Weekly Report for Week Ending January 26, 1999



 Project Control Meeting Agenda   Highlights   Hanford Observatory     Livingston Observatory     Detector    Project Office    System Engineering    Administrative    Past Weekly Reports

The Project Control Meeting Agenda for Monday  February 1, 1999 will be:
 (Meeting time: 10:30 am Pacific Time)

  1. Announcements (5 minutes)
  2. Review of Action Items (10 minutes)
  3. Comments on Weekly Report (5 minutes)
  4. Field Change Orders/Contingency Liens/Change Requests (10 minutes)
  5. Review of ISSUES AND PROBLEMS by Subsystem/Activity (10 minutes each)
Special Items:


Special Announcements:


Weekly Report Highlights in blue below
 


LIGO Hanford Observatory (LHO) Operations



 (F. Raab)
=========================================================

General Items:
--------------
(Fred Raab)

This week saw the successful re-balancing of MMT3 and scurrying to get alignment
fixturing whipped into shape. (Read that: "Don't expect a report from Doug Cook
today!)
(GHS note: Balancing did not succeed without removal of spacer rod. So regluing, baking is needed. Mark Barton and Helena have started. In the meantime, another MMT3 was installed in HAM7 today as a stand in to permit an alignment run through. Many lessons were learned in this exercise.)
We had a video crew out taping material for an educational video, called
"The Scientific Method at Work", whose purpose is to give kids an idea of how
science and math get applied in real-life science and engineering workplaces. We
should get some good video and graphics material for LIGO outreach from this
program. The demo Michelson interferometer put together by Rick Savage and
Russell, a student from Southridge high School, made a big hit with the video
crew.

Professors Braginsky and Mitrofanov are visiting LHO this week and were kind
enough to give an instructive seminar on their work at MSU. We hope that many of
our visitors will follow their example in future.

Facilities:
-----------
O. Matherny

New Construction: George Grant Construction Co. placed concrete for the building
floor slab. Two thirds is complete.
 

Water System modification: Apollo is 75% complete with the water modification
project. The 8000 gallon tank was delivered but not yet plumbed in. After
examination of the water tank we rejected the tank for cosmetic reasons. The
insulation was installed extremely sloppily, and the tank looks like it is made
from paper. The supplier is taking the tank back to the factory for re-work. This
will add a two week delay to the completion.

Compressors: We requested Sullair to give us a quote for replacing the 10
compressors with units that are compatible with our environment. The new
compressors are approximately $60K. We are in process of trying to get our money
back from Kaeser, since they guaranteed that we will never get any oil in our air
lines.
 

Seismic Isolation Installation:
-------------------------------
(C. Gray, H. Radkins)

Leveling and setting of elevation on HAM 7 Optics Table was done with the help of
Hugh's surveying skills and Larry Jones. This went well. We didn't install the
remaining 240 (of 500) lbs. (we did account for the loading of the springs with
this additional weight and set the elevation accordingly however). One concern
was raised about the w-adjustment (via Scissors Tables), and that was the concern
of uneven loading between the Vertical Stop Bolts and the jacks; will look into
ways of correcting this on next elevation adjustment.

Will receive Air Bearing next Tues (2/2); this will enable us to install Air
Bearings, install weights, fix cabling, and set elevation for the Optics Table for
a hand off for Recycling Mirror installation later that week.

The installation of out of vacuum BSC8 components was completed this week,
including the complete actuation stack and the crossbeam.  We continue to
complete the many small tasks as we gear up to in-vacuum installations ~2
weeks away.

The south door on BSC8 has been removed and preparations are underway with
MIT for the initial alignment of MMT3 and the RM.

Computing Systems:
------------------
(C. Patton)

The General Computing network is now accessible from the LVEA. I will be setting
up two P5-90 PCs for general use. I have also put out two 4 port hubs, which can
be used to plug other computers into the network. One hub is behind the vacuum VME
rack on the X arm, the other is behind the vacuum rack on the Y arm. If you do
plug a computer into the hub, be aware of others and safety considerations with
computer cables and power cords.

Beam-Tube Bake Out:
-------------------
(M. Lubinski, M. Guenther, and W. Althouse)

The RGA and calibration cart have been installed at X1-5, leak checked, and is
currently being baked. The Cryopump at X1-2 has been installed and leak checked.
Sun River has completed all blanket installation and check out at the mid and end
stations on X1 module. PUD (the local electric power company) has disconnected the transformers
on
Y1 arm and Sun River has moved them to the X2 module. We are going to test the DC
power supplies Thursday (1/28/99) to verify operation and control. We should be
ready to begin the bake out of X1 module next week.

 


LIGO Livingston Observatory (LLO) Operations



 

Preparation for beam tube bakeout (Cecil Franklin, Kerry Stiff): We have received the bid package from Caltech for the insulation work for the Beam Tube X &Y arms. Also an advertisement was placed in the Baton Rouge Advocate that will run for six days, stating all the details pertaining to the job. All local contractor packages will be mailed from the LLO Livingston Observatory site. All other Bid packages will be mailed from Caltech.   Beam Tube thermocouple installation has been completed on the X-1 Module and also on the Y-1 module. The X-2 and Y-2 modules are each approximately 60% completed.

