Weekly Report for Week Ending December
14, 1999
Project Control Meeting Agenda Highlights
Hanford Observatory Livingston
Observatory Detector
Project Office System/Data
Analysis
Administrative
Past Weekly Reports
The Project Control Meeting
Agenda for Monday December 20, 1999 will be:
(Meeting time: 10:30 am Pacific Time)
-
Announcements (5 minutes)
-
Review of Action Items (10 minutes)
-
Comments on Weekly Report (5 minutes)
-
Field Change Orders/Contingency Liens/Change Requests (10 minutes)
-
Review of ISSUES AND PROBLEMS by Subsystem/Activity (10 minutes each)
-
- Integration/Installation (Coyne)
Detector
Installation & Commissioning Bulletin Board
-
- Hanford Observatory (Raab)
-
- Livingston Observatory (Coles)
-
- Beam Tube Bakeout (Althouse)
-
- Data Analysis and Computing (Lazzarini)
-
- Project Controls / Operations (Lindquist)
-
- Lasers and Optics (Camp)
-
- Isolation (Fine)
-
- Interf. Sensing (Zucker)
-
- Control and Data (Bork)
-
- Advanced R&D (Sanders)
Special Items: In January, we want to change to a
new kind of meeting incorporating the broader functions of the LIGO Laboratory
thru a LIGO Lab Executive Committee. How we insure the business carried
out at PC meeting gets done in this new scheme is important, so if business
is light some discussion of what functions need to be preserved and how
would be useful.
Special Announcements:
Weekly
Report Highlights
Technical
problems with the mirror drive electronics which impaired locking of the
two kilometer cavity have now been diagnosed and repaired.
LIGO Hanford Observatory (LHO) Operations
Bake Oven:
(K. Ryan)
LHO Vacuum Bake Oven load #69, consisting of an LOS structure and misc.
SS fasteners, was released this week.
Load #70, consisting of two complete sets of BSC leg elements and pins,
clevis block and misc. class A vacuum fittings, is vacuum baking and is
scheduled to be released on Monday, Dec 16th.
Changes were made in the backing pump configuration for load #69 which
resulted in an increase in the sensitivity performance of the RGA.
The pros and cons of keeping this as a permanent change is being considered.
WA2K Interferometer Simulation:
(R. Savage)
B. Bhawal is here this week to work on the modeling of the 2-kilometer
interferometer. We are documenting what has been done to date and
generating a notebook containing modeling results.
During recent activity with the one-arm test, Fred Raab noticed that
the power spectrum of the long arm error signal during locked stretches
was dominated by a peak at 60 Hz. During a lunchtime commissioning
progress discussion, Daniel Sigg proposed an explanation for several features
of the data Fred presented. B. Bhawal and R. Savage used the end-to-end
model of the long-arm cavity to test whether all the peaks in the spectra
could be caused by frequency modulation at 60Hz. The model predicts
that a frequency modulation amplitude of 2.55 times the cavity half width
at half maximum (HWHM) results in the observed ratio of the 60 Hz peak
to the 180 Hz peak in the PSD (about 5). Furthermore, the predicted
ratio of about 1.3 between the 120 Hz peak and the 240 Hz peak in the reflected
light monitor PSD is consistent with the data. We thus estimated
that the peak amplitude of the 60 Hz frequency modulation during the one
locked section analyzed is about 464 Hz.
Seismic Systems:
(C. Gray & H. Radkins)
BSC1: Beginning of internal hardware; Support Tubes, Downtube,
and Bellows (partially). The plan is to finish off the Bellows and
seal up the chamber today.
HAM work: Z-pivot replacement fixtures were installed on 4k HAMs--these
fixtures will "lock" the Air Bearings in position to prevent any translations
due to bumps. Still awaiting some additional items from the machine
shop to complete their installation (should finish these guys off next
week).
Computing:
(C. Patton)
I have finally made contact with the Sun representative and have gotten
a quote for renewal of our maintenance contract. The Purchase Request
is written. I'm just waiting for the Sun representative to make some
corrections to the addresses on the quote. I have a quote to upgrade
all the site PCs to Windows 98, I'm expecting two more quotes from other
companies by Friday. I ordered tapes for the CDS Cybernetics tape
robot.
Continued network security maintenance, did the usual backups, helped
with several printer and PC problems, added a couple new user accounts,
changed the passwords on several accounts because the users had forgotten
their passwords, and kept the GC accounting paper work up to date.
LIGO Livingston Observatory (LLO)
Operations
Optics: MMT-3 is in position on Ham1, and the Recycling Mirror
should be in Ham 3 by day's end. We've had a few problems during our first
optics installation, but they've all been minor, although time consuming.
Removal of spool LBE-1A has worked well for alignment, but we lost time
Monday removing a vacuum header that was in Ken's way. Next, the power
cables to LGV-2 shorted and Allen had to manually open the valve for us.
