Weekly Report for Week Ending September
14, 1999
Project Control Meeting Agenda Highlights
Hanford Observatory Livingston
Observatory Detector
Project Office System/Data
Analysis Administrative
Past Weekly Reports
The Project Control Meeting
Agenda for Monday September 20, 1999 will be:
(Meeting time: 10:30 am Pacific Time)
-
Announcements (5 minutes)
-
Review of Action Items (10 minutes)
-
Comments on Weekly Report (5 minutes)
-
Field Change Orders/Contingency Liens/Change Requests (10 minutes)
-
Review of ISSUES AND PROBLEMS by Subsystem/Activity (10 minutes each)
-
- Integration/Installation (Coyne)
Detector
Installation & Commissioning Bulletin Board
-
- Hanford Observatory (Raab)
-
- Livingston Observatory (Coles)
-
- Beam Tube Bakeout (Althouse)
-
- Data Analysis and Computing (Lazzarini)
-
- Project Controls / Operations (Lindquist)
-
- Lasers and Optics (Camp)
-
- Isolation (Fine)
-
- Interf. Sensing (Zucker)
-
- Control and Data (Bork)
-
- Advanced R&D (Sanders)
Special Items:
Special Announcements:
Weekly
Report Highlights
Vacuum Board will meet Friday 17 September to review H2O outgassing
data from SEI seats and to make a recommnedation on how to proceed.
LIGO Hanford Observatory (LHO) Operations
(J. Worden)
Bake Oven:
(K. Ryan)
LHO Vacuum Bake Oven A load #56, consisting of six large and six small
COS telescope silver coated parabolic mirrors, was released earlier
this week. Prior to starting this load, we tried a new adhesive product
(OMEGABOND 400) in an attempt to improve the adherence of the thermocouples
to the oven. During the course of this load, three of seven thermocouples
fell off!!! This event started a chain reaction of events which resulted
in a large temperature gradient across the oven's baseplate flange and
the corresponding mating belljar flange. The differing expansion
rates of these two mating flanges as the result of their differing temperatures
caused the hot baseplate to "expand into" (bind) the belljar flange which
galled (pressure welded) the two together. Upon separating these
two "welded" flanges, both flanges were damaged.
John Worden was able to file and polish the damaged areas, and we have
since confirmed that the flanges are still usable.
Load #57, consisting of two LOS structures + misc. fasteners, is currently
vacuum baking and should be released on Monday 9-20-99.
Computing:
(C. Patton)
Submitted purchase requests for more user PCs and a laptop to be used
as the System Administrator's troubleshooting/testing tool. Attended
the General Computing meeting. Albert was able to get connection
to the LHO modem pool from Caltech, still have not been able to reproduce
that from LHO. Gary Sanders has agreed to help test it when he is
here on 9/16. Part of the debugging problem has been that the only
computers at LHO with modems are Rick Savage's and Fred Raab's laptops
and Richard McCarthy's PC. Testing can only be done when one of these
computers is available for testing.
Monday night and again Wednesday night a hacker with an Italy ip address
broke into the subnet. The assault was halted early, it looks like
nothing was left on our system. Most of the rest of the week has
been spent cleaning up and trying to put in measures to prevent any future
break-ins.
If you have not changed your password on rainier, the LHO server, please
do so. As a result of the hacker and trying to get everyone to change
their passwords, we discovered a problem with Secure Shell 2.0. Apparently
ssh 2.0 is not compatible with the nispasswd command. We think it
may be the way ssh encrypts the password. We found that the old ssh
1.3 does work with the nispasswd.
LIGO Livingston Observatory (LLO)
Operations
Seismic installation:
BSC at south end-station: Cleaned and positioned clean-room over chamber.
Positioned, aligned, and leveled the support tube roller system. Removed
all but 3 dome bolts, removed the 4 D-nozzle conflat bolts (all but 2 bolts
ea.) Transported Genie Lift
from corner station to south end-station. Power washed and readied
two temporary scaffolding units. (Rich Riesen)
Optics: We have started assembling the first small optics suspension
(tower and optic). This will be used for testing purposes. We made six
magnet dumbbell combinations following the new fixture and procedure (cure
glue at 100 C for 1 hour). We cleaned one steering mirror following the
new cleaning procedure (put the optic in liquinox solution in an inner
beaker and put the inner beaker in an outer beaker filled with DI water).
We brought the solution temperature to 70 deg C and held for 15 min. Both
surfaces passed the water test after the second time using this procedure.
Jonathan Kern has devised an apparatus to measure optic thickness using
a height gauge and a microscope. It works well. Using this apparatus, we
measured the thickness of the steering mirror. The thicker side (on which
a wire standoff will be put) has been measured to be 24.76 mm. Jordan Camp
measured the field strength of the 50 magnets shipped from UF (and baked
at CIT). They are grouped to Group O through Group T. The scattering of
the strength within groups is less than 1.5%. The new groups are stored
at the same place as the first groups (Group A through Group N). (Sany
Yoshida)
Jonathan completed the alignment telescope fixture for Sany, and began
work on a modified fixture to assist in wire standoff alignment. Awaiting
2 ball lead screws, as well as powdercoating of the modified straddle fixture.
