Weekly Report for Week Ending May 18, 1999



 Project Control Meeting Agenda   Highlights   Hanford Observatory     Livingston Observatory     Detector    Project Office    System/Data Analysis    Administrative    Past Weekly Reports

The Project Control Meeting Agenda for Monday  May 24, 1999 will be:
 (Meeting time: 10:30 am Pacific Time)

  1. Announcements (5 minutes)
  2. Review of Action Items (10 minutes)
  3. Comments on Weekly Report (5 minutes)
  4. Field Change Orders/Contingency Liens/Change Requests (10 minutes)
  5. Review of ISSUES AND PROBLEMS by Subsystem/Activity (10 minutes each)
Special Items:  PAC meeting reprise


Special Announcements:   The LHO beam tube bakeout is done!!!    Congratulations to all who made this another successful effort in the construction of LIGO!


Weekly Report Highlights
 
 Magnet-optic bonding restarted

DAQ and GDS system integration tests at Hanford were successful.
 


LIGO Hanford Observatory (LHO) Operations



 
General Items:
--------------
(F. Raab)

PAC 6 meeting May 20-21.
 

Facilities:
-----------
O. Matherny

Water System modification:  The contract is complete. We are waiting for the State health department to approve the system. No change from last week.

New staging Building:  The contractor is 60% complete with the building. Interior insulation, wall panels, electrical and plumbing work are on going.

Compressors:  No change, the contractors are pointing fingers at each other. Will take a little more time to sort it out.

Water Supply:  Our well pump quit working. A new one is on order. Fortunately the 8000 gallon tank is installed, we filled it up by water truck. We are able to keep
the place operational until the pump is repaired.
 

Bake Oven:
----------
(K. Ryan)

LHO Vacuum Bake Oven A load #31 consisting of COS Beam Dump Glass is to be released 5.20.99.
 
We have been experiencing erratic behavior from the RGA beginning with load #30 and now believe this to be the result of the recent discovery that one of the RGA
probe pins ("filament return & repeller" pin) is still partially shorted to ground (initial problem thought to have been corrected earlier). Stan opted to approve this load
(load #31) based on the aggregate of more than one post bake scan.  The nature of this "erratic" behavior is such that the signal is either present or absent for a given
AMU for a given scan.  Thus, several scans, when looked at together, can show the total picture. I will vent, realign the repeller grid and reinstall the RGA probe
after load #31 gets unloaded.

LHO Vacuum Bake Oven A load #32 (Stainless Steel) is set to begin vacuum baking 5.21.99.

Seismic Isolation Installation:
-------------------------------
(C. Gray, H. Radkins)

Dome for BSC7 was installed and Bellows were all torqued.  Chamber was pumped down over the weekend.  After several Leak Tests it was determined that the
SW Bellows had a leak from its Large Conflat.  This is significant because in order to switch out the bad gasket, the imposing Gate Valve south of the chamber is in
very close proximity to this work area--so much so that the Bellows can not be removed unless either the Gate Valve is removed or the Support Tube is removed
(both jobs being considerably painful).  In order to make everyone happy a manuever was made to make the task trivial.  The Air Bearings were activated and the
whole system (Downtube, Support Tube, Crossbeams) were actuated ~.5" north, away from the Gate Valve.  This provided enough room for the V-Blocks to be
removed so that the Bellows could be moved just enough so that the suspect gaskets could be removed and swapped with a new pair.  This Bellows is being
worked on as I type.  All of this is being done without the removal of the Dome.

Leak Tests showed that the opposite Bellows on the same Support Tube is also a "leaker".  This one will be worked on in similar way to the one mentioned above,
but it should be monumentally easier.  Once both Bellows are Sealed up chamber will be pumped down and Leak Checks will be made (keep your fingers
crossed).  Thanks to Nergis Mavalvala, Gary Sanders, John Worden, and Bobby & Brenda for all of their help. And to Stan for realizing that the removal might be possible without pulling the dome and support tube!

Hugh is having fun in Livingston offering assistance with Seismic and alignment work.

As for next week, if we are lucky and our Bellows all pass, stack build up will begin.  Robert Scholfield will also work on taking some magnetic field measurements.
 

PreStabilized Laser:
--------------------
(Rick Savage)

The source of the daily variations in the PSL output power has been traced to ambient temperature fluctuations in the area that houses the laser water chiller causing
the laser head temperature to vary.  By opening the doors to the laser chiller enclosure and thus exposing the chiller to the temperature-stabilized LVEA environment,
the variations have been significantly reduced.

