Weekly Report for Week Ending July 20, 2000


 Exec. Comm. Agenda
Highlights
LSC
Administration
Hanford Observatory
Livingston Observatory
MIT
Caltech
Detector
40 Meter
TNI
LASTI
Data Analysis
LIGO II/Adv. R&D
Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  July 24, 2000 will be:
 (Meeting time: 10:30 am Pacific Time)

Open meeting 10:30 - 11:30

  1. Announcements
  2. LSC Issues (Weiss)
  3. Comments on Weekly Report
  4. WBS 1 LIGO I Construction (Lindquist)
  5. WBS 2 LIGO Lab Operations
  6. WBS 3 and 4  Advanced R&D and LIGO II (Sanders)
Executive Committee only 11:30 - noon
 

Special Items:


Special Announcements:


Weekly Report Highlights

LHO 2K power recycled Michelson locked and Y arm ETM illuminated. Stay tuned...


LSC Issues (Weiss)


No report this week.


LIGO I Construction/LIGO Laboratory Administration (Lindquist)


WBS 1.2 LIGO Operations--Administration


LIGO Weekly Site Telecon (Lindquist)

  • There was no site telecon held on July 20, 2000.  The list of current actions revised to reflect open actions assigned through June 22, 2000 may be found at ACTION LIST.

  •  

     
     
     
     
     
     
     
     
     


    PROPERTY MANAGEMENT (Chargois)

    From: Ed Chargois <chargois_e@ligo.caltech.edu>


    DOCUMENT CONTROL CENTER (Turner, Mak)

    From: the DCC <dcc@ligo.caltech.edu>

    Linda is working on a limited, part-time basis.

    Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .

    From: Cleveland Mak <mak_c@ligo.caltech.edu>

     ACTIVITY HIGHLIGHTS

    Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.


    COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Akutagawa, Kaufman)

    From: Esther Cunningham <esther@ligo.caltech.edu>


    Press here for ACCOUNTS PAYABLE HISTORY DATA.

    From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

    From: Florence Kaufman <fkaufman@ligo.caltech.edu>

    SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

    From: irena@ligo.caltech.edu (Irena Petrac)

    From: Ed Jasnow <jasnow@ligo.caltech.edu>

  • A lease is being prepared for a building to be used for storage space for the power supplies used in the beam tube bake.  The lease is with the Town of Livingston, and is for three years at a cost of $1,500 per month.


  • Support (Wood)

    Rita Torres

    Irene Baldon

    PLEASE NOTE: This report covers only three days since I took two days vacation last week.

    Dorothy Lloyd Elizabeth K. Wood

    Advanced LIGO (Frey, Petrac)

    From: Thomas Frey <tfrey@ligo.caltech.edu>

    Progress Period from 7.14 to 7.20

    Accomplishments:

    Schedule: 7.21 to 7.27 Anticipated Challenges: Corrective Action:

    WBS 1.4.1.2   Project Controls (LIGO Construction)

    Reports (Lindquist)

    The end-of-May Quarterly Progress Report has been sent to the NSF.  I am terrribly behind on the rest of the stuff; the FY 2001 Operations Report and Request for Continuing Funding, the FY 2002-2006 Continuing Operations Proposal, etc.  With luck there will be no call-in for Jury Duty next week.

    Change Control/Contingency (Lindquist)

    The following change requests have been submitted:
     

    CR-990028 WBS 1.1.3 Beam Tube Enclosure Closeout F. Asiri
    CR-000005 WBS 1.2.1 Upgrade Pre-stabilized Laser S. Whitcomb
    CR-000006 WBS 1.2.1 Re-polish Core Optics Components S. Whitcomb
    CR-000007 WBS 1.2.2 Replacement of Optical Lever Lasers S. Whitcomb
    CR-000008 WBS 1.1.4 Cameras and Projection System at LIGO Livingston Observatory F. Asiri
    CR-000009 WBS 1.1.4 Cameras and Projection System at LIGO Hanford Observatory F Asiri
    CR-000010 WBS 1.2.2 Redesign Suspension Controllers S. Whitcomb
    CR-000011 WBS 1.2.2 VME Development System and Spares S. Whitcomb
    CR-000012 WBS 1.2.2 ASC/LSC Rework S. Whitcomb

    Copies of these change requests have been distributed to memebers of the LIGO Change Control Board (See LIGO-M000176-00-P).  Two change requests, those for cameras and projection systems are for information purposes only (they fall below the threshold for CCB review and approval) and will be entered into the budget baseline.

    Press for the latest Contingency Needs Projection.