Corrected an oversized hole problem in an SOS for Dave Tanner. Corrected
numerous problems with several of the surplus vehicles in our carpool (another
engine blew up this week, trying to get 2 running for bakeout support).
(Jonathan Kern)
Beam tube bakeout: We have started to ramp down the bake of the
X2 module. Expected time of this ramp is 3 days and we should be at ambient
temp. by monday. At this time Rai feels we have a good bake. The Y-arm
end station has been vented and is at atmospheric pressure and purged for
detector installation activities.
Two of our QDP-80 pumps have failed in the last week and will have to
be returned to Edwards for repair. Unfortunately, both are out of warranty
and the cost will be about $6500 for each repair. (Allen Sibley)
PSL: The PSL enclosure was cleaned. Some open spots on the cement
floor should be sealed to reduce the production of dust. With the HEPA
filters turned on in the laser table enclosure, the particle count reads
zero.The pre mode cleaner is in place and aligned. The mode matching looks
good and is being checked. The PZT of the pre mode cleaner will then be
characterized. After this, the pre mode cleaner can be locked with a temporary
circuit and the total light output of the PSL can be measured. (Joe Kovalik)
Bake Oven: We have completed baking all BSC parts and are currently
baking RGA-tree components. (Tom Evans)
Control and data acquisition system: The SOS rack (1X6) is ready
for test. Rolf and Jay will be here on Tuesday to run through it.
The cables for the SOS satellite modules are run and awaiting termination.
Graphic displays for data acquisition are being updated so that they recognize
the path for Livingston. Permanent CDS power is now tied into the end station
racks. Power for the paging system is installed. (Rus Wooley)
Servo Test Stand--Serial cable made to communicate with Baja. Sucessfully
comunicated with Baja using serial port. Baja successfully loaded epics
and startup file. It can now be logged on from the net. Wrote and successfully
tested a "c" program on the Baja.
Suspension Test Stand--Talked with Jay Heefner and got operations manual
for Stand. He recommended that I check that the serial ports on the 162
were contected correctly. They were not. Joe and Rusyl swapped them to
the correct positions. Sani and I went thru with a scope and signal generator
and checked the circuits. Moving the OSEM from LL thru to Side we checked
both sides of the stand and found everything is now working.
Weather Station--Problem with Web data uncovered; James Finney says
Web data is now reasonable back to Sept 1st ; various fine tuning continues.
(Anthony Rizzi)
Facilities: The Louisiana Love Bug scourge continuous to plague
operations in terms of maintaining cleanliness. Pest control experts maintain
that only a cold snap will bring relief, as no effective spray is available
to check the problem. The access road is still not available for traffic.
The contractor has started to place gravel on the shoulder and estimates
another week for completion. (Gerry Stapfer)
WBS 1.2, 1.3
Detector Group
DETECTOR GROUP -- Whitcomb/Shoemaker
(WBS 1.2, 1.3)
Interferometer Sensing and Control -- M Zucker
(WBS 1.2.1.1.6, 1.2.1.1.7)
Initial Alignment (Matt Smith)
The ETM transmision monitor quad diode box was reworked this week and
reinstalled. Everything now fits together and will be aligned this week
an shipped to Hanford. Started to work on modifying the SOS assembly
postioning fixture to allow for rotation about the mirror. Waiting for
an Autocad drawing for the SOS assembly d960001.dwg.
IO Testing (Peter Fritschel)
(work by Nergis, Gaby, Haisheng, Stan, Peter):
-
MC1 diagonalization completed with some success; in particular the angular
motion of MC1 was significantly reduced after the diagonalization.
-
Calculated value of the local damping gain which minimizes the optic's
rms motion. Still to be implemented on the MC mirrors.
-
Took 15 minute data run with stably locked MC using Shourov's data acquisition
system. Channels measured were three axes of a seismometer, the MC length
control signal (to MC3), the MC laser frequency feed back signal (to VCO),
and the MC transmitted light. Data and some first-look results in ~gonzalez/HanfordSept99/
on LHO machines.
-
Electro-optic shutter got working. Locked MC with higher power. Observed
oscillation at 1 Hz when power got to 1 W. Found that MMT3 was not damped
and was swinging at 1 Hz. Replaced satellite box (blown PD bias supply).
-
PZT steering mirrors "sing" at 5 and 10 kHz. Problem found to be with PZT
driver, which is now being worked by Jay and Richard.
-
Internal Q's of MC mirrors drumhead mode were measured and found to be
good, all were above 3e5.
Lasers and Optics -- J. Camp
(1.2.1.1.2, 1.2.1.1.3, 1.2.1.1.4,1.2.1.1.5)
Pre-stabilized Laser (PSL) - Peter King
-
Two 21.5 MHz frequency reference cards are in the final stages of
manufacture. The frequency reference cards provide the local oscillator
and phase shifter signals for the frequency stabilization servo electronics.
-
Two 80 MHz VCO are in the final stages of manufacture.
-
Laser SN #110 was delivered by Lightwave Electronics.
Input Optics - Dave Reitze
LHO 2k (Haisheng Rong)
-
Haisheng and Stan measured the Q's of the 28.2 kHz resonance for the three
MC mirrors in situ with the following results:
MC1 7.8 x 10^5
MC2 3.7 x 10^5
MC3 1.35 x 10^6
These are better than the SOS Final Design spec.