Seismic Isolation Installation (Rich Riesen, Joe Giaime, Tom Evans): All HAM and BSC Pier layout is completed in the LVEA and both End Stations. 4 HAM's and 3 BSC's in the LVEA and 1 ea. BSC in the 2 end stations. Core drilling has begun for the BSC's in the LVEA (4 holes are completed on BSC#2). All HAM's (4ea.) anchor bolts (64 total) have been installed in the LVEA. High-Presser water w/detergent cleaning has begun on the grouting plates. HAM pier cleaning will start tommorow

Optics & Vacuum Labs: (Jonathan Kern): The Culligan RO/DI system remains erratic. Culligan installed a new circulating pump which allows the system to
remain on all the time, however water quality has suffered. The best we are doing right now is 10 mega-ohm water. Some stainless components in a flow meter are suspect.
Our second 4x10' optical table has been placed in the lab. We've decided to hire a local cabinet shop to repair the shipping damage to the flow benches, at Air-Tech's expense. About 1/2 of the optics hardware has been received from Opto-Sigma. The PSL safety enclosure (in plant office) has yet to be ordered;still waiting for final comments from interested parties.

Electrical installation (Juilien Svoboda): LVEA network: Ropes, Cat 5 cables, fish line and electrical tapes have been bought for the cable installation in LVEA area. It's scheduled to start today with Tom Evans' help. I hope that we can finish this project in 2 days.
Fiber Optic cable installation: The contractor for intallation of the fiber optic cables has finished installing more than half of the jacketing of the fiber cables in the BTEs. He is trying to increase the number of the workers to finish this job earlier. I estimate that this will take another two weeks to finish. When this is completed, Rolf and I will do the final testing together with MCA.
EE lab: I am organizing the documents for the electronics instruments in the EE lab and putting electronics parts away in a neat manner. This is going to be an on-going project next week. I am still having trouble with the shelves we bought from Equipto. Side and back panels have minor damage due to shipping. I am trying to talk to the
vendor to see how we can resolve this problem.
VME test stand: Rolf generously let me use the CDS group's spare 19" rack and VME crate for our test stand in the EE lab. This will save us money and time in the process. I have installed the test stand in the lab. The software interface and a VME CPU processor board will be needed. Currently I am borrowing CDS's SUN station and a CPU card to start the initial test.

Anthony Rizzi: The end-to-end model software has been put on a Sun and preliminary installation tests were successful.A Sun station to be used for learning the CDS system and for exploring system feedback issues has been set up in the room across from the Control room. I am in the process of identifying VME hardware that will be needed. Jay Heefner is investigating the status of the EPICs license at Livingston. I will give the colloqium at LSU on Thursday on the
angular momentum work in general relativity.

The PEM cart computer can now access the Local Area Network but still cannot be accessed by other LAN members.Tech Master has been asked
to look at this problem; they have investigated the problem and are still in process of troubleshooting.

Facilities issues (Gerry Stapfer): The manufacturer representative for the expansion joint was onsite to check what kind of fix to recommend to Hensel Phelps. HP will then make a recommendation to LIGO regarding how to proceed. Bernard (the mechanical contractor) is continuing to work on the punch list and as part of that we found that the damper valves in the return ducts in the LVEA are either defective or need readjustment. We have contacted Siemens to address this problem - they will be here next week. We were informed by the sewage maintenance company that unknown persons dumped a load of grease into our sewage treatment plant. The Livingston Sheriff's office was informed and a report was filed. We requested a cost estimate from Sicord Inc. to fix the bullet holes in the west end station wall panels. The proposed method is the same as that used by HPC - to put a sheet of matching material over the damaged panel.


WBS 1.2, 1.3    Detector Group


 
----------------------------------------------------
DETECTOR GROUP -- Whitcomb/Shoemaker

40 m Interferometer (Nergis Mavalvala)
---------------------------------------

40m Interferometer

The 40m is vented for mirror cleaning and installation of a
variable attenuator in the recycling mirror. Three of four
test masses were cleaned using a CO2 snow gun. On the south
end there was visible dust/dirt that was cleaned up by the
CO2. On the south vertex mirror significant scattered light
from a HeNe illuminating beam was not improved by repeated
cleaning. The east vertex HR surface is difficult to examine
but we believe some visible dust was removed by the CO2.

We plan to complete east end mirror cleaning and installation
of the variable attenuator in time for a Friday midday pumpdown.
Many thanks to Jim M, Phil W, Steve B, Daqun L, Shanti R, Eric B
and all other volunteers who have helped with the vent this week.
 

----------------------------------------------
Interferometer Sensing and Control -- M Zucker
(WBS 1.2.1.1.6, 1.2.1.1.7)
----------------------------------------------
 

Interferometer sense/control (Zucker)
-------------------------------------
[1/28 report]
------------------------------------
Fab-delivery status:
-----------------------
MMT3 optical lever  installed
RM optical lever    waiting for wedges at LHO, shipped 1/18
IOT7         on site
ISCT7,9,10 (Wa2k)   to be assembled on site starting mid-Feb
 

ISC implementation (Fritschel)
--------------------------------------
o Ed and Peter discussed with Jay and Lori the near term program for
ISC code development. We are working toward a combined test of parts
of the supervisory controls and the ASC front end servo code in
mid-February at Caltech. Specific components we intend to have ready
for the test are: the DDCU (digital data collection unit) code which
communicates with the DAQ system and moves DAQ and diagnostic data
to&from the front end servo code; the EPICS code and control screens
for control & monitor of the ASC system. Lori will provide the
complete ASC front end servo code (polishing up what she has already
done).

o Began procurement of equipment we will need at the sites for
assembly of future ISC tables.
 