    COST SCHEDULE CONTROL SYSTEMS (Duncan, Akutagawa)

    From: Kris Duncan <kris@ligo.caltech.edu>

  • From: Cindy Akutagawa <cindy@ligo.caltech.edu>


  • SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

    From: Ed Jasnow <jasnow@ligo.caltech.edu>

    A meeting was held on Tuesday, July 18, with the Caltech Controller, Al Horvath, his property consultant, Nancy Nerasaki, and the Manager of the Office of Sponsored Research, Dick Seligman.  Attending for LIGO were Florence Kaufman, Ed Chargois, and Ed Jasnow.  The purpose of the meeting was to determine the methodology of tracking LIGO property for Caltech.  It was agreed that the current LIGO property database being kept by Ed Chargois would be the one used by Caltech.  It was also agreed that, in accordance with the cooperative agreement, the intent at the time of purchase would be the criteria used to determine where title resides in equipment.


    Quality/Safety (Tyler)

    >From: Bill Tyler <tyler@ligo.caltech.edu>

    LIGO Hanford Observatory (LHO) Operations (Raab)


    General items:
    --------------
    (F. Raab)
     

    Efforts this week focused on locking the power-recycled Michelson. Stable locking was achieved last weekend and efforts to improve alignment behavior have helped. Now work is moving toward getting the Y arm to resonate as well.
     

    Doug has been doing staging work in the end stations to prepare for 4K optics installation. Corey and Hugh are converging on a measurement of the BSC stack transfer function.
     

    The Port of Benton is reviewing proposals to mine gravel at the north end of Richland, about 10 miles from LIGO. Alan Rohay of Batelle has been invited to some of the meetings and he has expressed concern that, in the absence of hard data on the the transmissibility of noise through the local terrain, it is hard to convince the Port not to proceed. Our SST team from Kamiakin High School has been working with Hugh Radkins to learn how to make seismic field measurements in preparation for characterizing impacts of man-made noise sources. Having completed their measurements characterizing the effects of traffic on a bump in one of our access roads, their next assignment will be to characterize the ACME gravel mining operations in the south end of Richland.
     

    We are planning a LIGO Public Lecture for the local community to kick off the August LSC meeting, featuring talks by Kip Thorne and John Wheeler. Wheeler has dual ties to Hanford history. In 1943, he was the lead scientist for the first plutonium production reactor, built at Hanford. Later, he gave birth to much of the science that LIGO will seek to uncover. Wheeler will be returning to Richland in August for the LIGO Science Collaboration meeting. While here, he will be signing his autobiography at CREHST, Sunday August 13, 3 to 4:30 p.m.  He will also appear at a public lecture with Kip Thorne at Battelle Auditorium, Monday August 14, at 7:45 p.m.
     

    Bake Oven:
    ----------
    (K. Ryan)
     

    Vacuum Bake Oven A load #97, consisting of Elliptical Baffle Components, Table Clamps and OSEM Cables, was released on 6/26/00.
     

    Load #98, consisting of misc. COS parts & fasteners and misc. small optics beam dump and mirror mount components, should begin on or before Monday, 7/24/00.
     

    Most of the modifications to oven A's control panel have been made but not all of these have been tested.
     

    Fabrication of Vacuum Bake Oven B has been delayed as the result of having to change vendors.  I expect oven B to be available sometime in late August.  Oven B will be used for
    small loads, i.e. fasteners, small plates and brackets, small optics and individual large optics and should improve turnaround times by ~30% or so.
     

    Seismic Systems:
    ----------------------
    (M. Guenther)
     

    CAS Status
     

    All CAS cables have been installed on BSCs 1, 2, 3. Position encoder
    readouts have all been tested successfully on these BSCs.
    Pneumatic assembly is continuing; we are expecting our back-ordered 1
    micron filters from Festo the week of 8/7.
     


    LIGO Livingston Observatory (LLO) Operations (Coles)



     

    OPTICS/COC/SEI INSTALLATION: In the course of COS installation we have discovered that the BSC tables are out of plane by as much as 0.015" in 12".  Not until after moving table weights around did we discover this. This of course makes the use of levels problematic; the appearance of being level depends upon where on the table one affixes the level!  The concern now is that we have perturbed the alignment of our ITMs, so we are removing the spoolpieces in order to re-setup the ISC theodolite and check their alignment. (Jonathan Kern)
     

    FACILITY: Met with Mr. Derral Jones, Mayor of Livingston and inspected the proposed storage building in town of Livingston. Finalized the term of lease and list of items need to be fixed in the building as condition of lease. Mr. Jones agreed to submit in writing the lease term. I have cordinated our discussion with Ed and Gerry.

