Weekly Report for Week Ending July 13, 1999



 Project Control Meeting Agenda  Highlights   Hanford Observatory     Livingston Observatory     Detector   Project Office    System/Data Analysis    Administrative   Past Weekly Reports

The Project Control Meeting Agenda for Monday  July 19, 1999 will be:

CANCELLED


Special Announcements:


Weekly Report Highlights

LHO mode cleaner work continues
 


LIGO Hanford Observatory (LHO) Operations



Facilities:
-----------
(Otto Matherny)

Water Well Problems:  We just received a $12K bill for the well rework
that occurred in May.
New staging Building:  The contractor is 99% complete with the building.
Only punch list items remain. The contractor submitted the shop drawings
for the bridge to the mezzanine.

Compressors:  Apollo started legal action against C&K Compressor, the
company who guaranteed the as-installed compressors to be oil free.
 

Seismic Systems:
----------------------
(C. Gray & H. Radkins)

BSC6(Y-MID): In the last two weeks, the Roller System has been positioned,
after having the Bellows Platforms modified to make room for it.  The top
Dome was removed and the upper Work Platforms installed.  Next the 'D'
Nozzle conflat covers were removed and the Support Tubes were installed.
The south chamber door was removed and the Support Table/Downtube/Optics
Table Assembly was then bolted to the Support Tubes.  With the Support
Tubes now centered, the Bellows' were installed and the custom conflats
torqued.  Next came the V-Blocks connecting the internal load to the
external structure.  This allows the Jib Cranes to be removed and the
16.5" seal to be torqued.

We were unable to get one seal to work and a chamfer was found on the
gasket preventing the gasket from holding in place during conflat sealing.
This set us back one day as we replaced the Jib Crane, disconnected and
removed the V-Blocks, removed the Bellows, replaced the gaskets, and then
reversed the disassembly.  The new gasket snapped easily in place and on
we traveled.

Staging of parts and fixturing for Phase 2 was completed 7-14, and stack
building began in earnest 7-14 pm.

BSC5(X-MID):  The Adapter Plates were aligned allowing the scissors tables
to be installed (near future) followed by the Fine Translation stage (yet
to be delivered.)

BSC4 : The three leaking gaskets on BSC4 have been replaced and it is now
pumping down for leak tests (See Corey Gray or Dennis Coyne)
 

Computing:
----------
(C. Patton)

I just returned from vacation, so this week has been spent catching-up
on everything that went on while I was away.  More Matlab and toolbox
licenses have been purchased and installed.  Completed installing the
new color laser printer on the Unix systems.  Backed-up the user
accounts, moved some user accounts around to keep disks from getting too
full, got caught-up on accounting paperwork, and helped several PC users
with several different problems.
 

Electrical & Electronics Systems:
---------------------------------
(R. McCarthy)

Installation of the UPS for the Control room is progressing.  All conduit
and cable have been installed and final terminations will take place
Friday.  Hopefully we will have a Control room computer and ATM switch on
the UPS early next week.

Conducted a walk through with US West (phone company) for an estimate on
running phone and data lines to the new staging building.  We should have a
quote tomorrow.

Worked on isolating a source of 52k Hz noise on the small optics
suspensions.  The are appear to be related to the coils.  Early next week I
will shut down the power to the controllers to ensure we are not
introducing the noise into the ckts.
 

Physics Environmental Monitoring
--------------------------------
(M. Lubinski)

I will be the person to look after PEM equipment here in consultation with
Daniel Sigg and Matt Smith. I am trying to get up to speed on all the PEM
equipment, location, operation, testing, calibration, and some data
analysis. We are currently looking at the data from seismometer in the
LVEA.
 


