|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The LIGO Executive Committee
Agenda for Monday October 2, 2000 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
Special Items:
No report.
WBS 1.2 LIGO Operations--Administration
From: Ed Chargois <chargois_e@ligo.caltech.edu>
>From: Linda Turner - turner@ligo.caltech.edu>
Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database.Take a look. . .
SEPTEMBER STATISTICS
September was an extremely active month. A total of 136 new documents were processed and made available on-line. Additionally, 261 documents were added to the DCC database. The fax traffic was high as well with 163 faxes sent and another 145 received. During this month, 92 packages were sent out while 94 were received.
| Packages | Faxes | |
| In | 50 | 44 |
| Out | 43 | 72 |
Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS PAYABLE HISTORY DATA.
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
Working on preparing the report for the Washington Sales tax auditor who will be here on Monday. Gathering information and copies of invoices for furniture orders placed for LHO.
Finishing up for the fiscal year 2000 which officially ends tomorrow.
Closing out PO's and removing encumbrances. Released $261.38 in
encumbrances on old FY99 PO's. Many of the PO's had only nominal
amounts encumbered.
From: Florence Kaufman <fkaufman@ligo.caltech.edu>
From: irena@ligo.caltech.edu (Irena Petrac)
·PLEASE
NOTE:This report only covers three (3) days since I was on vacation last
week.
·With
the help of Criselda and her great team and Liz, twelve (12) new trips
have been started during the past two (2) weeks. Seven (7) trips
are pending final approval from the traveler before tickets are issued.
·The
P-Cards are working great.A few of the card holders have started their
first trip using it, and it seems to be working well. I have started
working on Expense Reports for trips that I previously used my card on,
and this also is doing well. The form to be used for P-Card trips was changed
by Travel Audit, and they are constantly changing their minds as to how
they want it done, but we're working it out. Criselda has sent the new
Expense Report (which unfortunately is in Excel but is being worked to
convert to FileMaker Pro). I prepared a few Advance Requests and
Payment Requests using the old system due to various reasons, which excluded
them from the new system. Any trip that was started in the old system,
or any canceled/postponed tickets being reused on a new trip, must be done
using the old system. I can't tell you why. Travel Audit just
wants it that way.
·Worked
on, and completed twenty-three (23) Expense Reports. I have forty-five
(45) outstanding reports at the present time. I hope to work on these
outstanding reports this week and weekend. Rita Torres returned the
seven (7) reports she had previously taken to work on.
·Prepared
the Travel/Vacation Itinerary for the Week of September 25, 2000.
Performed normal recording and filing associated with Travel and Reimbursement.
Worked on several problem issues with Travel Audit. Also performed
miscellaneous duties as requested by various members of the LIGO Project
here at Caltech as well as from members of the staffs of each of the two
(2) sites. I continue to do MIT's travel to the sites for installation
activities and also to assist them wherever possible.
·Received
billed amounts on-line, to close out and remove remaining encumbrances
on old POs. Adjusted LIGO database accordingly.
·Began
updating PO Log books for the period July 15 through Sept. 15.
·Processed
the usual requisitions, invoices and receiving on-line. For more detail
see "Cost Schedule Control Systems" report by Esther Cunningham.
·Tracked
and followed up on invoice problems.
·Reviewed
and recorded payments processed by Esther for the week of September 18,
on contract summary sheets and LIGO database.
·Continue
to monitor contract and blanket order funding levels and notified task
managers when supplements are needed.
·Jim
continues to do data entry in the LIGO database and help out in the DCC.
·Had
a meeting with Toni Itano in the provost’s office to go over all the outstanding
visa issues in LIGO.
·Ordered many many many copies of Sky and Telescope to be distributed throughout LIGOland.
Progress Period from 9.22 to 9.28
Accomplishments:
The following Change Request has
been submitted:
| CR-000017 | WBS 1.1.4 | Design building for office space, laboratory space, and auditorium. Modify Staging building | O. Matherny |
Press for the latest Contingency Needs Projection.
From: Kris Duncan <kris@ligo.caltech.edu>
From: Irena Petrac <irena@ligo.caltech.edu>
Nothing significant to report (see above).
From: Ed Jasnow <jasnow@ligo.caltech.edu>
No report, see above.
