Weekly Report for Week Ending April 27, 1999



 Project Control Meeting Agenda   Highlights   Hanford Observatory     Livingston Observatory     Detector    Project Office    System/Data Analysis    Administrative    Past Weekly Reports

The Project Control Meeting Agenda for Monday  May 3, 1999 will be:
 (Meeting time: 10:30 am Pacific Time)

  1. Announcements (5 minutes)
  2. Review of Action Items (10 minutes)
  3. Comments on Weekly Report (5 minutes)
  4. Field Change Orders/Contingency Liens/Change Requests (10 minutes)
  5. Review of ISSUES AND PROBLEMS by Subsystem/Activity (10 minutes each)
Special Items:  NSF review reprise, LLO road, LLO security


Special Announcements:

Phil's transcription of the NSF Review Panel's exit comments follows. Congratulations to all for another successful review!
=================================================================
 

It is very satisfying for the Committee to see the hardware emerge from the
paper.
 

1. Installation and commissioning of the detector systems at both LHO and
LLO are going well. Although there has been a two to three month schedule
slip in some of the early milestones, this does not appear to delay the
first coincidence operation of the interferometer in December 2000.
 

2. The Committee urges LIGO to continue to monitor the potential
contamination for the Viton materials in the vacuum system.  Successful
operation of the two kilometer interferometer at LHO will add confidence
that this potential problem will not affect future LIGO operation.
 

3. The Committee commends the progress in developing data analysis and
simulation systems for LIGO.
 

4. The Committee recommends that LIGO and the LSC cooperatively establish a
set of pacing milestones to ensure timely completion of the LIGO software
suite.
 

5. The Committee urges NSF to work with all interested parties including
LSU and the State of Louisiana to define a plan for final resolution of the
access road to assure all-weather access to the site.
 

6. The Committee recognizes the seriousness of the recent security issues
and strongly recommends that the LIGO management continue to pursue and
expand appropriate safeguards.
 

7. The Committee recommends that NSF establish a focused review of the data
analysis and simulation systems for LIGO before the next annual review.


Weekly Report Highlights
 
 


LIGO Hanford Observatory (LHO) Operations



 
Facilities:
-----------
(O. Matherny )

Water System modification:  The contractor is in process of installing the
two additional sensors.
Parsons designer is scheduled to be at LHO April 29th to evaluate the work
accomplished.

New staging Building:  The contractor is installing the siding for the
building and
on April 29th is placing the concrete floor for the mezzanine.

Compressors:  No change.

Bake Oven:
----------
(K. Ryan)

LHO Vacuum Bake Oven A load #28 consisted of three BSC bellows and some
misc. conflat flanges and no Kapton cables as originally reported
(correction to last week's report).  The ribbon cable's Kapton insulation
was found to be shedding and required further preparation and, as such,
were not included in Load #28.

LHO Vacuum Bake Oven A load #29 consisting of elliptical baffle glass, beam
dump glass, elliptical baffle aluminum hardware, two small optics (glue
experiment-Haisheng) and several aluminum shims (seismic leg elements) has
started vacuum baking.

One of the seven independently heated zones of the vacuum bake oven system
was observed to have stopped heating in the middle of load #28. This proved
to be the result of a defective heat tape.  Also, the partial pressure of
amus 41 and 43 (in RGA volume background) have been rising steadily over
the past few months.  This is looking like a problem with the "upside down"
orientation of the RGA volume turbo molecular pump.  The pump
manufacturer's advertised literature implies that this orientation is valid
for this pump but conversations with the manufacturer's tech people seem to
contradict this.  In any case, we are going to vent the RGA and reorient
the turbo pump to be followed by a good ol fashioned baking.

Seismic Isolation Installation:
-------------------------------
(C. Gray, H. Radkins)

The second BSC seismic isolation system has now been completed with much
help from visitors Gary Sanders, Bill Kells, and numerous locals.  The
isolation stack was completed last week and the Optics Table lowered in
place.  Counterweights (shy 70 lbs) and cabling were installed and the dome
was replaced.  The bellows have not been leak checked yet and may not for
some time until the remaining chambers (Mode Cleaner Hams) are closed
again.  We have moved on to BSC7 (2K FM & ITMx); the Actuation Stack is
about 25% in place.  It is going a little slow waiting for the Actuation
Stack alignment to be completed on BSC3.

