Weekly Report for Week Ending August 31, 2000


 Exec. Comm. Agenda
Highlights
LSC
Administration
Hanford Observatory
Livingston Observatory
MIT
Caltech
Detector
40 Meter
TNI
LASTI
Data Analysis
LIGO II/Adv. R&D
Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  Sept 4, 2000 will be:

CANCELLED DUE TO HOLIDAY


Special Announcements:


Weekly Report Highlights
 


LSC Issues (Weiss)


No report this week.


LIGO I Construction/LIGO Laboratory Administration (Lindquist)


WBS 1.2 LIGO Operations--Administration


LIGO Weekly Site Telecon (Lindquist)


PROPERTY MANAGEMENT (Chargois)

From: Ed Chargois <chargois_e@ligo.caltech.edu>


DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner - turner@ligo.caltech.edu>

Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database.Take a look. . .

 ACTIVITY HIGHLIGHTS

From: Cleveland Mak <mak_c@ligo.caltech.edu> Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.


COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Akutagawa, Kaufman)

From: Esther Cunningham <esther@ligo.caltech.edu>

Press here for ACCOUNTS PAYABLE HISTORY DATA.

From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

Working on Triad c/o #58, Research Electro Optics, and a new LSU order.

From: Florence Kaufman <fkaufman@ligo.caltech.edu>



SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: irena@ligo.caltech.edu (Irena Petrac)

From: Ed Jasnow <jasnow@ligo.caltech.edu>



Support (Wood)

Dorothy Lloyd

Dorothy is on vacation for three weeks although she submitted the following (we should make sure that Dot is not bored while on vacation and submit lots of purchase reqs and invoices!):

Rita Torres Irene Baldon Elizabeth K. Wood

Advanced LIGO (Frey, Petrac)

From: Thomas Frey <tfrey@ligo.caltech.edu>

Progress Period from 8.25 to 8.31

Accomplishments:

Schedule: 9.1 to 9.7 Anticipated Challenges: Corrective Action: From: Irena Petrac <irena@ligo.caltech.edu>

WBS 1.4.1.2   Project Controls (LIGO Construction)


Reports (Lindquist)

Change Control/Contingency (Lindquist)

The following change requests have been submitted:
 

CR-990028 WBS 1.1.3 Beam Tube Enclosure Closeout (return of unused funds) F. Asirir
CR-000014 WBS 1.2.1 Additional Support Equipment for Commissioning D. Shoemaker
CR-000015 OPS Repair of Road along Beam Tube Enclosures at Hanford O. Matherny

We have tentatively scheduled a meeting of the LIGO Change Control Board for 9:00 am (PDT), Tuesday, September 12, 2000.

Press for the latest Contingency Needs Projection.


COST SCHEDULE CONTROL SYSTEMS (Duncan, Akutagawa)

From: Kris Duncan <kris@ligo.caltech.edu>

From: Cindy Akutagawa <cindy@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: Irena Petrac <irena@ligo.caltech.edu>

No report this week.

From: Ed Jasnow <jasnow@ligo.caltech.edu>

The Invitation for Bid for the Livingston Staging Building is undergoing a thorough review before issuance.  This may result in a delay of one week or more.


Quality/Safety (Tyler)

>From: Bill Tyler <tyler@ligo.caltech.edu>



LIGO Hanford Observatory (LHO) Operations (Raab)


General Items:
--------------
(F. Raab)
 

Work continued this week on WA4K-IO components and other preparations for installation and the tuning of suspension controls. Much of this work is reported elsewhere. Gerardo Moreno joined the operations staff this week. He had previously been supporting installation activities, working for Manpower. Most of our student workers have disappeared this week, as school begins in Eastern Washington.
 

Some detailed reports are given below.
 

