Weekly Report for Week Ending May 4, 2000


 Exec. Comm. Agenda
Highlights
LSC
Administration
Hanford Observatory
Livingston Observatory
MIT
Caltech
Detector
40 Meter
TNI
LASTI
Data Analysis
LIGO II/Adv. R&D
Past Weekly Reports

The LIGO Executive Committee Agenda for Monday  May 8, 2000 will be:
 (Meeting time: 10:30 am Pacific Time)

Open meeting 10:30 - 11:30

  1. Announcements
  2. LSC Issues (Weiss)
  3. Comments on Weekly Report
  4. WBS 1 LIGO I Construction (Lindquist)
  5. WBS 2 LIGO Lab Operations
  6. WBS 3 and 4  Advanced R&D and LIGO II (Sanders)
Executive Committee only 11:30 - noon
 

Special Items:  Operations budgets review


Special Announcements:


Weekly Report Highlights
 


LSC Issues (Weiss)


No report this week


LIGO I Construction/LIGO Laboratory Administration (Lindquist)


WBS 1.2 LIGO Operations--Administration


LIGO Weekly Site Telecon (Jasnow)

There was no site teleconference held Thursday, May 4, 2000. The list of current actions revised to reflect actions assigned during the meeting held on April 27, 2000 may be found at ACTION LIST.   The monthly financial reports can be found on the network in .pdf format.  See Cindy Akutagawa for the password to access these files.


PROPERTY MANAGEMENT (Chargois)

From: Ed Chargois <chargois_e@ligo.caltech.edu>

I attended a meeting at the Department Of  Energy/Hanford Works with the Chief of Property Management (Nancy Sitton) located in Richland, WA.  The purpose of this meeting was to establish a local "point of contact" to dispose of surplus property accumulated at the LIGO Hanford Observatory, (without paying a costly sum to transport the surplus equipment to the Defense Reutilization Material Office (DRMO) at Fort Lewis WA). The DOE will accept these items with proper release documentation (Standard Form 120) approved by the National Science Foundation..


DOCUMENT CONTROL CENTER (Turner, Mak)

From: the DCC <dcc@ligo.caltech.edu>

Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . . From: Cleveland Mak <mak_c@ligo.caltech.edu> Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.


COST SCHEDULE CONTROL SYSTEMS (Cunningham, Brambila, Akutagawa, Kaufman)

From: Esther Cunningham <esther@ligo.caltech.edu>

Press here for ACCOUNTS PAYABLE HISTORY DATA.

From: "Brambila, Ruth" <Ruth.Brambila@caltech.edu>

From: Florence Kaufman <fkaufman@ligo.caltech.edu> From: Cindy Akutagawa <cindy@ligo.caltech.edu>

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: irena@ligo.caltech.edu (Irena Petrac)

From: Ed Jasnow <jasnow@ligo.caltech.edu>

  • No report this week (vacation).


  • Support (Wood)

    Dorothy Lloyd

    Began reviewing old purchase orders that are complete, but remain encumbered dating as far back as 1995. It appears that in some cases we were never invoiced (maybe items were returned without my knowledge). In other cases, we were invoiced for less than the PO total (discounts, items returned and/or replaced at lower cost, etc.). I have begun pulling these and adjusting the LIGO database accordingly, and will forward them on to Ruth to "close out" and remove the encumbrances.

    Processing requisitions, invoices and receiving on-line continues. For more detail see "Cost Schedule Control Systems" report by Esther Cunningham.

    Tracked and follow up on invoice problems.

    Continue to monitor contract and blanket order funding levels and alerted task managers when supplements need to be made.

    Reviewed payments processed by Esther during the week of April 24. Payments were entered in contract summary sheets and the LIGO database.

    Updating PO Log Books continues.

    Irene Baldon

    This report covers a couple of days before my vacation and the week since my return.

    Worked on preparing the paper work for 27 new trips taken recently or upcoming (27 Payment Requests and 18 Advance Requests). There are approximately an additional 15 new trips in various stages pending completion of travel arrangements before the paper work can be completed.

    I also have the travel arrangements to be made for 23 incoming SURF students, some of which will be coming from Europe. We have 14 students coming to LIGO/Caltech, 3 students will be going to LIGO/Hanford, and 6 student will go to LIGO/Livingston. I have been able to start on some of them and will continue to push the others so that I can get the best possible fares.

    Completed 42 Expense Reports, some of which were extensive, involving 2-3 or more pages each. There are 37 Expense Reports still to be done. I'm holding 1 completed Expense Reports which requires a check from the Traveler before sending to Travel Audit to clear.

    Rita continues to try to fit into her schedule some time for travel. She has 6 Expense Reports to be done at the present time. She also completed 7 Expense Reports last week.

    Performed normal recording and filing associated with Travel and Reimbursement. Continued to research several items for Travel Audit in regards to Encumbrances not removed from Travelers records. Will continue to work with Travel Audit on this ongoing problem.

