Weekly Report for Week Ending August
3, 2000
The LIGO Executive Committee
Agenda for Monday August 7, 2000 will be:
(Meeting time: 10:30 am Pacific Time)
Open meeting 10:30 - 11:30
-
Announcements
-
LSC Issues (Weiss)
-
Comments on Weekly Report
-
WBS 1 LIGO I Construction (Lindquist)
-
Field Change Orders/Contingency Liens/Change Requests
-
WBS 2 LIGO Lab Operations
-
Administration (Lindquist)
-
Sites (Raab, Coles, Shoemaker, Sanders)
-
Detector (Whitcomb, Coyne)
-
Campus Research Facilities (Weinstein (40 Meter), Libbrecht (TNI), Zucker(LASTI))
-
Data Analysis and Computing (Lazzarini)
-
WBS 3 and 4 Advanced R&D and LIGO II
(Sanders)
Executive Committee only 11:30 - noon
Special Items:
Special Announcements:
Weekly
Report Highlights
LSC Issues (Weiss)
No report this week.
LIGO I Construction/LIGO Laboratory
Administration (Lindquist)
WBS 1.2 LIGO Operations--Administration
LIGO Weekly Site Telecon (Lindquist)
-
The site telecon on August 3, 2000 focused on the
disposition of the beam tube bake equipment, the FY 2001 budget model,
and the cost vs. budget numbers as of the end of July 2000. The list
of current actions revised to reflect open actions assigned through August
3, 2000 may be found at
ACTION
LIST.
PROPERTY
MANAGEMENT (Chargois)
From: Ed Chargois <chargois_e@ligo.caltech.edu>
-
Nothing significant to report.
DOCUMENT
CONTROL CENTER (Turner, Mak)
>From: Linda Turner
- turner@ligo.caltech.edu>
Web pages for the
DCC give simple how-to's for document numbering, easy access to the latest
on-line documents, and search capabilities for the DCC database.Take
a look. . .
ACTIVITY HIGHLIGHTS
-
During the month of July, a total of 69
new electronic documents were processed and made available. Additionally,
another 151 documents were added to the database. During the
same period, 130 faxes were sent and 143 received, while
52
packages were sent out and 123 were checked in.
-
The process of scanning all 40+ core optic
components files and making them available electronically continued.
-
I began preliminary plans for LIGO's Christmas
party, working on finalizing the date and location.
From: Cleveland Mak
<mak_c@ligo.caltech.edu>
|
In |
Out |
| Packages |
26 |
12 |
| Faxes |
27 |
30 |
Press here to access
the DOCUMENT CONTROL CENTER
WEB PAGE.
COST SCHEDULE
CONTROL SYSTEMS (Cunningham, Brambila, Akutagawa, Kaufman)
From: Esther Cunningham <esther@ligo.caltech.edu>
Press here for ACCOUNTS
PAYABLE HISTORY DATA.
From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>
Finished up the lease agreement. Have several subcontracts to
do and need to set up the files on these. Reconciled pcard transactions
and placed new orders on the pcard. Closed a few PO's out, but expect
to start closing PO's again on Monday.
From: Florence Kaufman <fkaufman@ligo.caltech.edu>
-
Started working on Operations reports for July.
-
At request of Sponsored Research Department prepared schedule of proposed
Budget Realignments for Construction accounts.
-
Prepared projection of expenditures for fiscal year 2000 Operations for
Hanford and Livingston.
-
Reviewed proposed 2001 Operations budgets for consistency with data for
2000 Operations.
-
Provided information to Albert Lazzarini for possible adjustment of Encumbrances
for Data Analysis Group on monthly Operations report.
SUBCONTRACTS MANAGEMENT (Petrac,
Jasnow)
From: irena@ligo.caltech.edu (Irena Petrac)
-
LaTech: CO#2 for a funding re-allocation, to pay
for costs incurred in shipment and installation of equipment donated for
LIGO research, was released to CIT procurement.
From: Ed Jasnow <jasnow@ligo.caltech.edu>
-
An orientation meeting on using the P-card for travel was held on Wednesday,
August 2. In attendance were representatives from Acquisitions and
Finance, as well as the LIGO cardholders whose cards will be capable of
being used for travel. LIGO is the only organization on campus participating
in this pilot program to develop a software module which will eventually
be used for reconciliation of travel expenses on the P-card.
-
The lease for storage space in Livingston was Fed Ex'd to the Mayor of
the town of Livingston on Wednesday, August 2. This space will be
used initially for electrical equipment from the beam tube bakeout.
Support (Wood)
Dorothy Lloyd
-
Worked with Ruth by receiving billed amounts on-line, to cancel lines for
various reasons or to close out and remove remaining encumbrances on POs
that are complete. Adjusted LIGO database accordingly.
-
Went over input of change order request for contracts, standard and blanket
PO requisitions in Oracle with Rita.
-
Processed the usual requisitions, invoices and receiving on-line. For more
detail see "Cost Schedule Control Systems" report by Esther Cunningham.
Tracked and followed up on invoice problems.
-
Reviewed and recorded payments processed by Esther for the week of July
24 on contract summary sheets and LIGO database.
-
Continue to monitor contract and blanket order funding levels and notified
task managers when supplements are needed.
-
Jim continues to do data entry in the LIGO database and help out in the
DCC.
