Weekly Report for Week Ending November 2, 2000


 Exec. Comm. Agenda
Highlights
LSC
Administration
Hanford Observatory
Livingston Observatory
MIT
Caltech
Detector
40 Meter
TNI
LASTI
Data Analysis
LIGO II/Adv. R&D
Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  November 6, 2000 will be:
 (Meeting time: 10:30 am Pacific Time)

Open meeting 10:30 - 11:30

  1. Announcements
  2. LSC Issues (Weiss)
  3. Comments on Weekly Report
  4. WBS 1 LIGO I Construction (Lindquist)
  5. WBS 2 LIGO Lab Operations
  6. WBS 3 and 4  Advanced R&D and LIGO II (Sanders)
Executive Committee only 11:30 - noon   Topics:
 

Special Items:


Special Announcements:


Weekly Report Highlights
 


LSC Issues (Weiss)


no report


LIGO I Construction/LIGO Laboratory Administration (Lindquist)


WBS 1.2 LIGO Operations--Administration


LIGO Weekly Site Telecon (Lindquist)

A site teleconference was held on Thursday, November 2, 2000.  Issues included a reduced bid package for the staging and storage facility at Livingston, the Manual being prepared for Interferometer Operations, and discussions held with the Office of Sponsored Research regarding the mechanism for a no cost extension for Construction funds into LIGO  FY 2002.

The next site telecon is scheduled for Thursday, November 9, 2000.

The list of current actions revised to reflect open actions assigned through November 2, 2000 may be found at ACTION LIST.


PROPERTY MANAGEMENT (Chargois)

From: Ed Chargois <chargois_e@ligo.caltech.edu>


DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner - turner@ligo.caltech.edu>

Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .

ACCOMPLISHMENTS

From: Cleveland Mak <mak_c@ligo.caltech.edu>

Progress is being made on auditing/sorting of drawings.  Physical audit of Livingston As Builts, Construction, Final Design, Bid Set, and BTE drawings on file were checked.  As of this day (there is still a considerable pile to sort through), all of the drawings were found on file with the exception of the Final Design Set.  A database check was done as well on these particular drawings, with most already being in the database with the exception of the latest revisions of the BTE drawings.  These revisions will be added to the database in the upcoming week.

Processed fairly high volume of electronic docs (mainly drawings) during this reporting period as well.
 

Packages Faxes
In 38 32
Out 9 31

Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.


COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Akutagawa, Kaufman)

From: Esther Cunningham <esther@ligo.caltech.edu>

Press here for ACCOUNTS PAYABLE HISTORY DATA.

From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

From: Florence Kaufman <fkaufman@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: irena@ligo.caltech.edu (Irena Petrac)

From: Ed Jasnow <jasnow@ligo.caltech.edu>



Support (Wood)
 