We located MMT-3 on the HAM table Tuesday morning, and we've coarsely aligned
it. The PAM nuts in the OSEMs are oversize, causing the PAM magnets to
make a "drunken walk" while being adjusted. Consequently, we've removed
the face OSEMS on MMT-3 and the RM and replaced the PAM nuts. The OSEMS
on the RM have been repositioned, and those on MMT-3 are being reset this
afternoon. The new controllers are taking some getting used to, but we
seem to have prevailed against the glitches we've met so far and I'm planning
on completion of MMT-3 today and the RM right after. (Jonathan Kern)
Sany and Szaby prepared all the small optics suspensions (put OSEMS,
PAM magnets) and started to install them to HAMs. (Sany)
Sany and I tested the new OSEM drivers (AC). They proved definitely
less sensitive to interference from 1.06 micron light than the old (DC)
drivers. A draft version of our report is available from me or Sany - we
will put a copy in the DCC. (Sany Yoshida, Szabolcs Marka)
CDS:
-
Assisting the installation and testing of the MMT3 and the RM.
-
Tested the cross-connection panel for 1X4.
-
Ordered the permanent lockout/tagout station for the control room.
-
Interface work between the facilities monitoring system and DAQS is ongoing.
-
Received and installed the last four monitors and two CPU's in the control
room.
-
Installed and terminated two new cat 5 cables from the mass storage room
to the control room.
GDS: GDS SUN Enterprise 450 was mounted and the operating system
was installed. It was tested on the CDS and GC networks, currently running
on GC with a 10BaseT connection. I am waiting for the OC3 card and SUN
ULTRA machine to install it on all 4 networks. Part of the utilities was
also installed but the loading of the software is still in process. GDS
VME crate is installed, containing 4 cards out of the necessary six (2
are still at LHO). Cabling is installed but not connected yet. Thanks to
Julien and Rus for their help. (Szabolcs Marka, Tom Evans)
Seismic noise injection: We were trying to inject a 'chirp' via
a shaker. We found that one of the seismometers has very long settling
time making the measurement very difficult (broken seismometer?). Another
seismometer made trials more fruitful, allowing us to produce a nice chirp,
alas not covering the full frequency range yet (dynamic range problems).
Hopefully we will be able to produce a full chirp by the end of the week.
(Szabolcs Marka, Anthony Rizzi)
LIGO II SAS: I analyzed the IP data (collected at CalTech IP).
The frequency vs. load behavior nicely aggrees with the predictions showing
very low Q around 528kg of load and supercritical behavior slightly above.
We recorded highly damped periodic motion with frequency as low as ~12mHz.
The damping changes with frequency aggress with predictions. We prepared
a talk for the Glasgow meeting including the above results. (The talk will
be presented by Joe Kovalik.) (Szabolcs Marka, Joe Kovalik)
LSU: The Graduate General Relativity Course that I taught went
very well. The final was given last week and course grades calculated and
turned in this week. Course attendance over the span of the semester included
professors, postdocs, auditing graduate students as well as the regular
grad. students.
GRASP Software: Modification of GRASP continues. 99% successful
test of calibration table input: still remains to correctly include dc
row format. Joel Tohline made some progress in figuring out how to impliment
the templates on the parallel system like the one at LSU. I also made progress
in figuring how GRASP can be modified to generate a binary inspiral mass
grid for chirps using seismic noise power spectrum data collected last
week. (Anthony Rizzi)
Seismic Measurements and Characterization: Sabi and I did measurements
to determine why when the shaker thru small accelerometer (PEM type) transfer
function is used in mathematica to generate a compensated chirp it does
not give the expected output. Sabi did tests under my direction to eliminate
some possibilities and found that the large accelermeter does behave more
or less as expected but the small one does not.... We now plan to try a
different small accelerometer and eliminate the possiblity of a bad accelerometer.
All these experiments are increasing our intuition and understanding of
delays, resonances and nonlinearities in the seismic detection and shaker
systems. (Anthony Rizzi)
Weather Station: We have a company lined up (InterMountain Environmental)
that can give us most of components for the two remaining end stations.
Meeting with LSU delayed because one of the LSU particpants, at the last
moment, could not make the planned meeting. (Anthony Rizzi)
Computers: We have received the Autocad installation CDs for
the Caltech site license and are installing it on several PCs. We have
both version R14 and version 2000. At the present time we intend to install
2000 on one machine and R14 on the rest. We are testing one of the Suns
as a secondary DNS server. (Tom Evans)
Bake Oven: We have finished a load of aluminum parts for the
SOS. (Tom Evans)
PEM: Installation of PEM sensors is underway. We had a meeting
with Matt Smith to coordinate this effort while he is here this week. He
is doing a lot of the sensor installation this week. Juilien is working
on data extraction from our Facility Monitoring Control System. An automatic
text file recording is needed. Building Samba in CDS gateway machine to
communicate with the building control PC. (Eom Evans, Juilien, Rus)
Beam tube bakeout: RGA measurements of the BT bake of lx1 are
being made and analyzed at this time and results will be available soon.
Cryo pumps have been removed and the H hardware has been installed, leak
checked and three ports have been baked. We have ordered a small shack
to house the heater blanket controllers in for the ly1 bake, so that they
will now be outside the LVEA during that bake to minimize trips into the
LVEA. All of the data system will also be outside in a trailer.