General Items:
--------------
(F. Raab)
We have made some reassignments of labor to cover 4K installation to
broaden the capabilities of the resident staff and to adjust to holes created
by LIGO-II commitments. Mark Guenther and Tom Mahood will work with Rick
Savage to install the 4K PSL; Corey Gray and Betsy Weaver will work with
Dave Ottaway on IO installation. Rick Graf will be helping support Doug
Cook with optics tasks.
Bake Oven:
----------
(K. Ryan)
LHO Vacuum Bake Oven A load #105, consisting of 10" optic ETM02-A and 3" optics MCFM01-1 and MCFM04-1, was released on 9-11-00.
Load #106, consisting of an SOS top block, Kapton cable w/peek connectors and misc. COS SS fasteners, was released 09-19-00.
Load #107, consisting of three 3" optics, should be released 9-29-00. This load had to be rebaked as two of the heated zones had run cooler than the programmed setpoint during the initial baking. This problem was found to be due a simple programming error and was corrected.
Vacuum Bake Oven B (small oven ~1.5-2.0 cubic feet) has been test fitted
and mounted to it's stand but is still waiting for a custom part before
final commissioning can be completed.
PreStabilized Lasers:
-----------------------------------
(M. Guenther T. Mahood & R. Savage)
Fabrication of the attachment fixtures for installation of the acoustical insulating panels into the 2k PSL enclosure have been completed and T. Mahood and G. Moreno have completed 95% of the installation.
The 4k 10 watt laser has now been activated in its enclosure in the south bay. There are no table optics at this time. It's just being run into a beam dump (a power meter) for startup and initial monitoring.
Optics:
---------------------
(D. Cook)
We closed out last week with the cleaning and realignment of ETMy-2k.
The optic had been showing a lot of scattering. The optic was quit dusty
and the BSC chamber floor was littered with aluminum foil chips, material
from clean room garb and some other debris which probably was the source
of the contamination. Quite dirty by normal standards. The chamber was
vacuumed and the optics table interior and adjacent modules were inspected
for additional contamination. We then adjusted the optic alignment to give
us a better dynamic range on the SUS and ASC bias adjustments. The optic
was then CO2 and N2 cleaned and inspected. An additional viewport was added
to accomodate the photon calibrator. Hopefully the H2O level will be such
that we can open gate valves and look at the lack of scattering and the
alignment. We are still processing optics and hardware for the 4K installation.
Seismic Systems:
----------------------
(C.Gray, H.Radkins, G.Moreno, M.Guenther)
SEI Coarse Actuation System:
Installation is essentially complete. Use of the CAS at LLO revealed
moves commanded produce smaller motions coupled with yaws at the Optics
Table. Testing at LHO has continued on the CAS (Instrumentation JPEG).
We have found definitively that the connection between the airbearing and
the crossbeam is too loose and allows the joint to rotate during CAS lateral
translation plot. This results in shorter than commanded moves and
unintended yaws as the two airbearing/crossbeam connections rotate different
amounts in response to different resistive loads from the expansion bellows.
We have fabricated custom shims to allows full torquing of this joint.
We will test this modification 9-28.
Fine-X
We were installing the PZT stacks in the Fine-X stages at Y-Mid when
we found the conical seat for the PZT installed backwards in the bottom
frame. This part needs precise machining and a hardened material
due to the continuous high stress it endures. It will be a few days
as we fabricate the solution.
SEI Transfer Function:
We have lost one of our reaction mass shakers to the commisioning group
working on modecleaner leveling. We'll get back to wrapping up the
results when we have the fourth shaker.
Other areas
--------------
ISC Alignment Sensing & Control
2k: Working with R. McCarthy to swap the QPDs with increased gain (10x)
models.
The 4 test mass optical levers are completed to date.
4k: Slowly putting in and testing the various components of the 4k optical
levers. Nothing significant new this week.
Computing:
----------
(C. Patton)
Evaluating Quick Restore backup software for possible purchase.
The
software provides a GUI on the Unix server, has drivers to control
the
Exabyte tape robot, and will backup the server and 5 Unix clients.
There are other options for more clients, drivers for different types
of
tape robots and Windows98 clients will be available by the end of this
year. So far it works well.