Dorothy Lloyd
  • Provided total amounts paid on all LIGO contract and blanket orders for fiscal year 1999-2000 to Acquisitions (Ruth) for DCAA auditors.
  • Continued to work on updating PO logbooks and general filing for Ed Jasnow.
  • Processed the usual requisitions, invoices and receiving on-line. For more detail, see "Cost Schedule Control Systems" report by Esther Cunningham.
  • Tracked and followed up on invoice problems.
  • Reviewed and recorded payments processed by Esther for the weeks of October 16 and 23, on contract summary sheets and LIGO database.
  • Continue to monitor contract and blanket order funding levels and notify task managers when supplements are needed.
  • Jim continues to do data entry in the LIGO database and help out in the DCC.
Irene Baldon
  • Twenty-two (22) new trips were started (including one trip using an old canceled ticket) and I have thirteen (13) trips pending final approval before tickets can be issued.  I prepared a few Advance Requests and Payment Requests using the old system due to various reasons that excluded them from the new system.
  • Worked with a few travelers who had questions or needed further clarification on using or reconciling their new P-Cards.  For the most part those having cards seem to be doing fine and fine the cards a convenience.
  • The P-Card Expense Report was revised by Michelle Thompson's group, and I made a few minor change recommendations.  My re-revised version was sent to Michelle for final approval but as of this writing I haven't heard if it has been accepted.  Once this new form is approved it will go over to Beth Moore's group to be put into FileMaker Pro form.
  • I worked with World Travel Group to clear some outstanding canceled trips that had tickets that either needed to be transferred to a new traveler or a credit due from the airlines.  These are special cases and since LIGO is a big ticket user with the airlines involved the airlines are giving us a case-by-case special credit or exchange.  We were able to get credit on two (2) trips (1 has been received and 1 is still coming) and the final two (2) trips were turned down.  I put through Expense Reports on these and closed them out.
  • Worked on and completed thirty-four (34) Expense Reports.  I have twenty-nine (29) Expense Reports to work on.
  • Prepared the Travel/Vacation Itinerary for the Week of October 30, 2000.  Performed normal recording and filing associated with Travel and Reimbursement.  Worked on several problem issues with Travel Audit in addition to the above listed.  Also performed miscellaneous duties as requested by various members of the LIGO Project here at Caltech as well as from members of the staffs of each of the two (2) sites.   I continue to do MIT's travel to the sites for installation activities and also to assist them wherever possible.
Rita Torres
  • I was in a Word class for two mornings.  When time permits, I will apply what I learned there to create a LIGO template for letters and memos.
  • FedExed for signature Attachment Z to Dominguez Hills, and Attachments B, C, D & Z to GEO.  Did Change Order No. 3 to Brian Loucks, obtained an Oracle number for it, distributed the signed requisition.  Did change order No. 3 to Corning Inc. and change order No. 3 to University of Michigan, also formatted their report from email.
  • Chased various details associated with Pcard purchases.  Ongoing activity: preparing a list to test the LSC email alias, hope to complete by next week.
Elizabeth K. Wood
  • Spent some time attempting to convert the proposal into a .pdf file.  The error messages we are getting aren’t exactly useful---they tell us we have an error.  So far all we know is that we have one error;  there may be more we can’t get to.  Lisa and Larry have been helping out.  It seems that there may be a compatibility problem with Microsoft Office 2000 and Acrobat.

Advanced LIGO (Frey, Petrac)

From: Thomas Frey <tfrey@ligo.caltech.edu>
 
Progress Period from 10.27 to 11.02

Accomplishments:

Schedule 11.03 to 11.09:
Anticipated Challenges:
Will not be able to produce a complete / accurate baseline schedule for the 40-Meter lab due to the lack of planning regarding the CDS.  Per 40-Meter meetings, I cannot expect to receive this data anytime soon if at all.
Corrective Action:

None to report at this time.


WBS 1.4.1.2   Project Controls (LIGO Construction)



Reports (Lindquist)

Annual Report:  There will be an Annual Report due as of the end of November.  I will be requesting inputs from the usual bunch mid-December after the dust from the proposal has a chance to settle a bit.  I propose to keep this report moderate in size, about the size and complexity of a Quarterly Report, to minimize the burden.



Change Control/Contingency (Lindquist)

The following Change Requests have been submitted:
 

CR-000018 WBS 1.1.4 Curbing for Service Roads at Livingston G. Stapfer
CR-000019 WBS 1.2 Additional Lab Equipment D. Coyne

Press for the latest Contingency Needs Projection.


COST SCHEDULE CONTROL SYSTEMS (Duncan, Akutagawa)

From: Kris Duncan <kris@ligo.caltech.edu>

From: Cindy Akutagawa <cindy@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: Ed Jasnow <jasnow@ligo.caltech.edu>

As a result of the high bids received on October 19 for the Livingston Staging Building, it has been decided to scrub the design and specifications for errors, and re-examine the scope to see if some items can be deferred to a later time.  Since all four of the bids received were very close to each other, we will be issuing a revised solicitation package to all four bidders on November 15, and open their revised bids on November 30.

