Weekly Report for Week Ending December 14, 1999



 Project Control Meeting Agenda  Highlights     Hanford Observatory     Livingston Observatory     Detector    Project Office    System/Data Analysis   Administrative        Past Weekly Reports

The Project Control Meeting Agenda for Monday  December 20, 1999 will be:
 (Meeting time: 10:30 am Pacific Time)

  1. Announcements (5 minutes)
  2. Review of Action Items (10 minutes)
  3. Comments on Weekly Report (5 minutes)
  4. Field Change Orders/Contingency Liens/Change Requests (10 minutes)
  5. Review of ISSUES AND PROBLEMS by Subsystem/Activity (10 minutes each)
Special Items:    In January, we want to change to a new kind of meeting incorporating the broader functions of the LIGO Laboratory thru a LIGO Lab Executive Committee. How we insure the business carried out at PC meeting gets done in this new scheme is important, so if business is light some discussion of what functions need to be preserved and how would be useful.


Special Announcements:


Weekly Report Highlights

Technical problems with the mirror drive electronics which impaired locking of the two kilometer cavity have now been diagnosed and repaired.


LIGO Hanford Observatory (LHO) Operations



Bake Oven:


(K. Ryan)

LHO Vacuum Bake Oven load #69, consisting of an LOS structure and misc. SS fasteners, was released this week.

Load #70, consisting of two complete sets of BSC leg elements and pins, clevis block and misc. class A vacuum fittings, is vacuum baking and is scheduled to be released on Monday, Dec 16th.

Changes were made in the backing pump configuration for load #69 which resulted in an increase in the sensitivity performance of the RGA.  The pros and cons of keeping this as a permanent change is being considered.

WA2K Interferometer Simulation:



(R. Savage)

B. Bhawal is here this week to work on the modeling of the 2-kilometer interferometer.  We are documenting what has been done to date and generating a notebook containing modeling results.

During recent activity with the one-arm test, Fred Raab noticed that the power spectrum of the long arm error signal during locked stretches was dominated by a peak at 60 Hz.  During a lunchtime commissioning progress discussion, Daniel Sigg proposed an explanation for several features of the data Fred presented.  B. Bhawal and R. Savage used the end-to-end model of the long-arm cavity to test whether all the peaks in the spectra could be caused by frequency modulation at 60Hz.  The model predicts that a frequency modulation amplitude of 2.55 times the cavity half width at half maximum (HWHM) results in the observed ratio of the 60 Hz peak to the 180 Hz peak in the PSD (about 5).  Furthermore, the predicted ratio of about 1.3 between the 120 Hz peak and the 240 Hz peak in the reflected light monitor PSD is consistent with the data.  We thus estimated that the peak amplitude of the 60 Hz frequency modulation during the one locked section analyzed is about 464 Hz.

Seismic Systems:



(C. Gray & H. Radkins)

BSC1:  Beginning of internal hardware;  Support Tubes, Downtube, and Bellows (partially).  The plan is to finish off the Bellows and seal up the chamber today.

HAM work:  Z-pivot replacement fixtures were installed on 4k HAMs--these fixtures will "lock" the Air Bearings in position to prevent any translations due to bumps.  Still awaiting some additional items from the machine shop to complete their installation (should finish these guys off next week).

Computing:



(C. Patton)

I have finally made contact with the Sun representative and have gotten a quote for renewal of our maintenance contract.  The Purchase Request is written.  I'm just waiting for the Sun representative to make some corrections to the addresses on the quote.  I have a quote to upgrade all the site PCs to Windows 98, I'm expecting two more quotes from other companies by Friday.  I ordered tapes for the CDS Cybernetics tape robot.

Continued network security maintenance, did the usual backups, helped with several printer and PC problems, added a couple new user accounts, changed the passwords on several accounts because the users had forgotten their passwords, and kept the GC accounting paper work up to date.


