Weekly Report for Week Ending November 9, 1999



 Project Control Meeting Agenda  Highlights  Hanford Observatory     Livingston Observatory     Detector   Project Office    System/Data Analysis    Administrative   Past Weekly Reports

The Project Control Meeting Agenda for Monday  November 15, 1999 will be:

CANCELLED

Special Items:


Special Announcements:


Weekly Report Highlights

Fringes in the 2K LHO Michelson!
 
 
 


LIGO Hanford Observatory (LHO) Operations



 

Bake Oven:
----------
(K. Ryan)

LHO Vacuum Bake Oven A load #64, consisting of
ETM Telescope Assemblies 002, 003, 004 and 005 was
released earlier this week.

Load #65, consisting of two reference cavities, is
vacuum baking at this time and is scheduled to be released
Friday, 11-12-99.

A component of the automatic shutdown and autodailer
system in the control panel for Oven A was found to be defective
this week.  The manual settings of the output variacs are being
used as the sole redundant over temperature protection (temperature
controller is primary protection) until this component can be
repaired.

Vacuum Bake Oven B is being repaired (welded) again
and should be available for re testing next week.
 

Core Optics Support:
--------------------
(D. Cook, B. Weaver)

Through a big effort of several people we managed to complete the
alignment of the 2K Core Optics in the LVEA, coupling them with the APS
telescope and its steering mirrors, the IOO optics and the Mode Cleaner.
The PSL beam was propagated through the APS telescope and its steering
optics and onto a target at the HAM 10  view port where it will eventually
enter the IOT10 optic table. With the beam now propagating through all the
optics, fringe patterns were observed in the Mode Cleaner!

It was necessary to reset most of the Optical Levers as part of the final
alignment. For your information if you monitor optic levers remotely, here
are the
changes:
     ITMy-2k nulled ( a loose mounting base plate was suspect in large changes
          during pump down).
    ITMx-2k nulled (after it was reinstalled following x-arm spool replacement)
    FMy -2k & FMx-2k, MMT3 nulled ( after the core optic alignment changes)
    RM nulled (after laser diode replacement)
    BS-2k (no change)
    ETMy-2k (remote monitoring capability only)

The optics tables were checked for final level (no changes were made),
optics were check for proper safety stop settings, the core optics went
through a final CO2 cleaning where necessary, the RM was purposely
misaligned for the 2k "short-arm" test, temporary fixtures removed, SUS
controllers checked out, bodies were removed from chambers and the doors
were replaced and the pumped down began.

The last of the 2K (ETMx) Core Optics will be readied today and installed
next week if all goes well. We should be staged at the X-MID by Friday.

COS
Betsy Weaver

Last week, we finally, successfully aligned the mid-station COC's.
As I'm sure you've heard, we were able to see fringes from the
APS telescope output in HAM 10.  Mike and I aligned the optical
train late last week to point the beam at a target which represented
the view port.  Haisheng and Peter revisited this alignment earlier
this week and fine tuned it.  The beam exits the window correctly.

Although one would think that with last weeks major accomplishment
behind us, things would calm down, however Doug and I have found
ourselves busier this week.  We are currently resuspending the ETMx
mirror after it's vacuum bake - it is due for installation at the X-Mid
next week (the tilt angle came back to almost 0 degrees - off by
maybe a minute).  I am also trying to assemble the ETMx Telescope
that just came out of the vacuum bake on Tuesday - also due for
installation next week.  I just received the ETMx beam dump which
will begin it's processing (cleaning and baking) today - ALSO due
for installation next week.  We are cutting it close.

Monday, John Worden helped me install the conical baffle in the
X-manifold in the LVEA, taking advantage of the easy access with the
spool piece sitting on the floor.  This baffle went in a lot easier  than the
one at the Y-Mid.  It still took some fussing, but we managed to get it
rigid and unmoving.
 

Seismic Systems:
----------------------
(C. Gray & H. Radkins)

4k HAM Installation work:

Air Bearings are installed on HAMs 1,2 &4 (HAM 3 is receiving air bearings
as I type).
The Crossbeams were installed and connected to the Support Tubes on HAMs 2&3;
other than final leveling, all 4k HAMs are ready for stack
installation--which is dependent
on processed Seat availability.

2k BSC Installation work:

Stack was installed and the chamber was sealed up at x-mid last Thurs.
afternoon.
Seat exposure time was ~29 hours w/ a humidity ranging from 15-29%.  This
concludes
SEI Installation for the 2k interferometer at LHO!