    Prepared the Travel/Vacation Itinerary for the Week of May 1, 2000.

    Rita Torres

    Formatted incoming Stanford progress report, sent to DCC to be posted on the MOU/LSC web page. Continued to coordinate food arrangements for the 5/8-5/11 NSF review; lots of follow-up phone calls. SEI drawings: compared list with a stack submitted by M. Fine, added to list the missing drawings. Handed revised list to F. Asiri; project on-going.

    Obtained Oracle requisition numbers. Spent more time on Expense Reports. P-card activities, the usual chase of invoice information.

    INFORMATION - Reminder. "Graphic Arts MAY Special Color copies at Caltech Graphic Arts are $.75, each & every Wednesday in the month of May! This offer applies to all orders we receive during our business hours for 8 1/2 X 11, single-sided, regular stock copies."

    Details: http://atcaltech.caltech.edu/news/item.tcl?news_id=1228

    Elizabeth K. Wood

    Continued preparations for the NSF site review. Thanks again to Rita and Irene.

    Did a lot of personnel-related work.


    LIGO II (Frey)

    From: Thomas Frey <tfrey@ligo.caltech.edu>

    Progress Period from 4.28 to 5.4

    Accomplishments:

    Schedule: Anticipated Challenges: Corrective Action:

    WBS 1.4.1.2   Project Controls (LIGO Construction)


    Reports (Lindquist)

    We are preparing a schedule for the support that is going to be required for proposals, work plans, and reports for the last half of FY 2000.  Clearly there is a lot of information needed, and there is a lot of overlap in the schedules that will have to be spread out given limited resources.  Material for the End of May Quarterly Report is hereby requested by Friday, June 9.  Thanks!

    I have received draft material for all tasks except two (Photodetectors-PDT, Active Optics Compensation-AOC) for the Advanced R&D Annual Report and Request for Continuing Funds. There are some holes in the information provided relative to what is requested by the NSF on their FastLane system. I will be distributing a draft for review this week.


    Change Control/Contingency (Lindquist)

    The following change requests have been submitted:
     

    CR-990028 WBS 1.1.3 Beam Tube Enclosure Closeout F. Asiri
    CR-000005 WBS 1.2.1 Upgrade Pre-stabilized Laser S. Whitcomb
    CR-000006 WBS 1.2.1 Re-polish Core Optics Components S. Whitcomb

    Press for the latest Contingency Needs Projection.


    COST SCHEDULE CONTROL SYSTEMS (Duncan, Akutagawa)

    From: Kris Duncan <kris@ligo.caltech.edu>

    From: Cindy Akutagawa <cindy@ligo.caltech.edu>

    SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

    From: irena@ligo.caltech.edu (Irena Petrac)

    From: Ed Jasnow <jasnow@acrux.ligo.caltech.edu>


    Quality/Safety (Tyler)

    >From: Bill Tyler <tyler@ligo.caltech.edu>

    No report this week.


    LIGO Hanford Observatory (LHO) Operations (Raab)


    Announcements:
    --------------
    (F. Raab)
     

    We now have a new web page to keep up with LHO activities, called "This Week at LIGO Hanford Observatory" ( http://www.ligo-wa.caltech.edu/thisweek.html ). We will try to keep it up to date.
     

    Last week, there was no LHO weekly due to "Operator Error" on my part. This error is all the more egregious because I was to announce that ALL LIGO-1 SEI CONSTRUCTION HAS BEEN SUCCESSFULLY COMPLETED. It looks like "test and trim" from here on out on seismic work.
     

    A disturbing discovery was made during mod's to the 2K mode cleaner. See contamination report, below.
     

    Tom Mahood will join the LHO staff on May 22. Tom comes to us from Cal. State. Fullerton where he worked on torsion-balance experiments for his masters thesis.
     

    Bake Oven:
    ----------
    (K. Ryan)
     

    LHO Vacuum Bake Oven A load #88, consisting of HAM 6, 12 and BSC 4 purge air hardware and Mike Zucker's view ports was released Tuesday 4.25.00.
     

    Load #89, consisting of 2K and 4K LHO and LLO HAM Beam Dump assemblies, was released on Tuesday 5.2.00.
     

    Load #90, consisting of Arm Cavity Baffle parts, is vacuum baking and is scheduled to be released on Friday 5.5.00.
     

    The need for a "B" oven is being revisited (see weekly from 11.18.99).  A cost proposal has been submitted.
     

    ## The "B" oven would be a smaller unit, more convenient for small loads.
     

    Contamination Incident
    -----------------------
    Michael Landry, Haisheng Rong
     

    Recently, MC1 was removed from HAM7 to replace the 0.0017" diameter suspension wire with 0.0016" (in keeping with MC2-3).  Once the mirror was moved to the optics lab, a large deposit was noted on the MC1 front face. The deposit ran in a streak from the edge of the optic, approximately 1.5" long, ending in a tear shaped smudge.  As the streak ran from near the top of the front face and straight down, the contamination occurred after the optic had been hung.  The deposit may have been sweat that was shed during installation or subsequent work in HAM7.  It also may have been Liquinox, although this appears less likely as such a deposit would have probably been observed at bake time.
     