LIGO Livingston Observatory (LLO) Operations


Optics: MMT-3 is in position on Ham1, and the Recycling Mirror should be in Ham 3 by day's end. We've had a few problems during our first optics installation, but they've all been minor, although time consuming. Removal of spool LBE-1A has worked well for alignment, but we lost time Monday removing a vacuum header that was in Ken's way. Next, the power cables to LGV-2 shorted and Allen had to manually open the valve for us. We located MMT-3 on the HAM table Tuesday morning, and we've coarsely aligned it. The PAM nuts in the OSEMs are oversize, causing the PAM magnets to make a "drunken walk" while being adjusted. Consequently, we've removed the face OSEMS on MMT-3 and the RM and replaced the PAM nuts. The OSEMS on the RM have been repositioned, and those on MMT-3 are being reset this afternoon. The new controllers are taking some getting used to, but we seem to have prevailed against the glitches we've met so far and I'm planning on completion of MMT-3 today and the RM right after. (Jonathan Kern)

Sany and Szaby prepared all the small optics suspensions (put OSEMS, PAM magnets) and started to install them to HAMs.  (Sany)

Sany and I tested the new OSEM drivers (AC). They proved definitely less sensitive to interference from 1.06 micron light than the old (DC) drivers. A draft version of our report is available from me or Sany - we will put a copy in the DCC. (Sany Yoshida, Szabolcs Marka)

CDS:

  1. Assisting the installation and testing of the MMT3 and the RM.
  2. Tested the cross-connection panel for 1X4.
  3. Ordered the permanent lockout/tagout station for the control room.
  4. Interface work between the facilities monitoring system and DAQS is ongoing.
  5. Received and installed the last four monitors and two CPU's in the control room.
  6. Installed and terminated two new cat 5 cables from the mass storage room to the control room.
GDS: GDS SUN Enterprise 450 was mounted and the operating system was installed. It was tested on the CDS and GC networks, currently running on GC with a 10BaseT connection. I am waiting for the OC3 card and SUN ULTRA machine to install it on all 4 networks. Part of the utilities was also installed but the loading of the software is still in process. GDS VME crate is installed, containing 4 cards out of the necessary six (2 are still at LHO). Cabling is installed but not connected yet. Thanks to Julien and Rus for their help. (Szabolcs Marka, Tom Evans)

Seismic noise injection: We were trying to inject a 'chirp' via a shaker. We found that one of the seismometers has very long settling time making the measurement very difficult (broken seismometer?). Another seismometer made trials more fruitful, allowing us to produce a nice chirp, alas not covering the full frequency range yet (dynamic range problems). Hopefully we will be able to produce a full chirp by the end of the week. (Szabolcs Marka, Anthony Rizzi)

LIGO II SAS: I analyzed the IP data (collected at CalTech IP). The frequency vs. load behavior nicely aggrees with the predictions showing very low Q around 528kg of load and supercritical behavior slightly above. We recorded highly damped periodic motion with frequency as low as ~12mHz. The damping changes with frequency aggress with predictions. We prepared a talk for the Glasgow meeting including the above results. (The talk will be presented by Joe Kovalik.) (Szabolcs Marka, Joe Kovalik)

LSU: The Graduate General Relativity Course that I taught went very well. The final was given last week and course grades calculated and turned in this week. Course attendance over the span of the semester included professors, postdocs, auditing graduate students as well as the regular grad. students.