Community relations: 77 3rd graders from Isidore Newman School
came out to the facility on Wednesday. After we visited their school several
weeks ago with an educational outreach presentation on polarization, they
were so exited and interested in LIGO that they came out for a tour, to
paint murals on the beam tube enclosures, and have a picnic lunch.
WBS 1.2, 1.3
Detector Group
Interferometer Sensing and Control -- M Zucker
(WBS 1.2.1.1.6, 1.2.1.1.7)
2km Cavity Test (Fritschel, Mavalvala, Heefner, Kells, McCarthy, &
others)
Another very good week. Most readers will have seen separate emails
by Fred Raab and Peter Fritschel with more details.
To
summarize, technical problems with the mirror drive electronics which impaired
locking of the cavity have now been diagnosed and repaired. The remaining
obstacle to truly robust locking (and the detailed characterization that
will enable) is nuisance 60 Hz line interference, which is being debugged
offline while other tasks proceed. We expect to reopen the gate valves
and resume locking & characterization in the new year.
Nergis adds that in addition to this "high profile" stuff some really important
grunt work got done:
-
completed isolation of all components on IOT7 and ISCT10 and cabled all
"field" outputs to temporary DAQ channels.
-
we have locked the Michelson ifo to measure the internal resonances of
the core optics.
-
Rana has set up the phase camera on the reflectin port of the mode cleaner
and is measuring the beam profile.
-
Bill Kells & Peter Fritschel took some more swings at the ETM transmission
monitor. We'll take a wag at redesigning the optics head for "user friendliness"
when Matt gets back (should be easier to align when we get a solid cavity
lock too).
ISC Fabrication/installation (Matt Smith from LLO)
This week at Livingston I started staging the optical lever tables
in each building. They are not yet assembled but are at least in their
appropriate building.
IAS Initial Alignment (K. Mason, M. MacInnis)
Ken and Myron are in Livingston aligning MMT3 and the Recycling mirror.
They have not been aligned as of yet due to stripped screws on the Large
Optic Support. They are being repaired and hopefully will still be aligned
this week. All Initial alignment equipment has arrived at LLO and has been
recalibrated. The IOT1 table arrived at LLO with serious crate damage.
As of now we know the table and optics are very dirty, but we have not
fully assessed the physical damage as of yet.
#MZ The shipping company has still offered no explanation. We are being
rather deliberate about assessing damage in order to support a claim if
so indicated. At this time we do not believe this incident will affect
the LLO integration schedule.
Lasers and Optics -- J. Camp
(1.2.1.1.2, 1.2.1.1.3, 1.2.1.1.4,1.2.1.1.5)
Prestabilized Laser -- Peter King
-
The LHO 2k IFO PSL is a year old this week.
-
The silver braided shielded co-axial cable used for some signals in the
PSL has been replaced by insulated shielded coax (RG405). The signals
originated from 2X7 over to the PSL table.
-
A change was made to the PSL EPICS records database. The record concerned,
H2:PSL-126MOPA_FAULT, was corrected to enable the alarm handler.
The laser is now on the LHO critical systems alarm handler. Should the
laser's power supply indicate a fault, meaning that the laser has tripped
out for some reason, then this is now indicated in the LHO control room.
Input/Output Optics -- Dave Reitze, UF
LHO 2k (Haisheng Rong, Guido Mueller)
Tracked down RFAM problems in the EOMs and after the mode cleaner:
-
Time varying RFAM in the range 10-3 - 10-2 was observed
on the PSL table in preparation for the long arm test. A polarizer was
inserted before the EOMs after the half wave plate on the PSL table. The
RFAM of the 26MHz measured on the PSL is in the order of 1e-5 and stable.
The RFAM of the 29.8MHz is now 10-4 on the PSL table and is
very stable (since 16h no major change).
-
Not surprisingly, behind the MC, the RFAM depends strongly on the modulation
frequency. If the resonant mod. freq. is detuned by 100Hz off resonance,
we observe strong fluctuations in the amplitude with max 5e-4. On
the resonance we had 5e-5 (smaller than in front of the MC) and very stable.
Also found that the RFAM in the spatial wings of the beam (higher order
modes) is much worse, presumably because the higher order modes are further
off resonance.
The mode cleaner transmission was measured to be 89% (error bars of
+/-5% due to uncertainty in R,Ts of mirrors which route the beam). This
value corresponds to roughly 200ppm roundtrip losses in the cavity. The
finesse is 1326, compared with a ringdown result of 1331 measured a few
weeks ago.
LLO 4k (Sany Yoshida, David Tanner, David Reitze)
Installation of the small IO optics started in the HAMs. After all of
the PAMs were put on the small optics, the first two suspensions (MC2 and
MMT2) were transported to the LVEA and positioned in HAM2. The transmittance
of the MC flats and steering mirrors were measured as a function of angle
and polarization. The MC flats have Ts of ~ 2400 ppm at the operation angle
and 's' polarization. The SM mirror has T=2900 ppm at 's' (considerably
less than the design value of 5000 ppm, but it should be sufficient for
PSL intensity stabilization)
Core Optics Procurement and Metrology -- GariLynn Billingsley
We are still measuring BS02.