PreStabilized Laser:
--------------------
(Rick Savage)

J. Myers and I continue to investigate laser output power drops that appear
to be correlated with water temperature excursions.  The chiller appears to
be unable to keep up with temperature excursions inside the exclosure where
the chiller is located.

The disk in the SparcStation located inside the laser area enclosure has
crashed.  D. Barker has removed the faulty disk and hopes to replaced the
computer within the next few days.  It is thus temporarily not possible to
control the PSL locally via computer.  This does not affect the performance
of the PSL or the data logging.
Core Optics Support:
-----------------
(B. Weaver)

Last week I had the opportunity to meet with Mike Smith, for the
first time face to face, regarding upcoming COS installations.  We
spent a good portion of Thursday and Friday afternoons going over
baffles, beam dumps, telescopes, etc.  I received many drawings that
will help me familiarize myself with most of the COS components.  We
also assisted with the installation (and removal) of the FMy in WBSC 8.
Thanks Mike - especially for the softball tips!

This week, I received the 36 pieces of glass to be used in the beam
dump assembles.  I have cleaned 9 pieces and included them in the current
vacuum bake load with the four pieces of elliptical baffle glass.  The rest
will be included in a later load.  Bake load #29 (COS glass) is expected to
be released Monday, May 3.

Optics:
---------------------
(D. Cook & B. Weaver)

With the optics installations on hold due to the gluing process refinements
and OSEM problems, we have had an opportunity to catch up in other areas. I
have been working with Larry on some new installation tooling and
techniques which will allow us access into BSC chambers that restrict the
use of our current equipment. We are making some minor changes to some of
the existing fixturing as well.

The Optics and Vacuum Prep. Labs have been up graded with the addition of
new power circuits and cable trays. Betsy and I have taken some time to
reorganize the labs to better facilitate their use. I had an opportunity to
work with M. Zucker in the Optics Lab measuring the amount of scattering
from the COS elliptical baffles. There was some hope that a weak signal
could be reflected from them, but they are too efficient as baffles.
"(they're just doing their job)".

I have started on a new COC installation procedure, using our new
techniques. I will be reviewing it with the detector team when finished.
John Worden and I meet with the owner of a local machine shop, hoping for a
second source to obtain machined parts. They have CNC capabilities and may
be better suited to machining some of our more technical components. They
are competitive in their hourly rate to Larsen's.  Both shops will prove
out to have their strong points. Larsen has hopes of retiring in the
next few months.

Computing Systems:
------------------
(C. Patton)

Did the usual weekly backups, ordered some more backup tapes and
ethernet cables.  One of the student helpers has started re-organizing
the GCnet patch panel, which is always "a jumble of spaghetti".
Contacted HP about sending our Deskjet color printer in for repair.

I have three test user accounts working on the LHO modem pool for telnet
sessions only.  I'm still working on setting up the security and other
login protocols.

Beam-Tube Bake Out:
-------------------
(M. Lubinski, M. Guenther, and W. Althouse)

We turned power off on the X2 module Sunday (4/25/99) and we are continuing
to pump on the tube at ports X2-1 and 9 with our turbo pumps and cryopumps.
We performed a leak isolation Monday and discovered our leak at port X2-2.
We conducted a helium leak check to locate the leak and found the "H"
hardware was leaking at the 6:00 position.  We checked the torque on the
bolts and found 2 at that position were slightly loose.  Upon further
inspection the gasket had some very tiny scratches.  All of the Cryopumps
have been removed from ports X2-2, 3, 4, 6, 7 and 8.  "H" hardware has been
installed at these ports and been leak checked.  Ports X2-3, 4 and 2 are
baking.  The RGA at port X2-5 has been shut down and is currently baking to
clean it up for the post bake measurements.  Rai Weiss will be out here the
week of 3 May to conduct these measurements.  Sun River will be out next
week to begin the removal of the bake equipment and preparation for
shipment to Livingston for their module bakes.  We shipped 2 of our DC
power supply trailers and 5 transformers to Livingston.  Cecil Franklin
reported that all arrived.