GRASP Software: Modification of GRASP continues. 99% successful test of calibration table input: still remains to correctly include dc row format. Joel Tohline made some progress in figuring out how to impliment the templates on the parallel system like the one at LSU. I also made progress in figuring how GRASP can be modified to generate a binary inspiral mass grid for chirps using seismic noise power spectrum data collected last week. (Anthony Rizzi)

Seismic Measurements and Characterization: Sabi and I did measurements to determine why when the shaker thru small accelerometer (PEM type) transfer function is used in mathematica to generate a compensated chirp it does not give the expected output. Sabi did tests under my direction to eliminate some possibilities and found that the large accelermeter does behave more or less as expected but the small one does not.... We now plan to try a different small accelerometer and eliminate the possiblity of a bad accelerometer. All these experiments are increasing our intuition and understanding of delays, resonances and nonlinearities in the seismic detection and shaker systems. (Anthony Rizzi)

Weather Station: We have a company lined up (InterMountain Environmental) that can give us most of components for the two remaining end stations. Meeting with LSU delayed because one of the LSU particpants, at the last moment, could not make the planned meeting. (Anthony Rizzi)

Computers: We have received the Autocad installation CDs for the Caltech site license and are installing it on several PCs. We have both version R14 and version 2000. At the present time we intend to install 2000 on one machine and R14 on the rest. We are testing one of the Suns as a secondary DNS server. (Tom Evans)

Bake Oven: We have finished a load of aluminum parts for the SOS. (Tom Evans)

PEM: Installation of PEM sensors is underway. We had a meeting with Matt Smith to coordinate this effort while he is here this week. He is doing a lot of the sensor installation this week. Juilien is working on data extraction from our Facility Monitoring Control System. An automatic text file recording is needed. Building Samba in CDS gateway machine to communicate with the building control PC. (Eom Evans, Juilien, Rus)

Beam tube bakeout: RGA measurements of the BT bake of lx1 are being made and analyzed at this time and results will be available soon. Cryo pumps have been removed and the H hardware has been installed, leak checked and three ports have been baked. We have ordered a small shack to house the heater blanket controllers in for the ly1 bake, so that they will now be outside the LVEA during that bake to minimize trips into the LVEA. All of the data system will also be outside in a trailer.

Community relations: 77 3rd graders from Isidore Newman School came out to the facility on Wednesday. After we visited their school several weeks ago with an educational outreach presentation on polarization, they were so exited and interested in LIGO that they came out for a tour, to paint murals on the beam tube enclosures, and have a picnic lunch.


WBS 1.2, 1.3    Detector Group



Interferometer Sensing and Control -- M Zucker
(WBS 1.2.1.1.6, 1.2.1.1.7)

2km Cavity Test (Fritschel, Mavalvala, Heefner, Kells, McCarthy, & others)



Another very good week. Most readers will have seen separate emails by Fred Raab and Peter Fritschel with more details.
To summarize, technical problems with the mirror drive electronics which impaired locking of the cavity have now been diagnosed and repaired. The remaining obstacle to truly robust locking (and the detailed characterization that will enable) is nuisance 60 Hz line interference, which is being debugged offline while other tasks proceed. We expect to reopen the gate valves and resume locking & characterization in the new year.  Nergis adds that in addition to this "high profile" stuff some really important grunt work got done: ISC Fabrication/installation (Matt Smith from LLO)


This week at Livingston I started staging the optical lever tables in each building. They are not yet assembled but are at least in their appropriate building.

IAS Initial Alignment (K. Mason, M. MacInnis)



Ken and Myron are in Livingston aligning MMT3 and the Recycling mirror.  They have not been aligned as of yet due to stripped screws on the Large Optic Support. They are being repaired and hopefully will still be aligned this week. All Initial alignment equipment has arrived at LLO and has been recalibrated.  The IOT1 table arrived at LLO with serious crate damage. As of now we know the table and optics are very dirty, but we have not fully assessed the physical damage as of yet.
#MZ The shipping company has still offered no explanation. We are being rather deliberate about assessing damage in order to support a claim if so indicated. At this time we do not believe this incident will affect the LLO integration schedule.