Bryan Loucks, who designed the Metrology tooling, will be designing
another piece which will allow vertical testing of core optics. With this,
we hope to have better homogeneity measurements by avoiding the internal
thermal gradients we currently have which are caused by the V-block support.
Core Optics Support -- Michael Smith
PO TELESCOPE
A quotation is expected from Allied for cleaning of the large PO telescope
parts.
ETM TELESCOPE
3 telescope lenses are at the vendor, being stripped and AR coated.
PO MIRROR MOUNT
The majority of the 4K PO mirror mounts for LHO and LLO have been received.
Several parts are still pending.
ARM CAVITY BAFFLE
Production of the additional 7 inner support and outer frame assemblies
are in process. Paul K. is working on the assembly drawings for the LHO
and LLO arm cavity baffles.
ELLIPTICAL BAFFLE
The 4K elliptical baffle glass is being AR coated .
IO BAFFLE
The 4K IO baffle mechanical parts are being fabricated. The black glass
will be shipped to LLO and LHO by 12/17.
MODECLEANER BAFFLE
Modecleaner baffle glass has been shipped to LHO and LLO.
COS ALIGNMENT
The reworked video camera mounts for the autocollimators are being
fabricated. The IR lasers are at the manufacture being reworked.
INSTALLATION PLAN, LHO
| Item |
Completion |
Install |
| 4K IO Baffle, HAM2 |
12/29 |
? |
| Elliptical baffle 4KITMx, BSC3 |
12/29 |
? |
| Elliptical baffle 4KITMy, BSC1 |
12/29 |
? |
| Elliptical baffle 4KRM, HAM3 |
12/29 |
? |
| PO mirror, 4KITMy, BSC2 |
12/29 |
? |
| PO mirror, 4KITMx, BSC2 |
12/29 |
? |
| PO mirror, 4KBS-1, BSC1 |
12/29 |
? |
| PO mirror, 4KBS-2, BSC1 |
12/29 |
? |
| Beam dump 4KETMy vac window |
? |
? |
| Beam dump 4KETMx vac window |
? |
? |
| Arm Cavity Baffle, X-vertex |
12/29 |
? |
| Arm Cavity Baffle, Y-vertex |
12/29 |
? |
| Arm Cavity Baffle, X-end |
12/29 |
? |
| Arm Cavity Baffle, Y-end |
12/29 |
? |
INSTALLATION PLAN, LLO
| Item |
Completion |
Install |
| 4K IO Baffle, HAM2 |
12/29 |
? |
| Elliptical baffle 4KITMx, BSC3 |
12/29 |
? |
| Elliptical baffle 4KITMy, BSC1 |
12/29 |
? |
| Elliptical baffle 4KRM, HAM3 |
12/29 |
? |
| PO mirror, 4KITMy, BSC2 |
12/29 |
? |
| PO mirror, 4KITMx, BSC2 |
12/29 |
? |
| PO mirror, 4KBS-1, BSC1 |
12/29 |
? |
| PO mirror, 4KBS-2, BSC1 |
12/29 |
? |
| Beam dump ETMy vac window |
? |
? |
| Beam dump ETMx vac window |
? |
? |
| Arm Cavity Baffle, X-vertex |
12/29 |
? |
| Arm Cavity Baffle, Y-vertex |
12/29 |
? |
| Arm Cavity Baffle, X-end |
12/29 |
? |
| Arm Cavity Baffle, Y-end |
12/29 |
? |
Isolation Group -- M. Fine
Seismic Design (Mike Fine)
1. Counter Weight Production:
The counter weights are being delivered to Allied for cleaning, expecting
Friday arrival. Allied will start the cleaing next week.
2. In-Vacuum Hardware:
The final shipment to Hanford is going out of Allied tomorrow and expected
to arrived before the holidays. The shipment includes 2 BSC support tubes,
1 BSC downtube, 1 HAM optical table, 13 stack shims, and 108 10# counter
weights.
3. Coarse Actuator System (CAS) Training:
The CAS training, to be held at Livingston, is tentatively scheduled
for the end of Feb. This is a week long training with 3 days designated
for operational aspects of the hardware and the software, 1 day for troubleshooting,
and 1 day for advanced programming.
The training is structured to include 4-5 hours/day of classroom instruction
followed by 3-4 hours of hands-on operation of a BSC.
The exact dates for the training will be announced when firmed up.
Suspension -- (Janeen Hazel/Mark Barton/Mike Fine)
1. Report from Janeen:
-Mark Barton and I are in Livingston supporting the installation of
the MMT3 and the RM. We are preparing the ETMy for installation in January
and preparing the ETMx for balancing.
Detector Systems Engineering -- D. Shoemaker/D Coyne
(WBS 1.2.1.1.9)
Physics Environmental Monitor(Matt Smith, David Shoemaker)
This week at Livingston, accelerometers were installed onto the PSL,
HAMs 1, 2, 3, and 4. The cables will be installed later.
Four electro-magnetic shaker assemblies was put together.
Sat with a group of people here and discussed PEM issues and priorities.