ISC implementation (Nergis Mavalvala)
--------------------------------------
WIOT7 status:
*  beam alignment checked for both beam lines
*  both periscopes installed
*  mechanical shutters in place
*  all optics bolted down, i.e. IOT7 ready to pivot

MC alignment WFS heads could not be tuned and will be done
during next visit to Hanford.
 

ISC supervisory controls (Daw)
------------------------------
This week Peter and I figured out a list of data acquisition
channels for the ASC and LSC digital data collection units (ddcus).
Rolf is now ( or has already ) inserted the correct channel names
and rates into the Hanford data acquisition system configuration
manager. I will update my ddcu code at Hanford to collect the
relevant data.

ISC fab (Smith)
---------------------------------
The table, legs and support piers for the optical levers to the input
test masses were ordered.  I changed the optical enclosure drawing to
include holes for the support of the acoustical blankets.  The blankets
were ordered(1 set) and should be at Hanford in two weeks.  The wedge
supports for the optical levers for the recycling mirror has not
arrived yet.  They were shipped Monday, Jan 18.
 

IAS Initial Alignment  (K.Mason, M. McInnis)
----------------------------------------------
Installed mmt3 support, laser, and photodiode outside of Wham7 at
Hanford. A chart recorder is being hooked up to monitor the orientation
of mmt3.

Two additional monuments have been placed along the Y-arm to align mmt3
and the recycling mirror through the door in BSC8.  The alignment
equipment is being set up to align mmt3 which is expected to be
available friday morning.
 

[1/21 report]
------------------------------------

Interferometer sense/control (Zucker)
---------------------------------------
Announcement: We are sorry to say that Brent Ware has announced he
will be leaving LIGO shortly.  We thank him for his outstanding
contributions to ISC lock acquisition simulation and design, and look
forward with confidence to implementing them in the real world. Good
luck in your future endeavors Brent!

ISC implementation (Nergis Mavalvala)
--------------------------------------
Documentation and parts for installation of WIOT7 received and
alignment checkout is underway.

WFS Guoy phase telescope (GPT) design for 2km antisymmetric port
sensor completed, accounting for COS beam reducing telescope. Since
the beam from the 8X reducing telescope is a quite large (~4 mm
radius) the GPT design needed a trade off between compactness of
the GPT and sensitivity to error in the lens separation.

ISC initial alignment (Smith, McInnes, Mason)
---------------------------------------------
Design for ISCT7 completed and reviewed;
procurements for ISCT7 assembly nearly completed (most
components already laid in, a few short-leads left to get).

Preparations for alignment of MMT3 are underway.  Updates
to MMT3 optical lever assembly are on their way to Hanford to
address punch list developed by M. Zucker last week.  The
laser autocollimator was returned to MIT for evaluation of
the theodolite mount.  It looks like a revised assembly
procedure will take care of the problems found last week.

IOT7 components and documentation are in hand at Hanford
to complete Nergis' alignment verification and final
installation.

ISC controls (P. Fritschel, E. Daw)
------------------------------------
o More setup of the EPICS environment on our development system so that
it now compiles and loads C code correctly

o Iterated on the layout of ISCT7, the reflection port table.

o Reviewed UFl's test plan for the Input Optics, and began working on that
part of the plan involving the mode cleaner.
 

-------------------------------------------
Lasers and Optics -- J. Camp
(1.2.1.1.2, 1.2.1.1.3, 1.2.1.1.4,1.2.1.1.5)
--------------------------------------------

Prestabilized Laser -- Peter King
--------------------------------------------

- The pieces for the reference cavity vibration isolation stacks have been
delivered.

- The first article form fit heater jacket for the reference cavity vacuum
chamber has arrived.  The jacket fits snugly around the vacuum chamber and
comes in two halves.  Each half is fastened by Velcro.  Each heater has a
resistance of 50 ohms.  The new heaters should provide a more even heating
of the chamber than the heater used on the PSL in the Lauritsen lab.

- A 21.5 MHz rf photodetector has been completed for the LLO 4k IFO PSL.

- The LHO 2k IFO PSL was shutdown on Monday to facilitate a modification to
the IOO/PSL optical table enclosure.  The PSL was operational for a period
of 39 days.
 

Input/Output Optics -- Dave Reitze, UF
-----------------------------------------

Installation -

David Tanner is at LHO from the 27th til the 30th. We have reglued the
magnet on the side of the mode cleaner curved mirror. During this we
noticed that the magnets on the side of the mirrors are strongly affected
by the fields from the magnets on the faces. For example, it is not
possible to balance the side magnet on the mirror (oriented on its edge,
with the face vertical). The fields from the front magnets cause the
magnet/dumbell to fall over and fall off.

MMT2 has been measured to hav ea radius of curvature of 2.0985 m (spec is
2.1000 m). MMT1 and MCCM are yet to be measured.

The Faraday rotator has been properly aligned and oriented.

The periscope height on the PSL table has been adjusted for proper
injection into the vacuum.

The beam tube connecting the PSL and HAM?7 has been installed.

Qi-Ze is coordinating with Sany and Malik in an effort to fine tune the
mode matching to the mode cleaner. The beam profile after the EOMs have
been measured at 150 mW and 7.2 W and Gaussian beam parameters obtained
show the expected thermal effects.
 