    A photo of MC1 prior to re-cleaning is available at http://www.ligo-wa.caltech.edu/~mlandry/ .
     
     

    Optics:
    ---------------------
    (D. Cook)
     

    BSC7&4; HAMs7,8,9 optic tables have been leveled and reset to proper elevations using the optical level. Some of these optic tables had not been set after the seat replacement. The realignment of the Core optics using the COS autocollimator technique is taking longer than expected. It became necessary to closely identify the actual optic heights, target placement in relation to the therorical beam path, table elevations. The X-arm should finish by weeks end and the Y-arm by early next week. The balance of COS baffles, telescopes and dumps will
    follow on over the next two weeks
     
     

    Seismic Systems:
    ----------------------
    (H. Radkins, C. Gray & M. Guenther)
    **note:  activities since 4/20 are reported**
     

    BSC9 (4k ETMx):
    4/20-4/27---Encapsulated accelerometer is now on-line.  It can be seen on:
    H0:PEM-BSC9_MIC.  This accelerometer is a different model than our PEM on-site accelerometers (731A vs. 731-207) and has a sensitivity up to 1000 V/g.  Other BSC9 news is that the Expansion Bellows passed their leak check.
     

    4/27-5/4---Z-pivots have partially been installed.  External Accelerometers (731-207) have been mounted and are on-line.
     
     

    2k HAMs:
    4/27-5/4---Elevations/level of HAMs 7-9 were checked; target Z = -200.0 mm (global), +/- 0.3 mm level, +/- 1.0 mm elevation.  No adjustments required for HAM7; HAM8&9 needed adjustment (see detector e-log 5/20).
     

    CAS:
    4/20-4/27---A CAS test was run 4/20 on BSC 7 to investigate the effect
    of holding torque to the positioning motors on optics alignment. No effect
    on alignment was found with holding torque, however the air bearings were
    also floated during the test and a possible "strain relief" effect was noted.
     

    A minor revision 1.3 of the CAS software has been installed on the
    2-channel and 4-channel racks. Air supply has been run to the 2-channel
    rack, and its BSC 8 database has been transferred from the 4-channel rack.
     

    We now have CAS capability on BSC 4, 7, and 8.  The calibration of the Fine Actuator Hytec prototype PZT channels is nearing completion. We expect to receive them back from Physik Instrumente next week.
     

    4/27-5/4---A height adjustment was performed on BSC 7. The operation went smoothly.  An air bearing filter upgrade is planned to extend air bottle life. Parts are on order.
     


    LIGO Livingston Observatory (LLO) Operations (Coles)



     

    Detector Commissioning: We measured the cavity pole frequency of the mode cleaner and found that it has not changed  over tyhe past two months. We measured the alignment sensing matrix for the wave front sensors and then implemented the alignment control software. We found that there was some gain at DC but negligible gain above 0.1 Hz. We are trying to increase the gain by putting more power on the wave front sensors. We are now investigating the relationship between the SFW outputs and the control signals placed on the MC mirrors. We find that there is a strong coupling between longitudinal actuation and measured pitch and yaw.

    We re-measured the violin mode Q of the recycling mirror suspension in air. This time we measured the motion of the wire with a shadow sensor using a He/Ne laser and a centroid sensor. We excited the violin mode with the same coil as previously. We drove the coil by a sine wave at one half of the violin mode resonant frequency so that the wire oscillates at the resonant frequency (335 Hz). When the excitation was turned off clean ringdown waveforms were observed. The Q value estimated from the decay time was 2520 +/-83. We also swept the frequency of the excitation (signal to drive the coil) and plotted the amplitude of the detected signal as a function of frequency. The Q value estimated from the width of this plotting agreed with the Q estimated from the decay time.

    We optimized the local (position) damping of MC1, MC2, MC3 and MMT1. We gave a square wave to the POS test port and measured the POS monitor's response. For MC1 and MC2, the response was close to the theoretical step response of the SOS calculated by P. Fritschel when POS gain was 10. So we set all gains at 10 for MC1 - MC3. In the case of MMT1, POS gain of ~5 gave the closest response to the theoretical step response. We also observed that the ratio of the stack rms motion to the pendulum rms motion (estimated from the spectrum of POS monitor) increases linearly with the POS gain indicating that as the gain increases the optic tends to follow the suspension tower's motion.

    CDS: Juilien Svoboda will be leaving LIGO after May 4 to prepare for her new baby. She has completed two documents describing PEM software interfaces to the dust monitors and FMCS. Drafts can be viewed at http://abundance.ligo-la.caltech.edu/~juiliens/ and final versions will be placed in the DCC after review.   If any question should arise in the future, Juilien can be reached through email at home.

    Installed cables at the south and west end stations for camera's, illuminator, quad cell and optical lever.