Graphic provided by Cindy Akutagawa
Irene Baldon
-
Due to numerous meetings and training session on our new Travel P-Cards
I was unable to do much this past week (stats) This situation will continue
through at least this week. We will be up an running, ready or not, on
Monday morning (August 7th). There will be a total of 16 cards issued to
a representative cross-section of LIGO travelers. It is felt that this
group best represents LIGO's various travel needs. During this trial period
(3 months per the Controller) we need to either solve our problems or have
a course of action in place that will work before he approves the plan
for final use Campus wide. All participants will be asked to follow the
procedures and expect changes at any given time. This three (3) month period
will be constantly evolving/changing and everyone's cooperation and patience
will be greatly appreciated by all those who follow us. Thanks in advance!
-
Worked on preparing the paper work for eleven (11) new trips taken recently
or upcoming (11 Payment Requests and 10 Advance Requests). There are approximately
an additional fifteen (15) new trips in various stages pending completion
of travel arrangements before the paper work can be completed.
-
Completed all final arrangements for our SURF/LIGO/Hanford and SURF/LIGO/Livingston
Students coming to Caltech for a tour of LIGO/Caltech (40-meter, TNI, SAS,
etc.) and JPL on Aug. 3rd and 4th, and for our SURF/LIGO/Caltech Students
travel to LIGO/Hanford for their presentations and tours on Aug. 10th and
11th. All shuttles, vans, hotels, etc., are completed.
-
Have not been able to work on Expense Reports this week. I have 27 Expense
Reports to work on. I plan to work on these and other matters through this
weekend so that I will have relatively less pressure on Monday when the
new system starts up.
-
Prepared the Travel/Vacation Itinerary for the Week of July 31, 2000. Performed
normal recording and filing associated with Travel and Reimbursement. Worked
on several problem issues with Travel Audit. Also performed miscellaneous
duties as requested by various members of the LIGO Project here at Caltech
as well as from members of the staffs of each of the two (2) sites. I continue
to do MIT's travel to the sites for installation activities and also to
assist them wherever possible.
Elizabeth K. Wood
-
Corrected some Web internal charges that Florence discovered had been put
into the wrong account.
-
Did a lot of various activities related to visas, green cards, hiring,
and terminating. No exterminating, however.
-
Brought several visitors on board. Benoit Mours is in Millikan 612 , x
8510. B. S. Sathyaprakash is in Millikan 611, x. 8511. Giovanni Losurdo
is in WB 358, x. 3691.
-
I am continuing to do an amazing amount of check requests.
Advanced LIGO (Frey, Petrac)
From: Thomas Frey <tfrey@ligo.caltech.edu>
Progress Period from 7.28 to 8.3
Accomplishments:
-
Held LIGO II Project Controls meeting with Phil, Dennis, and Gary.
Focus of meeting was status of LIGO II Proposal.
-
Held meeting with Barbara K. regarding the Cost Book Tool. Agreed
that additional meetings will be informal via email or phone.
-
Incorporated version 11r1 of WBS to Primavera, and related changes to the
Chart of Accounts. Posted to site.
-
Proposal plan development for LIGO II and Operations continues.
-
Progress data as of 8.4.00 is due Friday.
-
Attended meeting with SEI and SUS groups.
-
Project Plan for the 40-Meter Lab Upgrade continues.
-
Final scope and mission of the lab is in flux. Should be finalized
by August LSC.
-
Updated the plan with progress as of 7.28.00 provided by Fred Asiri and
Peter King.
-
Planning process for the LASTI project at MIT is in progress.
-
Finished review of 2nd iteration.
-
David will issue 3rd iteration after LSC.
-
Initiated travel request for attendance at the LSC meetings from 8.15 to
8.17 at Hanford Observatory.
-
Development of the LIGO II Project Controls Guidebook continues.
Continuing to write section on data dictionaries.
-
Project Web Site for posting schedule and progress related data continues
to be updated with the latest and greatest.
Schedule: 8.4 to 8.10
-
Out of office on August 4th - in Portland for
Timberline Certified Trainer's / Consultant's Conference.
-
Next weekly meeting will be Monday afternoon August 7 from 1 to 3pm regarding
the planning and control of the LIGO II proposal development.
-
LIGO II Proposal Status meeting will be Tuesday morning August 8 from 9:30am
to 11am. Each system leader to discuss issues specific
to he LIGO II proposals.
-
No more meetings schedule with Barbara K. to discuss the Cost Book Tool.
Development is in final phases.
-
Will continue to follow up on the LASTI data development.
-
Will continue to update the LIGO II / Ops Proposal Plans and incorporate
any changes.
-
Will post progress report by end of day Monday.
-
Will issue fifth week of status data to teams.
-
Will continue updating the 40 meter schedule per progress as of 8.4.00.
-
Cost Book Tool development continues. Will be importing data for
Installation so that Dennis Coyne can proceed with estimating.
-
Will continue the development of the LIGO II Project Web Site.
-
Will continue the development of the LIGO II Project Controls Guide Book.
Finish section on data dictionaries and start on update process.
Anticipated Challenges:
-
Collection of schedule data is moving slower than anticipated.
Corrective Action:
-
None to report at this time.
From: Irena Petrac <irena@ligo.caltech.edu>
-
REO / LIGO II optics: A telecon was help with REO principals regarding
options for continuing collaboration (beyond LIGO I) in support of the
LIGO II optics coating pathfinder and production coating program. REO's
response was positive and constructive, however, the "rates have gone up".
WBS 1.4.1.2 Project Controls (LIGO Construction)
Reports (Lindquist)
I have distributed a second draft budget for FY 2001
Operations and already received some comments that will be incorporated.
Task managers are requested to provide substantive corrections by Friday,
August 11, 2000. I have also started the text portions of the submittal
for FY 2001 Continuing Operations. Everything related to the proposals
continues to be a month or so behind schedule.