-
The aluminum brackets for the in-vacuum beam dumps are being manufactured
now. The black glass and its antireflection coating has been ordered, with
delivery expected in 2-3 weeks. We will coordinate the clean/bake of these
with Janeen Romie at CIT.
LLO 4k (Sany Yoshida)
We have started assembling the first small optics suspension (tower
and optic). This will be used for testing purposes. We made six magnet
dumbbell combinations following the new fixture and procedure. We cleaned
one steering mirror following the new cleaning procedure. Both surfaces
passed the water test after second time of this procedure. Jordan Camp
measured the field strength of the 50 magnets shipped from UF (and baked
at CIT). They are grouped to Group O through Group T. The scattering of
the strength within groups is less than 1.5%. The new groups are stored
at the same place as the first groups (Group A through Group N).
Mechanical Design (Dan Dickrell)
Our shop has finished a few remaining parts for the IOO installation
at Livingston: Holders for the 2 PZT mounts on the PSL/IOO table and vented
posts for the DLC fixed in-vacuum mirror mounts. These will be shipped
to LLO shortly; the posts and fork clamps will need to be put in the queue
for clean/bake.
Core Optics Procurement and Metrology - Gari Billingsley
No report received.
Core Optics Coating and Cleaning - Helena Armandula
Measured transmission from beamsplitters BS03; 04; 02; and 01. Transmission
is within specs.; BS03 and 04 measured 50.7% at 45 degrees (+/- 0.5 degree)
"p" polarization; BS01 and 02 measured 50.3%. The offset on the detector
is .006mV.
These measurements are quite sensitive to angle of incidence, they
change about 1.6% per degree.
Core Optics Support - Mike Smith
PO TELESCOPE
Ken M. and Mike S. successfully aligned the APS PO telescope with the
dielectric coated mirrors. The previous alignment failure was caused by
lack of visibility of the return autocollimator beam. A 990nm diode laser
(courtesy of Daniel Sigg) provided a significantly higher reflectance than
the previous 940 nm beam, and returned a high visibility image which was
relatively easy to align. Production fabrication of the PO telescopes is
in process.
ETM TELESCOPE.
Alignment of the ETM telescope will take place at the next COS trip
to Hanford. Fabrication of the ETM telescopes is proceeding.
STEERING MIRRORS
50 sets are awaiting assembly at CIT.
VACUUM WINDOW
Jonathan K. is in the process of shipping some COS vacuum windows to
LHO.
ARM CAVITY BAFFLE
Baffle assembly fabrication is in process. Bids are being evaluated
for support frame assembly. Paul K. is working on the top
assembly drawings for LHO and LLO.
CONICAL BAFFLE
First article has been reworked and is being cleaned and air-baked.
Production fabrication of the conical baffles is in process.
AUTOCOLLIMATOR
The optical elements of the COS autocollimator are in the process of
being anti-reflection coated to eliminate excessive internal glare. Ken
M. and Mike S. are reworking the fixturing for mounting the CCD cameras,
autococollimators, and laser illumination sources.
INSTALLATION PLAN
item
completion install
Elliptical baffle 2KRM, HAM9 done done
Elliptical baffle 2KITMy, BSC8 done done
Beam dump FMYY, BSC8 done done
Beam dump FMYX, BSC8 done pending
Beam dump 4KITMHR3, BSC8 done pending
Beam dump 4KITMHR4, BSC8 done pending
Beam dump RMHR3, BSC4 done pending
Beam dump BSHR3P-2, BSC4 done pending
Beam dump ITMXAR1, BSC4 done partial
Beam dump ITMXAR4, BSC4 done partial
Beam dump ITMXAR4, BSC4 done partial
Beam dump ITMXAR4, BSC4 done partial
Beam dump ITMyAR1, BSC4 done partial
Beam dump ITMyAR4, BSC4 done partial
Elliptical baffle 2KITMx, BSC7 done pending
Beam dump FMXX, BSC7 done pending
Beam dump FMXY, BSC7 done pending
PO Tel, APS, HAM10 done pending
PO Tel, BS, HAM10 10/8 ?
PO Tel, ITMy, HAM10 10/8 ?
PO Tel, ITMx, HAM9 10/8 ?
ETMy Tel done 8/23-9/3
ETMx Tel 9/24 ?
Beam dump ETMy vac window done 8/23 - 9/3
Beam dump ETMy vac window ? ?
Arm Cavity Baffle, vertex 10/15 ?
Arm Cavity Baffle, end 10/15 ?
Conical baffle, vertex 9/27 ?
Conical baffle, mid station 9/27 ?
Vacuum windows ?
Isolation Group -- M. Fine
Seismic Design (Mike Fine)
1. Scissors Tables:
Hytec has received the final 16 scissors tables from Hand Precision.
They have begun the assembly and will have them completed by the September
24th ship date. The four scissors tables used on the prototype BSC will
be delivered to LHO as spare units. They are missing one hole pattern and
will need to be reworked. Hand Precision is going to rework the scissors
table so they can be delivered on the October 8th shipment.