 


LIGO Livingston Observatory (LLO) Operations



 
 
Detector Installation: Bellows were installed on HAM's 2 and 3 foloowed by pump down and leak check. We discovered that one bellows is leaking. It is located on HAM 3 on the northeast side. We have determined that the small seal is the problem. The system is now at atmosphere and we will repair the bellows this week. Installation of the seismic stack in HAM 1 is now underway. The bake oven had a small air leak on the last pump down. This is a load for PSL reference cavity, however we should have this repaired and running today, so we expect no effect on PSL installation. (Rich Riesen, Allen Sibley, Tom Evans)

Electrical Installation:
· Fiber optic cable from MSR to 1X22 has been terminated.
· CDS equipment in the Mass Storage Room is now on the UPS
· HEPA filters on the PSL enclosure have been rewired so that they are VEAC power and are isolated from CDS power.
· Cable tray in the big house is complete
· Cable tray is installed up to HAM 2. The supports will be done next week after we the vessels are closed back up.
· Ordered material and began installation of the temperature sensors for the corner station
· Replaced all the Motorola controllers in the vacuum racks and sent the old ones to Dave Barker @ Hanford.
· Extended conduits, in the vault, 20" and foam filled around conduit to try and prevent water from entering the building
· Assembled and placed new shelving in the Electronics Lab for storage of the remaining major testing instruments
· Received and assembled cart for the rework station
· Began testing vacuum signals with the updated software
· A successful test was performed today on the UPS in the Mass Storage Room. Power to the room was disconnected for approx. 5 min. The new UPS switched and settled out with an estimated life of 54 min. Power was restored without incident. The UPS was at full load for the test.
(Russ Wooley, Juilien  Svoboda)

Optics & Vacuum Labs: (Jonathan Kern): Added two site telephones in the PSL Safety Enclosure, permitting entrants to use the intercom feature to announce themselves before entering. Installed the PolyPro sink in the Optics Lab, and assisted the PSL group in powering the 10w in the Laser Safety Enclosure. Installed and wired the Reibo drill-press in the machine shop, and used the wheel loader to dress the contractor's trailer site as a parking lot. Setup the 6" binoculars on the observing platform for NSF review visitors, and adapted the 10" Celestron for nite observing Tuesday evening. Completed the location and boring of 5 ISC pier locations, and received and began QC of 33 sets of COS viewports from Varian.

Computers: We have received and installed Matlab. We have ordered Mathematica for the Unix system. (Tom Evans)

Weather Station/Suspension test stand: Basic code(with minimal checking) to convert incoming data logger data to the correct form has been written and compiled and successfully tested on abundance using gcc. Troubleshooting in VxWorks underway. Basic code(minimal checking) for I/O written needs to be tested. Hardware for interface between VME162 and data logger complete. (A. Rizzi)
GRASP- Frame data ported from Milwaukee with help of B. Allen. Now able to animate frame format 40m data. Livingston ligo frame data ported from CDS network with help of R. Bork. Work underway to make Grasp code compatible with ligo channel label with goal of reading frame data from ligo format. Changes in installation parameters for frame require relook at versions of various helper applications.  (A. Rizzi)
End-to-End Model - New version of alfi3 installed and latest psl model installed from Rick Savage's directory. Last period, Rick Savage corridinated a telcon with A. Rizzi , Biplap and Hiro. We discussed the e2e modeling done so far and organized for future work.  (A. Rizzi)

Beam tube bake out preparation: LIGO has performed the preliminary inspection of the thermocouples on the beam tube, we found two TCs that are buried in the insulation. A final acceptance inspection for the X-2 module will be conducted this week. We are waiting on PII to schedule this inspection. We did a temporary fix around the beam tube penetration in the Corner Station and West End station. This temporary fix will help control contamination within the building caused by the insulation work being done inside the BTE.
LLO has received the two Power Supply trailers and one load of support equipment from LHO. The two power supply trailers have been staged along the X-2 module to the right of port X-2-3 and X-2-7. Randy has modified the air header to include three times as many taps. We continue to ordered vacuum equipment, cable ties, wire labels, kapton tape and other consumable supplies. (Cecil Franklin,Kerry Stiff)

Facilities: Construction of the access road is continuing. The communication cables
providing telephone and computer access to LLO were moved to accommodate the
road construction. Contrary to our fears, communication was not lost as a
result of this move. (Gerry Stapfer)
 


WBS 1.2, 1.3    Detector Group


 
----------------------------------------------------
DETECTOR GROUP -- Whitcomb/Shoemaker

(WBS 1.2, 1.3)
----------------------------------------------------

----------------------------------------------
Interferometer Sensing and Control -- M Zucker
(WBS 1.2.1.1.6, 1.2.1.1.7)
----------------------------------------------

