Weekly Report for Week Ending August 24, 2000


 Exec. Comm. Agenda
Highlights
LSC
Administration
Hanford Observatory
Livingston Observatory
MIT
Caltech
Detector
40 Meter
TNI
LASTI
Data Analysis
LIGO II/Adv. R&D
Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  August 28, 2000 will be:
 (Meeting time: 10:30 am Pacific Time)

Open meeting 10:30 - 11:30

  1. Announcements
  2. LSC Issues (Weiss)
  3. Comments on Weekly Report
  4. WBS 1 LIGO I Construction (Lindquist)
  5. WBS 2 LIGO Lab Operations
  6. WBS 3 and 4  Advanced R&D and LIGO II (Sanders)
Executive Committee only 11:30 - noon
 

Special Items:


Special Announcements:

The LIGO staff directory roster is at:

http://www.ligo.caltech.edu/LIGO_web/sidebar/roster.html

It  is updated 2 to 3 times per month. Please use it in lieu of any paper rosters you may possess and use it instead of requesting information from the administrative staff.   -  GHS


Weekly Report Highlights
 
 


LSC Issues (Weiss)


No report this week.


LIGO I Construction/LIGO Laboratory Administration (Lindquist)


WBS 1.2 LIGO Operations--Administration


LIGO Weekly Site Telecon (Lindquist)


PROPERTY MANAGEMENT (Chargois)

From: Ed Chargois <chargois_e@ligo.caltech.edu>


DOCUMENT CONTROL CENTER (Turner, Mak)

>From: Linda Turner - turner@ligo.caltech.edu>

Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database.Take a look. . .

 ACTIVITY HIGHLIGHTS

From: Cleveland Mak <mak_c@ligo.caltech.edu> Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.


COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Akutagawa, Kaufman)

From: Esther Cunningham <esther@ligo.caltech.edu>

Press here for ACCOUNTS PAYABLE HISTORY DATA.

From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

No report this week.

From: Florence Kaufman <fkaufman@ligo.caltech.edu>



SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: irena@ligo.caltech.edu (Irena Petrac)

From: Ed Jasnow <jasnow@ligo.caltech.edu>



Support (Wood)

Dorothy Lloyd

Rita Torres Irene Baldon Elizabeth K. Wood

Advanced LIGO (Frey, Petrac)

From: Thomas Frey <tfrey@ligo.caltech.edu>

Progress Period from 8.11 to 8.24

Accomplishments:

Schedule: 8.25 to 8.31 Anticipated Challenges: Corrective Action: From: Irena Petrac <irena@ligo.caltech.edu>

WBS 1.4.1.2   Project Controls (LIGO Construction)

Reports (Lindquist)

I have distributed a draft of the "Report and Request for FY 2001 Funds" for review and comment (text portions only). Revised budgets for FY 2001 will be distributed shortly.

A quarterly progress report will be due shortly for the quarter ending August 31, 2000.  I am tentatively requesting inputs September 15, but we should probably discuss how best to fit this in.



Change Control/Contingency (Lindquist)

The following change request has been submitted:
 

CR-0000014 WBS 1.2.1 Additional Support Equipment for Commissioning D. Shoemaker

Press for the latest Contingency Needs Projection.


COST SCHEDULE CONTROL SYSTEMS (Duncan, Akutagawa)

From: Kris Duncan <kris@ligo.caltech.edu>

From: Cindy Akutagawa <cindy@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: Irena Petrac <irena@ligo.caltech.edu>

No report this week.

From: Ed Jasnow <jasnow@ligo.caltech.edu>

The schedule for the Livingston Staging Building has been finalized.   The Invitation for Bid will be issued on September 7,  the job walk will be held on September 21, and the bid opening will be on October 12.   Advertising for this project will be put in the Baton Rouge and New Orleans newspapers next week.


Quality/Safety (Tyler)

>From: Bill Tyler <tyler@ligo.caltech.edu>



LIGO Hanford Observatory (LHO) Operations (Raab)


General Items:
--------------
(F. Raab)

Staging activities continue for installation of the WA4K.
 