On October 25, Ruth Brambila and Ed Jasnow met with auditors from the Washington State Department of Revenue to discuss LIGO's obligations for use tax.  The supervising auditor, Ms. Rhonda McKnight, stated that she feels that under the special legislation passed for LIGO, all materials and supplies purchased for the laboratory related to scientific or engineering work are exempt from sales and use tax.  This is a far more liberal interpretation of the law than we have ever received.  Under this interpretation, LIGO will receive a substantial credit for sales tax previously paid.  Using this guidance, and with the hard work of Ruth Brambila, Esther Cunningham, and Michelle Thompson, we were able to file our quarterly tax return to the State of Washington on time.  LIGO owed $1,551.24 in use tax for the third quarter.  Additionally, there is over $2,000 in sales tax that we can recover from various vendors.

From: irena@ligo.caltech.edu (Irena Petrac)


Quality/Safety (Tyler)

>From: Bill Tyler <tyler@ligo.caltech.edu>



LIGO Hanford Observatory (LHO) Operations (Raab).


General Items:
--------------
(F. Raab)

Getting ready for E2.

PreStabilized Lasers:
--------------------
(M. Guenther, T. Mahood, R. Savage)

-Mirror mount resonances:
M. Landry and B. Butler have completed optical mount resonance
measurements.  In a nutshell, they recommend that we avoid using the New
Focus hold-down forks and screw directly to the table with
several screws per mount.  They also recommend using the Newport U100
mounts as a first choice and the Klinger mounts as a second choice.
Based upon their findings, we've designed new monolithic, bolt-down
aluminum mounts to support both Newport U100 and Newport SL25.4 (AKA
"Klinger mounts") mirror mounts. We've continued the concept and
designed similar mounts to support our polarizing
beam splitter cubes.  These new mounts are presently out for
fabrication.

-Optical table legs:
R. Schofield identified the optical table legs as the source of a broad
peak in the PSL frequency noise spectrum centered around 50 Hz.  We plan
to replace the six legs now being used with three fixed-height legs
after the E2 engineering run (see below).  In the meantime, we are
attempting to reduce the noised induced by the present legs.  We
fabricated 3/4" thick steel disks with slots that allow them to be
bolted to the bottom of the legs using the existing lock nuts.  After
bolting the disks to the legs, the broad 50 Hz peak shifted to about 80
Hz at slightly higher amplitude.  The narrow peaks in the spectrum
around 50 Hz  were significantly reduced in amplitude.  We have procured
some Dyad material that we will install between the bottom of the table
legs and the steel plated in an effort to reduce the amplitude of the 80
Hz peak.

The design of the new PSL table legs has been completed, and we are
awaiting the delivery of aluminum for machining them. The legs will
initially be tested on the 4k PSL as a way to reduce a 50 Hz (now 80 Hz)
resonance that has been observed. If successful, the design will be
applied to the 2k PSL after the upcoming engineering run is over.

-Frequency noise:
As reported last week, e2e modeling  (carried out with B. Bhawal)
supported a hypothesis that optical table motion relative to the
suspended (and therefore isolated) reference cavity and modecleaner was
causing differential mode doppler shifting because the beams entering
the two cavities were oppositely directed.  If this were the source of
the noise, we expected that it would be reduced if the reference cavity
were to enter from the other  end so  that the Doppler shift would be
common mode.  With the help of S. Whitcomb and R. Graff, we redirected
the input to the PSL reference cavity so that it was incident from the
opposite direction.  Surprisingly, we observed almost no change in the
frequency noise in this new configuration.  We are now trying to
understand why.

-Fast channels
We are verifying calibration of PSL fast channels to be used during the
engineering run. The channels are: H2:PSL-FSS_FAST_F,
H2:PSL-ISS_ISERR_F, H2:PSL-PMC_ERR_F, H2:PSL-PMC_PZT_F, and H2:IOO-MC_F
(really an IOO channel)

-Electronics:
The cross-connect for the 4k PSL has been fabricated and wired, and is
ready for installation pending a final approval of the layout plans
from  Caltech.  The Eurocrate backplane has been wired and is also ready
for rack installation.

-Engineering run:

We are planning to monitor PSL frequency glitches during the upcoming
engineering run.  We will also look for intensity glitches, although
without the intensity stabilization servo we will likely not have much
sensitivity.
 