      Met with John Desmond and Craig Sauvac the Architect for the new staging building. We have work out he arrangement of the Auditorium. They will finalize the architectural drawings for review by next Monday, July 24.(Fred Asiri)


    MIT (Shoemaker)


    Covered elsewhere


    Caltech (Sanders)


    Covered elsewhere


    Detector/Technical Support (Whitcomb, Coyne)


     
    Installation & Commissioning:
    Hanford
    Livingston
    Other Science/Engineering Activities:
    Design/Analysis/Fab
    Issues/Concerns
    See also the Installation web page

    1.1 LHO INSTALLATION & COMMISSIONING

    2km Commissioning

    Peter Fritschel, Bill Kells, Nergis Mavalvala, Matt, Evans, Julien Sylvestre, Rana Adhikari, Rolf Bork, Jamie Rollins
    Aligned the power-recycled Michelson (PRM) portion of the 2 km interferometer (consisting of the recycling mirror, beam splitter and two input test masses, and (after working out some minor bugs with the electronics) locked it using the digital control electronics from the LSC.

    Depending on alignment, the PRM frequently showed periodic alignment fluctuations which produced huge modulation of the power inside the cavity.  We had initially suspected 1 micron light coupling to the suspension local sensors, and had done various tests such as reducing the input light power and disabling and/or lowering gains on the local dampingloops, but had seen no clear effects. Then Bill K's keen eyes noticed an increase in the beamsplitter's (BS) optical lever signals when the PRM was locked; since we are sending no control signals to the BS, we began to again suspect 1 micron light coupling. This time we turned off all 4 damping loops on the beamsplitter, and this seemed to be the key: the periodic power fluctuations essentially went away, leaving only the 10-20% random fluctuations that we had seen from time to time. So it looks like the driven oscillations were caused by 1 micron light coupling into the beamsplitter local sensors, and that we were finding places by adjusting the overall alignment where less light was scattered into them. Bill K also notes that previous measurements of 1 micron light coupling into all the LOS local sensors showed a higher coupling to the BS sensors than the other optics. Since this initial test we have turned the BS damping loops back on, but reduced the gain in each loop to 1.0; this seems so far to be small enough to avoid the light-coupling driven fluctuations.

    The measured recycling buildup was a factor of ~7 for the carrier and about a factor 4 for the sidebands, in fairly close agreement with what is expected for the as-built cavity without the thermal lensing in the ITMs that will come into play when the full power is used in the interferometer.

    Since we made progress in understanding and curing the alignment oscillations, and had success with locking on the RF sidebands (using either the AS port or the Reflected Q-phase demod signal), we decided to go ahead and open up the Y-arm to look for the beam.  With the PRM locked on the carrier, we immediately saw the beam on the lower left edge of ETMY, so the input beam pointing was still reasonably good.  Rana adjusted the angles of ETMY and ITMY to get a circularly symmetric beam as seen by the ETMY transmission camera.

    We currently don't have the software and hardware to send a LSC control signal to ETMY, so we couldn't try locking the arm cavity; there is also currently no quadrant detector on the ETMY transmission beam. So we couldn't do much more, but we did learn one important piece of information: when we initially operated this system with the PRM locked on the RF sidebands, with any reasonably close alignment of the ETM, the cavity resonances would destroy the PRM lock. This is not good because in the lock acquisition scheme we are supposed to be able to transition from the PRM sideband lock state to state 3, which adds an arm cavity locked to the carrier. Then we found we could lower the Michelson (lm) loop gain (by a factor of 2-3) to keep the PRM stable as the cavity went through resonances.

    Before the next attempt, we will get the LSC hardware/software going at Y-Mid, and get the new ETMY transmission monitor assembly together.

    Suspension Electronics

    Jay Heefner
    2 SOS controllers have been tested in preparation for building portable suspension controllers to support LHO 4K optics installation. We should have 6 controllers ready by mid August.

    ASC/LSC Electronics

    Rolf Bork
    Installed new LSC software and supporting testing with requested changes as we go along.  Primary changes are:
     
  • Increased ADC clock rate to 32KHz and DAC clock rates to 1MHz to reduce pipeline delay noted by PF last week.  This reduced the delay to approx. the 1/2ADC sample time + 3/2 DAC sample time requirement, or 90-100 usec from input, thru processing to output. I will probably look at it closer on my test stand when I get back to Caltech, as the numbers don't quite add up ie 30usec  ADC delay + 30usec processing + ?? = 90.
  • Added an input matrix in addition to the output matrix.
  • Added input phase settings.
  • Mid station software upgraded to handle second DAC for LSC output and additional LSC parameters.

  •  

     
     
     
     
     
     
     
     
     
     
     

    I also hope to load and run the new DAQ software later this week.

    1.2 LLO INSTALLATION & COMMISSIONING

    Input  Optics

    Dave Reitze, Sany Yoshida, Haisheng Rong
    The alignment of the mode cleaner continued. During the course of the alignment, we discovered that MC3 (the mirror that was not re-glued) had a pitch balance angle outside of the controller tolerance.  We were able to correct this 'in-vacuo' by adjusting the wire cradle position.   We then discovered the same problem affecting MC2 (which was hung and re-installed prior to alignment).  We have no hard evidence as to the cause, but possibilities are a shift during transportation and miscalibration of the position sensor during the balancing.  MC2 has been pulled and will be re-balanced.

