about
80
Hz at slightly higher amplitude. The narrow peaks in the spectrum
around 50 Hz were significantly reduced in amplitude. We
have procured
some Dyad material that we will install between the bottom of the table
legs and the steel plated in an effort to reduce the amplitude of the
80
Hz peak.
The design of the new PSL table legs has been completed, and we are
awaiting the delivery of aluminum for machining them. The legs will
initially be tested on the 4k PSL as a way to reduce a 50 Hz (now 80
Hz)
resonance that has been observed. If successful, the design will be
applied to the 2k PSL after the upcoming engineering run is over.
-Frequency noise:
As reported last week, e2e modeling (carried out with B. Bhawal)
supported a hypothesis that optical table motion relative to the
suspended (and therefore isolated) reference cavity and modecleaner
was
causing differential mode doppler shifting because the beams entering
the two cavities were oppositely directed. If this were the source
of
the noise, we expected that it would be reduced if the reference cavity
were to enter from the other end so that the Doppler shift
would be
common mode. With the help of S. Whitcomb and R. Graff, we redirected
the input to the PSL reference cavity so that it was incident from
the
opposite direction. Surprisingly, we observed almost no change
in the
frequency noise in this new configuration. We are now trying
to
understand why.
-Fast channels
We are verifying calibration of PSL fast channels to be used during
the
engineering run. The channels are: H2:PSL-FSS_FAST_F,
H2:PSL-ISS_ISERR_F, H2:PSL-PMC_ERR_F, H2:PSL-PMC_PZT_F, and H2:IOO-MC_F
(really an IOO channel)
-Electronics:
The cross-connect for the 4k PSL has been fabricated and wired, and
is
ready for installation pending a final approval of the layout plans
from Caltech. The Eurocrate backplane has been wired and
is also ready
for rack installation.
-Engineering run:
We are planning to monitor PSL frequency glitches during the upcoming
engineering run. We will also look for intensity glitches, although
without the intensity stabilization servo we will likely not have much
sensitivity.
LIGO Livingston Observatory (LLO) Operations
(Coles).
OPTICS/COC/SEI INSTALLATION: The bellows replacement and realignment
of ETM-x is completed. We've staged everything at the Y-end, and resurveyed
all of the IAM monuments. Allen suspected a leak in the annulus if the
dome on BSC-5, so we removed it and found a pinched O-ring. We've replaced
it and are in the process of refitting the dome this afternoon. We'll setup
the IAM instrumentation tomorrow and begin the realignment of ETM-y thereafter.
Held a Laser Safety Quarterly Walkthrough Monday, and have been obtaining
quotes and issuing Purchase Requisitions of the additional Commissioning
equipment for LLO. (Jonathan Kern)
ISC (from Anthony Rizzi): Due to IOISC reboot, we lost pzt position
(input beam alignment).
Sany and I reestablished pzt location (new bias settings: M1 pitch:
.488 yaw: .16 M2: pitch .08 yaw: .26 ). We then
reestablished mode cleaner lock. We installed camera on roof of HAM1
using gimble mount done by Sany. We located both input
and returning beam on MMT1's baffle and adjusted. We had previously
verified presence of input beam by moving SM1 and
observing the beam move (and no motion of it when MMT's moved), we
now moved MMT2 until the return beam moved into hole. We
were aided in this by slight mirror oscillation that we still have
to understand (probably due to non-optimal suspension control
settings). We then saw both the low power beam we had been seeing along
with a much higher power beam out of the Faraday
port. The low power beam did not swing but the high power one did.
We are now investigating a large oscillation problem in the Recycle
Mirror that started at the end of our observation. Once the beam is
stable we will be able to make final periscope height determination.
We recorded the settings of suspension controls that allowed us to
see the high power beam; they can be found in an e-log entry that
Sany will make today (11/2).
Detector/Technical Support (Whitcomb,
Coyne).
1.1 LHO
INSTALLATION & COMMISSIONING
2km Commissioning
Matt Evans, Stan Whitcomb, Josh Myers, Richard McCarthy,
Nergis Mavalvala
We locked a non-power-recycled interferometer
this week. To do this Matt added some more code. We have performed some
diagnostics in this configuration. Among other things, we measured the
displacement sensitivity to be 1e-15 m/rtHz with a minimum at a few hundred
hertz. Between 40 and 90 Hz laser frequency noise still contributes to
the differential mode signal.
We are now performing calibrations to attempt
full interferometer locking.
We also began to set up the wavefront sensing
system, which has undergone a few modifications since the one arm test.
We are still trying to make sense of the signals measured on WFS1
using a single arm cavity. Rolf is helping us with some missing ASC test
points.
Bill Kells
Work on modeling (e2e simulations) Han2k full
locking behaviour.