Interferometer sense/control (Zucker)
--------------------------------------

Component delivery status:

IOT7          complete, installed
ISCT7          complete
ISCT9          in progress
ISCT10          in progress

LHO IAS equip.       complete

LHO viewports      complete
LHO chamber video     installation in progress
LHO illuminators       complete

LHO 2k optical levers:
    MMT3      complete
    RM          complete
    FMy         ready, on hold
    BS        ready, on hold
    FMx,y       ready, on hold
    ITMx,y          ready, on hold
    ETMx,y        support platforms in fab
 

LLO viewports      in vacuum prep
LLO survey monuments       in progress
LLO opt. lev. type I supports   in progress
LLO illuminators       complete, shipping this week
 

LHO installation activity (MZ)
--------------------------------------
MZ is at LHO this week doing things like:

- COS baffle backscatter test;  Betsy and Doug helped me set up a COS
elliptical baffle and glass beam dump (just cleaned, immediately prior
to vacuum bakeout) in the optics lab to check their BRDF's.  Using a
KP-160 CCD and a Lightwave 125 laser we found preliminary backscatter
coefficients of order 10^-7 /sr for the beamdump and < 10^-8 /sr for the
COS elliptical baffle (upper limit; only point surface defects could be
detected on the baffle). These are referred to calibration of another
KP-160 at MIT last week against a MartinBlack test target, and a similar
measurement on a beam dump sample sent to MIT.  Bottom line; as beam
dumps, these things rule.  On the other hand it'll be very hard to see
the beam on them during initial alignment.

- Worked with Sani Yoshida on post-modulator RFAM noise from the PSL.
Puzzle of the excess broadband AM appearing in the vicinity of the RF
carrier is deepening.  We need to understand this and fix it. Fritschel
suggested some additional tests.

-Unpacked and stowed remainder of ISC optical lever transmitter and
receiver heads for LHO 2k and 4k (16 total arrived Mon.).

- With lots of help from Larry, Corey and Hugh, I reinstalled RM optical
lever and got the beam back out. Now setting up to log alignment on
stripchart.  Last week Stan and Hugh reported a _possible_ movement of the
RM over the intervening month since installation (sort of a 1-sigma effect);
we want to keep an eye on it.

- Doing general cleanup of ISC equipment and 2k ISCT assembly area, shipping
empty containers back to MIT, etc.
 
 

ISC implementation (P. Fritschel)
----------------------------------
(4/22 report)

o Hiro is visiting this week, and I am working with him to
implement the ISC controls in the end-to-end model. I'll
start with simulating the lock acquisition of a single
2 km long arm cavity. There are a couple of new pieces
that we are working on adding to the e2e: a locally-damped
optic; the first internal resonance (9.5kHz) of an (COC)
optic.

(4/29 report)
o Continued working with Hiro on implementing a locally damped
optic in the e2e model.

o Reviewed Jay's schematics for the wavefront sensor whitening
boards which interface the demodulator outputs to the Pentek
ADC inputs.
 
 

IAS Initial Alignment (K.Mason, M.MacInnis)
-------------------------------------------
All remaining optical levers for Hanford have been assembled and
Shipped.

5 Base plates and 1 grout plate is being crated and will be shipped to
Livingston today.

All the Illuminators for Livingston are being boxed and will be shipped
early next week.

Myron is assembling an ISC clean room to begin assembly of ISC tables
for the 2k dark port and reflected port.

The Initial Alignment procedures T970151 has been revised and includes
all 2k optics alignment. A preliminary copy for review can be found on
the Caltech ftp site at /pub/kmason/T970151-B1.PDF.
 

-------------------------------------------
Lasers and Optics -- D. Shoemaker for J. Camp
(1.2.1.1.2, 1.2.1.1.3, 1.2.1.1.4,1.2.1.1.5)
--------------------------------------------

Core Optics Support (Mike Smith)
--------------------------------

PO TELESCOPE
SORL still estimates that polishing will be completed for 6
sets of parabolic mirrors by 5/15.  Mike S. is working on the CCD camera
alignment proceedure for the telescope. Brackets are being designed and
fabricated to hold the CCD cameras. A dummy primary and secondary mirror
have been fabricated for testing of the alignment proceedure.

ETM TELESCOPE
Fabrication of a first article ETM Telescope is ongoing.