ISC: H.Radkins
Initial Alignment Monuments
Monuments are in place at the X End, pending installation at Y End, and waiting for location from ISC for the Corner Station.
4k IFO Optical Levers
                Laser/QPD       SM motor        Mounted Remarks
ITMx Tx tested          tested          no              Ready for mounting
ITMy Tx tested          tested          no              "       "
MMT3 Tx needs           tested          no              Will install laser after mounting
MMT3 Rx tested          tested          no              Ready for mounting
ITMy Rx needs           untested        no              QPD ready for install
ITMx Rx needs           untested        no              "       "       "
RM Tx   tested          tested          yes             already in use
RM Rx   tested          tested          yes             already in use
BS Tx           tested          tested          yes             already in use
BS Rx   tested          tested          yes             already in use
ETMx Tx needs           untested        no              Ready to test SM
ETMx Rx needs           untested        no              QPD ready for install
ETMy Tx untested        untested        no              Ready to test Laser/SM
ETMy Rx needs           untested        no              "       "       SM
So, if all this is correct, we need 2 laser sources, and 4 QPD.  There are no lasers and only 3 QPDs on hand at LHO; will procure ASAP.  In general, all OLs need DAQ power and data cabling/connectors.
 

FACILITIES: H.Radkins
Preliminary results from the warehouse/LVEA seismic study indicates the warehouse is 5 times noisier than the LVEA during no wind conditions and 10 time noisier with 30 mph winds.  Over these wind changes, the LVEA slab motion doubles while the warehouse slab motion increases 5 times.
 

SEISMIC ISOLATION: C.Gray
BSC9(x-end) Stack Transfer Function measurements:
 

Investigating the vertical component of the Stack's transfer function (only exciting in the z-axis and have just one z-axis accelerometer on the stack). Several types of measurements have been performed (FFTs w/ & w/o "white noise" and Swept Sine) and a couple of points can be made thus far. The only "coherent" Transfer Function values are between 2-25 Hz--due to accelerometer limitations at the low frequencies and performance of the stack at higher frequencies. Need to determine whether the high frequency data on the stack is noise or signal (looks mainly like noise at f>100Hz---data looks to be 3 times higher than the accelerometer's specified noise floor.
 

There seems to be a "coherent" peak at about 33.25-33.50Hz that pops up, w/ enough excitation. This peak seems to be related to a structural (Pier, Support Tube/Table assembly?) resonance we can easily see on our external accelerometer at the same frequency.
 

Remaining tasks: 1) determine whether we are seeing structural resonances through stack (@ ~33Hz and possibly ~54Hz), 2) classify f > 25 Hz as noise floor of accelerometer, other noise, or real signal.
 

LASTI SEI:
 

X/Y and Z Dummies were shipped out to MIT yesterday for SEI installation.
 


LIGO Livingston Observatory (LLO) Operations (Coles)



 

OPTICS/COC/SEI INSTALLATION: I reported last week that the two Newport Laser Autocollimators which we have at LLO failed to yield similar measurements in identical test situations. This was a serious and troubling discovery, because the Newport Laser Autocollimator is the instrument by which we align the interferometer. Hugh Radkins at LHO shipped us his theodolite/LAC to compare with ours. Having all three instruments on hand, we identified our problem as a faulty cable, which made the LAC susceptible to RF generated by our theodolite. We also made visual checks comparing the LAC measurements to those of the Sokkia theodolite. We now make certain that we can see the reflected image in the Sokkia, and check the LAC's readout, by comparing the coordinates displayed at the theodolite. We also discovered that the unit Newport loaned is in error by ~100 u-rad. While disappointing and requiring resurvey of every CO in the vertex, we learned the importance of verifying the LAC measurements with the visual telescope of the Sokkia theodolite. I'm satisfied we know and can check what we're doing, and have a reliable and verifiable instrument to proceed with our task. We have now re-surveyed and correctly positioned four optics (MMT-3, RM, BS & ITM-x) along the X-axis. Today, we will realign ITM-y and position the BS in the Y-axis. Completing this, Mike Smith will be able to complete the COS installation. (Jonathan Kern)

Vacuum: The X arm cryo pump is cold and in operation. The control system is being tuned for optimal flow.The Y arm pump is also being prepared for start up. We are leak checking the X end station and getting all the annulus pump systems in order. (Allen Sibley)

General Computing: Installed an ATM network card in our Windows file and print server. This will give it 155 Mbps throughput rather than the 10 Mbps it has now. This will reduce the chances of someone not being able to print because someone else is copying a file to it etc. I will be plugging it in today once I have it configured properly. It has been tested for a couple of weeks now as a file and print server and I have had no significant problems other than the bandwidth bottleneck. After I move it to the ATM, the PC's should be configured to print through it instead of Opelousas.

Visual Studio 6 will be installed on a public machine this week for anyone who needs to do any Windows based programming. Several people have
requested it over the last few months.