PSL
Peter King
The PSL frequency noise
was measured with the suspended modecleaner. Comparison with the previously
measured frequency noise spectrum shows that for frequencies below approximately
500 Hz, the performance was degraded. Above 1 kHz, there was a small improvement
in the spectrum up to approximately 8 kHz. Roughly speaking the frequency
noise is a factor of 6 over spec. above 1 kHz and a factor of 8 over spec.
below 1 kHz. This measurement may have been affected by non-optimal
modecleaner servo settings. Although the modecleaner servo gain and
bypass gain were adjusted to yield the best spectrum.
Observed in the modecleaner
servo "PSL Out Mon", the control signal to the VCO, was a constant ~200
mV DC offset. In addition a large number of high frequency peaks
were present, which were also found to be present in the modecleaner transmitted
light. For reasons I have not figured out yet, the modecleaner servo
unity gain frequency could not be pushed higher than about 22 kHz.
The modified current shunt
was installed into laser #103. A quick test of the shunt verified
that it was functional.
The intensity noise of the
modecleaner transmitted light was measured. Numerous peaks were observed
in the transmitted light, the first at approximately 13.6 kHz. This
peak was not present in the pre-modecleaner transmitted light noise spectrum,
nor on the light after the three Pockels cells in the IO optics chain.
Tuning of the LSC photodetectors
is about to start, after some delays because of other tasks that needed
to be completed.
Lee Cardenas
Designing a mounting block
to hold the pre-modecleaner. The block should kinematically locate the
pre-modecleaner body.
DAQ
Rolf Bork, Dave Barker
Completed frontend data
acq code port to Pentium. This seems to be able to handle full 5
ADC boards (160 channels), plus incorporates moving avg. filtering.
Present MIPS units only handle 2-3 boards and do not yet have moving avg
filter. We may want to change out the LVEA multi-MIPS units and replace
with single Pentium, particularly since we seem to have occassional sync
problems in these multi-CPU frontends (noticed by Daniel and being checked
by Dave today).
Trying to help Dave with
EPICS data collection in light of the increased number of channels and
rates in support of the second engineering run (E2). The numbers
may dictate using multiple CPUs to collect this data, and I am working
on how to do that. I should have some code ready by later today.
IO
Dave Reitze
David Ottaway and Betsy
have measured the ellipsity that is imposed on a beam reflected from a
Brewster angle polarizer. The value is 0.87. Another point about such polarizers
is that when light in the rejected polarization state is incident on such
a polarizer about 25% is reflected off the input polarizer's entry window
(Simple Fresnel Reflection). As this is reflected straight off an air/calcite
interface it is reflected without becoming elliptical, perhaps this
could be used for the wavefront sensing. Could also possibly use AR coatings
for s-polarization.
A stand for the Faraday
isolator was shipped to LHO this week.
LIGO-TriNet
Szabi Marka
We set up the Quanterra
4128 datalogger with Bob Busby, Dave Johnson and Mike Watkins of the CalTech
Seismological Lab. Thanks very much for their help! It is now able to send
packets to TriNet and to LIGO hosts. I still have to work on our reception
code. The full setup including sensors and electrical system (except battery
and fiber converter) is being tested at the Kresgee Seismological Lab.
Upon successful outcome I will transport the system to LHO and set it up
in one of our buildings until the vault is completed.
RF Frequency Distribution System
Rich Abbott
A mockup of the LHO Frequency
dist. system has been constructed. A test of before and after the
modifications to cure the RF radiation problem is being performed.
1.2
LLO INSTALLATION & COMMISSIONING
RF Frequency Distribution System
Rich Abbott
Installed and commissioned the frequency distribution system for LLO.
We added the necessary components to cure the RF radiation problems as
proposed for LHO
2.0 Other
Engineering and Scientific Activities
2.1 Design/Analysis/Fab
Optical Metrology
GariLynn Billingsley, Helena
Armandula
Analysis of the BS03 data is complete. The optic will ship to
Hanford this week . Since the Beamsplitter measurement setup is difficult,
we took the opportunity to
survey the two spare Beamsplitters, BS04 and BS05. A summary
of the optical sag is shown below. The sign convention indicates that the
coated BSs are all convex.
Specification: 7 nm > Surface 1 sagitta > -25 nm
| Optic |
Coated(CIT) |
Uncoated(CSIRO) |
Notes |
| BS01 |
-36 |
-10.3 |
Hanford 2K |
| BS02 |
-28 |
-6 |
Livingston 4K |
| BS03 |
-15 |
3 |
Hanford 4K |
| BS04 |
-27 |
-20 |
|
| BS05 |
-14 |
0.2 |
Mottled surface |
BS05 was found to exhibit similar markings to those found on two of
the 4ITMs and one SPETM (ie: optics from both polishers.) The exception
is that instead of
streaks, which appear on the other optics,BS05 exhibits spots.