Optics:
---------------------
(D. Cook)

Most of this week has been dedicated to the preparations needed for the 4K
IFO installations. Assembling the optical lever reciever and transmitter
boxes, finishing out the transmission monitor boxes. Betsy is getting the
COS components built up and ready for bench alignments as well as helping
with COC processing and staging. I have been working with L. Jones to
assemble two detailed 4k installation specification documents to be used to
coordinate the 4k IFO installation. One for the end stations and one for
the corner station. This will help to organize tasks as we will be
installing all the COC, COS, IOO, componets as well as the support
equipment like the optical levers and transmission monitors, the beam dumps
and baffles during the same vacuum incursion. It is a check list to track
the progress of each step of the installation including the preliminary
testing of equipment etc. Assisted B.Butler in setting up a test to measure
the effects of the IR light on the 'new' vs 'old' OSEMs. He has posted the
results on the e-log (The new OSEMs are ~2000 times less sensitive to
1064nM IR).
 
 


LIGO Livingston Observatory (LLO) Operations (Coles)



 

OPTICS/COC/SEI INSTALLATION: Mark Guenther has spent the last week here debugging CAS software, and implementing changes that Hytec suggested. We have successfully run all 3 BSC CAS systems through a battery of tests, and we feel comfortable using the system, although an issue concerning the lower limit to the acceleration rate remains unresolved. (Thanks to Mark and Joe Hanson working both days last weekend!!) We installed high resolution position indicator on each axis of the Parker translation slides, and have performed preliminary characterization measurements. During the CAS testing, we have been using a loaned LDS-1000 laser autocollimator, in conjunction with our own unit which is a component of the IAS alignment setup. We note that each instrument yields a slightly different reading when placed in identical situations and we are investigating why. (Jonathan Kern)

Vacuum: Liquid nitrogen tanks at LLO are now full in preparation for check out of the cryo-pump controls.

Community Relations: Approximately 60 members of the Gulf Coast Section of the IEEE toured LLO this week.
 


MIT (Shoemaker)


Covered elsewhere.


Caltech (Sanders)


Covered elsewhere.


Detector/Technical Support (Whitcomb, Coyne)


 
Installation & Commissioning:
Hanford
Livingston
Other Science/Engineering Activities:
Design/Analysis/Fab
Issues/Concerns
See also the Installation web page

1.1 LHO INSTALLATION & COMMISSIONING

2km Commissioning

Daniel Sigg, Mike Landry, Richard McCarthy, Dave Barker, Nergis Mavalvala, Rolf Bork, Peter Fritschel, Matt Evans, Dick Gustafson, Bill Kells, Luca Matone, Stan Whitcomb
This week we have locked the PRM on the SB resonance along with an arm cavity resonating the carrier at the same time.  We were able to do this for either arm, but not for both simultaneously.

The things we found to be important in acquiring the PRM+ARM lock were:

Since locking the PRM+ARM we have: Based on these measurements we have calculated the parameters for the input matrix we expect to use to lock the whole IFO.

We were also able to image the beam spot on the ETMs using the frame-grabber.  Both spots seemed to be well centered on the optics. We expect this method to allow centering to within a centimeter or less.

LSC Software

Rolf Bork
Spent the past 8 days at Hanford.

DAQ Software

Rolf Bork, Dave Barker
Updated Hanford DAQ system to V3.0 software.   The outstanding problem is with the EPICS (slow) data collection.  The MIPS CPU used for this continues to run out of network sockets (we have not been able to find the source of this), thereby not connecting all requested channels, and eventually dies.  We ported this code to run on one of our Motorola processor boards, and we do not have the socket problems.  However, these CPUs can not keep up with data collection at 16Hz.  So, for now, we plan to switch to the Motorola CPU today, and reduce the acquisition rate to 4Hz for slow channels.  This will hopefully make slow data acq stable while we pursue porting EPICS over to a Pentium processor.

Suspension Controls

Jay Heefner
In the process of modifying and testing old satelitte amplifiers for use with the new OSEMs it has been determined that the 50mA LED drive can not be supplied by the present design. As an interim fix Peter F. and Jay decided to decrease the drive to 25mA and increase the PD gain by a factor of 2. This will maintain the sensitivity, but increase the noise floor. Both solutions of the AC OSEM should support the required 50mA drive.

