Weekly Report for Week Ending May 11, 2000


 Exec. Comm. Agenda
Highlights
LSC
Administration
Hanford Observatory
Livingston Observatory
MIT
Caltech
Detector
40 Meter
TNI
LASTI
Data Analysis
LIGO II/Adv. R&D
Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  May 15, 2000 will be:
 (Meeting time: 10:30 am Pacific Time)

Open meeting 10:30 - 11:30

  1. Announcements
  2. LSC Issues (Weiss)
  3. Comments on Weekly Report
  4. WBS 1 LIGO I Construction (Lindquist)
  5. WBS 2 LIGO Lab Operations
  6. WBS 3 and 4  Advanced R&D and LIGO II (Sanders)
Executive Committee only 11:30 - noon
 

Special Items:  NSF review reprise


Special Announcements:


Weekly Report Highlights

NSF Review reccomendations
 


LSC Issues (Weiss)


Alan Wiseman of the University of Wisconsin at Milwaukee will become
the LIGO/LSC Software Coordinator. He will also chair the LIGO/LSC
Software Coordinating committee which was organized and chaired by Stuart
Anderson. Stuart will continue to serve on the committee. The Project and
the LSC appreciate the work that was by done Stuart and thank him for
his efforts in beginning the software coordination and the data
analysis proposal evaluation process.
 


LIGO I Construction/LIGO Laboratory Administration (Lindquist)


WBS 1.2 LIGO Operations--Administration


LIGO Weekly Site Telecon (Jasnow)

There was no site teleconference held Thursday, May 11, 2000. The list of current actions revised to reflect actions assigned during the meeting held on April 27, 2000 may be found at ACTION LIST.   The monthly financial reports can be found on the network in .pdf format.  See Cindy Akutagawa for the password to access these files.


PROPERTY MANAGEMENT (Chargois)

From: Ed Chargois <chargois_e@ligo.caltech.edu>

No report this week.


DOCUMENT CONTROL CENTER (Turner, Mak)

From: the DCC <dcc@ligo.caltech.edu>

Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . . [It has come to my attention that there are some journal publications that are not submitted to the DCC.  We are preparing a list of LIGO publications to be submitted with the Advanced R&D proposal.  Please provide a list of all publications during the last 18 months to Elizabeth Wood and a copy of each publication to the DCC. -pel]

From: Cleveland Mak <mak_c@ligo.caltech.edu>

Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.


COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Akutagawa, Kaufman)

From: Esther Cunningham <esther@ligo.caltech.edu>

Press here for ACCOUNTS PAYABLE HISTORY DATA.

From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

From: Florence Kaufman <fkaufman@ligo.caltech.edu> From: Cindy Akutagawa <cindy@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: irena@ligo.caltech.edu (Irena Petrac)

From: Ed Jasnow <jasnow@ligo.caltech.edu>

  • A meeting is being scheduled for the week of May 22 to force the issue of using the Caltech P-card, or another Caltech card, for use on travel.  This meeting will be with the Institute Controller, Al Horvath.


  • Support (Wood)

    Rita Torres

    Started to format additions to Stanford progress report received last week but ran into problems, some text omitted from transmission. Meeting on 5/11 with B. Kratochwill to try to find a solution.

    Continued to coordinate food arrangements for the 5/8-5/11 NSF review. Lots of phone calls and emails, and a trip to Smart & Final -- thanks to C. Mak for unloading my vehicle, and for general help.

    Obtained Oracle requisition numbers. Did site trips updates. Spent a bit of time on Expense Reports. P-card activities, the usual chase for invoice information, and reconciling.

    INFORMATION - From Caltech Weekly Update 5/8/00:

    ALL CALTECH / FEDEX SERVICE USERS

    All FedEx shipments must be received at the FedEx service counter by 4:30pm. Caltech is required to have all packages ready for the driver to pick up and scan by this time.

    The FedEx driver must dispatch from Caltech to the Los Angeles FedEx facility by 4:40pm to assure that the packages meet their service commitment times.  Details: http://atcaltech.caltech.edu/news/item.tcl?news_id=1275

    Irene Baldon

    Worked on preparing the paper work for 12 new trips taken recently or upcoming (12 Payment Requests and 14 Advance Requests). There are approximately an additional 15 new trips in various stages pending completion of travel arrangements before the paper work can be completed. Also, there are 3 trips that require extensive attention due to various problems incurred.

    I have started the travel arrangements needed for 23 incoming SURF students, some of which will be coming from Europe. This is the highest number of students that LIGO has had since we started working with the SURF Program. We have 14 students coming to LIGO/Caltech, 3 will be going to LIGO/Hanford, and 6 will go to LIGO/Livingston. I have been able to start on some of them and will continue to push the others so that I can get the best possible fares.