Core Optics Procurement and Metrology -- GariLynn Billingsley
-------------------------------------------------------------

2ITM01 has been measured and a brief survey of all of the 2KITMs has been
completed.  Our next objective is to show that good data can be obtained on
a Folding Mirror at 0 degrees, where data are much more repeatable.  To
show this we will compare data taken at 45 degrees with data taken at 0
degrees.  We intend to ship a 2KITM and a FM to Hanford by February 8th.

Rai Weiss has been with us and shown two resonances which effect our
measurement.  One is vibrational at roughly 24Hz, the other is acoustic at
roughly 108Hz.  We have acoustic, vibrational ground and table spectra and
thermal gradient measurements which characterize a "good" measurement day
in the Metrology lab, this gives us a figure of merit for evaluating new
locations for the Metrology lab.  A busy machine shop is moving in beneath
the current lab within the next 3 months, we anticipate the quality of data
to degrade significantly when this happens.
 

Core Optics Coatings -- Helena Armandula
--------------------------------------------------

(Helena is at the Hanford site, cleaning and suspending MMT3.)
 

Core Optics Support -- Michael Smith
------------------------------------

BEAM-DUMPS
Mark B. and Mike S. completed measurements of the principal resonant
frequencies and Q's of the double cavity beam dump. The frequencies lie
within the range 30 to 200 Hz as expected, and are acceptable. One of the
lowest frequencies will be increased by strengthening the lateral walls of
the beam dump. Craig C. is creating elevation and plan view layouts of all
the cavity beam dumps in the BSC chambers, prior to completing the drawings
of the horizontal and vertical mounting support structures.

PO TELESCOPE
All the parts for the PO telescope are being fabricated.

PO MIRROR
Modifications to the flexure design have been completed by Ken M. He is
modifying the vertical support structure to avoid interference with  the
LOS structures on the SEI platforms.

BEAM STEERING MIRROR and PERISCOPE
All of the beam steering mirrors for the output beams of the PO telescopes
have been received, as well as the posts, mirror clamps, and bases for the
periscopes. The mirror clamps are being modified to adapt to the standard
mirror holders.

VACUUM WINDOW
Experimental conflats and windows are being fabricated by Varian.

NEW CONICAL BAFFLE at MID STATION
Design is pending.

TRIPLE FLEXURE BRACKET for BEAM DUMP
Mike S. is studying the design requirements.

ELLIPTICAL BAFFLE/BEAM DUMP
A purchase order will be issued for production parts shortly.

IO BAFFLE, 2K
The parts for the IO baffle are scheduled to be baked and ready for
assembly on 2/1/99. Mike S., Betsy W., Jonathan K. , and Hugh Radkins will
asemble and align the baffle during the week of 2/1/99.  Paul K. has almost
completed  the released documentation package.

ITM BAFFLE
Angel and Mike S. have almost completed the redesign of the ITMx baffle. A
modification is required for the ITMy baffle, because the baffle must tilt
in the opposite direction.

INSTRUMENTATION BEAM
The ITM baffle and the ETM baffle have a 3.25 inch diameter hole which will
provide a clear line of sight down the entire length of the 4K beam tube.

INSTALLATION PLAN
item                               completion date     bake @ LHO   install
date
Mode cleaner baffle                 12/30/98       NA           ?
IO baffle                           1/11/99         1/28/99      2/1/99
 

--------------------------
Isolation Group -- M. Fine
--------------------------

Seismic Design (Mike Fine)
--------------------------------------
1. Electronics Rack:
The assembly of the rack hardware will be complete by the end of the 1st week
of February. Packaging modifications to the original design are being made
to improve the layout and maintenance of the rack. In addition new hardware
to remotely turn-on and off the amplifiers is being integrated into the rack.
Two additional items not in the prototype are the cable connector panel and
the multiplexing for three BSCs. These changes/additions have slowed
progress temporarily. Hytec will begin assembly of the second rack shortly
after the first has been shipped.

2. Coarse Actuator Components
MSI told Hytec that the actuator components from Daedal (Coarse Actuators)
have a 4-6 week lead-time from last Monday. This is 2 to 3 weeks longer than
earlier quotes.  Hytec since asked for partial shipment and will now receive
8 actuator sets on 2/19. They will then assemble the actuators onto the scissor
tables and ship them to LHO on 2/23.

3. Near-Term SEI Hardware Delivery Schedule:
1 set of BSC in-vacuo hardware (Handord)                   2/4/99
1 HAM optical table                                        2/4/99
5 HAM leg elements                                         2/4/99
1 actuator rack (Hanford)                                  2/15/98

Suspension -- (Janeen Hazel/Mark Barton/Mike Fine)
-------------------------------------------------------------------
1. SUS Installation:
Helena Armandula and Mark Barton are cleaning the MMT3,2k and the RM,2k at
Hanford. MMT3 has been sucessfully cleaned and Mark is starting to rehang it.
(GHS note: This operation will have to be repeated due to balancing problems (see LHO report)
They are using the traditional soaking-in-warm-Liquinox method of cleaning.

2. LOS Structure:
Brookfield has sent the reworked RM structure. It will be cleaned and prepared
to go into oven on Friday night or Saturday morning. It can be at Hanford on
next Thursday or Friday.

3. SUS Hardware Delivery:
SUS Structure Delivery Dates: [numbers in parentheses are quantities.]
LOS1(for ETM, ITM, MMT): 1/29(2), 2/5(2), 2/12(2), 2/19(2),
                         2/26(1)
LOS2(for BS): 1st artcle on 2/15(2), 2/28(1)
LOS3(for FM): 2/12(2)*, 2/28(1)

*new dates
 

---------------------------------------------------------
Detector Systems Engineering -- D. Shoemaker/D Coyne
(WBS 1.2.1.1.9)
---------------------------------------------------------
 

Global Diagnostics System  (Daniel Sigg, John Zweizig)
------------------------------------------------------

John Zweizig

I continued to develop the software interfaces for algorithms to be
developed by the LSC and others, sketched useful data types, discussed
with Walid where defined data types are needed and how they should be
implemented.