    Core Optics Support (COS) Assembly

    Lee Cardenas, Ken Mailand, Joe Hansen, Mike Smith, et. al.
    Began measurements with the COS alignment laser/autocollimator mounted in HAM2.  Observations of the return spots from the RM, ITMX and ITMY did not coicide, indicating possible misalignment, probably of at least two of the Core Optics.  The optics seemed to have an anomoulously large response to changes in the table tilt.  In the end it was decided to remove (at least) one of the spool pieces so that we can resurvey the ITMs using the ISC theodelite/autocollimator.

    PSL

    Peter King
    Fabrication of a new pre-modecleaner for LLO has commenced.  The PMC should be completed by week's end.

    ISC Design

    Ken Mason
    ISC Layout drawings D970220-C for Hanford and D970499-C for Livingston have been completed and filed in the DCC. The Initial Alignment Procedures T970151-C has been updated to include Livingston 4K alignment and has been filed in the DCC.

    PEM Commissioning

    Peter Saulson
    Doug Lormand and the UT Brownsville team have continued to check out PEM signal channels, and have started to characterize our first sensor, the tiltmeters. The team will soon add accelerometers and seismometers. We have been consulting with Mark Lubinski at LHO, Robert Schofield at Oregon for advice on tests to make and methods of documentation, and with Julien Sylvestre at MIT for help with his time-frequency software.

    ASC Electronincs

    Jay Heefner
  • 8 WFS demod boards have been tested and are ready to ship to LLO.
  • 4 WFS DC Whitening Boards are being tested and should be ready to ship by 7/21.
  • Suspensions

    Mark Barton
    With the help of SURF student Josh Smith, I got the updated suspension controller tuning software installed at LLO and tuned the input matrix for ETMy. We also adapted the input matrix tuning software for SOS and tuned the input matrix for MC3. This was the first SOS to be successfully tuned. The PAMs had been removed the day before and in contrast to previous efforts the procedure went perfectly smoothly.

    LLO Passcal Seismic Array

    Szabi, Keisha Williams (SURF)
    Keisha continues the thermal characterization of the test vault. The contractor will start to clear the triangular area behind the beamtube where the array will be installed. Kevin and Keisha tested the seismometers and dataloggers. They encountered only one faulty unit. We are working on the diagnosis.

    2.0 Other Engineering and Scientific Activities

    2.1 Design/Analysis/Fab

    PSL

    Peter King
    Drawings for a new smaller reference cavity vacuum chamber and vibration isolation stack have been sent out for bid.  The smaller design is partly motivated by the small amount of optical table real estate available in the 40m Lab.

    A new optical layout for the 40m Lab PSL has been initiated.  The current table will be somewhat more crowded than initially thought.

    Rich Abbott
    Further testing has revealed considerable insight into the behavior of the frequency control servo.  Several new topologies have been tested and each has brought me significantly closer to a robust solution.  Several more tests in the Lauritson lab are to be performed.
     

    ISC fab

    Matt Smith
    Finished all the piece part drawings for the Photon Calibrator.  They are all out for quote.  I am finishing up the assembly drawing and started the installation layout drawing that specifies the location for the support pier to the Photon Calibrator. I will supply this information to each site.  Holes will need to be drilled and tapped (3/8-24) on the optical lever tables at each end station.

    The machined parts for the last two ETM transmission monitors (for Washington 4K) have been completed.  I will finish the assembly of these two and ship them sometime next week.

    COC Metrology

    GariLynn Billingsley, Michael Hrynevych
    Measurement of ETM02 is now complete, ETMs 01 and 02 will ship to Hanford this week. Measurement of the 4K optics for the corner station are commencing.

    ASC/LSC/SUS Electronics

    Dale Ouimette, Mohana Mageswaram, Flavio Nocera
    I have finished the next generation of the Mode Cleaner Servo Amplifier  Block Diagram and given it for a review. I have fixed the oscillation problem which the LSC Anti Aliasing filter was having. And I will be working on the Mode Cleaner Servo Amplifier schematic.

    Suspensions/OSEM Head Re-Design

    Janeen Romie
    Working procurement of new osem parts and design of new osem fixtures. Oliver is sending 5 old heads here for cleaning and baking. These will be used for the suspension balancing until the new ones are complete. POs are out for three other coatings to compare with the zirconium nitride; ITO, silver and diamond/carbon. Sany sent small osems from Livingston to LHO for suspension balancing until the new ones are completed.

    Jay Heefner
    Work continues on the various AC osem ideas, but there is nothing new to report.
     