Lasers and Optics -- J. Camp
(1.2.1.1.2, 1.2.1.1.3, 1.2.1.1.4,1.2.1.1.5)

Prestabilized Laser -- Peter King


Input/Output Optics -- Dave Reitze, UF


LHO 2k (Haisheng Rong, Guido Mueller)

Tracked down RFAM problems in the EOMs and after the mode cleaner:

LLO 4k (Sany Yoshida, David Tanner, David Reitze)

Installation of the small IO optics started in the HAMs. After all of the PAMs were put on the small optics, the first two suspensions (MC2 and MMT2) were transported to the LVEA and positioned in HAM2. The transmittance of the MC flats and steering mirrors were measured as a function of angle and polarization. The MC flats have Ts of ~ 2400 ppm at the operation angle and 's' polarization. The SM mirror has T=2900 ppm at 's' (considerably less than the design value of 5000 ppm, but it should be sufficient for PSL intensity stabilization)

Core Optics Procurement and Metrology -- GariLynn Billingsley



We are still measuring BS02.
Bryan Loucks, who designed the Metrology tooling, will be designing another piece which will allow vertical testing of core optics. With this, we hope to have better homogeneity measurements by avoiding the internal thermal gradients we currently have which are caused by the V-block support.

Core Optics Support -- Michael Smith



PO TELESCOPE
A quotation is expected from Allied for cleaning of the large PO telescope parts.
ETM TELESCOPE
3 telescope lenses are at the vendor, being stripped and AR coated.
PO MIRROR MOUNT
The majority of the 4K PO mirror mounts for LHO and LLO have been received.  Several parts are still pending.
ARM CAVITY BAFFLE
Production of the additional 7 inner support and outer frame assemblies are in process. Paul K. is working on the assembly drawings for the LHO and LLO arm cavity baffles.
ELLIPTICAL BAFFLE
The 4K elliptical baffle glass is being AR coated .
IO BAFFLE
The 4K IO baffle mechanical parts are being fabricated. The black glass will be shipped to LLO and LHO by 12/17.
MODECLEANER BAFFLE
Modecleaner baffle glass has been shipped to LHO and LLO.
COS ALIGNMENT
The reworked video camera mounts for the autocollimators are being fabricated. The IR lasers are at the manufacture being reworked.
 

INSTALLATION PLAN, LHO
 

Item Completion Install
4K IO Baffle, HAM2 12/29 ?
Elliptical baffle 4KITMx, BSC3 12/29 ?
Elliptical baffle 4KITMy, BSC1 12/29 ?
Elliptical baffle 4KRM, HAM3  12/29 ?
PO mirror, 4KITMy, BSC2  12/29 ?
PO mirror, 4KITMx, BSC2 12/29 ?
PO mirror, 4KBS-1, BSC1  12/29 ?
PO mirror, 4KBS-2, BSC1  12/29 ?
Beam dump 4KETMy vac window ? ?
Beam dump 4KETMx vac window ? ?
Arm Cavity Baffle, X-vertex 12/29 ?
Arm Cavity Baffle, Y-vertex  12/29 ?
Arm Cavity Baffle, X-end  12/29 ?
Arm Cavity Baffle, Y-end  12/29 ?

INSTALLATION PLAN, LLO
 

Item Completion Install
4K IO Baffle, HAM2  12/29 ?
Elliptical baffle 4KITMx, BSC3  12/29 ?
Elliptical baffle 4KITMy, BSC1 12/29 ?
Elliptical baffle 4KRM, HAM3  12/29 ?
PO mirror, 4KITMy, BSC2 12/29 ?
PO mirror, 4KITMx, BSC2 12/29 ?
PO mirror, 4KBS-1, BSC1  12/29 ?
PO mirror, 4KBS-2, BSC1 12/29 ?
Beam dump ETMy vac window ? ?
Beam dump ETMx vac window ? ?
Arm Cavity Baffle, X-vertex 12/29 ?
Arm Cavity Baffle, Y-vertex 12/29 ?
Arm Cavity Baffle, X-end  12/29 ?
Arm Cavity Baffle, Y-end  12/29 ?