    Completed 35 Expense Reports, some of which were extensive, involving 2-3 or more pages each. There are 21 Expense Reports still to be done. I’m holding 2 completed Expense Reports which requires a check from the Traveler before sending to Travel Audit to clear.

    Rita continues to try to fit into her schedule some time for travel. She has 9 Expense Reports to be done at the present time. She also completed 6 Expense Reports last week.

    Performed normal recording and filing associated with Travel and Reimbursement. Had an extensive discussion with Wayne Morales, Supervisor, Travel Audit, regarding Advance Checks. They will no longer expedite Advances that do not get over to them before the trip begins/ends. In fact they want the Advance Request to be sent a minimum of 1 week before the trip starts. This can be difficult since sometimes I have difficulty getting an approval signature before I can send it over. I again pushed for the use of P-Cards for Travel, which Gary Sanders, Phil Lindquist and Ed Jasnow are also pushing. I will keep you informed as to what happens. I attended a meeting on Travel arranged by the PMA office conducted by Wayne Morales with Davida Perez, Mitchell Thompson, and Karen Dumbroski. This meeting was of a general nature, not much new, just a few points of fine tuning.

    I also assisted with NSF participants wherever possible both on their travel and their meetings here in Millikan.

    Prepared the Travel/Vacation Itinerary for the Week of May 8, 2000.

    Dorothy Lloyd

    Continue to review "old" open purchase orders in IFIS and those converted to Oracle. Submitted approximately 20 to Acquisitions (Ruth) to "close out" and remove the encumbrance. Adjusted LIGO database accordingly.

    Processed requisitions, invoices and receiving on-line. For more detail see "Cost Schedule Control Systems" report by Esther Cunningham. Volume of invoices received to process is still low.

    Tracked and followed up on invoice problems.

    Monitoring of contract and blanket order funding levels is ongoing.

    Jim continues to maintain files and do data entry.

    Elizabeth K. Wood

    Dealt with the little details of the NSF site review.  Many thanks to Rita Torres for taking care of the catering details and to Irene Baldon for overseeing the accommodations of the reviewers.

    Began gathering together a list of LIGO publications from the past 18 months for the annual report. Not all publications produced by LIGO are submitted to the DCC.


    LIGO II (Frey)

    From: Thomas Frey <tfrey@ligo.caltech.edu>

    Progress Period from 5.5 to 5.11

    Accomplishments:

    Schedule: Anticipated Challenges: Corrective Action:

    WBS 1.4.1.2   Project Controls (LIGO Construction)

    NSF Review (Lindquist)

    The NSF conducted a review of the LIGO Project at Caltech May 9-11, 2000.  The Review Committee was charged to: The review committee presented the following recommendations during their exit debriefing on May 11:
    The committee recommends that the revised HPP include:

    Reports (Lindquist)

    We are preparing a schedule for the support that is going to be required for proposals, work plans, and reports for the last half of FY 2000.  Clearly there is a lot of information needed, and there is a lot of overlap in the schedules that will have to be spread out given limited resources.  Material for the End of May Quarterly Report is hereby requested by Friday, June 9.  Thanks! I have distributed draft copies of the text and budgets for the Advanced R&D Annual Report and Request for Continuing Funds. We will be finalizing this material next week for entry into FastLane.


    Change Control/Contingency (Lindquist)

    The following change requests have been submitted:
     

    CR-990028 WBS 1.1.3 Beam Tube Enclosure Closeout F. Asiri
    CR-000005 WBS 1.2.1 Upgrade Pre-stabilized Laser S. Whitcomb
    CR-000006 WBS 1.2.1 Re-polish Core Optics Components S. Whitcomb
    CR-000007 WBS 1.2.2 Replacement of Optical Lever Lasers S. Whitcomb

    Press for the latest Contingency Needs Projection.


    COST SCHEDULE CONTROL SYSTEMS (Duncan, Akutagawa)

    From: Kris Duncan <kris@ligo.caltech.edu>

    From: Cindy Akutagawa <cindy@ligo.caltech.edu>

    SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

    From: irena@ligo.caltech.edu (Irena Petrac)

    From: Ed Jasnow <jasnow@acrux.ligo.caltech.edu>


    LIGO Hanford Observatory (LHO) Operations (Raab)


    Announcements:
    --------------
    (F. Raab)

    We found another "surprise" magnet (see Optics report). Work continues on debugging our laser telephone system and lots of alignment activity.