4k BSC Installation work:

Staging began for work on BSC3.

Computing:
----------
(C. Patton)

Continued network security maintenance.  Continued moving computers
around to upgrade some computers and move the older computers out to the
Mid and End stations.  Continued trying to contact the Sun
representative to get maintenance contracts renewed.

Did the usual backups, helped with several printer and PC problems and
kept the GC accounting paper work up to date.

Electrical & Electronics Systems:
---------------------------------
(R. McCarthy)

Installed the necessary electronic components for the ETM-X install next week.
The controller will be tested tomorrow.  The database was built today and
all the
signals are present.  The cabling for the auxiliary equipment is being
completed
today and should be ready for Monday.  One minor problem is the lack of a
Xycom 220 board.  This will cause some minor inconveniences but work arounds
are being installed.

We have decided to introduce some more competition on site with the electrical
contractors.  This week I met with American Electric to bid some jobs for us.
They are a reputable company and I expect some very competitive bids
between them
and Sun River.  Not that we are unhappy with Sun River it is just that
sometime
contractors get complacent.
 


LIGO Livingston Observatory (LLO) Operations



 

BSC#2: Completed stack buildup, completed cable installation, did continuity
check, all OK. Spring seat/shim exposure time 31 hrs. 45 min. Corner station
now being pumped down. (Riesen & co.)

With the help of Janeen and Helena, Gary and Sany continued preparing small
optics
suspensions. As of Nov. 10,
One Mode cleaner flat mirror has been balanced.
All six magnets, a wire standoff and a wire guide rod have been glued to
the other mode cleaner flat mirror, two mode matching telescope mirrors and
a steering mirror.
A wire stand off and a guide rod have been glued to the mode cleaner curved
mirror.

Bake out of X-1 has begun.

Most of the week was preoccupied with preparation and execution of the LIGO
Science Symposium and Inauguration activities. A fuller weekly report will
be issued next week when things get back to normal.
 


WBS 1.2, 1.3    Detector Group


----------------------------------------------
Interferometer Sensing and Control -- M Zucker
(WBS 1.2.1.1.6, 1.2.1.1.7)
----------------------------------------------

Report from LHO (Peter, Haisheng, Nergis):
------------------------------------------
This past week was spent rather tediously aligning the IO beam to the core
optics, but with the big payoff of seeing for the first time interference
fringes in the core optics!
Alignment of the mode matching telescope got off to a bad start last
Friday when it was discovered that a side magnet on MMT1 had fallen
off (the one the osem was using, of course). When we tried to move (in
place) the osem to the other side of the suspension, we saw that this
magnet was too low and would interfere with the osem. So we pulled
MMT1 out of WHAM7 and rehung it with a new wire, raising it up a couple of
mm; in the process we also adjusted the centering of the face osems, two of
which had also been significantly off-center. We then went through a
couple of iterations of co-aligning the IO beam with a reticle pattern
that was being projected through the Y-manifold, set up initially to
align the core optics. This ultimately gave a pretty good retro-reflection
of the IO beam off the recycling mirror, which we fine tuned by adjusting
the orientation of MMT3.
We then blocked the beam going to the X-arm, so that we had a cavity
formed by the recycling mirror and ITM-Y, with the beamsplitter inside
making the finesse very low. The angle of FMY was adjusted until we saw
nice interference at the beam coming out of the anti-symmetric port
telescope -- at times the beam would uniformly flicker between bright and
dark, though alignment fluctutations also produced varying spatial fringes
across the beam (we're still in air!). Some time traces of the power at
the AS port can be viewed at:
http://www.ligo-wa.caltech.edu/~pf/2km/*.pdf
We then tried to bring in the beam from the X-arm (using FMX), but saw
only small increases in the stored power. Later, after the Y-arm had been
blocked by the gate valve for pumpdown and we had again a simple cavity
formed by the recycling mirror and now ITM-X, we found that more pitch
adjustment was needed on this arm to get good alignment with the RM.
We were out of range on FMX, so by pitching the beamsplitter we were
able to see the same kind of interference we had seen with the Y-arm.
We finished by carefully misaligning the RM and dumping the RM reflected
beam into a pair of beam dumps, in preparation for the 2km cavity testing.
Unfortunately, this means we won't have another opportunity to see
interference in the power-recycled Michelson for a while. However, as soon
as the diagonal section and X-manifold are pumped out, we will have the
opportunity (prior to opening up to the beam tube) of looking at the
Michelson interference -- we will soon be able to make the very
interesting measurement of the contrast in the simple Michelson.