2. Prototype Hardware:
The Hytec prototype BSC is nearly disassembled. Most of the hardware
requires some rework to bring it to the latest revision. The air bearing
mounting plates and actuator spacer blocks are currently being reworked.
The X-Fine stage and scissors tables require some rework and will be delivered
to Hand Precision by September 17th. The X-Fine stage will not be completely
revised to the current revision due to the number of major changes that
were made to the stage. Instead, the X-Fine stage will be updated to include
all of the interface changes required to mate up with the scissors tables
and air bearing mounting plates. The functionality of the X-Fine stage
will not differ from the latest production hardware.
3. Electronics Rack:
The LHO Rack (Rack #4) initial debug was completed without identifying
any issues regarding the electrical connections, noise or function. The
final checkout (software integration with mechanical components) has been
delayed as a result of manpower issues regarding other programmatic requirements
within Hytec. The final checkout will be done and the rack will be shipped
on October 8th. It will be delivered to LHO on October 12th.
Suspension -- (Janeen Hazel/Mark Barton/Mike Fine)
1. Report from Janeen:
-
Vendors have delayed delivering the final parts for the little beam dumps.
The stands won't be here till tomorrow. The delay in the vent at LHO makes
this slip acceptable. We will try to get those parts to the sites by the
end of next week after cleaning and baking.
-
Working with IO folks on SOS suspension issues. Attended the meeting
on SOS diagonalization on Tuesday.
-
Doing more prep work for LLO suspensions. Ordered more equipment and parts.
-
Submitted a design to CES for fabrication of a bracket that will work with
the optics holder to hold the optics in place while they are baking.
Detector Systems Engineering -- D. Shoemaker/D Coyne
(WBS 1.2.1.1.9)
Global Diagnostics System (Daniel Sigg, John Zweizig)
I improved the operation of the Data monitor environment under root
by adding the interrupt handling. I tested this by porting the Chart macro
(produces a free-running chart of band-limited rms for a set of channels
and frequency bands defined by a configuration file) to the data monitor
environment.
I also prepared for trip next week to LHO by installing the new (now
understood and working well) versions of gcc on the DMT machine and reorganising
all the dmt software directories to be transferred to CVS. I have started
a perl script to manage the running of monitors and the infrastructure
processes.
Time spent debugging diagnostics test code and solve synchronization
problems between different CPUs.
Physics Environmental Monitor(Matt Smith, David Shoemaker)
Ed Daw will be traveling to Livingston the week of September 20 I will
be traveling to Livingston for the week of September 27th for PEM installation.
I sat with Ed Daw to set up a plan for PEM installtion tasks for his trip
next week. He will work on installing seismometer and tiltmeter breakout
boxes, and dust monitors. I will work on installing, interface plates,
accelerometers and cables, RGAs, computers, and PEM stay clear zones. Mark
Lubinski is going to try to take pictures of some of the PEM sensor locations
as installed at Hanford for reference.
A pdf file has now been created for the pem sensor locations at Livingston.
they can be found at:
~matt/PEM/livingston/pemLivingston_sh1.pdf
~matt/PEM/livingston/pemLivingston_sh2.pdf
~matt/PEM/livingston/pemLivingston_sh3.pdf
Control and Data System -- R. Bork
(WBS 1.2.2)
Near Term Installation
Sept. 20-24: Jay and Rolf at Livingston for IO suspension system checkout.
Sept. 25-Oct. 1: Rolf at Hanford for continued ASC tests.
Sept. 27-Oct. 1: Dale at Hanford for one arm test installation.
Oct. 4 - Oct. 15: Rich at Livingston for continued PSL commissioning.
General
-
Working on a proposal for a configuration control scheme for CDS installations
at the sites. A draft document should be out in the next few days.
-
Received quotes for most of remaining Commercial Off The Shelf (COTS) items
necessary to complete both sites. Orders will be placed over the next few
days.
ASC (Jay)
Status of modules needed for 2K one arm test:
Module Needed Needed
Name one arm
Full ASC Status
----------- ------- -------
--------------
WFS Demod 2 5 2 Tested and ready, 4 stuffed, need test
WFS PD 2 5 4 Boards stuffed and in test
WFS Whitening 2 5 6 boards tested and ready
WFS DC White 1 3 2 boards tested and ready
WFS Dewhite 2 4 2 boards tested and ready
BE Demod 2 2 Same board as WFS Demod, boards stuffed
BE PD 2 2 Same as WFS PD, 2 stuffed and in test
BE White 2 2 2 stuffed, need test
QPD 1 2 4 stuffed, 2 Tested
QPD whitening 1 2 3 boards tested and ready
-
Completed the testing and calibration of 3 WFS PDs. 2 Bull's eye PDs are
being tested and should be complete by 9/17.
-
Construction of the X and Y arm ASC controls wiring harness is complete.
The harnesses will be shipped to LHO next week.
LSC (Jay)
-
Two LSC One Arm Servo Amplifiers are complete and ready for test. Tests
should be complete by 9/24.
-
Power supplies and crates have been mounted in rack 2X1.
-
System drawings for the One arm LSC controls are 95% complete. The wiring
harness for rack 2X1 has been started and should be complete by 9/24.