We plan to add louvers to the enclosure doors as a permanent solution.  Note that this is not expected to be an issue for the 4k interferometers at Hanford or
Louisiana because the chiller enclosures for those lasers are not adjacent to an outside wall of the buildings.

I attended a very productive end-to-end model meeting a Caltech earlier this week. We generated a schedule for the modeling and integration of the PSL and IOO
components of the WA-2k ifo. model.  Basically, we plan to have significant validation results by the LSC meeting in July.

Optics:
---------------------
(D. Cook & B. Weaver)

Activities are picking up in the optics lab once more with the first attempts of gluing SOS optics with the new fixtures and procedures. The ITMy-2k and Fmy-2k
are being re-cleaned and will be fitted to there new gluing fixtures. Hopefully we will be back on track installing optics soon. It will be nice to give chase to those
seismic installation guys. Thursday was an interesting day with the PAC meetings, tours and activities. They were very informative talks.

Electronics & Electrical Systems
--------------------------------
(R. McCarthy)

The PSL DCU monitor cables have been installed and we will be looking at signals from them as soon as possible.  The cables are connected to a new board made
by Jay H. and installed by Rich A.  This will be the burn in test of this board.

A new power center has been assembled and moved into the LVEA.  This is to provide power for the various installations that are going on.   At times the facility
does not have enough outlets for the equipment need for installation.  This new power center will be used to provide enough ckts for the installation and is portable to
relocate to where it is needed.

Computing Systems:
------------------
(C. Patton)

This week I finished typing the email account aliases into the database on the server.  I helped with a couple of problems getting PCs setup to use the new email
server.  Otherwise, the new email server seems to be working well.  All the LHO permanent residents are now getting their email from the LHO email server.

Beam-Tube Bake Out:
-------------------
(M. Lubinski, M. Guenther, and W. Althouse)

Still chasing a leak...

At the time this report was compiled, Ski informed the LHO staff that the leak was resolved and that, therefore, the 4 module beam tube bakeout is now complete. Congratulations are above. - GHS
 


LIGO Livingston Observatory (LLO) Operations



 
 
Detector Installation
The alignment of the adapter plate for BSC #3 has been completed.
Continued work on the alignment of the adapter plate for the BSC #1. It
should be completed by this Friday May 21. Installed the Air Bearings for
the HAM # 4.(Fred Asiri)
 
 

Optics & Vacuum Labs: This is the last of the Culligan DI saga; we're over
spec and have been so with 18.3 meg-ohm water for 3 weeks now, and I've
signed off on their PO! The first batch of ISC viewports are out of the bake
oven, and we'll begin installation as soon as the vertex is up to air, next
week. The 40 gal ultrasonic cleaner we made works great, and as soon as we
complete a fixture to create a false bottom above the transducer we'll begin
cleaning large items. Liquinox was definitely the culprit causing the
foaming in the waste treatment plant. Henceforth Liquinox waste goes into
the storm drains so Gerry can use it for watering the lawn. Hugh Radkins has
been here all week, and Ken Mason arrived Wednesday to go over alignment
issues. Continued working in the shop area. We've plumbed in shop air,
installed a small bead-blast cabinet and erected a dustscreen behind the
panel saw. (Jonathan Kern)
 

Vacuum System The clean purge air compressors ,for the VE, have been
serviced by the manufacturer, JPL Consultants, and will be back in service
as soon as we receive the timing module for the dryers. We expect to have
them on Fri. The bellows for the BSC support tubes are in the bake oven and
will be ready early next week. (Allen Sibley)
 

Beam Tube Bake out (Cecil Franklin)
1.We have been notified by PII the X-1 module is now completed, and ready
for a LIGO acceptance walk down inspection. This inspection has been
scheduled for 5-24-99.

2.Excel have completed the visual and electrical megaohm inspection of the
five transformer shipped from Hanford.

3.We have unpack the Power Supply trailers and return the tie down straps
to Hanford.

4.Custom Concrete cutters Inc. has completed the coring all the round holes
in the BTE along the X and Y arms a total of 30ea. 6" holes and 29ea. 4'
holes were cored.
 
 

Administrative (Bonnie Wascom)
- New check payment procedure in place which consist of a check request
form.  This system is intended to assist in more timely payments and provide
for better record keeping in case of an audit.

- Staff web page complete although a revision is planned soon to add a
section for students and long term contractors.

- new SLU student (Gwen) begin work today as an Administrative helper.