-------------------------------------------
Lasers and Optics -- J. Camp
(1.2.1.1.2, 1.2.1.1.3, 1.2.1.1.4,1.2.1.1.5)
--------------------------------------------
Prestabilized Laser -- Peter King
--------------------------------------------
- The current shunt actuator was installed on laser #107 at Caltech by G.
Truong and S. Gomes of Lightwave Electronics. However two laser power
supplies, one of which was brand new, malfunctioned. For reasons unknown
four FETs in the laser power supply blew.
A possible cause is a ground path through the indium bonding
between a 20-W diode bar and the power amplifier cold plate. Whilst this
has not occurred on any 10-W laser before, it has been apparently observed
in other Lightwave lasers. Both the laser and power supplies have been
returned to Lightwave for repair.
- Following the installation of the new low voltage PZT version of the
pre-modecleaner (PMC) at LHO, there were reports of large intensity
fluctuations in the output of the PSL. The reasons for this are not
known but one possible cause is the epoxy bonding of the aluminum cap
holding the PZT to the fused silica body.
The intensity fluctuations were looked for in the output of the
LLO PMC and were not observed. Both PMCs are identical in construction.
- A reference cavity vacuum chamber has been repaired by Nor-Cal. Previously
during the initial cleaning and preparation for baking, it was observed that
one of the ConFlat knife edges had a nick in it. The chamber is now back
at LHO for cleaning and baking.

Input/Output Optics -- Dave Reitze, UF
-----------------------------------------
UF weekly report.
Dave and Isabelle Reitze had a healthy 6 lb baby girl this morning. Mother
and daughter are doing fine.

# DHS Congratulations!

In-vacuum Faraday isolator
Design of a subassembly module for the in-vacuum Faraday isolator is
complete and parts are being made in the shop. This is a small optical
aluminum breadboard on which the rotator, polarizers, and rotators can be
assembled and aligned prior to insertion into the HAM.
WA-2k MMT alignment
Finally we have achieved good MMT alignment. The input beam is very well
centered on RM (within <5mm) and gets retro-reflected, rejected by the
Faraday isolator and sent to the symmetric port.
What is more, we also aligned the short Michelson/recycling cavity and we
observed nice fringes at the output of the APS telescope. A contrast of
(Max-Min)/Max = 90% has been obtained. Some neat data traces will be
available soon.
We also measured the mode matching parameters of the 2k IFO input beam
using a large aperture (7") COS lens and a beam profile scanner. Data will
be analyzed.
LA-4k installation
With the help of Janeen, Helena, and Gary, we continued preparing small optics
suspensions. As of Nov. 10 the status is:
One Mode cleaner flat mirror has been balanced.
All six magnets, a wire standoff and a wire guide rod have been glued to
the other mode cleaner flat mirror, two mode matching telescope mirrors and
a steering mirror.
A wire standoff and a guide rod have been glued to the mode cleaner curved
mirror.

Core Optics Procurement and Metrology -- GariLynn Billingsley
-------------------------------------------------------------
We are finished with SPETM07. The next optics to be processed (in
order) are BS, ITM for Livingston. We have learned more about the art
of keeping up with changeing room temperature using chilled water flow
as a control and measured tilt as a feedback.
 

Core Optics Coatings -- Helena Armandula
--------------------------------------------------

Assisted Janeen and Sany with suspension work (balancing, rebalancing
optics, preparing PAM magnets and OSEMS.
Inspection of epoxied springs in progress.