Input Optics

Dave Ottaway, Haisheng Rong
Dave Ottaway and Haisheng continued the preparation of IO in-vacuum installation for LHO 4k IFO. The following is a summary of the status:
  We also verified the performance of the ionizing air guns at LHO with an electro-static fieldmeter. They have been tuned up and can now effectively remove static charges from the mirror surface, eliminating one major factor that can cause the mirror balance angle change.

Core Optics Support (COS)

Betsy Weaver, Mike Smith, et. al.

Optical Levers

Matt Smith
Received 6 photodiode boards and assembled 4 of them into their mechanical boxes and sent them to Hanford.  I have no more mechanical boxes and need to order them.

PEM Cosmic Ray Detector

Matt Smith, R. Frey, U of Oregon
The LHO cosmic ray detector was installed Aug 16. The detector, which rests on the floor below BSC1, consists of two 2.5x78x78 cm**3 scintillator slabs in an aluminum frame. Each slab is readout with two photomultiplier tubes having different gains. Clear signals from cosmic ray muons were seen on an oscilloscope.

The readout electronics is currently being assembled, with signal digitization to occur in rack 1x5. Data will be bundled in events triggered by large cosmic ray showers, with each event consisting of pulse height and time information.

LIGO-TriNet seismic stations

Szabi Marka
We have the STS-2 seismometers and the Episensor strong motion sensors. We are waiting for the Quanterra datalogger units (expected delivery 4-6 weeks from now, according to the company). The fiberglass structure was ordered. Scheduled delivery to Hanford is ~09/06/2000. We had a successful week (Alan Rohay and Szabi) and logged considerable streches of data during the last week. We set up one of the STS-2 units next to a USGS Guralp CMG3-NSN seismometer in the NIKE silo at Rattlesnake Mountain. We are currently retrieving the USGS data for direct comparison and calibration. Many thanks to Alan for his help!

1.2 LLO INSTALLATION & COMMISSIONING

Commissioning

Peter Saulson
No conventional commissioning to report.

We have made arrangements to continue our PEM audit into a second phase, without the help of UT Brownsville students. Doug Lormand will continue to work on this project; he will be assisted on a part-time basis by LSU undergrad Laura Schlecht.

Input  Optics

Sany Yoshida, David Reitze, Malik Rakhmanov
Finalized 4K PSL table layout:
- RFAM wedge pick-off placed in beam; RFPD aligned
- replaced the last of the old kinematic mounts with stable mounts

Measured absolute RFAM levels on the beam from the EOMS.  After optimization, all are dI/I < 5 X 10^-6 of carrier.  The New Focus 1811 RPFDs saturate at ~ 50 uW of input power, so shot noise and any frequency noise riding around the sidebands is below the noise floor of the measurement.  We are currently putting in a high power RFPD to get the shot noise up to a level where we can measure it

DAQ/LSC Software

Rolf Bork
Next week, will be at Livingston.  Plans include:

New OSEM Heads

Janeen Hazel-Romie, Peter Fritschel, Myron McInnis
Hope to install the new osems in one of the ETMs the week of Sept 4th. The osems must go in for clean and bake next week.

###SEW: Late update.  With the problems in the alignment of the core optics delaying the closure of the vacuum system, it looks like we will have the opportunity to put the new OSEMs on at least two of the optics in the LVEA.  We will attempt this unless it results in unacceptable delays.

Core Optics Support (COS)

Ken Mailand, Mike Smith, et. al. Lee Cardenas
Cleaned one of the IO Baffle black glass ready for bake.
Assembled the Outer frame for the  X-end ACBaffle.
Assembled the ACBaffle surfboard frame, black glass in progress.

PSL

Lee Cardenas
I Brought (6) PMC mirrors from CIT.  I have all of them  the vac-seal dissolved just using heated DI water.  All of them cleaned and ready to be baked.  As well as (1) of the 7mm dia. curved mirror cleaned and ready to be baked.