- MSDS book set up in control room and being maintained by Bonnie, includes
tabs for each MSDS.  Please turn in new sheets as received.
 

Facilities
The 75% Design for the Landscape/Erosion work was completed. We estimate
that the design package will be completed next week and will be ready for
the proposal release by the 1st week of June. (Gerry Stapfer)
 


WBS 1.2, 1.3    Detector Group



 

----------------------------------------------------
DETECTOR GROUP -- Whitcomb/Shoemaker

(WBS 1.2, 1.3)
----------------------------------------------------
 

----------------------------------------------
Interferometer Sensing and Control -- M Zucker
(WBS 1.2.1.1.6, 1.2.1.1.7)
----------------------------------------------

Interferometer sense/control (Zucker)
---------------------------------------
Most folks on travel this week.
Mavalvala and Daw are at LHO working on excess RFAM in the
laser and GDS/DAQ/ISC software interoperability/intercommunication,
respectively.

Mason is at LLO working on initial alignment survey requirements.

Zucker and Fritschel are at LHO for the PAC meeting and
(incidentally) working on some optical levers.

-------------------------------------------
Lasers and Optics -- J. Camp
(1.2.1.1.2, 1.2.1.1.3, 1.2.1.1.4,1.2.1.1.5)
--------------------------------------------

Prestabilized Laser -- Peter King
--------------------------------------------

- The reference cavities used in the frequency stabilization of the PSL
have arrived from REO.  All reference cavities for the sites are now in
house.

- Modification of the remaining PDA-55 photodetectors, to lower their
transimpedance, has commenced.  Only 6 more photodetectors require the
modification.  These photodetectors are used for the intensity
stabilization and for monitoring the transmission of the pre-modecleaner
and reference cavities.

- Below is the current PSL deployment status as of 05/20.

Assy/Subsys:    2k IFO     LLO 4k     LHO 4k     Notes
-------------------------------------------------------------------------------
1. 10-W LIGO    10/7     |    4/19/99    |   x   | all units delivered
    Laser       |     |       | 1 unit to be
           |     |       | rebuilt at LHO.
-------------------------------------------------------------------------------
2. reference     10/7     |      4/99     |     4/99      | all units delivered
    cavity     |       |         |
-------------------------------------------------------------------------------
3. freq. stab.   10/7     |      4/99     |       ?       |
    hardware         |       |     |
-------------------------------------------------------------------------------
4. PMC   10/7     |      4/99      |      ?      | redesign pending
-------------------------------------------------------------------------------
5. PMC hardware  10/7     |      4/99     |       ?       | all detection
           |     |       | hardware constructed
-------------------------------------------------------------------------------
6. misc. optics  10/7     |      1/99     |       | 80% already ordered
-------------------------------------------------------------------------------
7. ISS   10/7      |      ?      |       ?      | pending testing of
           |     |       | current hardware at
           |     |       | LHO 2k IFO and LLO
                          |               |               | evaluation of
                          |               |               | different AOM about
                          |               |               | to commence
-------------------------------------------------------------------------------
8. beam dumps    10/7     |    1/31/99    |     | completed
-------------------------------------------------------------------------------
9. software (SW) 10/7     |       |         | 2k IFO evaluation
   FSS SW       |     |       |
   PMC SW       |     |       |
   ISS SW       |     |       |
   laser control      |       |     |
-------------------------------------------------------------------------------
Installation:       |     |       |
Start:   10/7     |  4/99     |     ?     |
Completion:      12/15    |       |         |
-------------------------------------------------------------------------------
 
 
 

Input/Output Optics -- Dave Reitze, UF
-----------------------------------------

Hanford 2-k IOO

- SOS gluing

Cleaned mode cleaner flat, mode cleaner curved, and MMT1. Measured the
thickness of these optics and glued wire stand offs and wire guid rod. The
methods to measure the thickness and to glue the wire standoffs are the
same as previously (Used the previous fixture).

Helena, Sany, Janeen, Betsy, and Dave have started the (hopefully) last
gluing of the MCCM. MCFM, and MMT2 using the new fixtures.

- RFAM

Nergis and Sany have performed more RFAM measurements; the optical layout
has been modified to eliminate measure spurious RFAM on the orthogonal
polarization channel.  There is still excess noise at 30 MHz (even
with the modulator off) which could be caused by the 30 MHz signal
being picked up in the PSL, or some leakage of the LO into the modulator
(which was still cabled).  Experiments are ongoing.

LLO 4K

Seven small optic suspensions were shipped to Livingston today, for vacuum
baking there.
 