I continued discussion of the data types are needed for online analysis and
how they should be implemented.

I started work on defining and implementing the trigger reporting software.
I have started to create trigger data classes that are in line with the
database tables being designed by Xiao. These will be used in the monitor
programs to describe triggers and to send them to the Trigger Broker. I am
also starting the design of the Trigger Broker.

Discussed hardware and software overlap with other GDS LDAS and CDS
group members.

An overview of the Data Monitor Tool project and a brief description of its
current status are available on the web at:

     http://www.ligo.caltech.edu/~jzweizig/DMT-Project.html.

I try to keep these as up-to-date as possible.

Daniel Sigg

Received the sine detection (i.e. swept sine analysis) routine from
Peter F.

Continued in writing the command line interface to the diagnostics.
Did the modules for controlling digital test points and using the arbitrary
waveform generator.

Integrated some 'old' driver code written by Mark P. which controls
a DS340 signal generator remotely into the arbitrary waveform generator/
command line interface to provide a common interface.
 

Physics Environmental Monitor(Matt Smith, David Shoemaker & Alex Marin)
-----------------------------------------------------------------------

    1. The delivery schedule is posted at :

       http://web.mit.edu/marin/www/PEM_Delivery.html

    2. LHO: Most of the PEM equipment is already shipped. This week
the PEM team tested the installation procedure for the seismometers,
tiltmeters, interface plates with accelerometers and PZT shakers. The PEM cart
DAQ was used. We performed studies on the tiltmeter long time stability,
response of the seismometer and tiltmeters to the ground noise, correlated
response of various combinations of signals from two tiltmeters or
tiltmeter seismometer combination. The results will be used for the final
installation configuration procedure. In particular, the tiltmeters will
be mounted on polished granite plates.
    Interface plates, accelerometers and PZT shakers were mounted on
HAM 9. Again we performed studies on the performance of the PZT shakers.
Preliminary results indicate that they are adequate for the DC-200Hz
interval, as indicated by the manufacturer.
    As we write this report, more tests are in progress: correlation
between barometric pressure and tilts, the excitation magnetic coils
performance.

    3. LLO: the DAQ cart was assembled and now is tested by Rizzi. Seismic
measurements are under way (Mark).
 

Optical Contamination (Daqun Li)
--------------------------------

One week data monitoring of air baked steel did not show an increase
in losses (either total loss or absorption loss). A few more weeks is
needed to complete this testing.

The automation code rewritting last week for the Loss Scanner turned
out to shorten the scanning duration by a factor of 3 with a scanning
stepsize of 0.4 mm. With this achievement, scanning a large surface
area of core optics can be completed within a full day.

Enjoyed a first working day at the 40m lab by helping the 40m vent-
cleaning task currently being conducted at the 40m.
 
 

-----------------------------------------
Control and Data System -- R. Bork
(WBS 1.2.2)
-------------------------------------------

Data Acquistion System
======================
Hanford:
  - Basic components are on hand to start up the system. About 1-2 weeks work
are needed to run the system on a near full time basis:
    - Rack 2X3 (2k primary timing and suspension acq.) is complete, but 2X5
(PEM/PSL/IO) rack still requires signal cable connections. Seismometer and PSL
signal connects should be complete by end next week.
    - Mid and end station VME acquisition units will be assembled over the
course of the next 4-6 weeks.
    - Due to the SUN PCI bus bug, we have to reorder the data on the
reflected memory to meet the 16Hz update requirment on the frameBuilder and
Network Data Server. This required a software change and a private reflected
memory net to the Sun. The VME side of the software is complete, with Sun side
to be completed early next week. Initial tests indicate this limits total
system
thruput (from ADC readout to disk write) to 8MByte/sec/reflected memory net.
    - The GEO Triana  and LIGO dataviewer and network data server software
packages are installed and operational. The data conversion software (allows
users to specify channels of interest and have them written to separate files
with various formats) should be ready for first release late next week.
 
Livingston:
  - Began equipment procurement process, with requisitions placed this week
for:
    - SUN450 server
    - VME processors
    - ADC modules
  Equipment should start arriving in 4-6 weeks.
 
Control Area & Networking
=========================
Livingston:
   - Fiber optics still being installed (est. two more weeks).
   - PO placed for five Sun Ultra60 workstations to be used as operator
consoles.
 
Input Optics
===================================
- 90% of the cables required for operation of the WA 2K IO controls are
installed and terminated.
- Cross connect wiring for controls is 90% complete.
- Database records, state notation code and operator screens for control of IO
components will be complete by 2/15.
- We will be testing IO controls functions starting 2/15 and should be
ready for
locking of the mode cleaner starting 3/1.

Suspension
===================================
- Cable pull lists for 2K LVEA core optics suspensions have been sent to
Hanford. Cables should be pulled and terminated by 2/15.
- System testing for these systems will begin 2/15.
- 7 LOS controllers and satellite amplifiers are being wired and tested for
installation starting 2/15.

ASC and LSC Controls
==================================
- A test of the ASC front end and back end code has been scheduled for
2/22. The
test will be conducted at Caltech.