Core Optics Support -- Michael Smith
------------------------------------
PO TELESCOPE
All the production PO telescopes have been received and are being inspected
prior to shipping to LHO and LLO for cleaning and baking.
ETM TELESCOPE
All production ETM telescopes have been sent to LHO and LLO for cleaning
and baking. The AR coating on three lenses were damaged during the normal
LIGO cleaning procedure. The lenses have been sent back to the manufacturer
for evaluation. Helena A. is revising the cleaning procedure for commercial
optics. The 2K ETMx telescope is being assembled by Betsy W. at LHO for
installation on 11/15.
PO MIRRORS
Awaiting delivery of 4K LHO and 4K LLO PO mirror mounts.
VACUUM WINDOW
Widows have been installed in HAM10, BSC6. BSC5 window is being installed
prior to 11/15.
ARM CAVITY BAFFLE
Received partial delivery of production items for Inner Baffle, awaiting
balance. Received partial first article parts of the Outer Support Frame.
The top assembly drawings for five arm cavity baffle configurations have
not been completed. Glass has not been ordered.
CONICAL BAFFLE
All production baffles have been received at LHO. A conical baffle was
partially installed in the cryopump at y-midstation, by John W. and Betsy
W. The baffle was restricted by the cold shield inside the cryopump from
opening to the designed diameter, so the fastening tabs on the baffle were
inaccessible and will have to be modified at a future date. The conical
baffle in the x-midstation is expected to be installed on 11/15.
COS ALIGNMENT PROCEDURE
The alignment of the FMx, FMy, APS telescope, and RM mirror which was done
on 10/18 was discovered to be in error with several unexplained
discrepancies. The alignment errors were attributed to several positioning
errors involving the autocollimator, the BSC7 optical table, and the
alignment targets. The alignment was repeated on 11/4. The COS
autocolliimator height at the x-manifold was determined with an optical
level, and the projected beam angle was established by autocollimating from
the HR surface of the ITMx. The y and z position of the ITMx was measured
by means of a target placed on the LOS structure, and the BSC7 optical
table was moved in the y-direction to correct for a slight error. The
target in front of the RM was re-positioned both in the y and z axes. Then
the FMx was re-aligned to project the beam from the x-manifold, through the
ITMx, off the FMx, off the BS, to the target in front of the RM. The target
was removed to allow the beam to transmit through the RM, and the beam
position was measured in front of the MMT3 on HAM7. There was a total
angular error of approximately 200 microradians in the beam direction from
the RM to the MMT3. The APS telescope was realigned, and the previous
height discrepancy of approximately 15 mm was found to be eliminated. It
appears that the corrections which were made to the alignment procedure
eliminated and explained the discrepancies which were noted after the
initial alignment on 10/18.
4K IO BAFFLE
Glass for the 4K LHO and 4K LLO IO baffles will be ordered 11/11. Awaiting
delivery of the production parts for the frame assembly.
4K ELLIPTICAL BAFFLE
Most of the production parts have been received for the 4K LHO and 4K LLO
Elliptical baffles, the remainder are expected to be received on 11/15. The
glass has been fabricated and is in the process of being AR coated, with an
expected completion date of 11/22.
INSTALLATION PLAN
item completion install
Elliptical baffle 4KRM, HAM3 11/22 ?
Elliptical baffle 4KITMy, BSC8 11/22 ?
Beam dump FMYX, BSC8 done pending
Beam dump 4KITMHR3, BSC8 done pending
Beam dump 4KITMHR4, BSC8 done pending
Beam dump 2KRMHR3, BSC4 done pending
Beam dump 2KBSHR3P-2, BSC4 done pending
Beam dump 2KITMXAR1, BSC4 done partial
Beam dump 2KITMXAR4, BSC4 done partial
Beam dump 2KITMXAR4, BSC4 done partial
Beam dump 2KITMXAR4, BSC4 done partial
Beam dump 2KITMyAR1, BSC4 done partial
Beam dump 2KITMyAR4, BSC4 done partial
Elliptical baffle 2KITMx, BSC7 done pending
Elliptical baffle 4KITMx, BSC3 11/22 ?
Beam dump FMXX, BSC7 done pending
Beam dump FMXY, BSC7 done pending
PO Tel, 2KAPS, HAM10 done done
PO Tel, 2KBS, HAM10 done ?
PO Tel, 2KITMy, HAM10 done ?
PO Tel, 2KITMx, HAM9 done ?
PO Tel, 4KAPS, HAM4 done ?
PO Tel, 4KBS, HAM4 done ?
PO Tel, 4KITMy, HAM3 done ?
PO Tel, 4KITMx, HAM4 done ?
PO mirror, 2KITMy, BSC4 done done
PO mirror, 2KITMx, BSC4 done done
PO mirror, 2KBS, BSC7 done done
PO mirror, 4KITMy, BSC2 ? ?
PO mirror, 4KITMx, BSC2 ? ?
PO mirror, 4KBS-1, BSC1 ? ?
PO mirror, 4KBS-2, BSC1 ? ?
ETMy Tel done done
ETMx Tel done 11/15
Beam dump ETMy vac window done done
Beam dump ETMx vac window done 11/5
Arm Cavity Baffle, X-vertex 11/29 ?
Arm Cavity Baffle, Y-vertex 11/29 ?
Arm Cavity Baffle, X-end 11/29 ?
Arm Cavity Baffle, Y-end 11/29 ?
Conical baffle, X-vertex done ?
Conical baffle, Y-vertex done ?
Conical baffle, X-mid station done 11/15
Conical baffle, Y-mid station done done
Vacuum window-2KAPS, HAM10 done done
Vacuum window-2KITMy, HAM10 done done
Vacuum window-2KBS, HAM10 done done
Vacuum window-2KITMx, HAM9 done ?
Vacuum window-2KETMX, BSC6 done done
Vacuum window-2KETMY, BSC5 done 11/15
 