LIGO Livingston Observatory (LLO) Operations



 

Detector Installation: Installed the Hytec BSC Control Rack. The system appears to be functioning properly after we worked out some software bugs. We exercised the systemextensively with U,V,W Translations, rolls, and yaws. Hytec is going to makeup some different length cables (of the lengths they brought, some were to long and some were to short), and send them our way next week, thus keeping our cable trays neat. We are continuing the cleaning and staging of equip.and parts for the buildup of BSC 1 which will commence next Monday 7-19-99. (Rich Riesen)

Optics:   Cleaning (36) ISC viewports from MDC.  The glass to metal seal is filthy, and is taking 3 or 4 cycles through the ultrasonic cleaner to stop the shedding. Also received the reworked viewports from Varian this morning and will begin cleaning and assembling these for Mike Smith. Optics for COS viewports received from Helena last week. Ordered additional small LN2 dewars for the SEI installation and labs.  We're going through a lot of gas and since the big dewars for the cryopumps are yet filled; we have to import from Baton Rouge.  We had to rob the lab source Tuesday so Hytech could
float air bearings. The machine shop is getting a lot of use, modifying tooling for Rich and yesterday I had to machine two rollers for GNB. Placed an order with a local contractor to provide a roof for the hazardous material storage bunker.  With the summer heat, we've had lab solvent drums rupture so an elevated roof will permit shaded storage, out of the rain as well. (Jonathan Kern)

Electrical installation: The small optic suspension test stand control rack has been wired and is ready for preliminary testing.  Two 20 amp circuits for the Hytec control rack are installed.  Permanent CDS rack power tie-ins have been made to racks 1X4 thru 1X9 and 1X22. (Rus Wooley)

EE lab: Redhat Linux 6.0 is received and is in the process of installation onto the lab PC. Ordered and received few soldering accessories.
CDS: Stored new arrival equipment from Caltech and Updated hardware inventory on the web. (Juilien Svoboda)

Bake Oven: We have installed a N2 leak for calibration purposes. We are continuing to bake BSC bellows. (Tom Evans)

GC Computers: We are beginning the installation of Solaris 7, and will eventually upgrade all the Sun GC machines to this version. (Tom Evans)

Other: Attended oracle training in preparation for the dark period.  Worked with Larry to get PC requirements and have upgraded in preparation to run Oracle.  Have reset up petty cash software to be able to process checks with new charge codes and reimbursement requirements; and began paying bills on site again as a result.   Updated passport software on everyone's computer (except Mark's because he is out this week).  Obtained and distributed new Caltech ID cards. (Bonnie Wascom)

Mark Coles obtained a "Morgan Coil" - harmonic coil used for precision magnetic field measurements of accelerator magnets, as a loan from FNAL. Jonathan and Mark measured the AC multipole magnetic moments inside BSC3 over the 4th of July weekend by wrapping the entire assembly in clean room wrapping and suspending it from a PVC pipe between viewports in opposite doors. We made measurements of the dipole, quad, sextupole, octopole, decapole, 14p, and 18p. We also made measurements in air at mid height in the LVEA by suspending the coil from the crane and we made background measurements by replacing the coil with a load resistor in the amplifier chain. This data is now being analyzed to see what impact it might have on the LSC and ASC dynamic range requirements. While the coil is constructed with very tight dimensional tolerances so that it can accurately measure field derivatives, the areaXnumber of turns is small, so it's important that we dont fool ourselves.
 


WBS 1.2, 1.3    Detector Group



 

----------------------------------------------------
DETECTOR GROUP -- Whitcomb/Shoemaker

(WBS 1.2, 1.3)
----------------------------------------------------

IAS Initial Alignment (K.Mason, M. MacInnis)

The componants for ISCT10 have been assembled and will be boxed for
shipment to Hanford.  Assembly of ISCT9 componants has begun.

Recalculated optic positions and orientations for FMy and RM. Dennis
Coyne and I have finalized theodolite positions and orientations. Both
optics will be repositioned next week in Hanford using the PLX periscope
to view around installed optics.

IO Mode Cleaner Commissioning (N. Mavalvala)

Since the successes of the previous week when we locked the mode cleaner
using P-polarized input light, we characterized the control loops, which
were
as expected. We are in the process of modifying the servo characteristics
to engage the bypass path (which was too conditionally stable to use
without more careful characterisation) and to use the length path.

We also measured the length of the cavity using a resonant RF sideband
and found it to be 15.256 m (it needs to be 15.240 m, so we'll have to
move
MC2 during a vent).