PSL
======
1.  Received the final version of the PSL frequency reference cards.
Boards are in the process of being stuffed.
2.  Final version 80 MHz VCO boards are in the layout stage and will go to
the board house in several days.
3.  Received the fabricated heaters for the PSL reference cavity and they
work and look fine.  They are completely removable by a velcro fastening
system.
4.  Reference cavity that was shipped to the east coast for fitting of
insulation jacket will be shipped back on Friday 29 Jan.
5.  Last board to be fabricated for the PSL is a frequency summing board
for the summation of the PMC modulation sidebands into the FSS pockels
cell.  This board will be fabricated in house on the mill.

MC LSC:
=============
Most of the LSC Mode Cleaner hardware is installed in 2X8 at Hanford and
most of the cables are run. This should be completed during my next trip
which will probably be the week of February 15th. The MC Servo Amp should
be completed and tested and ready to install that week. I am building some
RF amplifiers for the modulation drivers. Parts have been ordered for the
RF and LO distribution.

Timing System:
=============
Two Timing boards are operational at Hanford. We have successfully
characterized the ICS 110B ADC boards so that we know how to talk to
synchronize them with GPS. We are now implementing the changes to the
design and will produce the final version as quickly as we can. It should
be ready to test by the beginning of March. We are adding a Ramp Circuit
that is synchronized to the GPS 1PPS signal. By sampling the ramp output at
16 KHz and extrapolating to " T ZERO " we can check the system
synchronization to a precision much better than a 16KHz period.
 


WBS 1.4    Project Office



 

 1.4.1.2 Project Controls (Lindquist)


Reports, Proposals, Work Plans (Lindquist)

A final DRAFT of the Annual Report for FY 1999 (ending November 1998) may be found at
http://www.ligo.caltech.edu/~phil/Distribution/november.pdf
All comments are welcome.

Change Control (Lindquist)

The following change request has been submitted:
 

CR-990001 WBS 1.3 Return Unused Budget for Construction Related R&D to Contingency P. Lindquist


LIGO Weekly Site Telecon (Jasnow)

The last Site Telecon was held Thursday, January 14, 1999. The open action list is as follows:
 
Action No. Description Responsibility Assigned Date Due Date
17 Louisiana Road Access M. Coles/G. Stapfer October 8, 1998 January 28, 1999
19 Consider Lawsuit Against Panel Manufacturer at Livingston R. Pool/E. Jasnow October 15, 1998 January 28, 1999
21 Letterhead and Business Cards for Sites F. Raab/M. Coles November 5, 1998 February 18, 1999
25 Check on Overhead for B&O Taxes E. Jasnow January 14, 1999 CLOSED
26 Provide Detail on Amount Contained in Equipment Line in FY 1999 Budget F. Raab/M. Coles January 14, 1999 CLOSED
27 Acquire Design for Site Signs P. Lindquist/E. Jasnow January 28, 1999 April 15, 1999
28 Requirements for Site Dedication Support M. Coles/F. Raab January 28, 1999 November 4, 1999

PROPERTY MANAGEMENT (Chargois)

>From: Ed Chargois <chargois_e@ligo.caltech.edu>

Assisted the Optics Engineer with the Packaging and Shipping of Series 150 wired instrument (NIB BIN) w/Model 200 Power Supply Serial No. 891024  to Mechtronics Nuclear at Melrose Park, IL for repair. Acct # 5B511.

Provided the LIGO Livingston Observatory with Updated Vehicle Insurance Certificates required by DMV for registration purposes.

Confirmation received from Livingston Observatory Manager indicating the receipt of Equipment ($87,605.42) from the Helium Operation located in Amarillo, TX. on January 28, 1999..

Preparing a Standard Form (SF 122) to the National Science Foundation to acquire a Variable Reach Forklift  Federal Stock Number 3930-01-158-0849 valued at $721,370.00 from the Defense Reutilization Material Office (DRMO)  Barstow CA to be delivered to the LIGO Livingston Site during the week of February 1, 1999.


DOCUMENT CONTROL CENTER (Turner)

>From: the DCC <dcc@ligo.caltech.edu>

STATISTICS


COST SCHEDULE CONTROL SYSTEMS (Duncan, Rianda, Leonhardt, Akutagawa, Kaufman)

>From: Cindy Akutagawa <cindy@acrux.ligo.caltech.edu>

I have been working on understanding/correcting the CIT status report actuals problem that has been in effect since the November 1998 reports
were issued. [There seem to be some unsubstantiated and one sided journal entries that Cindy and Florence are tracking down. -pel]

I have been working on the MIT invoices for the months of September, October and November, and have received the twonk for December 1998. I am updating the LIGO Signature Authorization List, inserting the new account numbers, including columns for 'Closed' account numbers.

>From: "Britt Leonhardt (T)" <brittl@FINANCE.caltech.edu>

This week has been abnormally busy, with Dorothy back, the invoices are flooding in.  I am processing these as quickly as possible.  There have been several contracts which have needed the attention of myself, Phyllis and Florence.  I have also been in contact with Price Waterhouse for Auditing purposes and have supplied them with the necessary information.
 