We are developing a library of computer reference books, which are available on the bookshelf in the computer users room. This week we ordered some GNU manuals for much of the GNU tools that we use (example: gcc).

CDS:  Setting up three Sun Ultra 10s that will go into the LVEA as CDS workstations. (Shannon Roddy)

PSL: Rich Abbot and Peter King are here this week. They have upgraded the Freq. Servo Board. It now can withstand transients without going into oscillation. It also has more gain than the older version. We are also going to check the PMC servo to make sure we have a good distribution of gain. We are also doing some house keeping to upgrade the PSL table layout designs and the epics screens for the PSL. (joe Kovalik)

Other: Shipped all necessary fixtures, equipment and tools to MIT in support of the LASTI seismic buildup. (Rich Riesen and Harry Overmeier will go to MIT to install the LASTI seismic buildup once the LOS installation is completed at LLO.) (Rich Riesen)

Fred Asiri:
Facility/LLO: I have received construction document (39 drawings and technical specification) for Staging Building and Renovations to Existing Storage Building at LLO. We are in process of reviewing and completing this document to turn it in a "Bid Package". I will be at LLO next week to complete this process as well as other outstanding issues.


MIT (Shoemaker)


covered elsewhere


Caltech (Sanders)


covered elsewhere


Detector/Technical Support (Whitcomb, Coyne)



 

Installation & Commissioning:
Hanford
Livingston
Other Science/Engineering Activities:
Design/Analysis/Fab
Issues/Concerns
See also the Installation web page

1.1 LHO INSTALLATION & COMMISSIONING

2km Commissioning

Nergis Mavalvala, Matt Evans, Daniel Sigg, Bill Kells, Dick Gustafson, Stan Whitcomb
We completed all optical measurements on the power recycled Michelson which were needed for the lock acquisition input matrix. We were unable to try this for acquiring the full ifo since some filters for the Lp path in the LSC front end code were not configured. Gate valves on both X and Y arms were closed Friday morning.

4 km Installation Planning

Ken Mason
Began writing up the initial alignment procedures for the LHO corner station. A change has been made in the alignment of the ITMx and ITMy optics. Instead of aligning to the back (AR) surface, we will set up offset 400 mm from the beam path and use the PLX retroreflector to reflect off the front (HR) surface. The advantages to this method is we align to the critical surface of the optic and the autocollimator is still in position monitoring the ITM angle while COS is verifying the large optic alignment.

Larry Jones, Doug Cook
Developing detailed instalation sequence and procedure document.

Suspension Tuning

Mark Barton
This week I've been at Hanford working on suspension controller tuning. I moved over most of the software that I had created at LLO. With Betsy's help I set up to work on FMy. I solved a few teething problems with the upgraded version of the DAQ system. In particular I had to get Daniel Sigg to update the utility xmlconv (for extracting data from .xml files generated by GDS). I debugged the software for tuning the yaw component of the output matrix using the OSEM sensors as a reference (which I had written on the last LLO trip but not tested). I updated the software for the pitch and position components of the output matrix with the improved output format that I had developed while working on yaw.

Since optical levers were available I took the opportunity to compare the results of the optical lever and OSEM sensor versions of the procedure for the position component of the output matrix. Unfortunately the agreement is not very good, at least for this optic. The tuning using the sensors gives crosscouplings to pitch and yaw equivalent to gain perturbations of order 10%. This is probably due to the effect of the PAMs on the normal modes. The input matrix tuning software tries to make the post-gain sensor signals have the relative magnitudes they should have assuming they represent a random mix of free normal-mode motion with modes of particular shapes. If the real mode shapes are different, it still shoehorns them into looking the ideal ones. This is only a relatively small perturbation for the LOS but it's comparable to the scatter in the OSEM sensor sensitivities and somewhat more than the typical scatter in the coil strengths. Therefore it's probably no use as
a reference, at least for LOS. Betsy and I will try the whole procedure over on a small optic tomorrow. Because there are no PAMs, there is reason to hope that the sensor method will be adequate. However a new method will be required for LOS. For the position components, probably the output matrix can be tuned first using the optical levers (acoording to the existing procedure), and then the input matrix can be tuned to it.