    Detector installation: Cleaning and baking of COS components continues. ISCT3 moved from lab into position. ISCT1 moved into lab for assembly.

    Weather Stations: South End remote connection established (this allows among other things Web access when equipment is all functional). South end datalogger program running and cds collection software functioning and talking to data logger.

    Data logging and Seismometers: ADCU 5 and 6 have all the anti-aliasing chips in and are running. Initial seismic coherence measurements done. Anthony has made some initial measurements of the coherence of the z-axis of the three seismometers.

    Community relations: LSU physics majors taking Greg Stacey's optics class toured LIGO last Friday. About 50 K-12 teachers participating in project PLATO, a teacher in-service program to improve science teaching, spent a full day at LIGO on tuesday touring the site, going through the hands-on activity with polarizers and spectrometers, and then conducting other business using our conference rooms. Three more groups are scheduled to visit this Saturday.
     


    MIT (Shoemaker)


    All MIT activities reported in other categories


    Caltech (Sanders)


    All CIT activities reported in other categories


    Detector/Technical Support (Whitcomb, Coyne)



     


    Installation:
    Hanford
    Livingston
    Commissioning:
    Hanford
    Livingston
    Other Science/Engineering
    Activities

    Special Note:

    A director's review was held cotemporaneously with the PAC review meeting. The topic was the 2 km long arm testing that has recently completed. The viewgraphs can be found as Adobe pdf files in the electronic Document Control Center (DCC) as follows:
    Note: These links will not work until the files are reviewed and transferred into the archive.
    Stan Whitcomb, Introduction and Concluding Remarks
    Peter Fritschel, Servo Charaterization and Performance
    Nergis Mavalala, Suspensions
    Daniel Sigg, Characterization of Environmental & Input Beam Noise Inputs
    Bill Kells, Core Optics Characterization

    1.0 INSTALLATION (including fabrication and subsystem test)

    see also the Installation web page

    1.1 LHO

    Length Sensing & Control Electronics

    Dale Ouimette
    The 8 Channel LSC Whitening Filter PCB layout is complete and in fabrication. Blank boards are due back in one week. It will take about a week to stuff the first article and test it along with the LSC Anti Alias Filter first article. In a day or so I should have the Mode Cleaner GDS Interface board PCB layout complete and in fabrication. I am also getting back to the LSC Photodiode PCB redesign. There will probably not be any significant changes other than some mechanical fixes to the board.

    Video Cameras

    Mike Zucker
    Completed installation of video cameras for full W 2k interferometer and documented configuration for tracking and control.  Now obtaining quotes for additional cameras & optics as indicated by increased coverage scope.

    ISC Tables

    Mike Zucker, David Ottoway
    The balance of the ISC tables for the 2 km interferometer are nearing completion. Completed enclosure hardware detailing on ISCT9 which is ready for wiring and final alignment to the IFO.  Optical assembly of ISCT10 is underway.

    Input Optics

    Haisheng Rong, Mike Landry, David Ottoway, David Reitze
    We safely moved MMT2 towards MMT3 (and MMT1) by 9 mm (+/- 0.1) to improve the mode matching into the arm cavities.

    We started MC realignment and we encountered a major problem: MC1 (surface normal) seems tilted up by about 1.3 mrad and can not be fully compensated by the SUS controller. We checked the balance angle of this mirror after we changed the wire in the optics lab, and it was within 0.5 mrad. Some changes must happened during transportation and installation. We are working on the final diagnosis.

    An AR coated beam pick-off wedge (30') from CVI has been checked out, and it looks suitable for the RFAM measurements after the EOMs on the PSL/IO table. At 3 - 8 degrees of angle of incidence, the reflectivity of the AR surface is 0.5% and the difference between S and P components is 3%. As a comparison, the beam pick-off mirror currently being used has transmission of 0.8% and the difference between S and P is 5% at 8 degrees of angle of incidence.

    Core Optics Support Installation (& Core Optics Alignment/Position check)

    Mike Smith, Dennis Coyne, Doug Cook, Mike Zucker, Larry Jones, Betsy Weaver, Hugh Radkins, Janeen Romie
    Check of the alignment and positioning of the 2 km core optics components is proceeding, with some difficulties; This is a first step in developing the alignment reference for the installation of the balance of the 2 km COS components. An autocollimator was set up in the spool area at the end of the X beam manifold, on the beam axis and aligned set to the theoretically best ITMx HR surface alignment (as derived from survey monuments). After much archaeology to uncover all the cumulative corrections needed to reconstruct the X arm alignment as of the last "good" 2k cavity run, we decided the original monument-based initial alignment procedure was more reliable, so we used that. We have now proceeded to adjust the alignment of the FMx and BS. Inconsistancies and repeatability problems are slowing down progress against the plan.