Suspension (Jay)
-
Chassis for the remaining SOS and LOS controllers have been ordered and
should be delivered by 10/20.
-
Two LOS controllers for LLO COS are being tested.
-
System tests for LLO IO Suspension controls will be done by 9/24.
-
We have run out of Satellite modules and are in the process of fabricating
the remining modules. Fabrication has hit a snag because the vendor who
engraves the boxes for us is holding them until they are paid for their
last invoice. (I guess they are not impressed by Caltech's new finance
system). At last word, Caltech was going to cut a check and Paul Russell
was going to deliver it to the vendor and pick up the boxes.
2K One-Arm Test CDS: (DAO)
Status:
LSC Photodiodes: Four diodes are currently being assembled, tested
and tuned.
LSC Photodiode Interface: In PCB layout this week.
LSC I & Q Demodulator: One is complete and tested. Will try to
get a second completed in the next few weeks.
LSC Servo Amp: Two are built and ready to be tested.
LSC Notch Filter: Due back from PCB fab. Will assemble and test next
week.
EPICS Screens: We have started constructing screens and data base records.
GPS Timing System: (DAO)
Twenty blank PCBs of the final version of the Clock Driver are in hand.
Two are being assembled this week. Will test them next week. I am
sending two more Clock Fanouts to Hanford and One to Livingston.
The front panels are in for the ISC clock fanouts. Will assemble, test
and ship 4 to Hanford next week.
PSL (Rich)
1. In the process of gathering information about the LSC/ASC frequency
distribution system with the short term goal of writing a small requirements
document.
2. Designed a frequency reference card for 27 MHz and harmonics. Sent
board out for manufacture.
3. Ordered parts for various circuit boards.
40M Lab (Rolf)
-
A stuck bit was identified by John Zweizig on data coming from the ICS
ADC module. The ADC module was replaced. Problem turned out to be a bent
pin on the edge connector.
-
Added three more 16KHz channels to the acquisition system.
Data Acquisition System
-
Hongyu completed the operator's manual for version 2 of the Dataviewer
software. This will be distributed to the sites.
-
Alex adding a new class to the Frame C++ library to improve the write performance
of the system.
-
Looking into alternatives for storing trend data to improve the data retrieval
rates.
-
PMC reflected memory modules due on loan from VMIC tomorrow. Will evaluate
next week to verify they will meet performance needs (>12MByte/sec) for
Hanford site.
WBS 1.4 Project
Office
Visitor's Program, Conferences
(Meshkov)
From: Syd Meshkov <syd@ligo.caltech.edu>
No report this week.
Reports, Proposals (Lindquist)
The LIGO II Project Plan was submitted to the
NSF on September 10.
The Quarterly Report will be submitted to the
NSF at the end of September. Please submit contributions by Friday,
September 17, 1999. Early submittals will be appreciated. A
copy of the previous Quarterly Report is available at Quarterly
Report.
We will submit an Operations Work Plan for FY
2000 in October. I have asked task managers to submit budgets to
Florence Kaufman by the end of this month and text by the middle of October.
Again, early contributions will be appreciated.
Change Control/Contingency (Lindquist)
We held a LIGO Change Control Board
Tuesday, September 14, 1999. The following change requests were approved:
| CR-990001 |
WBS 1.3 |
Return Unused Budget for Construction Related
R&D to Contingency |
P. Lindquist |
| CR-990017 |
WBS 1.4.1 |
Administrative Account Closeout |
P. Lindquist |
| CR-990019 |
WBS 1.2.1 |
Detector Systems--Optic Tables Balance Weights |
D. Coyne |
| CR-990020 |
WBS 1.2.1 |
Seismic Isolation System--Material and Subcontract Closeout |
S. Whitcomb |
| CR-990021 |
WBS 1.2.4 |
Support Equipment--Additional Cleanrooms and Laminar Flow Benches |
S. Whitcomb |
| CR-990022 |
WBS 1.2 |
Detector Staffing |
S. Whitcomb |
| CR-990023 |
WBS 1.3 |
Beam Tube Enclosure--Hanford--Closeout |
F. Asiri |
Press for the latest Contingency
Needs Projection
LIGO Weekly Site Telecon (Jasnow)
A site telecon was held on Thursday, September 16,
1999. The list of current actions assigned may be found at ACTION
LIST.
Everyone is reminded to provide a redlined copy of their current LIGO
business card to Ed Jasnow so that we may plug it into the print shop for
new ones.
PROPERTY MANAGEMENT
(Chargois)
From: Ed Chargois <chargois_e@ligo.caltech.edu>
Assisted the Detector Group (M. Fine) with packaging
and shipping of thirty-two (32) Springs to Astropack, (attn: Kevin
Strange), delivery confirmation received. Acct # P96916.
Assisted the Optic Engineer with packaging and
shipping of optical equipment to LIGO Livingston Observatory, (attn: S.Yoshida),
delivery confirmation received. Acct # P47041.
Assisted the System Administrator with packaging
and shipping of computer related equipment to the LIGO Hanford
Observatory (attn: C. Patton), delivery confirmation received. Acct#
P97266.
Received disposition instructions from the National
Science Foundation (NSF) Property Administrator (Mr.K Rorer) granting permission
to dispose of the LIGO property located at Hytec for $27,803.37.