I talked with Russ on the mounting of the microphone power supplies, dust
monitors and accelerometers . We will also go over the seismometer and
tiltmeter breakout box locations.
Global Diagnostics System
(Daniel Sigg, John Zweizig)
Held a meeting on calibration, reduced data set (RDS) infrastructure
and event database. Identified the need for a calibration database so calibration
data can be entered in the control room and then automatically distributed
to clients such as the data viewer (in order to put physical units on the
vertical scales) and the frame builder (in order to copy the information
into the frame header). Decided to go ahead with the reduce data set management
software for the LSC tape robot (desired features: management software
can handle multiple users and is independent of the RDS generators; first
RDS generator would be a "beefed-up" jdclient; second generator would be
the LIGO/LSC standard RDS; also need to be able to read data back and feed
it to the NDS.)
Between telecons and meetings (LSCDC, GDS/LDAS/CDS, data conditioning
API, frames) I tested the latest versions of the DMT software in preparation
for a new release, helped various users of the DMT and framecpp libraries
and started to upgrade the trigger classes to reflect the database table
structures described in Peter Shawhan's memo.
Continued to work on the graphical user interface for the diagnostics
test tool. Discovered a strange problem with the test point manager running
on the same CPU as the DAQ configuration manager/EDCU. Putting them on
two different CPUs made the (resource?) problem disappear.
Control and Data System -- R. Bork
(WBS 1.2.2)
Data Acquistion
-
Added ability to read trend frames into Matlab; undergoing testing.
-
Attended Frame specification meetings hosted by LDAS.
-
Paul shipped one BNC version of the Antialiasing Filter Chassis to Hanford
yesterday afternoon. This completed Hanford's order for 7 LEMO Version
and one BNC version of the AA Filter Chassis for December.
-
Liasoned with PalPilot for assembling 12 LEMO and 6 BNC AA Filter Chassis
for the coming months.
LSC CDS: (Dale)
We shipped a photodiode circuit and 6 photodiodes to MIT this week
for high power testing. We are testing a second photodiode Interface board.
Should be ready today. I am setting up a blanket order with a local board
stuffing house to take some of the load off of our CDS board stuffer (Phoenix).
Four more LSC Notch Filters are being stuffed now. We are in the process
of working out the details of the Common Mode Servo with Mike and Peter
so we can get started with that design. I am working on an LSC document
to nail down the CDS requirements.
WBS 1.4 Project
Office
Reports (Lindquist)
-
We are still waiting for some contributions for the
FY 2000 Operations Annual Work Plan.
-
We requested submittals for the Annual Report for
the Construction Project by Friday, December 17, 1999. So far, contributions
have been pouring in with the roar of a leaky faucet.
Change Control/Contingency (Lindquist)
The following change request has
been submitted:
| CR-990028 |
WBS 1.1.3 |
Beam Tube Enclosure Closeout |
F. Asiri |
Press for the latest Contingency
Needs Projection
LIGO Weekly Site Telecon (Jasnow)
A site telecon was held on on Thursday, December
16, 1999. The list of current actions assigned may be found at ACTION
LIST.
PROPERTY
MANAGEMENT (Chargois)
From: Ed Chargois <chargois_e@ligo.caltech.edu>
Assisted the Detector Group (M.Fine) with the
transportation of 350 pounds of seismic weights from CONEJO Industries
in Newbury Park, CA. to ALLIED ENGINEERING and PRODUCTION,
delivery expected DEC 16,1999. Account Number 5F511.
Assisted the Project Office (E. Wood) with packing
and shipping of a return order of office supplies to Viking for reimbursement.
Assisted Seismic Isolation with packaging and
shipping of a Vacuum Chamber and Pump to the LIGO Livingston
Observatory (J. Kovalik) expected arrival date Dec. 28, 1999. Account Number
50481.
Assisting the Detector Group (M. Smith) with the
preparation of CALTECH'S Physical Plant Project Request for packing
and shipping crate. Account Number 5F515.
Received two Vehicle Certificate Of
Title for vehicles purchased by the LIGO Hanford Observatory. A copy will
be forwarded to LHO, and the original will be turned over to the Document
Control Center for safe keeping.
DOCUMENT
CONTROL CENTER (Turner)
From: the DCC <dcc@ligo.caltech.edu>
Web pages for the DCC
give simple how-to's for document numbering, easy access to the latest
on-line documents, and search capabilities for the DCC database. Take
a look. . .
ACTIVITY HIGHLIGHTS
-
For the past week's
processing statistics, check the DCC
web page.
-
Finished final preparations
for the LIGO Christmas Party held this past week.
-
Organized all LIGO shirt
orders and created master order for final quotation from marketing company.
-
Continued the work of
scanning all PAC presentations.
-
Continued converting
presentation files from the Science Symposium into .pdf format for electronic
library availability.
From: Cleveland Mak <mak_c@ligo.caltech.edu>
These figures include last reporting period since we didn't do one
for last week.
|
Packages |
Faxes |
| In |
34 |
20 |
| Out |
13 |
40 |
Press here to access
the DOCUMENT CONTROL CENTER
WEB PAGE.