Change Control/Contingency (Lindquist)
A meeting of LIGO Change Control
Board, Tuesday, August 1, 2000 at 9:30 PDT in the Science Conference Room
(SCR)
The following change requests were
approved:
| CR-000005 |
WBS 1.2.1 |
Upgrade Pre-stabilized Laser |
S. Whitcomb |
| CR-000006 |
WBS 1.2.1 |
Re-polish Core Optics Components |
S. Whitcomb |
| CR-000007 |
WBS 1.2.2 |
Replacement of Optical Lever Lasers |
S. Whitcomb |
| CR-000008 |
WBS 1.1.4 |
Cameras and Projection System at LIGO Livingston Observatory |
F. Asiri |
| CR-000009 |
WBS 1.1.4 |
Cameras and Projection System at LIGO Hanford Observatory |
F Asiri |
| CR-000010 |
WBS 1.2.2 |
Redesign Controllers for Large Optics Suspensions |
S. Whitcomb |
| CR-000011 |
WBS 1.2.2 |
VME Development System and Spares |
S. Whitcomb |
| CR-000012 |
WBS 1.2.2 |
ASC/LSC Rework |
S. Whitcomb |
| CR-000013 |
WBS 1.2.2 |
Redesign Controllers for Small Optics Suspensions |
D. Coyne |
Minutes of the LIGO Change Control Board have been prepared
and will be distributed (See LIGO-M000237-00-P).
Press for the latest Contingency
Needs Projection.
COST SCHEDULE CONTROL SYSTEMS (Duncan,
Akutagawa)
From: Kris Duncan <kris@ligo.caltech.edu>
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
-
I am gathering the data for the monthly reports for
July 2000.
-
Continue to reviewed the open encumbrances on the
Construction and Advanced R&D accounts to see if the requested removals
have been made. I will continue to review these accounts weekly until all
encumbrances have been removed.
-
Received the MIT invoice for June 2000. I processed
the data from the MIT TWONK report and got it signed and gave it to Esther
to be paid.
-
The financial reports on the web provide supporting
detail.
SUBCONTRACTS MANAGEMENT (Petrac,
Jasnow)
From: Irena Petrac <irena@ligo.caltech.edu>
CO #7 was processed for a-cost extension of the REO contract to allow
completion of ongoing coating and re-coating of LIGO I optics.
From: Ed Jasnow <jasnow@ligo.caltech.edu>
See above.
Quality/Safety (Tyler)
>From: Bill Tyler <tyler@ligo.caltech.edu>
LIGO Hanford Observatory (LHO) Operations
(Raab)
General Items:
--------------
(F. Raab)
Activities are heating up related to installation as evidenced by the
greater length of this report. An optic was scratched near its edge in
handling, but a review of the situation indicates it should not adversely
affect performance.
The Kamiakin SST team have gotten some nice measurements of ground vibrations
from the present gravel mine in south Richland. They have collected field
measurements at a number of sites at various distances from the plant,
with plant operations on/off and with varying distance from the local highway.
Analysis proceeds.
Bake Oven:
----------
(K. Ryan)
LHO Vacuum Bake Oven A load #98, consisting of misc. COS parts &
fasteners and misc. small optics beam dump and mirror mount components,
was released on 8-2-00.
Load #99, consisting of new OSEM bodies and misc. IOO (SOS top block)
and COS parts, is to begin vacuum baking on the afternoon of 8/3/00- to
be released on 8/7/00.
PreStabilized Laser:
--------------------
(R. Savage)
- Recently, a problem with the HVAC system in the LVEA caused a diurnal
temperature variation of several degrees Fahrenheit. As
a result, the PSL
output power varied by several percent. The HVAC system has been
patched
and the large PSL power fluctuations eliminated. M. Guenther
is using the
data from this accidental experiment in an effort to understand and
hopefully reduce the sensitivity of the PSL output power to ambient
temperature variations. M. Lubinski has installed a temperature
sensor
that is connected to the DAQ system in the 2k PSL chiller closet that
should help us assess the role of the closet temperature variations.
- We have received the acoustic insulation panels for the 2k PSL table
enclosure. We ordered panels covered with PVF film rather than
PVC film.
We don't notice any odor from the new panels as we did from the PVC-covered
panels. G. Moreno is using the 4k PSL enclosure to investigate
a method of
attaching the panels.
- T. Mahood has generated a new comprehensive optical layout of the
2k
IOO/PSL optical table using autocad. The layout is to scale,
+,- ~ 0.25
inch. He is in the process of updating the optical component
information
and is following the naming schemes devised by M. Guenther and the
IOO group.
- T. Mahood, D. Cook and R. Savage have begun installing the
upgraded beam dumps on the PSL IOO optical table. D. Cook has
cut the beam
tubes (1" diameter Al. tubing) to length and they are out for anodizing.
- D. Ottaway and R. Savage plan to release a new draft of the LIGO II
PSL
Conceptual Design Document (in the new Microsoft Word format) by early
next
week. It appears that the Design Requirements Review for the
LIGO II PSL
will not take place during the LSC meeting next month as previously
planned.
Optics:
---------------------
(D. Cook)
The ETMx-4k has its magnets/standoff glued and we will balance it Friday
and
get it into the Vacuum bake on Tuesday. ETMy-4k will be have the guide
rod
and wire standoff glued on Friday and the Magnets/standoffs and balance
hopefully in time to hit the same bake load on Tues. The ETM transmission
monitors are being installed after sorting through some minor confusions
and modifications. The optical levers will follow as parts are received.