Funds will be returned to the LIGO Account.
Received confirmation from Bruel & Kjaer concerning
the calibration and repair of a Verburator for the R&D Lab. (DeSalvo)
Estimated cost of $1779.00 vs new $4,878.00.
Received confirmation from Crown International
concerning the repair of a Power Supply for the R&D Lab. (DeSalvo)
Estimated cost including shipping $310.00.
DOCUMENT CONTROL
CENTER (Turner)
From: the DCC <dcc@ligo.caltech.edu>
PLEASE NOTE: We are going to close the DCC
from Monday through Wednesday next week (September 20-22) for normal business
to inventory and organize all the documents not yet entered. LIGO
Document numbers are available through the WEB page. If there are
any urgent matters please bring them to the attention of Linda or Phil.
Web pages for the
DCC give simple how-to's for document numbering, easy access to the latest
on-line documents, and search capabilities for the DCC database.Take
a look. . .
ACTIVITY HIGHLIGHTS
-
For the past two week's
processing statistics, check the DCC
web page.
-
Continued working with
Paul Kabot on identifying numerous duplicate numbers representing different
hardware parts. Several options were discussed with Paul and Mike
Smith in cross-referencing any number changes. Further discussion
is planned before setting up a procedure.
-
Battled with printer
and software problems to empty an overloaded OUT folder of electronic document
submittals. Over 80 documents were successfully processed and placed
on-line. However, there still remains about 30 documents. With
luck, these too should be available on-line in the next couple of days.
-
Met with Dennis Coyne
and several others from Hanford regarding the use and processing of Process
Travelers.
Press here to access
the DOCUMENT CONTROL CENTER
WEB PAGE.
COST SCHEDULE CONTROL
SYSTEMS (Duncan, Moore, Akutagawa, Kaufman)
From: Sarita Moore<moore_s@ligo.caltech.edu>
Press here for ACCOUNTS
PAYABLE HISTORY DATA.
From: Kris Duncan <kris@ligo.caltech.edu>
-
Completed and distributed the July 1999 CSSR.
The construction project is currently 95.9% complete.
-
Advanced the calendars in COBRA and posted
the level of effort earned value for the R&D and Project Office accounts.
-
Continued to work with WEBSTER to download August
1999 actual costs to date. The commitment data continues to be
incorrect.
-
Began a replan of the four LDAS accounts in COBRA
based on Albert's input.
-
Received (2) Excel files that consisted of staffing
plans located at the various sites (CIT, LHO, LLO and MIT) and put the
information into a MS Project format.
-
Continuing to review "Open Plan" schedule files and
update them for task managers review for August 1999 status.
From: Florence Kaufman <fkaufman@ligo.caltech.edu>
Spent a lot of time working on providing information
regarding problems I had encountered with Oracle to various individuals
working on correcting them. Good news is that corrections are being
made. However, reports for August 99 for both Construction and Operations
accounts should be viewed with caution since most of the corrections were
not made until September. Problems to be aware of include:
-
Overstatement of encumbrances due to certain contract
balances being entered twice. This problem has been corrected in
September.
-
P-Card transactions for July and August are not reflected
on the Oracle reports for August. This problem has also been corrected
in September.
-
Travel encumbrances overstated. This problem
appears to be on-going at this point.
-
Overstatement of overhead charges due to misclassifications
of items from Equipment to Materials and Supplies. Acquisitions and
Payables Department has been provided with a list and are in the process
of making corrections.
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
Downloading detailed cost and encumbrance data from WEBSTER has proven
difficult since the system has not been responsive for most of the week.
Since this is the first time since the conversion from IFIS it is VERY
important that everyone takes the time to really look these figures over.
Only the Task Managers can tell if these expenditures/encumbrances are
against the correct account and we need to get all corrections started
as quickly as possible as it may take a LONG time to get the errors corrected.
Cindy will be preparing a report for distribution and review as soon as
the process of downloading all of the data can be completed. We will
need people's cooperation reviewing the data.
SUBCONTRACTS MANAGEMENT
(Petrac, Jasnow)
From: irena@ligo.caltech.edu (Irena Petrac)
No report this week.
From: Ed Jasnow <jasnow@acrux.ligo.caltech.edu>
No report this week.
TECHNICAL CONFIGURATION MANAGEMENT
(Althouse)
From: wea@acrux (William Althouse)
No report. See Bake out.
1.4.2.1
Quality Assurance (Vincent)
From: robert vincent <robert.w.vincent@jpl.nasa.gov>
No report this week.
WBS 1.4.3 Systems
Engineering / Data Analysis and Computing (Lazzarini)
Vacuum Board will meet Friday 17 September to review H2O outgassing
data from SEI seats and to make a recommnedation on how to proceed.
Lazzarini analyzed IMTEC's vertical control survey data for Livingston
BT/VE interface markers for the Detector initial alignment survey team.
The technical report T980044 was updated (first try http://docuserv.ligo.caltech.edu/~coyne/docs/T980044.pdf,
or if that link is broken it will be at http://www.ligo.caltech.edu/docs/T/T980044-08.pdf)
Modeling and Simulation (E2E)
Biplab Bhalwa
-
Worked on the summation cavity validation.