Finished putting the fiber onto the GC license server so that it is
now
serving licensed software to the CDS network computers as well as the
GC
computers. This makes Matlab, Mathematica, GNU compilers, Latex,
emacs,
Ghostview and Ghostscript and several other applications available
on
the CDS network.
OPTICS/COC/SEI INSTALLATION: ITM-x has been fine aligned, and
its Optical Lever enabled. With the COS-LAC established the X-manifold
and used to
coalign MMT-3 with MMT-2 and the projected PSL beam, we found that
MMT-3 required quite a bit of PAM bias in yaw. We backed out the PAM screws
to
minimize their influence and corrected the Yaw misalignment by loosening
MMT-3 from the HAM table and yawing the entire LOS. We also found that
after yawing the LOS we no longer observed pitch/yaw cross talk. BSC
3, as well as HAMS 3, 4 and 5 have been documented and closed; this morning
we're completing the photographic documentation of HAMS 1 and 2 and replacing
their doors. We'll kill the purge air briefly, and place the air-dam
between HAM-3 and BSC-2 so that we can make the in-air length measurement
of the MC. Following this, I plan to complete the checkout/cleaning of
both
ITMs and the BS, replace the remaining BSC door and X-manifold spoolpiece
and begin pump down of the vertex Friday or Monday. (Jonathan Kern)
LLO Computing: Larry Wallace and several members of the Livingston
staff had a series of talks with representatives from Bell South about
our eventual
conversion to a fiber link to LSU. A fiber has been installed between
LLO and the nearest Bell South substation, but many administrative issues
remain to be resolved before we can switch over to the fiber. (Shannon
Roddy)
Outreach: One school group visited this week. This Saturday, the U of New Orleans and Loyola University SPS and Astronomy club students and some faculty tour LIGO.
Late news: After an extended installation period
this summer, the mode cleaner is once again locking for brief periods in
air!
| Installation
& Commissioning:
Livingston |
Other Science/Engineering
Activities:
Issues/Concerns |
See also the Installation web page
Bill Kells
Mostly have concentrated
on interpretation of full lock data brought back from LHO since then.
Finished up e2e runs (started at LHO) to show difference between LHO 2k and 40m PRM lock in presence of arm fringes. A striking difference is apparent which corresponds (qualitatively to observation).
First step will be the in-air measurement of the length of the re-installed Mode Cleaner, which should take place by the end of this week.
LSC software: Waiting for header files and lock acq. code updates from M. Evans to incorporate in front end code for next run.
ASC software: Awaiting decision/guidance on adding optical lever signals and servos into ASC front end software.
Prepared all the components, procedures, pictures and drawings required to Suspend a Ref. Cavity for the PSL at LHO. As per request from Rick Savage and Mark Guenther.
Took last parameter measurements for the Laser MOPA S/N 110 that it is going to Lightwave.
Peter King
Some parts are coming in
for fabrication of the 4k PSL.
The 0º incidence measurements of the Beamsplitter are nearly complete. We have yet to start the 45º incidence measurements.
#SEW# We have decided to go ahead with RM03 for the LHO 4 km interferometer, based on real absorption measurements for the ITMs and some FFT analysis by Bill Kells. It is shipping to LHO today.
The network link down to the PSL Lab seems to be behaving properly now, at least there aren't so many dropped packets. A new problem popped up when no non-root user could log in but that has since been fixed.
Rick and Peter have been taking measurements characterizing the current shunt actuator, for frequencies below 100 kHz. We feel that it is important to also obtain data beyond 100 kHz, since this will give us a good indication of just how high we can extend the bandwidth of any intensity stabilization servo.
The paperwork for some 40m Lab and LASTI PSL components has been submitted. These being for the PSL optical table and pre-modecleaner. Other bits and bobs continue to trickle in.
Paul Russell
I am looking forward to
my association with Rick Karwoski. This week has been dedicated to getting
my tasks at the wilson house finished up... this might take a week or two,
in the mean time I'm trying to collect and absorb all the info on
the PSL.
ASC software: Awaiting decision/guidance on adding optical lever signals and servos into ASC front end software.
Wesgo/Duramic has come back with a quote for alumina heads. Surmet and Progressive Technology say they will quote by the end of this week. Working on osem documentation.
The SOS dewhitening schematics are being reviewed and completion of the design is scheduled for next week.