Most recently we have locked the mode cleaner using S-polarized light,
which is the design polarization. Some new mysteries have emerged:

(i) We can detect no appreciable S-polarized light in transmission
through SM1. We measure the polarization ratio S/P of the input beam to be
around 1000, yet we see only P light transmitted through SM1. We placed a
polarizer cube in the transmitted light beam line to remove P light and
were
then able to pick up a miniscule amount of S-light. Even with 100 mW of
input power we would expect ~150 uW of light to arrive on IOT7. (Is it
possible that SM1 is a high reflector for S, rather than the speced 0.5%
transmitter?)

(ii) The visibility we measure is only 30% (we expect ~100%). Since we
have no measureable transmitted light and the spot we see using a camera
pointed at MC2 is too speckled to tell, it's possible we are locked in the
wrong mode, but not very likely, since we are well aligned (checked using
P pol). We are
about to set up a ringdown measurement to measure the finesse of the
cavity.

(iii) We tried operating at higher power to get some transmitted light
through SM1, but that drives MC3 into large pitching motion, completely
correlated with light build up in the cavity.

Next will attempt to
* lock the cavity with modified bypass and length control paths
* realign the input beam path to center spot on MC1,3

-------------------------------------------
Lasers and Optics -- J. Camp
(1.2.1.1.2, 1.2.1.1.3, 1.2.1.1.4,1.2.1.1.5)
--------------------------------------------

Lasers and Optics -- Jordan Camp
(WBS 1.2.1.1.2, 1.2.1.1.3, 1.2.1.1.4, 1.2.1.1.5)
================================================

Prestabilized Laser -- Peter King
--------------------------------------------

- In an exercise aimed at exploring if the beam quality of the laser could
be improved, laser SN #107 was re-aligned.  Upon return from Lightwave
Electronics, the performance data reported an M-squared values of 1.16 and
1.17 in the horizontal and vertical directions respectively.

    After re-alignment at Caltech, M-squared was approximately 1.10 in
both directions with a small, ~100 mW, drop in the output power of the
laser.  The phase-correcting EOM was then installed between the NPRO master
oscillator and the power amplifier.  After a minor re-adjustment to the
alignment of the laser, the M-squared parameter was re-measured.  It was
found that the EOM did not affect the M-squared parameter.  A result that
is consistent with previous experience with the laser.
 

Input/Output Optics -- Dave Reitze, UF
-----------------------------------------

We worked on the design change on the PSL/IOO table associated with
the RFAM measurement and the use of Brewster-angle polarizers. The new
layout uses a pair of Brewster polarizers before and after the three
EOM chain, and three steering mirrors after the EOM having an angle of
incidence ~22 deg for two of them and a near-normal incidence for the other
mirror. This mirror has about 1% transmision to give a
polarization-insensitive signal for RFAM measurements. We will order these
optics soon.

We have also worked on new beam alignment fixtures for MCMs

Dan Dickrell and Sany Yoshida will travel to LHO next week.
 

Core Optics Procurement and Metrology -- GariLynn Billingsley
-------------------------------------------------------------

We have the temperature stabilized in Lauritsen to the point where we can
take data on SPETM04.  Unfortunately this thermally stable time is not
coincident with a vibrationally stable time.  Therefore we are accepting
data with a vibrational signature, namely a bullseye pattern with 3 sigma
P-V amplitude of ~1.2 nm.  The optic is to be handed off for scanner
measurements on the 16th and is to ship to Hanford on the 23rd.

CSIRO performed measurements on 2 of the 4 Beamsplitters which needed
re-work last September.  The first type of measurement was of the surface
figure (looking for change in curvature pre to post coating) using the same
technique as is used for final acceptance of the polished optics.  The
second type was measurement of coating thickness, using elipsometry.

Bob Oreb of CSIRO is presenting the BS coating measurement result at a LIGO
session which is being held July 21 at the Denver SPIE meeting.  The LIGO
number for this paper is: C990866-00-D

The following is an e-mail excerpt comparing results of our post-coating
surface figure measurement of BS01 to the predicted surface figure of BS01.
The prediction is based on pre-coating measurements plus the coating
induced changes of other BSs measured at CSIRO.