Core Optics Procurement and Metrology -- GariLynn Billingsley
-------------------------------------------------------------

We have measured the first in our survey measurements of End Test Masses.
The survey is intended to sort and match ETMs into pairs of similar Radius
of Curvature.  Unfortunately the building air conditioning has changed from
winter to summer mode and we are having difficulty stabilizing the
temperature in the room.  Each new configuration takes over a day to check
out, although some are seen to be clearly inappropriate within a few hours.

Fortunately the End test masses have the smallest radius of curvature (7400
m) so that 0.3 degrees change in temperature seems to only cause ~30 meter
change in measured radius of curvature.  It is worthwhile to bear in mind
that we are only matching here... we needn't yet have the absolute numbers.
 
 
 

Core Optics Coatings -- Helena Armandula
--------------------------------------------------
Bonding issues: Moving ahead. We made several sets of magnet / dumbbell
assemblies. The bonds tested were strong. One of them held 4 kgs. of shear
force for 16 hrs. without breaking, another took the 4 kgs. for a few
minutes.  The bonds are strong enough for our application. The fixtures
used to make this assembly need some modifications.
Tested the new SOS fixture on a dummy mass. Working with hot fixtures makes
the process difficult, requires 2-3 people to complete the task. However,
the fixture seems to work and we'll start the bonding of face magnets on
Florida's optics today.
Also the Folding Mirror is in process, Janeen removed the old standoffs,
cleaned the optic and cemented the wire standoffs. We are ready to bond
face magnets.
 

Core Optics Support -- Michael Smith
------------------------------------

PO TELESCOPE
Awaiting completion by SORL for the polished mirrors. Ken M. is continuing
to revise the production
drawings for the PO telescope. Mike S. is designing alignment fixtures for
the PO telescope procedure.

ETM TELESCOPE
First article ETM Telescope has been assembled and checked. Several parts
will be modified at production to reduce weight and provide for ease of
assembly. The lens mounting bores were too tight and will be opened up in
the production model. The smallest diameter lenses of the lot of 7 should
fit inside the present housing. Ken M. is designing assembly tools for
inserting the lenses.

PO MIRRORS
All fabrication is complete for the 2K PO mirror assemblies except for
minor rework to correct a fabrication error on one of the tilt assemblies.
Ken has selected a stronger return spring for the tilt mechanism.

CAVITY BEAM DUMP
Drawings are complete. Craig C. and Paul K. prepared drawing packages, and
a purchase order is being processed for the beam dump support structures in
BSC8. Craig has completed the detailing of the beam dump structures for
BSC4. BSC7 should be completed the week of 5/24. A purchase order will be
let for the BSC4 and BSC7 beam dump structures after the BSC8 parts have
been received and checked, approximately 6/16/99. The glass for the plate
beam dumps is being AR coated.

VACUUM WINDOW
Awaiting delivery from Varian of the re-made con-flat o-ring groove parts.

COS IR ALIGNMENT BEAM
The COS IR alignment illumination source has been ordered. The surveillance
camera for viewing the projected alignment beams has been ordered.

ARM CAVITY BAFFLE
Paul K. has resumed detailing of the arm cavity baffles.

INSTALLATION PLAN
item                                  completion          install

Mode cleaner baffle                   done                   done
IO baffle                             done                   done
Elliptical baffle 2KRM, HAM9         done                   on hold
Elliptical baffle 2KITMy, BSC8        done                   on hold
Beam dump BSAR3, BSC8                6/11                     ?
Beam dump FMYX, BSC8                 6/11                    ?
Beam dump FMYY, BSC8                 6/11                     ?
Beam dump 4KITMHR3, BSC8             6/11                     ?
Beam dump 4KITMHR4, BSC8             6/11                     ?
PO mirror 2KITMx, BSC4               done                     ?
PO mirror 2KITMy, BSC4               done                     ?
Beam dump RMHR3, BSC4                                          ?
Beam dump BSHR3P-2, BSC4                                     ?
Beam dump ITMXAR1, BSC4                                    ?
Beam dump ITMXAR4, BSC4                                    ?
Beam dump ITMXAR4, BSC4                                    ?
Beam dump ITMXAR4, BSC4                                    ?
Beam dump ITMyAR1, BSC4                                    ?
Beam dump ITMyAR4, BSC4                                    ?
Elliptical baffle 2KITMx, BSC7      done                    on hold
Beam dump FMXX, BSC7                                          ?
Beam dump FMXY, BSC7                                         ?
PO mirror BS, BSC7                  5/28                    ?
PO Tel, APS, HAM10               mirrors 6/14               ?
ETM Tel                             done                   ?
 