    Optics:
    ---------------------
    (D. Cook)

    The COC re-alignment tasks are steadily plodding along with varying degrees of sucess. We have encountered several problems along the way that eventually got resolved. We encountered another "stowaway"  magnet in an OSEM on the same FMY-2k optic. This time on the upper left face magnet. While making what would have been the final tweek of the PAM screw, the
    optic made a sudden lurch. Upon looking for the cause I discovered  the culprit. We ended up removing the OSEM and the magnet soon followed. We then pulled all of the face OSEMs, carefully inspected the interiors for possibly breeding pairs, reset the OSEMs and finished the alignment. I cannot explain where in the past reprocessing of the optic that this
    happened or even how it was missed on the last episode. We have developed some new successful techniques which hopefully will prove to give us a closer alignment.

    Seismic Systems:
    ----------------------
    (H. Radkins, C. Gray & M. Guenther)

    2k HAMs--
    Looked at a "wobble" issue on HAM7 which came up during Mode Cleaner Alignment (it was thought that the table could be causing misalignments because of "three-legged stool effects" from the Stop Screws of the Scissors Tables).  We saw a slight wobble in one axis ~roughly 1/8 mm, and were able to decrease the wobble by ~half of that by adjusting the Stop  Screws.

    Checked level/elevation of HAM10.  Were within 1.15 mm in elevation and level range was 1/16 mm.  No changes made.

    BSC9--
    EM shakers are being installed.

    Controls:
    ---------
    D.Barker

    Implementation of new CDS file system almost complete. All LHO target names have been changed to conform to the naming standard [IFO][System][Location or identifier]. See the full list in http://blue.ligo-wa.caltech.edu/targets/LHOTargetsNewOld.html

    Presently 26 of the 45 LHO target systems (VME computers which run the VxWorks Real-Time kernel) have been changed to the new naming convention. All LHO targets now boot from the new CDS area $CDSROOT/lho/targets.

    All source code is under full configuration control using the LDAS CVS system. Using this system CDS code is mirrored at all LIGO sites.

    All EPICS targets are being converted to use the save-restore faciltiy, which automatically backs up all PV values every 10 minutes. When a target is rebooted, it restores all of its values from the last backup.

    All targets now have a data file, called TARGET. This is an XML file which provides CDS with information about the target. See http://blue.ligo-wa.caltech.edu/CVS/CdsCvs.html for more information, see http://blue.ligo-wa.caltech.edu/targets/LHOTargets.html for the target XML data.

    CDS code is being made generic under the $CDSROOT/project areas. The goal is to  generate site specific object files from a single generic source. The Vacuum Controls system was built with this design from the beginning. Existing systems will be converted to this design, the suspensions controls will be the first to be ported.

    Almost all the EPICS MEDM files have been ported to the new CDS file system. All LHO MEDM files reside in a single directory ($CDSROOT/lho/medm). All files must conform to the new MEDM naming standard <IFO><SYS>_<SUBSYS>.adl. Top level and overview screens must have a _Main.adl suffix. A perl program which runs every 10 minutes collects all the *_Main.adl files and organizes them into the site map. In this way, new files are made available to all site users within 10 minutes. See http://blue.ligo-wa.caltech.edu/screenShots/sitemap.jpg for an example.

    I am working on the new "CDS Programmers Development Guide" which will describe all these changes in detail.

    C.Patton

    Testing new vacuum control software;

    PID controllers for LN2 Cryogenic pumps which maintain the LN2 liquid level to a setpoint.
    The Cold Cathode vacuum guage is now averaged over a 10 second period before being sent to the Beam Tube Protection system to prevent gate valve closures on a vacuum glitch.

    All vacuum target systems are being changed to the new cvs system. IOC names will become h0ve(ex,mx,lx,mr,ly,my,ey) and boot from the new $CDSROOT/lho/targets area.
     


    LIGO Livingston Observatory (LLO) Operations (Coles)



     

    Interferometer Commissioning: A test using an optical lever on the output of the mode cleaner showed that we are not dominated by noise from light scattering in the OSEMs until at least 750 mW. The principal focus of our efforts is now in understanding the unlocked motion of the optics and the diagonalization of the length control signal. The length control signal does look reasonably diagonal.We are trying to understand why MC1 moves even when it is unlocked by putting a quad cell on the reflected beam and using it as an optical lever. It seems the motions of the mirrors pitch, yaw, pendulum and sideways pendulum motion are not very orthogonal.

    Detector Installation: All vacuum hardware (gaging, annulus plumbing) has been reinstalled on HAM 3, and BSCs 1-4. During our annual crane inspection,we found the south crane bridge drive pinion gear has prematurely worn out due to misalignment of the pinion gear and the bridge runway. The south crane is still operational while awaiting parts.

    General computing: We have received the installation media for Solaris 8, and are testing it on the machine formerly known as sirius. This machine is slated to become our new fileserver.