    Optics Table Level and Elevation

    Mike Smith, Doug Cook, Mark Guenther, Corey Gray, Doug Cook, Larry Jones
    Balance weights on the WBSC 4 optical table were shifted to level the table prior to BS alignment. The table elevation was measured with an optical level, and found to be 3.0 mm low. This was corrected with a 3.3 mm upward shift, using the CAS system. At that time, WBSC 4 air bearings were confirmed to be free floating. The WBSC 7 table was found to be out of level by 0.8 mrad, but was not corrected as the ITMx is being referenced as a primary alignment axis. The WBSC 7 table elevation was measured and found to be within specification.
    WHAMs 7, 8 and 9 optical tables were checked with an optical level for levelness and elevation: WHAM 7 was found to be within specification. WHAM 8 was raised 0.5 mm on the east side to correct an out-of-level condition. WHAM 9 was raised 2.1 mm on all four corners to correct an elevation deficiency.
    N.B.: It is not yet clear whether some of these alignment and elevation shifts are self inflicted, corrections to initial or re-visited installation or drifts representing instability of the tables; This needs to be sorted out. (D. Coyne)

    Gerrado Moreno, Larry Jones
    An instance of ribbon cable touching (contacting the support table, between the support table clamp and the first leg element clamp) was discovered on the east side of WHAM 8. This will be corrected by adjusting the unsupported length.
    N.B.: This is the first instance of a cabling problem on the HAM chambers. The general problem of cable creep is under investigation. (D. Coyne)

    Pre-Stabilized Laser Modifications

     Rich Abbott, Peter King Now that the hardware has been installed, we need to finish the characterization and commissioning of each system.  This will be done this week.

    Seismic Fine Actuator Control Electronics

    Sander Liu, Fred Mann
    Seismic System - Board No.2 PCB design is now complete and the boards are on order. Fred is working on the faceplates for both board No.1 and 2.

    1.2 LLO

    Automated Polarization Control

    Ed Daw
    This week I am installing hardware in preparation for automating the polarization control for the laser beam at Livingston. The software is ready; The crate will be rebooted and the software tested soon to see if we can control the New Focus rotating stage from epics.

    Core Optics Support Assembly

    Lee Cardenas
    The following Core Optics Support assemblies have been built: I will continue assembling the rest of the 4K Pick-Off mirror assemblies and hopefully finish cleaning the remaining black glass.

    2.0 COMMISSIONING (incl. diagnostics and characterization)

    2.1 LHO

    Arm Cavity Mode Matching

    Guido Mueller, Bill Kells (reported by David Reitze)
    Guido and Bill Kells have converged on a value for the mode matching in the arm cavity - somewhere between 96% and 97% in TEM00 power.  The MMT has been moved 9 mm closer to MMT3 (see above) to improve the mode match to > 98%.

    Arm Cavity Mode Matching

    GariLynn Billingsley
    Provided 2 ITM Phase map differences with rms data for Bill Kells in order to look into contrast defect measurements at the 2 km LHO interferometer.

    Beam Dump Assembly Resonant Frequencies

    Betsy Weaver, Luca Matone
    An accelerometer was mounted on a beam dump and resonant frequencies were measured; data is being reviewed. Two resonances seemed to dominate the power spectrum: ~14 Hz (compliance of the rotary joints?) and ~26 Hz with non-negligible frequency components up to ~200 Hz. The structure was problaby being excited by acustical coupling. By observing the ringdowns, we estimate a Q of 50-100. Mike Smith will compare this modal survey to design requirements.

    2.2 LLO

    Input Optic Damping Gain Optimization

    David Reitze
    We optimized the local (position) damping of MC1, MC2, MC3 and MMT1. We gave a square wave to POS test port and measured the POS monitor's response. For MC1 and MC2, the response was close to the theoretical step response of  SOS calculated by P. Fritschel when POS gain was 10. So we set all gains at 10 for MC1 - MC3. In the case of MMT1, POS gain of ~5 gave the closest response to the theoretical step response. We also observed that the ratio of the stack rms motion to the pendulum rms motion (estimated from  the spectrum of POS monitor) increases linearly with the POS gain indicating that as the gain increases the optic tends to follow the suspension tower's motion.

    Optical Lever Drift (Data Monitoring Tool)

    Ed Daw
    I am writing a Data Monitoring Tool monitor in root for looking at long term drifts in the optical lever signals at the South (Y) endstation for Joe Kovalik. This code should be running 5/3.

    Mode Cleaner Wavefront Sensing & Control

    Joe Kovalik
    The wavefront sensors were tested and after a great deal of debugging, all channells worked in DC and RF.  Also, all the alignment servo signals worked properly. The elements of the alignment sensing matrix were measured and then implemented in order to close the alignment loop.  There seems to be some gain at DC.  This is especially evident as changing the signs of the feedback misaligns the mode cleaner. Measurement of the alignment transfer function shows very little gain in the system.  We are trying to increase the gain by putting more power on the wavefront sensor photodiodes. We rebooted the IOISC and IOSUS1 crates.  We recovered functioning of the system, although we still need to make more complete burt files.  The mode cleaner seems to be locking with slightly less beam jitter than before.