The new OSEMs will come out of the bake and sent to MIT to be completed
and
tested. The ETM optics HR surface yields ~ 1% reflectivity at 633 nm.
This
is too low for our total station autocollimator. Upon its availability,
we
will borrow the one from LLO which has been modified and is more sensitive
to weaker return signals. We will use ours for the balancing and wedge
angle measurements in the interim. Betsy continues to build up the
COS
components as time allows.
Seismic Systems:
----------------------
(C. Gray, M. Guenther & H. Radkins)
Are seeing light at the end of the tunnel for the transfer function
measurements for a BSC Seismic Isolation Stack (at X-End). Have
performed
a few Swept Sine Measurements on the stack, but have had difficulties
producing coherence plots for these measurements. Will now try
to obtain
coherence data by using "white noise" as a source for our system.
Ribbon Cable Sag Test is still on going and Coarse Actuation System
(CAS)
cabling installation is a background activity.
Controls:
---------
(D. Barker)
Replaced 50GB Cybernetics RAID with 18GB Sun and 36GB IBM disks on
hanford1. Waiting for RMAs to return Cybernetics RAID and Tape Robot
for
repair. Using exabyte tape for CDS backups in the mean time, at a much
reduced rate.
Coding the next release of the DAQ ADCU code, which will run more
efficiently by using the DMA engines in both the onboard VIC64 chip
on
the baja, and the DMA chips on the VMIC 5588 RFM modules. This will
free
the baja CPU to perform digital filtering when decimating the data.
Data
transmission to the RFM will be more closely monitored. In cases of
network collisions a "back off then retry" algorithm will be used.
DCU
processing will be handled by three tasks instead of the current single
task, allowing for parallel processing of the tasks.
Completing the LHO EPICS save/restore system by forcing passive output
records to run at initialisation time to restore the saved setting.
Preparing for the CDS upgrade at Louisiana which will take place at
the
end of the month.
Physics Environmental Monitoring:
---------------------------------
(M. Lubinski)
We are changing the gain setting in the Endevco accelerometer
chassis (Isotron power supply, model 2793) from X1(factory setting)
to X10.
This will increase sensitivity of the instruments. We are also
working on
calibration of accelerometers to be able to correlate counts to acceleration.
We have developed a calibration method for the microphones using a Bruel
and Kjaer piston phone (model 4228) calibration unit with an attenuator
unit
attached. This calibration is in progress. All of the data
for the above
calibrations will be put on the CDS web page under "Installation files"
when completed.
LIGO Livingston Observatory (LLO) Operations
(Coles)
The new Pre Mode Cleaner is running continuously with 5.4 Watts of output
with 7 Watts of input power. The cavity FWHM was measured to be 4.5
MHz.
The old pre mode cleaner was open to the atmosphere and the feedback
voltage on the PZT to keep it locked showed a strong correlation with
atmospheric pressure. The new pre mode cleaner is hermetically sealed.
The
PZT voltage no longer shows any correlation with atmospheric pressure,
but
rather strongly correlates with the table temperature.
Sany, Haisheng, and Dave R. worked on getting the mode cleaner and MMT
aligned. We discovered that some of the cabling which carries
the MC
alignment bias voltage into the controllers had been crossed. Cables
are
now labeled and connected to the proper controllers. The MC has been
aligned to the point where flashes are coming through MC3. Beams are
centered on the mirrors to 1 mm or better. Pitch and Yaw biases for
the MCs
are in the range |1 - 4| V. Reflected and transmitted MC beams are
aligned
out of the chamber for IOT pickoff. MMT alignment - SM1 had to be shifted
a
few mm to center the beam on the mirror. Faraday is aligned; MMT alignment
underway.
MIT (Shoemaker)
All activity reported elsewhere.
Caltech (Sanders)
Kip Thorne has organized an association of the gravitation research
projects at Caltech and JPL. An organizing meeting was held last Friday.
Among other things, it was decided to combine and share the associations
seminar series with the LIGO series, approximately equally. The time for
the seminar series has been movedto a time convenient for the JPL attendees
so they do not have to make a roundtrip. Thus, in the fall,
the combined seminar series will meet on Fridays at 4 pm,
not at the old Tuesday 11:00 am time.
Detector/Technical Support (Whitcomb,
Coyne)
1.1 LHO
INSTALLATION & COMMISSIONING
2km Commissioning
Mike Zucker, Nergis Mavalvala,
Rana Adhikari
Trying to obtain multichannel
time series of single-arm lock attempt, with view toward comparison with
E2E results and diagnosis of locking problems described last week. Got
readouts working on internal recycling cavity pickoff light and got dark
port wavefront sensor working, although control loop code seems to be broken
and parts of both WFS demodulator boards on site turned out to be fried.
Debugging and repairing software and hardware problems continues and hope
springs eternal.
4km Suspensions
Janeen Romie, Phoenix Hoang,
Paul Russell, Helena Armandula
Working procurement of new
OSEM parts and fixtures. Fixture for mounting boards works; Physics machine
shop is making 8 more sets by 8/8. Phoenix is assembling the circuit boards.
Paul is making the PFA connectors. Helena is helping to write the assembly
procedure. Working on design documentation.
During processing of the
first 10 short and 10 long OSEMs, one short OSEM has broken. We will investigate
why/how this occurred and determine a course of action.
Supporting LHO personnel
with their processing/assembly of the ETM suspensions.
1.2
LLO INSTALLATION & COMMISSIONING
Input Optics
Sany Yoshida, Haisheng Rong,
Dave Reitze
MC alignment: We discovered that some of the cabling which carried
the alignment bias voltage into the controllers had been crossed.