--------------------------
Isolation Group -- M. Fine
--------------------------

Seismic Design (Mike Fine)
--------------------------------------
1. Electronics Rack:
The side panel has been installed in the rack and the multiplexer is
being connected to the top plate cables.  Hytec expects to complete the
multiplexer installation this week, at which time they will begin the
side panel to multiplexer wiring. This operation will take most of the
next week.

2. Cables:
Hytec has performed continuity checks on BSC4 cables.  All of the
cables checkout without problems. They will be shipping the cables to LHO
early next week.  BSC7 and BSC1 cables will be inspected and shipped to
LHO around the end of May or beginning of June.

3. Scissors Tables:
Hytec has completed the assembly of the four BSC scissors table and shipped
them to LLO.  The next BSC scissors tables will not be available until the
end of the May.  Hand Precision has pushed both the April and May delivery,
eight tables for each month - 16 total, to the end of May. The Superior Jig
scissors tables have been reworked (spring cup holes tapped). Hytec has begun
assembly of these scissors tables as HAM units and plans to complete the
assembly of all 16 tables by the end of May.

3. Near-Term SEI Hardware Delivery Schedule:
3 BSC Downtubes (Livingston)      5/28

Suspension -- (Janeen Hazel/Mark Barton/Mike Fine)
-------------------------------------------------------------------
1. Report from Janeen:
-The LOS gluing fixtures for all optics but the beamsplitters are here at
Hanford and will be utilized on the FM this morning.
-Supporting IOO on using their gluing fixtures. We did a trial run using the
pre-heated fixture yesterday afternoon on an alum. optic and the bonds were
good.
-Working with Gabriela Gonzales on characterizing the cross coupling of the
MMT3 osems. Her goal is to tune the suspension controllers to take into
account these cross couplings.
 

---------------------------------------------------------
Detector Systems Engineering -- D. Shoemaker/D Coyne
(WBS 1.2.1.1.9)
---------------------------------------------------------

Physics Environmental Monitor(Matt Smith, David Shoemaker & Alex Marin)
-----------------------------------------------------------------------

    1.The delivery schedule is posted at :
       http://web.mit.edu/marin/www/PEM_Delivery.html

    2. Accelerometer positions and locations are posted at
       http://web.mit.edu/marin/www/Accel_Cable.html

We decided to test a new suspension material for the microphone, latex
tubing.  We will be able to suspend this in the same manner as the
previous design, with out any changes to the suspension mounting parts
that are on order.  I had also modified the design for the support
bracket that will be used for the microphones on the HAMs (this has not
been ordered yet, so there is no change to parts on order).  The
previous design was to flexible.  New quotes are due in by Monday.
Finished the assembly drawings for the microphones on HAMs and BSCs.

Continued work is being done to clean up the drawing for the sensor
locations for Hanford.  The Livingston drawing will follow after the
Hanford drawing is complete.

Continue to clean up the assembly drawings for the sensors to their
respective mounts at unique locations.

Continue to work on the particle monitor design.

Daniel proposed a new list for the power line monitoring. A list of all
possibly useful power monitor channels can be found at:

http://www.ligo-wa.caltech.edu/~sigg/ChannelCount/PEM_PWR.asc
 

Optical Contamination (Steve Bell)
--------------------------------

No activity.

-----------------------------------------
Control and Data System -- R. Bork
(WBS 1.2.2)
-------------------------------------------

Data Acquistion
====================
- DAQ and GDS system integration tests at Hanford were successful.

# DHS  Good news!

Suspension
====================
- The wiring harness for the LLO COS suspensions is ~50% complete and
should be
ready for shipment to LLO by 5/28/99.

ASC
=====================
- Rev B WFS Demod boards received. The first board will be stuffed and tested
next week as time permits.
- LHO 2K LVEA ASC system wiring diagrams and rack drawings are ~50% complete.
- WFS dewhitening board schematics are ~75% complete and should be complete by
5/28. Board layout will begin after the WFS/Bull's Eye PD board is complete.
- WFS/Bull's Eye PD schematics are 95% complete. They will be finalized next
week after tests of the new digital attenuator are complete.
- Quad PD schematics are complete and preliminary board layout has begun.

LSC CDS:
==========
I had to rework part of the LSC photodiode PCB layout because of some
mechanical problems with Joe's packaging in the RF box. I am working on the
system layout drawings at the same time to sort out the interfacing and
cabling.