    Community relations: Tours of the LLO were taken by school classes from Houma and Baton Rouge. The Baton Rouge Astronomical Society toured the site on Saturday night and stayed on for star gazing. Six faculty from Southern University toured the site on May 9 (they are interested in areas of possible collaboration with LIGO). The SPS group from Louisiana Tech University toured the site 5/11. Two more school classes are scheduled for 5/12.
     


    MIT (Shoemaker)


    All activities covered elsewhere.


    Caltech (Sanders)


    All activities covered elsewhere.


    Detector/Technical Support (Whitcomb, Coyne)


    Installation:
    Hanford
    Livingston
    Commissioning:
    Hanford
    Livingston
    Other Science/Engineering
    Activities

    1.0 INSTALLATION (including fabrication and subsystem test)

    see also the Installation web page

    1.1 LHO

    Vent Housekeeping

    Larry Jones
    Two more instances of ribbon cable touchings were found in WBSC 8. These
    were corrected by tuning the cable lengths, and inverting one of the cables.

    PSL

    Peter King
    The installation of the latest frequency servo has been placed on hold.  Although the servo functioned when it came to locking the servo, it was found that the servo gain could not be increased to the desired operating point.  It was decided to ship that frequency servo and the "old" frequency servo back to Caltech to figure out why the two boards exhibit different behavior in the Pockels cell path.

    The newly modified current shunt has been installed.  The modification consisted of replacing a pair of 1/4-W resistors for a 10-W power resistor.

    The data acquisition wiring in the PSL rack has been modified to now permit removal of the generic data acquisition card without bringing down the entire Eurocard cage.

    Rich Abbott
    During visit to Hanford, we installed the Tidal servo components and did modifications to the FSS.  We ran into difficulties with the FSS which are now traced to their source.  More testing is to follow in the beginning of next week and then the board will be shipped back to LHO. Part of what we think we now understand is the difference in the locking characteristics of the FSS in LHO and LLO.  Time will tell if we are correct.

    A revision to the PSL schematics has been submitted to the DCC along with the appropriate DCN.

    COS Alignment

    Hugh Radkins, Mike Zucker, Daniel Sigg, Richard McCarthy
    Mike Smith, Doug Cook, Betsy Weaver, Garilynn Billingsley, Larry Jones, Janeen Hazel-Romie
    Alignment of the 2K IFO core optics in the LVEA was completed on 5/9.   All of the COC mirrors within the recycling cavity have been aligned, including the MMT3. The beam from autocollimator #2, behind the RM, passed through the face center of the BS and was centered on the ITMy mirror; FMy was adjusted to autocollimate from ITMy. The BS was steered to hit the center of ITMx and FMx was adjusted to autocolliimate from ITMx. Autocollimator #1 was projected down to MMT3 and the position recorded on the MMT3 target. MMT3 was steered to hit the center of MMT2.

    Many delays were experienced due to various setup problems, as this was the first time for the procedure of using ITM optics as reference. We had a big surprise when FMy PAM adjustment difficulties led to the discovery of another stowaway magnet!! And this is the same optic that had the first stowaway! The magnet was in a different OSEM; needless to say, all OSEMs on this optic were removed and carefully inspected for additional stowaways. We are now working on Faraday Isolator installation, telescope installation, and arm cavity baffle alignment.  Janeen is supporting Mike Smith's target work at Hanford. Releasing those drawings.

    COS 2 km interferometer Assemblies

    Mike Smith, Ken Mailand, Betsy Weaver, Doug Cook
    The Faraday isolator was assembled and aligned. The throughput is 97% and the extinction ratio is 10,000:1. The RM ghost beam beam dumps for HAM9 has been assembled and is awaiting installation. The viewport beams dumps on HAM9 and HAM10 were assembled, awaiting
    installation. The APS telescope baffle was assembled and is awaiting installation. The y-manifold arm cavity baffle was aligned to the 2K optical centerline.

    The HAM viewport window target fixture was assembled and appropriate targets are being made to direct the output beams on HAM9 and HAM10. Preparations are in process for re-aligning the APS telescope and installing the Faraday isolator. A height fixture was made for setting the height of the PO Telescopes on the table.

    Luca Matone, Betsy Weaver
    Concluded a set of measurements on the Beam Dump assembly resonant frequencies. The setup consisted on the monitoring of two accelerometers, one placed on the Beam Dump while the other placed on the chamber itself. By comparing the two signals, we found 3 resonances that dominated the motion (@ 6 Hz, 14 Hz, 26 Hz). The 14 Hz contribution, often dominating the other two, had an amplitude of ~1 micron RMS. For details, see the 5/5/00 elog

    Mode Cleaner

    Haisheng Rong, David Ottaway, David Reitze, David Tanner
     
     

    1.2 LLO

    ISC

    Matt Smith, Ken Mason, Myron McInnis
    Created a new assembly drawing, D000178-A,  for the as built assembly of LA-ISCT4 table that was put together and shipped to LA.  The drawing will be released this week as well.  ISCT 10 for the 2K in Washington will be modified using this layout.