Cables are now labeled and connected to the proper controllers. The
MC has been aligned to the point where flashes are coming through MC3.
Beams are centered on the mirrors to 1 mm or better. Pitch and Yaw
biases for the MCs are in the range |1 - 4| V. Reflected and transmitted
MC beams are aligned out of the chamber for IOT pickoff.
MMT alignment: SM1 had to be shifted a few mm to center the
beam on the mirror. Faraday is aligned; MMT alignment underway.
ITMy
Gary Traylor, Joe Hanson, Harry
Overmeyer
Completed reprocessing the
ITMy (as a result of the failed rear face magnet, which was in turn a casualty
of investigating why the aligment was drifting in pitch) and have installed
the ITMy back into chamber LBSC1. Alignment to follow.
PEM Audit
Peter Saulson
The first phase of our PEM Audit, carried out with students from UT
Brownsville, wrapped up with a final presentation by the teams working
on the tiltmeters and on the accelerometers. They are leaving behind a
written report of their work. It was a very successful student project,
that will leave a genuine legacy for LIGO. We will have to develop a plan
to continue the work with permanent LLO staff.
Core Optics Support (COS)
Lee Cardenas
Installed the (2) Black glass
pieces missing in the Cavity Beam Dump in BSC2.
Gathered all the COS spare parts,
which will be shipped to LHO.
Prepared and separated all the
parts needed to complete installation and alignment for the PO telescope
in HAM3.
PSL
Peter King, Joe Kovalik
The performance of the new
pre-modecleaner is being monitored. At one stage the visibility (1
- locked / unlocked) was tweaked to greater than 90%. This was found
to degrade during the installation of the pre-modecleaner for reasons unknown
at the time. Joe K has been monitoring the performance and concluded
that the laser power was varying during the periods of observed visibility
decay.
A small analyzer cavity
was fabricated to measure the PSL frequency noise. The analyzer cavity
has a PZT at one end, otherwise it is the same as the reference cavity.
Lee Cardenas
Gathered the old pre-mode cleaner
(PMC) assembly and set it in the optic lab to be taken apart carefully.
Gathered and shipped all the
equipment needed for assembly of a new PMC for the PSL at CIT.
Preparation for changing and
flushing the heat exchanger cooling water for the Laser is on-going.
Contacted Class One Co. for
the new Laser Enclosure with acoustic sound proof material.
Rich Abbott
Shipped a full set of frequency
distribution components to LLO for installation in the near term on a trip
to the site that I am planning.
SUS Electronics
Jay Heefner
This week we have received
3 broken LOS controllers. Two have been repaired and sent back to LLO.
One had a blown basic stamp. The other had a vaporized trace on a coil
driver output.
A blown satellite amplifier
has been received and is being repaired. It appears as though the 24 volt
input power had been reversed which blow up a capacitor and destroyed both
regulators. In addition two of the PD monitors are blown, the result of
being connected to a shorted cable. A second satellite received earlier
also appears to have been reversed polarized and connected to shorted cables
on the PD monitors. Both units will be repaired and sent back.
LLO One Arm Test
Jay Heefner
The system drawing and cross
connect lists for the one arm test have been completed and sent to Rusyl.
He will begin building the cross connect harness and installation of equipment
when he receives all the parts. The system should be ready for test some
time in early Sept.
Suspensions Controller Tuning
Mark Barton
This week I spent at LLO
doing more suspension controller tuning R&D. There were a number of
teething problems with the data acquisition system and the controllers
so I started with a fair bit of debugging. The MC1 controller had to have
its RS232 interface replaced and the SM1 needs the same fix. I ended up
taking some good data on MC3 and developed a new chunk of the procedure:
tuning the position component of the output matrix using the tuned input
matrix as a reference (as opposed to using optical levers).
2.0 Other
Engineering and Scientific Activities
2.1 Design/Analysis/Fab
PSL
Peter King, Rich Abbott, Todd
Etzel
A number of modifications to the FAST path of the frequency stabilization
servo have been made and studied by Rich and Todd, to improve the robustness
of lock and lock acquisition response. The servo at present limits
the FAST actuator dynamic range and places slightly more burden on the
SLOW actuator. In this configuration, with the FAST actuator centered,
the servo recovered spontaneously at operational COMMON and FAST gains.
With the FAST actuator voltage biased, recovery takes a little longer,
since the SLOW actuator is adjusted to correct for offsets in the FAST
actuator voltage. Once the SLOW actuator is adjusted to bring the
FAST actuator to within approximately 0.5 V of center, the servo recovers.
More investigations are continuing to see if this is a reproducible result
on a different servo card (of the same rev. level).
At present the SLOW actuator voltage is controlled by a simple deadband
algorithm. For better control, this will change to a EPICS PID record
to remove the +/-0.5 V deadband.
COC Metrology
GariLynn Billingsley, Michael
Hrynevych
Michael Hrynevych's last day was Friday July 28, best of luck to him
in his new job.
Measurement of 4ITM06 is complete, measurement of 4ITM07 has started.
4ITM06 shows a Radius of curvature of 13.68 km, comfortably within the
spec of 14.18 +140, -1000 The rms deviation from a perfect flat after subtraction
of Tilt Power and Astigmatism over 80 mm is 0.79 nm. The requirement is
that it be less than 0.8 nm rms.
LSC Electronics
Dale Ouimette, Mohana Mageswaram,
Flavio Nocera
Mohana is doing the re-design, including Cadence simulation for the
gain requirements and the noise analysis, for the Mode Cleaner Servo Amp.