>From Bob Oreb:
_________________
Thank you very much for the feedback on our BS01 coatings paper.
I would like to make a couple of comments regarding your and our results:

1. You estimate the ROC of Side 1 to be between -66 km and -188 km with a
preferred  value of -140 km. From our measurements on the uncoated and re
polished BS01, side 1 had a sag of ~ -10 nm. If we assume that the
coatings deposited on  the re polished BS01 behaved or influenced the
substrate in the same way as our assessment of the earlier coatings then we
would expect the curvature of side 1 to change by ~ -45nm from its uncoated
state. This would then make the final coated surface 1 curvature have a sag
of ~ -10 - 45 = - 55 nm or ~-91km. This value lies comfortably within your
estimated spread of values quoted above.

2. Your measurements indicate that side 2 appears to be 50 nm more concave
as a result of the coatings. Our measurements indicate that side 2 became
45 nm more concave (and side 1 45 nm more convex). These results are very
close.

3. "HR coating is known to be compressive" - this is consistent with our
measurements which show side 1 becoming more convex and side 2 more concave
as a result of the HR coating. Our results also indicate that the AR
coating has the opposite deformation effect than the HR coating and so it
may have tensile stress. It would be useful to get an explanation for this
apparent difference.
 
 

Core Optics Coatings -- Helena Armandula
--------------------------------------------------

This week I attended several talks at the Amaldi Conference, worked on the
up-date of the Vacuum Document, reviewed the LOS installations procedure to
be able to help install the BS next week at Hanford and cleaned some
optical stages.
 

Core Optics Support -- Michael Smith
------------------------------------

PO TELESCOPE
The 2K APS PO telescope is being aligned at CIT, but alignment will not be
completed until the week of 7/26 when Mike S. returns from LHO. After
alignment, it will be disassembled and shipped to LHO by 7/30. A production
contract for 12 PO telescopes is expected to be let the week of 7/26.
Delivery is expected 6 weeks ARO.

ETM TELESCOPE
The bids have been received, and a purchase order for 6 ETM telescopes is
expected to be let by 7/16.

PO MIRRORS
The electropolished tilt screws and one tilt plate had to be re-baked at
CIT. These parts are expected to be hand carried to LHO on 7/18. The
alignment apertures for the PO mirrors have been fabricated and tested with
the 640nm battery-operated diode laser pointer. They will be air baked and
shipped to LHO on 7/16. Ken M. and Mike S. are adjusting the placement of
the final design PO telescopes on HAM9 and HAM10 optical tables to insure
that there will be no interference of the PO beam optical train hardware on
the table.

STEERING MIRRORS
10 sets of 2 inch steering mirrors are being baked at CIT and are expected
to be hand carried to LHO on 7/18. Steve B. will assemble the mirror mounts
at LHO the week of 7/19. 7 sets are to be used by IOO, and 3 sets are for COS.

CAVITY BEAM DUMP
The batch of beam dump parts which failed the bake load at LHO has been
sent to Pasadena for electropolishing of the SS parts and caustic etch of
the aluminum parts. They should be cleaned and shipped back to LHO by 7/23.

VACUUM WINDOW
Helena A. sent the vacuum windows to Jonathan K. at LLO.

COS IR ALIGNMENT BEAM
The IR laser diode has not been received.

ARM CAVITY BAFFLE
Paul K. is detailing the arm cavity baffles.

CONICAL BAFFLE
Craig C. has completed the conical baffle design. The same design will used
both at the vertex station and at the mid station. A purchase order for 6
baffles is expected to be let by 7/16.