    Received the bare breadboard, from Thorlabs, for the ETM transmission monitors.  These are now at the machine shop for the necessary modifications.  Started to receive the balance of the parts for the ETM transmission monitor assembly.  We should have three more complete by the end of next week.

    ISCT4 for Livingston has been aligned and crated. It is scheduled to be picked up by North American Van Lines on 5/11/00 and will arrive in Livingston the week of 5/15. Myron will be in Livingston when it arrives.

    Nergis Mavalvala
    I have continued working on the design of the 4km Guoy phase telescopes.  This design must take into account the mode matching telscope and the beam reducing telescope, which I'm revisiting in light of our recent experience with the 2km arm cavity tests.

    COS

    Lee Cardenas
    All the Cavity beam Dump Assemblies completed as reported before and I have stored all of them after labeled completely along with the drawings.  All the (4)  4K PO mirror assembly completed labeled and stored.  Four of the Hinged H tube ~ 44" long taken to be baked.

    Suspensions

    Mark Barton
    I made preparations to go to LLO to work with Gabriela Gonzales on suspension controller tuning. The strategy used successfully for the LOS sensor tuning assumed that we knew the shapes of the normal modes. However in the SOS, where the optic is much lighter, the PAMs introduce substantial cross-coupling between the modes. I made a fairly detailed Mathematica model of the final pendulum stage of the SOS (or with different parameters, the LOS) incorporating the wire elasticity and the effect of the PAM magnets, to study the effect of the PAMs on the normal modes.

    DAQ

    Sander Liu, Paul Russell
    Built three new +/-5 V power supply chassis from Kepco modules. Paul shipped all three units to LLO.  Built one No.1 Seismic System Antialiasing Filter Board (D000108). Currently in the process of performing first article testing.
     

    LIGO-TriNet Seismic Monitoring Station

    Szabolcs Marka
    We received the quote from the contractor on the LLO station. Negotiations started.
     

    2.0 COMMISSIONING (incl. diagnostics and characterization)

    2.1 LHO

    PSL

    Peter King
    A new version of the pre-modecleaner lock acquisition software has been installed.  The new version relies on the PEM atmospheric pressure sensor readout to calculate whereabouts in the PZT travel the pre-modecleaner should acquire lock.  If the PEM channel H0:PEM-PSL2_BP was not online, resulting in an atmospheric pressure reading of 0 Pa, the pre-modecleaner acquires lock at the low-voltage end of its travel.  For now, the fix would be to break lock on the pre-modecleaner and re-initiate the lock sequence by depressing the PZT BLANK button and the lock acquisition button.  The software seemed to function okay on the four times when it was deliberately tested and the two (or three) occassions when the laser power supply faulted during work on the PSL rack.
     

    2.2 LLO

    Mode Cleaner and PSL

    Peter Saulson, Joe Kovalik, Sany Yoshida,  Peter Fritschel, Haisheng Rong, Gabriela Gonzalez, Tom Nash
    Work during the past week has concentrated on searching for the cause of excess beam jitter seen at both input and output of the LLO MC, as compared to the one at LHO. We have roughly an order of magnitude more motion than at LHO, and it is more pronounced in yaw. We found coherence between LSC drive and angular jitter of the output spot, and have also measured directly the length-to-angle coupling. Nevertheless, the most striking clue is that the input spot moves by too much, even when the MC is not locked. This suggests that we have a problem either with the amount of damped MC1 motion (independent of the MC locking system) or perhaps even a problem of motion of the beam presented to the MC by the PSL-IOO table.

    The spectrum of the MC1 reflected light is NOT dominated by resonances of the MC1 suspension, but is broad and featureless. This clue is being actively followed up at the time of this writing.

    Last week we worked on implementing the wavefront sensor alignment servo on the MC. This servo controls the direction of the input beam (4 degrees-of-freedom) to follow the optic axis of the MC. After setting the control matrix based on open-loop measurements of the sensing matrix, the loops were closed and we saw that the servo did bring the beam into proper alignment, but that there was very little gain in the system. We increased the gain by increasing the light power on the wavefront sensors by a factor of about 20 (changed a beamsplitter to one with higher transmission, and increased the overall power on the IOT1 reflection port). Subsequent closed loop measurements of the system showed that the unity gain frequency of the system is about 3 Hz (more than adequate). There is still larger cross-coupling between different channels than we would like; this will be followed up next week.