LIGO-TriNet seismic stations

Szabi Marka
We have the STS-2 seismometers and the Episensor strong motion sensors. We are waiting for the Quanterra datalogger units (expected delivery 4-6 weeks from now, according to the company). The fiberglass vault structure was delivered to the site. The contractor is ready to start the work.

Keisha Williams finished her term with nice results and paper.

2.0 Other Engineering and Scientific Activities

2.1 Design/Analysis/Fab

PSL

Peter King
An RMA # has been requested for laser #110 because the output power of the laser has dropped and the laser power supply does not permit the diode current to be increased from the front panel.

Measurements characterizing the modified current shunt have been completed.

Modulated OSEM Design

Jay Heefner, Rich Abbott
Following completion of a few more tests of the stabilized oscillator version of the circuit, it will be sent back to Caltech. Once at Caltech the output noise will be measured and hopefully an explanation of the excess noise will be found. In addition, a design of a better prototype that uses mixers more suited to the task has been started. The prototype tested at LHO was a quick turn around proof of concept unit assembled from parts and boards already in house.

Two prototype boards of the supressed carrier version of the circuit are stuffed and testing should begin by 8/24. Once bench tests at Caltech are complete a board will be sent to LHO for testing. The other board will be sent to Rai at LLO for additional testing.

New OSEM Heads

Janeen Hazel-Romie
Working with Betsy and Doug as they assemble and test the new osems. They will be cleaned, baked and installed at LLO. The rest of the new osems will be plated with zirconium nitride. I have asked for a quote to plate the remaining 30 short and 30 long heads from Superior Jig. Sending one spare zirconium nitride head to Oliver for coil winding Doug is having the new optic holder fabricated.

Digital Suspensions

Jay Heefner
Discussions of the LOS coil driver requirements and configuration are on going, but should converge on a design over the next week.

Data Monitoring Tool

John Zweizig
This week I worked on Data monitoring software at LHO. After the CDS frame builder software was updated, the DMT software stopped working. I traced this problem to the use of "seek" instructions on the data stream from the shared memory partition which were implemented, but not tested. After fixing this, I put the patch release (v1.2.1) into rpoduction on the DMT machines. In addition to fixing the bug mentioned above, the patch version fixed several other bugs found in the previous release and added some new functionality (e.g. Sergeys wavelet code).

I also finished updated the trend generation class to allow trending of multiple channels in a single trend frame and automatic writing of the trend frames. I then used this in a new program that monitors the time jitter of the ADC clocks relative to the GPS time reference. I found that the measured timing jitter is 50ns. Several effects (e.g. basline noise) have not been corrected and may contribute to the measured jitter. Rolf says that a <100ns jitter is expected of the GPS time stamp, so the measurement seems to be sufficiently precise.

Global Diagnostics

Sander Liu, Paul Russell
Received a quote from Accu-sembly Inc for assembling the 14 boards for us at $143.27 each. This is far below our estimated internal labor cost. Sub-contracting this type of work out may just be the most cost effective way to go. We are currently pulling kits to send to them for assembly.

2.2 Issues Concerns

None


40 Meter Interferometer (Weinstein)



 


Minutes of the third meeting of the
40 Meter Interferometer Technical Advisory Committee
Wednesday, August 16, 2000, LSC meeting at LHO.
 

Ken Strain (chair)    kstrain@physics.gla.ac.uk +44 141 330 5884
Minutes by Alan Weinstein, ajw@caltech.edu,         626-395-6682

- Ken Strain gave a brief resume of the newly proposed
  LIGO-II control scheme
  (I wasn't taking notes, so I can't do it justice)

- Ken went on to describe plans for a quick test of this scheme
  at Glasgow 10m. (ditto).

- AJW presented a host of transparencies (see
  http://www.ligo.caltech.edu/~ajw/G000194-00.pdf ).

  - Re-statement of objectives of the upgrade,
    posing the question of whether the control system risk
    is high enough to warrant 40m upgrade effort.

    ** There were very few comments made!
       AJW remains uncomfortable,
       and concerned about drumming up LSC interest/participation.
 