CAVITY BEAM DUMP
Paul K. is assisting with detailing the beam dump support
structures. Craig C. has simplified the beam dumps by using an AR coated
flat black glass instead of a cavity beam dump to dump the 2nd order ghost
beams. He has also eliminated several horizontal support structures by
supporting two beam dumps from the same horizontal support structure. The
horizontal support structure cross section was increased to support the
additional weight.  The glass for the beam dumps has been fabricated and
shipped to LHO for cleaning and baking.

VACUUM WINDOW
The conflats have been received from Varian. The AR coated windows for the
APS beam have been received from REO. Helena A. will scribe part numbers on
the windows before they are shipped to Jonathan K. in LLO for clean, bake,
assembly, and leak test of the completed window assemblies.

ARM CAVITY BAFFLES
Paul K. is continuing to work on detailing shop drawings for the ITM and
ETM arm cavity baffles for LHO and LLO.

INSTALLATION PLAN
item                                            completion          install

Mode cleaner baffle                       done                   done
IO baffle                                       done                   done
Elliptical baffle 2KRM, HAM9         done                   on hold
Elliptical baffle 2KITMy, BSC8        done                   on hold
Beam dump BSAR3, BSC8            partial                  ?
Beam dump FMYX, BSC8              partial                  ?
Beam dump FMYY, BSC8              partial                  ?
Beam dump 4KITMHR3, BSC8        partial                  ?
Beam dump 4KITMHR4, BSC8                                  ?
PO mirror 2KITMx, BSC4               partial                  ?
PO mirror 2KITMy, BSC4               partial                  ?
Beam dump RMHR3, BSC4                                      ?
Beam dump BSHR3P-2, BSC4                                  ?
Beam dump ITMXAR1, BSC4          partial                  ?
Beam dump ITMXAR4, BSC4                                    ?
Beam dump ITMXAR4, BSC4                                    ?
Beam dump ITMXAR4, BSC4                                    ?
Beam dump ITMyAR1, BSC4                                    ?
Beam dump ITMyAR4, BSC4                                    ?
Elliptical baffle 2KITMx, BSC7         done                    on hold
Beam dump FMXX, BSC7                                          ?
Beam dump FMXY, BSC7                                         ?
PO mirror BS, BSC7                      partial                  ?
PO Tel, APS, HAM10                    partial                  ?
ETM Tel                                                                   ?
 

--------------------------
Isolation Group -- M. Fine
--------------------------
 

Seismic Design (Mike Fine)
--------------------------------------
1. Electronics Rack:
Progress is continuing with the rack assembly.  Hytec expect to have the side
panel electronics completed this week.  The multiplexer has been
started and Hytec expect to have it completed next week.  At that time
they will begin to install the electronics into the rack.
 
2. Near-Term SEI Hardware Delivery Schedule:
3 sets of BSC legs                                         5/5/99
700# balance weights                                       5/5/99
3 sets of HAM springs (Livingston)                         5/5/99
1 set of BSC springs (Hanford)                             5/12/99
2 BSC Downtubes (Hanford)                                  5/12/99
1 BSC bellows (Hanford)                                    5/7/99
1 HAM bellows and 6 BSC bellows (Livingston)               5/7/99
4 BSC bellows (MIT)                                        5/7/99

Suspension -- (Janeen Hazel/Mark Barton/Mike Fine)
-------------------------------------------------------------------
1. Report form Janeen:
-Working on redesign of LOS fixtures.
-Working on LED and Photodiode problems with Jay, Oliver, Dennis and Mark.
-Working on alignment fixtures issues with Doug Cook and Ken Mason.
-Working on bonding issues with Helena Armandula, et.al.

2. SUS Hardware Delivery:
SUS Structure Delivery Dates: [numbers in parentheses are quantities.]
LOS1(for ETM, ITM, MMT): 5/5(1)
LOS2: 5/5(1)

---------------------------------------------------------
Detector Systems Engineering -- D. Shoemaker/D Coyne
(WBS 1.2.1.1.9)
---------------------------------------------------------
 
 

Global Diagnostics System
(Daniel Sigg, John Zweizig)

The documentation of the GDS final design review has been finished
and sent to dcc and committee (T990013-A and T990018-A).

Finished a prototype version within the DMT environment of a data
quality scanner to be used in the characterization of the 1994 40m data.
This project is now waiting for a further development of the trigger
interface which will be used to log the data quality statistics to a
database, underway. Also continued general analysis  tool
development and debugging, in particular those functions used by the data
quality monitor.