    Digital Suspensions

    Jay Heefner
  • The design of the suspension whitening filter board is complete and the boards are out for fab.
  • Jay has produced a more complete copy of the digital SOS design document and it has been sent to Peter F. and Rolf for comment. Once their comments are received it will be distributed to a wider audience.
  • Specifications for the anti-Image filter used for the LSC/ASC and SUS are just about complete. Frequency devices feels that they can meet the requirements by modifying one of their current products. These filters will be used to replace the filters that are currently installed on the LHO 2K and in all future systems.
  • Global Diagnostics

    Sander Liu
    All Vero chassis are in and front panel design is complete. Will send the front panels out for fabrication within the next couple of days. Except for a few long lead items, most electronic components are in.

    2.2 Issues Concerns

    Optical Lever Lasers

    Mike Zucker, Ken Mason
    MZ and Ken Mason met with Paul Rivers and David Pointer of Point Source UK at MIT on Monday.  They shared recent data on lifetime testing of their new temperature-regulated 638 nm product, which is optically compatible with our current installation.  They are projecting failure rates of a few percent at 24,000 hours, and could identify a gradual systematic increase in diode operating current (observable at the new design's power connector) as a precursor to possible failure some thousands of hours in advance.  As a result we would project no more than 1 or 2 such laser failures over the LIGO I observing period. We could also attain adequate advance warning (order months) to schedule replacement of degrading units without loss of observing time, assuming we accept the additional burden of monitoring their currents (7 to 9 additional slow channels per interferometer).  A fixed-price quotation for 29 units is in the works; production speed appears (just) adequate to equip the LHO 4k with the new units.

    40 Meter Interferometer (Weinstein)




    Thermal Noise Interferometer (Libbrecht)


    No report received.


    LASTI (Zucker)


    Vacuum/infrastructure: Ed K. completed some annulus leak rate tests and
    characterized the flow rate of our new HC/particulate/water vapor
    trapping backfill filter.
     

    Seismic isolation: Ken M. began mobilization for installing the seismic
    isolation external supports and some internals. Useful advice was
    obtained from LLO and LHO experts (as well as generous offers of
    much-needed help).
     

    Experiment design & test goals: Ken, Mike and David developed a baseline
    interferometer optical and control plan which we think strikes a good
    balance among the mission goals proposed by our advisory panel. We
    started optomechanical design (Ken), noise analysis (David) and control
    systems topology definition (Mike). We will seek feedback from the Lab
    and Collaboration at the August LSC meeting.


    Data Analysis and Computing (Lazzarini)



     
     

    Simulation and Modeling

    >> at LHO

    Matt participated in the Power Recycled Michelson lock.

    Biplab worked with Brad and Rick on effects of higher order modes
    on error signals and noises in Frequency Stabilization System
    (FSS) of PSL that includes the reference cavity.

    >> Adlib code

    Biplab, Luca and Hiro worked on the lock acquisition simulation with
    misalignments. Luca found that very small misalignment make the
    system too hard to lock, compared with the case with no misalignment.
    The problem was traced to a possible bug in the simulation code.
    Biplab looked into the case and make a temporal fix.

    During this study, the problem of the slowness of the simulation
    makes it take too difficult to solve the problem. To simulate
    one second, it takes a few 10 minutes and to see if once case locks,
    it takes several hours. This problem needs to be solved by both
    software and hardware. None has been achieved yet, because of
    lack of manpower, especially the software improvements.
    This will become a more and more serious problem as we go into
    the detail simulations including more modes.

    Biplab could generate noise-curve of only W2K arm including
    shot, seismic and thermal noises. Some questions of detail still
    to be sorted out.

    Hiro wrote a new input module to read data from a disk file. This
    is used y Biplab with Rick and Brad to read the data of the simulated
    reference cavity mirror motion generated by G.Cella. This simulation
    is used to test the noise caused by the motion of the reference cavity
    of PSL table.

    The idealistic solution is to use MSE fully integrated with e2e.
    G.Cella has written a code providing API of MSE for e2e when
    he visited here last time. Unfortunately, the integration has not
    been completed because of lack of man powers.

    >> Hardware performance test on Alpha and Pentium

    Chris Lee of CARA helped to run e2e simulation (lock acquisition case)
    on his Alpha machine to measure the performance. On his Alpha
    workstation DS20 and XP1000, running at 500 MHz, the speed was faster than sargas
    by factor of 2.53.   The same code was run on m71 (500 MHz Pentium) to
    find the speed gain of 2.11.

    >> Alfi

    Ed and Bruce are working on alfi. There are several issues to be solved
    before anything new are to be added/improved.