Modulated OSEM & Digital
Suspension Controller Design
Jay Heefner
The schematics for the suppressed
carrier version of the AC OSEMs are 90% complete. Board layout will begin
by 8/4.
The prototype for the amplitude
stabilized oscillator version of the AC OSEMs is being tested. Initial
tests show amplitude stabilization of 1e10-5 to 1e10-6. It is hoped that
10e-7 can be achieved.
The document describing the
digital suspension controls has been released and a review has been scheduled
for 8/2.
The PD whitening and interface
boards for the LHO 4K SOS controls have been stuffed and will be tested
next week.
GDS electronics
Sander Liu, Paul Russell
Placed an order with Bloss
to fabricate the chassis faceplates. They should be back within the next
couple of weeks. Circuit boards from TechniCircuits should be in sometime
next week for us to begin assembling them.
DMT
John Zweizig
This week I continued to
debug and improve the DMT library software, including testing and fixing
the inverse Fourier transform code, reorganizing frequency series storage
to make it more obvious (although probably less efficient), writing a Perl
script to display the DMT data manager status, and updating documentation.
2.2 Issues
Concerns
Better MTBF Optical Lever Lasers
Mike Zucker, Ken Mason
Placed order for 30 new
optical lever lasers with Point Source ltd. These units have been engineered
for reliability and tested by the manufacturers; projected MTTF indicates
2 or fewer failures expected during LIGO I observation & commissioning
period. They will be integrated initially at H4k and then retrofitted to
H2k and L4k machines.
PSL Laser Supply Trip-out problem
solved
Peter King
I have been told that Lightwave
have "fixed" the problem with the laser power supply tripping out -- something
which occurs more frequently at LHO than at LLO. The problem being
that the diode protection circuitry was too sensitive to transients.
This has been apparently fixed by removing the protection circuitry. After
an engineering review, Lightwave Electronics decided to remove this diode
protection circuit from all their products, not just the 10-W LIGO Laser.
40 Meter Interferometer (Weinstein)
-
40 m Lab Rehab: Contractor has placed concrete for footings and slab for
additional room at Northwest side of the Lab. He has erected the wood framing
and outside paneling. It is about 15% complete.
-
Fred Asiri, Rick Karwoski, and Steve Vass met with an electrical engineer
and electrician from Physical Plant at the 40m. Discussed possible methods
to improve "clean" power distribution for the electronics work. We will
discuss these methods with Jay/Rolf and if they are in agreement, Fred
will obtain cost and schedule impacts for management decision.
-
Painters are stripping old paint off of the three overhead cranes in the
lab, in preparation for painting them.
-
Output Chamber: Fabrication of the seismic isolation and support system
for the Output Chamber is in progress at Caltech Central Engineering Services.
Fabrication is about 30% complete.
-
Papers placed in a time capsule under the NW corner of the 40m lab on 7/31/00,
G000179-00.pdf.
-
SURF students toured the lab on 8/3/00, and there will be a tour for political
reporters (in town for the DNC) on Monday.
-
In preparation for these tours, a set of 56 slides on LIGO physics was
made into seven 8-slide posters for display at the 40m lab, G000183-00.pdf.
-
Dennis Ugolini continues to bring up bits of the upgraded vacuum control
system. All gauges can be read on the EPICS screen, serial port communications
with ion pump controllers work, and read-back of valve and pump status
lines will be up soon. Remaining: relays for switching remote valves and
pumps, and shakedown of the control software, alarms, etc.
-
Steve Vass and Ivica have plumbed up the (empty) output chamber and are
pumping it down. After 2 days, it's already below 1e-5 torr, and RGA scans
are being monitored. We'll pump on it with a small turbo pump and then
a big ion pump, for some weeks; but it already looks to be pretty clean.
We will solicit advice from vacuum experts on the criterion for deciding
whether the chamber needs to be sent out for cleaning and baking.
-
Continued great progress from the SURF students: Ivica S. is modelling
the new digital LOS and SOS suspension controllers, and has a rather deep
understanding of its workings. Brian Kappus has a very nice WFS control
plant for dual recycling, both for LIGO II and 40m. Ten Jou has a variety
of good models for length control of a dual-recycled 40m (different signal
recycling tunes). Lisa Goggin has good designs for the 40m optics, including
12 meter mode cleaner and two mode matching telescopes. Jit Chauhan knows
how to build much of the GDS code on the 40m suns (his list of code to
install includes gds, diag, dmt, dataviewer, GRASP, and 3rd party stuff:
root, fftw, etc).
-
From Rick Karwoski: During the past week I continued my efforts on infrastructure
aspects of the new 40 meter facility. Specifically, I worked with Jay,
Fred and Steve to resolve power, grounding isolation and distribution.
We also met with the CalTech facilities folks who provided some fine input
regarding the matter. Over the past week the facility power issues have
become much clearer. After our final discussions with Jay today, I believe
that Fred and I have a good idea of how things might best proceed. Tomorrow
we hope to review our findings and recommendations with both of you. During
the other part of my life, I continued to delve into the details of the
LIGO system. A number of sessions with Stan has helped immensely in this
regard. Likewise general conversations with Jay concerning ISC particulars
and Rich regarding the PSL have been instructive.
Thermal Noise Interferometer (Libbrecht)
This week, still with Seiji's considerable help, we have been studying
the
noise in our mode cleaner frequency-stabilization servo. We measured
both
the electronic noise and the shot noise in our frequency measurement
system
(photodiode, demodulator, etc.) and found them to be comparable.
We have
also been moving components in the feedback loop around to improve
its
noise performance and to replace as many active components as possible
with
passive ones.