LIGO Livingston Observatory (LLO) Operations (Coles).



 

OPTICS/COC/SEI INSTALLATION: The bellows replacement and realignment of ETM-x is completed. We've staged everything at the Y-end, and resurveyed all of the IAM monuments. Allen suspected a leak in the annulus if the dome on BSC-5, so we removed it and found a pinched O-ring. We've replaced it and are in the process of refitting the dome this afternoon. We'll setup the IAM instrumentation tomorrow and begin the realignment of ETM-y thereafter. Held a Laser Safety Quarterly Walkthrough Monday, and have been obtaining quotes and issuing Purchase Requisitions of the additional Commissioning equipment for LLO. (Jonathan Kern)

ISC (from Anthony Rizzi): Due to IOISC reboot, we lost pzt position (input beam alignment).
Sany and I reestablished pzt location (new bias settings: M1 pitch: .488 yaw: .16 M2: pitch .08 yaw: .26 ). We then
reestablished mode cleaner lock. We installed camera on roof of HAM1 using gimble mount done by Sany. We located both input
and returning beam on MMT1's baffle and adjusted. We had previously verified presence of input beam by moving SM1 and
observing the beam move (and no motion of it when MMT's moved), we now moved MMT2 until the return beam moved into hole. We
were aided in this by slight mirror oscillation that we still have to understand (probably due to non-optimal suspension control
settings). We then saw both the low power beam we had been seeing along with a much higher power beam out of the Faraday
port. The low power beam did not swing but the high power one did. We are now investigating a large oscillation problem in the Recycle
Mirror that started at the end of our observation. Once the beam is stable we will be able to make final periscope height determination.
We recorded the settings of suspension controls that allowed us to see the high power beam; they can be found in an e-log entry that
Sany will make today (11/2).


Detector/Technical Support (Whitcomb, Coyne).



 

Installation & Commissioning:
Hanford
Livingston
Other Science/Engineering Activities:
Design/Analysis/Fab
Issues/Concerns
See also the Installation web page

1.1 LHO INSTALLATION & COMMISSIONING

2km Commissioning

Matt Evans, Stan Whitcomb, Josh Myers, Richard McCarthy, Nergis Mavalvala

We locked a non-power-recycled interferometer this week. To do this Matt added some more code. We have performed some diagnostics in this configuration. Among other things, we measured the displacement sensitivity to be 1e-15 m/rtHz with a minimum at a few hundred hertz. Between 40 and 90 Hz laser frequency noise still contributes to the differential mode signal.

We are now performing calibrations to attempt full interferometer locking.

We also began to set up the wavefront sensing system, which has undergone a few modifications since the one arm test. We are still trying to make sense of  the signals measured on WFS1 using a single arm cavity. Rolf is helping us with some missing ASC test points.

Bill Kells
Work on modeling (e2e simulations) Han2k full locking behaviour.

PSL

Peter King
The PSL frequency noise was measured with the suspended modecleaner. Comparison with the previously measured frequency noise spectrum shows that for frequencies below approximately 500 Hz, the performance was degraded. Above 1 kHz, there was a small improvement in the spectrum up to approximately 8 kHz.  Roughly speaking the frequency noise is a factor of 6 over spec. above 1 kHz and a factor of 8 over spec. below 1 kHz.  This measurement may have been affected by non-optimal modecleaner servo settings.  Although the modecleaner servo gain and bypass gain were adjusted to yield the best spectrum.

Observed in the modecleaner servo "PSL Out Mon", the control signal to the VCO, was a constant ~200 mV DC offset.  In addition a large number of high frequency peaks were present, which were also found to be present in the modecleaner transmitted light.  For reasons I have not figured out yet, the modecleaner servo unity gain frequency could not be pushed higher than about 22 kHz.

The modified current shunt was installed into laser #103.  A quick test of the shunt verified that it was functional.

The intensity noise of the modecleaner transmitted light was measured. Numerous peaks were observed in the transmitted light, the first at approximately 13.6 kHz.  This peak was not present in the pre-modecleaner transmitted light noise spectrum, nor on the light after the three Pockels cells in the IO optics chain.