    The big issue now is the pointing stability of the MC output beam. It is not particularly stable due to instability of the MC mirror angles. A measurement of position fluctuations of the transmitted beam indicated that its pointing is fluctuating by about 8 microrad-rms horizontally, and about 2 microrad-rms vertically. It is not clear yet what is causing the MC mirror angle fluctuations; tests are ongoing.

    We also adjusted the position damping of each mode cleaner mirror by doing a step response measurement, and adjusting the gain to obtain a Q value of about 8. This seemed to help with the lock robustness; before this the gain was much lower (much higher Q).

    3.0 Other Engineering and Scientific Activities

    3.1 Design/Analysis

    CDS Software

    Rolf Bork
    Working on making changes to DAQS controller which will be necessary to accomodate the digital suspension controllers. In this process, I am moving all of the C code onto a single Pentium processor (presently runs on three separate MIPS processors). I still require a second CPU to run all of the epics stuff, including the epics data collection unit (edcu). For now, this is a MIPS, but will try to change to a Motorola 262.

    This scheme also removes the epics 1Hz, or "slow data", channels from the reflected memory network.  Instead, the edcu processor opens its memory up to the VME bus and the Pentium reads the data directly from that memory.  Among other things, this would allow us to increase the storage rate of epics channels from 1Hz to 16Hz, though the data would not be as accurately time synced as other data as the epics systems are not synched up to the 16KHz clocks. However, this would provide more resolution, as has been requested by various folks, for diagnostics.

    This new system is presently operating at Wilson and undergoing performance testing.  Initial testing indicates this configuration can deliver data to the FrameBuilder at >15MByte/sec, as compared to the max thruput of the present MIPS system of 10.2MByte/sec. This is still with the reflected memory net set to "redundant transfer mode" ie all data transferred twice for data error checking

    LSC CDS

    Dale Ouimette, Mohana Mageswaran, Flavio Nocera
    Mohana has built up a second LSC Anti Alias board and is in the process of testing both. Flavio is testing the two LSC photodiodes. Dale is putting together all of the wiring diagrams for rack 2X1 so that the wire harness can can get started at Hanford. The LSC Whitening Filter is due back from PCB fab this Friday. Assembly and testing will be next week. I still need to complete the Photodiode Differential Driver chassis design so that Fred can begin PC layout and front panel.

    ASC/LSC/Suspension

    Jay Heefner
    The prototype for the universal dewhitening filter required by the digital suspension and LSC has been tested and appears to perform as predicted. A module is now being designed. We now need to decide on the requirements for the anti-image filter.

    A prototype for the digital suspension LOS coil driver is being fab'd and should be tested by next week.

    Bill Kells
    Begin WFS tuning at CDS.

    PSL

    Peter King
    At present a Cadence model comparison is being performed of the Rev. A. frequency servo and the Rev. C. frequency servo to try and understand the different behavior exhibited by the servos.  The PSL in the PSL Lab is being reconfigured to the old optical configuration to accommodate testing of the frequency servo in a configuration identical to that of the sites.

    Inquiries have been made with Karl Lambrecht Corp. about the possibility of making their air-spaced double plate waveplates in a smaller package so that they can fit in the existing rotation stages.

    Lee Cardenas]
    Started to complete the drawings for the new Enclosure for the 40m Lab. Sketches have done and processed an order.
    I am upgrading the MOPA #110 in the PSL Lab. By checking all the parameters specified by the Lightwave and re-aligned the optics inside the box to bring the previous output power. Enquiring in obtaining a new Ref. Cav. Pump station with a new oil-free pump and a new turbo pump. Right now, I am cleaning the laser cooling system completely.  This laser MOPA # 110, eventually will go to 40m. Lab in the near future.

    Suspensions

    Janeen Romie
    New Osems: Sent out second RFQ, for modified quantities with released prints, to Superior Jig and Spacecraft Specialists. Hope to initiate PO process by tomorrow afternoon.

    E2E model for the recycled Michelson

    Luca Matone

    I began to setup an e2e model to simulate the recycled michelson itf. The first goal is to observe what the power fluctuations are once the system is locked and aligned. At the moment, only the optical system of the model has been setup and verified.
     

    3.2 Issues Concerns

    Optical Lever Lasers Reliability

    Mike Zucker, Ken Mason
    An installation procedure for the adjustment of the optical lever laser power has been written. It is document number E000238-0 and can be found in dcc/OUT or in the kmason directory. We are lowering the power of these diode lasers in an attempt to increase their life expectancy.

    Cable Sag Test

    Larry Jones
    The cable sag test has shown 2 mm of sag in one month of testing, in the particular cable run that accounts for most of the touching instances. This amount is not sufficient to cause touching; data taking is continuing.