INSTALLATION PLAN
item                             completion          install

Mode cleaner baffle                 done                done
IO baffle                           done                done
Elliptical baffle 2KRM, HAM9         done               done
Elliptical baffle 2KITMy, BSC8     done                 pending
Beam dump BSAR3, BSC8              done                 done
Beam dump FMYX, BSC8              done                  pending
Beam dump FMYY, BSC8               done                 done
Beam dump 4KITMHR3, BSC8          done                  pending
Beam dump 4KITMHR4, BSC8           done                 pending
PO mirror 2KITMx, BSC4               done               7/19
PO mirror 2KITMy, BSC4               done               7/19
Beam dump RMHR3, BSC4            done                    pending
Beam dump BSHR3P-2, BSC4         done                    pending
Beam dump ITMXAR1, BSC4          done                    pending
Beam dump ITMXAR4, BSC4          done                    pending
Beam dump ITMXAR4, BSC4          done                    pending
Beam dump ITMXAR4, BSC4          done                    pending
Beam dump ITMyAR1, BSC4          done                    pending
Beam dump ITMyAR4, BSC4          done                    pending
Elliptical baffle 2KITMx, BSC7    done                    7/29
Beam dump FMXX, BSC7              done                    7/29
Beam dump FMXY, BSC7              done                    7/29
PO mirror BS, BSC7                done                    7/19
PO Tel, APS, HAM10                done                    8/3
ETMy Tel                          done                    8/25
Arm Cavity Baffle, vertex          9/27                     ?
Arm Cavity Baffle, end             10/27                    ?
Conical baffle, vertex              8/30                    ?
Conical baffle, mid station         8/30                     ?
Vacuum windows                       ?

--------------------------
Isolation Group -- M. Fine
--------------------------

Nothing significant to report this week.

---------------------------------------------------------
Detector Systems Engineering -- D. Shoemaker/D Coyne
(WBS 1.2.1.1.9)
---------------------------------------------------------

Physics Environmental Monitor(Matt Smith, David Shoemaker & Alex Marin)
-----------------------------------------------------------------------

No report received.

-----------------------------------------
Control and Data System -- R. Bork
(WBS 1.2.2)
-------------------------------------------

Data Acquisition
=============
- Performing testing at Hanford to try and locate source of ADC rollover
problem (reported by B. Allen) and erroneous timestamps (which occur
when GDS querried).
- In process of replacing VIRGO C Frame library with LDAS C++ library on
the DAQS Framebuilder.
- Continued work on making changes/improvements requested for Dataviewer
software.

ASC
======
- Signal conditioning modules completed and being shipped to Hanford.
- Front end system shipped to Hanford and being testing this and next
week.

Timing
=======
- New master timing modules are now operational; testing continues at
Hanford.
 


WBS 1.4    Project Office



 

1.4.1.2 Project Controls (Lindquist)


PROPERTY MANAGEMENT (Chargois)

From: Ed Chargois <chargois_e@ligo.caltech.edu>


DOCUMENT CONTROL CENTER (Turner)

From: the DCC <dcc@ligo.caltech.edu>

New web pages for the DCC gives simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database.Take a look. . .

Recent Activities

Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.


COST SCHEDULE CONTROL SYSTEMS (Duncan, Moore, Akutagawa, Kaufman)

From: Sarita Moore<moore_s@ligo.caltech.edu>

Press here for ACCOUNTS PAYABLE HISTORY DATA.

From: Kris Duncan <kris@ligo.caltech.edu>

From: Florence Kaufman <fkaufman@ligo.caltech.edu> From: Cindy Akutagawa <cindy@ligo.caltech.edu>
SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: irena@ligo.caltech.edu (Irena Petrac)

From: Ed Jasnow <jasnow@acrux.ligo.caltech.edu>

TECHNICAL CONFIGURATION MANAGEMENT (Althouse)

From: wea@acrux (William Althouse)

Nothing new this week.


1.4.2.1 Quality Assurance (Tyler)

From: "William H. Tyler" <tyler_w@ligo.caltech.edu>

No report this week.


1.4.2.2 Safety (Zydowicz)

From: Mike Zydowicz <zydowicz_m@ligo.caltech.edu>

No report this week.
 