  - ** All of the key elements of the
    newly proposed LIGO-II control scheme
    can most likely be prototyped at the 40m
    in a straightforward and extrapolatable way.
    The smaller PRC at the 40m makes the control matrix
    a bit less diagonal, but do-able.
 

  - recent activity (dismantling, building rehab,
    vacuum control system, output chamber & seismic stack) described.
 

  - Preliminary optical layout presented, including 12m mode cleaner,
    and fixed steering mirrors and MMT lenses.
 

    ** AJW requested help/advice in analyzing noise produced
    by these fixed elements; no volunteers.
 

  - Need for active seismic isolation (STACIS) addressed.
 

    ** No one offered any wisdom on the analysis (MTTL,
       minimum frequency for evaluating rms motion, etc).
    ** It comes down to whether the installation
       can be effectively and safely managed.
       If Larry Jones says he can do it, we'll do it!
 

  - Question raised as to appropriate size of core optics
    (3", 0.25 kg vs 4", 1.56 kg).
    (Use 3" SOS optics for MMT1-3, RM, BS, SM).
 

    ** Still under debate, advice welcome!
 

  - Question raised as to choice of flat ITMs or symmetric arms.
 

    ** opinions favored flat ITMs. OK!
 

  - Very brief mention of designs for LSC and ASC,
    in the context of Jim Mason's control scheme.
    Designs will be updated for the new proposed LIGO II control scheme.
 

_______________________________
OK, now here's AJW's reconstruction
of the main features of the newly proposed LIGO-II control scheme,
as described by Ken Strain and Peter Fritchel:
 

  - phase-modulated sidebands placed before a 16.5 m mode cleaner
    at 9 MHz and at 180 MHz
    - two Pockels cells in series
    - parasitic modulations at 171 and 189 are not a problem...
    - some control signals using balanced RF sidebands
      cancel each other when operated in RSE mode,
      but only one sideband is used when detuned,
      so these control signals are present.
  - small Michelson l- asymmetry to put 180MHz on a bright fringe
    out the asymmetric port, while only a small amount of 9 MHz
    goes there.
  - beats between 9 and 180 (double-demodulated)
    gives clean separation between l+ and ls DOF.
  - Other DOF (L+, L-, l-) derived in the usual way.
  - GW signal to be obtained using DC locking:
    - let some carrier light come out the dark port, either by:
      - take arms slightly out of resonance in opposite directions
      - tiny (additional) Michelson l- asymmetry to let carrier out
      - They like the fist approach better; not sure why
    - beat carrier against signal sidebands to get GW signal
    - get rid of all RF signals with a short output mode cleaner
      (after picking the light off to control ls, L-)
    - Since only low-noise, arm-filtered light is used,
      extracting the signal at DC is not too noisy.


Thermal Noise Interferometer (Libbrecht)



 
 


LASTI (Zucker)


LASTI (Mason, Smith, Kruzel, MacInnis, Shoemaker, Zucker)
---------------------------------------------------------
SEI installation prep (Smith):
The pier anchor holes are marked on two of the three HAMS.  Ordered the
bushing tool to scarify the concrete floor.  The drill should arrive
thursday and some missing pieces needed to be ordered, which should
arrive Thursday or Friday.  Started to review the BSC pier installation
procedure and noted that we need a large jig fixture from Livingston
before the holes can even be located.  We should also be receiving the
springs(left and right epoxy and non epoxy springs from Hanford.)
 

Our bakeout vacuum oven needs to be put back together(missing scroll
pump) to bake out the spring seats.


Data Analysis and Computing (Lazzarini)



 

Simulation and Modeling

> PSL work continues

After sorting out various confusions, finally the reference cavity
simulation could be run with Cella-supplied time-series obtained
from mechanical simulation of this cavity.
It's found that the error signal peaks for its mechanical motion
correspond to frequency modulation with amplitudes of the order
of a few centiHertz or less.

> Noise curve

Key ingredients of noise sources, seismic, thermal and shotnoise, are
in the model now.  Biplab is working to iron out one or two oddities
in the E2E_generated noise  curves of W2K one FP system.
He will start generating noise curves for the full W2K LIGO
interferometer soon.