WE Date Incoming Invoices and Receivers Wire Transfers Large Contract Invoices New Purchase Orders
11/5/98 141 2 20 41
11/12/98 132 1 11 63
11/19/98 118 2 8 14
11/25/98 61 1 4 4
12/3/98 186 2 15 102
12/10/98 175 0 6 90
12/17/98 125 0 12 28
12/29/98 
(two weeks)
164 0 21 3
1/7/99 75 2 10 66
1/14/99 161 0 32 27
1/21/99 199 1 22 60

>From: Kris Duncan <kris@ligo.caltech.edu>

Completed and distributed the December 1998 LIGO cost/schedule report. Began preparing presentation materials for the Project Control meeting on Monday, February 1.  Initiated work on the reports for the monthly NSF report.   Continued working on reconciling the LIGO actual costs with CIT financial reports.

Initiated a replan of work packages 5N513 and 5N514.Began analysis and incorporation of Change Request's 980048 through 980050 into the January 1999 Performance Measurement Baseline. Continued work on the reconciliation of contingency in the COBRA reporting system vs. the LIGO Project Change Request Log.

>From: Florence Kaufman <fkaufman@ligo.caltech.edu>


SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

>From: irena@ligo.caltech.edu (Irena Petrac)

>From: Ed Jasnow <jasnow@acrux.ligo.caltech.edu>

Modifications were issued to both Benton County PUD and DEMCO for the purpose of providing electrical power for the coming year both for the sites and for the beam tube bakeout.

A modification was issued to the Apollo Sheet Metal contract to cover effort expended to support detector installation.

A modification was issued to Yakima Industries, exercising one of the one-year options under which they will continue removing tumbleweeds from
the Hanford site.

PSI has submitted a list of equipment which they are offering for sale to LIGO.  This is equipment remaining at the end of the vacuum equipment contract.  This list is being circulated among the LIGO  staff to see if anyone wants anything on the list.

Work has begun to search for designers and implementers for new signs to be erected in the front of both sites.  It is hoped to establish a competition among three firms, with a committee selecting the best submittals for implementation.


TECHNICAL CONFIGURATION MANAGEMENT (Althouse)

>From: wea@acrux (William Althouse)

No report. See Bake out.


1.4.2.1 Quality Assurance (Tyler)

>From: "William H. Tyler" <tyler_w@ligo.caltech.edu>

LIGO QA has now obtained four different Fluorel o-ring samples for evaluation/testing by R. Weiss. They are expected to be at MIT early next week. Quotes for buying a quantity of extruded Fluorel cord along with a limited set of test o-rings are still pending. Vendors have given us verbal cost estimates for this option which does not appear to be very expensive.

GNB has indicated that they expect to submit their bid by the end of this week (this is for the hands-on gate valve disassmbly/reassembly and change out of the gate o-rings).

Continued to work with L. Turner, R. Torres and B. Kratochwill to get all the available Hanford operational procedures on-line. Also, assisting M. Zydowicz with mark up revision of the new Operations Safety Manual.
 


WBS 1.4.3    Systems Engineering / Data Analysis and Computing



 
 
1.4.3 System Engineering / Data Anlysis and Computing

* Simulation

= Adlib multi mode implementation

"rec_sum", the module to be used for performing fast
simulation of LIGO is cleaned-up, wavefront characteristics
at various ports tested. New data type "clamp" that carries
mechanical information (position, pitch etc.) to mirrors has
been implemented in this module. Self-validation for single-mode
or multi-mode (but without swinging mirrors) and validations by
comparing with Twiddle are complete. The single-mode results
just matches with Twiddle outputs at all ports. Validation
with Ray Beausoleil's code for swinging mirrors is to be
started soon.
functions used by "lens" module have been rearranged in a
more software-efficient way.

The multi-mode version of the detector and telescope are being
contructed now. It will include the shotnoise effect.

documents are being rearranged and updated.

= Alfi GUI

Removed .prm and .xbm files from Alfi and moved them to Adlib and
AdlibMM

Release Alfi 3.1.13
   Bugs Fixed:
     1) Alfi no longer consumes enormous amounts of cpu time when
        performing minor tasks.
     2) Bringing up the the popup menu from the edit canvas no longer
        causes a system crash.
     3) When viewing the internals of a box, the contents are immediately
        displayed.

   New Features:
     1) Tool tips for boxes and ports now appear above the box or port
        they are describing.
     2) To move all the components on the screen, hold down the control
        key and right mouse button while dragging the mouse. Releasing the
        mouse button will set the placement of the components.

= e2e support outside of CIT

  The binary programs of e2e have been copied to Livingston site computer
  and the computer environments are set so that the programs can be used.

  The latest version of the source code is copied to UFL.

= TAMA

  Helped TAMA to use FFT. They expressed a possibility to send a student
  to Caltech for a week or so.
 

* LIGO Dana Analysis and Acquisition

= Lazzarini met with Bernard Schutz(GEO600) to discuss the possibility of
  sharing GEO data with LIGO as part of a reciprocity agreement within the
  LIGO-GEO MOU.

= Walid Majid
  I defined a number of classes intended to be used for an algorithm
  library. The definition consisted of identifying the data members as
  well as a number of useful methods or functions.

  I compiled the latest release of ROOT v2.20/06 on our machines and
  installed an interface with Fcl and Vega packages.  If anyone is
  interested in running ROOT with our framed data, I can help.

= Xiao Hu
  XHU worked on frame database queries
  XHU worked on GDS tables and queries
  XHU worked on LDAS LOG tables

= David Farnham
  DWF met with Kent Blackburn and Abert Lazzarini to discuss design and
  implementation of FrameCPP library.

  DWF designed class heirarchy and public interface for FrameCPP library.

  DWF met with John Zweizig to discuss library use and changes.