Input Optics

Dave Ottoway, Dave Reitze
This week at LHO the first small optic (and MC flat mirror) for the 4k was successfully balanced. The last of the 4k SOS passed the cleaning test and is ready to have guide rods, stand-offs and magnets attached.

Non-magnetic phosphor-bronze screws were sent to LHO for use in the SOS safety stops.

Core Optics Support (COS)

Mike Smith

1.2 LLO INSTALLATION & COMMISSIONING

Commissioning

Commissioning at LLO is still waiting for the installation to finish.

PSL

Joe Kovalik, Rich Abbott, Peter King
The new FSS board being installed in the PSL seems to have solved the oscillation problem which will make commissioning of the mode cleaner and subsequent parts of the interferometer easier. Made the modifications to the frequency servo that were done to the servos at Caltech and we are seeing the same performance as we did in the Lauritson lab.  To date, we have modified three servo cards and all of them seem consistent with each other.  We are able to run higher gains than before and the servo spontaneously recovers from a loss of lock without going into oscillation.  Also, the system is immune from oscillation when the wideband input to the VCO is triggered.  We are in the process of characterizing the system. We will be working on the PMC servo today with a goal of checking its transfer function against the LHO as built.

RF Distribution System

Rich Abbott
Installation of the frequency distribution system is hampered by the open vacuum chambers.  We are not able to run the cables to interconnect the various boxes at this time but all the material is on site to do it later.  Unfortunately, there was a lapse in communication that has caused three of these boxes to be set to the wrong frequency.  This will result in them having to be shipped back to CIT for retrofit and retesting.

Input  Optics

Dave Reitze, Sany Yoshida
More RFAM measurements - using a high power RFPD (LSC diode configured for broadband), we were able to get measurements at 100 mW by demodulating the RFPD output.  Instead of taking the RFPD output directly into a spectrum analyzer, we split the (+13 dBm) output from the Marconi -> EOM and -> LO.  (The modulation index was probably less than 0.5; we amplified the LO for compatibility with a level 23 mixer, which was all we had available.)  The output of the mixer was sent into an SRS audio spectrum analyzer.  After verifying that the noise was safely above the noise floor with the EOM off, we measured the RFAM spectrum and found: By changing cable lengths to discretely change the phase of the LO, it seems that most of the noise is in-phase.  Haven't looked at how stationary the measurement is; also, we still need to optimize the alignment of the EOM/pol.

LSC

Jay Heefner
System wiring diagrams and cross connect drawings are 75% complete and should be ready for wiring harness fab starting next week. The current plan is for Jay to visit LLO the week of 9/18 for installation completion and test of the LSC rack wiring and software.

DAQ System Update

Rolf Bork, Dave Barker
Primary purpose of visit this week is to update DAQ system to Version 3 (same as Hanford). This was completed 8/30, with testing to run thru Friday.  Only unit not up is south end station, which needs a new timing control module (Fedex should arrive tomorrow). Other tasks, as time permits, are updating Epics displays from Hanford, auto backup/restore, and alarm managers.  Some items, such as vacuum control updates, will probably have to wait for next visit.

Core Optics Support (COS)

Lee Cadenas
Assembly of both the ETM-X and ETM-Y arm cavity baffles are wrapped and ready to be installed at the end stations.

PSL

Peter King, Rich Abbott, Joe Kovalik
Power supply #103 has had the diode protection circuitry removed, per the manufacturer's recommendation. Thus far no dire effects have been observed.

The frequency stabilization servo has been modified to the same level as the one in the PSL Lab.  The servo has been installed and is currently under-going some tests.

2.0 Other Engineering and Scientific Activities

2.1 Design/Analysis/Fab

PSL

Lee Cardenas
I have assembled the new polished PMC and designed a small acoustic enclosure for the PMC.
I have been making  power measurements of the 10 watt Laser every single day in order to track the power behavior and possible degradation of the diodes.  This laser will be sent back to Lightwave for repair.

LSC Electronics

Dale Ouimette, Mohana Mageswaran, Flavio Nocero, Paul Russell, Dave Grimmett
Dale is getting all of the LSC and Timing System stuff organized and ready to hand off to Rich Abbott (LSC) and Mohana (Timing) before heading West. We (Dale, Flavio and Jay) are getting all of the wiring diagrams ready to ship to LLO so the LSC harness can be built up. Mohana is completing the design of the Mode Cleaner Servo. Paul is assembling the GP Differential Driver / Receiver boxes. Dave finished testing the Common Mode Servo Board 1 (2 each) and is installing a modification to the gain readback.