> Lock acquisition

Matt is working at LHO to lock the system.

Biplab is running the simulation to find the effect of the misalignment
on the Lock Acquisition.

> Thermal lensing

Hiro will start working to implement the thermal lensing in the current
optics/field implementation. This will be a minimal work to make the
simulation of the LIGO I realistic.

> alfi

An interface to edit a text with multiple lines has been developed.
This enables to edit complex mathematical expressions in function
parser modules.

> Manual

Hiro started to update the manuals, the primitive list and the getting
started.

> A new programmer coming

A new contract programmer is coming at the beginning of September.
His main task is the improvement of the simulation engine. Ed and
Bruce will still focus on GUI.

LIGO Data Analysis System

  • Software Systems (Blackburn)

  •  

     
     
     
     
     

         The issue with not being able to start multiple threads in the
         dataconditionAPI was solved this week. The command used to poll
         the state of a thread was fould to be "blocking" meaning that
         when you asked if a thread was still running, the result of asking
         was not returned until the thread finished. A polling command was
         developed for the genericAPI two years ago and available for use
         in the dataconditionAPI so it was used in place of the one that
         was developed specifically for call-chains. It immediately worked,
         allowing use to start multi-threaded call-chains across multiple
         cpus on a Sun 450. Having the multi-threaded capability did
         reveal that the handling of the results of threads lacked adequate
         indexing to associate results with issuing call-chain commands.
         This problem is being fixed in the TCL layer. Multi-threads also
         revealed a need for an association with thread-ids in the cases
         where threaded call chains throw exceptions. This will require a
         minor modification to the SWIG layer of the dataconditionAPI.

         The problem with sending multiple data sets out threaded sockets
         was also solved this week. The problem was identified as a compile
         time association with a non-thread safe malloc. The LDAS build
         scripts have been significantly improved to properly convey all
         the needed flags to build thread safe shared objects.

         The wrapperAPI documentation was modified this week to emphasis
         the indexing nature of the interface which was shadowed by the
         unfortunate use of the word template. This should make clearer
         understanding of the flexibility of the wrapperAPI.

         Work on the wrapperAPI has continued to improve its communication
         performance. It is now 150 times faster than the original version.
         I reported ~100x last week.

         We have started integrating a new dynamically loaded shared
         object for parallel searches into the wrapperAPI. The dso was
         developed over the summer as part of a SURF project and is an
         implementation to search for damped oscillators and chirps using
         simple physics models.

         The internal compiler error that was occurring when LDAS was
         being built at UWM has been traced and fixed.

         This was a very active week for giving personal tutorials on the
         LDAS system to members of the LSC visiting LIGO after the meeting
         last week. Five individuals asked for and received presentations
         which overviewed LDAS and one more is planned for next week. If
         nothing else, this past LSC meeting sparked interest in learning
         more about the LDAS design.

         Jeff Edlund (CIT Undergrad):
     

         I completed a prototype LAL implementation of the Fast Chirp Transform for
         an arbitrary number of terms.  This new implementation also allows more
         flexiblity in choosing the evaluation space.  For the next week and a half
         I'll be working on parallelizing and testing it.

     
  • Hardware Systems (Anderson)

  •  

     

    Electrical re-wiring of the CIT LDAS production machine room has been
    approved.

    Migration from the old Ultra10 LDAS software development server (spica)
    has begun to a new quad-processor E450 (ldas-sw). The new E450 was
    temporarily available as dataconsparc in the CIT ldas-dev network, but
    is no longer available as such.

    A 933MHz PIII test beowulf node from HPC was received and is being returned
    due to out-of-spec physical dimensions.

    A multi-vendor GigE switch interoperability test has been organized
    in conjunction with hardware from SRL at Caltech.

    ----- Forwarded message from Greg Mendell -----

    Report on Activity at LDAS-WA

    1) Detailed specifications have been received about various "enterprise
    level" Tape Libraries that might be used by LDAS.  These have been used
    to update drawings of the Mass Storage Room at LHO, showing the floor
    plan including the location of tape libraries.  Similear drawings have
    been requested from LLO.