-
Worked on implementing the cavity response to the phase changes correctly.
-
Discussed with Rick and Hiro about the future development of PSL modeling.
Matt Evans
-
Worked on formulating and implementing the new scheme of the time domain
modal model.
Ed Maros
-
alfi3.7 released. New feature is a support of hierarchical folder structure
and a crashing bug is fixed.
-
Conrad's codes have been combined, applied patches to make it compilable.
This makes e2e software SGI STL dependent.
Hiro Yamamoto
-
Looking into the improvement of the loop behavior in adlib.
-
Worked on validating the Conrads code
-
Worked on the cavity response of cavity to phase changes.
-
Discussed with Matt about the model implementation
LIGO Data Analysis System
[Masha Barnes]
-
(MB) Added getLwTOC() function to lwAPI to display content of specified
LIGO_LW element in the document.
-
(MB) putLwData() for lwAPI: ability to store raw data in external files
for specified elements:
-
(MB) Working on getLwData function for lwAPI to handle externally stored
data in the elements.
-
(MB) Had a meeting with Phil on generating frame ilwd files of different
size for time testing.
[Kent Blackburn]
-
(JKB) Wrote Quarterly Report section for LDAS software group.
-
(JKB) Held two Group Meetings to maintain the level of awareness
as to where our current transition software problems fall and how to resolve
them. Learned that the C++ object sockets are currently not working and
this is getting high priority. I have been working closely with Nathan
to track this down and fix it. Spent a good deal of time working with rest
of group on each individuals particular difficulties, training in some
sense on the use of Unix development/debugging tools.
The state of the Makefile are probably of second highest priority.
At this point we have pretty much fixed all the GNU GCC 2.9.5.1 issues.
-
(JKB) Helped Masha track down a problem using standalone executables that
link in the TCL API libraries but don't run in TCL. Described a way to
use DDD with the tclsh shell. (
-
JKB) Worked with the Univ. of Florida group to get them up to speed using
the elastic cylinder resonance frequency and effective mass code.
-
(JKB) Downloaded new C and FORTRAN compilers from Compaq for the Alpha
processor but due to some auto mount issues on sadan, have not been able
to install and test them yet.
[ Phil Ehrens ]
-
(PSE) Wrote an index file for the developer docs for LDAS to provide a
single entry point for all Tcl and C++ code in all the API's.
-
(PSE) Wrote documentation for the getData user command and an index page
for the user command docs.
-
(PSE) Began to investigate resource requirement issues of the frame and
lw API's. Each of these API's might require a large pool of physical
memory to be able to run smoothly for extended periods of time.
[Xiao Hu]
-
(XH) updated the the database web pages.
-
(XH) worked on other database documentations.
-
(XH) fixed some bugs related to database.
[Barbara Kratochwill]
-
(BK) Cloned the CDS Channel Configuration application for Livingston. Created
a second database and loaded the basic channels substituting an "L" for
the "H" in the channel names. Copied all the forms and pointed them
at the new database.
[Bruce Sears]
-
(BS) Ilog system:
-
User database maintenance at LLO.
-
(BS) VRVS Video-Conferencing System:
-
Reported to Albert on comparisons of the VRVS system with other video-conferencing
systems such as CU-SeeMe, MeetingPoint, and NetMeeting. The system
which best suits LIGO needs apears to be VRVS, though the other systems
also have their points.
-
(BS) LDAS Code Documentation:
-
Researching the Perceps tool for C++ documentation for the LDAS group.
Looking into how it has been used in the group already in order to make
guidelines for auto-documentation of new C++ code written by members of
the group who have not yet been using Perceps.
[Nathan Yospe]
-
(NY) Continued development of prototype data conditioning classes, including
the wrapper for the power spectrum functionality, which now conforms to
the specification laid out in the LIGO Data Analysis System - Numerical
Algorithms Library Specification and Style Guide document.
-
(NY) Found two minor problems in the compilation of the ospace libraries
that might account for segmentation faults occuring in calls to the genericAPI.
Recompiled ospace for Sun and Linux platforms, recompiled genericAPI for
Sun, working on Linux.
-
(NY) Identified a possible casting problem in the implementation of the
general lib, in the destructor of the class LdasBinary, and will look into
workarounds once everything is compiling and testable.
-
(NY) Began modifying tcl scripts for testing purposes in my linux and sun
environments
SBA
Integrated an 8x4GB disk shelf from the decomissioned Intel Paragon
at CACR to run software RAID on the LDAS database server at Caltech.
Larry Wallace
Placed orders for the following LDAS equipment to be shipped to Livingston:
FORE 2810
Rack
Cart
NTI switch box
UPS unit
Shelving material for the rack
We have received the quotes for the SUN units and the PC's. Those orders
should be started today. Cable orders should be out this week also. The
NTI switch box has arrived at Livingston. Tom E. is checking items out
the facilitate the running of the cables at the Observatory.
General Computing
MIT:
Working on getting new PC's. Also acquiring the Exceed pkg. from Hummingbird.
Livingston:
Larry worked through some FTP issues with Alan S.. The transfer was
completed but Alan will need to get some of the logistics worked out with
Tom so the transfers can go a little easier.