Isolation Group -- M. Fine

Seismic Design (Mike Fine)



1. Counter Weight Production:
The counter weights are being delivered to Allied for cleaning, expecting Friday arrival. Allied will start the cleaing next week.
2. In-Vacuum Hardware:
The final shipment to Hanford is going out of Allied tomorrow and expected to arrived before the holidays. The shipment includes 2 BSC support tubes, 1 BSC downtube, 1 HAM optical table, 13 stack shims, and 108 10# counter weights.
3. Coarse Actuator System (CAS) Training:
The CAS training, to be held at Livingston, is tentatively scheduled for the end of Feb. This is a week long training with 3 days designated for operational aspects of the hardware and the software, 1 day for troubleshooting, and 1 day for advanced programming.
The training is structured to include 4-5 hours/day of classroom instruction followed by 3-4 hours of hands-on operation of a BSC.
The exact dates for the training will be announced when firmed up.

Suspension -- (Janeen Hazel/Mark Barton/Mike Fine)



1. Report from Janeen:
-Mark Barton and I are in Livingston supporting the installation of the MMT3 and the RM. We are preparing the ETMy for installation in January and preparing the ETMx for balancing.



Detector Systems Engineering -- D. Shoemaker/D Coyne
(WBS 1.2.1.1.9)


Physics Environmental Monitor(Matt Smith, David Shoemaker)

This week at Livingston, accelerometers were installed onto the PSL, HAMs 1, 2, 3, and 4. The cables will be installed later.

Four electro-magnetic shaker assemblies was put together.

Sat with a group of people here and discussed PEM issues and priorities. I talked with Russ on the mounting of the microphone power supplies, dust monitors and accelerometers . We will also go over the seismometer and tiltmeter breakout box locations.

Global Diagnostics System
(Daniel Sigg, John Zweizig)



Held a meeting on calibration, reduced data set (RDS) infrastructure and event database. Identified the need for a calibration database so calibration data can be entered in the control room and then automatically distributed to clients such as the data viewer (in order to put physical units on the vertical scales) and the frame builder (in order to copy the information into the frame header). Decided to go ahead with the reduce data set management software for the LSC tape robot (desired features: management software can handle multiple users and is independent of the RDS generators; first RDS generator would be a "beefed-up" jdclient; second generator would be the LIGO/LSC standard RDS; also need to be able to read data back and feed it to the NDS.)

Between telecons and meetings (LSCDC, GDS/LDAS/CDS, data conditioning API, frames) I tested the latest versions of the DMT software in preparation for a new release, helped various users of the DMT and framecpp libraries and started to upgrade the trigger classes to reflect the database table structures described in Peter Shawhan's memo.

Continued to work on the graphical user interface for the diagnostics test tool. Discovered a strange problem with the test point manager running on the same CPU as the DAQ configuration manager/EDCU. Putting them on two different CPUs made the (resource?) problem disappear.



Control and Data System -- R. Bork
(WBS 1.2.2)

Data Acquistion


LSC CDS: (Dale)


We shipped a photodiode circuit and 6 photodiodes to MIT this week for high power testing. We are testing a second photodiode Interface board. Should be ready today. I am setting up a blanket order with a local board stuffing house to take some of the load off of our CDS board stuffer (Phoenix). Four more LSC Notch Filters are being stuffed now. We are in the process of working out the details of the Common Mode Servo with Mike and Peter so we can get started with that design. I am working on an LSC document to nail down the CDS requirements.


WBS 1.4    Project Office



Reports (Lindquist) Change Control/Contingency (Lindquist)

The following change request has been submitted:
 

CR-990028 WBS 1.1.3 Beam Tube Enclosure Closeout F. Asiri

Press for the latest Contingency Needs Projection


LIGO Weekly Site Telecon (Jasnow)

A site telecon was held on on Thursday, December 16, 1999.  The list of current actions assigned may be found at ACTION LIST.