Started preparation of the FDR presentation on the DMT.

The capability of using channel names to select digital test points
has been added to the test point manager. Also, a keep alive function
has been added (transparent to the user), so that test points from
clients which abort abnormally are released automatically.
 

Physics Environmental Monitor(Matt Smith, David Shoemaker & Alex Marin)
-----------------------------------------------------------------------

We are trying to finish up all the procurement for the PEM supplies.
Some items that will be orderded are two spare tiltmeters, the
Temperature /Humidity sensors for the partical counters, tripods for the
magnetometers, and computers for RGAs.

Some more work is being done on the microphone suspension system. The
HAMS will require an additional support bracket since there is nothing
physically on the HAM that can be used directly.

The seismometrs delivery slipped another month to May 24.  We are
getting a free Hand Held Control Unit (worth 1K) for our troubles,
though.

Getting quotes to purchase the computers for the RGAs.  We will also be
able to return two RGA heads and electronics that are a surplus.  We may
have to pay a restocking fee.

More work has been done for the muon detector final design. It will be
presented next month and parts will be ordered.

We are revising the final channel count both in Hanford and Livingston.
(with Daniel Sigg and Rolf Bork). The scheme proposed by Daniel for the
LHO will be adapted for the LLO IFO.
 

Optical Contamination
---------------------

We wish Daqun all the best.

-----------------------------------------
Control and Data System -- R. Bork
(WBS 1.2.2)
-------------------------------------------

Suspension
===============================
- The rack drawings, system drawings and cross connect list for the Y-arm, mid
station rack are complete. Cross connect wiring and rack assembly will be
completed by Hanford site personnel.
- We have borrowed one XYCOM 220 from the 40 meter WFS system to get the
Caltech
suspension controller test stand operational. There is a shortage of modules
between the sites due to shipping delays from the manufacturer. Until more
modules are received the Hanford and LA suspension test stands are on hold and
operation of the LVEA COS suspension systems is limited to 3 optics at any one
time.

ASC
==============================
- The design for the WFS whitening board is complete and board layout will
begin
next week.
- The board layout for the WFS DC signal DAQ interface board is complete and
being checked.
- The board layout for the WFS Demod rev B modules is complete and being
checked.
- A 4 bit attenuator was tested with the amplifier design used in the WFS PDs.
The amplifier/attenuator combination showed reliable performance to freq
greater
than 200 MHz with attenuator induced phase shifts < 5 degrees between high
gain
and low gain modes. These attenuators will be incorporated into the next
generation of the WFS PD board.
- The WFS demod board was tested and performance confirmed to frequencies
greater than 75 MHz. LIGO requires operation to ~70 MHz.
- Design of the Quad PD board has been started.

Timing System:
===============
- Due to a problem with the Protel PCB layout of the GPS Clock Driver, the
board had to be completely re-layedout. I am doing the final check of the
board before it goes out for fab.

LSC CDS:
==============
- Completed the design of clock fanout for the Pentek ADCs. This will take
the clock out of the GPS Clock Driver, translate it and send it to the
whitening boards to be input into the front end connector of the ADC.
Continuing work on the LSC servo  for the Hanford 2K One-arm lock.
 


WBS 1.4    Project Office



 

 1.4.1.2 Project Controls (Lindquist)


Change Control/Contingency (Lindquist)

The following change requests are open:
 
CR-990001 WBS 1.3 Return Unused Budget for Construction Related R&D to Contingency P. Lindquist
CR-990005 WBS-1.1.4 Livingston Site Fiber Optics Cable Installation F. Asiri
Press Here for the latest Contingency Needs Projection


LIGO Weekly Site Telecon (Jasnow)

A site telcon was held on Thursday, April 29, 1999.  The list of current actions assigned may be found at ACTION LIST.


PROPERTY MANAGEMENT (Chargois)

From: Ed Chargois <chargois_e@ligo.caltech.edu>

Assisted the Detector Group with the packaging and shipping of hardware to Allied Engineering (attn: Steve Jones), Alameda, Ca. Safe arrival and timely delivery confirmed. Account 5F511.

Assisted the Detector Group with transportation of two thousand lbs. of hardware being transported from Superior Jig Co., Anaheim, Ca. to Hytec Inc., Los Alamos MN.  Account 5F511.

Assisted the System Administrator with the shipment of two computers to the LIGO Livingston Observatory, attn: R. Riesen.  Account 5N511.