    40 Meter Interferometer (Weinstein)




    Thermal Noise Interferometer (Libbrecht)


    Pumpdown of the TNI chamber went well.  We quickly got down to a moderate
    vacuum, then turned the pumps off to do some noise measurements.  By
    comparing measurements of our mode cleaner in air and in vacuum (with the
    stops clamped down), we are able to separate acoustic noise from seismic.
    As Riccardo predicted, the noise on top of our stack below 100 Hz is mainly
    seismic, and the component above 100 Hz is nearly all acoustic.
     

    We also measured the finesse of the mode cleaner, and found it to be 5,260
    +/- 500, just what we expected it to be.  There was some worry that the
    finesse of this cavity would have been degraded by our having worked with
    the mirrors in air for several months, but this does not appear to have
    happened.

    We now plan to release the stops and start looking at a suspended cavity.
     


    LASTI (Zucker)


    Nothing to report.


    Data Analysis and Computing (Lazzarini)



     

    Simulation and Modeling


    Lock Acquisition

    Matt kept working to push the acquisition more robust. Luca is working
    with Matt to study the locking scheme for the Michelson cavity by
    introducing
    mirror angular motion.

    DEC-ALPHA

    all e2e softwares, alfi4 and modeler/modeler_freq, have been compiled on

    sadan. The programs run fine without code change. modeler runs around
    twice
    as fast compared to the run on SUN Ultra-30 (rana). Both are compiled
    with
    g++ -g -O2. There are some problems with support softwares, like ddd,
    but
    it is promising.  Matt is going to run the Lock Acquisition code on
    sadan.

    alfi

    Basic validation of alfi4 is done and will go into filed test after one
    more
    bug is fixed. alfi is compiled on DEC-Alpha (sadan) and seems to be
    working
    fine. After a few more essential bugs are fixed, rename/save as, cut and
    paste
    and junction point will be iomplemented.

    LIGO Data Analysis System


    LDAS pre-version 0.0.11 was once again built and installed
    at the sites for testing this week. All earlier bugs have
    been fixed except a rather large memory leak in the FrameAPI.
    This will be tackled in two ways: The managerAPI has the
    functionality to test memory usage in all distributed LDAS
    APIs so it will look for APIs exceeding a some configuration
    size and restart that particular API as soon as it is no longer
    being used. Secondly, several memory allocation/garbage collection
    packages have been identified and will be incorporated into
    the LDAS system in a transparent manor so as to allow better
    leak detection and garbage collection of fragmented memory.

    A pre-release of GNU's GCC-2.96 was built and used to test
    several problems with classes from the standard template library
    which ranged from memory leaks to non reentrant code. These
    problems are all fixed with by this version of the compiler.
    However, this compiler is further along in its implementation
    of the ANSI C++ standard and identified several area where the
    LDAS code was not meeting the standard but meeting the 2.95.2
    compiler. These non standard lines of source code have been
    identified and fixed for the general and framecpp libraries.
    Other code has yet to be tested and made more complient.

    The output data structures for the wrapperAPI were completed
    and tested this week. This means that data can now be sent
    using message passing call to and from the master and slaves
    within the parallel code.

    With the NSF review bringing several key figures from the LSC
    here to CIT this week, Kent had the opportunity to hold several
    lengthy meetings on the dataConditionAPI, the wrapperAPI and
    the Mock Data Challenges (MDC)s. All meeting were extremely
    productive and resolved long standing technical issues that
    have been difficult to put to rest over the phone.

    An attempt to enable status and health monitoring functions in
    our DB2 server failed and resulted is a zombie database table
    on the CIT database. A replacement table set was immediately
    created, but the stale tables have not been removed. We have
    been modestly successful at getting support from IBM but as
    of yet have no working solution.
    ----- Forwarded message from Omar Rashad (LDAS SysAdmin) -----

    Activated additional network ports and hubs for use during the NSF review.

    With the arrival of the new UPS, development has restarted on performing
    controlled shutdowns in the event of an extended power outage.

    Setting up new user workstation m90 for new user.

    Checking new dataconditioning server for use of Intel chipset under recall.

    Installing new keyboard/monitor switch so new dataconditioning server is
    accessible.

    Performing monthly backup while simultaneously testing new ait2 tape drive.
     

    General Computing


    MIT:
    Nothing to report.

    Livingston:
    Testing out Solaris version 8 on the SUN E3000.

    Hanford:
    Moving licenses to a new license server but this should not affect the users.

    CIT:
    Minor changes and fixes have been performed on both the LIGO web server and the
    LIGO internal web server.