Mohana will be starting the protel design soon of the MC Servo. Preliminary noise analysis results:
        PSL output noise:       < 28.5nV/rHz    f > 100Hz
        MCA output noise:       < 6.99nV/rHz    f > 40Hz
are being reviewed.

Modulated OSEM Design

Jay Heefner


Nergis Mavalvala
We measured the sensitivity of the AC modulated OSEMs to 1.06 um light by modulating the laser intensity and measuring the response on the OSEMs on MC1 (the mode cleaner was misaligned out of the way). Comparison with the DC OSEMs showed a -20 dB suppresion of 1.06 um light, which is smaller than expected. The AC module will be further tested at Caltech.

New OSEM Heads

Janeen Romie, Myron MacInnis
The short ones have exhibited a plating problem. It is speculated by the plating company that this is due to 'porosity' of the surface; The surface finish of many of the OSEM MACOR heads manufacturered by one vendor was poor. The plating vendor is making a test run of three parts this week, or early next week, with heads that have a better surface finish.

The long ones have gone through their final vacuum bake at LLO and three heads have cracked optical filters. We are looking into alternative attachment methods. Despite these setbacks we're still working to get a full complement of new osems (36 short and 42 long) for the LHO 4k IFO completed in 8 weeks. Working on the assembly specification.

#D. Coyne: There were a number of QC problems discovered at Livingston in this first set of new sensor/actuator heads (OSEMs): cracked optical filters, loose coil wires, PD/LED apparently not flat on the ceramic circuit boards and PAM screws binding in the PAM brackets. Plans to install some new OSEMs in the Livingston inteferometer in this vacuum vent period are cancelled. Plans to install suspended optics in the 4 km interferometer at Hanford are on hold util these QC problems are resolved.

Jay Heefner
7 High current drive and 6 standard drive satellite amps are completed and ready for shipment to the sites. The high current drives are for the new OSEM design.

Digital Suspensions

Jay Heefner

Optics Metrology

GariLynn Billingsley, Helena Armandula
4ITM07 was shipped to Hanford on Monday.  A BS and RM are the remaining optics to ship for completion of the COC for the WA4K.  Three of 4 re-polished SPETMs were received from General Optics.  We have data from all three but have yet to analyze the results.

EO Shutter Control

Sander Liu
Received couple of 2KV high voltage power supplies from Ultra Volt, Inc. Currently in the process of replacing the bad 2KV power supply and testing in the final controller in stock.

Data Monitoring Tool

John Zweizig
This week I chased down a few bugs in the DMT softeware, wrote a root based trend viewer and started preparation of a new DMT software distribution kit.

Szabi Marka
We are developing a monitor script which checks for running Monitors on the DMTs and provides easy access to detailed information about existing monitors:
http://blue.ligo-wa.caltech.edu/gds/dmt/Monitors/spi.html

Global Diagnostics

Daniel Sigg Paul Russell
Delivered kits for fourteen (14) Printed Circuit Boards (PCB) to Accu-sembly for fabrication. He is in the process of completing the first unit for field testing.

2.2 Issues Concerns

None



40 Meter Interferometer (Weinstein)



 



Thermal Noise Interferometer (Libbrecht)


        We are finishing up the TNI mode-cleaner locking electronics by producing
a stand-alone servo box to replace a chain of SR560 amplifiers and
breadboard circuits.
 

        Magnets and stand-offs have been attached to the TNI test masses, and the
rate-limiting step is now OSEM electronics.  We verified that we have at
least two working OSEM controllers, and produced a preliminary design for
satellite amplifiers that communicate between the old-style OSEM
controllers and the new-style sensor-actuator heads.
 

        A design was laid out for a small breadboard optical table to be located
on the side of the TNI vacuum chamber, for output and diagnostic optics.
 