The depth of the features are consistent on all of the optics at ~6-10nm.
These features have been found on both coated and uncoated optics and have
affected 10% of the LIGO optics. There has been some speculation
that the marks are due to the cleaning process, but we have been unable
to induce any changes on the one uncoated optic which is streaky.
We have attempted to change the optic by using reasonable variations in
the cleaning process. Both polishing companies have been questioned
about this effect, both have seen the effect, neither GO or CSIRO
know the cause.
PSL
Peter King
-
For the past few months I have
been trying to find another source of super polished fused silica substrates
other than General Optics. Recently I was told that a company in
Mississippi might be able to provide super-polished substrates. Apparently
they have polished some and are getting the samples tested/verified.
Lee Cardenas
-
Measurements of performance
data on the Laser Mopa S/N 107 completed and checked daily. Installation
of a new EOM(Pockels Cell) on the laser, alignment and power optimization,
Free-space propagation and M-squared measurements is in progress.
-
I have received from Lightwave
Laser Mopa S/N 110. This Laser will replace the one which is
on now. Laser MOPA S/N 107 will be sent to LHO.
Rick Karwoski, Paul Russell
To provide the basic light
source to Hanford we are concentrating on building and testing the three
pre-mode-cleaner boards. Thus far we have completely
stuffed: 2 ea. PMC Servo
Cards, 2 ea. Frequency References We will begin stuffing the Photodetectors
this week. In parallel and in support of the built/test effort we
are building up our new lab. The test equipment we will
need for testing PSL modules
has begun to arrive.
ISC
Mohana Mageswaran
Both the boards(MC Servo
and Elliptic Filter) have been sent out for fabrication, and expected to
get back them by next week. I will start testing the next generation MC
Servo Boards soon.
Rich Abbott
We are doing an inventory
to determine what to order for the remaining LSC components (Pentek clock
fanout boards are certainly needed)
New OSEM Heads
Janeen Hazel-Romie
Peter Fritschel has found
a prospective plater in Colorado. Progressive Technology may also have
a subcontractor that can provide a satisfactory plating job for us. Trial
runs will be made by both before one is chosen. A visit to a die cutting
company this afternoon who bid on the PFA 440HP connectors ws disappointing.
Since we have enough PFA 440HP parts already on-hand for the 4km LHO interferometer,
we will have the balance of parts made by the CIT shop.
Data Monitoring Tool
John Zweizig
This week I have continued preparations of the DMT software for the
coming engineering run. I have written a new monitor that looks for
the data acquisition errors seen in the first engineering run where a 1/16th
second slice of data is replaced by data from the same channel from about
1/4 second later. The monitor also looks for other basic problems like
frames that are not aligned with the GPS second or are not 1 second long.
A trigger is generated whenever one of these conditions is discovered.
In addition to developing the new monitor I have installed monitor code
contributed by several LSCDC working group members and run a test of trigger
recoding into the LDAS meta-Database.
DAQ Antialiasing Filter
Sander Liu
DAQ Antialiasing Filter
Chassis - In the process of ordering parts to build six more BNC
and six more LEMO chassis.
Global Diagnostics
Daniel Sigg
-
Most of the time spent with E2 preparations.
-
The 1TB RAID5 system on fortress has been used heavily for test purposes.
No problems so far.
-
The diagnostics software on fortress has been updated. The rds script now
supports multiple writers as long as they are writing to different locations.
Sander Liu
-
Dave Grimmett has finished building
and testing one chassis. Will start to ship the units to the field in the
next couple to weeks.
2.2 Issues
Concerns
nothing
new
40 Meter Interferometer (Weinstein).
-
HRH Prince Andrew, the
Duke of York visited the 40 Meter Laboratory on Thursday (picture),
and got the LIGO spiel from Kip Thorne and Alan Weinstein. He asked lots
of questions and seemed to have a good time. Also in attendance was one
of his subjects, Sheila Rowan of Glasgow, who explained that the GEO detector
will have comparable sensitivity to LIGO, despite its far smaller price
tag.
-
AJW presented the proposed optical configuration for the 40m upgrade LIGO
II prototype. Transparencies here.
Comments welcome!
-
At long last, quotes are in from both Corning and Heraeus for suspended
optic blanks. Gari is preparing a PO for all suspended optics, plus spares,
to go out this week.
-
Fred Asiri reports that Caltech has the 40m re-roofing job on their list,
and will tell us when they'll do the job, within the next two weeks. Special
attention will be paid to all roof penetrations and joints, where the leaks
come in. The rains have already started!