  DWF continued coding for FrameCPP library.  The library is approx. 75%
  complete.

= Philip Ehrens
  PSE nearly finished the managerAPI.tcl
 
  PSE is studying models of non-blocking I/O in Tcl to develop and I/O
  class for general use throughout the LDAS.
 

* Computing

= MIT:
Nothing to report.

= Livingston:
Received three Sun Ultra 10 CPUs and three monitors, but two of the monitors
were damaged in shipment and have been returned.
 

= Hanford:
Installed the GC network into the LVEA X arm so the bakeout crew can use
elog.  The GC network is already installed on the LVEA Y arm.  The two
P5-90 PCs sent up from Caltech will be set-up in the LVEA for general
purpose use.

Started going over LDAS connections and layout with Larry W. along with some of
the security procedures.

= CIT:

Barbara K. finished changes to the DCC web application for document searching.
Added two more fields for both author and keyword searching to be used in lieu
of the pull-down menus.  The pull-downs aren't usable on unix workstations
because they are too long.  Reviewed changes to both web applications with
Linda Turner and incorporated her suggestions.  Help page for searching
still needs to be updated.  Then both applications are ready to be
installed once Antares is ready.  Antares is to be moved to D. Beckett's
old workspace and then the software has to be reloaded to fix a problem
drive letters.

Wrote a query and form for DCC to use to repair the keyword table.  Also
devised a query for searching for 2 keywords assigned to the same document.
Began working on Y2K changes for DCC database.

Made several quick web site changes.  Reviewed the sample web page for the
as-built drawings with Fred Asiri and incorporated his suggestions.

Samantha has finished installing the scanner for GC usage. We now have a scanner
and CD-burner that can be used by all on LIGO.
Working on the replacement of multiple pc's.

Suresh is working on the monthly full backups of the LIGO servers (sirius, ligo,
gsparc, kater, spica). Resolved a number of PC related issues. Working with the
rest of the group on the installation of the new Ultra 10 units that have
finally arrived. One of the units will be replacing the old (acrux) mail server.

Sean is still working some modem issues as well as working on the configuration
for using qmail to replace sendmail for mail services on acrux and ligo.

A number of software issues are being worked on. Just as a note the student
version of Mathematica is not valid for use by non-students and the site
licenses of other packages we are using are good only for computers on the main
campus of Caltech.

A number of computers have been relocated to accommodate staff changes and
visitors. A number of new computer orders are in process to upgrade obsolete
systems.
 


WBS 1.4.4.1    Administrative Group


 Dorothy Lloyd

 Returned to work on Monday, Jan 25, after being away for five weeks, to an extremely heavy load of paperwork with problems needing to be resolved (new account codes, invoicing, purchase orders, funding supplements for contracts, etc.). Processed enormous stack of invoices and receivers for payment (see Cost Schedule Control Systems report submitted by Britt Leonhardt for further details). Continued to monitor and support the temporary help, who did a great job in my absence.

 
Rita Torres

 For I. Petrac did change order No. 1 to SORL, Space Optics, change order No. 5 to General Optics, and letter to Hytec, Inc.

 For E. Jasnow helped prepare IFB EJ-309 for Furnishing and Installation of BT Insulation at Livingston, FedExed 20 bound copies to be furnished to bidders by the site. For P. Lindquist reorganized reports in the binders in his office.

 With W. Tyler and L. Turner, determined status of safety procedures. Coordinated with the DCC to obtain electronic versions, or have site deposit them there. Spent most of Wednesday updating the document list to reflect status, distributed list; obtained hard copies of documents missing from my office.

 Distributed: PC289817 with ASCO Engineering, Inc., and PC290156 with Conejo Industries, Inc., also Distributed 84 sets of science articles to the science group.

 

 Irene Baldon

 PLEASE NOTE: As of today I have no backlog. All Expense Reports turned in have been completed and are in the hands of Travel Audit or out for signature and/or signature approval. My backlog remains ZERO.

 Worked on the paper work for various new trips taken recently (7 Purchase Requisitions and 9 Advance Requests). There are 12 additional new trips pending completion of travel arrangements. Completed 13 Expense Reports, some of these were still not taped or completed by the Traveler. As a result of the push a couple of weeks ago to clear my backlog, I have had extensive recording and filing to do this week.

 Prepared Travel/Vacation Itinerary for the Week of January 25th, 1999.

 Performed miscellaneous duties as requested by various members of the LIGO Project here at Caltech, as well as for members of the staffs of each of the two (2) sites.

 

 Elizabeth K. Wood

 A reminder: If the information about you in the new Caltech phone book is incorrect or if you want any changes, please let me know.

 Kept in contact with the phone office to find out about moving phones. The phone office has been in disarray due to moving themselves from one building to another. I don’t have an exact date yet when various phone will be moved; I’ll keep the affected parties notified.

 I talked with Lee Stevens and sent a memo to Tom Schmitt at HR concerning Caltech paid vacation time for state holidays. This was prompted by Mark’s question about getting Mardi Gras off in Louisiana. Here is Lee Stevens’s answer:

 "We don't give off state holidays... here in California, Hawaii, Washington or Louisiana. ...they would need to take their personal holiday or a vacation day. ...we need to be consistent with all our staff- regardless of where they are based."

Dealt with a variety of personnel issues among them clarifying retirement benefits. Also looked into new ways of doing the same things. Still working on it.

 


For additional information about this report, contact sanders@ligo.caltech.edu