LASTI (Zucker)



Matt Smith:
> Corey shipped the Hilti Hammer drill last week from Hanford and we
> received in on Thursday.  We unpacked it and put it all together and
> determined we were missing some components for the water supply and
> ordered them from Hilti. In the mean time I jury-rigged our own hose to
> use water directly from our tap on the nearby sink. So far holes two
> piers are drilled.  The drilling is going smoothly, it took me about 6
> hours to drill 8 holes.  We should be done drilling by the end of next
> week.
>
> Ed Kruzel received the quote for the hardware which turned out to be in
> excess of 4K if he buys it all from one vendor. He is breaking up the
> order to buy the hardware from two different vendors which will end up
> costing less than if he bought all from one.
>
> Talked with Rich Reisen on the shipment of tools and fixtures that was
> shipped from LA on Monday and should arrive here by Friday.


Data Analysis and Computing (Lazzarini)



 
 

Simulation and Modeling

simulation work [biplab]

* Working on generation of noise-curves for Full W2K ITF.
  Faced some problems in holding the locked state when
  seismic noise is switched on after achieving steady-state
  in a static ITF.
  Worked with Matt on this and after a few hiccups, could
  find out suitable gain values of loops which could hold
  the ITF in stable locked state.

* Ran Matt's locking sequence for a few more cases. Upto
  a level of 1e-8 rad in width of white-noise in pitch/yaw in all
  mirrors, W2K could lock. Above that level of misalignment
  noise, no locking could be observed.  (very preliminary)

* Worked some more on refence cavity simulation using MSE
  generated time-series. The PSD plots show that most of the
  contribution in error signals (from mechanical motion
  and rotation of the cavity, assuming perfect TEM00 input)
  originate from the longitudinal motion of the whole cavity
  wrt the laser.

alfi [ed, bruce]

Completed work on the multi-line setting value edit capability.
Completed work on the deletion of ALFI components from parent nodes.
Working on identical box loading problem.

distribution [ed]

Started to work on installation documentation

LIGO Data Analysis System

  • Software Systems (Blackburn)

  •  

     
     
     

    The LDAS system has now been built and installed at Univ. of Texas
    Brownsville by Joe Romano. Wait, there's more...Joe has also been able
    to start LDAS running at UTB and has issued LDAS user commands to the
    system to carry out data conditioning on test data used in the MDC
    on the UTB LDAS system! Congratulations Joe! You're the first outside
    the core LDAS team do achieve this level of notoriety.

    The dataCondtionAPI at CIT has a new bug which cases the API to abort
    at startup when run on linux platforms. The abort was originally only
    happening when the manager started the api on linux but now it occurs
    each time the dataCondtionAPI is started. It looks as though memory
    (possibly in the kernel) is being overwritten. No other LDAS API has
    exhibited this behavior, isolating the problem to the shared objects
    specific to the dataCondtionAPI.

    The dataConditionAPI group is working on a "Developer's Guide to
    writing code module for the dataConditionAPI". A first draft has
    already been passed around the group and will soon be tested as
    new members from the LSC join the development effort for the
    dataConditionAPI.

    On last Friday a CIT SURF student was successful in writing a new
    shared object for the wrapperAPI which searches for wee-bangies in
    a data stream using simple parameterized waveforms. Work has also
    begun on getting an implementation of FCT ready for inclusion as a
    shared object for the wrapperAPI.

    LDAS worked closely with UWM this week to get LDAS and wrapperAPI
    to compile on their Alpha based Beowulf. We lack sufficient alpha
    hardware and staff here at CIT to do full alpha development so the
    use of their system has uncovered several alpha specific issues in
    the LDAS software which we have worked to fix (without breaking the
    working code on Suns and Intel's).

    The controlMonitorAPI is continuing nicely, now having more
    integrated support for monitoring the Beowulf cluster using
    internally developed interfaces and a public domain package
    called "bwatch".

    We have completed the initial planning for the Database Mock
    Data Challenge.  The main goals of this MDC are to certify
    the LDAS database as operational, to test the insertion of
    data generated by the Data Monitoring Tool (DMT) computers,
    and to establish a fairly complete set of user interface
    tools (both interactive and for use from within
    scripts/programs).  This effort will involve a combination
    of LSC members and LDAS personnel, with a target completion
    date tentatively scheduled for late November.  A specific
    list of tasks will be distributed within a few weeks, along
    with a call for volunteers.

    Quite a bit of effort went into cleaning up the LDAS build
    scripts and instructions this week. Several places in the
    code were found to inconsistently pass necessary compiler
    time parameters which influenced the behavior of the system.
    Much of this work was done with inputs and suggestions from
    the UTB group.