COST SCHEDULE
CONTROL SYSTEMS (Duncan, Moore, Akutagawa, Kaufman)
From: Sarita Moore<moore_s@ligo.caltech.edu>
Press here for ACCOUNTS
PAYABLE HISTORY DATA.
From: Ruth Brambila
I'm catching up from last week when I was out.
I've been working on getting a report for Ed to see what open PO's need
to have funds transferred to the new FY [2000 -pel] PTA's.
From: Kris Duncan <kris@ligo.caltech.edu>
-
Continued to trouble-shoot, reinstall, repair files,
etc. in COBRA.
-
Finalized the October 1999 reports and distributed
the CSSR. Prepared presentation materials and participated in the
Project Control meeting held on Monday, December 13.
-
Reviewed the approved change request's and began
incorporating them into the baseline.
-
Advanced the calendars in COBRA for November reporting,
rebuilt indexes, and began input of actual costs to date as reported by
CIT finance.
[Our old DOS based version of COBRA (the cost
performance database and report generator) is dying. We have not
upgraded to the newer WINDOWS version because acceptable replacements for
our report formats are not available on the new system. The old DOS
version is no longer supported by WELCOM Software. Kris is arranging
with WELCOM to have the reports that LIGO needs prepared for the newer
COBRA. -pel]
From: Florence Kaufman <fkaufman@ligo.caltech.edu>
-
Worked on revision of the Livingston report for Operations for November
99, based on information provided by Mark Coles and Gerry Stapfer.
-
Updated report format for Year 2000 Operations.
-
Issued one page summary of Frequently Used Expenditure Types by Ligo Project.
-
Reviewed reports in Webster of 2000 Ops accounts, some costs mainly payroll
and Internal Charges, are now being charged to the new accounts.
From: Cindy Akutagawa <cindy@ligo.caltech.edu>
I am working on the November status reports and should have them on
the network by Friday. I made up the list of LIGO FY 2000 Account
Numbers and gave them to Barbara to put on the Internal Bulletin Board.
The link is http://docuserv.ligo.caltech.edu/.
SUBCONTRACTS MANAGEMENT (Petrac,
Jasnow)
From: irena@ligo.caltech.edu (Irena Petrac)
-
Crystal Systems: Subcontract is at NSF for approval.
-
Lightwave: Proposal for Phase V (FY 2000) support was received. CO #5,
incorporating agreements for the continued technical support and adding
required funds, was released by the Detector group.
-
FDC: CO #24, extending the contract through Nov. 30, 2000, adjusting billing
rates for merit increases and adding funds for the required technical and
administrative support, was released by the Project Controls group.
-
Galli&Morelli: CO #8, for machining of additional SAS seismic attenuation
prototype components, is in Advanced Detector Suspensions group review.
This contract change brings the Order total over $100K threshold making
it a 'significant' LIGO Laboratory action and hence subject to NSF approval
prior to placement.
-
Schober's: CO #10 for machining of additional PAM screws was released to
CIT Acquisition.
-
MIT: Contract change to incorporate the FY 2000 budget for the MIT LIGO
group is in preparation. CO #5, authorizing a no-cost extension through
January. 31, 2000, was issued in the mean time.
From: Ed Jasnow <jasnow@acrux.ligo.caltech.edu>
Change Order No. 2 is being issued to the MMR contract to cover additional
costs for the Livingston bakeout. This modification is in the amount
of $19,100.
Davies Associates, the designer responsible for the LIGO logo, has assigned
all copyrights for the logo to Caltech, so we now own it. The copyright
assignment document is now in the hands of Adam Cochran, Office of General
Counsel, who will advise us on the form of infringement protection we need
to acquire.
TECHNICAL CONFIGURATION MANAGEMENT
(Althouse)
From: wea@acrux (William Althouse)
No report. See Bake out.
WBS 1.4.3 Systems
Engineering / Data Analysis and Computing
Systems Engineering
No report
Simulation and Modeling
Modeling
Biplab Bhawal
Working at LHO to complete the e2e PSL/IOO model .
Ed Maros
(EFM) Worked with Bruce to track down wxString problem.
[Bruce Sears]
(BS) Alfi 4 Software Development: (3.5 days)
-
Continuing systematic exercising of Alfi 4 features to determine where
work is still needed for release.
-
Completed the first set of tests and am working with Ed on making
fixes to bugs found.
-
(BS) E2E GNATS Bug Reporter: (0.5 days)
-
First attempt at E2E GNATS setup. Working, but will need to be refined
most likely.
Hiro Yamamoto
Worked with Matt Evens to analyze the fringe structure of LHO 2K FP
data to extract finess and velocity.
LIGO Data Analysis System
[Masha Barnes]
-
(MB) Worked on DataConditioning API:
-
added the automake/autoconfig/make scripts;
-
wrote dummy wrapper functions for the analysis functions specified in the
Data Conditioning API requirements document.
-
(MB) LightweightAPI:
-
added support for the C-like data types( short, int, long, float, double)
in LIGO_LW Arrays and Params elements.
-
handle formatted data (base64, binary ) in xml documents for conversion
into the ILWD format.
-
(MB) Working on frame concatenation:
-
modified concatAdcData() and concatProcData() functions to do a proper
parameter checking.