    3.0 Other Engineering and Scientific Activities

    3.1 Design/Analysis

    Core Optic Metrology

    GariLynn Billingsley
    We've had a visit in the Met. lab by George Weal and Tim Ranalli of Physical plant.  They suggest modifying the drive on the air handler to use the original fan, albeit at a lower speed.  I'm a bit nervous about this, but if it works it will have been well worth the try.  Interestingly enough they found that a flow regulator was supposed to have been installed when the chilled water was put in originally.

    The three flat test progresses when the room temperature is stable.

    Digital Suspension Controller

    Rolf Bok
    Continued work on code for digital suspension controller.  Completed some initial timing tests, which look favorable.  Presently trying to work out an  upsampling filter (as LSC runs at 16k, ASC and SUS at 2k) so that we don't get signal imaging effects from the lower sample rates.
    Implementation of a digital sus controller will require modifications to the DAQ system. Not only will we have the same data channels as with the analog  controllers, but we will also have associated GDS excitation and test point data to deal with.  This is not accounted for in the present DAQ reflected memory (which is already full), plus the end station controllers do not presently have these memory modules. I am running some timing tests to see if the suspension signals (and corresponding GDS signals) could be moved from VME reflected memory onto PCI bus reflected memory. This would have several advantages over adding more VME memory boards, including price ($2K vs $8K), memory (64MB vs 2MB), and size (PMC plugs onto VME processor ie no VME slots used). Down side is only half the speed, but there would not be as much data on this net as the main DAQ net. Timing tests are being focused on the CPU which must read data from the main DAQ net, plus this new net, reformat the data, and move it to the framebuilder.

    Dataviewer Software

    Hongyu Ding, Rolf Bork
    Worked on layout for redesign of Dataviewer software (as per meeting with Stan, Daniel, et. al. at Hanford).  Hongyu is now starting work on modifying the user interface.

    Global Diagnostic System (GDS)

    Sander Lui
    Global Diagnostic System (GDS) - In the process of designing the signal processor for the system.

    3.2 Issues Concerns

    Second Source for Coatings

    Helena Armandula, Jordan Camp
    REO is busy with some very lucrative business (communications?) and is growing at an impressive rate.  In essence Ramin said that they would not be able to be as responsive to LIGO as they had been in the past.  He suggested that perhaps another company (one Helena recognizes) might be able to work with us on our R&D type runs which involve coating properties.  The only thing the other company can't give us is uniformity, because they don't have the kind of planetary system that REO does. Ramin emphasized that he personally is still very interested in LIGO but he doesn't have control over the scheduling of chambers. The bottom line: REO coating runs will need to be scheduled far in advance and will need to have some cushion built into the schedule.

    Optical Lever Laser Replacement/Wavelength Change

    Mike Zucker, Mike Landry
    Mike Landry has measured reflectance of some COC coating witness samples at 670 nm on a tight (1 degree) angle-of-incidence grid.  No sharp minima have been found, which is puzzling given the low reflectances experienced with the laser autocollimator. We are rechecking the bookkeeping and original QA scans of these samples to see if we can resolve the puzzle.

    ITM Difference Map
     

    Phase map difference between transmission measurements of 2ITM01 and 2ITM04 (flipped about Y)
    LHO 2K Y and X ITMs respectively.

    T=Tilt  P=Power A=Astigmatism
    Diameter  rms-T  rms-TP  rms-TPA
    (mm)  (nm) (nm) (nm)
    200 18.9 18.7 18.5
    80 7.7 4.4 3.6
    60 5.9 3.8 3.5
    40 4.0 3.2 3.1
    30  3.5 3.2 3.1
    rms surface variation with Piston subtracted, over various diameters
    with Tilt Power and Astigmatism removed
     

    A Phase map of the full 200 mm of ITM Difference data
    Taken from the two CSIRO Phase maps of the ITMs in transmission.  Measured through side 2, off side 1 and returning through side 2.  The factor of 2 is accounted for in the CSIRO software.  ITMy-ITMx (flipped about y)


     
      2itmDIFF-LHO-200mm.jpg


    40 Meter Interferometer (Weinstein)



    Thermal Noise Interferometer (Libbrecht)


        This week we began a pumpdown of the TNI, in order to check our mode
    cleaner optics and track down some residual shake in the mirrors, which are
    still clamped to their earthquake stops.  We also wanted to do a dry run to
    make sure our vacuum hardware still works, since the pumps haven't been
    exercised in some time.
     

        In preparation for this experiment, we moved some optics out of the
    chamber and changed the oil in our large roughing pump.  We closed the
    chamber on Tuesday and began pumping down on Wednesday.
     

        Alignment was not affected much by closing the chamber.  The mode cleaner
    still resonated in the TM00 mode, but we did need to walk the beam to
    recover optimum transmission, about 70% for our rough alignment.  We have
    not yet measured the noise or the finesse, but we expect to do so within
    the next day or two.
     