We have successfully glued magnets and guide rods to two test masses,
and
we plan to begin installing one test cavity in a few days. There's
a fair
bit of electronics that needs to be built before we will have a working
suspended test cavity, but we have decided to take advantage of Seiji's
expertise while he is here and install the mirrors anyway, clamp the
masses
down with their earthquake stops and look at the finesse and throughput
of
the cavity. The mirrors will remain under vacuum during these
tests and
while the electronics are being finished.
LASTI (Zucker)
LASTI: Continued work on documentation for LASTI program discussion
and review
for week of 8/15.
LIGO II ISC: Continued work on WBS dictionary. Circulated "fanciful"
hybrid
block diagram of sensing & control scheme, incorporating elements
of all major
modulation/readout schemes under current consideration, to act as a
strawman
for hardware & software cost effort.
HAM Installation
All parts and tooling for the installation of the first HAM seismic
isolation system has been located with the exception of an adapter
plate
and hardware. These items are short lead and will be ordered early
next
week if not found before then.
Installation is scheduled to begin 9/11. LLO will be sending 2 people
for two weeks to get us started.
Recieved and installed Algor analysis software to assist Stanford with
STIFF prototype design.
Data Analysis and Computing (Lazzarini)
Simulation and Modeling
Lock Acquisition
Matt is working to implement a better logic for Jim's RSE.
He is also working to find a better robust locking of LHO Michelson.
PSL
Rick, Brad and Biplab kept working to study the noise sources of
PSL using e2e. The result will be summarized in the SURF report.
(possibly LIGO note, or better yet publication?)
adlib
Biplab worked hard to trace bugs which were found when the mis aligment
effect for the lock acquisition was studied. The bug fix release will
be
very
soon.
alfi / GUI
A new version, 4.0.13, was released. New features in this release are
(1) better support of multiple directories
(2) better information feedback to the user
in addition to the fixes of some of the known bugs.
A few problems were found after the release and Bruce worked to trace
the cause. A new revised version is expected to be released very soon.
After that revised version goes through basic QA, it will be installed
at
LHO.
Improvement works are going on as well. Bruce is working to implement
a better interface to edit the settings. He is also working to implement
a semi-automatized ALFI test suite so that ALFI can be tested more
reliably after changes are made in maintenance and features are added.
LIGO Data Analysis System
Software Systems (Blackburn)
(Lazzarini for Kent)
This week has been consumed by an intense effort to perform the first
LDAS Mock Data Challenge. More will be provided next week. PSU, UTB and
ANU visitors have been working around the clock with LIGO people to complete
the challenge.
Hardware Systems (Anderson)
----- Forwarded message from Omar Rashad (LDAS SysAdmin) -----
Applied slight tweaks to LDAS servers requested for MDC
Resurrected muscida from temp storage for usage by visitors for MDC
Gnats:
Added MDC visitors to edit access for ldas-bugs database
Created associations from newly utilized mdc categories to responsible
email addresses
Corrected associations in the ldas_procurrements db to use alias groups
and migrated references in existing problem reports
Similar corrections should be applied to GC database
Installs/reinstalls:
Resurrected apache on ldas-wa after server hardware replacement
Reinstalling Linux OS on kitalpha and all 8 beowulf nodes to bring
them up
to must current official release
Helping with Linux install on users laptops
----- End of forwarded message from Omar Rashad (LDAS SysAdmin) -----
For Omar add,
Fixed hardware problem with ldas-pcdev1 that prevented it from using
both CPU's.
P.S. Should we consider opening up the GNATS ldas_procurement table
to
perusal by interested LSC members? I can imagine that some of them
will be interested to know when certain computational resources
will be made avilable.
Data Analysis Activities
New LIGO visitors to LDAS:
Sathya is here from GEO to work for one month with Tom, Jeff Edlund,
and myself one understanding how to integrate the Fast Chirp Transform
(FCT) approach with the standard template based optimal filtering approach
-- e.g., finding regions in the parameter space where there is complementarity,
etc.
Also, Beoit Mours has arrived for his year-long sabbatical visit from
VIRGO. He will likely work in two areas: user interfaces to LDAS (with
Peter Shawhan); multiple interferometer analysis (with Sam Finn and other
GWIC researchers in this area).
LIGO-SNEWS: (K. Ganezer, A Lazzarini, Sz. Marka)
We welcome Albert Lazzarini in our group. Albert helped us along the
way to draft our proposal and plans to participate in the development
of
our coincidence system.
We sheduled our introductory SNEW talk for the 08/2000 LSC Meeting
in
Hanford. We would like to use the opportunity discuss the project with
interested LSC members especially experts already working on burst
detection algorithms.
Jeff Edlund (summer student):
I modified the code for the Fast Chirp Transform (FCT) so that it
automatically corrects for phase functions that are not 0 at x=0 and
1 at
x=1. Phase functions are now only required to be monotonically
increasing.
I started a small web page to keep track of my progress.
I completed my comparison of the 2D FFT FCT method and our new method
that
does the FFTs of the columns by inspection. I showed that the results
at
powers of 2 were consistent with the change in order.
I'm currently working on understanding how to apply the FCT to
gravitational chirps from the binary inspiral of neutron stars.
General Computing
MIT:
Has received most of the SUN equipment from the special SUN order.
Larry will be traveling to MIT the third week of August to assist in
setting the
new computers up.
Livingston:
Nothing to report from General Computing. Bellsouth and LSC did have
some
network problems but they did not adversly affect the Observatory.
Hanford:
Preparing for the LSC meeting.