    Just as a reminder concerning viruses. We've had a number of machines with virus
    attacks but the virusscan s/w has been able to take care of the problems but we
    still need to be careful.
    Also, there is a minor security problem with Internet Explorer. Check
    http://www.peacefire.org/security/iecookies for more information, I don't think
    most people have anything to be concerned about but it may be worth checking
    out.
     


    LIGO II/Advanced R&D (Sanders)


    Stiff isolation system (S. Richman)
     

    We have closed all 12 loops on the stiff two-stage prototype, using
    geophones and relative position sensors.  This allowed for the first time a
    measurement of top-to-bottom horizontal isolation from ground noise.  At 10
    Hz this is 33 dB, most severely limited by position sensor noise.  The
    vertical isolation at 10 Hz is 63 dB.  The stability appears quite good,
    and the forcers use only about 5% of their dynamic range.  We expect it
    will be fairly straightforward to configure filters in the horizontal loops
    to reduce the position sensor noise contribution and significantly increase
    isolation performance.
     

    Today (Wednesday) we took advantage of our severe environment to do a
    robustness/stability check.  Tuesday night the high bay air conditioning
    died and this morning the temperature was about 24.5 deg. C.  We closed
    loops and let the system run throughout the day.  The A/C was repaired in
    the afternoon, and the temperature came down slowly.  We opened the loops
    at the end of the day, after 8 hours of operation with a ~3 deg. C
    temperature drift and the dull roar of construction next door (though
    thankfully the pile driving has ended).
     

    SAS system report
    From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>

    Szabi
    All oil bearing hardware in house, start testing.
    Design CRS platforms for IP and TAMA towers in new location
     

    Alessandro
    Calibrated Horizontal accelerometer Transferred controls of Hareem, gone
    back to Pisa.
    Making LVDT and possibly all other coils in Pisa.
    Starting design of Vertical accelerometer with F. Fidecaro.
     

    Virginio
    Achieved DC controls of position of IP. Grounds moves tens of
    microradians a day, requiring a few grams of actuator force each day to
    keep IP in position.
    Preparing for Accelerometer characterisation with Hareem.
     

    Akiteru
    Learning controls from Virginio.
    Writing TAMA suspension description document.  Present design a single
    intermediate mass supporting a mirror and a concentric recoil mass.
    Actuation from recoil mass and from filter. Total MGASF filter <= 10
    Kg,  will need thinner blades.
     

    Hareem
    MGASFs tuned to correct diameter and generated updated blade design for
    G&M.  Blades in production.
    Measured 176 mHz vertical resonance frequency (see outreach) with
    present parameters,  going for low frequencies when convenient.
    Measuring Q-factors at various frequencies.
    Going to measure temperature coefficient at 350 mHz and at lower
    frequencies.
     

    Riccardo
    Mounted larger diameter disk on old GASF filter, achieved 220 mHz VRF
    (see outreach), Hareem will measure Q-factors later.
     

    Flavio
    Nothing relevant new.
     

    Chenyang
    Working on actuator report.
     

    G&M
    Received modifications of design from RDS, new raw materials for
    corrections arriving this coming Friday, machining asap,  delivery of
    TAMA IP suspended waiting for modifications.
    Baking bodies of TAMA MGASF filters, final machining from the 11th, all
    material should be shipped by end of next week (19th of May).
     

    Outreach program: Riccardo, Chenyang, Flavio and Hareem.
     

    Received professor Ronald Lu and five High school students from the LA
    county school of arts (and Martina DeSalvo slipped in from St. Elisabeth
    middle school) for a day of hands on activity.
    They measured the frequency response of both MGASF and GASF filters.
    A ringdown curve:
    http://www.ligo.caltech.edu/~citsas/Picture_Gallery/12_8mm64.828.pdf
    A frequency versus height curve
    http://www.ligo.caltech.edu/~citsas/Picture_Gallery/fq_12_8mm.PDF
    It was great fun, they are smart kids.
     

    From: Helena Armandula <ahelena@ligo.caltech.edu>

    Today, Wednesday, we received the two AR coated sapphire pieces from REO.
    Looking for an alternative coating source, and following Ramin's (REO)
    suggestion, we contacted Anthony Louderback from MDL, Eugene, Oregon.
    Mr. Louderback, together with Dr. David Wei, developed Ion Beam coatings
    for Litton, their names are in the patent assigned to Litton.
    MDL is able to handle only small substrates at this time. They can not meet
    our uniformity specs. on large optics because they do not have the
    appropriate rotator. We plan on sending same samples to get coated to
    evaluate their work.

    (Incidentally, I've known Mr. Louderback for a long time; he trained me to
    continue the coating work when he left Litton.)


    For additional information about this report, contact sanders@ligo.caltech.edu