        Eric presented a paper at the APS meeting in Long Beach on Sunday, Ken
    gave a talk at the PAC meeting on Monday, and Luca has been at Hanford all
    this week.


    LASTI (Zucker)


    ----------------
    Vacuum:
    Ed K. has physically completed all the remaining annulus systems and
    tested/pulled vacuum on all but BSC0 using turbos.  Annulus
    ion pumps are operating valved off as we wait for the annulus waterload to
    decrease.
     

    Mike Z. has returned from travel and is trying to calibrate
    and interpret the RGA spectra from the main volume.
     

    Infrastructure:
    Nearby construction has stepped up, with vibrating pile drivers now
    inducing perceptible accelerations in our building (especially
    unnerving to the few of us with direct earthquake experience).
    "High-level" talks have been initiated with those in charge.


    Data Analysis and Computing (Lazzarini)


    Simulation and Modeling

    Talks/presentations

    Three talks/presentations are given related to e2e in the past week.
    Two are at ASP by Biplab (e2e general and optics) and Hiro (MSE).

    The third presentation was given by Hiro at the PAC meeting, summarizing
    what has been done at the W2K one arm run, what is going on, especially
    the lock acquisition work by Matt, and the future planning and resources.

    Meeting

    After the PAC review meeting, in the regular e2e meeting, with Albert
    and Kent attending, two topics which were hilited at the PAC were discussed.
    One was various possibilities of speeding up the simulation.

    The first action item is to evaluate DEC ALPHA. Ed will install e2e-all
    package on the existing DEC ALPHA to see the compatibility and the speed
    gain. After the installation, Hiro will join to test the simulation engine
    compatibility test. If we see positive results, Albert will look into
    the possibility of purchasing faster DEC ALPHA (1.2GHz), possibly with multiple
    CPUs.

    There are several possibilities of the speed up by the imporvement of the
    software code. Hiro will lead this effort, possibly with the help of <to be
    appointed> programmer(s).

    Another topic discussed was the future development of alfi. There was a
    suggestion raised to move to use JAVA. The pros and cons are discussed,
    including the scope and lifetime of the software, but no definitive
    conclusions come out of the discussion.

    Lock Acquisition

    The c code version of the Lock Acquisition filter is developed and improved.
    e2e codes are modified and it is easier now to share the codes between
    CDS and e2e. A C++ code has been completed which provides the same
    functionality as Peter Fritschel's pz2iir.

    Alfi

    Bruce wrote a perl code to help people to reorganize box files in a logical
    way, which can be handled properly by in the new version of alfi.

    paper

    Biplab started planning to write a e2e paper on the implementation of the
    optics and field.

    MSE

    G.Cella was supposed to come on April 29 for one week at CIT. Because of
    unknown reason, he could not get the prepaid ticket at Pisa and the trip
    was canceled. The next trip is being discussed, and the possible visit is in the
    middle of June.

    LIGO Data Analysis System


    LDAS presented its status to the PAC this week. There were no major
    surprises or concerns raised during the presentations. On Monday,
    bugs were found in the socket testing benchmark code where had to
    be fixed "just in time" to present on Tuesday. The code is now able
    to accurately measure data throughput in LDAS.

    Even though the 0.0.11 version of LDAS was successful in injesting
    trigger data from the GDS DMT system over the weekend, several significant
    bugs in the software were identified and are being fixed. Among these
    were corruption of char and char_u data types in the ilwd upon being
    passed through the strstream class-still open; slowness and even failure
    of the lightWeightAPI to handle large LIGO_LW documents-now fixed; the
    metadataAPI was corrupting its logfiles-now fixed.

    The dataConditionAPI now has an FFT engine that supports both double
    and single precision calculations. This required the use of dynamically
    loaded libraries to implement since the FFTW package only supports one
    or the other in a process.

    The wrapperAPI's interface to LAL code is better defined this week after
    a meeting with UWM and a tremendous effort by Jolien Creighton to join
    the two worlds. The communications of input data have now been completed
    and the communication of output data is about half done. Work will begin
    on the flow control for the parallel computing once the output data is
    working.

    Peter Shawhan overhauled his GUILD userAPI's communication with LDAS to
    use a new socket based method. He also added the ability to run multiple
    jobs and to cancel a job.

    A bug in GCC was discovered which caused the frameCPP library to be non
    reentrant. A fix exist for this within the GCC CVS repository and was
    tested and found to be reason the library was not reentrant.

    General Computing

    MIT:
    Working on upgrading a couple of computers and fixing some security issues.

    CIT:
    Docuserv has been taken off of gsparc and is now on its own machine. There are a
    few minor changes that need to be made but so far everything is looking pretty
    good.

    The third floor of Bridge and Wilson House now have color printers installed.
    Duplex units are being added to the color printers on the 3rd floor of Bridge
    and the one in Millikan.