PROPERTY MANAGEMENT (Chargois)
From: Ed Chargois <chargois_e@ligo.caltech.edu>

Assisted the Detector Group (M.Fine) with the transportation of  350 pounds of seismic weights from CONEJO Industries in Newbury Park, CA. to ALLIED  ENGINEERING  and PRODUCTION, delivery expected DEC 16,1999.  Account Number 5F511.

Assisted the Project Office (E. Wood) with packing and shipping of a return order of office supplies to Viking for reimbursement.

Assisted Seismic Isolation with packaging and shipping of a Vacuum Chamber and  Pump  to the LIGO Livingston Observatory (J. Kovalik) expected arrival date Dec. 28, 1999. Account Number 50481.

Assisting the Detector Group (M. Smith) with the preparation of CALTECH'S  Physical Plant Project Request for packing and shipping crate. Account Number 5F515.

Received  two Vehicle Certificate Of  Title for vehicles purchased by the LIGO Hanford Observatory. A copy will be forwarded to LHO, and the original will be turned over to the Document Control Center for safe keeping.


DOCUMENT CONTROL CENTER (Turner)

From: the DCC <dcc@ligo.caltech.edu>

Web pages for the DCC give simple how-to's for document numbering, easy access to the latest on-line documents, and search capabilities for the DCC database. Take a look. . .

ACTIVITY HIGHLIGHTS

From: Cleveland Mak <mak_c@ligo.caltech.edu> Press here to access the DOCUMENT CONTROL CENTER WEB PAGE.


COST SCHEDULE CONTROL SYSTEMS (Duncan, Moore, Akutagawa, Kaufman)

From: Sarita Moore<moore_s@ligo.caltech.edu>

Press here for ACCOUNTS PAYABLE HISTORY DATA.

From: Ruth Brambila

I'm catching up from last week when I was out.  I've been working on getting a report for Ed to see what open PO's need to have funds transferred to the new FY [2000 -pel] PTA's.

From: Kris Duncan <kris@ligo.caltech.edu>

From: Florence Kaufman <fkaufman@ligo.caltech.edu> From: Cindy Akutagawa <cindy@ligo.caltech.edu>

I am working on the November status reports and should have them on the network by Friday.  I made up the list of LIGO FY 2000 Account Numbers and gave them to Barbara to put on the Internal Bulletin Board.  The link is http://docuserv.ligo.caltech.edu/.

SUBCONTRACTS MANAGEMENT (Petrac, Jasnow)

From: irena@ligo.caltech.edu (Irena Petrac)

From: Ed Jasnow <jasnow@acrux.ligo.caltech.edu>

Change Order No. 2 is being issued to the MMR contract to cover additional costs for the Livingston bakeout.  This modification is in the amount of $19,100.

Davies Associates, the designer responsible for the LIGO logo, has assigned all copyrights for the logo to Caltech, so we now own it.  The copyright assignment document is now in the hands of Adam Cochran, Office of General Counsel, who will advise us on the form of infringement protection we need to acquire.

TECHNICAL CONFIGURATION MANAGEMENT (Althouse)

From: wea@acrux (William Althouse)

No report. See Bake out.


WBS 1.4.3    Systems Engineering / Data Analysis and Computing


Systems Engineering

No report

Simulation and Modeling

Modeling

Biplab Bhawal
Working at LHO to complete the e2e PSL/IOO model .

Ed Maros
(EFM)   Worked with Bruce to track down wxString problem.

[Bruce Sears]
(BS) Alfi 4 Software Development:     (3.5 days)

Hiro Yamamoto

Worked with Matt Evens to analyze the fringe structure of LHO 2K FP data to extract finess and velocity.

LIGO Data Analysis System

[Masha Barnes] [Kent Blackburn] [Alex Ivanhov] [Grace Hu] [Mary Lei] [ Edward Maros ] [Bruce Sears] Stuart Anderson

General Computing

MIT: Livingston: Hanford: CIT:



WBS 1.4.4.1    Administrative Group



Dorothy Lloyd
Continue to process invoices for payment using both on- and off-line approval methods. Track and solve invoice problems. Entered and approved requisitions on-line (for more detail see "Cost Schedule Control Systems" report by Sarita Moore). Receiving on-line continues daily.