    LIGO Data Analysis System

  • Software Systems (Blackburn)

  • The CSCC meeting outside Athens included a significant number of talks on
    signal processing and computation. The signal processing talks were weighted
    towards applications of wavelets and time-frequency methods. Many of these
    applications seemed to be motivated by trend instead of applicability of
    wavelets and such. The signal processing community also presented several
    talks on advances in mathematical approaches for digital filter algorithms,
    though most of these were applied to hardware. The focus was to reduce the
    number of cycles needed to apply a digital filter (using mathematical
    transformations on the filter) and on reducing the number of interations of
    a digital filter to detect oscillations inherent in the filter design. The
    motivation behind these projects being to extend battery life in cellular
    phones and other digital hand held communications devices. One interested
    speaker presented the trend towards more and more expensive testing costs
    for large integrated software system, as much as 70% of software costs are
    in testing for such environments now. All in all the conference proved to
    be interesting but noticably less dynamic than a typical GW or LSC meeting.

    A new memory leak in the LDAS software was identified this week. The leak
    may have existed prior to this week but was not exercised until we had the
    support in the frameAPI to concatenate frame data into ILWDs via user commands
    from the manager.

    The dataConditionAPI has now been started up and run for several hours on the
    Quad PentiumIII box. This marks the first LDAS API to be run on a LINUX platform
    and the first to run on the quad PIII. The user command for this API is still
    under development and only a handful of action functions are available for the
    algorithm. This does make the group a bit more at ease about being ready for
    the Mock Data Challenge at the end of the month.

    The wrapperAPI has now been shown to run with the binary inspiral search
    dynamically loaded shared object library from UWM on linux platforms. In fact,
    the results produced by the run are in agreement with other codes that perform
    the search. This is a major success for the parallel analysis working group
    and even though much work remains ahead on this project they have demonstrated
    a very important component of LDAS to work.

    A new test script is being developed to run nightly which will test each LDAS
    API for start up CPU and MEMORY usage to be used as a first look into the
    process loads and derivatives for APIs as they develop and evolve. It will also
    test that the API can actually be started without aborting nightly.

    The multi-client GUI interface to the controlMonitorAPI for LDAS is now
    working. The server side can distinguish unique requests from separate users
    to monitor LDAS and present the requested information appropriate the each
    request.

    The problem with NaN (Not a Number) reads in the ILWD that were found last
    week have been tracked down to the standard library in C++. The fix was to
    use C's standard library functions instead of the iostream from C++ to be
    able to correctly handle NaNs.

     
  • Hardware Systems (Anderson)

  •  

     
     
     
     
     
     
     
     
     
     
     

    1) Initial installation of Solaris 8, GigE cards and D1000 disk array
    in the two new LDAS E450's at LHO is complete. Work is ongoing for the
    installation of LDAS software as upgrades for the current U10 dataserver
    and U10 metaserver.

    2) The beowulf rack equipment from LLO has made it to LHO and awaits a final
    decision on the floor plan before installing. The CIT development rack
    installation is 90% complete.

    3) The gateway to the current LDAS system at Caltech has been renamed
    from ldas.ligo.caltech.edu to ldas-dev.ligo.caltech.edu to reflect
    its function as a development system and to make room for the installation
    of the Caltech production system starting in August, which will have
    the gateway named ldas.ligo.caltech.edu.

    4) A dual processor Linux box has been added to the LIGO GC network
    with the necessary configuration to access LDAS software and be used
    without need for coordination with the LDAS programmers as a software
    test-bed by LSC programmers. It is named ldas-pcdev1.ligo.caltech.edu.
    Expect a similarly named Sun computer (ldas-sundev1) in the near future.

     
  • Data Analysis Activities

  • >From Philip Charlton:

    Main activities have been preparation for the Data Conditioning API Mock
    Data Challenge which begins in the last week of July.

    I have also been working with Antony Searle at ANU towards getting the
    LDAS system to build on Sam Finn's machine at Penn State.

    Last week I finished the real and complex versions of the fast exact
    quadratic chirp transforms and sent them to Julien Sylvestre. He will
    be integrating this code and that developed by Jeff Edlund into his code
    for analysing the data from the engineering run.

    >From Jeff Edlund:

    I completed the first draft of the fast approximate chirp transform for a
    phase function with an arbitrary number of parameters. This version
    improves upon the original code from Rick Jenet by doing many of the FFTs
    by inspection when the sequence to be FFTed has only one non-zero
    element. I tested it with 2, 3, and 4 parameters. The chirp was found
    exactly in the 2 term case.  With 3 and 4 parameters, accuracy was limited
    by memory.  Further testing is required.

    I'm working on measuring the execution time of the algorithim at various
    data sizes to determine the order of the algorithm and compare the
    execution time with that of Rick's code.

    > Lazzarini
    I am working with Sam Finn on a short note for publication that deals with an
    improved measurement of the narrowband stochastic background that will be possible
    using the LLO+Allegro pair. The idea is to modulate the background by rotating Allegro
    periodically (once every ~1/2 year, e.g.). Unfortunately, LIGO I senstivie at ~1kHz is not as good as Allegro's.
    Nonetheless the technique allows one in principle to deduce correlated terrestrial backgrounds.