Tuning of the LSC photodetectors is about to start, after some delays because of other tasks that needed to be completed.

Lee Cardenas
Designing a mounting block to hold the pre-modecleaner. The block should kinematically locate the pre-modecleaner body.

DAQ

Rolf Bork, Dave Barker
Completed frontend data acq code port to Pentium.  This seems to be able to handle full 5 ADC boards (160 channels), plus incorporates moving avg. filtering.  Present MIPS units only handle 2-3 boards and do not yet have moving avg filter.  We may want to change out the LVEA multi-MIPS units and replace with single Pentium, particularly since we seem to have occassional sync problems in these multi-CPU frontends (noticed by Daniel and being checked by Dave today).

Trying to help Dave with EPICS data collection in light of the increased number of channels and rates in support of the second engineering run (E2).  The numbers may dictate using multiple CPUs to collect this data, and I am working on how to do that.  I should have some code ready by later today.

IO

Dave Reitze
David Ottaway and Betsy have measured the ellipsity that is imposed on a beam reflected from a Brewster angle polarizer. The value is 0.87. Another point about such polarizers is that when light in the rejected polarization state is incident on such a polarizer about 25% is reflected off the input polarizer's entry window (Simple Fresnel Reflection). As this is reflected straight off an air/calcite interface it is  reflected without becoming elliptical, perhaps this could be used for the wavefront sensing. Could also possibly use AR coatings for s-polarization.
A stand for the Faraday isolator was shipped to LHO this week.

LIGO-TriNet

Szabi Marka
We set up the Quanterra 4128 datalogger with Bob Busby, Dave Johnson and Mike Watkins of the CalTech Seismological Lab. Thanks very much for their help! It is now able to send packets to TriNet and to LIGO hosts. I still have to work on our reception code. The full setup including sensors and electrical system (except battery and fiber converter) is being tested at the Kresgee Seismological Lab. Upon successful outcome I will transport the system to LHO and set it up in one of our buildings until the vault is completed.

RF Frequency Distribution System

Rich Abbott
A mockup of the LHO Frequency dist. system has been constructed.  A test of before and after the modifications to cure the RF radiation problem is being performed.

1.2 LLO INSTALLATION & COMMISSIONING

RF Frequency Distribution System

Rich Abbott
Installed and commissioned the frequency distribution system for LLO.  We added the necessary components to cure the RF radiation problems as proposed for LHO

2.0 Other Engineering and Scientific Activities

2.1 Design/Analysis/Fab

Optical Metrology

GariLynn Billingsley, Helena Armandula
Analysis of the BS03 data is complete.  The optic will ship to Hanford this week .  Since the Beamsplitter measurement setup is difficult, we took the opportunity to
survey the two spare Beamsplitters, BS04 and BS05.  A summary of the optical sag is shown below. The sign convention indicates that the coated BSs are all convex.

Specification: 7 nm > Surface 1 sagitta > -25 nm
 
Optic Coated(CIT) Uncoated(CSIRO) Notes
BS01 -36 -10.3 Hanford 2K
BS02  -28 -6 Livingston 4K
BS03  -15 3 Hanford 4K
BS04 -27 -20
BS05 -14 0.2 Mottled surface

BS05 was found to exhibit similar markings to those found on two of the 4ITMs and one SPETM (ie: optics from both polishers.)  The exception is that instead of
streaks, which appear on the other optics,BS05 exhibits spots.   The depth of the features are consistent on all of the optics at ~6-10nm. These features have been found on both coated and uncoated optics and have affected 10% of the LIGO optics.  There has been some speculation that the marks are due to the cleaning process, but we have been unable to induce any changes on the one uncoated optic which is streaky.  We have attempted to change the optic by using reasonable variations in the cleaning process.  Both polishing companies have been questioned about this effect, both  have seen the effect, neither GO or CSIRO know the cause.