Timing System:
===========
The first article of the new GPS Clock Driver is almost finished being
stuffed. I should be able to test it with the fanout module during the next
week.
 


WBS 1.4    Project Office



 

 1.4.1.2 Project Controls (Lindquist)


Change Control/Contingency (Lindquist)

The following change requests are have been submitted:
 
CR-990001 WBS 1.3 Return Unused Budget for Construction Related R&D to Contingency P. Lindquist
CR-990005 WBS 1.1.4 Livingston Site Fiber Optics Cable Installation F. Asiri
CR-990010 WBS 1.4.4 Tape Drives for LDAS Hanford and Livingston Observatories A. Lazzarini
CR-990011 WBS 1.1.1 Stiles, Scaffolding, Vacuum Cleaning J. Worden
 
Press for the latest Contingency Needs Projection


LIGO Weekly Site Telecon (Jasnow)

There was no site telecon on Thursday, May 20, 1999.  The list of current actions assigned may be found at ACTION LIST.


PROPERTY MANAGEMENT (Chargois)

From: Ed Chargois <chargois_e@ligo.caltech.edu>

Assisted the Optical Engineer by preparing a Commercial Invoice and shipping three (3) Optics Containers to CSIRO Division Of Applied Physics (Australia), attention: Mr. C. Walsh, account # 5F514.

Assisted the Livingston Site Manager by requesting two (2) Vehicles from the General Services Administration (GSA) Fleet Management Office in Harahan, LA, attention: Mr. John Creel.

Prepared a prepaid Purchase Requisition to United Motor Freight for transporting two (2) Bake-Out Trailers scheduled for 6/2/99. This
pre-payment will eliminate the possibility of late payment during the Oracle Conversion (Dark Period) which is scheduled for 6/15/99.


DOCUMENT CONTROL CENTER (Turner)

From: the DCC <dcc@ligo.caltech.edu>

New web pages for the DCC gives simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .

ACTIVITY HIGHLIGHTS

Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.


COST SCHEDULE CONTROL SYSTEMS (Duncan, Moore, Akutagawa, Kaufman)

From: Sarita Moore<moore_s@ligo.caltech.edu>

Press here for ACCOUNTS PAYABLE HISTORY DATA.

From: Kris Duncan <kris@ligo.caltech.edu>

From: Florence Kaufman <fkaufman@ligo.caltech.edu> From: Cindy Akutagawa <cindy@ligo.caltech.edu>
SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: irena@ligo.caltech.edu (Irena Petrac)

From: Ed Jasnow <jasnow@acrux.ligo.caltech.edu>

TECHNICAL CONFIGURATION MANAGEMENT (Althouse)

From: wea@acrux (William Althouse)

No report. See Bake out.


1.4.2.1 Quality Assurance (Tyler)

From: "William H. Tyler" <tyler_w@ligo.caltech.edu>

LIGO QA has essientially completed ordering all of the equipment required for the in-house Walkerizing operation. All facility related modification service requests have been placed, the DOI water system ordered and supporting process documentation initiated and/or "drafts" prepared. The target date for starting this operation is after the Memorial Day weekend.

LIGO QA is working with Rai Weiss to revise the vendor Fluorel o-ring bakeout set up. Plan to have the vendor run additional Fluorel samples with an oven air bleed this weekend for Weiss to conduct sticking tests late next week. Additional Fluorel o-rings are on order, but LIGO will need a bigger bakeout capability (compared to size of R. Weiss oven) to not impact the Livingston bakeout schedule.


1.4.2.2 Safety (Zydowicz)

From: Mike Zydowicz <zydowicz_m@ligo.caltech.edu>

No report.
 


WBS 1.4.3    Systems Engineering / Data Analysis and Computing



 
 

Systems Engineering

Nothing to report

Modeling

On May 17 and 18, there was a meeting discussing about the current status and future
plan of the End to End model simulation activities. All presentations were given on May
17th, and May 18th was devoted for the discussions, mainly about the subsystem
development plan. Viewgraphs of the presentations and the minute of the May 18th
discussion are available in the e2e home page.

Data Analysis

* (KB) Developed an LDAS installation schedule for hardware and os
       infra-structure at the Hanford site. The initial phase will
       involve completion of tests of LDAS software development tools
       under Solaris 7 and RedHat 6. During the week of June 15, a
       team of LDAS OS and hardware people will travel to Handford to
       configure and install the LDAS infrastructure. During the next
       month work will focus on completion of the LDAS API components
       needed for the Alpha Release of LDAS. Then remote installation
       of the LDAS APIs will begin in mid-July, followed by a team of
       LDAS software developers traveling to the sites during the last
       week of July to validate LDAS software and provide training.