    General Computing


    MIT:
    Still preparing for new computer room installation. Detailed information about
    the room has been sent to Albert and Larry.
     

    Livingston:
    Working on their mirror of the DCC.
    Continuing work on the network backbone.
     

    Hanford:
    Nothing to report

    CIT:
    (Barbara)
    - Installed a first iteration of a web report for the CostBook.  Installed
    changes to CostBook web forms for Management resource.  Imported updated
    tables from P3.
    - Made changes to LDAS images and scripts for new server arrangement.
    Added/updated links for User Commands, LAL, and LDAS Build.
    - Made web site changes -- new page for science seminar transparencies,
    updates to fellowship pages, couple of LSC documents.

    (Lisa)
    - Rebuilt the OS on graffias. Learned how to set up a NIS+ client.  This has
    also gotten me into looking at how NIS+ and NFS mounts are working in our
    cluster.  Since there are a couple of areas in which the NFS mounts need to be
    changed (like Luna), I am spending a lot of time trying to really get a good
    picture of how all of the pieces are coming together.
    - Spent time working on the PC's in Wilson House.  Rich Abbott is getting moved
    off of his old box. We should be able to recover that for someone else by the
    end of the week. Spent a little time with Mohana clearing up some lingering
    issues. Reworking the basic network setups on the PC's this should clear up some
    of the network issues at Wislon House.
    - The new Cadence software and the hard disk for it have arrived.  I will be
    working on getting that installed this week.  We have another temporary license
    to use while the installation takes place.
    - Still plugging away at getting specs and prices on an upgrade for our Remote
    Access Server. I should have all the info we need to make a decision today.
    - Finished running new network cables and hubs in our office.

    (Samantha)
    - Built a new PC for 40M lab.
    - Worked on more documentation.
    - Built a machine to test WIN2000 on.
    - Still working on NT server items such as a new backup method.
    - Backed up files for people.
    - Burned a number of CD's.
    - Testing norton anti virus (installs just fine on every computer tested on
    except mine). Once our licenses for McAffee expire we will switch to Norton on
    Caltechs site license.
    Picking on Ed Chargois.

    (Suresh)
    On Vacation until August 23rd.

    (Larry)
    Finished up some cabling in a few different areas.
    Spent a great deal of time working on budgets and procurement plans.
    Resolved a number of issues on the servers. Going back to make sure the units
    are rebooted at least once a month just to fsck the disks and clean out old
    processes. The reboots will be scheduled after the monthly backups.
    Worked a number of procurement issues and still working with Ed C. on getting
    some of the old equipment cleaned out.
    Went over the network situation for the Lab Room in Bridge that the CDS group is
    going to occupy.
    Helping Lisa and Sam become more familiar with the server setup and network
    setup here at CIT.
    Resolved some licensing issues with Cadence.


    LIGO II/Advanced R&D (Sanders)


    Peter King

    LIGO II PSL
    The first draft of the LIGO-II PSL WBS dictionary has been
    completed.
     

    Rich Abbott

    Began process of cost estimation for LIGO II frequency distribution assuming a similar requirement to the LIGO I system
     

    From: Jordan Camp <jordan@ligo.caltech.edu>
    The following is a status report on the sapphire development program:

    Polishing: 2 half size test samples have been sent to CSIRO for optical
    characterization, including measurement of optical inhomogeneity. Preliminary
    measurements showed about 0.15 wave peak-valley inhomogeneity in transmission
    through the substrate, an encouraging number. After characterization, the optics
    will be polished to see if they can be brought to specification for surface
    figure, microroughness, and homogeneity.
    Q measurements: Q's of bare polished sapphire pieces have been typically better
    than 2x10^8. Measurements of the effect of attachments and coating on Q are
    pending.
    Coating absorption: absorption measurements of coatings of both c and m axis
    sapphire have shown < 1 ppm absorption.
    Coating birefringence: a preliminary experiment which measured resonant
    frequency spacings through a Fabry Perot cavity showed about 10 mrad
    birefringence for a 100 ppm transmission coating on an m-axis sapphire
    substrate. This number was consistent with an earlier experiment by Blair, and
    is probably low enough to permit the use of m-axis coated sapphire, but further
    work in mapping the birefringence is necessary.
    Substrate absorption: measurements of substrate absorption have been made of 4
    different starting materials from Crystal Systems, at 3 different places in each
    boule (to look for possible segregation of impurities). The data shows no
    correlation of material or boule location with absorption. The average value of
    absorption is 80 ppm/cm. Further measurements will involve zone refining of
    sapphire boules to produce higher purity material, and annealing studies to
    examine the effects of oxidation on the absorption. Measured samples will also
    be sent out for spectroscopic analysis to see if any correlations can be made
    with absorption and chemical composition. We have also received a couple of
    sapphire samples from SIOM, China which will be measured for absorption.