Rolf Bork
Got back to work on the
LOS controller output stage software. Running some preliminary performance
and timing tests using the LSC system to provide inputs to the system via
reflected memory.
Originally, 14 units were requested. Now the number has increased to 17. We are in the process of buying additional components to fill the new order. Previous order for two pin LEMO connectors has fallen through the crack and are being reordered.
This week, while waiting on new filters for our laminar flow hood, we
reassembled the hood to get it up and running again and then used it
to
glue magnets and guide rods onto our third test mass. Once the
epoxy has
set, we will only have one more mirror to prepare.
Jay Heefner laid out the boards for our satellite amplifiers, and we
should
receive a quote for fabrication by the end of the week. We anticipate
a
one week turnaround time for these boards, and we hope to start stuffing
them very soon.
Components for the mode cleaner servo and the satellite amplifiers arrived
from Digi-Key, as did suspension wire from California Fine Wire.
The
Carpentry shop delivered our custom optical table, a lightweight breadboard
mounted on wooden legs, on Tuesday. This table will be for diagnostic
optics, mostly cameras used to look at the modes of each cavity, and
replaces a shelf-on-wheels that we have been using.
Planning/budget (DHS & MZ): completed & distributed for comment
hardware budget estimate for LASTI R&D program corresponding to
reviewed project plan. Daniel and Rolf's analysis of reduced
requirements for the planned experiments led to significant savings
on
the DAQ and GDS portions over 'carbon copy' site-type installations.
Lab infrastructure (M. MacInnis, M. Smith, K. Mason, E. Kruzel, MZ):
Cleared out stored equipment to make room for SEI hardware. With
riggers, moved donated cleanrooms and gowning room from CSR into high
bay; cleaned fan units and erected cleanroom over right end HAM. May
want to raise the height a tad but otherwise looks like it was made
for
the job.
Erected donated cleanroom-compatible aluminum gantry crane for testing
door removal options (no Toyota here and no space to drive it...).
SEI external installation(M. MacInnis, M. Smith, K. Mason, E. Kruzel):
Finished HAM anchor drilling (turns out carbide hole saws work best
on
SST rebars). Set anchor bolts for all HAM chambers, scarified
concrete
for grouting and rough-set SEI support piers for 2 of 3 HAM's. Cleaned
corrosion and passivated surfaces of all HAM piers. Staged remaining
equipment for SEI installation and scheduled cleaning crew to clean
up
next week.
1. Matt works on improving the lock servo design.
2. Luca repdoduced the LHO 2k lock experiment
with ETMs misaligned.
Luca is looking into
the details of the simulated lock process to find
what breaks the lock.
3. Biplab studied the effect of the misalignments
of mirrors on the lock.
He found that there
is a threshold at around several x 10-8 rad above
which the system would
not lock. He summarized the result in LIGO
note T000106
Simulations
Jim found a discrepancy between data and the simulated result when the
waist position of the incoming field is shifted by 10% of the Raleigh
length.
The simulation predicts a big change of the stored power in the cavity
(several 10% reduction), while the measurement sees much smaller effect.
The cause, possibly the perturbative expansion keeping only the lowest
order
of the shift, is being looked into.
GUI
The new alfi based on a revised version of the graphics rendering code
has been
released. With this version, improvements of stability and performance
are
expected. Various reported problems were also addressed, including
the issues related
to removing objects cleanly.
Simulation Code improvements
Tavio worked on improving the matrix class. By chaning the return type
of various
operators whose values are not used (e.g., *= ) to void and by removing
the creation
of temporary memory allocation by suing dual storage based on the idea
of Matt,
the multi mode code runs several 10% faster. He is cleaning another
part of the
matrix class.
There was a discussion about the implementation of the parallelization
of the code
among Matt, Hiro and Tavio. The strategy is well formulated.
Distribution
Ed wrote a documentation explaining the installation process. The document
and
tar files of the latest e2e release are now available from the e2e
webpage. When
a new version is released, it will be notified to the registered users
and they can
download. Gerhert of TAMA has followed this document to install from
the scratch
to his PC linux machine, and after a few exchane of mails with Ed,
he could install
all softwares.
TAMA
Hiro went to National Astronomical Observatory, the host institute of
TAMA.