--------------------------
Isolation Group -- M. Fine
--------------------------
Seismic Design (Mike Fine)
--------------------------------------------------------------------------
1. Allied Shipment to LHO:
Allied is preparing a shipment to go out to Hanford this Friday. This
shipment contains 4 BSC downtubes, 8 BSC support tubes, 3 sets of
BSC leg elements, a reworked #3 leg element, and a batch of assorted
balance weights. The arrival is scheduled to be next Monday.
Suspension -- (Janeen Hazel/Mark Barton/Mike Fine)
-------------------------------------------------------------------
1. Report from Janeen:
-As there is no clear installation date for the
TMs at Livingston I have postponed the trip to
LLO to process the second ETM. Helena will be
traveling to LLO to support IO work the week of
Nov 29-Dec 3.
-The ciruit boards for mounting the SMD LED and
photodiode are due here on friday. I will
forward them to Jay to test. The spacers to
mount them in osem heads will not be here for a
few more weeks.
 

---------------------------------------------------------
Detector Systems Engineering -- D. Shoemaker/D Coyne
(WBS 1.2.1.1.9)
---------------------------------------------------------

Report delayed by email.

-----------------------------------------
Control and Data System -- R. Bork
(WBS 1.2.2)
-------------------------------------------

No report received.
 


WBS 1.4    Project Office


NO REPORT


WBS 1.4.3    Systems Engineering / Data Analysis and Computing



 

1.4.3 System Enginnering / Data Analysis

Simulation and Modeling

[Biplab Bhawal]

o Trying to fix a few differences between signals generated
  by primitive module calculations and summation-recycling-cavity
  calculations.

o Started modifying recycling_summation module to take care of
  time-varying input fields. This'll let us run faster with good
  accuracy in the presence of intensity-noise or frequency-noise.

[Giancarlo Cella]

* Cella is going to stay in CIT until Nov. 25th.
* Cella has written a C++ library MSE (Mechanics simulation engine),
   which uses NAG library. NAG Is a commercial software; and CIT
   has a site license.
* Cella has built a explicit case of a signle suspended mirror to be
   tested by comparing with the model of Malik.
* Cella is going to help us integrate MSE into e2e.
* Cella is going to implement the thermal noise in his framework.

[Ed Maros]

(EFM)   Worked on getting screen refreshing to work in Alfi 4

[Bruce Sears]

* (BS) Alfi 4 Software Development:
        - Completed the Alfi component tree display.
        - Implementation of Alfi box edit access via the tree is mostly
          complete as well now, but must wait on Ed's graphics work in
          order to be tested more completely.
        - Getting further up to speed on C++ via an excellent book called
          C++ for Java Programmers which much more efficiently exposes me
          to the parts of C++ which I don't already know/understand.

[Hiro Yamamoto]
* Installed e2e on the computer at TAMA following the MOU attachment
   for the simulatio effort. Gave several talks and demos about e2e to
   TAMA sicentists.
* Discussed with Mr.Tomaru and Prof.Ohashi about the FFT simulation of
   TAMA IFO including the measured phasemap.
* Discussed with Anthony about the LSC implementation in the LIGO model.
* Discussed with G.Cella about the development and future collaboration
   of the mechanics simulation.
   A single suspended mirror calculations will be used to validate the code
   outside of e2e, and then integrate into the standard e2e package. A strategy
   of linking or exlcuing Cella's mechanics library was discussed including
   E.Maros.

LIGO Data Analysis System

[Masha Barnes]

* (MB) 'Table' element support for lwAPI:
       - Added "units" attribute to the 'lstring' element in ilwd.
       - Added support for 'lstring' with units attribute in the lwAPI.