* (BS) Ilog Installation and Upgrade
       - The E2E and LDAS groups have been set up in the electronic log.
       - Upgrading the system to auto-update pages already showing on
         users browsers.  Also working on a software mirroring system
         because the electronic log will now be running at at least 3
         different locations.

* (BS) Web Server Installation and Configuration
       - An Apache web server has been installed on spica.ligo.caltech.edu
         for future use as an electronic log server amongst other things.

* (BS) Majordomo Installation and Configuration
       - Majordomo has been installed to be used for creating weekly digests
         of status reports, etc.

* (PE) Wrote generic wrapper for low-level APIs which
       provides a consistent interface between low-level
       API's and between a low-level API and the manager.
       All api command validation, logging, error reporting,
       and socket communication routines are provided by
       the wrapper.

* (PE) Currently testing and debugging the user-mgr-assistant-api
       system with a single API (the frame API), and concurrently
       writing general purpose macros which will be used by the
       frame API.  Some of these macros will be portable to the
       other API's as they become available.

* (DF) Added support for opening files and reading/writing ILWD elements

* (DF) Continued debugging ILWD and generic API.

* (ML) Worked with Ed on problem of genericAPI interference with database
       open in metadataAPI. Preloading of DB2 odbc libraries did not
       eliminate the problem. Another alternative is to download
       an ODBC driver for DB2 from OpenLink software and use it
       as a driver instead of the IBM driver.

* (ML) Committed metadataAPI scripts and regression test script to
       check out SQL functions and data socket on the metadataAPI.
       These were developed against shared objects in /ldcg/lib.

* (MB) Reviewed LDAS Lightweight API, LDAS Lightweight Format, and Data
       Conditioning API documentation.

* (MB) Met with Kent to discuss technical issues associated with reviewed APIs.

* (MB) Clarified some issues regarding LDAS Lightweight Format documentation
       with Roy Williams.

* (XH) modified LDAS frame table [AL note: this includes statistics requested by Fred Raab]

* (XH) worked on GDS ilwd file to match the change in genericAPI

* (XH) worked on GDS trigger/event table

* (XH) worked with Mark on GDS SQL statement

* (XH) worked on LDAS event ilwd file

* (RW) Trying to streamline bakeout ingestion system by eliminating
       WebBase and using Visual Basic in Access. Tedious and long-winded
       Microsoft installation problem precludes this.

* (RW) Development work on LIGO_LW browser. Discovering how to maintain
       large Java project: external libraries for parsing, DOM, graphics.
       Understanding the Java Swing classes for tree visualization and
       editing.

* (RW) Fixing bugs in LIGO_LW DTD [reported by Maria Barnes].

* (BK) Resumed work on the web application for CDS.  Reworked most of
       the forms for the modified file structure and am finishing up
       the 2 editting forms. The editting forms now allow you to choose
       one or more subsystems in a configuration to edit.  Next task is
       to add a new form for merging two configurations into one.  Began
       writing some documentation for the system.

Maros -----

Installed CVS 1.10
Installed iODBC under Linux (Intel and Alpha)

Anderson:

Testing HPSS for sustained high speed parallel data transfers.
Initial test was successful for 15 hours at a sustained rate of 8MByte/s
for a total of ~0.5 TByte successfully transferred from the 40m into HPSS.
Individual file transfers where running at ~20MByte/s.

Lazzarini:

Worked with Mark Coles and Joe Romano (U.T. at Brownsville) on a proposal by UTB to NSF for a minority education program. It would involve students working at LLO and parallel [beowulf] computing architecture implementation at UTB for student education with this type of technology.

Issued a revised draft of the numerical algorithms library design doc. for review by LSC data chairs and LDAS/GDS staff.

Coordinated with Wallace, Kent on a near-term schedule for LDAS installation at LHO.

General Computing

MIT:
Nothing to report

Livingston:
We are working on removing a virus from the PCs.
We are getting prices for additional software packages.
 

Hanford:
This week Christine finished typing the e-mail account aliases into the database
on the server. Helped with a couple of problems getting PCs setup to
use the new e-mail server.  Otherwise, the new e-mail server seems to be
working well.  All the LHO permanent residents are now getting their
e-mail from the LHO e-mail server

CIT:

Samantha has been working on copying CDs for different people. It was
discovered that certain files copy well under one installation of Windows95 and
not another. She will be looking into seeing what the problem may be.