Prior to his visit, Ed worked hard to install all e2e softwares on
a TAMA
computer. Hiro explained the basic use of e2e to scientists from NAO,
ICCR and
Univ. of Tokyo, together with the HAN2K package used for the Hanford
2k locking
servo design.
Hiro discussed with Prof. Ohashi and Mr.Tomaru about the plan of improving
and publishing a FFT paper mainly done by Tomaru by using the polished
surface data in the FFT simulation. One improvement mentioned by Ohashi
was to include some measurement of performance of TAMA in the paper.
Software Systems (Blackburn)
The wrapperAPI interface function design was finalized during a set
of teleconferences held Friday, Saturday and Monday between CIT and
UWM. Work will begin today on the development of a new wrapperAPI that
will meet the design criteria of this new interface design. The first
version of the wrapperAPI has been checked into the CVS respository
and tagged so that it can easily be distinguished from the new version
during development.A bug in the genericAPI TCL code which cropped up on Monday of this
week and caused all LDAS APIs to stop running after 16 minutes has
been tracked down and fixed. A meeting to review our testing procedure
was held to insure more thorough integration testing of new code prior
to system testing so that this type of bug (common to all system
components) does not get into the main stream system builds. However,
it was very reassuring to be able to isolate and fix this level of
bug in less than two days.An exhaustive suite of tests are currently underway for the version of
the LDAS system running on the development hardware. We plan to push
this version to the sites over the weekend if all tests pass. A test
status meeting will be held Friday to discuss the push to the sites.LDAS participated in a meeting of the Network Analysis Working Group,
now called (NAWG). Kent Blackburn reported on his activities to put
together a "data flow model" for gravitational wave network analysis.
A draft of this was placed on the web and will continue to evolve as
the details of performing a network wide analysis become more clear.The next challenge for the dataConditionAPI working group is to design
a "Unified Data Type" (UDT) C++ class. The requirements for this class
were presented last week to the group and implemetation was discussed
this week. The current leader is an implementation which uses multiple
inheritance to organize the marginally related objects needed to
support the UDT classs. Ed Maros is presenting a C++ class based on
multiple inheritance to the group next week.The other big news for the dataConditionAPI from this week is that the
memory leak which was only half solved last week is now completely
removed.
Hardware Systems (Anderson)
Started upgrade of LDAS @ LLO from U10 workstations to E450 servers, Solaris 7
to Solaris 8, ATM to Gigabit Ethernet, and adding additional 250GB disk system.Installed and started performance testing of 1.5TB DotHill RAID system.
Installed and started configuration of 16node development Beowulf cluster
at Caltech.Switched Caltech LDAS development network from fast Ethernet hub to
Gigabit Ethernet switch.
Livingston:
Working on setting up a new server layout.
Checking on tape robots to be purchased for a new backup system.
Met with Larry and Bellsouth reps concerning the fiber connection.
The copper connection should be converted over to the fiber connection
sometime in the Dec-Jan time frame. Shannon Roddy will be working the
logistics at the Observatory.
Hanford:
Evaluating Quick Restore backup software for possible purchase.
The
software provides a GUI on the Unix server, has drivers to control
the
Exabyte tape robot, and will backup the server and 5 Unix clients.
There are other options for more clients, drivers for different types
of
tape robots and Windows98 clients will be available by the end of this
year. So far it works well.
Finished putting the fiber onto the GC license server so that it is
now
serving licensed software to the CDS network computers as well as the
GC
computers. This makes Matlab, Mathematica, GNU compilers, Latex,
emacs,
Ghostview and Ghostscript and several other applications available
on
the CDS network.
CIT:
(Lisa)
-Installed staroffice for Janeen Romie
-Contacted Cactus software to get a demo copy of their network backup
software
for solaris/NT.
-Received and installed a replacement CPU for Rich Abbott's old gateway.
It is
now back over in Wilson House. Swapped some other pc's around.
-Switched a SUN box from the 115 to the 125 for the Wilson backhouse.
- Created accounts for 2 wilson house employees who never had accounts
created -
Dave Grimmett and Shaun Rahimi.
- Set up Rick Karwoski to run Cadence from his PC.
- Fixed the NIS+ on Peter King's sparc20 in Lauritson Lab. It
lost its sync
after the fiber move.
- Started building HTML pages for a cadence web site. This site
will contain my
notes about Cadence as well as any info that comes in from users here
at
Caltech.