WBS 1.4.3    Systems Engineering / Data Analysis and Computing


Systems Engineering

No reports received

Modeling

[ Biplab Bhawal ]
o From now onwards, a zero setting for "max_mode_order" will
  mean only TEM00 mode (single-mode case) and "-1" setting will
  mean the plane-wave case. Important changes in names
  (*single_mode* to *plane_wave*, *multi_mode* to *gaussian_beam* etc)
  related to this and in algebra have been made in the code. Document
  9900004 updated.

o Fitted (approximately) the intensity noise curves of Laser with
  poles and zeros using Matlab. Will try more to get a more satisfactory
  plot. This's for generating the corresponding time_series.

o some minor changes made and a bug in triangular summation cavity
  (detected by Michelle, the SURF student, in her run) have been fixed.

[ Ed Maros ]
o Added support for absolute and relative paths in the Parser.

o Adopted Autoconf and Automake to build the E2E system.

o Corrected error with SaveAs.

[ Conrad Taylor ]
o In Adlib, there are claased which were developed before STL and have equivalent classes in STL.
   Worked to replace those classes by STL routines. The code crashed after the modification and
   spent time for the debugging.

o investigated the use of a smart pointer class to
    resolve the memory leak problems.  Also, I have
    performed minimal testing regards to the STL.

o optimized some the implemented overloaded assignment
    operators by taking into account the case where the
    invoking object may be assigned to itself.

o provided set of test cases to Brian Eng in regards to
    matrix performance testing.

[ Hiro Yamamoto ]

o PSL FSS module is unstable when run using large time step. Looked into the details of the
   time devolution of the control signal to trace the origine.

o Converted the Malik's single suspended mass model into a e2e primitive.

o Discussed with Matt and Biplab implementing a revised Field class.

[ SURF students ]

o Sam[surf student] is working to compare e2e ligo model with the calculation done last year at LHO using Ray's code.

o Michelle[surf student] is working to understand the characteristics of the mode cleaner.

[ Brian Eng, Summer work student ]

o Looking into various matrix class to be adopted in e2e.

o Did bench mark test to test the dependence on the matrix size.

o Right now, he is forcusing on MTL.

Data Analysis


[Kent Blackburn]
* (KB) Worked out a schedule of tasks and tests of the alpha release
       of the LDAS software for Hanford installation at the end of the
       month.
* (KB) Met with Masha to work out character protocal problem in FTP
       C code needed by the XML parser.

* (KB) Met with Ed and Dave to sort out the install directory tree
       for LDAS releases and development versions, mirroring and
       makefile issues.

* (KB) Met with Albert and Sam Finn to modify the software style guideline
       documentation for the LLAL.

* (KB) Met with Stuart and StorageTek to discuss LDAS archive needs.

[Mary Lei]

* (ML)  Updated getMetaData to conform the specifications
        set up during status meeting and email.

* (ML)  Changed metadataAPI to output ilwd (lstrings only) correctly
        via the genericAPI and not via tcl puts.

* (ML)  Attended database to discuss the new metadata commands
        putMetaData (insert/update data) and descMetaData (get
        database schema info).

* (ML)  Developing the tcl ilwd translator to create ilwd object
        for metadataAPI. Documented ilwd format in ilwd tcl file.

* (ML)  Cleaned up metadata tcl code; remove excess logging and add catch
        for all possible errors.

* (ML)  Unit tested metadata with sql queries to be used for demo.

* (ML)  Integrated metadata with ldas manager and exercised the interface
        with userAPI commands in a tcl script.

* (ML)  Supported Ed's needs to test metadata so with metadata tcl. Resolved
        some problems with environment setup of metadataAPI.

* (ML)  Conducted the getMetaData demo to show 2 forms of the getMetaData
        command.

[Masha Barnes]
* (MB) Met with Kent to discuss DOM and SAX parser interfaces.

* (MB) Fixed some bugs in XML parser (memory leaks).

* (MB) Reviewed updated LIGO_LW Format document.

* (MB) Studied IBM's XML parser code to add other than 'file://' URL support.

* (MB) Had a meeting with Dave, Kent, and Albert on LightweightAPI.

* (MB) Integrated http support into XML parser (to expand external DTD and
       external entities).