(Barbara K.)The web application for LSC progress reports is now available to the
public.  Worked with Syd to test the forms and make a number of last minute
changes.  Attended a meeting about procedural issues surrounding the
reports.  Put links to the application on the LIGO Home and LSC web pages.
Since Syd sent out his announcement about the site,  we've received one
report.
Prepared a web page with draft plan for reworking the web servers.
Rebuilt the web DCC database used for searching.
Entered 8 abstracts into the Amaldi database.  These are abstracts that
were received by e-mail before we added an abstract text field to the forms
and database.  Talked with a candidate for Valeda's position.

Worked on a number of SUN boxes in recovery of the break-in that took place last
week. Going over the logistics of eliminating some of the services that can be
exploited and how those services can be better controlled if they are still
needed.
Rebuilding and fixing a number of PC's that have been infected by the
"Happy99.exe" virus. We have had to rebuild a few of the machines but most were
fixed by running a anti-virus routine. Jonathan Kern from the Livingston
Observatory also sent a procedure that they used to clean out the virus which
appears to work.

A number of orders have been placed for new equipment to be located at CIT and
the Observatories. Also, going over maintenance contracts and s/w license
renewals.

Sean has resumed work on the kater replacement unit after being distracted by
the break-in. The unit is complete with the exception of a few applications that
need to be installed.


WBS 1.4.4.1    Administrative Group


 

Rita Torres

For I Petrac did change order No. 5 to Allied Engineering, change order No. 5 to Schober Machine, change order No. 1 to ASCO Engineering, change order No. 4 to MIT. Distributed the signed Schober, ASCO, CRDF documents. Helped format attachment 3 to the Virgo MOU.

For Detector group, began work on various documents related to Fluoride extraction, including ways of tracking. This project is ongoing. Took an all-day class on Project '98 to better navigate in the tool so as to better support the Detector group in tracking trips and other things.

For G. Billingsley obtained hardcopies of 14 publications -- thanks go to C. Mak who helped with most of them. For R. DeSalvo typed from handwritten technical notes; result 6 pages. Copied and distributed for review the set of operating procedures for Livingston. Ordered supplies for Wilson House.

Dorothy Lloyd

No report as Dot is currently deluged.

Irene Baldon

PLEASE NOTE: This report is for 4 days only. One day taken as Vacation.

Worked on preparing the paper work for various new trips taken recently (17 Purchase Requisitions and 15 Advance Requests). There are 16 additional new trips in various stages pending completion of travel arrangements.

Completed all of SURF Travel except for the 1 student coming from Belgrade, Yugoslavia. His participating in the 1999 SURF Program is becoming doubtful since I haven't been able to contact him for about 2 weeks. The SURF schedule is from June 14th thru August 20th and many of LIGO's members are acting as Mentors.

Completed 29 Expense Reports, some of which were extensive, involving 2 or more pages each. Many of these reports were still not taped or completed by the Traveler, and required additional time for completion. Also worked on a number of problem issues which required a good portion of my time. Received, but not yet completed my audit, 22 Expense Reports. These should be completed in next couple of days, barring unexpected delays. I'm holding 6 expense reports which require additional information and/or missing receipts from the traveler.

Prepared Travel/Vacation Itinerary for the Week of May 17th, 1999.

Performed miscellaneous duties as requested by various members of the LIGO Project here at Caltech, as well as from members of the staffs of each of the two (2) sites.
 
Elizabeth K. Wood

Attended yet another APE Town Hall. This one was entitled AN OVERVIEW OF THE APE TRAINING PLAN.  Indeed it was.  We still don't know when we'll start training nor do we have any idea what the training schedule will be, but we have definitely gotten an overview of the intentions of APE to get us trained.

Dealt with some fun personnel issues. This week's crisis centered around visas for various and sundry employees. Many thanks to Ben Ortega for his insight and knowledge of the ins and outs of the INS.

In anticipation of the arrival of ORACLE, I sent a memo over to the phone office changing the account numbers to which our long distance access codes are being charged. Also have updated PAN forms in anticipation of the HRIS dark period. Has everyone had a good look at the Ape Bulletin outlining the current tentative schedule of events?  Does everyone know about the dark period for purchasing and hiring?

Typed up a draft of a memo from Riccardo concerning the Advanced R&D Progress Report to the NSF.

  


For additional information about this report, contact sanders@ligo.caltech.edu