* (MB) Finished modifying lwAPI to use hash_maps with function pointers,
       tested on Solaris and Linux - works.

* (MB) Changed getLwTOC command in lwAPI to use different output format.

* (MB) Creating C++ classes documentation for lwAPI.
 

[ Phil Ehrens ]

* (PSE) Added command "dataSend" to the generic API which
        can be used to send frame and lightweight document files,
        LW document objects, ilwd text files and strings,
        and c++ object pointers (ilwd element and container,
        frame, and LWDocument types are all supported) through
        ObjectSpace data sockets.

* (PSE) Added command "ligolw::all2lwp" to the ligolw
        (lightweight API) to convert frame files, ilwd text
        files, LW document files, ilwd strings, and c++ object
        pointers to lightweight document objects.

* (PSE) Added sanity checks to the frame API which parse the
        most recent frame file and make a log entry describing
        global file attributes useful for debugging the frame API.

* (PSE) Modified appropriate files to fix errors in the
        documentation generation for the various API's.

* (PSE) Added doumentation to the frame API c++ code, parts of
        which were incomplete or absent.

* (PSE) Supported Mary Lei in the development of user commands
        which make use of the data sockets and the rudiments of
        the lightweight API.

[Grace Hu]

* (GH) Updated dynamically creating new group communicator - fixed most
         errors which show on screen.

* (GH) Created new programs for master processor distributing an array and
       letting slaves processors processing FFT transfer.

* (GH) Almost finishing writing commont on C++ source code.

* (GH) Still working on adding more parameters on "mpirun" command.

[Mary Lei]

* (ML)  Created tables at LSC database llo_1.

* (ML)  Updated element test scripts to use a host name
        when creating data sockets since at the sites
        the gateway (dataserver) has 2 port numbers and
        defaults to the external port.

* (ML)  Updated sock.tcl to use a local host name obtained from
        resource file when creating server and client
        data sockets. This is because gateway machines
        have dual network cards and the default IP
        address is the outside one.

* (ML)  While testing sending data between metadata and lw,
        got a core dump in metadataAPI shared object
        at the binaryinspiral query. Later
        retest with Ed's metadata so after he fixed the
        problem: not handling null data in result column.

* (ML)  Added a function to ligolwAPI tcl to output LW doc
        from ilwd object. Move handleDataSockCmd into
        ligolw.tcl to do data receives and execute command.

* (ML)  Ran element tests for data sockets at LSC and LHO.
        Got consistent results.

* (ML)  Updated all tcl scripts, pkgIndex.tcl and resource
        files to change lwAPI to ligolwAPI.

* (ML)  Tested multiple queries for getMetaData with returnformat
        set to LIGO_LW using metadataAPI, ligolwAPI and
        managerAPI. Threading works most of the time but
        there are cases where the thread gets timed out
        without connecting. Better synchronization is needed.

[Edward Maros]

(EFM)   Corrected metadataAPI to handle null data being returned
        in binary data sets.
(EFM)   Fixed configure.in in api/lwAPI/tcl and api/metadataAPI/tcl
(EFM)   Minor fixes in Makefile.am to support ligolwAPI naming
        convention.
(EFM)   Did test runs of building 0.0.5 system.

[Bruce Sears]

* (BS) Bug Reporter Research:
        - Downloaded and researched docs on the Bugzilla bug tracking
          software to see if it will be suitable for LDAS to use.  Working
          with Ed on installation issues.

[Peter Shawhan]
* (PSS) Finished revising LDAS database table design (for now),
        and completed document describing it.

LDAS hardware

[Edward Maros]

(EFM)   Fixed http autostarting from cfengine.
(EFM)   Have standardized the configuration of the http daemon
        between spica, ldas.ligo-wa.caltech.edu, and
        ldas.ligo-la.caltech.edu

[Stuart Anderson]

Moved the high-speed ATM link between LIGO and CACR from
a particular LIGO workstation to the now operational large LIGO ATM switch
and started discussions with CACR on how to best make use of the increased
network topologies consequently made available.
 

General Computing

MIT:
David S. is checking out various issues that they have. Looking into modem pool
setup and VPN.

Livingston:
Nothing to report. Probably busy with the conference.

Hanford:

Continued network security maintenance. Continued moving computers
around to upgrade some computers and move the older computers out to the
Mid and End stations. Continued trying to contact the Sun
representative to get maintenance contracts renewed.