PSL

Peter King Lee Cardenas Rick Karwoski, Paul Russell
To provide the basic light source to Hanford we are concentrating on building and testing the three pre-mode-cleaner boards. Thus far we have completely
stuffed: 2 ea. PMC Servo Cards, 2 ea. Frequency References We will begin stuffing  the Photodetectors this week.  In parallel and in support of the built/test effort we are building up our new lab.  The test equipment we will
need for testing PSL modules has begun to arrive.

ISC

Mohana Mageswaran
Both the boards(MC Servo and Elliptic Filter) have been sent out for fabrication, and expected to get back them by next week. I will start testing the next generation MC Servo Boards soon.

Rich Abbott
We are doing an inventory to determine what to order for the remaining LSC components (Pentek clock fanout boards are certainly needed)

New OSEM Heads

Janeen Hazel-Romie
Peter Fritschel has found a prospective plater in Colorado. Progressive Technology may also have a subcontractor that can provide a satisfactory plating job for us. Trial runs will be made by both before one is chosen. A visit to a die cutting company this afternoon who bid on the PFA 440HP connectors ws disappointing. Since we have enough PFA 440HP parts already on-hand for the 4km LHO interferometer, we will have the balance of parts made by the CIT shop.

Data Monitoring Tool

John Zweizig
This week I have continued preparations of the DMT software for the coming engineering run.  I have written a new monitor that looks for the data acquisition errors seen in the first engineering run where a 1/16th second slice of data is replaced by data from the same channel from about 1/4 second later. The monitor also looks for other basic problems like frames that are not aligned with the GPS second or are not 1 second long. A trigger is generated whenever one of these conditions is discovered. In addition to developing the new monitor I have installed monitor code contributed by several LSCDC working group members and run a test of trigger recoding into the LDAS meta-Database.

DAQ Antialiasing Filter

Sander Liu
DAQ Antialiasing Filter Chassis - In the process of  ordering parts to build six more BNC and six more LEMO chassis.

Global Diagnostics

Daniel Sigg Sander Liu

2.2 Issues Concerns

nothing new



40 Meter Interferometer (Weinstein).




Thermal Noise Interferometer (Libbrecht).


We are still making progress on our test cavities.  The physics shop milled
the front panels for the NIM boxes for our satellite amplifiers, and we cut
the holes in the back panels for the input and output connectors.  We
expect to have at least one working unit by the end of today (Thursday). We
are still making cables, lots of cables, to carry the signals between these
satellite boxes, the sensor/actuator heads, and the OSEM controllers.
 

We have balanced and aligned one test cavity, and we applied epoxy to the
wire standoffs to preserve this alignment.  Diagnostic-optics mounts have
been cleaned and placed in the chamber, but optics have not yet been
installed.
 


LASTI (Zucker).


Seismic isolation installation (Zucker, Mason, Smith,
McInnis, Kruzel, Radkins, Grey.)

-HAM13: Completed 10/26/00

-HAM21: The clean room has been positioned over HAM20 and the doors removed.
The support tubes and support table have been installed and leveled.
We are currently installing bellows.

-HAM20: Still waiting on a couple miscellaneous small parts. We will
finish and leakcheck 21 and come back to 20 when they come in.

-BSC0: Mounting holes are marked;
we will start drilling for the support pier anchors
as soon as HAM21 is buttoned up for leakchecking (~ Friday).

Electronics: DHS, MZ and KM reviewed electronics rack size
and placement with Jay Heefner and Rolf Bork.  They have
the green light to procure the DAQ/GDS infrastructure equipment
(plus suspension controllers for the first phase).


Data Analysis and Computing (Lazzarini)


No report received.


LIGO II/Advanced R&D (Sanders)


Bill Kells:
1. Helped Jordan finish sapphire test mirror birefringence studies.
    Written up in paper draft. Also obtained crude measure of
    Rayleigh scatter in same test substrate.
 
2. Further MELODY-FFT cross comparison runs. This work is stalled at a
   disagreement cum interpretation issue with Ray B. Note that already
   a couple of MELODY version patches have resulted from this work.
 


For additional information about this report, contact sanders@ligo.caltech.edu