    2) An analysis has begun to investigate the requirements needed for LDAS
    to write data to tape using automated scripts during upcoming
    engineering runs.
     

  • Data Analysis  (Lazzarini)

  •  

     
     
     

    The stochastic background paper Finn and I are writing has led to derivation of an
    optimal filter for the case in which there is inter-detector background correlated noise.
    This is a refinement of the optimal filter found in the current literature and includes the
    cross-spectral power density in a natural way.
     

  • General Computing

  • MIT:
    Checked the order that has arrived from SUN and it appears that all of the
    equipment has arrived.
    The SUN 450 and a number of the Ultra 10's are near completion for their s/w
    installations. All are having Solaris 8 loaded on them which means a number of
    the units now being used will have to be upgraded in the near future.
    The video switch and UPS are setup and working but need to be installed in the
    rack when it arrives.
    David S. is getting a few more IP addresses for visitor usage.
    A number of the old computers are being turned in and replaced with the new
    Ultra 10's.

    Livingston:
    General Computing budget issues are being worked on.
    Working on a number of maint. contracts and new purchases.

    Hanford:
    Nothing to report.
     

    CIT:

    (Sam)
    - Back from vacation. Worked on a switch box and developing some web pages
    concerning GC help for all the CIT LIGO users.
    - Fixed a few oracle items.

    (Barbara)
    - Reviewed the Roster database with Elizabeth Wood and made modifications
    per her comments.  Hopefully every flavor of visitor and resource can now
    be accommodated.   Developed a means for adding departmental information
    and printing the one-page paper directory.

    (Suresh)
    - Has returned from vacation. Assisted on getting 40M network back on-line.

    (Lisa)
    - Covering for Larry while he is at MIT.
    - Setting up more Ultra 10's.
    - Finishing the install of Cadence. There were some license issues such as a
    missing pkg. and incorrect license sent. Hopefully, all will be resolved before
    the old licenses expire.
    - Worked with Larry on trouble shooting a server problem.
    - Has found a number of machines (along with Stuart) missing their default
    router information. The machines have been taken care of but it is something to
    watch for.

    (Larry)
    - Worked a number of network issues in Bridge and went over some of the issues
    with Steve and Alan at the 40M.
    - Working some maint. contracts with SUN.
    - After discussions with Barry and Gary we've decided to mount the projectors in
    the conference rooms and we will purchase a few portable units to help
    accommodate the needs for conferences.
    - Working on Ultra 10 installations and testing some of the hardware.


    LIGO II/Advanced R&D (Sanders)


    From Riccardo DeSalvo:

    All SURFERS leaving.  Good luck.
    The lab will be emptier next week!
     

    Francesco, Soy
    Acoustic emission noise levels checked.
    Developing triggering scheme of average HF/LF ratio.
    Need to estimate actual noise levels.
     

    Akiteru
    After the good IP pendulum new oil bearing pump problems,  need to fix
    before arrival of new counterweights.
    IP flex joints that were at 9 mm (zero frequency for >200Kg load) have
    been modified to 8 mm (obtaining 175 mHz  frequency at ~120Kg nominal
    load) and will be modified to 7.3 mm (to obtain zero frequency for
    ~120Kg load).  This will happen after counterweight tests.
     

    James (left, report by Akiteru)
    Performed test of double TAMA MGASF, will see results next week,
    measurement, as expected, limited by accelerometer sensitivity at ?80
    dB.
     

    Brett (left, report by Virginio)
    PCB board finished plus program compiled.
     

    Lisa (left, report by Francesco)
    Need dedicated R?O station, system presently cannibalised.  Achieved 1
    um stability in LVDTs.
     

    Ruggero, Giovanni, Virginio
    Setup of Virgo’s accelerometers on LIGO IP completed.  Starting Inertial
    damping on complete IP plus 2 GASF tower.  Will make accelerometer
    inertialdamping without including the LVDTs for a first step.
     