Received information from Caltech's  Insurance Carrier indicating that a check was issued to  McCurley Import  Tri-Cities for the property damage created by LIGO Boom Truck; please consider the matter resolved.


DOCUMENT CONTROL CENTER (Turner)

From: the DCC <dcc@ligo.caltech.edu>

DON'T FORGET:  New web pages for the DCC gives simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database.

 ACTIVITY HIGHLIGHTS

Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.


COST SCHEDULE CONTROL SYSTEMS (Duncan, Moore, Akutagawa, Kaufman)

From: Sarita Moore<moore_s@ligo.caltech.edu>

Press here for ACCOUNTS PAYABLE HISTORY DATA. [No report this week--jury duty -pel]

From: Kris Duncan <kris@ligo.caltech.edu>

From: Florence Kaufman <fkaufman@ligo.caltech.edu> From: Cindy Akutagawa <cindy@ligo.caltech.edu>

No report.


SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: irena@ligo.caltech.edu (Irena Petrac)

From: Ed Jasnow <jasnow@acrux.ligo.caltech.edu>

TECHNICAL CONFIGURATION MANAGEMENT (Althouse)

From: wea@acrux (William Althouse)

No report. See Bake out.


1.4.2.1 Quality Assurance (Tyler)

From: "William H. Tyler" <tyler_w@ligo.caltech.edu>

LIGO QA visited Walker & Sons in New Castle,OK to audit their fluoride extraction process and facility. The implementation of their extraction process is fairly simple and unsophisticated. They have developed and use process paperwork. I also was advised that they will submit to LIGO a process plan for the LIGO hardware (I just received this by fax). They also gave me a copy of their QA Plan for information. I advised them that they needed to make improvements in the ways they protect the hardware from the possibility of environmental contamination. Bob Walker agreed to make improvements in how they handle LIGO parts. They are also doing some experimentation with some Fluorel o-ring samples supplied by Rai Weiss to see if can detect any "effect" of the fluoride extraction process.

LIGO QA (Bob Vincent) participated with GNB to evaluate how gate seals (o-rings) were being measured to verify correct inside diameters. This investigation was prompted by the recent dimensional changes reported by GNB for two of the four Fluorel o-rings processed by Walker & Sons. Mr. Vincent also provided a "pi" tape as an alternate method of measuring o-ring diameters. The conclusion was that the existing GNB measuring methods were less "reliable" compared to the pi tape data. It was agreed that in the future, O-ring diameters will be measured by using the pi tape.

LIGO QA (Bob Vincent and Bill Tyler), witnessed the diameter and cross-section measurements of recently baked (by R. Weiss) Fluorel o-rings. Also witnessed the assembly of the stick test gate and seal plate. The heat up of this hardware was started late Wednesday, 28 April. The test is scheduled to end on the 6th of May when the chamber will be vented and the gate separated from the sealing plate to determine the amount of sticking and/or surface deposits from the o-rings. This effort will also be witnessed by LIGO personnel.
 


WBS 1.4.3    Systems Engineering / Data Analysis and Computing


 Systems Engineering

Modeling

(Hiro) (Biplab) (Ed)

Data Analysis - Software

Data Analysis - Hardware

General Computing

MIT:
Nothing to report.

Livingston:
(Tom Evans)
Received Matlab for both Unix and PC platforms.
Ordered Mathematica for the Unix system.
Providing support for computer access for the NSF review.
Working on getting color printer repaired/refurbished.

Hanford:
(Christine Patton)

Did the usual weekly backups, ordered some more backup tapes and
ethernet cables.  One of the student helpers has started re-organizing
the GCnet patch panel, which is always "a jumble of spaghetti".
Contacted HP about sending our Deskjet color printer in for repair.
Have three test user accounts working on the LHO modem pool for telnet
sessions only. Still working on setting up the security and other
login protocols.

CIT:

Barbara updated the web pages on the main LIGO server. Working on setting up web
access for the bakeout data.

Sean has finished building the replacement for canopus and should be making the
swap in the next few days. Worked on the sendmail configuration to address some
of the mail relay issues. Has also put in a script to rotate the log files on
the servers.

Suresh has changed the subnet access on a number of PC's to where they are now
on the new network. This was in result to a cable being broken in the ceiling on
the old subnet. He has also moved a number of computers around. Is working on
the migration of pollux to replace sirius. Worked on a couple of tape backup
issues.