    LIGO II ISC (Zucker, Bork, Ouimette, Heefner, Fritschel, Mavalvala, Sigg, Abbott)
    -----------------------------------------
    MZ agreed to provisionally take the lead organizing LIGO II ISC
    definition for the proposal. Please copy Mike (and continue to copy
    Dennis, Gary, David and Peter Fritschel) on significant LIGO II ISC
    interface & requirements issues.
     

    Began drafting of reference design document and WBS to support proposal.
    Significant input on modulation & sensing topology will be required from
    the next Systems/Config summit and the following LSC meeting discussion.
    We have enough to start on describing the actual controls
    electronic/software implementation (in a "plant-independent" way at
    least), much of the alignment system, photodetectors, and some top-level
    requirements definition.

    From: Helena Armandula <ahelena@ligo.caltech.edu>

    LIGO II coatings:
    A conference call with REO and LIGO management will take place next week to discuss the possible involvement of REO as LIGO II coating's supplier and to formulate plans.
    SIlica bonding:
    (See P. Willems report)
     

    Stiff isolation system (Sam Richman, Jamie Rollins)

    Jamie has the Siglab system working and we will now use this to do additional characterization of the isolation prototype.  Sam beginning to write up descriptions of the instrumentation and control system of the prototype, as well the measurement procedures.

    From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>

    Yesterday removed the LIGO IP from the space allocated for Minos,
    reassemble of IP during this week
     

    Lisa, Gigio, Paolo
    Ready to test LVDTs stability in oven.
    Computers breaks down repetitively, cause unknown, reliability is a
    serious a problem for long term Creep DAQ.
    Oven stable within +/- 2 degrees C peak peak over many days.
    No internal/external temperature correlation.
     

    Gigio, Paolo
    Tested and calibrated and assembled LVDTs for oven test.
    Gotten additional DAQ computer in working order.
    Prepared cables for DAQ.
     

    Akiteru
    IP transfer function looks understandable, and plateau lowered possibly
    to 35 dB, counter weight still to be tuned,  too heavy for good
    plateau.  Some problem with perpendicular direction sensitivity of
    commercial accelerometers,  maybe will have to make TF with LVDTs
    instead of accelerometers.
     

    Hareem
    Computer for filter thermal stability measurements working again after
    removal.
    Located by-metal strip/coil manufacturers for GASF thermal drift
    compensation.
    By metal strips easily deliver the 20 to 60 g/degrees lift necessary to
    compensate the GASF springs thermal lift loss.
     

    Brett
    Stepper motor noise reduction effort,  not easy to do cheaply, silent
    steppers probably useless because steppers would be used with IFO off
    lock.
    Stepper motor driver PCB to be delivered soon.  Working on VME software.
     

    Soy
    Acoustic emission setup ready to run, starting connecting noise pickup
    sensor on stressed blade.
     

    Susha
    Simulation still produces too high vertical resonant frequencies (2 Hz
    instead of 100 mHz).  Found bug and now, at least, increased radial
    compression correctly yields lower resonant frequencies.  Looking for
    working point.
     

    James
    First MGASF transfer function, hoping to reproduce earlier results next
    week and then proceed with further measurements.
     

    Virginio
    Rediagonalised IP MIMO under different conditions before disassemblying
    of IP
     

    ChenYang
    Preparing Marconi circuitry.
     

    Alessandro/ Pisa technicians, Galli&Morelli
    Tested new accelerometer, kinematically perfect but still lower quality
    factor than expected.  Earlier prototype with 5000 series Aluminum, this
    one with 2000 series,  it is then no bulk problem.  Likely coming from 2
    micron melted layer left by EDM on two faces of 50 micron flex joints.
    Will try double cure:
    thermal annealing and tempering process (under vacuum) to eliminate
    recrystallization stresses
    resuming electro polishing to eliminate presumed offending layer.
    These tests to be made first on old prototypes to minimize risks.
    Still accelerometer more than adequate for present inertial damping use
    (thermal noise problem only relevant in advanced inertial damping and
    performance monitoring uses).
    Put 3+1 accelerometers in production for TAMA IP damping,  mechanics
    machining  e.t.a. this Friday,  e.d.m. machining e.t.a middle of next
    week.
    Accelerometer readout electronics modules OK, e.t.a. next week,
    populated PCBs will be sent without NIM module mechanics,  need to
    procure NIM modules in Pasadena.
     

    In Pasadena disassembled and shipped accelerometer back to Pisa for
    risky tests.
     


    For additional information about this report, contact sanders@ligo.caltech.edu