    Alessandro, Carlo.
    Finally found the problem with the monolithic accelerometer
    construction.
    After breaking many tools in drilling and tapping the mechanics and
    wasting ages in EDM the drill bit corpses out of it, they passed to the
    final milling and immediately discovered the problem.  The tools did not
    break because of material hardness (as speculated so far).  The forged
    material is full of internal cracks (we paid a bundle for material
    certified free of defects from the most prestigious German firm) because
    of insufficient forging.
    As the defects are in the core, far from the flex joints, we will finish
    the parts and temporarily use the accelerometers while we will get
    replacements from the material provider (and damages, the material was
    certified).
     

    Susha, Giancarlo
    After some corrections, freeing some parameter and inserting the
    physical shape and the physical boundary conditions the simulation
    starts giving physical responses, still some problems.
     
     

    From: Helena Armandula <ahelena@ligo.caltech.edu>

    Silica Bonding
    I met in Stanford with Sheila Rowan and J. Hough.
    We discussed surface preparation prior to bonding.
    Cleanliness of the surface before bonding seems to be closely tied to bond strength.
    Investigated several cleaning methods:
    Cleaning with warm Liquinox; cleaning with Micro 90 at different temperatures; scrubbing the surface with cerium oxide; scrubbing with calcium carbonate.
    All these methods clean the glass efficiently, allowing  the water to sheet-off the surface, however, the scrubbing with cerium oxide and calcium carbonate achieve the results in minutes instead of the long hour the detergents take.
    We made some bonds at Caltech using calcium carbonate to clean the surfaces; some minor degradation of the surface was observed in two substrates out of eight, after cleaning.
    Scratches do not affect bonds as long as flatness is preserved.
    The bonds will be tested after some curing period.
    This scrubbing method looks very promising to clean the flats on the mirrors because it would be very difficult to clean those surfaces any other way.

    From: Phil Willems <willems@ligo.caltech.edu>
    Fused silica fibers/ribbons:
    ----------------------------

    We have measured the dependence of the Young's modulus on temperature for
    Suprasil fused silica by analysis of the free oscillations of a fiber at
    various temperatures.  The fractional change in the Young's modulus is
    +1.52e-4/K.  This data will be used to design the optimum fiber/ribbon
    dimensions for the suspensions in light of the nonlinear thermoelastic
    noise. (Phil Willems, Virginio Sannibale)

    From: Janeen Hazel <romie_j@ligo.caltech.edu>

    Working on Advanced LIGO issues.
    Working on 40m Upgrade.
     

    From: Sam Richman <srichman@ligo.mit.edu>
    Stiff isolation system (Sam Richman, Wensheng Hua)
     

    We have tested a controller in which the vertical signals are used to subtract out a tilt component from horizontal seismometers at low frequencies (~30 to 500 mHz).  The vertical signals can come from either position sensors or seismometers.  The tilt cancellation was measured and can be done quite accurately.  This has allowed us for the first time to close all of the upper stage loops with position sensors and broadband seismometers.

    From MIKE SMITH:
    LIGO 2

    Scattered Light Requirements:
    A preliminary scattered light requirement for LIGO 2 was completed, based on the LIGO 1 interferometer configuration; the requirement will be revised to incorporate the LIGO 2 gravity wave signal transfer functions.

    Conceptual Design:
    Preliminary conceptual designs for the ETM telescope, PO/APS telescope, suspended arm cavity baffle, and all other pick-off optical path elements and light control elements were completed.

    From PETER KING:

    3.1 LIGO II PSL
            Some modifications to the draft PSL schedule have been made to
    explicitly call out a few tasks, procurement of electronics components in
    particular.

    A start has been made on the PSL development plan.

    Characterization of the pump diodes for the Stanford slab amplifier has
    begun.  The pump diode assembly consists of 24 30-W pump diodes, each with
    their own thermo-electric cooler (TEC).  Each TEC controls the pump diode's
    temperature such that its emission wavelength is optimized for maximum
    absorption by the Nd:YAG gain medium.  Every pump diode is being temperature
    mapped.  Each diode temperature is stored so that when time comes to run
    the amplifier, each diode will be operating at its optimum temperature.
    This work is being carried out with Todd Rutherford and Shally Saraf.


    For additional information about this report, contact sanders@ligo.caltech.edu