* (MB) Wrote an application to implement ftp's 'get file' and 'put file'
       functions.

* (MB) Integrating ftp support into XML parser (to expand external DTD and
       external entities).

* (MB) Had a meeting with Dave on LightweightAPI.

[David Farnham]

* (DWF) Continued working with PERCEPS to set up an auto-documentation
system for my libraries/APIs.  I have written filters which produce
documentation for parameters, return values, exceptions and to-do
lists.  I have also written an input filter which scans !ppp: fields in
comments to pre-process the file before running PERCEPS on it.

* (DWF) Continued working with Phil on the FrameAPI and Masha on the
Light-weight data API.

[Bruce Sears]
* (BS) Ilog system:
       - A list of tasks completed this week:
           * Remove annoying "Initialize Today's Log?" form.                Done.
           * Remove almost as annoying auto "Log Initialized" entry.        Done.
           * Enable easily placed hyperlinks in entries.                    1/2 done.
       - Enabled simple pre-formatted tables to keep their format when
         placed in an entry.                                                Spec done and
                                                                            distributed.
       - Slight modification of Ilog XML, and the change was propogated
         throughout all existing ilog files (both at hanford and at
         livingston.)  This was in order to enable a few of the new log
         viewing changes.
       - Entry form was modified slightly to give more space for viewing
         and formatting entries.
       - Defined an ilog entry url reference specification.  this enables
         people to put references to a particular entry in e-mail or a web
         page (including another ilog entry).
       - Created an ilog-users mailing list
       - Mailed detailed instructions about using new ilog features to
         the ilog users.

* (BS) LDAS User API:
       - Following and commenting on the ongoing development of the User API
         base command set.

* (BS) LIGO Majordomo system:
       - Final testing of weekly report lists.  They should be ready to use.

* (BS) Ilog system:
       - Created a system for easily determining the URL of an ILOG entry.
       - Created a system for easily embedding an ILOG entry's URL into another
         ILOG entry as a reference.
       - Work on setting up linked lists of ILOG entries for cases of entry
         obsolesence and entry updating.

[Edward F. Maros]
* (EFM) Added support for blobs under metadataAPI.

* (EFM) Added function to retrieve the Column Name of a Select statement.

* (EFM) Met with Mary to discuss ilwd binding issues at the TCL layer.

(EFM)   Modified cfengine scripts to add users to ldas systems at Hanford.
(EFM)   Added several of Phil's entries into the Software.txt file.
(EFM)   Met with Kent and Dave to discuss LDAS software installation.

[Xiao Hu]
* XHU worked on metadataAPI and ilwd performance test

* XHU worked on building database tables on metaserver

* XHU worked on testing db2 on metaserver

[Phil Ehrens]

* (PSE) Worked with David Farnham to complete necessary
programming tasks required to present and demonstrate
the user command "getFrameData".

* (PSE) Demonstrated user command "getFrameData" to the LDAS
programming group. (David Farnham assisted, demo was
witnessed by Ed Maros, Mary Lei, Masha Barnes, Xhao Hu,
Barbara Kratochwill, Kent Blackburn, and Albert Lazzarini.

* (PSE) Assisted Mary Lei in preparing the demonstration of the
user command "getMetaData".

* (PSE) Continued to debug the LDAS system.  The demo's pointed
to a leakage of filehandles within the low-level api's,
and I am tracing these leaks.

* (PSE) Preparing to install the alpha release of the LDAS system,
including the manager, frame, and metadata API's, at the
Hanford, WA observatory.

[Stuart Anderson]
        Installed and started 2 week test of 200GB network attached
hardware RAID disk cache from Network Appliance. This installation
utilized the last of the 4 LIGO fibre pairs running to the 6th floor
of Millikan, and also involves upgrading Linux to support NFSv3.

        Meet with StorageTek to discuss their current and future offerings
for mass storage as a possible solution for the on-site and main CIT
LIGO data archives.

        Started XML database of software installation rules.

General Computing

[Barbara Kratochiwill]

- - Reviewed the plan for web services with Gary and received an ok to proceed.