(Barbara)
- Tied up loose ends regarding the LSC transparencies.
- Enhanced the LSC roster to include additional information for discipline,
LIGO I, Advanced LIGO, and Council members.
- Made changes to the LDAS web site for server aliases and ilog links.
- Made quick changes to the CostBook.
- Continued efforts on the publications list/web pages.
(Suresh)
-Assisted electricians to move networking fibers from telephone closet
to
computer room on last saturday.
-Restored LIGO templates for Adobe Framemaker from backup tape of former
sirius.
-Made some changes on DNS server (ligo) to reflect system named lionking
which
is currently in Lauritsen building to be visible to outside world.
-Put a Sparc 5 system in the 115 subnet in Room #354 in bridge.
-Testing "snort" and Intrusion Detection System (IDS) both on PC and
solaris.
-Installing and configuring necessary softwares in PCs to be used with
projectors in conferece rooms in Millikan and third floor bridge.
(Larry)
- Worked a number of contract issues and put in a number of orders
for
maintenance contracts as well as some hardware purchases.
- Working a number of budget issues for this fiscal year as well as
the future
years.
- Met with Bellsouth the OTM of Louisiana and LSU to go over the costs
and
logistics of the OC3 installation. Most of the information that is
needed will
be supplied by Bellsouth in the near future, both cost and time estimates.
- Working on a number of procedure setups covering OS installations,
LSC
meetings, and sysadmin documentation.
- Worked on a number of fiber issues through out the CIT/LIGO network.
(Samantha)
Worked on getting the new Dell lap top up and going. It has issues
though.
Worked on burning cds.
Getting a number of parts from different computers to be used in other
computers.
Physical therapy
From Mike Smith:
LIGO 2
Pricing for the reference design is in process.
From Bill Kells:
Also tackling analysis of fate of Rayleigh scatter from
Sapphire TMs in LIGO II.
More on MElody validation, including steps to get FFT
up and running on EXEMPLAR.
From Janeen:
Working on Advanced LIGO schedule and costs for labor and materials.
From Peter King:
3.1 LIGO II PSL
The LIGO II PSL schedule has been reworked after a meeting with
Dennis Coyne and Thomas Frey. The old schedule had a large number of
tasks
in parallel since I didn't know about what should go where and when.
The
new schedule has removed most of that and has incorporated the PSL
delivery dates from David Shoemaker's LASTI schedule.
From: Helena Armandula <ahelena@ligo.caltech.edu>
Silicate bonding
Investigated surface preparation prior to bonding.
Two sets of bonds were prepared.
In one set the substrates were cleaned with calcium carbonate and were
well rinsed.
In the other, the substrates were rubbed with calcium carbonate and
the residue was cleaned by wiping the surface several times with a wet
cloth (no rinsing).
The strength of the bonds were compared, obtained very similar results,
averaging ~330kg of shear for a 1/2"-diameter bond.
From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>
Akiteru:
Coming back from JPS meeting
Virginio:
Cleaner measurement on the SAS chain after the construction of the
enclosure. It seems possible now to run measurements when the very
noisy
around and the MINOS group is working.
Found an unexpected noise problem and its source of in the DAQ system
and fixed.
Made a simple simulation of the system to study and optimize the
blending of the Accelerometers and the LVDT. Test on the IP chain under
progress.
New version of GASF paper.
Alessandro
Assembling and tuning four Copper Beryllium accelerometers.
Frederick
Early result of evaluation of mechanical simulation packages.
Ansys
seems better so far.
Riccardo, Frederick:
Assembled filter 1 in TAMA IP
Built enclosure for LIGO IP
Tested first TAMA miniGAS springs, setting dimensions for production.
Virginio, Akiteru:
Still no DSP chips found, but found a likely source in Singapore to
be
checked.
From: GariLynn Billingsley <Billingsley_G@ligo.caltech.edu>
The Corning representative was in on Tuesday. We have fairly good
numbers for our Corning fused silica now. Heraeus has given us some
rough $/kg numbers. They are having a hard time getting actual quotes
from Germany. (~2months to quote) The great news is that Corning
is developing a low water glass in cooperation with the government, and
expect to be selling it sometime next year. They are sending us a
sample of the development material for absorption testing.
For additional information about this report, contact sanders@ligo.caltech.edu