-
Fred Asiri reports that all new, in-vacuum parts for the output optic chamber
(seismic stack, bellows, etc) have been shipped to Allied for cleaning
and baking, and should come back in ~ 6 weeks.
-
Steve Vass and Fred Asiri have been monitoring the ongoing electrical and
cable tray installation work, and it seems to be satisfactory. The cable
tray work should be complete in the next week.
-
Fred continues to await word from Physical Plant on suitable and available
isolation transformers for the 40m lab.
-
STACIS active seismic isolators: Larry Jones reports that the manufacture
of the support brackets and grout plates is somewhat delayed. He hopes
to get grout plates within the next day or 2, at which time, he and Steve
Vass can grout them to the floor around the test mass chambers. The STACIS
pedestals sit on these flat, level plates.
-
We expect the remaining 3 sets of STACIS isolators to be delivered by the
end of this week.
-
Steve Vass has gone over the pieces required to assemble the 12 meter mode
cleaner vacuum envelope and seismic stack. He has discovered that many
key pieces of hardware were not manufactured. This includes the end chamber
seismic stack support beams and vacuum bellows, seismic stack bottom plate,
adjustable bellows for the beam tube, etc. He and Larry Jones are assembling
the drawings for these pieces, and Larry is having them manufactured by
CES and Hyspan. Steve will measure the seismic stack height, in order to
determine the thickness of the bottom plate needed to get the top table
of the stack at the same height as the rest of the 40m optical tables (36"
off the floor).
-
Dennis Ugolini has written and tested all the software (non-critical) interlocks
for the vacuum control system. Ben Abbott has wired up all of the remote
vacuum valve control boxes, and he and Dennis are ordering cables to run
from the vacuum control rack to the remote boxes, and thence to the vacuum
valves themselves.
-
Dennis Ugolini is moving all the code for 40m DAQS, EPICS, VxWorks, etc,
to local 40m machines. All exectuables are already there, but Dennis has
been compiling and linking VxWorks executables on kater. We want to be
able to do all that on local machines.
-
Rolf, Dennis Ugolini, AJW, and Larry Wallace need to meet and agree on
the computer networking at the 40m.
-
Rick Karwoski has been working on the PSL's for Hanford 4K, 40m, and LASTI.
-
Rick, Jay Heefner, Rolf Bork, and Ben Abbott have been preparing an order
for racks, crates, and some fraction of the VME boards (CPUs, ADCs, reflective
memory, etc) needed for the CDS for the 40m. Orders will go out this week
(along with similar stuff for LASTI).
-
Tom Frey, AJW, and any other interested parties will meet on Monday to
develop the 40m "experiment" schedule, in Primevera.
Thermal Noise Interferometer (Libbrecht).
We are still making progress on our test cavities. The physics
shop milled
the front panels for the NIM boxes for our satellite amplifiers, and
we cut
the holes in the back panels for the input and output connectors.
We
expect to have at least one working unit by the end of today (Thursday).
We
are still making cables, lots of cables, to carry the signals between
these
satellite boxes, the sensor/actuator heads, and the OSEM controllers.
We have balanced and aligned one test cavity, and we applied epoxy to
the
wire standoffs to preserve this alignment. Diagnostic-optics
mounts have
been cleaned and placed in the chamber, but optics have not yet been
installed.
LASTI (Zucker).
Seismic isolation installation (Zucker, Mason, Smith,
McInnis, Kruzel, Radkins, Grey.)
-HAM13: Completed 10/26/00
-HAM21: The clean room has been positioned over HAM20 and the doors
removed.
The support tubes and support table have been installed and leveled.
We are currently installing bellows.
-HAM20: Still waiting on a couple miscellaneous small parts. We will
finish and leakcheck 21 and come back to 20 when they come in.
-BSC0: Mounting holes are marked;
we will start drilling for the support pier anchors
as soon as HAM21 is buttoned up for leakchecking (~ Friday).
Electronics: DHS, MZ and KM reviewed electronics rack size
and placement with Jay Heefner and Rolf Bork. They have
the green light to procure the DAQ/GDS infrastructure equipment
(plus suspension controllers for the first phase).
Data Analysis and Computing (Lazzarini)
No report received.
LIGO II/Advanced R&D (Sanders)
Bill Kells:
1. Helped Jordan finish sapphire test mirror birefringence studies.
Written up in paper draft. Also obtained crude measure
of
Rayleigh scatter in same test substrate.
2. Further MELODY-FFT cross comparison runs. This work is stalled at
a
disagreement cum interpretation issue with Ray B. Note
that already
a couple of MELODY version patches have resulted from
this work.
For additional information about this report, contact sanders@ligo.caltech.edu