[Kent Blackburn]
-
(JKB) Attended teleconference meeting on LIGO Calibration.
-
(JKB) Met with Beniot Mours of VIRGO to discuss VIRGO plans for Calibration.
-
(JKB) Met with Ian Taylar of GEO to discuss issues of Software Documentation.
-
Contacted Paul Walker about a C++ to HTML package called grdoc.
-
(JKB) Attended 3 day meeting on Frames had at Caltech in collaboration
with VIRGO, GEO, TAMA and LIGO. Meeting has resulted in a number of
proposed changes to the Frame Specification which enhance Frame functionality.
-
(JKB) Met with staff to discuss missing functionality in the FrameAPI to
support concatenation. Masha and Alex are working on the ILWD and Frame
aspects of this respectively. Also, outlined plans with staff to set up
local LDAS system in Millikan which complements systems at sites.
[Alex Ivanhov]
-
(AI) Looked more into the LDAS code and into TCL language.
-
(AI) Wednesday I spent whole day at the Frame meeting.
[Grace Hu]
-
(GH) Testing and debugging programs for message passing over data socket.
Implementing sending a text message to mpiAPI on SUN machines. When I tested
on Kitalpha, the system showed that no enough space to load library.
-
(GH) Finished writing MPI data translation program.
-
(GH) Writing programs for wrapperAPI to send and receive ILWD data through
LDAS data sockets.
[Mary Lei]
-
(ML) Tried to set up trigger for deleting datasource and transdata
rows if parent is deleted. Needs to investigate syntax.
-
(ML) Create tcl script createMain.tcl to generate the main ilwd source
code for any combination of records and to output the make script for each
type of ilwd.
-
(ML) Created ilwds of 10 and 100 rows and measured insertion rate
of the new tables on deneb.
-
(ML) Provided John Zweizig with xml examples of new tables by converting
ilwds to xml via ligolwAPI.
-
(ML) Updated ilwd files for hanford testing and cvs all changes.
-
(ML) Installed new tables at Hanford and started insertion rate testing.
[ Edward Maros ]
-
(EFM) Rewrote of autoconfig and automake files.
[Bruce Sears]
-
(BS) LDAS GNATS Bug Reporter:
(0.5 days)
-
Working at determining the GNATS configuration when there are multiple
databases in the system.
Stuart Anderson
-
Worked with Suresh to perform the initial install of the Sun computers
for the CIT LDAS system--E450, 2 U10's, keyboard/video/mouse switch, and
10/100 Ethernet switch.
General Computing
MIT:
Livingston:
-
We have received the Autocad installation CDs for the Caltech site license
and are installing it on several PCs. We have both version R14 and version
2000. At the present time we intend to install 2000 on one machine and
R14 on the rest.
-
We are testing one of the Suns as a secondary DNS server.
-
Received SUN 450 and installing it.
Hanford:
-
I have finally made contact with the Sun representative and have gotten
a quote for renewal of our maintenance contract. The Purchase Request
is written. I'm just waiting for the Sun representative to make some
corrections to the addresses on the quote. I have a quote to upgrade
all the site PCs to Windows 98, I'm expecting two more quotes from other
companies by Friday. I ordered tapes for the CDS Cybernetics tape
robot.
-
Continued network security maintenance, did the usual backups, helped with
several printer and PC problems, added a couple new user accounts, changed
the passwords on several accounts because the users had forgotten their
passwords, and kept the GC accounting paper work up to date.
CIT:
-
Samantha -IT IS NOW DONE. All PC's on the project should have had
virus scan installed along with all the y2k patches. The PC's in the sub-basement
of Bridge will be finished on Friday. There was were problems following
the massive installation of virus scan and the patchs this weekend. All
of those problems have now been dealt with.
FYI: The installation of virus scan should not have messed up
your PC unless you had viruses on it, in which case when the viruses were
deleted it could have caused problems.
-
Refomatted Fred Mann's pc and installed win98 and other software on it.
Hopefully his computer will now cease having diffculties.
-
Finished building Veronica's computer and moved it over to her cubicle.
Connected her new computer to the 115 subnet, hopefully this will also
make things faster for her.
-
Y2k a laptop. If people are wishing me to get to their laptops before the
year 2000 they then need to bring them in on Friday or Saturday because
I go home on Sunday and will not return until next year. Made adjustments
to the DVD player on my computer, it now is fully functional.
-
Took care of some administrative stuff.
-
FINISHED the maps of the project. They are now up to date. Will print
out the final copy on Friday.
-
Barbara began efforts to put the LIGO dedication video tapes on our web
site. Rented a Betacam tape player and reviewed the tapes. Determined
most likely segments for creating web files.
-
Began to work on a web page for submitting DCC documents. Updated the LSC
Council page on the web site.
-
Suresh worked with Stuart Anderson to build LDAS private network in Millikan
6th floor. Installed solaris 7 in Sun Enterprise 450 and two Ultra 10s.
Installed two ATM cards in Enterprise 450. A video switched has been set
up to switch among these system to work from single keyboard and monitor.
-
Assisted users for printing, network, email etc problems.