    The hot topic for the day was the virus alert for the "ILOVEYOU" virus.
    Fortunately, there were a number of people that helped spread the word such as
    David S. at MIT and Liz W. at CIT. Also, thanks to Phil E. who was able to get a
    temporary method of fixing the problem out to us. Most of the virusscan vendors
    now have a fix for the problem.

    Full monthly backups were finished.

    Larry is working on some financial and future planning of GC equipment.
    Presently, talking with each of the groups to get more information on what
    future needs may be.

    Barbara has made a number of WEB changes and is working on a server upgrade for
    document searches.


    LIGO II/Advanced R&D (Sanders)


    Stiff isolation system (S. Richman, J. Rollins, S. Chatterji)

    We have been working on developing robust controllers using the position
    sensors and geophones.  We can now close all 6 loops on the upper stage and
    4 of the 6 loops (2 vertical, 2 horizontal) loops on the lower stage to
    within a factor of 2 of the design gain.  This configuration is quite
    stable and reduces the very-low-frequency horizontal motion we had
    experienced with earlier controllers to ~10 micrometers.  We are not
    lacking for seismic drive signals; construction activity in our backyard
    has actually increased and crept toward us (20 m from the experiment at
    closest approach!)

    Jamie is nearing completion of a setup to measure multiple transfer
    functions of the prototype simultaneously using the digital control
    system.  Shorouv is working on replacing the forcer current drivers (the
    current set are on loan from JILA).

    Monitoring of the position sensors has shown the prototype has had little
    significant drift over the past 1 1/2 months. Operating in air with ~ few
    degree C temperature changes in the high bay, motion in horizontal and
    vertical directions has been less than 10 micrometers.  The pitch and roll
    have been negligible, though there has been a noticeable yaw.

    From: Riccardo DeSalvo <desalvo@ligo.caltech.edu>
    "soft" system report

    We held no group meeting this week because of APS, PAC and TAG meeting.
    So I made up the weekly report from my personal inquiries.  I may have
    made several mistakes.

    Everybody, prepared the seven APS presentations for last Sunday’s APS
    meeting in Long Beach.  It was a very good show!
    I was also pleased with the remaining TAG members visit to our lab.

    Szabi
    New HAM design simulation and definition of drawing parameters.
    Continuing on earthquake injection.

    Alessandro
    Tested Accelerometer on IP, found a large resonance at 30 Hz, that
    almost saturated the accelerometer response.  Finally tracked the
    resonance to the leg’s segmented counterweights vibrating in quadrupole
    fashion.

    Virginio
    Full diagonalization achieved, found bug in software. Closed loop of
    damping. Measuring performances.

    Akiteru
    Simulation: Writing a document on designing of suspension for TAMA SAS.
    Controls: Started working with Virginio. Found a bug in a program of
    actuation matrixdiagonalization.

    Hareem
    Testing new blades on the blade testing fixture.  The correction factor
    applied from the old to the new blades was found to be 12 mm instead of
    6.  Will try to shorten blades and will determine new correction
    parameter.

    Riccardo
    Designed ring counterweights and put them in production both for the
    test setup and for TAMA.  Stopped delivery of TAMA IP system until new
    counterweight will be ready.  The new counterweights will use the same
    bell for the TAMA prototype and a new one for the test tower. E.t.a. to
    be figured out starting from raw materials delivery times.

    Flavio
    Tested the Marconi drive lasers

    Small reminder.
    This coming saturday, in the outreach spirit, we will host half a dozen
    High School students, they will characterise a few filters.  Please do
    not leave measurements ongoing because we will disturb them. Do not
    leave delicate and/or dangerous things around.
    Thanks to the ones that will assist me.     Ric
     

    From: "Ryan C. Lawrence" <rclawren@ligo.mit.edu>
    Core Optics Compensation:

    I finished installing and aligning the in-vacuum optics, heaters, and
    shields, and realigned the optics on the I/O table.  I'm continuing
    work on characterizing the CO2 laser in situ by using the galvos to scan
    the beam over a pyroelectric sensor.  The VI appears to work, and the beam
    looks fairly decent.  I'm now working on ironing out a few minor details
    in the VI, and making sure that what I'm seeing is real.
     

    From: GariLynn Billingsley <Billingsley_G@ligo.caltech.edu>
    Metrology

    Veeco has not yet responded to the RFQ for an interferometer upgrade.  They
    hope to respond next week.
     

    From: Phil Willems <willems@ligo.caltech.edu>
    Hydroxy-catalysis bonding:
    -------------------------

    Last week we tested the last of the hydroxy-catalysis bonds that we made at
    Stanford in February.  Our ultimate strength was 2.5e7 Pa, which is within 15%
    of the unpublished ultimate strength value from Gravity Probe B.  There is still
    lots of scatter in bond strength, but most values are well above LIGO II
    requirements.  Future work will focus on speeding up bonding and identifying the
    clinkers as they are made.  Tests of an ultrasonic flaw detector for this
    purpose were inconclusive.  (Helena Armandula, Phil Willems)
     


    For additional information about this report, contact sanders@ligo.caltech.edu