  • Hardware Systems (Anderson)

  •  

     
     
     

    Upgraded the main LDAS software server from an U10 to an E450 and renamed
    it from spica.ligo.caltech.edu to ldas-sw.ligo.caltech.edu.

    Finished performance evaluation of the new Sun fibre channel RAID box, see
    http://www.srl.caltech.edu/personnel/sba/ligo/raid

    Started acceptance testing first of 16 933MHz beowulf nodes for LDAS Caltech
    development system.

    Developed plan to migrate LDAS from ATM to Ethernet.

    Developed plan to complete the migration of LDAS Sun computers from Solaris 7
    to Solaris 8 after testing of DB2 database, ATM, AIT-2 tape robot, and
    Gigabit Ethernet where all successfully completed.

    Integrated LDAS filesystems so each LDAS location has a single NFS server.

    Moved vendor specific software used by LDAS to an exported filesystem
    general available at each LIGO site. This initially includes, Linux (kernel,
    redhat, howto), Solaris patches, Sun software RAID, IBM database,
    FORE ATM drivers.

    Received 30 slot tape robot and started work on tape archive script for
    upcoming engineering run(s) at LHO.

     
  • Data Analysis Activities
  • Jeff Edlund (summer student):

  • This week I made further modifications to the LAL implementation of the
    Fast Chirp Transform that allow user of the FCT library to specify their
    own function that will return a list of rows to calculate.  This will
    allow the user of the library to have more flexibility in dealing with
    interdependencies between the constants they are searching for.  I'm also
    writing the wrapper functions that will parallelize the code using the
    LDAS wrapper API.

    General Computing

    MIT:
    The Solaris 8 s/w has been installed on the 8 new Ultra 10's and the 450. The
    machines are ready for use with some minor file changes that may be needed.
    Replaced the sendmail program to help cut down on spamming.
    Resolved a number of other e-mail issues and some minor issues concerning user
    account setups. Larry needed a couple more days to handle a few more problems
    but over all most of the work related to the new install was accomplished.
    David S. is putting in a request for a few more IP addresses and names.
    A rack to hold the LDAS equipment and a few other items has been ordered.

    Livingston:
    Some network problems with LSU's network but they did not cause too many
    problems at the Observatory.
    Larry has contacted Bellsouth and they are working on getting some information
    together for the OC3 connection request. They will be contacting Mark Coles and
    Larry Wallace when they get the information.

    Hanford:
    Nothing to report.

    CIT:
    (Barbara)
    - Installed a first iteration of the revised Roster database.  Converted
    existing data and reviewed new features with Rita.  Added fields for LIGO I
    and LIGO II participation to tables, forms, reports, etc.  This morning saw
    that some full-time LIGO contractors will be considered LIGO members of the
    LSC so more changes will be needed.

    - Began work on an equipment database LDAS.  Defined the tables and began
    putting together the web forms.

    - Spent too much time researching a claim that a publication had been dropped
    from the DCC database when in fact it had never been submitted.  In the
    process uncovered another unsubmitted publication.

    (Sam)
    -Fixed a drive on Ed C.'s computer
    -Rebuilt sander's computer
    -Backed-up an old micron and paul r's old computer
    -Finally figured out the office2k key code. Will start doing installations
    this week.
    -Burned a bunch of Cd's
    -Rebuilt a machine using it's image (This works wonderfully, will save
    hours of work)
    -More work on web pages
    -More documentation

    Probably did more but it is too early in the morning for me to think.

    (Suresh)
    - Installed Solaris 8 on two new Ultra 10s.
    - Evaluating Checkpoint's RealSecure 5.0, an industry leading real-time
    intrusion detection and reporting package. It has been designed to detect and
    respond several hundreds of attacks and new attack signatures can be updated
    from their web-site.
    - Providing system and network related support services to 40 meter lab on
    regular basis.
    - Set up new users account and worked on few aliases.

    (Lisa)
    -I was really glad Larry came back from Boston.
    -Worked on PC issues at Wilson House.
    -Got the pieces of Cadence that Ligo uses fully installed, configured and
    tested.
    There are still some pieces left to configure but the critical portions are
    there.  WooHoo!
    -Pulled 2 of the sparc 5's from 3rd floor of Bridge and replaced them with Ultra
    10's.  Got 2 Ultra 10's installed in Wilson House as well.  Started building
    Ultra 10's with system 2.8 for the 6th Floor Milliken.
    -Started Monthly Backups
    -Revamped the daily/weekly backups (again).
    -Actively working on getting old equipment surplussed.