Continue to monitor contract funding levels and request supplements from task managers were needed.

Data entry for current payments made for both contract and purchase orders is on-going by both Jim and me. Jim continues to work on reconciling status reports and data entry in LIGO database.

Rita Torres

Ongoing work on travel documents.

For I. Petrac did letter to Shanghai Institute (SIOM) to transmit Attachment No. 1 to their MOU.  Did letter to Penn State to transmit Attachments A, B, & Z to their MOU.  Final edits to Crystal Systems package, FedExed for NSF review and approval. Distributed the signed change order No. 10 to Schober Machine.

For E. Jasnow prepared contract with John Desmond & Associates for LLO Staging Building, obtained an Oracle requisition number, and coordinated with R. Brambila to obtain PO #1008883.  Thank you Ruth for the timely response.  FedExed 3 copies of the contract for Desmond signature, distributed 10 copies in-house.

Ordered items using the P-Card. Reconciled P-Card purchases, one order contained 27 line items. Last Thursday met with I. Baldon and B. Kratochwill to discuss updating the FileMaker Pro application for travel, these forms as well as other travel forms must eventually interface with Oracle.

Helped D. Tomlinson copy and distribute flyers for upcoming seminars.

Irene Baldon

Worked on preparing the paper work for 9 new trips taken recently or upcoming (9 Payment Requests and 2 Advance Requests). There are approximately an additional 6 new trips in various stages pending completion of travel arrangements before the paper work can be completed. Also worked on an unusually high number of problem issues which required a good portion of my time. A relocation to Livingston and a number Post Docs took an additional amount of my time.

Completed 27 Expense Reports, some of which were extensive, involving 2-3 or more pages each. Some of these reports were still not taped or completed by the Traveler, and required additional time for completion. Worked additionally on a number of problem issues associated with these which required a good portion of my time. There are 11 Expense Reports still to be done. I'm holding 3 completed Expense Reports which require a check from the Traveler before sending to Travel Audit to clear. Also assisted and advised both Rita and Liz on the preparation of Expense Reports.

Rita and Liz were able to complete 20 Expense Reports for me. They have an additional 9 Expense Reports in the process of completion. Thanks Rita and Liz.

I have not seen any significant change in the time lag for receiving checks nor have I started receiving T numbers for the trips prior to or during the duration of the trip. I continue to receive T numbers after the completion and pay off of the Expense Report. Met with Barbara and Rita last Thursday to see if we could create some sort of data base using ORACLE's Excel forms. We came up with something as a stop-gap (its very time consuming but at least it allows me to maintain copies/information) until Barbara can see if she can modify the Excel Program for me.

Performed normal recording and filing associated with Travel and Reimbursement.

Prepared the Travel/Vacation Itinerary for the Week of December 14, 1999.

Performed miscellaneous duties as requested by various members of the LIGO Project here at Caltech, as well as from members of the staffs of each of the two (2) sites. I continue to do MIT's travel to the sites for installation activities and assist them wherever possible.

Elizabeth K. Wood

Returned many inkjet transparencies that we got at a really terrific price that are completely useless to us because we are now using a laserjet printer. The inkjet transparencies are not compatible with laserjet printers. Now I have to find a really terrific price on laserjet transparencies. Probably just in time for the printers to be changed again.

Went to Straightline Offline in Burbank with Barbara K. to rent a beta videotape machine for use in timing the talks at LIGOfest so they can be edited and put on the web.

Spent some time tracking down two missing paychecks for a student employee. Since the checks are gone gone gone, we must stop payment on the checks and have them reissued.

Made arrangements with Graphic Arts to make reprints of the LIGO article from Engineering and Science since we are running low on the ones I have left.

Helped Irene with travel reimbursements.


For additional information about this report, contact sanders@ligo.caltech.edu