CIT:
(Barbara)
- Continued work on the web reports for the CostBook.
- Helped Irena with the LSC progress reports and research plans.
Made some
minor changes to the Access application.
(Sam)
Finished up a new PC build. Worked on documentation.
(Lisa)
- Finished monthly backups. This included centralizing the backup
scripts and
changing them to use hardware compression. We are still only
getting about 10G
per tape.I want to look into it a bit more to see if I can get closer
to the
14G mark.
- Added users to the dial up access. Will add an entry to the FAQ
on how to configure a user for dial-up. Will work on DHCP configuration
for
dial-up services.
- Changed (with Larry's help) the automaps on sirius and sadal.
Both servers
still had remnants of maps from kater and puma which was affecting
my ability to
install the new cadence software.
- Cadence installation has begun.
- Worked with Larry on moving the home accounts on home8 to a larger
disk array.
- Provided user support to Wilson House. Worked with Larry on installing
the
Multi-mode to Single-mode signal converter. The first test did not
pass on the
single mode connection so there will have to be some tweaking done.
(Suresh)
Still in Nepal visiting family.
(Larry)
- Still working procurement issues most dealing with LDAS but still
have a
number of items for the GC.
- Resolved a number of PC issues, most dealing with incorrect installations
of
s/w. Just a reminder for everyone to keep their virus-scan up to date,
we've had
a number of hits this past week and so far no major problems and the
virus-scan
s/w has helped in keeping the problems to a minimum.
- Installed a few more hubs and ran some more cable for the network.
- Working with Ed C. on getting some of the old equipment moved out.
- Started installation of equipment into a new rack.
- Working with Liz to get an area set aside for people to use the scanner
and CD
burner. Presently, looking at location on the third floor of Bridge.
LIGO II/Advanced R&D (Sanders)
From: Janeen Hazel <romie_j@ligo.caltech.edu>
Suspensions - Wednesday August 2, 2000
Working on LIGO II Proposal. Updated the Development Plan and the Table
listing which optic with which type of suspension (on the L2 Proposal
Suspension page.)
From: GariLynn Billingsley <Billingsley_G@ligo.caltech.edu>
A preliminary cost estimate has been received from CSIRO for polishing
a Pathfinder II piece. I will discuss this with them in depth when
I visit next week to take part in sapphire homogeneity measurements.
A SUS-COC interface meeting was held to try and find the dotted line
between the subsystems and to decide what type of requirements SUS might
put on COC. More in depth questions to follow, but it was a good
start.
From: Jordan Camp <jordan@ligo.caltech.edu>
Worked on LIGO-II PSL and COC proposal chapters.
Measured total loss and absorption of a 1" MLD mirror coating (MLD is
the Oregon
coating company founded by one of the co-inventors of the ion beam
sputtered
coating process.) The mirror appears to be in the supermirror category,
with
total loss (transmission+scatter+absorption) ~30 ppm, and with absorption
~1
ppm (comparable to the absorption of an REO mirror coating). At
present, MLD has no facilities for coating of LIGO size large optics,
but they
have expressed interest in the LIGO program and have asked for a copy
of our
coating specifications.
From: Virginio Sannibale <vsanni@ligo.caltech.edu>
Caltech SAS Seismic Group Short Report.
Akiteru
TAMA-IP transverse mode tuned at ~ 67mHz.
TAMA- IP Counter weight tunning: Coupling with the yaw mode fixed
by
using 2 accelerometers. Model to fit experimental data improved
by
considering an effective counter weight arm.
Brett and Virginio
Still working on the software to control the VME board to drive
the stepping
motor.
Lisa
finishing the cabling of the LVDT and testing the last 3 LVDT
drivers.
First run of the 3 reference LVDT placed into the oven seems
not to correlate
quite well with the temperature fluctuation. A better data analisys
is
needed
James and Akiteru
Transfer function measurement of the MGASF with different working
point under
progress.
Giovanni Lo Surdo
Remounting and re-wiring the IP sensors and actuators.
Soy and Francesco Fidecaro
Working on a Labview program to trigger the creak/creep noise
of a
loaded triangular blade.
Chenyang
improved the Q factor for the LC actuator circuit.
Virginio
Supervising the work of the LIGO-SAS surf students.
Working on fixing a bug on the DSP control program.
Hareem
Finishing the characterization of the MSGAF and GASF working
point
and Q factor of the vertical mode.
Susha Giancarlo Virginio
Found a better agreement on the simulation of the MGASF and the
experimental data for the blade working point. Fit of the blade
shape
under progress.
[1] From Peter King:3.1 LIGO II PSL
Quotations for various PSL-related components continue totricklein.
Currently the second draft of the PSL WBS Dictionary is beingworkedon,
after some guidance from the meeting held on Monday.
> LIGO II coatings> During a teleconference, REO reaffirmed their
intention to be involved with> the LIGO project.> They mentioned the possibility
of getting a dedicated chamber and staff to> support LIGO II coatings;
previous commitment ($$) from CALTECH is expected.>> Also, JM Mackowski,
from the Virgo coating laboratory, visited Caltech.> He also expressed
interest in making LIGO II coatings.> He had a very impressive presentation
about their capabilities. They have a> very complete characterization facility,
a coating chamber capable to fit> very large substrates, a very sophisticated
rotation / mask system capable> of correcting the surface wavefront in
a mirror.> However, they do not have cleaning or coating procedures in
place yet. They> just made some single coating layers.>>> A mirror from
MLD was tested, see Jordan's report. Maybe they can become a> good supplier
for coatings other than COC's.
For additional information about this report, contact sanders@ligo.caltech.edu