Did the usual backups, helped with several printer and PC problems and
kept the GC accounting paper work up to date.

CIT:

Sam moved a new computers to Dave B. and Syd M. office.
Working on setting up scanner on another computer.
Burned a number of cds.
Trying to figure out how to backup up sun machines, will contact Ed M.
to try it on the LINUX version of the CD burner.

Suresh insatalled SBus+ and Graphics+ I/O board for Sun Enterprise 3500 in
pollux in order to attach additional devices.
Modified a shell script to detect intruder's left over files to detect smurf
attacks.
Installed Sun OS in number of hacked systems.
Working on to install ForeView software for ATM network management.
Set up some user and group accounts and assited some users.

Barbara worked on a number of WEB based projects.

Larry placed a number of orders for SUN equipment and application pkgs.
Installed IDEAS Master Series 7 and now working out some of the bugs.
Worked on a number of network issues. Now trying to iron out some of the
logistics with FORE in getting some equipment replaced.
Finally, got the maintenance contract issues with SUN taken care of and put in
the paper work.
Checked on a number of purchase that are late. So far the lack of certain
necessary pieces has been the main excuse.
Getting new quotes for peripheral equipment needed througout the GC area.
Fixed a number of PC issues and file issues for DCC.
Working on setups of new computers being used for some of the server
replacements.

[Bruce Sears]
* (BS) ILOG Maintenance:
        - Fixed problems with non-standard ascii characters which the XML
          parser was choking on.
 


WBS 1.4.4.1    Administrative Group


From: torres <torres@ligo.caltech.edu>

For I. Petrac distributed signed change order No. 2 for Hand Machining.  Formatted the MOU with Southeastern Louisiana University.  Accessed current LSC reports and printed out for review.
For I. Petrac/P. Lindquist formatted letter going to NSF regarding Data Analysis System-Hardware Procedures Plan.

Did a few P-Card purchases, chased a billing discrepancy, reconciled some orders.  For J. Camp distributed an article to the science group inside and outside of CIT.  Dedicated more time to help I. Baldon get through the mountain of travel documents.  Tried to capture details of a foreign trip for proper recording.

From: Irene Baldon <baldon@ligo.caltech.edu>

Worked on preparing the paper work for 10 new trips taken recently or upcoming
(10 Payment Requests and 5 Advance Requests).  There are approximately an
additional 8 new trips in various stages pending completion of travel
arrangements before the paper work can be completed.  Also worked on a number
of problem issues which required a good portion of my time.

Completed 45 Expense Reports, some of which were extensive, involving 2-3 or
more pages each.  Some of these reports were still not taped or completed by
the Traveler, and required additional time for completion.  Worked on a number
of problem issues associated with these which required a good portion of my
time.  There are 22 Expense Reports still to be done, including 1 that requires
extensive work to complete.  I'm holding 5 completed Expense Reports which
require a check from the Traveler before sending to Travel Audit to clear.

Rita Torres through Liz was able to complete 5 Expense Reports for me.  She has
an additional  3 Expense Reports in the process of completion.  Thanks Rita.

I hate to have to continue to say it, but I continue to push for both Advance
and Expense Checks already submitted.  "The System" continues to be extremely
slow in processing these.  I'm still waiting for 7 Advance Checks that I
ordered for my receipt starting Oct. 29th thru Nov. 3rd.  Again, I am still
waiting for T numbers.  The new forms still take approximately 3-4 times my
time to complete and there is no way changes or corrections can be made which
requires me to redo many trips and cancel out the original.  Again, this takes
time.
 

Performed normal recording and filing associated with Travel and
Reimbursement.
 

Made last minute changes for travelers going to the LIGO Inauguration
Celebration.  I continue to monitor all the trips planned and assist wherever
possible.
 

Travel for the PAC7 Meeting to be held at LIGO/MIT from Nov. 18th through Nov.
19th has been completed.  If there is anyone still not booked please do so
now.
 

Prepared the Travel/Vacation Itinerary for the Week of November 1, 1999.
 

Performed miscellaneous duties as requested by various members of  the LIGO
Project here at Caltech, as well as from members of the staffs of each of the
two (2) sites.   I continue to do MIT's travel to the sites for installation
activities and assist them wherever possible.
 


For additional information about this report, contact sanders@ligo.caltech.edu