A number of procurement issues have been addressed and currently working on
getting things set to send in machines as part of the trade-in purchases made
some time ago. We have a number of FORE items being purchased and tried to get
the maintenance contract set to where all of the items will on one contract.
Working on rearranging the computer room and getting some of the old dead
equipment removed.
Worked a number of modem issues as well as setting up a number of accounts. A
list of old accounts will be sent out for approval for removal.
Working on updating documentation of the server room and related equipment.
Received the cisco router to replacment and will be working on it next week.
 


WBS 1.4.4.1    Administrative Group


From: "Elizabeth K. Wood" <ewood@ligo.caltech.edu>

Came to Louisiana early to help Mark out with an outreach demonstration at
the North Shore Mall in Slidell.  The two administrative assistants
demonstrated sound waves and polarized light while the Ph.D. physicists
looked on proudly.

Helped Bonnie with the NSF site review.

Tried to locate subaccounts for Bonnie to attach to account numbers.  It
seems that yes, we need subaccounts, but no, we are not allowed to know
what the subaccount numbers are.  The release of subaccount numbers could
mean the end of the civilized world as we know it.  Our thanks to Phil
Lindquist and Joann of the PMA office in tracking down at least a few.
 

From: torres <torres@ligo.caltech.edu>

For M. Zydowicz/W. Tyler continued udates to the LIGO Safety Plan which was
orginally issued in 1996.  Forms and figures in the plan were originally
done in Frame while the rest was done in Word.  It took a couple of days to
convert (actually to redo) these sections in Word.
 

For L. Wallace/A. Lazzarini continued to gather pricing information from
companies offering pagers with email/voicemail capability.  Submitted my
report to Larry who will obtain finer details.
 

Got a chance to purge old email files.  Our recent server problems
apparently caused files to multiply because I found several copies of the
same message beginning in October/November.  Many messages appeared this
way causing the count (or memory) to read over 16,000.  I've reported this
to S. Singh.

From: Dorothy Lloyd <dot@ligo.caltech.edu>

Continued to process heavy load of invoices for payment, and tracked
and followed up on various invoice problems. Processed the usual heavy
load of POs, reqs, change orders, check request, etc. Entered AP30
reports into database.

Continue to monitor and support the temp.

From: Irene Baldon <baldon@ligo.caltech.edu>

Worked on preparing the paper work for various new trips taken recently (12
Purchase Requisitions and 7 Advance Requests).  There are 12 additional new
trips in various stages pending completion of travel arrangements.
 

Still receiving inquiries and requests for travel from LIGO/SURF participants.
At the moment I'm working on 1 from Caltech to Hanford, WA; 1 from Caltech to
Livingston, LA; 1 from Pisa, Italy, to Caltech; 1 from Missouri to Caltech; 1
from Shreveport, LA, to Caltech; 1 from Lyon-Satolas, France, to Caltech; 2
from Leicester, England, to Caltech; and 1 from Belgrade, Yugoslavia, to
Caltech, for a total 9 at the moment.  The student from Yugoslavia is becoming
a real challenge.  Additional students will be contacting me as we get closer
to the start date or they know the dates for their finals.  The SURF schedule
is from June 14th thru August 20th and many of LIGO's members are acting as
Mentors.
 

Completed 24 Expense Reports, some of which were extensive, involving 2 to 4
pages each.  Many of these reports were still not taped or completed by the
Traveler, and required additional time for completion.   Also worked on a
number of problem issues which required a good portion of my time.  Received
yesterday and late Tuesday, but not yet completed my audit, 13 Expense
Reports.  These should be completed today, tomorrow at the latest, barring
unexpected delays.  I'm holding 1 expense report which requires additional
information or is missing receipts from the traveler.
 

Worked on 4 Foreign Visitor trips which required extensively planning and
coordination as well as the paper work involved for each.  Three (3) are
completed and one is pending final determination of flights and dates.  Had two
travelers going to the NSF Meetings rerouted by the airlines due to bad weather
in Dallas.  Dealt with the changes and details involved.
 

Prepared Travel/Vacation Itinerary for the Week of April 27th, 1999.
 

Performed miscellaneous duties as requested by various members of  the LIGO
Project here at Caltech, as well as from members of the staffs of each of the
two (2) sites.
 
 


For additional information about this report, contact sanders@ligo.caltech.edu