- - Resolved problems converting several long LSC reports to PDF.  Access had
problems paginating the memo fields in the report.  Then the pagination
didn't hold when the report was transferred to Word  (the "Publish with
Word" feature isn't quite what it seems).  Cleaned up one report that had
unprintable characters sprinkled throughout. Helped connect Irena to the
server with the LSC reports database.

- - Continued to help with Amaldi items -- applications, abstract
registrations, web site changes, submission of papers, etc.

[Christine Patton]
Subject: LHO weekly report

Investigated problems with the elm and pine mail tools on rainier and
apex.  Did the usual weekly backups, reconciled my LHO GC budget with
financial reports, and added/modified a couple of user accounts.  Helped
a user with a mail tool problem.  Worked with FORE Systems to get a
quote for the LHO ATM equipment maintenance contract.  Rebooted the
server after it crashed, apparently from a print job.  Ordered more
licenses for the Workshop compilers for the CDS server.


WBS 1.4.4.1    Administrative Group


Rita Torres

Took vacation on 7/12. Attempted several times (also sought help) to gain access to base applications on the Oracle system. Twice loaded a different version of Netscape; I still cannot access base apps. The frustration continues.

For I. Petrac did letter to S. Kawamura Re: MOU with TAMA. Obtained number for, formatted and did edits to, two MOUs. Did letter to NSF Re: Advance Notification Regarding Joint Programs with Foreign Entities; FedExed the letter with attachments. Cleaned up a list of delegates for the LSC program.

For E. Jasnow did letter Re: EJ-350, Landscape & Erosion Control; faxed to all and FedExed 1. Did contract #1000084 with MMR Constructors, Inc. for Electrical Contractor Service for the BT Bakeout at LLO. Also did #5559393 (temporary #) with Richard Price Contracting Co., Inc. for Landscape and Erosion Control at LLO; FedExed for NSF review and approval. Assisted at bid opening for IFB EJ-313 for Entrance Signs at LLO & LHO.

For M. Zydowicz did edits to the form Safety Inspection Checklist – OSB areas, and form Safety Inspection Hazardous for Technical areas – 13 pages. For Detector Group updated site trips.

Irene Baldon

Worked on preparing the paper work for 15 new trips taken recently (15 Purchase Requisitions and 3 Advance Requests). There are 10 additional new trips in various stages pending completion of travel arrangements.

Started working on arrangements for our LIGO/SURF Students' visit to LIGO/Hanford. There will be 12 students, plus Ken Libbrecht, traveling this summer. They will be departing on August 12th and returning on August 13th. A number of the students have requested a layover on the return in Seattle for the weekend of August 14th and 15.

Completed 27 Expense Reports, some of which were extensive, involving 2 or more pages each. Many of these reports were still not taped or completed by the Traveler, and required additional time for completion. Also worked on a number of problem issues which required a good portion of my time. Received, but not yet completed my audit, 25 Expense Reports. These should be completed in the next couple of days, barring unexpected delays.

Prepared Travel/Vacation Itinerary for the Week of July 12th, 1999.

Performed miscellaneous duties as requested by various members of the LIGO Project here at Caltech, as well as from members of the staffs of each of the two (2) sites.

Dorothy Lloyd

Work on reconciling status reports. Processed invoices for payment, and tracked and followed up on various invoice problems. Signed off on numerous PO receivers.

Elizabeth K. Wood

Did a little detective work and found out what phone company really installed the modem pool. Pacific Bell installs the line, MCI is our long-distance carrier. Joann in the PMA office has put in the order for two more modem lines.

Put visitors into offices and got lots and lots of keys. Note: Please remind your visitors to give the keys back to me BEFORE they leave.

Had a chat with Mark Coles about the preparations for the Fin-de-Construction Party in Louisiana.

Made arrangements for the Oversight Committee Telecon July 28.

Discovered if I put the new improved PTA numbers on the old PAN form, employee wages are charged to the wrong account.

Found which voicemail boxes are no longer in use.  The phone office will turn them off.
 
 


For additional information about this report, contact sanders@ligo.caltech.edu