    (Larry)
    - Resolved a number of PC problems.
    - Worked/working a number of procurement issues. Still working on the payment
    for the big SUN purchase. Purchasing another laptop to be checked out for those
    that go on travel. Working on getting a few more projectors to handle the demand
    during conferences.
    Getting quotes for more network equipment. We have run out of ports at a couple
    of locations so we will be getting more equipment to handle the demand.
    - Working a couple of calendar manager issues.
    - Installing OS on a few of the new Ultra 10's that require special builds.
    --


    LIGO II/Advanced R&D (Sanders)


    Peter King wrote:
    >
    > 3. Other Engineering and Science Issues
    > ---------------------------------------
    > 3.1 LIGO II PSL
    >         Preliminary data characterizing 2 of the 24, 30-W 808-nm pump
    > diodes has been obtained.  The data recorded, output power and threshold
    > current, was consistent with the data sheets provided by the manufacturer.
    > Characterization of the remaining diodes is expected to take another week
    > before work starts on aligning the output of the pump diodes to the YAG
    > slab.
    >
    > The output of each 30-W diode is fiber coupled to the YAG slab.  Each fiber
    > has to be stripped of ~5 layers of cladding before the core can be cleaved.
    > Oddly enough a visual inspection of the cleave isn't sufficient to tell if
    > the cleave is a good one.  The true test being whether or not the fiber
    > starts burning when the diodes are energized.

    From Garilynn Billingsley:
    CSIRO has completed the measurement of our first two 15 cm m-axis sapphire pieces. On the referenced web page you will find links their report for these measurements along with pictures of the maps, similar to those shown at the LSC meeting. These pictures are screen shots from "Vision" software, the analysis software which is run in the metrology lab at Caltech and at CSIRO. The software is fairly powerful, if you would like more information than is shown, please contact GariLynn Billingsley.  Maps of fused silica substrates, taken during the fabrication phase for LIGO 1 are shown through the final link.

    From: Helena Armandula <ahelena@ligo.caltech.edu>
    Silica Bonding
    Manufactured a 1" pull tester to test some of Sheila Rowan's bonded sapphire/silica substrates early next week.
    Upgraded the design of fixtures used to "load" bonds. They are being fabricated.
    The plan is to compare, if possible, the results from the "loaded" bonds at different weights, with results from the pull tester.

    From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>

    Minutes before the meeting TAMA achieved its target of 100 Hours on
    time, we were happy to hone them our congratulations. 1.5 10-18
    m/rootHz!!!  See web site http://tamago.mtk.nao.ac.jp/
     

    Akiteru ? Szabi
    Oil bearing reassembled and better than ever (oil filtering and proper
    assembly sequence relevant)
    Horizontal TF now easy to make.  Disassembled IP to further reduce the
    flex joint diameter from 8 to 7.7 mm, then will mount and test new
    counterweights, then will mount F0, F1 and dummy payload to test full
    chain.
     

    Ruggero ? Giovanni ? Virginio
    Inertial damping loops closed individually angular and linear.  Good
    surprise; closing one d.o.f. does not excite the others!.  Next three
    days should be closing all d.o.f. together.
    Several software problems that appear to be computer dependent, is there
    a faulty connection?
     

    Francesco (Soy)
    Preliminary data trigger evolving,  see some event candidate.
     

    Virginio
    Fixing DSP software compiler, getting news from Motorola for new chips.
     

    Eric ?Luca ? Shanti
    Join the meeting and give short report TNI.
    Prestabilised laser suppressed in favour of laser locking to mode
    cleaner.  This is likely to be the final configuration; assembling the
    four test masses.  Expect data of TN before Christmas.
    Presented their estimations for a future low frequency evolution of TNI
    on SAS, internal noise should be visible with a 1/2 m Fabry Perot
    cavities, pedulum noise with a 1/2 cm cavity.
    Discussed on the possible options of making a cryogenic low frequency
    TNI.  Looks good and exciting.


    For additional information about this report, contact sanders@ligo.caltech.edu