-
Assisted Larry in setting up systems for getting a number of services back.
-
Larry worked with Jay on getting kater and the replacement for kater back
on-line. The old kater will be removed completely in the next month or
so. There have been some access problems on the kater replacement that
still need to be resolved.
-
Started setting up a number of replacement servers and installation of
a SUN 450 to be used as a compute server.
-
Resolved a number of procurement issues.
-
Reworked some network cables and fixed a number of PC's with s/w problems.
-
Shut down a few more services to cut down on the hacking problems while
building the new servers. The number of attempts to hack into the systems
has dropped but still have a large number of people knocking on the doors.
-
A number of people have had virus problems on e-mail attachments. Please,
do not open .exe files that are sent as attachments.
-
Checking on a couple of e-mail issues including pop and IMAP services.
Albert and others have been working out the logistics of getting the e-mail
service of netscape to work in a more secure manner. When we get a setup
that we feel comfortable with we will pass it on.
WBS 1.4.4.1 Administrative
Group
Dorothy Lloyd
Continue to process invoices for payment using both on- and off-line
approval methods. Track and solve invoice problems. Entered and approved
requisitions on-line (for more detail see "Cost Schedule Control Systems"
report by Sarita Moore). Receiving on-line continues daily.
Continue to monitor contract funding levels and request supplements
from task managers were needed.
Data entry for current payments made for both contract and purchase
orders is on-going by both Jim and me. Jim continues to work on reconciling
status reports and data entry in LIGO database.
Rita Torres
Ongoing work on travel documents.
For I. Petrac did letter to Shanghai Institute (SIOM) to transmit Attachment
No. 1 to their MOU. Did letter to Penn State to transmit Attachments
A, B, & Z to their MOU. Final edits to Crystal Systems package,
FedExed for NSF review and approval. Distributed the signed change order
No. 10 to Schober Machine.
For E. Jasnow prepared contract with John Desmond & Associates for
LLO Staging Building, obtained an Oracle requisition number, and coordinated
with R. Brambila to obtain PO #1008883. Thank you Ruth for the timely
response. FedExed 3 copies of the contract for Desmond signature,
distributed 10 copies in-house.
Ordered items using the P-Card. Reconciled P-Card purchases, one order
contained 27 line items. Last Thursday met with I. Baldon and B. Kratochwill
to discuss updating the FileMaker Pro application for travel, these forms
as well as other travel forms must eventually interface with Oracle.
Helped D. Tomlinson copy and distribute flyers for upcoming seminars.
Irene Baldon
Worked on preparing the paper work for 9 new trips taken recently or
upcoming (9 Payment Requests and 2 Advance Requests). There are approximately
an additional 6 new trips in various stages pending completion of travel
arrangements before the paper work can be completed. Also worked on an
unusually high number of problem issues which required a good portion of
my time. A relocation to Livingston and a number Post Docs took an additional
amount of my time.
Completed 27 Expense Reports, some of which were extensive, involving
2-3 or more pages each. Some of these reports were still not taped or completed
by the Traveler, and required additional time for completion. Worked additionally
on a number of problem issues associated with these which required a good
portion of my time. There are 11 Expense Reports still to be done. I'm
holding 3 completed Expense Reports which require a check from the Traveler
before sending to Travel Audit to clear. Also assisted and advised both
Rita and Liz on the preparation of Expense Reports.
Rita and Liz were able to complete 20 Expense Reports for me. They have
an additional 9 Expense Reports in the process of completion. Thanks Rita
and Liz.
I have not seen any significant change in the time lag for receiving
checks nor have I started receiving T numbers for the trips prior to or
during the duration of the trip. I continue to receive T numbers after
the completion and pay off of the Expense Report. Met with Barbara and
Rita last Thursday to see if we could create some sort of data base using
ORACLE's Excel forms. We came up with something as a stop-gap (its very
time consuming but at least it allows me to maintain copies/information)
until Barbara can see if she can modify the Excel Program for me.
Performed normal recording and filing associated with Travel and Reimbursement.
Prepared the Travel/Vacation Itinerary for the Week of December 14,
1999.
Performed miscellaneous duties as requested by various members of the
LIGO Project here at Caltech, as well as from members of the staffs of
each of the two (2) sites. I continue to do MIT's travel to the sites for
installation activities and assist them wherever possible.
Elizabeth K. Wood
Returned many inkjet transparencies that we got at a really terrific
price that are completely useless to us because we are now using a laserjet
printer. The inkjet transparencies are not compatible with laserjet printers.
Now I have to find a really terrific price on laserjet transparencies.
Probably just in time for the printers to be changed again.
Went to Straightline Offline in Burbank with Barbara K. to rent a beta
videotape machine for use in timing the talks at LIGOfest so they can be
edited and put on the web.
Spent some time tracking down two missing paychecks for a student employee.
Since the checks are gone gone gone, we must stop payment on the checks
and have them reissued.
Made arrangements with Graphic Arts to make reprints of the LIGO article
from Engineering and Science since we are running low on the ones I have
left.
Helped Irene with travel reimbursements.
For additional information about this report, contact sanders@ligo.caltech.edu