Hanford:
(Christine P. Submitted purchase requests for more user PCs and a laptop
to be used as the System Administrator's troubleshooting/testing tool.
Attended the General Computing meeting. Albert was able to get connection
to the LHO modem pool from Caltech, still have not been able to reproduce
that from LHO. Larry has also been able to get on the modem pool from Caltech.
Gary Sanders has agreed to help test it when he is here on 9/16. Part of
the debugging problem has been that the only computers at LHO with modems
are Rick Savage's and Fred Raab's laptops and Richard McCarthy's PC.
Testing can only be done when one of these computers is available for testing.
Monday night and again Wednesday night a hacker with an Italian ip address
broke into the subnet. The assault was halted early, it looks like
nothing was left on our system. Most of the rest of the week has
been spent cleaning up and trying to put in measures to prevent any future
break-ins.
If you have not changed your password on rainier, the LHO server, please
do so. As a result of the hacker and trying to get everyone to change
their passwords, we discovered a problem with Secure Shell 2.0. Apparently
ssh 2.0 is not compatible with the nispasswd command. We think it
may be the way ssh encrypts the password. We found that the old ssh
1.3 does work with the nispasswd.
CIT:
Barbara K. set up web pages for the Celebration. Helped with queries
on the Celebration database. Made several minor changes to the tables
and form. Made miscellaneous web site changes -- added links to LIGO
II site and to LIGO II documents on LSC page, removed links to Old Document
Index.
Samantha B. is working on updating code written by Sean and is having
some difficulty because of the lack of documentation of the code. Set up
a new computer for Cindy and Akiteru Takamori. Helped Liz with a few computer
issues. Discovered how to print a blank page in print job originating from
PC's, now working on getting the banners to work correctly. Worked on Dale's
PC in Wilson house. Worked on Linda's PC which is still having problems.
Working on more Y2K issues. Trying to wrap up testing on the PC applications.
Suresh installed various application softwares such as Framemaker5.5,
Applix, Mathematica, Matlab etc with renewed licenses in new file server
(replacement for sirius). We still need to install few more softwares.
Tests of these installed packages with a client workstation taking place
side by side. Test results are satisfactory.
Start working on the final stages of taking the FORE 200 switch off-line
but we have put that on hold until the 40M has finished their data run.
Resolved a number of network and program issues on the 40M GC and data
computers. Most of the problems were resolved with resetting some configuration
defaults. However, one machine had been hacked into and the system needed
a little more work.
Resolved a number of printing issues. Just as a note when setting up
a PC be sure to use a drive with the PS (postscript) option. Many of the
printers will take advantage of the extra features this option provides.
When using Norton Utilities. Run the program and fix any issues that
it may find. Then remove the program from the system. The monitoring tools
the program setup has been causing problems on a number of computers.
Working a number of procurement issues and maintenance contract renewals.
Going over the financial items. Working on getting things cleared up on
the new system. Continuing support during the transition to the new Oracle
accounting system. The number of issues brought to our group has diminished
but we still get a couple of items each day.
Started working on and testing the Sharewhiteboard and other programs
from SUN. So far things are looking pretty good. After testing is finished
with all of the sites we will start checking on how it will work with the
video conferencing project Albert is working on.
Worked a number of issues to help get documents out for the DCC group.
Spent some time trying to discover why Gary S. is having problems with
the modem pool and why we are not able to duplicate the problem. Gary has
also spent some time working this issue.
Added a few more users.
WBS 1.4.4.1 Administrative
Group
Dorothy Lloyd
Back from vacation. Inundated with
requisitions, receivers, POs, and invoices.
Irene Baldon
Not with us this week.
Rita Torres
Between Labor Day and my vacation,
did the following. For I. Petrac did letter to P. Saulsen regarding Attachment
Z to MOU with Syracuse University. Did change order No. 9 to Brookfield.
For P. Lindquist distributed material
for CCB scheduled for 9/14/99. On 9/14 helped make viewgraphs and set up
the teleconference for the CCB. FedExed to NSF and to distribution the
LIGO Laboratory Charter.
Along with other Admins, attended
a 1-1/2 Hr. meeting with D. Werntz to discuss Oracle issues. Over several
days input requisitions to the system in D. Lloyd's absence. Also input
data to Dorothy's database for internal safekeeping. Input information
for my first P-Card purchase, must reconcile items by 9/22. For one day,
sorted/distributed mail in C. Mak's absence. For A. Weisman/T. Prince sent
out message to ASIS members then reported responses.
For S. Whitcomb distributed a science
article to groups at LLO, LHO, and CIT. Provided copies to JPL of eye exam
reports for former LIGOites now working at the lab. Updated trips schedule
for Detector Group. Got a chance to straighten out files.
Elizabeth K. Wood
Mailed off the LIGO II White Paper.
Worked on the LIGOfest.
Disbursed checks and airline tickets
in Irene's absence.
Communicated many times with Sharon
Borbon about visas.
Asked the electrical people not to
turn off the power at the 40M for the big run this weekend. They said okay.
Reconciled passport charges.
Have successfully avoided nervous
breakdown.
For additional information about this report, contact sanders@ligo.caltech.edu